What is Earned Value Analysis?
3/33
Some Introductory Definitions
4/33
Basic Concepts of Earned Value
Management
5/33
Some More Useful Terms
6/33
A Simple but Edible Example
Our “Plan”
40 cookies per batch
5 batches per hour (200 cookies per hour)
Schedule: 5 hours to make 1,000 cookies
Budgeted cost per cookie – $0.05
Total Budget = $50.00
Analysis after one (1) hour of baking we’ve made …
150 edible cookies – some were burnt, some hit the floor, the
kids ate some, and fed some to the dog.
Actual cost of ingredients after one hour (ACWP) = $9.00
8/33
After One Hour of Making Cookies
Simple EVMS
BCWS = $10.00
BCWP = 150 cookies X $0.05/Cookie = $7.50
ACWP = $9.00
Cost and Schedule Variance
SV = BCWP – BCWS = –$2.50 (we’re behind schedule)
CV = BCWP – ACWP = $7.50 – $9.00 = –$1.50 (we’re over
budget)
SPI = BCWP / BCWS = 0.75 (we’re running at 75% of planned
schedule)
CPI = BCWP / ACWP = 0.833 (we’re running about 17% over
budget)
9/33
Forecasting the Cookie Schedule and Budget
10/33
Can we Catch Up?
12/33
A Simple EVMS Chart
$50.00
$40.00
BCWS SV
in $ CV
$30.00
$20.00 SV in hours
ACWP
$10.00
BCWP
13/33
Putting This Simple Concept into
Practice
16/33
A Framework for Deploying EVMS
18/33
10 Criteria for Successful EVMS
19/33
Define Authorized Work Elements
20/33
Identify Project Organizational Structure
21/33
Provide Integrated Planning, Scheduling, Budgeting, Work
Authorization, and Cost Accumulation Processes
22/33
Schedule the Authorized Work in a Sequential Manner
That Identifies the the Significant Task Dependencies
23/33
Identify Physical Products and Organizations
24/33
Establish & Maintain Time–Phased Budget Baseline
25/33
Record Direct Cost Consistency in a Formal System
26/33
Periodically Generate Project Metrics
27/33
Develop Revised Cost Estimates–at–Completion
(EAC) Based on Performance to Date
28/33
Incorporate Authorized Changes in a Timely
Manner
29/33
Ten Benefits of EVMS
30/33
What’s Next