Beruflich Dokumente
Kultur Dokumente
Thomas N. Hansen Tucson Electric Power Presented at: POWER-GEN International 2003 December 10, 2003
Introduction:
The long term commercialization of utility based solar PV electric generation requires the development of safe, reliable, affordable components and systems that meet utility expectations of performance and life cycle cost per kWh production goals, while allowing for full integration of time variant intermittent renewable generation resources in the utility generation portfolio. The higher cost of PV generation as compared to the price of traditionally fueled grid supplied energy is the primary barrier to widespread commercialization of PV systems. Cost reductions available through design, material specification and construction techniques developed by the power industry in response to the need for lower cost traditional generating stations can effect significant cost savings when applied to PV generation systems. As part of its program to meet the Arizona Corporation Commission (ACC) mandated Environmental Portfolio Standard (EPS) annual solar energy generation percentage goals, Tucson Electric Power (TEP) has developed a cookie cutter approach to the design and installation of large utility scale PV systems. This approach has resulted in a 3,780 kW DC at STC rated PV system located on the property of the coal fired Springerville Generating Station in eastern Arizona. In 2001 the ACC passed an EPS setting a goal that all ACC jurisdictional utilities shall derive from renewable energy resources an increasing amount of electricity sold at retail. The EPS requires that 1.1% of retail electricity sold will come from renewable resources in 2007 through 2012 and that 60% of that must be from solar electric generation sources. Various multiplying factors can be applied to reduce the actual amount of electricity produced. These factors provide incentives for in-state location of the renewable generators, early installation, net metering, green pricing programs, in-state manufacturing of renewable generation components and distributed generation. -1-
Although TEP already produces sufficient electricity from landfill gas to meet the non-solar renewable portion of the EPS goals, the EPS requires the installation of just over 10 MW of solar electric generation by 2007. In recognition that the funding for the EPS is not sufficient to meet the goal in the time required, the EPS currently has no penalty provision. Review of the EPS program results in 2003 demonstrated that the EPS has to date been very successful and while no jurisdictional utility has yet met its full renewable energy percentage goals, the EPS has resulted in installation of over 7,000 kW DC at STC of new PV in Arizona in less than three years. For a complete review of the costs and benefits associated with development of renewable resources under the EPS, please see the Cost Evaluation Working Group report at http://www.cc.state.az.us
-2-
Program Planning:
TEP chose two PV based solar generation development programs to meet its EPS goals. Although one large solar thermal generation plant could have met the EPS solar goals, such a project would have done nothing toward developing cost effective customer based solar generation, a long term goal of TEPs energy supply strategy. The SunShare PV hardware buydown program provides financial and maintenance support incentives for customers to install their own PV system. To date the SunShare and other customer partnering programs have over 40 customers with more than 120 kW of installed PV. However, given that meeting the EPS goal requires installation of more than 10,000 kW of PV in seven years, TEP also determined that the solar portfolio must include noncustomer sited solar generation. Therefore, TEP started developing large distributed generation PV systems to meet the portion of the EPS goal not expected to be met by SunShare, initially 90% of the EPS solar goal. As in real estate, siting a solar generator is location, location, location. TEP had been performing solar and wind resource survey work for 5 years prior to the start of the EPS. This survey and data gathering and analysis work had been performed at many TEP owned sites as well as some customer owned sites. The high elevation desert region near the Springerville Generating Station (SGS) in eastern Arizona was found to have better annual average and peak solar insolation levels, cooler annual average temperatures and higher average winds during daylight hours - all factors positively affecting PV solar generation - than any other location surveyed. Cloud cover percentage at SGS was greater than at Tucson, but the net annual effect of all factors resulted in an expected improvement of about 3% net annual AC energy production at SGS over Tucson. In addition, the property tax rates at SGS are less than half of those in Tucson which provides a significant economic benefit for a highly capital intensive project like solar PV. The SGS is operated on 21 square miles land with very little growth of more than native grasses. Consequently, land space was not a concern. A square mile that is very nearly flat with only eight bushes and a bisecting 35 kV transmission line was selected as the location of the solar system. An aerial view of the site taken in late 2002 is shown below for reference. The 35 kV line provides power to the well field pumps that provide raw cooling water for the 760 MW coal fired generating station. The PV system was designed for a completed maximum size of 10 MW AC peak to provide distributed generation support for the pump load, and will be built in phases to reach that size in 2010. TEP was committed to using at least three different types of PV technology at the solar system. The design needed to flexibly accommodate different types of PV modules. The use of different PV technology types in a side by side comparison would provide cost and performance data beneficial to making improvements in future PV technology.
-3-
-4-
-5-
Low efficiency PV module array block size was set at 300 feet north-south by 250 feet east-west for the overall system layout. All intermodule DC connections are to be made by MC connectors. Significant training must be given to the installers to ensure proper seating of the connectors by the installers. The DC wiring design was for 0.5% maximum voltage drop from the furthest point of the array to the inverter. A balance of voltage drop design and conduit fill derating required by the NEC was used to determine main DC conductor size as a #4 AWG. The AC wiring and physical layout of the transformers, disconnects, meter and inverter for all systems is cookie cutter identical with the exception of the number of fuses in the DC interconnection cabinet, called the marshalling box. This allowed for very simple replication for different types of PV modules. The National Electrical Code allows electric power to be distributed at a voltage up to 600 volts without need for special voltage equipment or wiring, thus use of 480 volt AC equipment can maximize the capacity per dollar ratio. Availability and price of DC wiring components is much more favorable when the DC design is kept below a working voltage of 600 volts. Due to the SGS site conditions favoring solar generation, the DC array power rating was designed to be no more than 90% of the AC rating of the inverter. Cloud enhancement can at times drive insolation levels over 1500 watts per square meter for 15 minute intervals, demanding that the inverter have some available power capacity to adjust for the onset of this effect. This design point also allows the inverters to spend most of their operating time in the sweet spot of their efficiency curve.
When large numbers of similar systems are to be installed, extra care can be taken using these and other design concepts in the design phase to reduce the cost of both the DC and AC wiring systems. With certain types of PV modules, a single DC electrical trunk connection can be made for more than 5 kW DC at STC of PV modules. This dramatically reduces the cost of the DC electrical trunk system. Proper design of the electrical system and proper construction staging can reduce the installed cost of the electrical portion of a utility scale PV system using skilled union labor to less than $0.30 per DC watt of PV capacity. Likewise, design optimization of the PV array support structure must be performed and the support structure should fill other functions such as lightning protection and erosion control to minimize the cost of the support. Given that utility scale PV systems will likely be installed where there is more land area than is required, advantage can be taken of the extra land. Design can be simple and maximize the number of watts of PV capacity installed per support. It can also take advantage of the strength of the frame already designed into many PV modules or provide a simplistic assembly method for unframed modules. Support structure design can also be optimized to make maximum use of raw material, coating systems available for the dry Arizona climate, existing construction components and simplicity of design to allow use of low cost assembly crews. Supports can be designed to be matched to a particular PV module to take advantage of the PV module frame rigidity. Development of long term -6-
commitments with PV module makers takes advantage of partnering opportunities on structure development. Support structure installed cost after a year of experience in developing construction staging methods can be as low as $0.15 per DC watt of PV capacity. Developing relations with inverter makers is essential to standardize large utility scale inverters, their support software and infrastructure and thus the cost of inverters and inverter installation support components and tooling. Utility scale PV inverters with 99+% reliability, 96+% conversion efficiency and sophisticated service features can now be purchased for less than half of their small PV inverter counterparts on a cost per watt basis. Installed costs of inverters and support systems are now less than $0.40 per DC watt of PV capacity. Ground preparation and grid connection work for a utility scale PV system can be done in sections, allowing for modular construction planning and associated efficiencies of construction. Preparation for the initial phase of the SGS Solar System included blocks for the interconnection of 24 systems, each of 150 kVA AC size, for a total of 3,600 kVA AC rated capacity. The ground prep and grid connection work was completed at a cost of less than $450,000. Assuming that each block will have a DC capacity of 135 KW, the installed cost is $0.14 per DC watt. This includes all surface preparation, underground conduit, concrete foundations, high voltage wiring, high voltage disconnects, soil stabilizer, transformers and grounding to a power plant specification. Even better, the second phase includes blocks for 20 more 150 kVA AC units and cost less than $210,000, for a cost of $0.08 per DC watt. The need for continuous data collection to a standard similar to conventional power plants was recognized as essential to solar system performance tracking and development of preventative maintenance algorithms. The data collection system was designed to interface directly with the inverters and the revenue meter. Data is collected on 10 second intervals and averaged for one minute intervals for archive. The data server is accessible from the Internet. Even remote sites such as the SGS can now be linked via inexpensive satellite ISPs to the Internet. Data collection systems, metering and connection to the Internet, again optimized for utility scale systems, have an installed cost of less than $1,000 for a 150 kVA system. This is less than $0.01 per DC watt. Optimizing the BOS design and installation, resulted in BOS costs of less than $1.00 per DC watt of installed PV capacity in 2003, only the third year of the EPS. This cost level meets a long term goal of many federal government grant opportunities. This benefit would not have been possible with a year to year type of EPS. Time and motion construction reviews provided insight into placement of material and kitting of parts to reduce lost motion in the field. This study was essential to reducing the costs of construction labor.
-7-
The ground preparation, underground conduit and concrete foundation work was performed by an earthwork contractor local to the SGS area, M&S Construction. The electrical grid interconnection work was performed by either TEP or a high voltage electrical contractor located in Tucson, Southwest Energy Solutions. The PV system array, inverter and electrical installation work was managed by Global Solar of Tucson. All units have been successfully completed on schedule and within budget. TEP is responsible for all design work.
-8-
Operating Results:
Installation of 28 large utility scale distributed generation PV systems is complete in Springerville. These systems use PV array building blocks of about 135 kW DC in size. Different PV module technologies have been used, including crystalline silicon, Cad-Tel and amorphous silicon. Testing of new module technologies is supported by TEP. The results of daily energy production performance are shared with interested manufacturers. These systems are heavily instrumented and results are reviewed daily to ensure proper operation of the systems. Effective availability of these systems in 2002 was 99.43%, a very high on line operational record for any generating system. These PV systems have proven to be reasonably cost effective installations using the opportunity provided by the EPS program to eliminate financing charges. Finance charges are a considerable portion of total costs in high capital, low operational cost projects such as PV. Elimination of finance charges to reduce life cycle ownership costs using the pay as you go up front funding concept inherent in the EPS mechanism adopted by the ACC has made a significant reduction in life cycle cost of energy generated with PV. Evaluation of life cycle costs given limited experience with long term operating costs of large scale PV indicate that large utility scale distributed PV generation systems should produce electricity at a simple cost basis of less than $0.11 per kWh at 2003 PV prices. Operating costs are expected to be $0.004 per kWh of that amount. PV module Degradation: One partnering PV module manufacturer recently retested PV modules which had been in service in Tucson for 28 months to test for dirt and time related output degradation. Modules were tested first without cleaning and then after cleaning. Results indicated soiling effect was less than 1% output degradation from modules which had not been cleaned in two years and overall time related degradation of clean modules much less than that expected. 9,000 of these modules are used in the SGS solar system. SGS modules have historically been cleaner than Tucson located modules due to no oily deposits and the ability of snow to very effectively remove solid deposits like bird droppings. The units at Springerville experienced three failures of the electrical grid during 2002. In all three cases all inverters met their IEEE-929 island detection requirements, even with 18 inverters in parallel on the line and some inductive pump motor load, and disconnected nearly instantaneously. As additional inverters are added and the installed capacity of PV approaches the installed load of the pumps and other loads on the radial line, it will be instructive to monitor the transient response of line faults as verification of correct IEEE-929 compliance. The same has been true of all 2003 transmission line power failures with up to 24 inverters connected and operating. While the TEP fleet of large scale PV systems had a very high percentage of effective availability in 2002, there are challenges remaining in maintenance of PV systems. There were 15 separate incidents in 2002 requiring some level of human response to restore the large system to full operation. These incidents were only identified because of the instrumentation and communications that is economically viable on large scale systems.
-9-
The following technical Qualitative PV Module Evaluation is based on 10 months of one minute interval data taken from operation of the Springerville solar units. Units U-1 through U-12 are each composed of 450 ASE 300DG-50 modules, connected with 9 in series. Units U-33 and U-34 are each composed of 2,688 First Solar FS-50 modules, connected 6 in series. Units U-37 through U-40 are each composed of 3,000 BP Solarex MST-43 modules, connected 5 in series. All modules are facing due south at an angle of 34 degrees from horizontal, which is latitude angle. The ASE and BP Solarex modules, with the exception of those in C-12 are commercial products, not test or preproduction modules. However, the First Solar modules are a preproduction module, purchased for testing purposes and were not expected to perform like production modules. Any interpretations of First Solar module data or comparisons with other systems at Springerville or elsewhere must reflect that the First Solar modules are a preproduction version. All units use a Xantrex PV-150 150 KVA inverter proven in operation to be capable of intermittent operation at output levels as high as 157 KVA AC. The 208 volt three phase output of the inverter is stepped up to 480 volt 3 phase at which point it is metered for reporting purposes and then transformed to transmission voltage of 34.5 kV. The site is at 6,600 foot elevation, in eastern Arizona. ASE modules were installed in 2001, 2002 and 2003, all BP modules, except replacement modules, were installed in 2001, and First Solar modules were installed in 2001, 2002 and 2003.
Unit 10 on 10/3/2002
150000 140000 130000 120000 110000 100000 Power in Watts 90000 80000 70000 60000 50000 40000 30000 20000 10000 0 3:00 1500 1400 1300 1200 1100 W/M2 & Volts & Amps 1000 900 800 700 600 500 400 300 200 100 0 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 Time of Day Power Solar Voltage Current
4:00
5:00
6:00
7:00
8:00
- 10 -
2003 the max power point was about 280 to 290 volts, so power loss was minimal, given the flat IV curve of a-si. As winter 2002 approached and temperatures dropped, the units exhibited a rise in DC voltage and a rise in power output, just like the ASE and First Solar units, and U-38, U-39 and U-40 started to exhibit DC bus voltages slightly above 300 volts in the early morning and the afternoon. However, toward the end of October 2002, the max power point DC bus voltage never climbed above 300 volts on any BP units, and worse, a downward trend in power output started, sometimes as much as 20% below the daily energy output of the ASE units. This effect did reverse in mid July 2003, but it took record high temperatures to promote the self annealing which reverses the loss of energy production performance. Less than 1% of modules had cracked or failed after one year of service and all failed modules were replaced under warranty by September 2002. During the second year of operation the failure rate fell to 30 modules out of 12,000 or 0.25%, a very good record. U-38 exhibits much higher instantaneous output during cloud enhancements than the other BP units. It is as yet not clear if the effect is due to the array or the inverter. U-38, U-39 & U-40 exhibit open circuit voltages within 1 volt of each other during start up and shutdown. They seem to be very similar in voltage characteristics. TEP has generally been satisfied with the performance of the BP systems, with the exception of U-37 and the concern over lost production in cold weather. The inverters are seldom able to follow maximum power point since the units generally have a max power point below the 300 volt floor of the inverter. Significant tuning of inverter constants to prevent inverter trip during cloud enhancement was needed. Monthly operating summaries are posted at GreenWatts.com During 2002, over 3,100 MWh of solar energy was produced at the SGS Solar System. It is expected that over 4,800 MWh of solar energy will be produced by solar energy at SGS in 2003, despite some downtime from a lightning storm that delivered nearly two years of ground strokes to the area of the SGS Solar System in the first 11 minutes of the storm. The high rate of annual energy production from PV at this location is due to the high level of solar insolation, cool temperatures and wind that generally blows during daylight hours. The lightning storm while apparently striking the PV system in at least four locations, did no external physical damage to the arrays, inverters or transformers. The damage found was associated with the data collection system between the 480 volt revenue meter, the inverter control and communications computer and the network switches. All three items are grounded at one location, but the location of the ground is not the same in all cases and the lightning current followed the path between the ground references to cause some damage on almost half of the systems. One previously weakened inverter matrix was also damaged, a contactor coil winding and a single data Cat 5 cable. All damage was repaired within 30 days at a cost of less than 0.1% of the initial cost of the PV system. Addition of surge protection and isolation devices was made to the data collection systems at a cost of less than $200 per inverter that is expected to fully prevent damage from occurring in the future from lightning. Additional operating and performance data is available at www.GreenWatts.com
- 12 -
- 13 -
0 $0 0 0 $0 $0 570 1,868 0 0%
495 $2,846 441 842,588 $26,348,908 $31.27 269 1,741 127 9.78%
- 14 -
Below is a graph of the TEP 2002 hourly native retail load, the hourly energy produced by 495 MW of hypothetical solar generation located at the Springerville Generating Station and the effect on fueled generation demand reduction 46 MW from the application of 495 MW of solar capacity. The 495 MW of solar capacity was chosen as the level needed to produce 10% of the TEP annual retail energy sold from new renewable generation sources in 2002, the proposed national renewable portfolio standard. The distance the red points are spaced above the yellow points represents the amount of load the renewable resource supports. Capacity support is only provided in hours ending 08:00 through 17:00. At the typical time of peak system loads at hour ending 16:00, the solar generation resource is providing only 46 MW of capacity support.
2000 1800 1600 1400 Power in MW 1200 1000 800 600 400 200 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour of Day Solar Pow er Fueled Gen - Solar Retail Load
- 15 -
Below is a graph of the TEP 2002 hourly daily maximum and minimum native load generation demand as if provided: 1. Maximum daily demand met by fueled generation only, in red; 2. Maximum daily demand met by fueled generation as reduced by 495 MW of Springerville Generating Station located solar generation, in pink; and 3. Minimum daily demand met by fueled generation as reduced by 495 MW of SGS located solar generation, in blue. Increasing amounts of red showing behind the pink indicate increasing amounts of fueled generation that could be displaced by solar generation. Increasing amounts of pink showing behind blue would represent reductions in minimum fueled generation requirements possibly requiring taking fueled units out of service when renewable generation was available. This does not appear to be a concern with solar generation.
2,000 1,800 1,600 1,400 1,200 MW 1,000 800 600 400 200 0 1 361 7211081 1801 2521 3241 3961 4681 5401 6121 6841 7561 8281 1441 2161 2881 3601 4321 5041 5761 6481 7201 7921 8641 Date Fuel Only Max Fuel - Solar Max Fuel - Solar Min
- 16 -
Below is a graph of the TEP 2002 hourly native retail load, the hourly energy produced by 495 MW of hypothetical solar generation located at TEPs Tucson located Operating Headquarters and the effect on fueled generation demand reduction 127 MW from the application of 495 MW of Tucson located solar capacity. The 495 MW of solar capacity was chosen as the level needed to produce nearly 10% of the TEP annual retail energy sold from new renewable generation sources in 2002, the proposed national renewable portfolio standard. The distance the red points are spaced above the yellow points represents the amount of load the renewable resource supports. Capacity support is only provided in hours ending 08:00 through 17:00. At the typical time of peak system loads at hour ending 16:00, the solar generation resource is providing 127 MW of capacity support.
2,000 1,800 1,600 1,400 Power in MW 1,200 1,000 800 600 400 200 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour of Day Solar Pow er Fueled Generation - Solar Retail Load
- 17 -
Below is a graph of the TEP 2002 hourly daily maximum and minimum native load generation demand as if provided: 1. Maximum daily demand met by fueled generation only, in red; 2. Maximum daily demand met by fueled generation as reduced by 495 MW of Tucson located solar generation, in pink; and 3. Minimum daily demand met by fueled generation as reduced by 495 MW of Tucson located solar generation, in blue. Increasing amounts of red showing behind the pink indicate increasing amounts of fueled generation that could be displaced by solar generation. Increasing amounts of pink showing behind blue would represent reductions in minimum fueled generation requirements possibly requiring taking fueled units out of service when renewable generation was available. This does not appear to be a concern with solar generation.
2,000 1,800 1,600 1,400 1,200 MW 1,000 800 600 400 200 0 1 505 1009 1513 2017 2521 3025 3529 4033 4537 5041 5545 6049 6553 7057 7561 8065 8569 Date Fuel Only Max Fuel - Solar Max Fuel - Solar Min
- 18 -
Below is a graph of the TEP 2002 hourly native retail load, the hourly energy produced by 509 MW of hypothetical wind generation located at the area of one of the TEP monitor stations in Apache County and the effect on fueled generation demand reduction 9 MW from the application of 509 MW of wind capacity. The 509 MW of wind capacity was chosen as the level needed to produce 10% of the TEP annual retail energy sold from new renewable generation sources in 2002, the proposed national renewable portfolio standard. The distance the red points are spaced above the yellow points represents the amount of load the renewable resource supports. Capacity support from wind in Arizona is not coincident with loads at any great degree of confidence, although a significant amount of the energy provided does occur during peak load hours.
2000 1800 1600 1400 Power in MW 1200 1000 800 600 400 200 0 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour of Day Wind Pow er Fueled Gen -Wind Retail Load
- 19 -
Below is a graph of the TEP 2002 hourly daily maximum and minimum native load generation demand as if provided: 1. Maximum daily demand met by fueled generation only, in red; 2. Maximum daily demand met by fueled generation as reduced by 509 MW of Apache County located wind generation, in pink; and 3. Minimum daily demand met by fueled generation as reduced by 509 MW of Apache County located wind generation, in blue. Minimum daily loads are much more difficult to predict with a significant amount of wind generation as part of the generation resource base. Increasing amounts of red showing behind the pink indicate increasing amounts of fueled generation that could be displaced by wind generation. Increasing amounts of pink showing behind blue would represent reductions in minimum fueled generation requirements possibly requiring taking fueled units out of service when renewable generation was available. This does appear to be a concern with wind generation.
2000 1800 1600 1400 1200 MW 1000 800 600 400 200 0 1 1 1 2 2 3 3 3 4 4 4 5 5 6 6 6 7 7 8 8 8 9 9 10 10 10 11 11 12 12 12 Date Fuel Only Max Fuel - Wind Max Fuel - Wind Min
- 20 -
available dual trace oscilloscope with a range to 100 kHz is needed. A harmonic meter and a three phase power meter are helpful. In addition it will be beneficial to build a module continuity tester that will test power output across a wide range of loads and solar insolation to build a module IV curve. A thermometer and a calibrated solar insolation meter are recommended tools for evaluating performance. A PC with Excel capability to monitor trends of data is highly recommended.
Watts Next??:
Implementation of large utility scale, distributed PV solar generation systems is developing a positive trend around the world. With the 2003 German installation of 4.0 MW of PV near Hemau and the announced start in July 2003 of a 5.0 MW PV system in Germany, the installation of 2.0 MW of tracking and concentrating PV by Arizona Public Service near Prescott, Arizona in 2003 and the continuing expansion of the Springerville Generating Station Solar System, there is developing a wealth of data on the design criteria, installation practices, operational experience and production results of large PV installations and their accompanying costs. Total installed cost is less than $6.00 per DC watt. By 2007 that is expected to be less than $5.00 per DC watt. The experience gained from these large solar PV systems will provide data needed for improving prediction of supply from intermittent generation resources and support development of the tools needed to mitigate the effects of that intermittency on grid regulation, as well as hour ahead and day ahead energy requirement forecasting. While customer located PV systems are still needed to fully take advantage of the potential of solar energy, large utility scale PV systems are starting to take their rightful place under the sun. For utilities, the time is now right to harness the power of the sun for the long term benefit of our customers. The promise of utility scale solar photovoltaic distributed generation is within our reach today.
- 22 -