Beruflich Dokumente
Kultur Dokumente
V400R006
User Guide
Issue 03
Date 2008-11-30
Website: http://www.huawei.com
Email: support@huawei.com
and other Huawei trademarks are the property of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective holders.
Notice
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but the statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Contents
Figures
Figure 4-29 Installing the BBU3900 body on the indoor installation rack........................................................4-35
Figure 4-30 Installing the DCDU on the indoor installation rack......................................................................4-36
Figure 4-31 Connections of the BBU3900 cables..............................................................................................4-37
Figure 4-32 BBU3900 cable layout on the indoor installation rack...................................................................4-38
Figure 4-33 Installing the BBU3900 body (in the 19-inch rack).......................................................................4-39
Figure 4-34 Connections of the BBU3900 cables..............................................................................................4-40
Figure 4-35 BBU3900 cable layout in the rack..................................................................................................4-41
Figure 4-36 Installing the BBU3900..................................................................................................................4-43
Figure 4-37 Power cable of the BBU3900.........................................................................................................4-44
Figure 4-38 Connection of the power cable.......................................................................................................4-45
Figure 4-39 SFP cable........................................................................................................................................4-46
Figure 4-40 Numbering of the HCPM/HECM...................................................................................................4-46
Figure 4-41 Installing the SFP cables (1)...........................................................................................................4-47
Figure 4-42 GPS clock cable connected to the CMPT panel.............................................................................4-48
Figure 4-43 GPS clock cable interconnected with the external GPS feeder......................................................4-48
Figure 4-44 Removing the cover plate from the GPS clock cable outlet at the bottom of the BBC..................4-49
Figure 4-45 Installing the GPS clock cables......................................................................................................4-49
Figure 4-46 Waterproofing N-type connectors..................................................................................................4-50
Figure 4-47 Routing of the BBU3900 cables.....................................................................................................4-50
Tables
Purpose
This document describes the product specifications of the BBU3900 and the procedure for
installing, commissioning, configuring, and troubleshooting the BBU3900.
Product Version
The following table lists the product version related to this document.
BBU3900 V400R006
Intended Audience
This document is intended for:
l Site maintainers
l Field engineers
l BTS installers
Change Records
For the change history, refer to Change History of the BBU3900 User Guide.
Organization
1 Safety Information
The BBU3900 contains mandatory boards (CMPT, HCPM/HECM, and UPEU), optional boards
(UTRP and USCU), and other modules. Data configuration should be performed on mandatory
boards and optional boards. For other modules, data configuration is not required.
After the site starts operation, you must perform routine maintenance for the BBU to ensure the
operation condition.
Conventions
1. Symbol Conventions
The following symbols may be found in this document. They are defined as follows
Symbol Description
TIP Indicates a tip that may help you solve a problem or save your
time.
2. General Conventions
Convention Description
3. Command Conventions
Convention Description
4. GUI Conventions
Convention Description
> Multi-level menus are in boldface and separated by the ">" signs.
For example,choose File > Create > Folder .
5. Keyboard Operation
Convention Description
Key1,Key2 Press the keys in turn.For example,pressing Alt,A means the two
keys should be pressed in turn.
6. Mouse Operation
Action Description
Click Select and release the primary mouse button without moving the
pointer.
Double-click Press the primary mouse button twice continuously and quickly
without moving the pointer.
Action Description
Drag Press and hold the primary mouse button and move the pointer
to a certain position.
1 Safety Information
The Danger, Caution, and Note items in the package of documents do not cover all the safety
precautions that must be followed. They only provide the generic safety precautions for
operations.
Symbols
DANGER
This symbol indicates that casualty or serious accident may occur if you ignore the safety
instruction.
CAUTION
This symbol indicates that serious or major injury may occur if you ignore the safety instruction.
NOTE
This symbol indicates that the operation may be easier if you pay attention to the safety instruction.
The rules for installing and maintaining the device are as follows:
l Only the trained and qualified personnel can install, operate and maintain the device.
l Only the qualified specialists are allowed to remove the safety facilities, and repair the
device.
l Any replacement of the device or part of the device (including the software) or any change
made to the device must be performed by qualified or authorized personnel of Huawei.
l Any fault or error that might cause safety problems must be reported immediately to the
personnel in charge.
Grounding Requirements
The following requirements are applicable to the device to be grounded:
l Ground the device before installation and remove the ground cable after uninstallation.
l Do not operate the device in the absence of a ground conductor. Do not damage the ground
conductor.
l The unit (or system) must be permanently connected to the protection ground before
operation. Check the electrical connection of the device before operation and ensure that
the device is reliably grounded.
Safety of Personnel
Ensure the following:
The previous two requirements are suitable for the wireless fixed terminal.
l To prevent electric shock, do not connect safety extra-low voltage (SELV) circuits to
telecommunication network voltage (TNV) circuits.
l To prevent laser radiation from injuring your eyes, never look into the optical fiber outlet
with unaided eyes.
l To prevent electric shock and burns, wear the electrostatic discharge (ESD) clothing, gloves
and wrist strap, and remove conductors such as jewelry and watch before operation.
Device Safety
l Before operation, the device must be secured on the floor or other fixed objects, such as
the walls and the mounting racks.
l Do not block ventilation openings while the system is running.
l When installing the panel, tighten the screw with the tool.
DANGER
l The high voltage power supply provides power for running the system. Direct contact with
the high voltage power supply or contact through damp objects may result in fatal danger.
l Non-standard and improper high voltage operations may result in fire and electric shock.
l The personnel who install the AC facility must be qualified to perform operations on high
voltage and AC power supply facilities.
l When installing the AC power supply facility, follow the local safety regulations.
l When operating the AC power supply facility, follow the local safety regulations.
l When operating the high voltage and AC power supply facilities, use the specific tools
instead of common tools.
l When the operation is performed in a damp environment, ensure that water is kept off the
device. If the cabinet is damp or wet, shut down the power supply immediately.
Thunderstorm
The following requirements are suitable only for the wireless base station or the device with an
antenna or GPS antenna.
DANGER
In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or
on a steel tower and mast.
CAUTION
Ground the device before powering on the device. Otherwise, the personnel and device are in
danger.
If the "high electrical leakage" flag is stuck to the power terminal of the device, you must ground
the device before powering it on.
Power Cable
CAUTION
Do not install and remove the power cable with a live line. Transient contact between the core
of the power cable and the conductor may generate electric arc or spark, which may cause fire
or eye injury.
l Before installing or removing the power cable, turn off the power switch.
l Before connecting the power cable, ensure that the power cable and label comply with the
requirements of the actual installation.
Fuse
CAUTION
To ensure that the system runs safely, when a fuse blows, replace it with a fuse of the same type
and specifications.
Electrostatic Discharge
CAUTION
The static electricity generated by the human body may damage the electrostatic sensitive
components on the circuit board, such as the large-scale integrated circuit (LIC).
In the following situations, the human body generates a static electromagnetic field:
The static electromagnetic field will remain within the human body for a long time.
Before contacting the device, plug boards, circuit boards, and application specific integrated
circuits (ASICs), wear a grounded ESD wrist strap. It can prevent the sensitive components from
being damaged by the static electricity in the human body.
DANGER
Do not place the device in the environment that has inflammable and explosive air or fog. Do
not perform any operation in this environment.
Any operation of the electrical device in the inflammable environment causes danger.
1.4 Battery
Storage Battery
DANGER
Before handling the storage battery, read the safety precautions for the handling and connection
of the storage battery.
Incorrect operation of storage batteries may cause danger. During operation, ensure the
following:
Electrolyte overflow may damage the device. It will corrode the metal parts and the circuit
boards, and ultimately damage the device and cause short-circuit of the circuit boards.
General Operations
Before installing and maintaining the storage battery, ensure the following:
Short-Circuit
DANGER
Short-circuit of the battery may cause injury. Although the voltage of a battery is low, high
transient current generated by short-circuit will release a surge of power.
Keep metal objects away from the battery to prevent short circuit. If they have to be used,
disconnect the battery in use before performing any other operation.
Harmful Gas
CAUTION
l Do not use unsealed lead-acid storage batteries, because the gas emitted from it may result
in fire or device corrosion.
l Lay the storage battery horizontally and fix it properly.
The lead-acid storage battery in use will emit flammable gas. Therefore, store it in a place with
good ventilation and take precautions against fire.
High Temperature
CAUTION
High temperature may result in distortion, damage, and electrolyte overflow of the battery.
When the temperature of the battery exceeds 60oC, check whether there is acid overflow. If acid
overflow occurs, handle the acid immediately.
Acid
CAUTION
If the acid overflows, it should be absorbed and neutralized immediately.
When handling a leaky battery, protect against the possible damage caused by the acid. Use the
following materials to absorb and neutralize acid spills:
Antacids must be used according to the instructions provided by the battery manufacturer.
Lithium Battery
CAUTION
There is danger of explosion if the battery is incorrectly replaced.
l Replace the lithium battery with the same or equivalent type recommended by the
manufacturer.
l Dispose of the used battery according to the instructions provided by the manufacturer.
l Do not dispose of the lithium battery in fire.
1.5 Radiation
Electromagnetic Field Exposure
CAUTION
High power radio-frequency signals are harmful to human body.
Before installing or maintaining an antenna on a steel tower or mast with a large number of
transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter
antennas are shut down.
The base transceiver station (BTS) has RF radiation (radiation hazard). Suggestions for the
installation and operation of BTSs are given in the following section. Operators are also required
to comply with the related local regulations on erecting BTSs.
l The antenna should be located in an area that is inaccessible to the public where the RF
radiation exceeds the stipulated value.
l If the areas where RF radiation exceeds the stipulated value are accessible to workers,
ensure that workers know where these areas are. They can shut down the transmitters before
entering these areas. Such areas may not exist; but if they exist, the areas must be within a
range of less than 10 m around the antennas.
l Each forbidden zone should be indicated by a physical barrier and striking sign to warn the
public or workers.
Laser
CAUTION
When handling optical fibers, do not stand close to, or look into the optical fiber outlet with
unaided eyes.
Laser transceivers or transmitters are used in the optical transmission system and associated test
tools. Because the laser that is transmitted through the optical fiber produces a small beam of
light, it has a very high power density and is invisible to human eyes. If a beam of light enters
the eye, the retina may be damaged.
Normally, staring into the end of an unterminated optical fiber or broken optical fiber with the
unaided eyes from a distance of more than 150 mm [5.91 in.] will not cause eye injury. Eyes
may, however, be damaged if an optical tool such as a microscope, magnifying glass or eye
loupe is used to stare into the bare optical fiber end.
Read the following guidelines to prevent laser radiation:
l Only the trained and authorized personnel can perform the operation.
l Wear a pair of eye-protective glasses when you are handling lasers or optical fibers.
l Ensure that the optical source is switched off before disconnecting optical fiber connectors.
l Never look into the end of an exposed optical fiber or an open connector if you cannot
ensure that the optical source is switched off.
l To ensure that the optical source is switched off, use an optical power meter.
l Before opening the front door of an optical transmission system, ensure that you are not
exposed to laser radiation.
l Never use an optical tool such as a microscope, a magnifying glass, or an eye loupe to look
into the optical fiber connector or end.
Read the following instructions before handling optical fibers:
l Only the trained personnel can cut and splice optical fibers.
l Before cutting or splicing an optical fiber, ensure that the optical fiber is disconnected from
the optical source. After disconnecting the optical fiber, use protecting caps to protect all
the optical connectors.
CAUTION
When working at heights, ensure that the objects do not fall.
When working at heights, ensure that the following requirements must be met:
l The personnel who work at heights must be trained.
l The operating machines and tools should be carried and handled safely to prevent them
from falling.
l Safety measures, such as wearing a helmet and a safety belt, should be taken.
l In cold regions, warm clothes should be worn before working at heights.
l Ensure that the lifting appliances are well prepared for working at heights.
Lifting Weights
CAUTION
Do not access the areas under the arm of the crane and the goods in suspension when lifting
weights.
l The slant angle is preferred to be 75o. The slant can be measured with the angle square or
with arms, as shown in Figure 1-3. When using a ladder, place the wider end of the ladder
on the ground and take protective measures on the base of the ladder against slippage. Place
the ladder on a stable ground.
When climbing the ladder, ensure the following:
l The gravity of the body does not shift from the edge of the ladder.
l Keep balance on the ladder before performing any operation.
l Do not climb higher than the fourth highest step of the ladder.
If you tend to climb to the roof, the length of the ladder should be at least one meter higher than
the eave, as shown in Figure 1-4.
CAUTION
Do not drill on the cabinet without permission. Inappropriate drilling on the cabinet may damage
the electromagnetic shielding and internal cables. Metal shavings from the drilling may result
in a short-circuit of the circuit board if they get into the cabinet.
l Before drilling a hole on the cabinet, remove the cables from the cabinet.
l During the drilling, wear blinkers to protect your eyes.
CAUTION
When carrying the device by hand, wear the protective gloves to prevent injury by sharp objects.
Handling Fans
l When replacing a component, place the component, screw, and tool at a safe place to prevent
them from falling into the running fan.
l When replacing the ambient equipment around the fan, do not place the finger or board
into the running fan until the fan is switched off and stops running.
CAUTION
l Be careful when moving heavy objects.
l When moving the chassis outwards, be aware about the unfixed or heavy objects on the
chassis to prevent injury.
l Two persons should be available to move a chassis; one person must not move a heavy
chassis. When moving a chassis, keep your back straight and move stably to prevent a
sprain.
l When moving or lifting a chassis, hold the handle or bottom of the chassis. Do not hold the
handle of the installed modules in the chassis, such as the power module, fan module, or
board.
1.8 Others
Inserting and Removing a Board
CAUTION
When inserting a board, wear the ESD wrist strap or gloves. Insert the board gently to prevent
any bent pins on the backplane.
CAUTION
Bundle the signal cables separately from the strong current cables or high voltage cables.
Cabling Requirements
At a very low temperature, movement of the cable may damage the plastic skin of the cable. To
ensure the construction safety, comply with the following requirements:
l When installing cables, ensure that the environment temperature is above 0oC.
l If cables are stored in the place below 0oC, move the cables into a place at a room
temperature and store the cables for more than 24 hours before installation.
l Move the cables with care, especially at a low temperature. Do not drop the cables directly
from the vehicle.
This describes the BBU3900 equipment and cables of the BBU3900. The information can be
used as reference for hardware installation and maintenance.
USCU Universal Satellite Card and It provides the input port for
Clock Unit external signals (including
satellite clock signals) and
provides synchronization clock
signals for the BBU3900 and the
RF modules connected to the
BBU3900.
– Each CMPT provides four E1/T1 ports and two FE ports. You can configure the CMPTs
based on capacity requirements and service types.
l HCPM configuration
– A maximum of six HCPMs can be configured.
– An HCPM reserves three SFP ports and supports removable optical modules.
– An HCPM is configured with only one CSM6700 chip. The chip processes 285 forward
channels and 256 reverse channels.
l HECM configuration
– A maximum of six HECMs can be configured.
– An HECM reserves three SFP ports and supports removable optical modules.
– An HECM is configured with only one CSM6800 chip, which supports 192 subscribers.
l UTRP configuration
– A maximum of two UTRPs working in load sharing mode or 1+1 backup mode can be
configured.
– Each UTRP provides eight E1/T1 ports.
l FAN configuration
A maximum of one FAN can be configured.
l UPEU configuration
A maximum of two UPEUs working in 1+1 backup mode can be configured.
l USCU configuration
A maximum of two USCUs can be configured. The USCU supports GPS or GPS/
GLONASS satellite card and RGPS signals.
l UELP configuration
A maximum of two UELPs can be configured. A UELP provides lightning protection for
four E1/T1 links.
l UFLP configuration
A maximum of two UFLPs can be configured. A UFLP provides lightning protection for
FE signals and supports two Ethernet connections.
NOTE
l With hybrid configuration of HCPMs and HECMs, the BBU3900 supports CDMA2000 1X and 1xEV-
DO services.
l The BBU3900 supports hybrid configuration of UELPs and UFLPs.
l The UELP/UFLP or the UTRP cannot be simultaneously configured in the BBU3900.
l When the BBU3900 is configured with the UTRP, the SLPU can be used to provide lightning
protection.
l The SLPU is an external universal lightning protection unit. It can house the UELP/UFLP. It is
used for the lightning protection of the E1/T1/FE cables. The SLPU supports mixed configuration
of the UELP and the UFLP. A maximum of four lightning protection boards can be configured.
l The BBU3900 can be configured with the CMPT and UTRP at the same time.
l If a new site requires more than four E1/T1 links, Huawei recommends that you use the E1/T1
resources on the UTRP directly.
l If an expanded site requires more than four E1/T1 links, Huawei recommends that you use the E1/
T1 resources provided by the extended transmission board, apart from the four E1/T1 links on the
main control transmission board.
HCPM: HERT channel processing HECM: HERT enhance channel CMPT: main processing and
module processing module transmission unit
UPEU: universal power and FAN: fan box USCU: universal satellite card and
environment interface unit clock unit
UELP: universal E1/T1 lighting UFLP: universal E1/T1 lighting
protection unit protection unit
NOTE
l When the UTRP is configured, the independent SLPU is used to provide lightning protection for the
external signal cables of the BBU3900.
Dimensions
The dimensions (height x width x depth) of the BBU3900 are 86 mm [3.39 in.] x 442 mm [17.40
in.] x 310 mm [12.20 in.], as shown in Figure 2-5.
Weight
l Empty cabinet (including the FAN and UPEU): ≤ 8 kg [17.64 lb]
l Fully-configured cabinet: ≤ 11 kg [24.26 lb]
NOTE
The UPEU is of two types, namely the UPEA and the UPEB. They support –48 V DC and +24 V DC power
input respectively
Power Consumption
Power consumption of a fully-configured BBU3900: ≤ 250 W
Operation Environment
l Ambient temperature
-10℃ to +55℃
l Relative humidity of the operating environment
5%RH to 95%RH
2.2.1 CMPT
The CMPT is the main processing and transmission unit. The CMPT processes and transmits
the data between the BTS and the BSC, controls and manages the BTS, and provides clock
signals for the BTS.
2.2.2 HCPM
The HCPM is a CDMA2000 1X channel processing board. It processes the CDMA2000 1X
service data on forward and reverse channels. By default, the HCPM is configured with one
CSM6700 chip.
2.2.3 HECM
The HECM is a CDMA2000 1xEV-DO channel processing board. It processes the CDMA2000
1xEV-DO service data on forward and reverse channels. By default, the HECM is configured
with one CSM6800 chip.
2.2.4 UPEU
The UPEU supplies power to the BBU3900. Therefore, it is mandatory. The UPEU converts
+24 V DC or –48 V DC power into +12 V DC power.
2.2.5 FAN
The fan implements the heat dissipation function of the BBU3900.
2.2.6 UTRP
The UTRP is a universal extension transmission processing unit. The UTRP supports E1/T1
transmission ports.
2.2.7 UELP
A UELP provides lightning protection for four E1/T1 links.
2.2.8 UFLP
A UFLP provides lightning protection for FE signals. It supports two Ethernet connections.
2.2.9 USCU
The USCU is compatible with six types of satellite cards. It provides absolute time information
and 1PPS reference clock source for the CMPT. In addition, the USCU supports RGPS and BITS
ports.
2.2.1 CMPT
The CMPT is the main processing and transmission unit. The CMPT processes and transmits
the data between the BTS and the BSC, controls and manages the BTS, and provides clock
signals for the BTS.
CMPT Panel
This describes the exterior and the ports and indicators of the CMPT panel.
Exterior
Figure 2-6 shows the CMPT panel.
(1) ETH port (2) FE0 port (3) FE1 port (4) USB port
Ports
Table 2-3 lists the ports on the CMPT panel.
Port Description
Indicators
Table 2-4 lists the indicators on the CMPT panel.
RUN Green Operation l ON: There is power input, but the Blinking at
indicator board is faulty. 0.5Hz
l OFF: There is no power input, or the
board is faulty.
l Blinking at 4 Hz: The board is in the
loading state.
l Blinking at 0.5 Hz: The board
functions normally.
l Blinking at 0.25 Hz: The board is
being tested.
l Other: The board is faulty.
Table 2-5 lists the settings of the DIP switches on the CMPT.
SW2 Settings for The four bits of SW2 are used to control the grounding status of
grounding of four unbalanced E1/T1 cables. The settings of SW2 are as
unbalanced follows:
cables l For the 75-ohm E1 coaxial cable grounded externally, all bits
of SW2 are set to ON.
l For the 120-ohm E1 coaxial cable or 100-ohm T1 twisted pair
cable grounded internally, all bits of SW2 are set to OFF.
l Dimensions (length x width x depth): 280 mm [11.02 in.] x 144.45 mm [5.69 in.] x 20.32
mm [0.80 in.]
l Input voltage: +12V
l Power consumption: ≤ 25 W
2.2.2 HCPM
The HCPM is a CDMA2000 1X channel processing board. It processes the CDMA2000 1X
service data on forward and reverse channels. By default, the HCPM is configured with one
CSM6700 chip.
HCPM Panel
This describes the exterior, ports, and indicators of the HCPM panel.
Exterior
Figure 2-8 shows the HCPM panel.
Ports
Table 2-6 lists the ports on the HCPM panel.
Port Description
Indicators
Table 2-7 lists the indicators on the HCPM panel.
l Dimensions (length x width x depth): 280 mm [11.02 in.] x 144.45 mm [5.69?in.] x 20.32
mm [0.80 in.]
l Input voltage: +12V
l Power consumption: ≤ 20 W
l Channel processing capacity: 285 forward channels and 256 reverse channels
2.2.3 HECM
The HECM is a CDMA2000 1xEV-DO channel processing board. It processes the CDMA2000
1xEV-DO service data on forward and reverse channels. By default, the HECM is configured
with one CSM6800 chip.
HECM Panel
This describes the exterior, ports, and indicators of the HECM panel.
Exterior
Figure 2-9 shows the HECM panel.
Ports
Table 2-8 lists the ports on the HECM panel.
Indicators
Table 2-9 lists the indicators on the HECM panel.
2.2.4 UPEU
The UPEU supplies power to the BBU3900. Therefore, it is mandatory. The UPEU converts
+24 V DC or –48 V DC power into +12 V DC power.
UPEU Panel
This describes the exterior, ports, and indicators of the UPEU panel.
Exterior
The UPEU is of two types, UPEA and UPEB. They support –48 V DC and +24 V DC power
input respectively.
l The UPEA converts –48 V DC power into +12 V DC power.
l The UPEB converts +24 V DC power into +12 V DC power.
l The exterior of the UPEA is similar to that of the UPEB. The only difference is the silkscreen
under the PWR port. It indicates the input voltage.
Figure 2-10 shows the UPEU panel.
Ports
Table 2-10 lists the ports on the UPEU panel.
Port Description
Port Description
Indicators
Table 2-11 lists the indicators on the UPEU panel.
l Dimensions (length x width x depth): 292.39 mm [11.51 in.] x 85 mm [3.35 in.] x 40.14
mm [1.58 in.]
l Input current: ≤ 18 A
l Input voltage:
– +24 V DC: +21.6 V DC to +29 V DC
– –48 V DC: –38.4 V DC to -57 V DC
l Output voltage: 12 V
l Rated power: 300 W
2.2.5 FAN
The fan implements the heat dissipation function of the BBU3900.
FAN Panel
This describes the appearance and the indicators of the FAN panel.
Appearance
Figure 2-11 shows the FAN panel.
Indicators
Table 2-12 lists the indicators on the FAN panel.
STATE Green or Red l Green and blinking at 4 Hz: The board is not registered and
no alarm is generated.
l ON in red: An alarm is generated.
l Green and blinking at 0.5 Hz: The board functions properly.
l Dimensions (length x width x depth): 25.4mm [11.51 in.] x 280mm [3.35 in.] x 80mm [1.58
in.]
l Input voltage: +12 V
l Power consumption: ≤ 20 W
2.2.6 UTRP
The UTRP is a universal extension transmission processing unit. The UTRP supports E1/T1
transmission ports.
UTRP Panel
This describes the exterior, ports, and indicators of the UTRP panel.
Exterior
The UTRP uses a design of motherboard and subboards. Through different subboards, the UTRP
supports different physical network access modes of BTSs. Currently, the UTRP supports only
the IP over E1/T1 transmission. Each UTRP provides eight E1/T1 ports.
Ports
Table 2-13 lists the ports on the UTRP panel.
Port Description
Indicators
Table 2-14 lists the indicators on the UTRP panel.
RUN Green Operation l ON: There is power input, but the Blinking at
indicator board is faulty. 0.5Hz
l OFF: There is no power input, or the
board is faulty.
l Blinking at 4 Hz: The board is in the
loading state.
l Blinking at 0.5 Hz: The board
functions normally.
l Blinking at 0.25 Hz: The board is
being tested.
l Other: The board is faulty.
Table 2-15 lists the settings of the DIP switches on the UTRP.
SW1/ Specifying the The eight bits of SW1 and SW2 are used to control the
SW2 grounding grounding status of eight E1/T1 signal cables. The settings of
status of the SW1 and SW2 are as follows:
signal cable l In any situation, the eight bits are set to OFF by default.
l When error bits exist in the eight E1 links, set the eight bits
to ON to delete the error bits in the links.
l Dimensions (length x width x depth): 280 mm [11.02 in.] x 144.45 mm [5.69?in.] x 20.32
mm [0.80 in.]
l Input voltage: +12V
l Power consumption: ≤ 20 W
2.2.7 UELP
A UELP provides lightning protection for four E1/T1 links.
UELP Panel
This describes the appearance and the ports of the UELP panel.
Exterior
Figure 2-14 shows the UELP panel.
Ports
Table 2-16 lists the ports on the UELP panel.
Port Description
Table 2-17 lists the settings of the DIP switches on the UELP.
2.2.8 UFLP
A UFLP provides lightning protection for FE signals. It supports two Ethernet connections.
UFLP Panel
This describes the appearance and the ports of the UFLP panel.
Exterior
Figure 2-16 shows the UFLP panel.
(1) INSIDE: FE0 port (2) INSIDE: FE1 port (3) OUTSIDE: FE0 port (4) OUTSIDE: FE1 port
Ports
Table 2-18 lists the ports on the UFLP panel.
INSIDE: FEO and FE1 ports FE ports, which are used to connect the
CMPT of the BBU3900
OUTSIDE: FEO and FE1 ports FE ports, which are used to connect external
devices
NOTE
For cable connection, INSIDE: FE0 port corresponds to OUTSIDE: FE0 port and INSIDE: FE1 port
corresponds to OUTSIDE: FE1 port.
2.2.9 USCU
The USCU is compatible with six types of satellite cards. It provides absolute time information
and 1PPS reference clock source for the CMPT. In addition, the USCU supports RGPS and BITS
ports.
USCU Panel
This describes the exterior, ports, and indicators of the USCU panel.
Exterior
Figure 2-17 shows the USCU panel.
(1) GPS port (2) RGPS port (3) BITS port (4) TEST port
Ports
Table 2-19 lists the ports on the USCU panel.
Indicators
Table 2-20 lists the indicators on the USCU panel.
RUN Green Operation l ON: There is power input, but the Blinking at 0.5
indicator board is faulty. Hz
l OFF: There is no power input, or
the board is faulty.
l Blinking at 4 Hz: The board is in
the loading state.
l Blinking at 0.5 Hz: The board
functions normally.
l Blinking at 0.25 Hz: The board is
being tested.
l Other: The board is faulty.
l Dimensions (length x width x depth): 280 mm [11.02 in.] x 144.45 mm [5.69?in.] x 20.32
mm [0.80 in.]
l Input voltage: +12V
l Power consumption: ≤ 3 W
The PGND cable ensures the grounding of the BBU3900. The PGND cable is required when
the BBU3900 is installed in a 19-inch rack. It is not required when the BBU3900 is installed in
a 19-inch cabinet/APM30.
2.3.2 Power Cable of the BBU3900
The power cables of the BBU3900 are –48 V power cable and +24 V power cable. The selection
of power cables depends on the input power.
2.3.3 E1/T1 Cable of the BBU3900
The E1/T1 cable connects the BBU3900 and the BSC. It is used to transmit baseband signals.
2.3.4 BBU3900 E1/T1 Lightning Protection Conversion Cable
The E1/T1 lightning conversion cable connects the CMPT/UTRP and the E1/T1 lightning
protection board. It is an optional cable.
2.3.5 FE Cable of the BBU3900
The FE cable connects the BBU3900 and the router in the equipment room so that the BBU3900
can communicate with the BSC.
2.3.6 FE Lightning Protection Conversion Cable of the BBU3900
The FE lightning protection conversion cable is used to connect the CMPT and the UFLP. It is
optional.
2.3.7 BBU3900 CPRI Cable
The CPRI cable carries CPRI signals between the BBU3900 and the RRU/ODU. There are two
types of CPRI cables, namely, optical fiber and SFP cable. The SFP cable is used only when the
BBU and the RRU/ODU are both installed indoors. In other scenarios, an optical fiber is used.
2.3.8 Alarm Cable of the BBU3900
The alarm cable carries the alarm signals from the external alarm devices to the BBU3900. It is
optional.
2.3.9 BBU3900 Monitoring Signal Cable
The BBU3900 signal cables are the power cabinet signal cable to the APM30 and the signal
cable to the EMUA.
2.3.10 Clock Cable of the BBU3900
This describes the GPS clock signal cable of the BBU3900.
Cable Exterior
The color of a PGND cable is yellow-green, and both ends are single-hole OT terminals. You
can add 2-hole OT terminals on the installation site.
Figure 2-18 shows the structure of the PGND cable.
Installation Position
Table 2-21 lists the installation position of the PGND cable.
NOTE
In the DBS3900, the BBU3900 supports the input mode of –48 V DC through the –48 V power cable.
Cable Exterior
One end of the power cable is a 3V3 power connector, and the other end is an OT terminal. If
the other end is bare, you must add an OT terminal on the installation site.
NOTE
The –48 V power cable is blue and black in color. The shape of the +24 V power cable is the same as that
of the –48 V power cable, but it is red and black in color.
Cables Description
The power cable is a 2-wire cable. Table 2-22 and Table 2-23 show the cores and pins.
A1 Blue -48V
A2 - -
A3 Black GND
A1 Red +24V
A2 - -
A3 Black GND
Installation Position
Table 2-24 lists the connections of the BBU3900 power cables.
NOTE
In the DBS3900, the power distribution box supplies power to the BBU3900. For the cable connections
between different power distribution boxes and the BBU3900, refer to Table 3-5.
Cable Appearance
The BBU3900 uses the following trunk cables: the 75-ohm E1 coaxial cable, 120-ohm E1 twisted
pair cable, and 100-ohm T1 twisted pair cable. One end of the E1/T1 cable is a DB26 male
connector, and the connector at the other end is made on the site depending on the actual
requirement.
l A 75-ohm coaxial cable consists of eight coaxial cables and can provide four E1 links.
l A 100-ohm twisted pair cable consists of eight pairs of (sixteen) cables and can provide
four T1 links.
l A 120-ohm twisted pair cable consists of eight pairs of (sixteen) cables and can provide
four E1 links.
Installation Position
Table 2-25 lists the connection of the E1/T1 cable in the BBU3900.
NOTE
The UELP can be installed in the SLPU to provide lightning protection for the E1/T1 cable.
(1) DB26 connector (2) Main label (3) 75-ohm coaxial cable (X1-X8)
Table 2-26 lists the mapping between the 75-ohm coaxial cable and the DB26 connector.
Table 2-26 Mapping between the 75-ohm coaxial cable and the DB26 connector
Cable
Numb
Cable er Start End Signal Remarks
X0.2 X1.Ring
X0.20 X2.Ring
X0.4 X3.Ring
X0.22 X4.Ring
X0.6 X5.Ring
X0. 24 X6.Ring
X0.8 X7.Ring
Cable
Numb
Cable er Start End Signal Remarks
X0.26 X8.Ring
NOTE
When installing the 100-ohm twisted pair cable, cut off the extra length of cable and pay attention to the
mapping between the twisted pair cable and the DB26 connector.
Table 2-27 lists the mapping between the 100-ohm twisted pair cable and the DB26 connector.
Table 2-27 Mapping between the 100-ohm twisted pair cable and the DB26 connector
Color of
Cable Start Sheath Signal Remarks
X0.20 Blue/white
X0.2 Orange/white
X0.22 Green/white
X0.4 Brown/white
Color of
Cable Start Sheath Signal Remarks
X0.24 Gray/white
X0. 6 Blue/red
X0.26 Orange/red
X0.8 Green/red
Table 2-28 lists the mapping between the 120-ohm twisted pair cable and the DB26 connector.
Table 2-28 Mapping between the 120-ohm twisted pair cable and the DB26 connector
Color of
Cable Start Sheath Signal Remarks
X0.20 White
X0.2 White
Color of
Cable Start Sheath Signal Remarks
X0.22 Red
X0.4 White
X0.24 Red
X0. 6 White
X0.26 Red
X0.8 White
Cable Exterior
One end of the E1/T1 lightning protection conversion cable is a DB26 male connector, and the
other end is a DB25 male connector.
Cables Description
Table 2-29 lists the use of the pins of the E1/T1 lightning protection conversion cable.
Table 2-29 Cores and pins of the E1/T1 lightning conversion cable
X1.19 X2.3
X1.3 X2.5
X1.21 X2.7
X1.5 X2.9
X1.23 X2.11
X1.7 X2.13
X1.2 X2.15
X1.26 X2.25
Installation Position
Table 2-30 lists the installation position of the E1/T1 lightning protection conversion cable.
Table 2-30 Installation position of the E1/T1 lightning protection conversion cable
When the UTRP is E1/T1 port on the CMPT INSIDE port on the UELP
not installed
Cable Exterior
Both ends of the FE cable are RJ45 connectors.
Figure 2-25 shows the FE cable.
Cables Description
Table 2-31 lists the pin assignment for the FE cable.
Installation Position
Table 2-32 lists the connection of the BBU3900 FE cable.
When the internal UFLP OUTSIDE FE0/FE1 port Routing device (connected to the
is used on the UFLP BSC)
External SLPU
NOTE
The UFLP can be installed in the SLPU for the lightning protection of the FE cable.
Cable Exterior
Both ends of the FE lightning protection conversion cable are RJ45 connectors.
Figure 2-26 shows the FE lightning protection conversion cable.
Cables Description
Table 2-33 lists the pin assignment for the FE cable.
Pin of the RJ45 Use of Core Use of Core Pin of the RJ45
Connector Connector
Installation Position
Table 2-34 lists the connection of the FE lightning protection conversion cable.
FE0 port on the CMPT FE port at the INSIDE position of the UFLP
Optical fiber
The CPRI optical cable is a multi-mode 2-wire cable with LC connectors at both ends. Figure
2-27 shows the CPRI optical cable.
SFP Cable
In the scenario of indoor centralized installation, the SFP high-speed cable is used to connect
the BBU and the RRU/ODU.
Installation Position
Table 2-35 lists the connection of the CPRI cable in the BBU3900.
Cable Exterior
Both ends of the alarm cable are RJ45 connectors. During installation, you must add a terminal
that is compatible with the external alarm device to one end of the cable.
Cables Description
Table 2-36 lists the pin assignment for the alarm cable.
Pin of the RJ45 Pin of the RJ45 Use of Core Use of Core
Connector Connector
Pin of the RJ45 Pin of the RJ45 Use of Core Use of Core
Connector Connector
Installation Position
Table 2-37 lists the connection of the BBU3900 alarm cable.
EXT_ALM0 port or EXT_ALM1 port on the Alarm signal port on the external alarm
UPEU device
Cable Exterior
Figure 2-30 shows the EMUA signal cable.
Cables Description
Table 2-38 lists the cores and pins of the EMUA signal cable.
Installation Position
Table 2-39 lists the installation position of the EMUA signal cable.
Signal Cable Connecting the BBU3900 and the APM30 (–48 V) Power Supply
Cabinet
The signal cable connecting the BBU3900 and the APM30 (–48 V) is delivered with the APM30.
It is used to carry the monitoring alarm signal from the APM30 (–48 V) power supply cabinet
to the BBU3900.
Cable Exterior
Figure 2-31 shows the APM30 (–48 V) signal cable.
Cables Description
Table 2-40 lists the cores and pins of the APM30 (–48 V) signal cable.
Table 2-40 Cores and pins of the APM30 (–48 V) signal cable
NOTE
Installation Position
Table 2-41 lists the installation position of the EMUA signal cable.
EXT-ALM of the UPEU AMPI of the APM30. For the connection relation, see
Table 2-40.
Cable Exterior
One end of the clock cable is an SMA male connector, and the other end is an N-type connector.
Figure 2-32 shows the clock cable.
Installation Position
Table 2-42 lists the installation position of the clock cable.
When the USCU is GPS port on the CMPT GPS lightning arrester at the BBU
not used side
CAUTION
The GPS lightning arrester of the BBU must be installed at a proper position and grounded
reliably. The GPS lightning arrester and the BBU must have the same potential.
The auxiliary devices of the BBU3900 are the indoor installation rack, APM30, power supply
device, monitoring and lightning protection device.
Equipment Exterior
Figure 3-1 shows the indoor installation rack and the installation mode.
NOTE
l If you want to fix the indoor installation rack on the wall, ensure that the load-bearing capacity of the
wall is 80 kg [176.37 lb] or higher.
l If two indoor installation racks are fixed on the wall and aligned horizontally, the distance between
them must be smaller than 10 mm [0.39 in.].
l For the installation of the indoor installation rack, refer to Indoor Installation Rack.
Engineering Specifications
Table 3-1 lists the engineering specifications of the indoor installation rack.
Item Specification
Item Specification
Scenarios
In terms of the DBS3900, the indoor installation rack supports only the BBU3900 and the
RRU3606. It does not support the ODU3601CE. The following are the scenarios:
l For indoor centralized installation, the –48 V DC input is supported. Figure 3-2 shows the
installation scenario.
l For indoor distributed installation, the –48 V DC input is supported. Figure 3-3 shows the
installation scenario.
3.2 APM30
The AMP30 is an integrated backup power supply system. It can be installed outdoors. The
APM30 provides power supply, backup power supply, transmission space, and lightning
protection for a distributed BTS. It supports multiple types of custom power supplies and
extended storage battery cabinets.
Equipment Exterior
With different modules equipped, the APM30 can be used as a power supply cabinet, battery
cabinet, or transmission cabinet. Figure 3-4 shows the power supply cabinet and transmission
cabinet. Figure 3-5 shows the battery cabinet.
For the description and installation guide of the APM30, refer to the APM30 User Guide.
Engineering Specifications
Table 3-2 lists the engineering specifications of the APM30.
APM30 Cabinet dimensions 600 mm x 700 mm x 480 mm [23.62 When the base is
(width x height x in. x 27.56 in. x 18.9 in.] not used
depth)
Figure 3-6 APM30 working with distributed BTS (internal storage batteries)
Figure 3-7 APM30 working with distributed BTS (external storage batteries)
NOTE
In different installation scenarios, the BBU3900 uses different power supply devices. The following describes
the power supply device of the DBS3900.
l In the scenario of outdoor AC power supply, the BBU3900 is installed in the APM30 AC
power supply cabinet and uses the AC power module.
l By default, the APM30 AC power cabinet contains an AC power supply module. Therefore,
you do not need to install it onsite.
The AC power supply module consists of the PMU, PSUAC/DC, and power supply subrack, as
shown in Figure 3-8.
PDU
The PDU supports 220/110 V AC input, 2 lines of AC output, and 10 lines of –48 V DC output
for AC/DC power distribution.
l By default, the APM30 AC power supply cabinet uses the PDU.
l Output current:
– AC: 10 A (max.)
– DC: 4 A (LOAD0–LOAD1), 12 A (LOAD2–LOAD3), 20 A (LOAD4–LOAD9)
NOTE
By default, the APM30 AC power cabinet contains a PDU. Therefore, you do not need to install it onsite.
(1) AC input wire terminal (2) AC input wire terminal (3) AC input wire terminals (4) AC output wire
(N) (L) (Lout1 and Lout2) terminals (Nout1 and
Nout2)
(5) MCB for AC input (6) MCB for AC output (7) MCBs for DC output (8) DC input wire terminals
(SW0–SW9) (LOAD0–LOAD9)
L3 L3
NOTE
The strap for the L wire post of AC INPUT on the PDU is installed before delivery. If the AC input is three-
phase 220 V, you must remove the strap from the L wire post.
DCDU
The DCDU supports one line of –48 V DC input and nine lines of –48 DC output for DC power
distribution.
By default, the APM30 (–48 V DC) AC power cabinet contains a DCDU-03C. Therefore, you do not need
to install it onsite.
Models have the same exterior design. The silkscreen indicating the model is printed on the
bottom-right of the panel, as shown in Figure 3-10.
Cable Connections Between the Power Distribution Box and the BBU3900
In the DBS3900, the power distribution box is the direct power supply device for the BBU3900.
It supplies –48 V DC power to the BBU3900.
The 3V3 connector of the BBU3900 –48 V power cable is connected to the UPEU, and the OT
terminal is connected to the DC output terminal of the power distribution box. For the cable
connections between the power distribution box and the BBU3900, refer to Table 3-5.
Table 3-5 Cable connections between the power distribution box and the BBU3900 (DBS3900)
3.4 SLPU
The Signal Lightning Protection Unit (SLPU) is installed outside the BBU3900. It protects the
E1/T1 signals and Ethernet signals from lightning surge.
Function
In the SLPU, the use of the UFLP or the UELP depends on the type of the trunk cable. Figure
3-11 shows the SLPU panel.
Configuration Principle
The use of the SLPU must follow the following rules:
l When the BBU3900 uses a UTRP, the SLPU must be used.
3.5 EMUA
The Environment Monitoring Unit (EMUA) is used to monitor the environment variables inside
the cabinet and handle the alarms. The BBU3900 can monitor the cabinet environment and dry
contact alarms through the EMUA.
Function
l Supporting a maximum of 32 dry contact connections
l Supporting the installation in the 19-inch cabinet and on the indoor installation rack
l Supporting the following monitoring items:
– Environment monitoring (including temperature, water penetration, smoke, and fog)
– Intruder monitoring (through infrared or access control)
– Monitoring power distribution
Configuration Principle
The BBU3900 provides 16 dry contact connections and two 485 alarm connections. The EMUA
can be added to expand the environment monitoring capacity and dry contract capacity.
The use of the EMUA must follow the following rules:
l If the number of alarm connections is smaller than 16, the EMUA is not required.
l If the number of alarm connections is greater than 16 and smaller than 32, an EMUA is
required.
For details about the EMUA, see the EMUA User Guide.
Figure 4-2 Space for different installation modes of the BBU3900 (unit: mm)
l A minimum space of 25 mm [0.98 in.] must be ensured on both sides for ventilation.
l A minimum space of 70 mm [2.76 in.] must be ensured in front of the panel for cable run.
NOTE
The D in this table stands for the diameter of the cable sheath, and the R stands for the bend radius of the
cable.
l To avoid damaging fibers, you must stuff the fiber inlet with soft filler. Fire cotton is
recommended.
l Before installation, check whether the fiber connector is contaminated. If it is contaminated,
use dust-free cotton or fiber optic cleaning kits to clean the connector.
l E1/T1 cables, FE cables and fibers can be used to connect the BBU to the BSC.
l The two types of CPRI cables, SFP cable and optical cable, can both be used to connect
the BBU and the RRU/ODU through their CPRI ports that is SFP ports. To use fibers,
optical modules are required.
l E1 conversion cables are used to connect the UELP/UFLP and the CMPT.
l DC power cables and signal cables are used to connect the BBU and the auxiliary devices.
NOTE
l If the BBU is installed in a 19-inch rack, you must install the PGND cables to ensure the grounding.
l The cable run of the BBU must meet the standard. The cables led from the boards on the left must be
routed along the left side of the BBU, and the cables led from the boards on the right must be routed
along the right side of the BBU
Unpacking the carton to check the integrity of the equipment is the prerequisite for installation.
Universal tools Measuring and Long tape, ruler (1 m [3.28 ft.]), marker, powder
marking marker, and pencil
instruments
Drilling tools One percussion drill, matched drill bits, and one
cleaner
CAUTION
When transporting, moving, and installing the equipment, components, or parts, prevent them
from colliding with doors, walls, or shelves.
CAUTION
The BTS must be powered on within 24 hours after the installation is complete.
When the BBU3900 is installed in the 19-inch cabinet, the cables to be installed are the power
cables, E1/T1/FE cables, CPRI cables, and alarm cables.
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Hold the BBU with both hands and align the mounting ears with the holes on the cabinet. Then
push the BBU into the cabinet along the guide rails.
Step 2 Use the Phillips screwdriver and four panel screws to fix the BBU to the cabinet. See Figure
4-4.
----End
Prerequisite
The Phillips screwdriver is available.
Installation Position
Figure 4-5 shows the installation position of the DCDU in the cabinet.
Procedure
Step 1 Hold the DCDU with both hands and place it in the position.
Step 3 Use the Phillips screwdriver and four screws to fix the DCDU in the cabinet by the mounting
ears on both sides.
----End
Prerequisite
The Phillips screwdriver is available.
Installation Position
Figure 4-6 shows the installation position of the SLPU in the cabinet.
Procedure
Step 1 Hold the SLPU with both hands and place it in the position.
Step 2 Push it into the cabinet.
Step 3 Use the Phillips screwdriver and four screws to fix the SLPU in the cabinet by the mounting
ears on both sides.
----End
Figure 4-8 Example of the BBU3900 cable layout in the 19-inch cabinet
This describes how to install power cables in the 19-inch cabinet. Power cables of the BBU3900
are used to connect the PWR port on the panel of the BBU3900 and the 12 A DC output wire
terminal in the DCDU of the 19-inch cabinet.
4.4.4.2 Installing E1/T1 Cables in the 19-Inch Cabinet
When the transmission mode between the BBU3900 and the BSC is E1/T1, E1/T1 cables must
be installed and lightning protection must be implemented for the cables.
4.4.4.3 Installing FE Cables in the 19-Inch Cabinet
When the transmission mode between the BBU3900 and the BSC is FE, FE cables must be
installed and lightning protection must be implemented for the cables.
4.4.4.4 Installing CPRI Cables in the 19-Inch Cabinet
When the BBU3900 is connected with the RRU/ODU through the CPRI port, the CPRI cable
can be an SFP cable or a fiber.
4.4.4.5 Installing Alarm Cables in the 19-Inch Cabinet
The alarm cable carries the alarm signals from the external alarm devices to the BBU3900.
Prerequisite
The Phillips screwdriver, wire nipper, multi-function pincers are available.
CAUTION
Before installation, ensure that the 19-inch cabinet is powered off.
Context
l For the BBU3900 installed in a 19-inch cabinet, the DCDU-O3B is recommended.
l The DCDU-O3B supports –48 V DC input for DC power distribution. For the details about
the DCDU-O3B, refer to PDU.
Procedure
Step 1 Connect the 3V3 connector of the power cable to the PWR ports on the BBU3900 panel, and
then tighten the screws on the connectors. See Figure 4-9.
Step 2 Connect the two OT terminals of the power cable to the 12 A DC output wire terminal in the
DCDU, and then tighten the screws.
12 A DC output wire terminals in the DCDU-03B: LOAD0–LOAD2.
----End
Prerequisite
l The Phillips screwdriver is available.
Context
l For E1/T1 transmission, the UELP is used to provide lightning protection.
l The E1/T1 conversion cables are used to connect the CMPT and the UELP.
l The E1/T1 cables are used to connect the UELP and the BSC.
Procedure
Step 1 Connect the DB26 connector of the E1/T1 cable to the E1/T1 port on the CMPT, and the DB25
connector to the INSIDE port on the UELP.
Step 2 For E1 cable layout outside the cabinet, refer to 4.1.3 General Requirements for BTS Cable
Layout.
Step 3 For leading the E1/T1 cable into the cabinet through the cable inlet on the right, refer to Figure
4-8.
Step 4 Connect the E1/T1 cable to the OUTSIDE port on the UELP.
Step 5 Route the E1 cable along the cabling space on the right inside the cabinet, and then use cable
ties to fix it.
Step 8 Use sealing glue to seal the E1/T1 cable, as shown in Figure 4-11.
NOTE
After the installation of all cables, use sealing glue to seal them.
Step 9 Use cable ties to bind the conductive cloth and the shielding layer together to ground the shielding
layer, as shown in Figure 4-12.
----End
Prerequisite
l The Phillips screwdriver is available.
Context
l For FE transmission the UFLP is used to provide lightning protection.
l The FE conversion cables are used to connect the CMPT and the UFLP.
l The FE cables are used to connect the UFLP and the BSC.
NOTE
Procedure
Step 1 Connect one end the FE cable to the FE0 port on the CMPT, and the other end to the INSIDE
port on the UFLP.
Step 2 For FE cable layout outside the cabinet, refer to 4.1.3 General Requirements for BTS Cable
Layout.
Step 3 After the FE cable is led into the cabinet, connect the RJ45 connector to the OUTSIDE port on
the UFLP.
Step 4 Route the FE cable along the cabling space in the cabinet, and then use cable ties to fix it.
----End
Postrequisite
After the installation of all cables, use sealing glue to seal them. For the details, refer to 4.4.4.2
Installing E1/T1 Cables in the 19-Inch Cabinet.
Prerequisite
l The Phillips screwdriver is available.
Context
l When the BBU3900 and the RRU/ODU are not in the same location, or when the BBU3900
is installed outdoors, you must connect a fiber to the CPRI port.
l When the BBU3900 and the RRU/ODU are in the same location, you can connect an SFP
cable to the CPRI port.
l When the optical cable is used, you must connect a removable optical module to the CPRI
port.
l Table 4-3 lists the connections of the CPRI cables.
NOTE
For the routing and sealing treatment of the SFP cable, refer to 4.4.4.3 Installing FE Cables in the 19-
Inch Cabinet. The following describes how to install fibers.
CAUTION
l The bend radius of a fiber cannot exceed 20 times of the diameter of the fiber. During
installation, avoid bending the fiber or its tail to a very acute angle.
l The end with the longer bare tail is connected to the BBU, and the end with the shorter one
is connected to the RRU/ODU.
CAUTION
During operation, ensure the ESD protection, for example, wearing an antistatic wrist strap or
gloves to protect the boards, modules, and electronic components against static damage.
Procedure
Step 1 Attach color ring labels to the optical fibers.
Step 2 For E1 cable layout outside the cabinet, refer to 4.1.3 General Requirements for BTS Cable
Layout.
Step 3 Remove the protective caps from the optical modules and the optical fibers.
Step 4 Insert the optical module into the SFP port on the BBU channel board.
Step 5 Insert the connector at one end of the optical fiber into the optical module, as shown in Figure
4-13.
CAUTION
Prevent the cabinet doors from catching the fibers.
Step 6 Wind the fiber winding tube around the tail, and the use fiber ties to fix it, as shown in Figure
4-14.
Step 7 Lead one end of the fiber out of the APM30 from the cable hole at the bottom right of the cabinet.
Step 8 Route the other end of the fiber close to the RRU/ODU.
Step 9 Insert the optical module of the CPRI port into the socket on the panel of the RRU/ODU, as
shown in Figure 4-15.
The silkscreen of the CPRI port on the RRU is CPRI_W, and the silkscreen of the CPRI port
on the ODU is A.
Step 10 Route the fibers along the cabling space in the cable cavity in the RRU/ODU.
Step 11 Insert the connector at one end of the optical fiber into the optical module on the panel of the
RRU/ODU.
Step 12 Attach labels to the fibers.
----End
Postrequisite
After the installation of all cables, use sealing glue to seal them. For the details, refer to 4.4.4.2
Installing E1/T1 Cables in the 19-Inch Cabinet.
Procedure
Step 1 Connect the RJ45 connector of the alarm cable to the EXT_ALM0 port or the EXT_ALM1
port on the panel of the UPEU, as shown in Figure 4-16.
Step 2 Add the terminal that the external alarm device requires to the other end of the alarm cable. For
the description of the cores and pins of the alarm cable, refer to Alarm Cable of the
BBU3900.
Step 3 Route the alarm cable along the cabling space on the right of the cabinet, and then use cable ties
to fix it.
Step 4 Connect the alarm cable to the alarm signal port on the external alarm device.
Step 5 Attach labels to the alarm cables.
----End
Context
l When the BBU3900 is installed in the APM30 AC cabinet, it supports the input modes of
110 V dual-phase, 220 V single-phase, and 220 V three-phase AC.
l When the BBU3900 installed in (–48 V) DC cabinet, it supports the –48 V DC input.
4.5.1 Installing the BBU3900 Body in the AMP30
Prerequisite
The Phillips screwdriver is available.
Installation Position
Figure 4-17 shows the installation position of the BBU3900 in the APM30. Figure 4-18 shows
the installation position in the APM30 (–48 V) DC cabinet.
Figure 4-18 Installation position of the BBU3900 in the APM30 (–48 V) DC cabinet
Procedure
Step 1 Install and tune the guide rails according to the actual situation.
Step 2 Hold the BBU3900 with both hands and align the mounting ears with the holes on the cabinet.
Then push the BBU3900 into the cabinet along the guide rails.
Step 3 Use four panel screws M6x12 to fix the BBU3900 in the APM30.
----End
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Position the SLPU and tune the guide rails according to the actual situation.
The recommended position for the SLPU is the space under the BBU3900 body.
Step 2 Hold the SLPU with both hands and place it in the position.
Step 4 Use the Phillips screwdriver and four screws to fix the SLPU in the cabinet by the mounting
ears on both sides.
----End
Figure 4-20 Example of the BBU3900 cable layout in the APM30 cabinet
Prerequisite
The Phillips screwdriver, wire nipper, multi-function pincers are available.
CAUTION
Before installation, ensure that the APM30 is powered off.
Context
l The APM30 has two models: APM30 AC power cabinet and APM30 (–48 V) DC power
cabinet.
l Different APM30 models have different DC power distribution boxes. For details, see
Power Distribution Box.
Procedure
Step 1 Connect the 3V3 connector of the power cable to the PWR ports on the BBU3900 panel, and
then tighten the screws on the connectors. See Figure 4-21.
Step 2 In the case of the APM30 AC power cabinet, connect the two OT terminals of the power cable
to the 12 A DC output wire terminal in the PDU, and then tighten the screws.
12 A DC input wire terminals in the PDU: LOAD2–LOAD3.
Step 3 In the case of the APM30 (–48 V) DC power cabinet, connect the two OT terminals of the power
cable to the 12 A DC output wire terminal in the DCDU-03C, and then tighten the screws.
----End
Prerequisite
l The Phillips screwdriver is available.
Context
l For E1/T1 transmission the UELP is used to provide lightning protection.
l The E1/T1 conversion cables are used to connect the CMPT and the UELP.
l The E1/T1 cables are used to connect the UELP and the BSC.
NOTE
Procedure
Step 1 Connect the DB26 connector of the E1/T1 cable to the E1/T1 port on the CMPT, and the DB25
connector to the INSIDE port on the UELP.
Step 2 For E1 cable layout outside the cabinet, refer to 4.1.3 General Requirements for BTS Cable
Layout.
Step 3 For leading the E1/T1 cable into the cabinet through the cable inlet on the right, refer to Figure
4-8.
Step 4 Connect the E1/T1 cable to the OUTSIDE port on the UELP.
Step 5 Route the E1 cable along the cabling space on the right inside the APM30, and then use cable
ties to fix it.
Step 6 Attach labels to the E1/T1 cable.
Step 7 At the part near the signal cable hole, strip a section (20 mm to 30 mm [0.79 in. to 1.18 in.]) off
the E1 cable to expose the shielding layer.
Step 8 Route the E1 cable through the metal grounding clip on the right side of the cabinet and ensure
the contact between them to ground the E1/T1 cable. See Figure 4-22.
----End
Postrequisite
After the installation of all cables, use sealing glue to seal them. For the details, refer to 4.4.4.2
Installing E1/T1 Cables in the 19-Inch Cabinet.
Prerequisite
l The Phillips screwdriver is available.
Context
l For FE transmission the UFLP is used to provide lightning protection.
l The FE conversion cables are used to connect the CMPT and the UFLP.
l The FE cables are used to connect the UFLP and the BSC.
NOTE
Procedure
Step 1 Connect one end the FE cable to the FE0 port on the CMPT, and the other end to the INSIDE
FE port on the UFLP.
Step 2 For FE cable layout outside the cabinet, refer to 4.1.3 General Requirements for BTS Cable
Layout.
Step 3 After the FE cable is led into the APM30, connect the RJ45 connector to the OUTSIDE port on
the UFLP.
Step 4 Route the FE cable along the cabling space in the APM30, and then use cable ties to fix it.
----End
Postrequisite
After the installation of all cables, use sealing glue to seal them. For the details, refer to 4.4.4.2
Installing E1/T1 Cables in the 19-Inch Cabinet.
Prerequisite
l The Phillips screwdriver is available.
Context
l When the BBU3900 and the RRU/ODU are not in the same location, or when the BBU3900
is installed outdoors, you must connect a fiber to the CPRI port.
l When the BBU3900 and the RRU/ODU are in the same location, you can connect an SFP
cable to the CPRI port.
l When the optical cable is used, you must connect a removable optical module to the CPRI
port.
NOTE
For the routing and sealing treatment of the SFP cable, refer to 4.4.4.3 Installing FE Cables in the 19-
Inch Cabinet. The following describes how to install fibers.
CAUTION
l The bend radius of a fiber cannot excceed 20 times of the diameter of the fiber. During
installation, avoid bending the fiber or the tail to a very acute angle.
l The end with the longer bare tail is connected to the BBU, and the end with the shorter one
is connected to the RRU/ODU.
CAUTION
During operation, ensure the ESD protection, for example, wearing an antistatic wrist strap or
gloves to protect the boards, modules, and electronic components against static damage.
Procedure
Step 1 Attach color ring labels to the optical fibers.
Step 2 For E1 cable layout outside the cabinet, refer to 4.1.3 General Requirements for BTS Cable
Layout.
Step 3 Remove the protective caps from the optical modules and the optical fibers.
Step 4 Insert the optical module into the SFP port on the BBU channel board.
Step 5 Insert the connector at one end of the optical fiber into the optical module, as shown in Figure
4-23.
CAUTION
Prevent the doors of the APM30 from catching the fibers.
Step 6 Wind the fiber winding tube around the tail, and the use fiber ties to fix it, as shown in Figure
4-24.
Step 7 Lead one end of the fiber out of the APM30 from the cable hole at the bottom right of the cabinet.
Step 8 Route the other end of the fiber close to the RRU/ODU.
Step 9 Insert the optical module of the CPRI port into the socket on the panel of the RRU/ODU, as
shown in Figure 4-25.
The silkscreen of the CPRI port on the RRU is CPRI_W, and the silkscreen of the CPRI port
on the ODU is A.
Step 10 Route the fibers along the cabling space in the cable cavity in the RRU/ODU.
Step 11 Insert the connector at one end of the optical fiber into the optical module on the panel of the
RRU/ODU.
Step 12 Attach labels to the fibers.
----End
Postrequisite
After the installation of all cables, use sealing glue to seal them. For the details, refer to 4.4.4.2
Installing E1/T1 Cables in the 19-Inch Cabinet.
Procedure
Step 1 Connect the RJ45 connector of the alarm cable to the EXT_ALM0 port or the EXT_ALM1
port on the panel of the UPEU, as shown in Figure 4-26.
Step 2 Add the terminal that the external alarm device requires to the other end of the alarm cable. For
the description of the cores and pins of the alarm cable, refer to Alarm Cable of the
BBU3900.
Step 3 Route the alarm cable along the cabling space on the right of the APM30, and then use cable
ties to fix it.
Step 4 Connect the alarm cable to the alarm signal port on the external alarm device.
Step 5 Attach labels to the alarm cables.
----End
Procedure
Step 1 Connect the RJ45 connector of the signal cable to the MON0 port or the MON1 port on the
panel of the UPEU, as shown in Figure 4-27.
Step 2 Remove RJ45 connector from the signal cable, and the connect X1.1, X1.2, X1.4, X1.5 to the
ports corresponding to the wire terminals according to the colors of the cores. See Table 4-5.
Table 4-5 Cores and pins of the APM30 (–48 V) signal cable
Step 3 Connect the two wire terminals to the TX-TX+ port and the RX-RX+ port on the panel of the
APMI, as shown in Figure 4-28.
Figure 4-28 Connecting the environment signal cable to the panel of the APMI
Step 4 Route the signal cable along the cabling space on the right inside the APM30, and then use cable
ties to fix it.
----End
When the BBU3900 is installed on the indoor installation rack, the cables to be installed are the
power cables, PGND cable, E1/T1/FE cables, CPRI fibers, alarm cables, and environment signal
cables.
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Hold the BBU with both hands and align the mounting ears with the holes on the cabinet.
Step 2 Use the Phillips screwdriver and four panel screws to fix the BBU to the subrack, as shown in
Figure 4-29.
Figure 4-29 Installing the BBU3900 body on the indoor installation rack
----End
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Hold the DCDU with both hands and align the mounting ears with the holes on the indoor
installatio rack.
Step 2 Use the Phillips screwdriver and four panel screws to fix the DCDU to the subrack, as shown
in Figure 4-30.
----End
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Hold the SLPU with both hands and align the mounting ears with the holes on the indoor
installation rack.
Step 2 Use the Phillips screwdriver and four panel screws to fix the SLPU to the rack.
----End
CAUTION
l When the BBU3900 is installed on the indoor installation rack, PGND cables must be
installed.
l One end of the PGND cable is connected to the grounding screw on the BBU3900, and the
other end is connected to the grounding screw on the side of the indoor installation rack.
Cable Connections
l When the BBU3900 is installed on the indoor installation rack, the DCDU-03B is used.
For the cable connections between the power distribution box and the BBU3900, refer to
Table 3-5.
l For the details about other cable connections, refer to 2.3 BBU3900 Cables.
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Hold the BBU with both hands and align the mounting ears with the holes on the cabinet.
Step 2 Use the Phillips screwdriver and four panel screws to fix the BBU to the subrack, as shown in
Figure 4-33.
Figure 4-33 Installing the BBU3900 body (in the 19-inch rack)
----End
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Hold the DCDU with both hands and align the mounting ears with the holes on the indoor
installation rack.
Step 2 Use the Phillips screwdriver and four panel screws to fix the DCDU to the rack.
----End
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 Hold the SLPU with both hands and align the mounting ears with the holes on the indoor
installation rack.
Step 2 Use the Phillips screwdriver and four panel screws to fix the SLPU to the rack.
----End
CAUTION
l When the BBU3900 is installed in the 19-inch rack, PGND cables must be installed.
l One end of the PGND cable is connected to the grounding screw on the BBU3900, and the
other end is connected to the grounding screw at the bottom of the 19-inch rack.
For the details about the cable connections, refer to 2.3 BBU3900 Cables.
Cable Connections
l When the BBU3900 is installed in the 19-inch rack, the DCDU-03B is used. For the cable
connections between the power distribution box and the BBU3900, refer to Table 3-5.
l For the details about other cable connections, refer to 2.3 BBU3900 Cables.
Procedure
Step 1 Remove the filler panel in the BBU subrack.
Step 2 Insert the BBU3900 into a BBU subrack, and then screw the BBU3900, as shown in Figure
4-36.
NOTE
l A BTS3606AE can be configured with BBU subrack 0 and BBU subrack 1, which house two
BBU3900s.
l When only one BBU3900 is configured, install it in BBU subrack 0.
l The BBU3900 installed in the BTS3606AE cabinet supports only +24 V DC power input, which is
distributed by the DC power distribution unit of the ODU or BBU in the BTS3606AE cabinet.
----End
Prerequisite
Context
Figure 4-37 shows the power cable of the BBU3900.
Procedure
Step 1 Connect the two 3-pin D connectors at one end of the power cable to the PWR ports on the
BBU3900 panel, and then fasten the screws on the connectors.
Step 2 Connect another 3-pin D connector at the other end of the power cable to BBU0 port on the DC
power distribution unit of the ODU or BBU.
Figure 4-38 shows the connection of the power cable.
----End
Prerequisite
Context
Figure 4-39 shows the SFP cable.
NOTE
l Before delivery, one end of the SFP cables is connected to the SFP port (with the silk screen "A") on
the OMTR and the SFP cables are preset in the RFC.
l When the SFP cable is used to connect the HCPM/HECM in the BBU3606 with the OMTR in the RFC,
you need not install the removable optical module, which is only required when you use optical fibers
to connect the HCPM/HECM in the BBU3606 with a lower-level BTS.
l After all the cables are connected, you need to seal the cable inlets and outlets at the bottom of the BBC
using plaster.
Procedure
Step 1 Route the other end of the SFP cables into the BBC through the cable inlet/outlet, as shown in
Figure 4-40.
Step 2 Route the SFP cables along the cabling trough at the right side of the BBC, and then connect
them to the SFP ports on the HCPM/HECM.
Figure 4-41 shows the connections of the SFP cables.
Step 3 Seal the cable inlet/outlet at the bottom of the BBC using plaster.
----End
Prerequisite
Context
The GPS clock cables are shown as follows:
l Figure 4-42 shows the GPS clock cable connected to the CMPT panel.
l Figure 4-43 shows the GPS clock cable interconnected with the external GPS feeder.
Figure 4-43 GPS clock cable interconnected with the external GPS feeder
Procedure
Step 1 Insert the SMA connector of the GPS clock cable into the port of the GPS clock cable on the
CMPT of the BBU3606.
Step 2 Remove the cover plate from the GPS clock cable outlet at the bottom of the BBC, as shown in
Figure 4-44.
Figure 4-44 Removing the cover plate from the GPS clock cable outlet at the bottom of the BBC
Step 3 Remove the nuts on the N-type connector. Route the N-type connector through the cover plate,
and then fasten the connector using the removed nuts.
Step 4 Route the external GPS feeder into the cabinet, and then interconnect the GPS feeder with the
N-type connector, as shown in Figure 4-45.
Step 5 Waterproof the N-type connectors at the bottom of the BBC. Do not use tape to wrap the screw
holes of the connectors,as shown in Figure 4-46.
----End
Postrequisite
You must power on the BTS, install the BTS software, and perform the initial configuration
after finishing the check. For the subsequent operations, refer to the related manuals.
1 All the screws that fix the BBU3900 are securely fastened.
4 The cables are bundled neatly with proper force. The cable ties are
arranged in the same direction and at the same interval.
5 Excess cable tails are cut and all the cable tails are flushed.
7 The boards installed in the BBU3900 are consistent with the boards listed
in the packing list.
Prerequisite
l The BBU3900 is properly installed and passes the installation check.
l The external power input of the BBU3900 meets the requirements.
– The BBU3900 supports two lines of –48 V DC/+24 V DC input
– In the DBS3900, the BBU3900 supports the input mode of –48 V DC.
– The BBU3900 installed in a BTS3606AE supports only +24 V DC input.
Procedure
Step 1 Set the external power switch to OFF.
Step 2 Ensure that all the boards in the BBU3900 are properly connected with the subrack.
Step 4 Observe the status of the RUN indicator on the UPEU panel, and then proceed with the next step
according to the indicator status.
If... Then...
l The RUN indicator is ON, You can infer that the UPEU starts to work.
Proceed with Step 5.
l The RUN indicator is OFF, You can infer that the UPEU is faulty or there
is no external power input. To clear the fault,
do as follows:
l Ensure that the external power cable is
properly connected.
l Remove the board and check whether the
pins are damaged. If the board pins are
damaged, replace the board. If the board
pins are intact, reinstall the board.
If the indicator is still OFF, contact Huawei
Technical Support.
Step 5 Power on other boards of the BBU3900 and load the software. Observe the indicator status, and
then proceed with the next step according to the indicator status.
If... Then...
l The RUN indicator blinks at 4 Hz, and You can infer that the board is being loaded.
l The ALM indicator is OFF
Other states You can infer that the board is faulty. Clear
the fault and proceed with Step 3.
Step 6 After the board software is loaded, the status of the board indicator changes. Proceed with the
next step according to the indicator status.
If... Then...
l The RUN indicator blinks at 0.5 Hz, and You can infer that the board functions
l The ALM indicator is OFF properly.
Other states You can infer that the board is faulty. Clear
the fault and proceed with Step 3.
----End
The BBU3900 contains mandatory boards (CMPT, HCPM/HECM, and UPEU), optional boards
(UTRP and USCU), and other modules. Data configuration should be performed on mandatory
boards and optional boards. For other modules, data configuration is not required.
Context
For the introduction to and configuration principle of the BBU3900, see BBU3900.
5.1 Configuring the CMPT
This describes how to configure the CMPT.
5.2 Configuring the UTRP
This describes how to configure the UTRP.
5.3 Configuring the HCPM
This describes how to configure the HCPM.
5.4 Configuring the HECM
This describes how to configure the HECM.
5.5 Configuring the UPEU
This describes how to configure the UPEU.
5.6 Configuring the USCU
This describes how to configure the USCU.
Task Description
Objective To configure the CMPT of the BBU3900.
Scenario This task is mandatory for the initial configuration of the BBU3900.
Data Preparation
Procedure
Run the ADD CBTSCMPT command to add a CMPT.
----End
Example
[Example] Add the active CMPT in BTS 1.
ADD CBTSCMPT: BTSID=1, BRDID=0;
Task Description
Objective To configure the UTRP of the BBU3900.
Scenario This task is mandatory when the UTRP is installed in the BBU3900.
Precautions l The UTRP cannot work with the UELP/UFLP. Do not configure both of
them in the BBU3900.
l The UTRP supports only E1/T1 transmission mode.
Data Preparation
Procedure
Run the ADD CBTSUTRP command to add a UTRP.
----End
Example
[Example] Add No.1 active UTRP in BTS 1.
ADD CBTSUTRP: BTSID=1, BRDID=1;
Task Description
Objective To configure the HCPM of the BBU3900.
Scenario This task must be performed to enable the BTS to support CDMA2000 1X
services.
Precautions The HCPM can be configured only after the corresponding resource pool is
successfully configured.
Data Preparation
Procedure
Step 1 Run the ADD CBTSCPL command to add a new resource pool to the BTS. (This step is
optional.)
Step 2 Run the ADD CBTSCPM command to add a HCPM.
Step 3 Run the SET CBTSCDMA1XCTRLPARA command to set the control parameters of the
HCPM. (This setp is optional.) The values must comply with the RNP requirements.
----End
Example
[Example] To add HCPM 1 of BTS 1 to resource pool 0, which is already configured, run the
following command:
ADD CBTSCPM: BTSID=1, BRDID=1, CPLID=0;
Task Description
Objective To configure the HECM of the BBU3900.
Scenario This task must be performed to enable the system to support CDMA2000
1xEV-DO services.
Precautions The HECM can be configured only after the corresponding resource pool is
successfully configured.
Data Preparation
Procedure
Step 1 Run the ADD CBTSCPL command to add a resouce pool to the new BTS. (This step is optional.)
This step is performed to add a resource pool. If an existing resource pool is available, skip this
step.
Step 2 Run the ADD CBTSECM command to add a HECM.
Step 3 Run the SET CBTSCDMADOCTRLPARA command to set the control parameters of the
HECM. (This step is optional.) The values must comply with the RNP requirements.
----End
Example
[Example] To add HECM 1 of BTS 1 to resource pool 1, which is already configured, run the
following command:
ADD CBTSECM: BTSID=1,BRDID=1,CPLID=1;
Task Description
Objective To configure the UPEU of the BBU3900.
Scenario This task is mandatory for the initial configuration of the BBU3900.
Precaution There are UPEUs of two models, which support power input of –48 V DC and
s + 24 V DC respectively.
Data Preparation
Procedure
Run the ADD CBTSUPEU command to add a UPEU.
----End
Example
[Example] Add UPEU 0 in BTS 1.
ADD CBTSUPEU: BTSID=1, BRDID=0;
Task Description
Objective To configure the USCU of the BBU3900.
Scenario This task is mandatory when the USCU is installed in the BBU3900.
Data Preparation
Board ID BRDID The board ID can be only 0 or 1, and only one USCU
can be added through one operation.
Procedure
Run the ADD CBTSUSCU command to add a USCU.
----End
Example
[Example] Add USCU 0 in BTS 1. The USCU supports the GPS satellite card and is inserted
into slot 2.
/* A GPS satellite card is used, so SNUM is 1. The USCU is inserted in slot 2, so SN is 2.*/
ADD CBTSUSCU: BTSID=1,BRDID=0,SNUM=1,SN=2;
After the site starts operation, you must perform routine maintenance for the BBU to ensure the
operation condition.
Context
Table 6-1 lists the equipment maintenance items.
Checking the Every week or Check the fans. Alarms related to the fans
fans every month are not generated.
(quarter)
Checking the Every month Check whether the status of The indicators indicate no
indicators (quarter) the indicators of the alarm.
equipment.
Power-On Check
For the procedure of power-on check, refer to Powering On the BBU3900.
Procedure
Step 1 As for powering off the BBU3900, you can perform regular power-off or emergent power-off
as needed.
If... Then...
Step 2 Stop the power supply of the BBU3900, and then switch off the power supply device provided
by the customer.
Step 3 Switch off the power supply device provided by the customer, and then stop the power supply
of the BBU3900 if time permits.
----End
Prerequisite
The Phillips screwdriver is available.
Procedure
Step 1 On the LMT, run the ULD CBTSSW command to upload the data configuration file to the LMT.
Step 2 Follow the instruction in Powering Off the BBU3900 to power off the BBU3900 and terminate
the external power supply.
Step 3 Mark the cables on the BBU3900 and then remove them and take insulation measures to protect
them.
NOTE
Remove the power cable, alarm cable, FE cable, E1 cable, CPRI cable, and PGND cable from the BBU3900.
Step 4 Use a Phillips screwdriver to loosen the four screws on the body.
Step 6 Place the new BBU3900 body into the slot of the faulty BBU3900 body, and the push it in.
Step 8 Switch on the external power supply of the BBU3900, and then follow instruction in Powering
On the BBU3900 to perform power-on.
Step 9 On the LMT, run the DLD CBTSSW command to download the data configuration file to the
new BBU3900.
Step 10 On the LMT, run the LST CBTSVER command to confirm the software version.
Step 11 Run the STR CBTS command the restart the BTS.
----End
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
The BBU3900 can be equipped with a maximum of two CMPTs, which work in active/standby
mode.
CAUTION
The impact of replacing the CMPT is as follows:
l If only one CMPT is installed in the BBU3900, the replacement disrupts the BTS services.
l If two CMPTs are installed in the BBU3900, the replacement does not disrupt the BTS
services.
NOTE
The following description is based on the BBU3900 with only one CMPT. If the BBU3900 has two CMPTs,
you can replace the faulty board without blocking the carriers.
Procedure
Step 1 Mark the position of the faulty board.
Before replacing the SPSU, attach a replacement label on the panel of the CMPT to be replaced
to avoid maloperations.
2. Run the DSP RES command to check whether the status of all the carriers of the BTS is
Blocked. If all the carriers of the BTS are blocked, go to the next step.
Step 5 Load.
l If the BTS auto-loading function is enabled, the system automatically loads the software of
the CMPT from the BAM after the CMPT is inserted into the subrack.
l If the auto-loading function is disabled, run the DLD CBTSSW command to load the
software of the CMPT.
Run the UBL RES command to unblock all the carriers of the BTS.
NOTE
Before replacing the CMPT, check the status of the E1/T1 links. Run the DSP CBTSLNKSTAT command
to query the links. Check and ensure that the operational status of the activated links is normal.
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
CAUTION
The impact of replacing the HCPM/HECM is as follows:
l If no cable is connected to the faulty board, the replacement disrupts only the services on
this board.
l If an RF module is connected to the faulty board, the replacement disrupts all carrier services
on this RF module.
Procedure
Step 1 Mark the position of the faulty board.
Before replacing the SPSU, attach a replacement label on the panel of the board to be replaced
to avoid maloperations.
Step 5 Load.
l If the BTS auto-loading function is enabled, the system automatically loads the field
programmable gate array (FPGA) software and then the CPU software for the HCPM/HECM
from the BAM after the HCPM/HECM is inserted into the subrack.
l If the auto-loading function is disabled, run the DLD CBTSSW command to load the FPGA
software and then the CPU software for the HCPM/HECM.
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
The BBU3900 can be equipped with a maximum of two UPEUs, which work in active/standby
mode. The configuration of two UPEUs is recommended because it is more reliable.
CAUTION
The impact of replacing the UPEU is as follows:
l If only one UPEU is installed in the BBU3900, the replacement stops the power supply and
disrupts the BTS services.
l If two UPEUs are installed in the BBU3900, the replacement does not disrupt the BTS
services.
NOTE
Procedure
Step 1 Remove the faulty UPEU.
1. Wear an ESD wrist strap and ESD gloves and insert the grounding plug into the antistatic
jack on the cabinet.
2. Set the switch on the panel of the UPEU to OFF.
3. If any cable is connected to the panel of the UPEU, label them and then remove them.
4. Loosen the two captive screws on the panel of the UPEU, and then remove the UPEU.
5. Put the removed board into an antistatic packing box/bag.
Step 2 Install the new UPEU.
1. Take out the new UPEU. Ensure that it is intact and its hardware version is the same as the
removed one.
2. Insert the new UPEU, and then tighten the captive screws on the panel of the UPEU.
3. If any cable was connected to the panel of the removed UPEU, restore the cable connections
according to cable labels.
4. Set the switch on the panel of the UPEU to ON.
Step 3 Check that the UPEU functions properly.
When a UPEU runs properly, the indicator is green and blinks at 0.5 Hz.
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
CAUTION
The replacement of the UTRP disrupts the transmission services on this board.
Procedure
Step 1 Mark the position of the faulty board.
Before replacing the SPSU, attach a replacement label on the panel of the UTRP to be replaced
to avoid maloperations.
Step 2 Block the carriers.
1. Run the BLK RES command to block all the carriers of the BTS. Set the priority to Low.
2. Run the DSP RES command to check whether the status of all the carriers of the BTS is
Blocked. If all the carriers of the BTS are blocked, go to the next step.
Step 3 Remove the faulty board.
1. Wear an ESD wrist strap and ESD gloves and insert the grounding plug into the antistatic
jack on the cabinet.
2. If any cable is connected to the panel of the UTRP, label them and then remove them.
3. Loosen the bolts on the panel, and then remove the board.
4. Put the removed board into an antistatic packing box/bag.
Step 4 Install the new board.
1. Take out the new UTRP. Ensure that it is intact and its hardware version is the same as the
removed one.
2. Insert the new UTRP, and then tighten the screws on the front panel.
3. If any cable was connected to the panel of the removed UTRP, restore the cable connections
according to cable labels.
Step 5 Load.
l If the BTS auto-loading function is enabled, the system automatically loads the CPU software
of the UTRP from the BAM after the UTRP is inserted into the subrack.
l If the auto-loading function is disabled, run the DLD CBTSSW command to load the
software of the UTRP.
Step 6 Unblock the carriers.
Run the UBL RES command to unblock all the carriers of the BTS.
Step 7 Check that the new board functions properly.
Refer to Verifying the Replaced Boards.
NOTE
Before replacing the UTRP, check the status of the E1/T1 links. Run the DSP CBTSLNKSTAT command
to query the links. Check and ensure that the operational status of the activated links is normal.
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
CAUTION
This replacement of the UELP/UFLP disrupts all services on the transmission links provided by
this board.
Procedure
Step 1 Mark the position of the faulty board.
Before replacing the SPSU, attach a replacement label on the panel of the board to be replaced
to avoid maloperations.
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
This topic describes how to install the hot-pluggable boards. All the BSC boards are hot-
pluggable.
Procedure
Step 1 Mark the position of the faulty board.
Before replacing the SPSU, attach a replacement label on the panel of the board to be replaced
to avoid maloperations.
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
The FAN is the heat dissipation entity of the BBU3900. The replacement of the FAN causes the
rise of temperature in the BBU3900. Replacing the SFBU within a short period does not affect
the BTS services.
Procedure
Step 1 Remove the faulty FAN.
1. Wear an ESD wrist strap and ESD gloves and insert the grounding plug into the antistatic
jack on the cabinet.
2. Loosen the two captive screws on the panel of the FAN, and then remove the FAN.
3. Put the removed board into an antistatic packing box/bag.
When a FAN runs properly, the indicator is green and blinks at 0.5 Hz.
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
l For details on the replacement preparations, see Preparing for Board Replacement.
Context
The removable optical module is used to connect a remote or cascading RRU/ODU. When
equipped with a removable optical module, the HCPM/HECM can be connected to the RRU/
ODU through a fiber.
Replacing the removable optical module disrupts all services provided by the connected RRU/
ODU.
Procedure
Step 1 Mark the position of the faulty optical module.
Before replacing the board, attach a replacement label near the faulty optical module to avoid
maloperations.
Run the UBL RES command to unblock all the carriers of the ODU connected through the port.
When the optical module is operational, the status of the indicators on the port is as follows:
l RX: blinking
l TX: blinking
----End
Postrequisite
1. Record the software version, board name, slot number, and site name of the faulty board.
2. Check whether there is visible physical damage on the board, for example, mechanical parts
or plug-ins are distorted, pins are bent or missing, or the board is burnt.
3. Record the information about the fault location process, including the cause of the fault,
fault symptoms, alarm name, status of indicators on the board panel, and detailed
procedures for identifying and clearing the fault on site.
4. Place the faulty board in an antistatic bag. Then, place the onsite fault record and the
antistatic bag in the board box, and store them properly.
Prerequisite
l Determine the type, model, and number of faulty cables and prepare the new cables.
l Ensure that the new trunk cables are intact. Do not use a cable with any damage.
l Record the installation positions and correspondence of the faulty trunk cables.
l If more than one cable needs to be replaced, add temporary labels to them. The temporary
labels help you identify the new cables. Ensure that the contents of the temporary labels
are the same as the contents of the labels on the faulty cables.
l Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Prerequisite
Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Context
CAUTION
Replacing the power cable of the BBU3900 disrupts all BTS services.
Procedure
Step 1 Cut a power cable with the same length as the original one.
Step 3 Use the Phillips screwdriver to loosen the screws on the 3V3 power connector, and then remove
the connector from the PWR port on the BBU panel.
Step 4 Connect the 3V3 power connector of the power cable to the PWR port on the BBU3900 panel,
and then fasten the screws on the connector.
Step 5 Route the new power cable along the original route to the external power supply.
Step 6 Strip the protection tube and shielding layer at the other end of the power cable and add an OT
terminal to it.
Step 7 Remove the faulty power cable, and then install the new power cable.
----End
Postrequisite
Discard the faulty trunk cables properly and clean the site.
Prerequisite
Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Context
CAUTION
When any E1/T1 cable is replaced, all the services carried on the cable are disrupted.
Procedure
Step 1 Mark the position of the faulty E1/T1 cable.
Before replacing the E1/T1 cable, attach a replacement label near the faulty E1/T1 cable to avoid
maloperations.
Run the UBL RES command to unblock all the carriers connected through the E1/T1 cable.
Run the DSP CBTSLNKSTAT command to query the links. Check and ensure that the
operational status of the used E1/T1 links is normal.
----End
Postrequisite
Discard the faulty trunk cables properly and clean the site.
Prerequisite
Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Context
CAUTION
Replacing an E1/T1 lightning protection conversion cable disrupts all transmission services on
the BTS.
Procedure
Step 1 Mark the position of the faulty E1/T1 cable.
Before replacing the E1/T1 cable, attach a replacement label near the faulty E1/T1 cable to avoid
maloperations.
Run the UBL RES command to unblock all the carriers connected through the E1/T1 cable.
Run the DSP CBTSLNKSTAT command to query the links. Check and ensure that the
operational status of the used E1/T1 links is normal.
----End
Postrequisite
Discard the faulty trunk cables properly and clean the site.
Prerequisite
Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Context
CAUTION
When any FE cable is replaced, all the services carried on the cable are disrupted.
Procedure
Step 1 Mark the position of the faulty FE cable.
Before replacing the E1/T1 cable, attach a replacement label near the faulty E1/T1 cable to avoid
maloperations.
Run the UBL RES command to unblock all the carriers connected through the FE cable.
Run the DSP CBTSFEPORTINFO command to query the links. Check and ensure that the
operational status of the used FE links is normal.
----End
Postrequisite
Discard the faulty trunk cables properly and clean the site.
Prerequisite
Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Context
CAUTION
Replacing an FE cable disrupts all transmission services on the BTS.
Procedure
Step 1 Mark the position of the faulty FE cable.
Before replacing the E1/T1 cable, attach a replacement label near the faulty E1/T1 cable to avoid
maloperations.
Step 2 Block the carriers.
1. Run the BLK RES command to block all the carriers connected through the FE cable. Set
the priority to Low.
2. Run the DSP RES command to check whether the status of all the carriers is Blocked. If
all the carriers of the BTS are blocked, go to the next step.
Step 3 Remove the FE cable.
1. Remove the FE cable from the CMPT.
2. Remove the FE cable from the FE lighting protection board.
3. Coil up the removed FE cable using a cable tray, and then put it into a plastic bag.
Step 4 Install the FE cable.
1. Take out the new FE cable and ensure that the new FE cable is intact and the model is the
same as the replaced one.
2. Connect the new FE cable to the original positions.
Step 5 Unblock the carriers.
Run the UBL RES command to unblock all the carriers connected through the FE cable.
Step 6 Ensure that the new FE cable functions properly.
Run the DSP CBTSFEPORTINFO command to query the links. Check and ensure that the
operational status of the used FE links is normal.
----End
Postrequisite
Discard the faulty trunk cables properly and clean the site.
Prerequisite
Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Context
CAUTION
When any CPRI cable is replaced, all the services carried on the cable are disrupted.
Procedure
Step 1 Mark the position of the faulty CPRI cable.
Before replacing the CPRI cable, attach a replacement label near the faulty cable to avoid
maloperations.
Run the UBL RES command to unblock all the carriers of the ODU connected through the CPRI
cable.
When the CPRI cable is operational, the status of the indicators on the port is as follows:
l RX: blinking
l TX: blinking
----End
Postrequisite
Discard the faulty trunk cables properly and clean the site.
Prerequisite
Required tools: ESD wrist strap and ESD gloves, cross screwdriver, and antistatic box/bag
Context
Both ends of the alarm cable are RJ45 connectors. One of the ends can be added with an OT
terminal.
Procedure
Step 1 Mark the position of the faulty alarm cable.
Before replacing the alarm cable, attach a replacement label near the faulty alarm cable to avoid
maloperations.
----End
Postrequisite
Discard the faulty trunk cables properly and clean the site.