Beruflich Dokumente
Kultur Dokumente
1
Presenters
Miriam Varend
Corporate Director, Contracts
Northrop Grumman Corporation
Miriam.Varend@ngc.com
2
Purpose
5
Incentive Contract Terminology
“A cost-plus-award-fee contract is a cost-reimbursement contract that provides for a fee
consisting of (1) a base amount fixed at inception of the contract, if applicable and at the
discretion of the contracting officer, and (2) an award amount that the contractor may earn in
whole or in part during performance and that is sufficient to provide motivation for
excellence in the areas of cost, schedule, and technical performance.” FAR 16.405-2
“Award-Fee Board means the team of individuals identified in the award-fee plan who have
been designated to assist the Fee-Determining Official in making award-fee determinations.
Fee-Determining Official (FDO) means the designated Agency official(s) who reviews the
recommendations of the Award-Fee Board in determining the amount of award fee to be
earned by the contractor for each evaluation period.
Rollover of unearned award fee means the process of transferring unearned award fee,
which the contractor had an opportunity to earn, from one evaluation period to a subsequent
evaluation period, thus allowing the contractor an additional opportunity to earn that
previously unearned award fee.” FAR 16.001
“A Provisional Award Fee payment is a payment made within an evaluation period prior to a
final evaluation for that period.” DFARS 216-405-2(b)
Base Fee < 3% of estimated cost and is not part of award fee. DFARS 216.405-2(c)
6
Incentive Contract Terminology
7
Incentive Contract Terminology
Award Term
– Not in FAR or DFARS as an official contract type. In the absence of
its own official contract type, Award Term could be viewed as an
element of whatever official contract type with which it is affiliated.
However, Award Term is unique in that it involves an extension to
the existing contract period of performance (“term”).
8
Cost Incentive (or Constraint)
9
Multiple-Incentive Contracts
12
Two Critical Incentive Contract Tenets
13
Two Critical Incentive Contract Tenets
Improved Communication
• Award Fees
– Via FDO within contract framework
– Manage expectations with FDO on AF
process
– Manage expectations with KR on rating scale
• Incentive Fees
– Via predetermined formulas in contract
language
– Discourages requirements creep
14
Recent Publicity & Resulting Policy
• GAO Report. Defense Acquisitions: DOD Has Paid Billions in Award
and Incentive Fees Regardless of Acquisition Outcomes GAO-06-66,
December 19, 2005
• DUSD(A&T) Memo dtd Mar 29, 2006, Subj: Award Fee Contracts
• GAO Testimony. Defense Acquisitions: DOD Wastes Billions of
Dollars through Poorly Structured Incentives GAO-06-409T, April 5, 2006
• GAO Report. NASA Procurement: Use of Award Fees for Achieving
Program Outcomes Should Be Improved GAO-07-58, January 17, 2007
• DPAP Memo dtd Apr 24, 2007, Subj: Proper Use of Award Fee
Contracts and Award Fee Provisions
• DPAP Memo dtd Apr 24, 2007, Subj: Award and Incentive Fees – Data
Collection
• DPAP Memo dtd May 15, 2007, Subj: Proper Use of Award Fee
Contracts and Award Fee Provisions
• OFPP Memo dtd Dec 4, 2007, Subj: Appropriate Use of Incentive
15
Contracts
Recent Publicity & Resulting Policy
(continued)
• GAO Report. Federal Contracting: Guidance on Award Fees Has Led to
Better Practices but Is Not Consistently Applied GAO-09-630, May 29, 2009
• GAP Testimony. Federal Contracting: Application of OMB Guidance Can
Improve Use of Award Fee Contracts GAO-09-839T, August 3, 2009
• DPAP Memo dtd Sep 22, 2009, Subj: Award and Incentive Fees – New GAO
Report and Evaluation of Data
• DPAP Memo dtd Apr 26, 2010, Subj: Class Deviation 2010-O0011 - Award Fee
Reduction or Denial for Jeopardizing the Health or Safety of Government
Personnel
16
October 2009 FAR Interim Rule
17
October 2009 FAR Interim Rule
18
October 2009 FAR Interim Rule
FAR Table 16-1
Award-Fee Adjectival Award-Fee Pool Available To Be Description
Rating Earned
Excellent 91%--100% Contractor has exceeded almost all of the significant award-
fee criteria and has met overall cost, schedule, and technical
performance requirements of the contract as defined and
measured against the criteria in the award-fee plan for the
award-fee evaluation period.
Very Good 76%--90% Contractor has exceeded many of the significant award-fee
criteria and has met overall cost, schedule, and technical
performance requirements of the contract as defined and
measured against the criteria in the award-fee plan for the
award-fee evaluation period.
Satisfactory No Greater Than 50%. Contractor has met overall cost, schedule, and technical
performance requirements of the contract as defined and
measured against the criteria in the award-fee plan for the
award-fee evaluation period.
20
April 2010 DFARS Proposed Case
21
April 2010 DFARS Proposed Case
AWARD FEE
The Contractor may earn award fee from a minimum of zero
dollars to the maximum amount stated in the award-fee plan
in this contract. In no event will award fee be paid to the
Contractor for any evaluation period in which the Government
rates the Contractor’s overall cost, schedule, and technical
performance below satisfactory. The Government may
unilaterally revise the award-fee plan prior to the beginning of
any rating period in order to redirect Contractor emphasis.
(End of clause)
22
Linking Contractor Effort
to C-S-P Trade Space
23
Cost Incentive (or Constraint)
24
Multiple-Incentive Contracts
Cost Control Fee (C) Interim Milestones (S, P) End Deliverable (S, P)
(Target: 4%, Maximum: 7%) (4% AF with Incentives) (4% IF with AF if not perfect)
Schedule RIE: 1 day (50% cut in Milestone AF). Performance RIE: None.
Cost Range of Incentive
If a milestone schedule is not met, maximum “All-or-None” KPP-based Fee
Effectiveness (RIE) is 15%
fee payout is 50% of the allotted fee pool for that Success assessed via comparing
(5% underrun to 10% overrun)
milestone. final test/analysis results against
Minimum fee is 0% and
Govt. sets a few milestone dates (e.g., IBR) performance specification
maximum fee is 7%
Offerors set remaining milestone schedules Schedule RIE: 0-90 days.
40/60 shareline under Target Cost
Govt. sets the milestones & fee percentages Incremental (days 1, 31, 61, 91)
60/40 shareline above Target Cost
Performance RIE: 0-100. Govt. rates each
Incrementally fund with 4% target fee
milestone for tech/mgmt. performance only
If the contractor meets or underruns target cost AND achieves 100% payout for end deliverable, the Govt. will
pay contractor: (a) additional 1% fee; and (b) Govt.’s underrun savings (up to 2.0% of target cost) based on
milestone schedules met and the performance ratings of such milestones
28
Interim Milestone Award Fees with
Performance & Schedule Parameters
3. Critical Design Review (CDR) All System and Segment Level CDRs successfully complete. Successful completion of the system
Phase and segment level CDRs is achieved when all the following exit criteria are met:
a) Segment and System level reviews conducted;
b) All action items closed or documented in a plan of closure;
c) Product Baseline established;
d) Delivery of the final System Performance Assessment Model; and;
e) Government approval of the associated deliverables: Software Test Description; Final System
Test and Integration Master Plan; Segments Test Plans; Software Test Plan; Final Satellite
Design Analysis and Verification Reports; Software Installation Plan; Interface Control
Documents; Final Material Review Data Packages; Operational Support Plan; Mission
Assurance Program Plan; Interface Requirements Specification; Launch Assurance Program
Plan; Launch Operations Plan; Concept of Operations; Security Verification Plan; and
TEMPEST Control Plan.
30
Award Fee Definitions (Systems)
IDEAS FOR CONTRACTING OFFICER SUPPLEMENTARY LANGUAGE TO FAR TABLE 16-1:
Very Good (76-90%): A very good grade reflects successful milestone completion with minor
problems, if any, that can be readily addressed to sufficiently maintain program cost, schedule, and
technical performance.
Good (51-75%): A good grade reflects successful milestone completion with some problems that
must be proactively address to sufficiently maintain program cost, schedule, and technical
performance.
Satisfactory (No greater than 50%): A satisfactory grade reflects successful milestone complete
despite some problems that must be proactively addressed with significant Government assistance
to sufficiently maintain program cost, schedule, and technical performance.
Unsatisfactory (0%): An unsatisfactory grade indicates that, while the Contractor may have
successfully completed the milestone, performance was below the satisfactory level. An
unsatisfactory grade reflects performance that negatively impacts program cost, schedule, and
technical performance.
31
CPIF/CPAF Fee Relationships
4% Incentive Fee for Cost Control
0-3% Contractor Underruns for More Incentive Fee
4% Award Fee with Incentives for Milestones
4% Incentive Fee (with AF if not perfect) for End Deliverable
IF
Parts (a) & (b)
Milestones 1% & 0-2%
4%
End
Deliverable
4%
32
C-S-P Fee Relationships
4% Incentive Fee for Cost Control (Cost)
0-3% Contractor Underruns for More Incentive Fee (Cost)
4% AF with incentives for Milestones (2% Perf., 2% Schedule)
4% IF with AF for End Deliverable (2% Perf., 2% Schedule)
IF
Parts (a) & (b)
1% & 0-2%
Schedule
Fees
Milestones- 4%
End
Deliverable – 4%
Performance
Fees 33
Ensure Fees are Performance-Based & Backloaded*
*but not too much
Sat #1 On-orbit
Delivery
Sat #2 On-orbit
Delivery
CDR
CAI FQT
PRR
NAVSOC Final
JTeL Cert Install
STRR #1 STRR #2
PDR NAVSOC 1st Sat FIST
Install PCA
IBR
Final Ground Install
2nd Sat Encap.
34
Understand Contractor’s Fee Cash Flow per Type of Fee (IF vs. AF, C-S-P)
Option CLINs -- FPIF/AF Structure
Production Units
Production Cost Control
Whenever possible, include FPIF/AF production options on the CPIF/AF development contract.
Establish the CPIF/AF and FPIF/AF structure around extent of COTS, COTS integration, and
technology readiness levels for your system. The more integration involved and the lower the
TRLs, the more the incentive parameters should shift risk to the Govt. If industry pushes back too
hard on FPIF/AF options, your requirements may be unrealistic.
35
Post-Award Changes
to Incentive Contract Fee Structure
36
Lessons Learned for Systems Buy
• Start Early!!!!
– Maximizes your trade space for schedule
• Maximize Pre-Solicitation Industry Exchanges
– Multiple one-on-one mtgs. and share as much info as possible
• Continuous Joint PM-PCO-Industry Effort
– Examine the C-S-P trade space
– Continuously, before and after award
• Get insight into prime-subcontractor C-S-P trade space
– Encourage IF/AF subcontracting arrangements
• Incentive Contracts result in PM-PCO working closer together from
RFP development through post award administration
• It will take longer to negotiate post award changes
– T&Cs get same attention as cost/price
– More program office involvement
– Benefit is more realistic ECP planning
37
Award Fee Definitions (Services)
IDEAS FOR CONTRACTING OFFICER SUPPLEMENTARY LANGUAGE TO FAR TABLE 16-1:
Excellent (91-100%): An excellent grade is considered to be exceptional and awarded
infrequently, reflects all of the following: very efficient and very effective performance (including
types and hours of labor), results are very reliable with high validity, results add value that is
vital to program decision-making and/or outcomes, and all other traits in this rating description
are reflected in the subcontract management as well.
Very Good (76-90%): A very good grade is the expected, consistent baseline of performance
and reflects all of the following: efficient and effective performance (including types and hours
of labor), results are reliable and valid, results add significant value to program decision-making
and/or outcomes, and good, proactive subcontract management.
Good (51-75%): A very good grade is the expected, consistent baseline of performance and
reflects all of the following: efficient and effective performance (including types and hours of
labor), results are consistently reliable and valid, results add value to program decision-making
and/or outcomes, and good, proactive subcontract management.
Satisfactory (No Greater than 50%): A satisfactory grade reflects some or all of the following:
mostly efficient and mostly effective performance (including types and hours of labor), the
results are somewhat reliable and valid, results add some value to program decision-making and/or
outcomes, and adequate subcontract management.
Unsatisfactory (0%): An unsatisfactory grade indicates that, while the Contractor successfully
completed the requirements, performance was below the satisfactory level. An unsatisfactory grade
reflects some or all of the following: inefficient or ineffective performance (including types and hours of
labor), results that may be unreliable or not valid, results add little or no value to program decision-
making and/or outcomes, and poor subcontract management.
38
Ideas to Streamline
Award Fee Process
• Award Fee Board (AFB) evaluates subjective matters only.
– Maximizing objective measures (IFs) means less work for the AFB.
• Avoid attaching a voluminous award fee plan to the contract.
– Add AFB membership, FDO, and definition info via award fee
clauses.
• No mandated “dog and pony” shows.
– Govt. reserves right to require KR to submit written self-evaluation.
• Focus on the differences between the award fee definitions.
– No “bottoms up” or “top down” scoring.
• No award fee report by AFB or FDO.
– PowerPoint presentation with FDO signature. Share with KR.
• No PCO letter to KR.
– Just the unilateral award fee modification.
• Avoid changes to the award fee criteria each evaluation period.
– Use comprehensive award fee definitions.
39
Lessons Learned
• Do not shy away from incentive contracts
• Remember it is simply linking fee/profit to C-S-P
with corresponding, viable cash flow
• Supplement FAR Table 16-1 adjectival rating
descriptions
• Continue work to reduce administrative burden of
the award fee process
• Stay in tune with GAO Reports & DPAP Policy
Vault memoranda
– Failure to self-monitor & improve practices leads to
increased regulations & challenges
• Continue to work with your PM Team and Industry
to structure contracts to focus on C, S, P and
the trade space
40
A Few Resources
on Incentive Contracts
**Note: This site will link you to many other great resources on
Incentive Contracts.**
41
Questions ?
42