Beruflich Dokumente
Kultur Dokumente
Chris Clayton
Issues
Issues
SPT 1902-1947
Most of the techniques we routinely use are between 60 and 100 years old
Bishop with U4 1944-45
1906
2006
Background
engineers imagined that the science of foundations would consist in carrying out the following program: 1. Drill a hole into the ground. 2. Send the soil samples obtained from the hole through a laboratory with standardized apparatus served by conscientious human automatons. 3. Collect the figures, introduce them into the equations, and compute the result Unfortunately, soils are made by nature and not by man, and the products of nature are always complex.
Terzaghi, 1936
6
Background
Background
interpretation of SI project planning site investigation planning additional work amended work quality control variation in quantities bills of quantities specification 60 100 % net additional cost 200
8
Issues
Aims
Subsurface projects present an enormous risk for the primary project stakeholders, i.e. the owner and contractor. Realistically, not all risk for subsurface conditions can be entirely avoided or eliminated. Hatem, 1998
Hazards and risks Geologic hazards Geomaterial hazards Geotechnical hazards Land use hazards and Residual uncertainties following GI
quality
programme
10
Ground geometry
Aims
(A geological model from Fookes, 1997) FOR PERSONAL USE ONLY (c) Chris Clayton
11
Aims
Risks
Vulnerability
12
4% 22%
6%
Aims
9%
13
(see the ICE/DETR Report on Managing Geotechnical Risk) FOR PERSONAL USE ONLY (c) Chris Clayton
14
Issues
15
Constraints
Ground conditions Equipment Supervision Knowledge and experience (in local conditions) Education Computation techniques Conditions of contract (?) Money (?)
16
SPT hammers
Constraints
U100 disturbance
Most data used in design are not fundamental - variations in the ways drilling, sampling and testing are done make the results very variable
17
Constraints
Constraints
A B C D E F G H I J K L M N O P 0 1000 2000
3000
4000
5000
6000
19 Wheeler, 1999
Constraints
There are known knowns. These are things that we know that we know. There are known unknowns. That is to say, there are things that we know we dont know. But there are also unknown unknowns. There are things we dont know we dont know. Donald Rumsfeld 20
FOR PERSONAL USE ONLY (c) Chris Clayton
Constraints
Constraints
Few consultants (or SI engineers / geologists) understand the details of drilling and testing techniques. Specification of more complex work can be poor. Consultant supervision is pointless unless informed and rigorous. GI contractors cannot afford to supervise fieldwork unless paid. Drillers and technicians are a most important resource. They need to be trained, and feel part of the team.
22
Issues
23
Urbanization
At the beginning of the 20th century 7% of the worlds population could be considered urban. Most urban dwellers lived in developed countries. By 1950 30% of the population lived in urban areas, and by 2000 47% was urban
Urbanization
24
Urbanization
At the beginning of the 20th century 7% of the worlds population could be considered urban. Most urban dwellers lived in developed countries. By 1950 30% of the population lived in urban areas, and by 2000 47% was urban By 2030 it is expected that >60% of the worlds population will live in an urban world. Most of the new urban areas will be in 25 developing countries.
FOR PERSONAL USE ONLY (c) Chris Clayton
Urbanization
Urbanization
URBAN
RURAL
Population (billions)
0
19 50 19 75 20 00 20 30 19 50 19 75 20 00 20 30
From Zlotnik (2003) 26 FOR PERSONAL USE ONLY (c) Chris Clayton
Urbanization
Anyone who believes that India is an economic powerhouse should try living there. The shortcomings of infrastructure are a huge problem. In Delhi some areas are blighted by daily four-hour power cuts. A report last week highlighted a 73km rail project in East Bengal that is still unfinished after 32 years.
Urban vulnerability
Urbanization
Instability of natural slopes Mining impacts Damage to infrastructure Effects of construction on nearby structures
28
Hong Kong, Po Shan Road Slide, 1972 Rainfall of 700mm in 3 days prior to slide Main slide involved 25,000m3 debris, moving 280m in 1 minute 1 block of flats pushed off foundations onto another 67 people died
29
Kinzie Street Bridge, Chicago 13 April 1992 Downtown basements flooded as a result of piling work. President signs disaster declaration.
31
20 October 1994
32
33
Urbanization
34
200m
Yule (1988)
FOR PERSONAL USE ONLY (c) Chris Clayton
35
http://www.londonbridgehotel.com/p_geology.html 36
FOR PERSONAL USE ONLY (c) Chris Clayton
Archaeological heritage
Rediscovery of the Rose Theatre in 1989
37
39
40
41
Battersea foundations
Desk study
42 Exhumation, examination and testing
Total destruction Damage beyond repair Seriously damaged, doubtful if repairable Seriously damaged but repairable at cost General blast damage, not structural Blast damage, minor in area Clearance areas
Issues
44
Essential components
Components
Competence / registration
Engineers Geologists SILC Technicians Drillers
Early involvement of geotechnical experts (hazard + risk assessment, conceptual design) Desk study and walkover survey Geological, geotechnical and land use ground models. Targetted planning of ground investigation
(AGS, 2006)
45
46
Essential components
Targetted direct investigation
Accurate identification of soil boundary locations Groundwater positions / conditions Contaminated land investigation Repeatable test results
Components
Supervision Informed interpretation Appropriate analysis Hand-over of residual risks (risk registers) Contribution to CDM
47
Summary
Definitions of content (essential components), to define negligence. Definitions of education, training, experience for all levels of staff, to define necessary levels of competence. Quality driven by site investigation industry, perhaps by peer review.
Distinct geotechnical design strategies for Routine construction Major projects or difficult ground
48
Recognise and understand current GI inadequacies. Make great use of desk study information Develop ground and land-use models (esp. cities) Proper planning and informed interpretation of site investigations Use local and company experience, and material performance database (case records) Hazard identification and risk analysis Conceptual design to avoid or mitigate risks Limited, basic, quick, repeatable ground investigation? Conservative and simple analyses Observation (and possibly monitoring) during construction
49
Windowless sampler
100mm ID 70mm ID 47mm ID 48% AR 81% AR 116% AR
(courtesy Lankelma) 51
From www.maps.live.com
52
(www.bgs.ac.uk/geoindex)
53
Borehole data Land use Archaeology Contamination Obstructions Superficial geology Solid geology Hydrogeology
54
Project owners must recognise that there are certain types of projects that simply cry out for a more sophisticated approach to doing the subsurface portion of the work. (from Brierley, 1998)
Use only when advanced geotechnical computation can yield major savings / gains. Need for sophisticated sampling and testing Advanced numerical modelling International and flexible approach to procurement. Partnering with ground investigation specialists. University collaboration?
55
Download a free copy of Site Investigation by Clayton, Matthews and Simons from www.geotechnique.info FOR PERSONAL USE ONLY (c) Chris Clayton