Beruflich Dokumente
Kultur Dokumente
LITTLE II TEST JOE LAUNCH VEHICLE NASA PROJECT APOLLO FINAL REPORT
NASACONTRACT NAS-9-492
By DYNAMICS
OF GENERAL For
National
Aeronautics Manned
Administration Center
Houston,
FOREWORD
Little
Joe II Program, by National Center was, vehicle report and the Division program
a part
Aeronautics as Contract in essence, on 20 January is to describe principles report of the The Dynamics
Space
Administration,
Manned 1962.
Spacecraft
NAS 9-492, Corporation 1966. the vehicles employed is issued of the completed
of General
evolved, volumes
Volume operations
nontechnical technical
Volume
Manager MSC
at,
he
INTRODUCTION
The sign, Module. gram. Flight Subsequent hardware, program. The this porting end sections erences t o flight
Joe for
fabricate,
launch
technical
performance sections
of the outline
launch services
is
presented
the development
description to accomplish
o p e r a t i o n s and
lists
material added
in supto the
volume. of its
specific text.
In those ref-
material
is not extensive,
ooo 111
VOLUME
II
CONTENTS
Page I. FLIGHT A. B. C. E. F. PERFORMANCE ........ 12-50-1 12-50-2 12-51-1 12-51-2 12-51-3 (QTV) (Mission (Mission (Mission (Mission A-001) A-002) A-003) A-004) CRITERIA 2-1 2-1 Design Criteria 2-8 2-11 2-19 Control 2-26 2-34 2-37 and i-i 1-2 1-13 1-18 1-26 1-33
D. Vehicle
ANALYSIS
AND DESIGN
B. Aerodynamics
3. VEHICLE
Ao
General Structure
B. C. E. F. G. I.
Pr opu Is ion D. Attitude Control Electrical System Radar Beacon Systems Instrumentation Instrumentation SUPPORT 36 Test ..... Facility (CSTF). (GSE)
4. LAUNCH
Equipment
CONTENTS
(CONTINUED)
Page
5. LAUNCH
Ao
OPERAT_NS 5-1 5-3 Acceptance Test. Checkout Operations. Station Assist Testing 5-3 5-4 5-15 5-18 5-19 5-21 5-26 5-26 5-33 5-33
Organization.
J. Recovery . K. Refurbishment L. Material 6. RELIABILITY A. General Plan. Analysis and Control Burn-In Program Limited Summary. Stress Testing Summary Support
vi
VOLUME
II
ILLUSTRATIONS
Figure
1-1 1-2 1-3 1-4 1-5 1-6 1-7 1-8 1-9 1-10 Little Joe II/Apollo Abort Flight Test
Title Program Regions. Summary Mission Objectives . 1-3 1-5 1-6 1-7 1-8 12-50 Without Vs. Destruct Dynamic QTV Pressure Mission - With 1-14 Thrust Mission Mission (A-001) 12-51-1 Mission (A-002) Termination/Spacecraft A-001 A-001 Mach for Number Vs. Dynamic A-002 Pressure ...... BP-23. Pressure. 12-51-1/Apollo 1-23 and Yaw ..... - Time History of Angular Velocities, 1-25 Attitude Vs. Time for Mission 1-24 Abort 1-15 1-17 1-18 1-19 1-21 1-22 1-9 1-10 1-11 1-12
LJ-H/Apollo Launch Launch Little Launch QTV Vehicle Pitch, Apollo Vehicle Vehicle Data Joe
Summary Model
(QTV)
12-50-1
Mission 12-50-2
Vehicle
Configuration
1-11
Pre-Launch Sequence
Apollo
Mission
Force
Coefficient
Mach
Number
1-18
Launch A-002
Vehicle .
Pitch,
Roll, .
1-19
Vehicle Elevon
12-51-1/Apollo Deflection,
Pressure
vii
ILLUSTRATIONS
(CONTINUED)
F re
1-20 1-21 Launch Sequence Vehicle 12-51-2Events for and
Title Mission Mission A-003. A-003 Profile - Vehicle 1-28 Mach Apollo Vs. Range for Number Mission Time Vs. A-003. During Mission Mission A-003 A-003. Dynamic Pressure 1-30 1-31 1-31 1-32 1-34 1-36 A-004 Boundary Abort Mach 1-38 Number Yaw Attitude Vs. Time, Apollo 1-40 Configurations Tunnel Tunnel Model Model - LJ-II/Apollo Installation - 7 Foot X 10 Foot, 300 MPH Wind 2-5 BP Test BP Test SC Test Schedule Schedule Schedule - 8 Foot LRC - LRC Transonic Plan Plan Pressure Wind Wind Tunnel. Tunnel Tunnel 2-5 2-6 Boilerplate Vehicle .2-2 .2-3 2-4 1-39 1-37 1-27
of Major
12-51-2/Apollo 1-22 1-23 1-24 1-25 1-26 1-27 1-28 1-29 Vehicle Altitude Vehicle Altitude Test Apollo Sequence Vehicle Number 1-30 1-31 Axial Launch Mission 2-1 2-2 2-3 2-4 Little 12-51-2 Vs.
Time
12-51-2 Plotted
Attitudes Against
Vehicle Mission
Mission B
A-004
Plotboard Apollo
Events, (A-004)
Mission Tumbling .
Force
0. 030 Scale LJ-II/Apollo LJ-II/Apollo Tunnel LJ-II/Apollo LJ-II/Apollo LJ-II/Apollo (Low Leg)
BP Test
Schedules
Unitary Unitary
- LJ-II/LEM - 8 Foot
Analysis
of 1/10
Scale
Model
Thrust
Bulkhead
.2-10
viii
ILLUSTRATIONS
(CONTINUED)
Figure 2-12 Structural Structural 2-13 2-14 2-15 2-16 2-17 2-18 Vibration Acoustic Fixed Fixed LJ-II Fin Fin Load Test Test Test Test of Vehicle
Page
Laboratory. Levels Levels Envelope Vibration Fin Test Ground Fin Models) Mission ...... E ..... - 12-51 F Version E Setup Vibration Test Flutter Setup Boundaries (Using
Flutter Ground
Attitude
Cantilevered Ground
Calculated
Vibration
2-17 2-19 2-20 2-21 2-22 2-23 2-25 LJ-H/Apollo 2-27 2-28 2-29 ...... Response Setup for Aerodynamic Control Subsystem 2-32 2-29 2-31
2-19 2-20 2-21 2-22 2-23 2-24 2-25 2-26 2-27 2-28 2-29 2-30
Flux
Thermal (12-50)
Heating Temperature
Motion,
Simulation
Subsystem Filter
2-31
Assembly
(One Control
Fin
Set)
Reaction in Test
Subsystem for
of Attitude Design
of Little
- Gust
Spectrum
Configuration Structural
3-4
ix
ILLUSTRATIONS
(CONTINUED)
Figure 3-3 Launch 12-51) 3-4 3-5 3-6 3-7 3-8 3-9 3-10 3-11 3-12 3-13 3-14 3-15 3-16 3-17 3-18 3-19 3-20 3-21 3-22 3-23 3-24 3-25 3-26 3-27 3-28 Structural Design Details Vehicle Structural
Title
Arrangement,
Controllable
Fin
(Version 3-5 3-7 3-8 3-9 3-9 3-10 3-12 3-13 3-14
Interface
Structure.
Algol Motor Algol Thrust Recruit Recruit Block Block Launch Recruit
Details
3-15 3-16
- Single Stage
3-17 3-18 3-19 3-21 3-22 3-23 3-24 3-25 3-26 3-28 3-29 3-30 3-34 3-34 3-36
Ignition System
Sequence
- Internal Assembly
Initiation .
Autopilot
Command Control
Control
Console
Parameters
Control
Reaction
ILLUSTRATIONS Figure 3-29 3-30 3-31 3-32 3-33 3-34 3-35 3-36 3-37 3-38 3-39 3-40 3-41 3-42 3-43 3-44 3-45 3-46 3-47 3-48 3-49 3-50 4-1 4-2 4-3
Actuator Actuator Attitude Autopilot Rate Attitude X-Ray Power Expendable Skirt . Expendable and Launcher Vehicle Block Block Thrust Charges Radio Block Block Gyro Gyro of Failed Distribution Harness and Vehicle Package Resistor Assembly Shaft Control Vibration Scoring Fin Test Test Setup Setup Title
(CONTINUED)
3-39 3-40 3-41 3-42 3-44 3-45 3-47 3-50 Grounding Connections at Vehicle 3-51
Harnesses
and
Vehicle
Grounding
Connections
Vehicle 3-52
Summary - Radar - RF
. Beacon System System Test Module After Detonation of Explosive (All Parts GFE) .
Command System
3-58 AN/DRW-11 - Range Safety System . 3-60 3-62 3-65 3-67 3-68 - Landline Instrumentation 3-70 3-71 3-72 4-2 Looking East 4-2 4-3
- Airborne
Instrumentation
Airborne
Measurements
Recorded
Measurements Measurements .
Monitoring Under
Pad Trench
Construction
Complex
xi
ILLUSTRATIONS
(CONTINUED)
Figure 4-4 4-5 4-6 4-7 4-8 Vehicle Launcher Launcher Launcher Assembly 12-60-1 Loaded Building Assembled on Trailers
Title 4-4 Pad at WSMR 4-6 .4-7 4-9 Azimuth Indicator by Use of Rail Targets and 4-11 Support Arms and Umbilical . 4-11 4-12 4-13 Retract Systems - Schematic 4-14 4-15 Launcher Missions Mast A-003 and A-004 Umbilical Retracting Mechanism 4-17 System Test Facility at CSTF . Measurements 4-17 4-18 4-18 4-19 4-20 4-22 Configuration Configuration. 4-23 4-24 4-24 in Pneumatic Trailer 4-25 4-26 Cart Test Manifold, and Fin Filter Units 4-27 4-28 4-16
to WSMR
Positioning
Calibrating Launcher Remote Controller Console Payload Support Support Parameters Test Setup, Controls Umbilical Arms Arms for
Mechanisms .
4-16 4-17 4-18 4-19 4-20 4-21 4-22 4-23 4-24 4-25 4-26 4-27 4-28
xii
ILLUSTRATIONS
F igu re 4-29 4-30 4-31 4-32 5-1 5-2 5-3 5-4 5-5 5-6 5-7 5-8 5-9 5-10 5-11 5-12 5-13 5-14 5-15 5-16 5-17 Environmental Sling Four Configuration Fins on Work Vehicle Operations Arriving Vehicle Vehicle Fin from Tent for for Title RCS Assembly Handling Vehicle
(CONTINUED)
Body
Motor
T/C .
Leadout
Installed
5-7 5-8
Motor
Afterbody
5-9 5-10
Forebody. .... Bench Aerosmith Rotary-Tilt Rate Table Scoresby Table ...... . Table
5-13 5-14 5-16 5-16 5-17 5-17 5-22 Equipment Used for LJ-II 12-51 5-24
Installation Checkout
Checkout Checkout
on Ideal on P-W
Gyro
System
xiii
ILLUSTRATIONS
(CONTINUED}
Figure 5-23 5-24 5-25 5-26 5-27 5-28 5-29 5-30 Recording Data Vehicle Vehicle Vehicle Postlaunch Launcher Launcher Environment 5-31 5-32 6-1 6-2 6-3 Property Parts Storage Storage at WSMR Rack Rack After After Fins Impact. Impact. After
Title
Impact
5-32 5-34
of Launcher Exposure Boot and to Lift-Off Wiring After Environment Exposure to Lift-Off
5-35
xiv
I FLIGHT
PERFORMANCE
FLIGHT
PERFORMANCE
A.
SUMMARY Of the five launches the of Little tests. (LEV) satisfied acceptable the need. The A-001 Joe II in the Apollo program, and served The this were the 1-2 the first to boost objectives 1-1. was was the designed for the Apollo of the case, more last
to demonstrate Apollo four these either than launch-escape missions, objectives the one The maneuver sometimes Mach which point test severe fourth of the results test
flightworthiness
its suitability
launch-escape vehicle
to a variety
in Figure
In general, from
and explicitly.
not the
as obtained
of results repeated.
of the
regions
These
to as test
number and dynamic pressure. each abort was achieved. For - or its occurred than launch LEV The test locus, planned, failed turned this in the hence to reach launch for case of the the somewhat outside
Displayed for comparison the first two launches and first launch however, of the mission. is summarized test mission WSMR figures detailed launch in Figure descriptions and results. Planned part vehicle however, - was the the within test structural window; the region;
is the test point the fifth, the test the window. were Only automatic design. The conditions
more
proving the test into each both at the were above section
adequacy
successful
vehicle total of each included. from level. most if more the results.
1-3. Joe
In II, the
mission
payload,
discussion. Launch
All five
II launch
at an altitude
The
in this
extracted vehicle,
a digest
of the
missions are
summarizes
Paragraphs objectives,
B through configurations,
F of this events,
missions:
performance
1-1
B.
VEHICLE 12-50-1
MISSION The first and was SUMMARY launch
(QTV)
vehicle, escape
was
equipped the
with
pay-
load weight
and
an inert
launch
to simulate
(QTV) Apollo
on 28 August
approximately of the
Spacecraft
bility of the launch A-001; see Figure Flight Convair TEST The achieve Algol eration during seconds. pellant lift-off than passed test and planned, through region; and Report, Report
vehicle to adequately perform the launch 1-1. A complete report on this mission Project Apollo, Little Joe 1963. II Qualification 28 October
NASA
GD/C-63-193A,
AND RESULTS at an elevation in the the first angle of 82 48', of the which was required The axial one accelthrust poundsproat vehicle A-001 region. to
launched test
desired Recruit
trajectory motors 105,000 was was the flight. test vehicle in the also 5g for was
presence 1-1/2
six
rocket time
as planned, seconds with 6.6% predicted. path presented a number illustration of meeting of the a total less
impulse
approximately
vehicle a slightly
trajectory flight
mission window.
planned
Among
of objectives,
demonstrated:
capability characteristics
Mission
2) flutter-free
transonic
the for
The only test objective not achieved WSMR command destruct subsystem this mission, as later was to an apogee in Figure Trajectory 1-7. - The are Mach trajectory for in Figure (M) vs. selected Vehicle 1-5 other adapted than for to test the its thrust feet
was the Algol in the vehicle. capability termination for (msl) launch
termination via was not required safety test motor mission requirements vehicle burnout. profile is con-
of approximately 28,400
27,600 from
feet the
approximately
test
vehicle
the 1-8
q
same mission
planned given
12-50-2 dynamic
on Apollo pressure
illustrates
number
test
region.
It is significant that time. This indicated as by using sure can to a more a real-time rapid be attributed
the flight conditions that a successful display partly of the of M vs. to the base vehicle;
were in the M-q test window abort could be made by timer q. drag see The higher-than-expected lower 1-9, than curve predicted a. being Figure
pitch-over
1-2
I
w _0_ w
o==
<
>
_o
_g
0
_<_
(.
_._
0 0
_ =<
_z
o_
.2
-_ o _ << _o r/l
=o_g_ _Z
0 _00
4
bdO 0
m L > L_J x_ :I:P}'-FLL <;[U]
Z_-C_m__ Or")--
,,=, _,,=,
=,
(..)
_< _<_
o_ z_ _z _ L_I (.._
_,8'-
I.->
(%1
,%0 o_.; _
0
L_J
F--z
,_
_z _ F--F--
<
<PP-.'gO
_oz I_LLI
_J :lz _z_ I-- Z
_u_m 3
_o_
-_
-_
i . W_
,4
i uJ
>
_Z_z _ z _ 0 _
uJ (n
o Lq p_g o_.
tOO
_
_0
I ,el
o_O
Cxl ::1_
_,m _o_ _
_ !_
C__. _z _ w _,
_0 _0_ zz_ __Uz_ _ Z r_ UA _I.L 0 C_ I-_ --I <f _ 'J) _X_ _ (/) Ld I.LI 7"I_ ..J _'(,,9 > 0 Ld<[ lad ._1F-I'-F" m
o_
_o _z_
-=_
-_o
p.- (.3
_N_
o
,,=, ,,=,
-n _-
--to-
_oo_
o uJ
Z_
_o
ul_> _z z_
__o < _ _=
o_
bJ_
E_(.)
NZ _c
>-
__. _>
> raw <.J p-
_z p-
>-
o>_,
I--- i-.0_ w ouJ ILl C:
_J
z_z_
_<
'
'
0 LL
,.o
CO o -,< o>.
,,,,
--c.) "0
g _ g.W o
h-
>
o
IF-o
._<
->0--
_ ____
I--I-UJO g,
L_ _
...
o
g
_
OOB
=_
_J.J F.- L4j u9 :-.>--
>" Ih, P-
5N
,,Q.
_z
>
1"4 Z
_<
i,.I-v 0 l.l.J I.I--
,,
C:I O
++P--
N.t
2
0
+
+;/ '_, "-' _\l
O O CO
.-,4
O bl0
p_
g
N I'--
O ,D O o
N :_+,.::",_.+_,/
._/2+++_ i _.4,_>'..,
_l g_
I_
--I I 0"
2Z
\
"/i
"_
Q
Z >-
X'
q_ f,.-I
.+
'
g
N
O O
a38mnNH:)Vlfll
1-5
APOLLO MISSION
PAYLOAD
23,185
9,361
- NUMBER
12-50-1
12-50-2
12-51-1
12-51-2
12-51-3
CONFIGURATION -WEIGHT INC. MOTORS (LBS) - BALLAST (LBS) - FIXED FIN - CONTROLLABLE FIN 6 1 32,941 X 32,595 X X 58,030 8,609 144,309 5,044 101,328 5,867
PROPULSION
- 1ST STAGE RECRUIT - 1ST STAGE ALGOL -2ND STAGE ALGOL PROGRAMMER CAPABILITY FILTER-2ND ORDER FILTER-NOTCH CONTROL CONTROL
ATTITUDE
CONTROL
-PITCH-UP
-REACTION
-AERODYNAMIC
- ELEVON ACTUATOR HYD. SUPPLY RF COMMAND -RANGE -THRUST -PITCH-UP -ABORT ELECTRICAL SAFETY DESTRUCT
- PRIMARY - INSTRUMENTATION
INSTRUMENTATION
-RF
TRANSMITTERS
3 66 24 X
2 58 37
1 39 36
C-6062-10
Figure
1-3.
Launch
Vehicle
Configuration
Summary
1-6
O0
m_ _ o ,,,
(.J
_o=_
_ _Jo
,0
(.3 W
i--h-
E_N
W
z_
J
0 en
P-t 0
U_
O_
O+ O0
O0 Z Z
T
IE
_<___g==g
_o_
r/l 0
_I
_" ..0
,3
_w
0 b. -_ (.3
i
;.0
oO_
, o=_,.,,=
0 0
14. 0
Zh-
_z
Z bd
o_
_ o
t_ ILl -J
W -J
I-"I"
bJ nrU b_
_z
0 _ l--_0
o.
b_
o_
<,,,i-e_
o
T
F-
Wl--
___
,-,m_
F-z o e'_
z 0
_d d_
W
: hE=
oo
OU.
0 z
1-7
0 .o** O0 .. _ _ __o _ _
O0
....
_._
i
?z
.
O0
I _A
(J O_
. N
_J
O0
o o_ S(J
__
__o_
{d
0 O0 D..
O0 _00_
z
Z 0 (.9 uJ ,y p0 4-) 0 O_
-J o_0_ _0 I.iJ Z 0 Z 0
O0 0 _0_ ....
E_
S-_,z
0_0_ .,. O.
_J
-J
_o
LO Z 0 Z
_'
oZ
Z _ Z 0 Z
,_
LO..O
I UJ'r X
Of
,or--
&
Ln Z .J O. Z 0 Z _ Z 0 Z _0 0 _0 ....0_ _0_
_tn
On
CJ
UJ
b.
o-.0-
NEo
_ _lid
__
_>-o_ _=_ _
-J
--_
__ dN-
_.J,_
__ _
A3-1
CD Z
O0 Z(J
I _lOi]
i-8
r,.) ..a
.,.:_,_ _/'
I
x 4t i
-g
>,
e,l
r,.)
I e_
_>
Z_ .-I _rt
i
,,o o o
'4' _
o,
_.-i
1-9
IJ
000I
- 39NVa
SS0_3
{
/ / /
/
f
f
O O
f r_
f /
U3 et
o o
,O
I--" h 0 0 0 p I laJ Z
/ I I I
0
O_
\ \ \ \ \
r_
D_
_>
\
\ \
I
,3 _=__ _,_,
i I
u_
++On.-
I
,,0 _ _ 03
I
CO eq _1" 0 .,O Oa
- 3(]131117V
1-10
1.1
35
REGION
r.....
7 I
I
I I
I PREDICTED I NOMINAL [TEST I POINT I _ 28.3 SEC
I
I
I I
L .....
26.1
SEC
400
_00
600
C-6062-55
7OO
DYNAMIC PRESSURE,
q - LBS/FT 2
Figure
1-8.
Vehicle
12-50-1
(QTV)
Mach
Number
Vs.
Dynamic
Pressure
i-ii
80 _
60
40
20
hJ ! IJJ
\ ACTUAL /
I-I-I'-.-
-r (J I--
-20
-4O
\
"%
0 10 2O 30 40 50 60 70 80 - SECONDS 90 1;O110 ELAPSED TIME FROM LIFT-OFF (a) PITCH ATTITUDE
-60
-8O
t._ a F.-
>.
,,-_
o/
-100
I I I I I
NOTE:
ROLL ATTITUDE & SPACECRAFT ABORT POINT (*) FROM MISSION A-O01 SHOWN FOR COMPARISON-OF RESULTS BETWEEN THE TWO FIXED FIN VEHICLES FLOWN.
ILl
F-
-200
_W
-300
OUJ n,t-_
12-50-2 -400
(MISSION
A-O01)
1
]tO
C-6062-56
Figure
1-9.
Pitch,
Yaw,
and Roll
Attitude,
Vehicle
12-50-1
QTV
Mission
1-12
The test
vehicle the
rolled time
left of roll
time
the curve at
region,
probably
of fin and/or
b, illustrates "test" time. Command properly the case. destruct that split were the the cluded destruct destruct in the
only
Destruct block
Subsystem
- The to the
portion
functioned block
in response pyrotechnic analysis had to insert portion case. - Base and and been
ground
indicated
propagating
ignition
Algol
Structure data for similar dynamic regardless Thermal in the for equipment calorimeter indicated C.
with
experimental readings,
bodies, varied
at maximum
pressure. of their
essentially surface
drop
analysis; motor
not necessary
a one-Algol,
configuration. as predicted.
fin temperatures
necessary, A-001)
(MISSION
Mission
test
1-10) successfully
was
on 13 May 1964. the BP-12 There, to the Apollo thrust vehicle. Apollo the launch
This Space-
fixed-fin-stabilized in a ballistic vehicle abort trajectory was Apollo A-001 launch dynamic Joe mission
by a ground program
command from
spacecraft
overall of the
to be tested during
a launch
to determine vehicle
and operational at transonic test purposes for (LJ-II Apollo 12-50-2). objectives were
an abort
One of the
Little
details
Mission
(BP-12),
NASA Report
MSC-R-A-64-1,
1-13
"--LAUNCH-ESCAPE SUBSYSTEM
1032.1"
I]
F]
JOE II VEHICLE
C-6002-57
Figure
i-i0.
Apollo With
A-001 502
BP-12
Test
Vehicle
Configuration
1-14
----4
1-15
TEST The and thrust within net greater pounds tion Real-time Officer onds). explosion module were spacecraft
RESULTS to set pounds ignited was thrust experienced. increased abort via motor vehicle the was test vehicle at an elevation SE surface by one by the motor just the Algol The single thrust prior NASA motor of the and Algol. was to the were Flight thrust. and caused abort ignited "hot the from angle winds. six were of 81 19' The Recruit expended a At lift-off 5 to 7 percent 105,000 terminaat the secresulting service " which initiated escape thrust Dynamics (T + 28.4 The the lines, launch rated ! J I
346 20'
to compensate were
for predominantly provided provided The with 122,000 test board casing forebody Algol altitude, pounds conditions station, termination to terminate and severing subsystem's line" simultaneously.
of approximately two
Recruits
thereafter,
as expected, of M-q
(at 6 seconds) Data initiated This destroyed pressure wrapped abort. around
to approximately optimum signal Algol to fail. of the launch (RTDS) the the plotting
command.
displayed
abort
the thrust
command
ruptured
afterbody,
bulkhead Severance
the thrust
primacord,
properly
simultaneously
and pitch control motors and separated on the launch vehicle; see Figure 1-12 Mission A-001 profile. A-001 flight first-order was of Mission was the
the command module from the service module for the resulting sequence of events, in the
were
The
launch the
vehicle ground
and testing
compatibility phase
both
operations. to that dynamic of the QTV, simulate and vehicle, on the thrust) thrust 1964 Report (LJ-II rather taken predicted have pressure allowing the Mach the QTV. and Saturn number for minor trajecexceeded was in flight is that
window
1-1),
the predictions; revised to take performance results discussed A-001 the Figure actual and (BP-12), time 1-13).
however, the reasons differ. into account the measurements the nominal in greater was abort three (zero wind, in equal measure, detail seconds been that the to high
drag estimate The disparity value effect. and This Mission Note 1-5 and
is attributed,
Apollo 12-50-2).
MSC-R-A-64-1, command
on time,
display of M versus "window." Aerodynamics problems winds by a small 135 degrees during as predicted: thrust CCW
it is certain
launch the
vehicle roll
loading
phase At abort
of flight.
stable -9 /sec,
approximate the
and/or forward
attitude
1-16
MAJOR EVENTS
1. 2 2.
LIFT-OFF THRUST TERMINATION & ABORT LAUNCH-ESCAPESUBSYSTEM MOTOR BURNOUT & COAST TOWER & FORWARD HEATSHIELD SEPARATION DROGUE PARACHUTE DEPLOYMENT PILOT PARACHUTE DEPLOYMENT MAIN PARACHUTE FULL INFLATION COMMAND MODULE LANDING
0 28.5
<
3.
"c,e
4.
44.0
5.
48.0
6.
116.0
7.
121.0
8.
350.3
C--6062-58
Figure
1-12.
Profile
of Apollo
Mission
A-001
1-17
1.0
0.9
t_ -m z -r L) 25.0 0.8
Figure
1-13.
Vehicle
12-50-2
(A-001)
Mach
Number
Vs.
Dynamic
Pressure
D.
VEHICLE MISSION
12-51-1 SUMMARY
(MISSION
A-002)
boost protective cover, and to verify the abort capability in the maximum pressure region with conditions approximating emergency
dynamic
angle-of-attack limits. A third-order test objective to demonstrate satisfactory performance of the launch vehicle attitudecontrol subsystem was achieved. It was the first of three attitude-controlledlaunch vehicles used in the program. control system programmed The attitude
(ACS) maintained the launch attitude in y&w and roll, and a preupon command from the ground, performed Detection Subsystem a to sinmlate the Saturn Emergency (EDS) anglerelay to
pitch-up maneuver
of-attack limits at abort initiation. The pitch-up signal activated a time-delay provide an abort signal to the launch escape vehicle (LEV). the arrangement of the complete test vehicle. Figure 1-3 summarizes
vehicle configuration. Postlaunch Report for Apollo Mission A-002 Report MSC-R-A-65-1, on the mission.
1-18
u_
1-19
TEST
DESCRIPTION
AND
RESULTS
The Mission A-002 test vehicle was positioned to 8402 ' in elevation and 0 in azimuth prior to takeoff. At countdown T - 0 seconds, the ignitioncurrents were simultaneously applied to the four Recruit and two Algol solid-propellant rocket motors. A launch thrust of approximately Recruit rocket motors, the was Recruit displayed Officer later. of the motors on the Responding Shortly sequence - The pressure in Figure the the pitch-up mission q at abort thrust dropped to 206,000 pounds, burned out. down at a rate of 0.52 deg/sec, Real-Time 358,000 pounds, provided by the two Algol and four longitudinal acceleration of 2.8 g's. The as of the (RTDS) via the flight vehicle vehicle When relayed broke plotting was the programmed desired board, radio abort up. was See M-q the to pitch test point Flight 2.1 1-15 for a NASA 0.4 percent below predicted at T + 1.5 seconds attitude System maneuver aboard the over abort launch the at lift-off. produced a maximum The Data
starting
initiated
(T + 33.6
Trajectory 1-16 higher predicted, RTDS sulted shows dynamic shown in a higher computer,
pitch-up
conditions
given the
the comparison
predicted
performance.
command planned,
subjecting
out failure.
Thus
deemed
to be successful. autopilot (with constant rate pitch elevons to maintain proper test vehicle The vehicle attitude was six-degree roll which mod-
provided proper corrective signals to the hydraulic-powered motors the pitch-up maneuver. The pronounced
and fin-mounted reaction control subsystem attitude (Figure 1-18), and perform well controlled from lift-off pitch-up. to
occurred just after lift-off was wholly predictable for launch with the No. 1 RCS ule inactive. This subject is discussed in more In regard to the aerodynamic detail in following paragraphs.
by the launch vehicle during the overall flight, although limit cycle oscillations of body bending were generated when the dynamic a and b.
The gyros revealed a frequency of about 3.4 cps, as illustrated in Figure 1-19, curves In following this signal, the unexpected oscillationof the hydraulic actuators hinge moment surface (Figures 1-19, curve c) prematurely depleted the hydraulic fluid with accompanying produced less than normal
pressure drop (Figure 1-19, curve d). As a result of the reduced available, and the high q, the pitch-up command
travel. Instead of the predicted 8.3 angle of attack, only 4.3 was achieved at abort initiation. Also, the resultant imbalance in elevon effectiveness among the four quadrants produced the sudden roll and yaw during pitch-up. fere with the LEV abort. These motions did not inter-
1-20
1.
2. 3.
33.6 35.7
121.3 123.3
DROGUE PARACHUTE DEPLOYMENT PILOT PARACHUTE DEPLOYMENT MAIN PARACHUTE INFLATION COMMAND MODULE LANDING
8.
160.4
9.
161.3
10.
443.4
10
C-6062-61
Figure
1-15.
Profile
of Apollo
Mission
A-002
- Vehicle
12-51-1/Apolio
BP-23 1-21
2.0
1.8
....
REGION /_]__sj,
I l I
I I L_ I I I
. _
1.6
3s.ss-)
37.55 1.4 I
PITCH-UP 33.6
I
LU nn
I I
! L ......
II
30 .'
Z -r <C
1.2
/j
1.0
JJ
"2/0__
0.8
0.6
0.4 iO0 " 600 700 800 900 q - LBS/FT 2 1000 1100
C-6062-62
DYNAMIC PRESSURE,
Figure 1-22
1-16.
Vehicle
12-51-1
(A-002)
Mach
Number
Vs.
Dynamic
Pressure
2.0
DERIVED
FROM
FLIGHT DATA
PERFORMANCE ESTIMATED
1.5
z w (.9 LL LL _J 0 D L_ 0 L_--J
MAXIMUM
/ NOMINAL
1.0
TAIL-OFF
0.5
INIMUM
0.5
1.0 MACH
1.5 NUMBER
2.0
2.5
3.0
C-6062-63
Figure
1-17.
Axial
Force
Coefficient BY- 23
Vs.
Mach
Number
for
Vehicle
12- 51-1/Apollo
In the seconds preset from and check tently the complete on, the
control data
to operate
T + 8 seconds,
aerodynamic recovery
corrected
by T + 4 seconds. cyclic
Attitude
programmed
a pre-launch occurred
tanks
operations
Inasmuch
for
vehicle
was on board only for its qualification, with the Fin 1 RCS inactive. Range the mission. unused abort. Safety Subsystem material - There signal sent aboard,
to launch
was was
for
destruct
A destruct
at T + 136 seconds,
in an effort to vehicle
pyrotechnic
- The occurred,
launch
loads estimated
prior
pressure
pressure
service
module.
to be about
in an aft direction;
1-23
LIFT-OFF
INITIATION ,, INITIATION _
OF SPACECRAFT
ABORT (T+35.7
SEC)\ SEC) \
INITIATION(T+O) I
/RCSON' PER,O0\
F -#
OF PITCH-UP
MANEUVER (T +33.6
\\
_ :
\ _ :
85,
_ THRU ABORT
(-9 UJ E3
I I
-I
I I I
I
w" 80
: ! !
"_?__
I-<
,,
I
|
:
I I
"/SEC
:
i
i
-r 75
p-
I
70
I I I I I I I I I I I I
I
65
I I I i I I
10,
0 IM
Ld
D
_
p< _.J _J 0 n,, -5
! I ! I I I I I I I I I I I I I I I I I !
10 ELAPSED 15 TIME, 20 SEC 25 30
i
i {
i
-10
I I
10,
I
(__ W r_
w"
r-,, pI-I--
I I I I I I I I
0 ,I I
i
o
_:
>-
-5 -I0
I I I
-5 5
35 c-6o62-64
4u
Figure
1-18.
Launch Time
Pitch, A-002
Attitude
Vs.
1-24
SPACECRAFT ABORT INITIATION (+35,70 SEC) LIFT-OFF & INITIATION PITCH PROGRAMMING OF PITCH-UP MANEUVER INITIATION (T+33.6 SEC) \
"=-"1
10
<_UJ _ ,.J QS --JLAJ Or'_ 0
__._RCS
_T.ROUG.
MOTORS OPERATIVE
ABORT
i
:
'
5
I I
I
""
-10
_I0
< LJ (J3
i
i,"
e_ _o
(3_
.'
' I
I
"
...............
+..._I.
=l&ll_
IJlu+
IL=I
lj llllll
LAIUI=+
ilm_
" A/i
A+-
-lO
LIJ
z"
0 Y--
10
J_
_0
2oZ 0 > LJ -J hl
"--_
-10
Z
eY
83o0o
ku tw 0.. CD
"_2000G
<Z ,... a >.'-1-
_Pi000 z_ -4
I.L
-2
10
12
14
16
18 SEC
20
22
24
26
28
30
32
34
36
ELAPSED TIME,
c-6o62.-(,5
Figure
1-19.
Vehicle Velocities,
12-51-1/Apollo Elevon
BP-23 Deflection,
- Time and
History
Hydraulic
Following the bulkheadfailure, the launch vehicle was exposedto an estimated bursting pressure of 10psi; as the strength of the vehicle was estimated to be approximately 5 psi, ultimate, the ensuingvehicle disintegration was considered normal. E. VEHICLE 12-51-2 (MISSIONA-003)
MISSION SUMMARY
The Apollo Mission A-003 test vehicle, consisting of Apollo Boilerplate Spacecraft BP-22 and Launch Vehicle 12-51-2 (Figure 1-20), was launched on 19 May the performance 1965. The
vehicle (LEV) in the high altituderegion of the Saturn IB and V launch trajectories, approximating the upper limit for the canard subsystems, and to demonstrate the orientation of the LEV to a main-heat-shield-forward attitudeafter abort. The launch configuration is shown in Figure 1-20. As noted in Figure 1-3, new filterswere added
at the vehicle firstbending frequency, to prevent the signals from feeding into the ACS. Also, the hydraulic fluid supply was doubled by the addition of a hydraulic system Due to a launch vehicle malfunction and subsequent vehicle break-up, an emergency
low-altitude abort was automatically initiated26.3 seconds after lift-off. A satisfactory abort sequence took place, culminating in a successful landing of the command module at T + 302.8 seconds. The abort was initiatedat a roll rate which far exceeded the limit of the Saturn emergency R-65-2, From detection subsystem (EDS). For postlauneh details, Report MSC-A-
refer to Postlaunch Report for Apollo Mission A-003 28 June 1965 (LJ-II 12-51-2).
(BP-22), NASA
coordinated analysis of flightsimulations, preflight data, flightdata and post(ACS) caused a maximum position from Break-up deflecthe
flightresults, itwas concluded that a malfunction in the launch vehicle quadrant IV servo loop portion of the attitudecontrol subsystem tion of fin 4 elevon. The elevon remained seconds after takeoff to vehicle break-up in the hard-over at 26.3 seconds. about 2.5
resulted from
centrifugal forces produced by rolling at nearly one revolution per second. this malfunction (the second-stage craft subsystems is shown LittleJoe II Algol motor their functions. abort events were precluded by vehicle break-up), correctly performed Because
Except for
all other launch vehicle and spaceThe mission profile achieved itwas
in Figure 1-21.
not possible to positively identifythe cause of failure. (The elevon position of the Nos. 3 and 4 fins were not instrumented for flight,nor were any portions of their control system servo loops.) A complete report on the subject is given in Postflight InvestiFlight, Convair Report GD/C-65-143, 23 June 1965
RESULTS
The Mission A-004 vehicle was launched at an elevation angle of 84 and at an azimuth angle of 356 . The aximuth angle was a deviation of 4 from the nominal North firing direction to avoid impact in the main area of the White Sands National
1-26
_
_ /
/o_ \
_ >
C_ 0 0 I C 0
e,3
I
oo
o _n
I l'--t I
%._,< >
0 C
,_ N
uJ
N _
_o
_-o o-w
_j_
1
I
?=
<3
\
_D
"I, d:,
i /
,_
'!,
._
1-27
%
TIME FROM MAJOR EVENTS LIFT-OFF, SEC
1.
J
LIFT-OFF & PITCH PROGRAMMING ABORT INITIATION CANARD DEPLOYMENT TOWER JETTISON APEX COVER JETTISON DROGUE PARACHUTE DEPLOYMENT PILOT PARACHUTE DEPLOYMENT MAIN PARACHUTE FULL INFLATION COMMAND MODULE LANDING
2. .3. 4. 5. 6.
7.
84.8
8.
106.0 8
9.
302.8
Figure
1-21.
Sequence Vehicle
of
Major
Events
and BP-22
Mission
A-003
Profile
12-51-2/Apollo
1-28
During meters
were
caused
by the following
vehicle
subsystems
pressurization
first-stage plugs
Algol at the
blockhouse
at T - 0 seconds.
pull-out
rise
2.5 seconds spacecraft between standing escape case all LEV could the
after lift-off, the fin 4 elevon anomaly abort at T + 26.3 seconds. Abort was launch vehicle failure Under the and spacecraft such was was of the (LEV). operated in Figure - The environment module leading that
and caused the premature when the abort "hot line" break-up. the attitude. on the command escape module The launch rocket However, landing, out-
severed the
of "spin-stabilizing" shield
a circumstance, to a heat
not orient
to a satisfactory
as illustrated Trajectory the abort grating pressure altitude The nominal BP-22
high
altitude and
(120,000
foot)
test
point
was
(12,400
recovered predictions
dynamic variation
(Figure
(see
Figures
1-1
and
1-5)
were
reasonably
close
to Saturn
trajectory. Control attitude occurred Subsystem exceeded (ACS) the range - Various of the I, II and deflection control overcome forces large attitude The fact that the in Figure For III. analyses ACS gyros, The of elevon pitch, (RCS) correct produced vehicle the flight angle of its moment No. indicate proper failure roll, was that, control from lift-off IV servo seconds.
Attitude until and control Elevons commands. post-launch rections elevon. creased Roll gyros. when vehicle the could Thus, the roll loop 1, responses 2,
commands
in the 4 at about
quadrant T + 2.5
resulted and Although analysis not, the point beyond is clearly angle 1-25) rate. no longer
correction These hard-over inseconds. attitude rapidly of the intended at an the cor-
not instrumented,
at T + 4 seconds, up the wherein of the path cross-coupling effects yaw path was
attitudes
introduce
70 . the
deviations
exceeding
control
be possible.
diminishing
report C A, was
for
Mission MSC-A-Rless
(Postlaunch 28 June
NASA Report
much
1-29
k I I \x
TEST REGION
f--
I
\ 3.5
oi
\89.0 \
I
I
\
\
\
\
\
\ 3.0
tO O(3
Z -r
1,5
1.0
0.5
/
0 200 400 DYNAMIC 600 PRESSURE, qLBS/FT 2 tOO0 II00 C_2_8
Figure 1-30
1-22.
Vehicle
12-51-2
(A-003)
Mach
Number
Vs.
Dynamic
Pressure
16
LL 0 0
8,
I hl
pp-,J
0 0 8 12 TIME, SEC 16 20 24
C =6062 -6 9
28
Figure
1-23.
Altitude
Vs.
Time
for
Apollo
Mission
A-003
I
I I
, ,
6O t i i
LAJ t_
4O
! ' N/
/
i
i,,,[
,El _'I El
I o i
2O
t i I
I I
L I
i YAwl I , ! .......... _-=........... ............... t.............._ _...... ---_...., ......... ' PROGRA_ PITCH
..;T. _
--''" [ ..............
-20 0
I
2 4 6 8 TIME, IO SEC 12 14 16 C-6062-70 18
Figure
1-24.
Vehicle
12-51-2
Attitudes
Vs.
Time
During
Mission
A-003 1-31
J';,
r
/
i/
CM _ LES-._)
TOWER JETTISON
e
biJ. O O
p4 I tlJ
12
A ,,
/x
ABORT (T +26.3
SEC)
I
PILOT PARACHUTE
I
DEPLOYMENT
pp-
_J
/4 Altitude
MALFUNCTION
IN FIN
12
16
20
C-6062-71
TOTAL RANGE- 1000 FT Figure 1- 25. Plotted Against Range for Apollo Mission A-003
than
the
at
numbers, In view of
but of the
was low
the
accuracy.
importance Structure
Math
number centrifugal
should force
Algols launch
the resulted. at
of the tracking
visible seconds,
film
data, The
335
motors two
Algol
designed vehicle
for moment
a fully the
resulting
reacted
to withstand - First-stage
conditions. normal; Lift-off transmitted as programmed (4-inch to the vehicle three secondrise) firstAfter burning the the
Propulsion stage occurred stage launch for some ignition 0. 443 motors. vehicle
did
notoccur, after
the
impulse and
break-up and
20 seconds grain
were of the
before Algol
impact by
propellant
in each
1-32
shock-sensitive throwing burning each motor. CONC The vehicle vehicle. severe the this repeat is, point F. ten
These motors were observed to ignite violently, within a radius of several hundred feet around
LUSIONS purpose of the objective test the mission was were success A-003 Saturn to obtain was safe to demonstrate but different either following altitude abort, satisfactory abort lower planned. it was The a successful from at a much from Mission abort recovery, V launch those A-004, Apollo from altitude launch the and basis. unnecessary premature, mission; a low altitude escape under of to but that test For
operations This (and test the other) objectives plus attempt Mission to the
to provide
recovery quite
in an emergency
launch
conditions
directly
or on a modified
reason,
demonstration
a satisfactory
12-51-3 purposes integrity The region forces to its of this in the from
(Figure
1-26),
the
last
Little Spacecraft
Joe
series,
boosted
a production-type of the test of the is defined were by the escape LEV airframe
on 20 January
an abort velocity
of aerodynamic module
launch limit.
impingement
command The
launch from
1-3. five
Some Recruit
stage;
relocation
(Station pitch
launch
vehicle lift-off
outer
(aft) face
of the thrust bulkhead; seconds; and deletion The cluding abort Apollo Spacecraft a pitch-up sequence. Mission
to T + 20
to the LEV
desired the
M-q
test
in-
during
power-on (LJ-II
contained
in Postlaunch
NASA Report
MSC-A-R-66-3
AND RESULTS positioned was wind ignition the at an elevation selected conditions of all five angle of 84 and of the prior motors at an azimuth impact Lift-off area, was rocket
azimuth for
desired
compensation
to launch.
first-stage
1-33
1-34
The vehicle
attitude until
control pitch
the
programmer seconds,
Pitch-down
programming motors
initiated
at T + 21 seconds At T + 36.4 timer. of information the launch was based vehicle upon the (approximately
at a constant
of 1.0 deg/sec. via an on-board On the Officer tail-off). "action seconds pitch-up motor module T + 70.81 basis seconds This line" after burning.
two second-stage
by the second
range
RTDS, by radio
the
Flight motor
initiated
command, q crossed
to start trace
of Algol of M vs.
at which
B (Figure 1-27). The action line was so derived that vehicle would be at the correct conditions for abort. to ensure of 11.1 that (+1.5) the were psi. (T + 73.73 initiated of events deployment mission some seconds), the of the profile, 60 yards abort drogue Figure away through LES the signal canard and from 1-28). time LEV also tumbled planned during launch-escape the conditions at abort to subject
maneuver
planned pressure
command
the
initiation RF and
delay de-
in the
vehicle apex
power-on were
tower Spacecraft
satisfactorily safely
in the upright
position
team. the The up, LEV high tearing continued Analysis abort, dynamic off the its the launch vehicle acting vehicle-SM intact, vehicle and service module angle ring (SM) continued caused 0. The the ground. lift-off to the
impact
- The
launch
controlled
abort. Based upon the M-q plotboard of the RTDS, the radio command for the pitch-up maneuver was so executed that the LEV abort 2.9 seconds later took place well within the ber used was onds the tions. closely test vs. window. dynamic one-half the (Figure date It is worth pressure percent estimates 1-5). The that noting, was and (Figure of the on Figure no wind. 1-30), 1-29, that from and pitch-up 25,000 the the the the axial point feet) Report actual overall force was used for Also, path of Mach situation thrust five density predicA-004 Mission secon coefficient reached in flight numwhich
significantly
predicted
standard
atmosphere
Although
average
matched
exceeded
atmosphere
in more
in Postlaunch (LJ-II
MSC-A-R-66-3
12-51-3).
vehicle
than predicted. These two facts led to the earlier Because the thrust had not markedly decayed, the occur the in the abort RTDS manner of the very aid; on the predicted close abort to the M-q plot.
desired
M-q time
stresses have
usefulness
of the
on an elapsed module.
in a low-pressure
command
1-35
9OO
8OO 700 600
IX
-_
LIJ
500 400
z
>Q
,o.4
0.8
2.4
2.8
C-6062-73
Figure
1-27.
Apollo
Mission
A-004
RTDS
Plotboard
- All Recruit firstindicated This also the and launch first data based (ACS) in the the of each
and Algol
and camera
second-stage accomplished in-flight Algol indicated motors on average - Some previous test attitude pitch-down and being and yaw was
no appreciable
motor.
of telemetered motors by + 0.5 Attitude used in this capability command stant were programmed increased was was
chamber to - 1.0
pressure percent,
satisfactory.
Individual
the pitch-up
ACS
1) RF command
abort
of 29.5
a time roll
of 0.52
at + 1 deg/see, autoptlot
T + 20 seconds
by one-third,
unchanged. the mission. the elevation The maximum as expected, Pitch-up angle excursions during was initi-
to 53 degrees; during
and roll
10 seconds
of flight,
1-36
MAJOR EVENTS
1. 2.
0 21.0
36.4
70.81 73.78
POWER-ON TUMBLING ABORT SERVICE MODULE BREAK-UP CANARD DEPLOYMENT TOWER JETTISON DROGUE PARACHUTE DEPLOYMENT MAIN PARACHUTE DEPLOYMENT COMMAND MODULE LANDING & MAIN PARACHUTE DISCONNECT LITTLE JOE II IMPACT
7. 8. 9.
10.
237.6
11.
310.0
12.
I 2
12
C-6062-74
Figure
1- 28.
Sequence
of Major
Events,
Apollo
Mission
A-004 1-37
2.8
I I \
% SEC
78.7
I P,TC.-UP _ i\
W n
/
2.0 I --
/
1.8
/ /
! I
1.6
/
700 750 C,-6062-75
Figure
1-29.
Vehicle Mach
12-51-3 Number
(A-004) Vs.
Power-On Pressure
Tumbling
Boundary
Abort
Dynamic
1-38
,I ALGOLSII =
I
(3 2 ALGOLS = --
I
i
I 2ND STAGE---.-.---I
I
IGNITION _
\
Z (._ h bI,I O (.9 hi C9 O b_ --J
_,_IST I
STAGE
BURN-OUT L,_PITCH-UP
MAXIMUM 1.0 (3
i I
<_
X
0.5
(3
I 0.5
I 1.0
I 2.0
I 2.5
3.0 c-6o62-76
Figure
1-30.
Axial
Force
Coefficient
Vs.
Math
Number
effectiveness. degree as shown angle - without location. were the effective in yaw
damped was
of about
of attack proof
fell
short
value
by several
- to wind
disparities
to uncertainty
any
structural
feedback,
or other
noise,
destabilizing Structure
vehicle-control
combination. forward from was module and these and Except time aft bulkheads accelerometers, LES, after ring showed The abort, the from that launch when launch impact. were the vehicle the used together
the command
insignificant.
top interface
of tail-first
ground
1-39
SPACECRAFT PITCH-UP
(T +73.73 SEC)
SEC)
INITIATION
"\ I I
M?
I I I I
I t
C_ W
_+I00
I pz
I I
I
I
+50
It II It I.
I I It I ,
h'-
+5
+2.5
uJ
I I I I
II
I I I
II It II
II
It I
I II
u_
I-I-i--
-2.5
I I I I I I
II II I.I It II II
-5 +10
!
I I
I I
1
+5
I.iJ c:3
I I
I I I I I
tl II It
II
II
I-I-I..J .J 0 J.w
o_
I
-5
t II II
-10 -10
It
0 10 20 30 40 SEC 50 60 7O
C-6062-77
8O
ELASPED TIME,
Figure
1-31.
Launch Apollo
Vehicle Mission
Pitch, A-004.
Roll,
and
Yaw
Attitude
Vs.
Time,
1-40
TECHNICAL
ANALYSIS
AND
DESIGN
CRITERIA
I TECHNICAL
ANALYSIS
AND
DESIGN
CRITERIA
A.
SCOPE Simplicity was fundamental of design areas, by making given, more to the was not Little used Joe II design philosophy. tests; analysis, e.g., tests simulation saving. in any of the necessary Little to add Joe II e.g., it was of thermal of vehicle without Where design it was of the protection base
conservatism In other tests For would benefits simple the been in terms
to supplant
proof
structure.
possible
example
have
expensive
of magnitude
providing
of manufacturing that weight test the desired which missions 2-1, large set was
It is of significance vehicles ballast The most ditions The Section B. part are launch 1. used in order critical outlined vehicle in the to obtain conditions with
Apollo
program.
it was
often
performance. the design includes margins limits planned the for for but the Little never Apollo Joe flown. flown, tests 1I were These for described for the conin
associated
in Figure possessed
missions
comparison.
AERODYNAMICS The basic 2-2 aerodynamic tests was and 2-3) coefficients conducted scaled for the Little at the Langley Joe H/Apollo Center. boilerplate vehicle The payloads were model on Little deter-
by wind tunnel
Research
to represent
the Apollo
was
from
the
full-scale in aerodata
(LES) 2-6.
tests
initially 2-3,
re-examined
of the with
or of the exhaust
reaction
of these These
to be estimated. patterns
See Reference
effects estimates
2-1
MISSION DESIGNATION
O 1 2 1
E 2 HIGH
I
HIGH MAX. DYNAMIC AT VERSION PRESSURE -50 17,60028,856 ALTITUDE AND MACH NO. -51 17,60028,856 -51 53,05080,000
J (A-O02)
N (A-O03) HIGH
Q (A-O04)
APOLLO
LEV
PAYLOAD WEIGHT (INCL PAYLOAD BALLAST) LITTLE MAIN JOE II BALLAST PROPULSION
8610 2 ALGOLS ZD ONE STAGE ;7RECRUITS TE-29 6 ALGOLS ID 7 ALGOLS ZD 2A 7 ALGOLS ZD 2A 7 ALGOLS 1D 4-3 3-3 4-2-1 4-3 OVERLAPPED 1 ALGOL ZD ONE STAGE 6RECRUITS TE-29 2 ALGOLS 1D ONE STAGE 4RECRUITS TE-29
5140 6 ALGOLS ZD
MOTOR
STAGING
3-3
BOO STER S DESIGN CONDITIONS: MACH NUMBER DYNAMIC PRESSURE, _q, DEGopSF THRUST/WEIGHT LEV TEST POINT: FT (ra$1)
q, PSF
(2)
ALTITUDE,
MACH NUMBER DYNAMIC PRESSURE, PSF FLIGHT PATH ANGLE, OEG ANGLE OF ATTACK, e, DEG
NOTE:
1. 2.
THE VALUES GIVEN WERE USED FOR DESIGN; THEY MAY NOT BE IDENTICALWITH THIS IS COVERED BY CONDITIONS FOR B AND OTHER MISSIONS.
THE FLIGHT
RESULTS.
C-6062-79
Figure
2-1.
Little
Joe
II Design
Configurations
the
data
from
subsequent A-001)
vehicle was
For
example, Vehicle of
data
up to M = 1.5,
performance
effect made
stability feet,
exhaust Inasmuch as
at high altitude
investigated
above
not directly
substantiated. Mission Additional References (see Note Tests by Little engine A-004 wind-tunnel 2-2, 1 on were Joe 2-3 Figure proposed called tests and 2-4. 2-2). whereby high altitudes zero-g the lunar excursion The module feet) configurations (LEM) to test would the of the be launched Little Joe for pitch-up (Figure The to a high 2-7) service were angle run was of attack data lengthened at a high Mach number. from SC-002
to obtain
module
1I to very
descent
in a near-vacuum,
environment.
II/LEM, using two versions of a shroud for the payload, are 2-9. As a result of wind tunnel tests (Figure 2-9) conducted Center desirable by analysis, 2-2 (Reference normal 2-9) force the N5 configuration were discarded was Although in favor selected mission characteristics.
illustrated in Figure at the Langley Research of its more established feasibility was tests.
because
the test
plans
of Saturn-boosted
A
TOP
==
FIN 4
4|
i,
1
COMMAND MODULE SECONDARY PITCH PLANE
\
4.80" NC TE I 4,620
1
TOP FIN 2
LITTLE
FIN 3
"AC1 _HINGE
C-606240
Figure
2-2.
0. 030 Scale
Wind
Tunnel
Model
-- LJ-II/Apollo
Boilerplate
Vehicle
2-3
2-4
RUN NOS.
RCS FAIRING
!No.
TAIL OFF - BODY ONLY 0 0 0 O -5 -10 -20 -5 -10 -20 -30 -5 -10 O -5 -10 =20 -30 -5 -10 0 -5 -I0 -2'0 =30 +5 +10 O
-2 o TO +95
ON
ON ,
13-14
15-16 I 17-19 20-21 22 -23 24
Ir 1r
-30 +5 +10 0
Ir
28,60
C,-6062 -B2
ALL RUNS MADE IN PRIMARY PITCH PLANE. NO HINGE MOMENIS RECORDED. RUNS 17 AND 18 ARE AT IDENTICAL CONDITIONS. Figure 2-4. LJ-II/Apollo 300 MPH Wind BP Test Schedules -7 Foot x 10 Foot,
Tunnel
RUN NOS.
LES WASHER
PITCH PLANE
1 2 3 4 5 6 7 8
s,,,4
OFF _
0',
ON
PRIMARY
ON OFF OFF ON -10 +10 -10 -10 -20 -10 -10 -20 -10 +10 -20
'r
dm .Z -_
oO Oh
NO YES
-20
-30
-5 +5
-so -30
-5 -5 -5 -5
-3o
-5 +5 NO
9 I0 ii 12
d_
II
TAIL OFF - BODY ONLY ON 0 0 0 0 SECONDARY ALL RUNS MADE WITH LES ON.
C-6062-83
Figure
2-5.
LJ-II/Apollo Transonic
BP Pressure
Test
Schedule Tunnel
--
8 Foot
2-5
ELEVON RUN NOS. TUNNEL LEG MACH NUMBER SCHEDULE LES WASHER NO.I I-3 4-7 8-ii 12-15 16-19 20-24 25-28 29-50 31-52 33-34 35-36 37-58 59-40 ALL RUNS MADE IN PRIMARY PITCH PLANE, NO HINGE MOMENTS WERE RECORDED. Figure 2-6. LJ-II/Apollo Plan Wind BP Tunnel Test WITH HIGH 2.80, 1.57, 1.57, 1.80, 1.80, 2.16 2.16, 2.80 LOW
i
DEFLECTION
1.57, 1.57,
ON OFF
1.80,
1.80, 2.16, 1.80, 1.57, 2.80 2.80, 1.57, 1.80, 2.16 5.86, 4.65
Schedule
LRC
Unitary
RUN NOS.
APOLLO PAYLOAD
ANGLE
OF
BP-4.8" SC-5.955"
I
SM SM
1.80,
2.16,
2.50,
1
-10 -15" -20" -25"
1.80,
2.16, 2.30,
2.86
2.80,
2.16,
2.86
-30" AND
C-6062-85
ALL RUNS MADE IN PRIMARY PITCH PLANE, WITH LES (LESS WASHER) RCS FAIRINGS ON. HINGE MOMENTS WERE MEASURED ON ONEELEVON.
Figure
2-7.
SC (Low
Test Leg)
Schedule
--
LRC
Unitary
Plan
2-6
N6 NOSE 2.208" _
LITTLE JOE II
=i
--.__
6.36"
,.!2,,
7
_]
FI
TOP
_,N 4
1
PITCH PLANE
C-6062-86
_,N 3
Figure
2-8.
0.030
Tunnel
Model
--
LJ-II/LEM
Shroud
RUN NOS.
NOSE SHAPE
TRANSITION STRIP NO
N6
2 3-4
N5
Or.-_
10
10
10
10
O0
N6 6-7
L
N5 N6
_00"N
OOr-I II
TAIL OFF
!
NO
I
INCOMPLETE YES
RUN9 DATA WERE INCOMPLETE. ALL RUNS MADE IN PRIMARY PITCH PLANE, WITH RCS FAIRINGS ON 50 FT 2 FINS (FULL-SCALE).
C-6062-87
Figure
2-9.
Shroud Tunnel
Test
Schedule
-- 8 Foot
Transonic
2-7
C.
DESIGN design
CRITERIA for Little Joe H were weight, test based a set upon three missions With some design the
described permutations criteria original seldom to satisfy The forms Vehicle analysis the
Statement
of Work Apollo
(Reference missions
2-10).
and of payload As new criteria launch were missions of Little resulted. vehicle considered Joe 2-13, using CPF 9,
(Referenee
2-11).
changes in design Thus, the resulting test missions stress which various analyses for these launcher mission essentially peak data the this gradient pressure. for
Old requirements design possessed during the the life in Reference dummy and 2-15). computer
is reported 2-14
for the
payload
12-50-1, each the wind wind, upon 2-10. attain based most
combination
dynamic through
initial Force
loads
Patrick
in Reference shape
envelope was
in Figure
envelope
is shown
determined on the
of a sharp-edged
to angle
of attack
was
determined
modes the
configurations. determined
therefore
for that
wavelength
response. to the selection of White suitable White Sands Missile were Range made Spacecraft Range, the vehicle percent jet) shown (WSMR) available Center N.M. design 2-10, is here as the launch in MSFC (MSC) was ," 15 October frequency MemoLittle 1962, required winds. together included for
Joe H/Apollo, Vehicle 2-17. of 99 percent design are profile. envelope. quite Studies, imposed
M-AERO-G-33-62,
the conditions
cumulative
in Figure
the exception
the wind
shears
similar. for the missions on the WSMR with on the than one actually flown by the the attitude gust the controlled The wind of for
vehicles
with
parameters
will occur
conservative
7O
6O
5O
phi LD h
=='_;
_c_'s
_Sc4,
40
O m I LU
__
..
"_-_. "-
-_ 30
I-F-J
r-"
_"
I I
/
2O
10
iI
0o
50
100
150
200
250
300
350
400
C-6062-88
500
Figure
2-10.
Design
Winds
for
Little
Joe
II
the
general to obviate
Little thrust
Joe
II design
to rely
on such
structural thrust
as on the is illustrated
A photoelastic results
of the design concept. The given in Reference 2-18. With II or its subjected Consider experienced specific stage) of the certain vehicle ipated remaining Algol rapidly was for one exception, subassemblies. to structural the failure launches structural in the increasing even of the pitched any intact motors
in Figure
full-scale The proof of the failure lateral tests Little prior restraint under particular angle missions. to earth
load was
tests
were
Joe
exception
the 2-12)
which
velocity,
to occur
inducing vehicle
of the this
withstood
_ll the
2-9
C-6062 -89
Figure 2-11.
Figure 2-12.
Structural Load Test of Vehicle 12-51 Attitude Control Fin in Convair Structural Test Laboratory
2- 10
D.
DYNAMICS
VIBRATION The original 2-14 AND ACOUSTICS design For vibration test applicable criteria and levels for Little adapted Joe testing for II were Little based Joe largely on
the 2-13
data and
in Reference
acoustics
of equipment,
Figures
IT as described
in Reference 2-21. These test levels were considered design, to be replaced if and when better criteria were certainty another, retained. The the however, environment. is unknown. FLUTTER Fixed (Reference envelope the analysis Fin than - Analysis indicated called carried The was was flutter. of the that fixed-fin flutter version stability proposed sea (12-50) existed missions. level dynamic of obtaining flight better criteria were by extrapolation not taken; the measurements original
to be suitable for preliminary available. Because of the unfrom one design flight configuration were to criteria
flight there
that
were
equal
to
demands.
be taken
on Vehicle
12-51-2; or acoustic
margins
environments
of the over As
launch greater
2-22)
a far
illustrated q = 1800
altitude psf,
test
performed for
the
natural com-
shapes
verification
calculated in Refer-
favorable
to exist
between
analysis
The flight of Vehicle 12-50-1 to sonic speed of the fins in the critical transonic region. Fin - The added problems of a movable
demonstrated
Controllable
elevon
plus
the
degrees
of
freedom in actuator bearing play, etc., were added ments of higher Mach number and dynamic pressure. necessary for the fixed structure, necessary flight such were flutter mandatory to conduct fin. of the testing to provide a more thorough of the flutter flutter and to the program Sensitivity elevon was the such stability by test launch design hinge
to the increased These factors for the to variations (Reference of an Apollo margins.
mission requiremade it fin than of the made Because it was of play, bolts, it no
of the fin-body
to determine
characteristics
flutter bearings,
2-11
1.0
I
I
0.1
,,,,[
,9
u"} -r rO Z ! LO I.--
2!
,o! \
o-' 0.01
FIN MTD. EQUrPMENT
W ..J m :D 0
0 THIS CURVE MAY BE USED IN LIEU 01_ WHEN GROSS THRUST <.500,000 LBF
0.001 1'0
! J I I | I I I I J I I I I I
100
I I
U_ 0. .)
I )I-Z UJ .J
12 DB/OCTAVE O.1
12
0.06
.) UJ L I,,n Z 0 I'-UJ --I UJ t) ,
O.Ol
1 I I
i |
50
1000
20_OO
Figure
2-13.
Vibration
Test
Levels
2-12
0
r_ i ,.,.I
160 DB REFERENCED
TO 0.0002
p BAR
-20
>
-3
)
-3o
==
Z 0
-40 37,5 75,0 75 150 1.50 .300 300 600 600 1200 1200 2400 2400 4800 4800 9600 c-6o6_-92
Figure
2-14.
Acoustic
Test
Levels
The shapes, program. it proved and test tests. analysis, mounting fixture, efforts leading was reduce bearings, beneficial vehicles. conducted to deeouple design stand
of the the
vibration ratios, initially control control failed rerun, in the from setup. changes assembly; installed.
was
the
natural
mode analysis
and damping more to the was clear The test the tests
to the flutter multiple setup and to the with system the rigidity more the
straightforward, test setups a fin employed theoretical of the rigid fixture of the fin, the series to a strong, rod-end to have production and thus of tests These which
to be much changes which making fixture. but without its the with free did disclose to third this vibration
designed
integration
The
sensitivity
resonant
unsuccessful. fixity to an afterbody During hydraulic tolerance proved for the system
of correctly
assembled play
II launcher;
design were
actuator flutter
bushings effect
and bolts
characteristics
2-13
401
II
FLUTTER ANALYSIS BOUNDARY J 1
I
I
I
i i i i
30 QTV (12-50-1) MAXIMUM
//
o.I
i i
I-'.1.0 I.IJ O. ) 0 0 i-I I UJ
i i i i
2O
i i i i
1-I-_1
10
/
0
/
l
i i i i i i i i i i i i i i
i
2
C-.6062-93
MACH NUMBER
Figure
2-15.
Fixed
Fin Flutter
Envelope
2-14
i
c
"I
2- 15
c -6 nf, 2 -9 5
Figure 2-17.
2- 16
As several vibration
a result additional
of the tests
lessons trailing
of deflection elevon
coefficients, test determination Using it was methods supersonic was was provided bolstered 2-18 the were
loading of the
fin with
a rigid
installed dynamic
of the hydraulic results that regions by use determined covered employed. of the of the
constant. analysis available. in the while level. from the greatest in the high the 2-18 Mission in Figure (Reference Three subsonic subsonic supersonic that the "E" 2-24), and
shown
adequate
stability
Strip MIT
confidence
Function
boundaries in Figure The 1600 analysis psf. The controllable region, tunnel ground
by these
below beyond
most
severe well
mission
pressures
and
the
flutter
most
flutter tests
for
this vehicle,
and
analysis
and on conservative
5 X 103----T N OTE:I
STABLE REGIONS ARE BELOW AND TO THE RIGHT OF THE BOUNDARY CURVES
F-O Z V i IJJ LIJ Q.
T
M.I.T. KERNEL FUNCTION THEORY
PISTON THEORY
eY I ,
LD -J
,
_> m Of bJ
STRIP THEORY"
Figure
2-18.
Controllable Vibration
Flutter
Boundaries
2-17
"FLUTTER" 2-25 that and panel 2-26 contain conservative, panel unlikely fins flutter was was albeit imprecise, launch the analyses vehicle series by flight of the fins. experience; of Little
of panels
in vibration of panel
- so-called failure
- of the corroborated
instability
no evidence
on the
recovered
from
BENDING to the stability were analysis. the fin analyses calculated, Although modes, the of the the Little Joe with was of body H/Apollo of the several negligible bending and higher to the autopilot as first control
in paragraph
F) was
determination
lowest
frequency of the
harmonics,
coupling
bending was
with
on the vehicle
important. bending was due escape was frequency proved primarily launch tower. improved ground The launch along this for to the excape Two among Vehicle use, 12-51-1 the in the were the test was and at the was actual modal predicted frequency analysis, to the to prevent American conducted the was case The to be 5.25 was 3.5 of incorrect estimated a recurrence Aviation/S&ID, of repeating prior by manually transverse repeated - that the for pitch in confirmed, vehicle prointerto exciting
Flight
assembled
booster
- movement be very
as a cantilevered
measurements
vided the frequency and damping ratio for the lations and test were carried out for Vehicles mass diction measured the was free-free given by the distribution for the and stiffness case frequency The the With between was was base the good. 1.60 restraint bending cantilevered vehicle.
fundamental cantilever 12-51-2 and -3 because Correlation 12-51-3, with for the for 1.65 On Vehicle
mode. The calcuof differences in of test example, cps with the for of the confidence were confirmed pre-
calculated
cantilevered
calculation
cantilever free-free
comparisons
considerable These
flight.
2-18
E.
THERMODYNAMICS
AERODYNAMIC HEATING portions of the The critical mission called stages. pressure The 1/8 point being exceeded inch calculations for a sevenThis of any (Referfin leading the from as a back
extent of aerodynamic heating was analyzed for various fin leading edge, fin skin, body skin and RCS fairing. standpoint in a 4-3 which high mission; 2-19, edge combination was no deleterious temperatures however, detail of the after on the was Mission with The were the below The was well region number results design extended the body "E," overlap which fired severe that arrangement of Mach studied. effects (above this fin was member. 65 seconds vehicle a) and was of the of the limit only melting skin as below
an aerothermodynamic configuration the Joe 2-28) would leading rather temperature b. At this most
produced
H configuration indicated experience of the the than edge (Figure leading only point
seconds
stressed, shown
in Figure
the design
] I/ - - "F'--F/- .... 1 il
;'
....
-'-'_ LIMIT TEMPERATURE BODY STA. 348 _" "" FROM L.E. I---0.25 FT FROM L.E.
ll/--
z w
W
1200 liO0
/
A, /
==o o It'
620 f
1000
I
1
B._.. / ,..-.----C _,,_]"_ DESIGN' LIMIT TEMPERATURE
i---
600
580 560
l[ I/
MELT POINT OF FIN L..(2024ALUM) IS i3 c, 40 60 80 I00 140
C--6062L97
_ U.I _-
540
600
_1_" "r"-_
.640R
FLIGHT
TIME - SECONDS
Figure
2-19.
Aerodynamic
Heating
- Mission
2-19
HEATING of the to high rocket when in the base with time design launch heat exhaust. region; vehicles fluxes. and the The first trailing source source plumes 2-20. mission. established; evaluated and heating edges was was of the fins heating heating producing 2-29 on the Figure presents foregoing, 2-21. of suitable motor a scale exhaust were model were from designed the occurred a disflux which both
base
exposure
radiant convective
the expanded
recirculation
and predictions
of the heat
a con-
to enable structure
fin base
Erosion after
rise,
adhesive gases
qualities
20 to 120 seconds
of exposure
Rp-1/GD 2 rocket engine. Acrylonitrile compound, and a Bonding the were were Cement lowest exhibited adhesives problems erosion
Five silicone rubber base compounds, a Butadiene (GenGard V44), a Concrete-Asbestos compound (Transite), were heat. reduced evaluated. had the Although its The Transite erosion had and DC-6510 rate. the best The heat with (uncured) bonding resistance, surfaces. more rate; by the regarding also EC-1293 highest Transite and bonding desirability
(EC-1293)
fabricating
it to irregular as compared
PROFI LE
C-b062-98
Figure 2-20
2-20.
Rocket
Exhaust
Interaction
160
LU
120 ",_4
MOTORS_
_.._3
MOTORS'---'_
8o
__
o o
<-I
20 2-21. rubber adhesion tests was made most and
RADIATION...,,,.,,,
RECIRCULATION + RADIATION
80 c-bo62-99 -- Mission E
Figure
Dow-Corning heat details Reference (Reference of DC-6510, large struetural was subjected of temperature protection, of the
DC-6510 erosion
silicone
was
selected
for
base
basis the
of
of
2-30, 2-29). as
protective of 0.5
the
in Figure
protect
the
Indeed, of only to
7 F when
inches
thick) (70 F)
BTU/ft2-see. rise tests high dynamic be highly short heating convective purely indicated than the
of 75 also
a temperature
in the
aforementioned
protective tests
high-velocity, erosive test than results Low produced exhaust the heating
in the
would were
recirculation
at high
altitude.
Thus,
the
conservative. duration of the heating radiant that flights, base. exemplified Without base the or fin by the QTV and Mission A-001, of the not occur; mission would see with Figure its 2-21
of the
in nature. the
base
0.10-inch
swept
uJ
z 0 I--
en
_,_--
L_I v
r/l
d
I
2-22
700
V7
ABSORPTIVITY = 0.5 = EMISSIVITY
6OO
500
0,375"
ALUMINUM
45 SWEPT
LL e
TRAILING 400
EDGE
'
LLI
I'-
0hi I--
300
200
i00
0 0 10 20 TIME SECONDS
C-6062-101
30
40
50
Figure
2-23.
LJ-II
(12-50)
Base
Heating
- Mission
F 2-23
greater above protection a 1/8-inch areas. aluminum GenGard ature abort, series easier good
view the
factor
with
could figure;
to the fin
Postflight structure
rise
in the structure
not more
ignition. 2-22,
as shown
and because
adhesion
and insulation
of the DC-6510. thermal thick the flight protection l_yer showed was provided cured material for the base at no a from change of
In the interest Vehicle 250 F. evidence mounted 24F nature Vehicle For area fired, altitude. imbedded trailing and 12-50-1. Measurements plate;
temperature
in the base
postflight
of the base
of any physical changes. Using the data obtained on the base, it was calculated that an uninsulated rise by the time of payload abort. base insulation This was of the design 12-50-2: Vehicles of the fins was analysis. As a result, fin trailing-edge and -2, with thermal
from two calorimeters base would experience confirmed protection provided the was omitted
temperature
conservative
as before. (one-half The and effect last inch vehicle was thick) base
DC-6510
(one-eighth subjected
of the body
no indications
of base
body struck
the ground
first,
the base
no observed
THRUST
MISALIGNMENT flightat very high altitude (i. e., very low air density) the disturbance of the Algol motors. was the design criterion for the reacwas the result of several sources
For powered
torque on the vehicle was due solely to the net thrust misalignment The magnitude of the transverse thrust component tion control system thrust. The total misalignment
of error: production tolerance in lateral position of the nozzle centerline; 2) production tolerance in angular position of the nozzle centerline; 3) installationtolerance in angular position of the nozzle; and 4) uncertainty in the displacement center from the geometric center of the nozzle. Manufacturing able for the Algols for items i) and 2). A reasonable on the accuracy of measurements quantity;the variabilityof gas flow in a rocket nozzle. purposes was obtained by extrapolating some of the gas flow for 3), based for design tolerances were avail-
rocket (Reference 2-32). Adding the four contributing errors on a root-sum-square basis gave the design thrust misalignment 2-24 for each mission. (References 2-33, 2-34, and 2-35 are for Vehicles 12-51-1, -2 and -3 respectively.)
C) THERMOCOUPLES /
140
120
Lt. o I W r,,," D t.-
...... ....
1 2 .3 4
,#, s _ sS
i/"i
I
100
.JY
sS
8O
Dr
60 -10
10 ELAPSED
20
30
40 - SECONDS
5O
60
C-6
062
-102
Figure
2-24.
Fin Trailing
Edge
Temperature 2-25
ALGOL Accurate uniform range Studies the stalled. ditioning grain was
REGULATION of the ballistic be maintained at White requirements properties within Sands were of the the range Missile within made for Algol motors required With air that a confor in2-38 air a
of 70 to 90 F.
5 F of the desired
selection
the launch
are documented
by References
Reference
presents the time variation of propellant conditioner and launch timer, for various F. STABILITY Within a flight during of this attitude The this AND CONTROL section system phase system In short, are for summarized Little the end Joe missions results
those and
the
synthesis H/Apollo
of
II simulation of these
of various
activities in Section
were
vehicle
were
a set
of orthogonal,
right-
hand coordinates vehicle as flown. the Astronauts direction), Linear Positive origin. forces Positive down) coordinate The attitude to the to-fin system dual right, displacements angular Because hinge when
origin at the center directions of the X, position (toward time mounted were root as the in the Little about between downward surface the a right-hand positive derivatives
of gravity (mass center) of the total Y, and Z axes were taken relative to module: positive and X-Z fin viewed were Figure forward tower), along axes, the (in the respectively. positive from positive wing. edge the (trailing illustrates axes. the flight Joe the with II launcher were the X-Y the wing. directions. NAS 9-492 the Apollo sizes was a study of the A, B up positive
in their
command
clockwise
as viewed planes,
on a fin taken moment viewed system initial control LEV area was system abort ratios, selected. made task
as a right-hand 2-25
deflection
clockwise
carried
requirements 2-1) which point. the After concept The possible with system gyros the only (RCS) The with combined this until
and C (Figure
conceived a study
angle
control-surfacecontrol 2-39. which such were of three attitude. integrators upon four Logic into readily degrees This could as a rejected
of a combined of this use alone, proposed the and error reaction would the of a single
aerodynamic-plus-reaction in Reference all Algol unit the missions, approaches exhaust, consisted vehicle and Based within
results
not be accomplished reaction after due orthogonal and control commands available of the 2-26 launch control rate to the consideration. circuitry components, attitude
aerodynamic
Other in the
electronic
aerodynamic
system at least
attitude
end of powered
flight.
+X
_J
LAUNCH-ESCAPE
SUBSYSTEM
/O_IF
_r1_
/__--_+Z
_w,._
,_
i'_0
..-,-=_-LAUNCH VEHICLE
-ZIRECTION
OF
LAUNCH
AXIS X Y Z
MOMENT L M N
POSITIVE DIRECTION Y TO Z Z TO X X TO Y
LINEAR VELOCITY u v w
ANGULAR VELOCITY P q
r c-6o62-1o3
Figure
2-25.
Axis
System
for Orientation
and
Motion,
LJ-II/Apollo 2-27
Early reducing
in 1963 the
a major error
change These
was more
made
accuracy,
allowable
(for elevations of the integrators parameters gyro system, A control using the
led to the replacement in control Joe just H. described, system, to the attitude
2-40).
discussion version
was
having to simulate
Convair
Analog
the control
the gravity field, of these elements. configuration. depicts the the simulation
2-26 depicts the relationship of the autopilot in its final in Reference 2-41. It is worth of rigid-body Figure noting freedom 2-28 that
simulation
of aerodynamic dynamics
control
of the vehicle
included
plus the first body bending mode in pitch and in yaw. se, because they were too high in frequency to affect steady aeroelastic 2-3, effects Appendix were C. manifest in the in Reference
aerodynamic
coefficients,
FORCES MOMENTS 1'AERD FORCES J 2 PROPULS,ON MOMENTS ] EQUATIONS 3 FINONTROL LOADMOTION C CONTROL I OF , REACT,ON
BODY AERO.
I_
I" TRANSLATIONAL I 1 VELOCITIES
I
LI POSITIONS COSINES ] DIRECTION
INERTIA
! FLIGHT
TABLE
, n1,2f3 VELOC
2. I 1. ATTITUDE ERRORS
c.P.
Ts.L"
V w
,8
FIN DEFLECTIONS
FORCES
C-6062-104
Figure
2-26.
Block
Diagram
-- Vehicle
Dynamic
Simulation
2-28
qoYRO ,,LOW-PASS H
_r
'(" _
q
I 'IFILTER I _
-J
P,TCH , _ i
r --
'
--
DRIFT = fit)
DEMOD.
COMBIN. FILTER
k-F
a
__
t....
8 4
FREE IGYRO _ _
'...... C-6062-105
Figure
2-27.
Block
Diagram
-- Autopilot
HM
_ HM =f(a,6, q)
s/_,_
" I I GAIN HYSTERESIS RATE LIMIT FIN DEFLECTION (a) AERODYNAMIC CONTROL
_1_
POSITION LIMIT
, iort l
;
-= -t
oocoq
0.035 SEC (OFF)
FR h O. O08S+I
FR.
C-6062-106
Figure
2-28.
Control
Subsystem
Simulation 2-29
Once the
stability pilot critical linear locus 2-44. contain gains, "time theory These the
control
system
had been
analyses were
were
made
and the overall hysteresis, in the trajectory; apply. function analyses of fixed e.g., The results diagrams, mass shift 2-43
system. and the like the velocity analyses, the analog break point. aimed modes 2-29. filter
investigated
of such
of Bode, (which
and describing
through
complemented
explicitly
of parametric The analysis filter was three going to block as experienced degrees analysis.
of Reference the coupling on Vehicle shown With the For second of freedom
was
the
of structural 12-51-1. schematically plus fundamental filter filters system analyses were selected three order),
attitude studied,
Of four
set up to check
encountered. critically
the other
damped
were
exhibited. of simplifications To answer was the question performed were conThe effects of nonlinearities were
of the such
stability
by linear
representation simplifications
of elements
of the
a nonlinear
(Reference 2-44). Nonlinearities sidered in the elevon positioning, each were calculated limit cycle as having attitude were by describing oscillations, a negligible control inserted and did create evaluated
of deadband, saturation and hysteresis hydraulic servovalve and the gyros. function the effect low on the techniques. level, vehicle Although and its control these low frequency
oscillations system.
was
translated 2-26.
into This
system, accuracy
as indicated servovalve,
in Figure made
analysis.
the system
simulated
Following
discovery,
portion
of a servovalve
succeeding
simulations. The and FIN block shown set in Figure 2-26 represents The for single six a single fin degrees aerodynamic fin-elevon were sufficient the remaining case had - excepting the
one quadrant
of reaction
controls.
for three-degree-of-freedom
simulations;
control quadrants had to be simulated. demonstrated the close check between servovalve freedom - simulation work. of all four
In practice, once the simpler simulated and actual controls was satisfactory for
quadrants
six-degree-of-
2-30
------r
,F,,
o,_
*-4 0 0 0
+ qP - OllV_ 301"lll-ldl/_V
2-31
The RCS was not mounted on the fin root (Figure 2-30), as on the vehicle, but w a s located in a test cell (Figure 2-31) for reasons of safety. Functionally, however, the two controls were connected into the autopilot (located with the analog computer at a third location) by electrical cables in the same scheme as in the vehicle. The gyros were mounted on a two-axis flight table adjacent to the analog computer laboratory. A closed-circuit television system permitted visual monitoring of the gyros, fin and RCS at the analog control station. The limitations of the flight table were two-fold. First, having only two degrees of freedom restricted the scope of the overall simulation. The second limitation w a s more severe: the large phase lags in the table response and the wave distortion of small amplitude signals made it impossible to obtain meaningful results with actual gyros in the test system. Simulated gyros were not known to represent accurately the response of the sensors. Because of this restriction, the simulation and hardware verification efforts were thereafter conducted largely at the Manned Spacecraft Center where a new, highly accurate three-axis flight table had just been received. Reference 2-41 contains a detailed comparison of the setups at Convair and MSC. The test fin system at Convair w a s duplicated at MSC; the RCS was not. Because the RCS unit, a s tested, confirmed very closely the analog representation, transfer of the hardware to MSC w a s unnecessary.
C-6062-108
Figure 2-30.
2-32
1 .
r; . C-6062-109 ,
Figure 2-31.
CW and CCW Test Assembly (One Fin Set) in Prototype Reaction Control Subsystem of Attitude Control System - H 0 Fueling in 2 2 Test C e l l
Integrated attitude control system tests were completed prior to the launch of the first controlled vehicle (12-51-1), the results being reported in References 2-41 and 2-46. Two design changes and a change in operating procedure resulted from the tests. A s reported in Reference 2-47, a failure mode analysis was performed for Mission E (seven-Algol configuration) using the six-degree-of-freedom analog simulation (Convair). Prior to each launch of a 12-51 version launch vehicle, a failure mode study was made, using the analog-plug-hardware simulation of the mission. A s a practical example, Vehicle 12-51-1 (Mission A-002) was launched with the No. 1RCS unit deactivated. Prelaunch analysis reported by Reference 2-48, showed that even a full-on RCS motor failure would not jeopardize this mission. RCS was not required for the A-002 mission but was being flight tested to qualify it for Mission A-003. The detailed failure analysis (Reference 2-49) considered single and multiple failures of elements of the sensing, logic, control and propulsion subsystem. Similar studies were carried out for Vehicles 12-51-2 (Reference 2-50) and 12-51-3 (Reference 2-51); however, the study for Vehicle 12-51-3 was conducted with a digital simulation. Following the in-flight failure of Vehicle 12-51-2, intensive efforts were made to simulate the flight history as an aid to failure analysis. A resonably good match of tlie vehicle dynamics was achieved with the six degree-of-freedom digital simulation, considering the meager flight data obtained on Vehicle 12-51-2. The results of the
2-33
indicated A-003 is
an active 4 elevon.
failure The
the hard-
displacement
of the Apollo
in Reference
DESIGN
ENVIRONMENTS to the design environments systems for and environments were Little specified Joe previously to guide II and design discussed, the design e.g., vibration Figure and 2-32 is
and type
qualification
equipment.
from
2-17, Sands
with
for conditions example, margin limit any suitable is below There winds exceed as shown
to Little
and White
acceleration
the minimum
at WSMR
or Wallops
CPF
surface at WSMR),
the 99 percent
at 4,000
(the elevation
the wind
velocity at launch was assumed down cables could be removed entire shown altitude in detail range b. is shown
velocity at which the tiewind envelope over the the design gust spectrum
a of Figure
With difficulties
environment
previously
discussed,
no great
by the environments.
2-34
PRESSURE 1. 2. IN-FLIGHT GROUND NONOPERATING OPERATING 3, AIR TRANSPORT 9.5 11.0 3.0 TO 15.5 TO 15.5 TO 15.5 PSI PSI PSI 1.5.5 TO 0.003 PSI IN TWO (2) MIN.
TEMPERATURE 1. IN-FLIGHT INTERNAL STA MOTOR CASE) FIN - MORE ELEVON HYDRAULIC 0-34.75 6" AFT L.E. 35" TO 160"F IN 60 IN 60 SEC SEC O* TO 352eF -1.5" TO 300eF -15 TO 160"F -15" TO 160F "LESS THAN 1050"F -15 TO 250F IN 60 SEC
THAN
ACTUATOR
COMPARTMENT
ACCUMULATOR NOZZLES
COMPARTMENT) REACTION CONTROL EXTERNAL 2. GROUND REACTION ALL ACCELERATION 1. IN-FLIGHT LONGITUDINAL TRANSVERSE PITCH VIBRATION 1. 2. IN-FLIGHT (SEE FIGURE OR YAW - C.G. - LOCAL OTHER SKIN
CONTROL
- FUELED
NONOPERATING) COMPONENTS
+8, +IG
-2 G
+2G +1 RAD/SEC
2-13) 5-27.5 +1.56 +1.30 1.04 CPS G G G 27.5-52 .043" .036" .029" CPS D.A. D.A. D.A. 52-500 *-6.0 CPS G
GROUND (NONOPERATING) WT < 50 LBS 50 1000 LBS < WT LBS <WT FIGURE < 1000 LBS
5.0 G 3.33 G
ACOUSTICS SHOCK 1.
(SEE
2-14)
GROUND
(NONOPERATING) WT < 250 LBS LBS LBS 30G, 24G, 21G, 18 11(1) 11(1) 11(+1) G, 11 MSEC MSEC MSEC
(I)MSEC
TO 100%
RELATIVE
HUMIDITY.
360 RAIN
BTU/FT2/HR
4 IN./HR 1 IN./HR
FOR ONE HOUR FOR ONE HOUR AREAS FOR TWO YEARS SILICA FLOUR FPM
EQUIVALENT WITH
PARTICLE
VELOCITY
UP TO 500
7.
WINDS A. ALOFT (SEE FIGURES 2-10 & 2-33) HEIGHT 8. SURFACE ABOVE GROUND (FEET) 10 30 60 100 150 99%(CPF) STEADY (KTS) 27.9 34.8 40.1 44.3 48.0
Figure
2-32.
Environment
for
Design
of Little
Joe
II 2-35
200
160
i, 0
=
...r
120
0 'lp! W Cl Ira I---I ,, q
/
/
CPF - CUMULATIVE
c
i--
80
"o._
500 0 20
40
/
40
/
60 80 - FT/SEC
_.-6062-111
oh; _
O 100 200 300 400 WIND SPEED - FT/SEC
100
GUST AMPLITUDE
Figure
2-33.
Wind
Profile
--
Gust Spectrum
2-36
REFERENCES
2-1
for
Little
Joe
II with
316-Inch
Service
Module
and
50 Ft 2
Document
LJ-004,
2-2
Wind Convair
Data
Report
1963. H-Apollo 5 March Based 1965. Little Fins, Joe NASA II-Apollo Project Apollo on Wind Tunnel Tests,
2-3
Aerodynamic GDC-63-137,
Revision
2-4
Static Working
Production Booster
Configuration
2-5
Launch Test
Flight 12-50-1,
Apollo,
Little
Joe
II Qualification 1963.
2-6
Postlaunch MSC-R-A-64-1,
Report
for
2-7
Postlaunch MSC-R-A-65-1,
Apollo
A-002
(BP-23),
NASA
Report
2-8
Little
Joe Number
II - Apollo 1.80
Configuration NASA,
at
of Attack
Up to 40 and at Mach
to 2.86,
2-9
Data
and
Analysis 8-Foot
of an 0.3 Transonic
Scale Pressure
Model
of a Little Test
Joe No.
H/LEM 288)
Configuration Report
(Langley
Tunnel
Convair
GDC-63-243, 2-10 Interim Launcher, 1962. 2-11 Air May 2-12 Stress 28 June Loads 1963; for
Structural Little
II Project,
Convair
Report
GD/C-62-278A,
25 September
Structural
Design
of Little 1965.
Joe
II,
Convair
Report
GD/C-63-102,
Revision
5, 30 November Joe
Analysis 1963.
of Little
II Stabilizing
Fins,
Convair
Report
GD/C-63-036,
2-37
2-13
Report I, Ballast
15 October
2-14
2-15
II Launcher,
GD/C-63-038,
Vehicle Addenda
Stress I-IH
Convair
Report
19 August
12 March
respectively). and Annual Base, NASA Wind Distribution July 1961. Atmosphere (Part I), IRIG Document as a Function Florida, by J. W. of Attitude Smith for Patrick W.
2-16
Cape
Canaveral,
and W.
TN D-610, Range
2-17
White 104-63.
Sands
Missile
Reference
2-18
Convair
Report
SL-62-028.
2-19
Little
Joe
II Attitude Addendum
Control 1,
Fin
Static
Proof 1963.
Test
Results,
Convair
Report
SL-63-024, 2-20 MIL-STD-810. Equipment, 2-21 Vibration Little and 12-50, 2-22 Little Report 2-23 Results Little 1964. 2-24 Little Test 2-25 Little Joe Modes, Joe Joe
15 October Test
Methods
for
Aerospace
and
Ground
for
Equipment
DF-12-101, Design
I, Vibration
of Little
If/Apollo
Fin
Flutter
Analysis,
Convair
Memo
and
Associated Report
Stiffness GD/C-64-023,
Tests
of the
II Attitude
Convair
10 January
Flutter
Analysis
Using
Ground 1964.
Vibration
29 January Convair
Memo 1962.
Report
A to Reference Analysis,
Vibration
DF-12-106,
Cantilevered
Fixed 19 March
Fin
Ground
Vibration
Test
Results,
Report
GDC-63-055,
1963.
2-38
2-28 2-29 2-30 2-31 2-32 2-33 2-34 2-35 2-36 2-37 2-38 2-39 2-40
2-41
Heating-Little
Joe
II Booster,
Convair
Memo
Report
T-12-25,
Joe Report
Algol 1963.
Rocket
Con-
Materials Evaluation Report RT-62-040, Base Heating-Little 13 November 1962. Davis, Inc., Little A-002), Little A-003), Little A-004), Little Joe November Little Memo Little Joe Joe Joe Follin 1958). Joe II Design Convair
Protection,
Convair
II Mission
Convair
Memo
Report
T-12-17,
& Blitzer,
Exterior
Ballistics
of Rockets
(D.
Van
Nostrand
Co.,
Thrust
Misalignment DC-12-023,
for
Mission 29 June
(NASA
Mission
Memo
Report
II Design Convair
Thrust
Misalignment D-65-15,
(NASA
Mission
Memo
Report
II Design Convair
Thrust
Misalignment D-65-40,
Mission
Memo Air
Report
H Ground 1962.
Conditioning,
II - Summary T-12-14,
of Ground 22 October
Air
Conditioning
Requirements,
Convair
Report Joe
1962. Temperature Report Variation T-12-26, Apollo 2 July Accuracy Test 1962. Study of the Little Joe with Air 1963. Vehicle -
II Rocket Removed,
Grain Memo
Conditioning Attitude Little Convair II Vehicle, Integrated Convair 2-42 Convair 23 July 2-43 Stability Apollo 2-44 Little 1965. 2-45 Convair
12 June Launch
1963). Little 1964. Analysis - Little Joe II, Joe II, NASA Apollo Project,
Control
30 November Stability
of Apollo Convair
Mission Report
A-003
(Little
Joe 3 March
12-51-2/
BP-22), Joe
Memo Stability
D-65-9,
II Nonlinear 12-51-2/Apollo
Analysis Convair
of Apollo Memo
Mission Report
(Little
Joe
II Vehicle
BP-22),
5 April
Memo
Report
DC-12-020,
Little
Joe
II Autopilot
Noise,
7 April
1964.
2-39
2-46
Integrated Apollo
Attitude
Control Convair
System Memo
Tests,
Little
Joe
51-2,
NASA
Project, Memo
Report
D-65-18, Joe
19 April II Failure
2-47
Report
DC-12-009,
Little
1 October
2-48
Memo
Report
The
Effect
of Reaction A-002), J,
Control
Malfunction 2-49 Little Joe DC-12-029, Little Memo 2-51 Little Memo 2-52 Post Joe
on Little
J (NASA Mission
14 September Memo
Convair
2-50
A-003,
Failure
Analysis,
Convair
Report Joe
II Vehicle D-65-39,
A-004,
Failure
Analysis,
Convair
Report Flight
Investigation, 23 June
A-003
Flight,
Convair
Report
GD/C-65-143,
2-40
VEHICLE
SYSTEMS
[VEHICLE
SYSTEMS
A.
GENERAL The vehicle systems purpose and testing developed, are summarized requirements, of components, specifications designed design are and assembled 3-1. description, listed Each and to meet vehicle systems, the Little and Joe discuschanges, I. II
in Figure
system
includes
development in Appendix
subassemblies
conclusions
A of Volume
designed developed
for
use the
of readily necessary
available developtests
off-
the-shelf This
components
and proven
on other
programs. are
procedure
As a result, to a minimum.
ment testing by Convair and vendors included in system discussions. QUALIFIC ATION TESTS
Development
The qualification testing performed on Little Joe II falls into three basic types: 1) purchased components requiring partial or complete testing to the Little Joe II requirements, 2} newly developed Convair ponents developed for Little Joe II. The total number of new components used, due components, and 3} subcontracted com-
was to the
actually extensive
quite use
small
compared
to the
of components
of previously
qualified
of the qualification
environmental testing
levels is included
for
Little
Joe system
II is presented section.
in Section
2.
in each
EVALUATION Interference to evaluate reviewed and tested for possible during EMI (EMI) support and systems design offered. Wiring both phases. specifications. installations at San Diego initial solutions was provided for Potential throughout the Little All areas electronic were system and and
Electromagnetic Joe were also II program were identified was tested systems equipment performance
components
Convair-built
to applicable
to ensure monitored
APOLLO MISSION
QTV 57,165 DUMMY CSM MOCKUP LES (LBS) (LBS) 12-50-1 24,225
PAYLOAD
- NUMBER
12-50-2
12-51-1
12-51-2
12-51-3
CONFIGURATION -WEIGHT INC. MOTORS - BALLAST (LBS) - FIXED FIN FIN - CONTROLLABLE (LBS) 32,941 X . 32,595 X 6 1 58,030 8,609 X 4 2 144,309 5,044 X 3 3 ORDER X X X X X SINGLE HYD. X X X X DUAL X DUAL X 101,328 5,867 X 5 2 2 X X X X
PROPULSION
- 1ST STAGE RECRUIT -1ST -2ND STAGE ALGOL STAGE ALGOL PROGRAMMER CAPABILITY FILTER-2ND FILTER-NOTCH CONTROL CONTROL ACTUATOR
ATTITUDE
CONTROL
- PITCH-UP
-REACTION -ELEVON SUPPLY RF COMMAND -RANGE -THRUST -PITCH-UP - ABORT ELECTRICAL - PRIMARY
-AERODYNAMIC
SAFETY
DESTRUCT
X -
X X
X X
X X X X X
LOCATED IN PAYLOAD 3 24
X X
- INSTRUMENTATION
INSTRUMENTATION
3 66 24 X
2 58 37
LOCATED IN PAYLOAD 13 45
1 39 36
RADAR BEACON
-LAUNCH -PAYLOAD
VEHICLE
X
C-6062-10
Figure
3-1.
Launch
Vehicle
Configuration
Summary
3-2
Military
specifications
were
used
as guides
for
the
These
were:
Control
Requirements Test
Interference
to MIL-I-26600 was the initial MIL-STD-826 of equipment Specification specification (upon request) MIL-I-26600 to which MIL-I-26600. the equip-
Specification applied
designed;
superseded
Tran-
EMI-10 or MIL-STD-826, for transient tests. All completion to modified test faces. Convair of each All systems were given
a Manufacturing phase. MAE and enabled of parameters harnessing, 0-09001. also checked
(MAE) was
ring-out,
Installation
out Procedures The phase reviewed Such areas Requests were for Design
during
MAE. the design and manufacturing vehicle. and formal All RFC's change. shipped it was
Inspection NASA
dispositioned
by a DEI board
The motors, and loads. Section The and site. from 3-3. stalled. side
was
designed loads
to take
the body
axial and
loads other
produced asymmetric
body bending caused airframe Maximum launch Either body vehicle fixed
and pitching
maneuvers,
environment
were
of the body and four control surfaces for alloy convenience construction sheets stabilized
movable
of assembly
of semi-monocoque
corrugated
3-3
t
TYPICAL ELECTRICAL INSTALLATION q i
;:_,
_'l _' | | _1
Ii
VEHIC LE FOREBODY'-_ _.i _ _ _'_"_ ,_ 'P'J_
,!
_--"J_'_--EQUIPMENT
EXTERNAL
LONGERON (6)_
IL]
II' !i;
' ,:
j
STATION H _ 227.0
"--
VEHICLE
AFTERBODY
RECRUT"OTOR<')--_i
ADAPTER (6).__ _-_t _. ._ =: _) _ _ ;!,=_p" STATION 227.0 /SPLICE BHD. (AFTERBODY)
suPPORT _ I TUBE(6)
\
__1 FIN RIB (TYPICAL) _ J FIN SKIN
_,
FIN (4)
C'-6062-112
Figure
3-2.
Launch
Vehicle
Structural
Arrangement,
Fixed
Fin
(Version
12-50)
3-4
0
SUPPORT HOOK(2) I_------/_ TYPICAL ELECTRICAL INSTALLATION VEHICLE STATION INTERFACE 0 EQUIP ACCESS M ENT DOOR AREA (3) SKIN (TYPICAL)
FRAME,_ f
t1111 ,,,,,
VEHICLE
FOREBOOY
-....
STATION 34.75 SUPPORT BULKHEAD
b_ b_ b_
MOTOR
-=_-BODY
FRAME (TYPICAL)
b_
b_ b_
b_
i
I
I
, r i i i i i i
_AC_T04) R ELEVON
MOTOR
7_ L_
ALGOL MOTOR (4)_._
L Z II_
,"_z_,_L
VEHICLE BODY-ATTITUDE
ELEVON ,,,
CONTROL
.------
RECRUIT
MOTOR
(5)
=.2
STATION SPLICE 227.0 BHD.
(AFTERBODY)
0
AIR DOOR
SUPORTTOB
CONDITIONING (2). \'_. II1_ I_IIIIITII CENTER SUPPORT TUBE _""_' STATION MAIN 347.0 VEHICLE BULKHEAD
_OUTER MOTO.
\ _._.|HIlII,',I
(TYPICA__
FIN
(4) C-6062-113
Figure
3-3.
Launch i2-5i)
Vehicle
Structural
Arrangement,
Controllable
Fin (Version
3-5
The while
afterbody
contained bay
and the fin mounting end of the and the The interface afterbody bulkhead main 3-4) 3-5. The interface
structure
to stabilize
the upper
forebody was
was
frame
approximately
description
Description
Manuals
GD/C-63-034A
and GD/C-64-356.
fin assemblies whether The fins and was 3-6. of the controllable
were fixed
equi-spaced or controllable,
the
afterbody; feet
see
Figure
50 square feet
in area: Station
fin measured from swept Vehicle back control tests, chiefly vehicle. edges
measured
extended
262 to Vehicle relative were during structural on each the side there
operated
for as
a hydrogen program,
in Figure of the
performed
conducted proposed
Tests, were
varying loaded in
lengths body
of 24-inch panels.
and of
to establish A photo
allowable
representative
short-column Long-Column buckling The ultimate A photo vehicle basic This however, loads
Compression body
established by tests
to failure
in compresin Figure
fixture
its first
can be attributed
encompassed Throughout
requirements.
as growth capability
the Little
Joe
3-6
SUPPORT
BULKHEAD
STATION
34.75
SERRATED
PLATE
ARM HOOK (2) HOOK SUPPORT DETAILS MOTOR SUPPORT PAD DETAILS
FIN
_.._
FIN FWD
_'_.J-_J,
_'J_"
,v
FIN
.. SUPPORT BULKHEAD STATION 278.80
,,
" SUPPORT BULKHEAD FIN AFT STATION ATTACH 347.0 FITTINGS (41
C-6062-114
Figure
3-4.
Structural
Design
Details
3-7
NAS625-14
PAYLOAD / /
STRUCTURE
AN960-516 WASHER
BALLAST
C-.6062-115
Figure 3-8
3-5.
LJ-II/Apollo
Interface
Structure
RCS MOTORS ( 8 )
VIEW LOOKING UP
CONTROL SUBSYSTEM ( 4 ) C-6062-116
Figure 3-6.
Fin Layout
Figure 3-7.
C-6062-117
3- 9
C-6062 18 -1
FAgure3-8. 3-10
fin. e.g., C.
The fin attachment fittings The extent of such increase maneuvering PROPULSION The propulsion to provide for Two each sizes thrust. mission systems rocket motors. specific are for loads.
on the afterbody can accommodate the loads of a larger depends on the particular mission requirements;
the
Little
Joe
Motor
thrust shown
supplied
The
larger
Algols, sustaining
manufactured
by Aerojet-General
Corporation,
primary, powered
manufactured An electrically
by Thiokol
provided high-boost-thrust for all motors initiated thrust. MOTORS Algol configurations nozzle; the Algol were ID, are of the
basic
used
on the in Figure
the
Algol The
II had exit
a fixed was
nozzle.
of these
given motor
and the
nozzle assembly and the and reflected heat. In preparation borescoped entire temperature When flanges was enabled The were see first Algol Staging period, Figure stage motors was to verify was was installed thrust laterally assembly for
installation integrity
each for
was igniter
carefully was
the
pressurized
maintained in the
between launch
motors which
on the
bulkhead
by adjustable
expansion
three on the
required
ignited
3-11. was
requiring second
to give
on the
in operation
and
performance
all five
successfully
accomplished
on Vehicle
3-11
FIN I FIN II _
+Z
/._
FIN I
50-1
51-1
IV
+_ALGOL
ID, MOD I
50-2
+Z
NOT FLOWN
+z
1ST STAGE ALGOLS Z = YAW AXIS RECRUITS 2ND STAGE IST STAGE
c -6062 -119
Figure
3-9.
Motor
Configuration
- View
Looking
Up
3-12
THE
IGNITER
ASSEMBLY,
INSTALLED OF
IN THE FORWARD A THERMOCOUPLE INSTALLATION ON THE MOTOR PROVIDED A MEANS OF MEASURING PROPELLANT GRAIN TEMPERATURE. COUPLES WERE TWO THERMOLOCATED ON THE
END OR DOME
THE MOTOR, WAS APPROXIMATELY 31 INCHES LONG AND WEIGHED APPROXIMATELY 35 POUNDS. THE IGNITER WAS ACTUATED BY TWO ELECTRIC INITIATORS.
INSIDE BORE OF THE GRAIN AND TWO OTHERS WERE ATTACHED TO THE OUTSIDE OF THE CHAMBER. THE THERMOCOUPLE LEADS TERMINATED IN A CONNECTOR ATTACHED TO THE OUTSIDE OF THE NOZZLE.
THE CHAMBER ASSEMBLY CONSISTED OF A WELDED CYLINDRICAL CASE FABRICATED OF HEATTREATED STEEL A CASE-BONDED AND LOADED WITH POLYURETHANE
PROPELLANT GRAIN. THE PROPELLANT WEIGHED APPROXIMATELY 19, ODD POUNDS AND HAD AN INTERNAL CONFIGURATION RESEMBLING AN EIGHT POINT STAR.
THE ALGOL ID, MOD II NOZZLE ASSEMBLY CONSISTED OF A STEEL HOUSING WITH A GRAPHITE INSERT THE ASSEMBLED MOTOR WAS 358 INCHES LONG, 40 INCHES IN DIAMETER, AND WEIGHED APPROXIMATELY 22,000 POUNDS. THE MOTOR CHARACTERISTICS AT SEA LEVEL AND 70F PROPELLANT GRAIN TEMPERATURE FOLLOWS: TOTAL AVERAGE ARE AS AT THE THROAT. THE MAXIMUM DIAMETER OF THE NOZZLE WAS APPROXIMATELY 32 INCHES, WHICH PROVIDED AN EXPANSION RATIO OF 4.64:1. THE ALGOL ID, MOTORS WERE MOD I ROCKET BASICALLY IDENT-
ICAL TO THE MOD II, EXCEPT THAT THE EXHAUST NOZZLE WAS A CANTED TYPE WHEREIN THE EXHAUST DISCHARGE ANGLE COULD BE VARIED BY MEANS FROM 0 TO 14 DEGREES OF A MICROMETER AS[
SEMBLY ADJUSTMENT. THE MAXIMUM DIAMETER AND EXPANSION RATIO WAS IDENTICAL TO THE FIXED NOZZLE.
J c-6o62-12o
Figure
3-10.
Algol
Motor
Details 3-13
120
lO0
%
PERFORMANCE BOUNDARIES FOR ALL LITTLE JOE II MISSIONS
8O
t_ en -1 O O O
60
b-
4O
2O
i0
20
30 TIME - SECONDS
40
50
60
70 C-6O62-121
Figure
3-11.
Algol
Thrust
RECRUIT Recruit motor stalled mounted figuration Prior The adapter properly maintained temperature The enabled thrust motors
MOTORS motors were used in the l_mnch vehicle to augment lift-off thrust. The
for Vehicle 12-50-1 nozzle. The motors dual initiators; 3-12. motor and the + 100 F, the in Figure each were angle,
with
to installation, and nozzle cant the between than Recruit one, installed
and
partially integrity
checked
indexed
temperature sensitive
although
in the enabled
launch
two or three
Recruits motor
bulkhead. in any
installation and
Recruit
or Algol
attachment nozzle
installation,
assembled
3-14
A PYROGEN-TYPE IGNITER WAS INSTALLED TO THE IGNITER PORT ON THE MOTOR HEAD. THE IGNITER WAS INITIATED BY TWO MODIFIED APOLLO STANDARD INITIATORS. THE PYROTECHNIC TRAIN CONSISTED OF THE TWO INITIATORS, THREE GRAMS OF BORON PELLETS AND 0.8 POUNDS OF PROPELLANT.
THE MOTOR CASE ASSEMBLY CONSISTED OF A WELDED, CYLINDRICAL CHAMBER FABRICATED OF 4130 HEAT-TREATED STEEL AND LOADED WITH A CASE-BONDED SOLID PROPELLANT. THE PROPELLANT HAD A FIVE-POINT STAR INTERNAL CONFIGURATION.
/
uI
THE CANTED ADAPTER, MADE OF STEEL, WAS INSTALLED BETWEEN THE CASE AND NOZZLE, BUT WAS ONLY SUPPLIED WITH THE MOTOR WHEN ANGULAR THRUST WAS REQUIRED. THE UNIT WAS APPROXIMATELY 3.5 INCHES LONG, 8 INCHES IN DIAMETER, WEIGHED APPROXIMATELY 9 POUNDS AND HAD A 6-1/2-DEGREE CANT ANGLE FOR DEFLECTION OF THE EXHAUST GAS F LOW.
"",-4
THE EXHAUST NOZZLE ASSEMBLY WAS A MACHINED STEEL ASSEMBLY INCORPORATING A GRAPHITE THROAT. THE NOZZLE WAS APPROXIMATELY 11 INCHES LONG, 9 INCH_'S IN DIAMETER AND WEIGHED APPROXIMATELY 20 POUNDS. THE EXPANSION RATIO WAS 4.28 TO 1. THE ASSEMBLED MOTOR WAS 104.8 INCHES LONG, 9 INCHES IN DIAMETER AND WEIGHED 367 POUNDS. THE MOTORS WERE RATED AS FOLLOWS WHEN FIRED AT 60F NOMINAL PROPELLANT GRAIN TEMPERATURE: THE NOZZLE CLOSURE, MADE OF STYROFOAM HAD A CONICAL SHAPE, AND WAS INSTALLED IN THE NOZZLE EXIT CONE FOR PROTECTION OF THE MOTOR. AVERAGE THRUST POUNDS TOTAL IMPULSE, LBF-SEC BURNING TIME, SECONDS PROPELLANT SPECIFIC IMPULSE, LB-SEC/LB PROPELLANT WEIGHT, POUNDS I AVERAGE PRESSURE, PSI = 37,100 = 57,000 = 1.536 = 213.9 = 267 =1748
C-6062-122
Figure
3-12.
Recruit
Motor
Details
3-15
Recruit provided
motors
satisfactorily source
on four see
a reliable
for lift-off;
in Vehicle
IGNITION The ignitionsubsystem arming initiatedAlgol and Recruit motor thrust. For single-stage
operation, isolated ignitionbatteries in the power building supplied dc current via the and control relays to dual head-mounted pyrotechnic initiatorson each motor; see Figure 3-14. Ignitionbattery voltage was adjusted to supply at least five amperes circuit. For two-stage operation, first-stage current current was supplied by
was supplied from the power building batteries. Second-stage two isolated ignitionbatteries in the vehicle; see Figure 3-15. The development of the ignition subsystem
gained on earlier solid-propellant propulsion systems. isolated from allother voltage sources. separated from other circuits and protected as much
Firing lines were physically and electrically as possible from radiation by shielding, and physical
use of separate metal junction boxes, conduit, magnetic cables in the facility. Multiple firing lines were highly reliable operation.
separation; twisted-shielded wire pairs were used in the vehicle and double-shielded routed to each motor to maintain a A remote arming and final
In the vehicle, separate firing lines were routed to each of building. Firing line resistance measurements
the four bridgewire circuits in the two initiatorsin each motor. box was located in the power arming could be made with fullpersonnel protection.
4O
3O
U_ rn ..J O O
20
I p-
tv -t-
l0
-0.4
0.4
0.8
1.2 $EC
Figure 3-16
3-13.
Recruit
Thrust
ARMING AND FIRING CONTROLS, TIMER COUNT AND MONITORING OF ALL RELAYS WAS ACCOMPLISHED ON THE IGNITION PANEL.
THE CONTROL ASSEMBLY CONTAINED ARMING AND FIRING RELAYS. AT LEAST TWO RELAY FAILURES WERE REQUIRED TO CAUSE A MALFUNCTION OF IGNITION. THE LAUNCH SEQUENCE TIMER WAS MANUALLY STARTED AT T-16 SECONDS, THEN AUTOMATIC STEPPING OCCURRED ONCE EACH SECOND. PRELAUNCH FUNCTIONS WERE ISOLATED FROM IGNITION CONTROL.
| | _, | | | "
HEAVY DUTY TRUCK BATTERASSEMBLY CONTROL BATT. IGN. IES SUPPLIED UP TO 150 AMPERES AT 34 VOLTS DC FOR IGNITION. A BATTERY CHARGER MAINTAINED THE BATTERY VOLTAGE.
TI
ER
I /
I ARM'NG I
FINAL ARMING WAS ACCOMPUSHED IN THE SAFETY OF | THE POWER BUILDING. PRIOR TO ARMING, ALL INITIATORS f WERE SHORTED AT THIS | POINT. J
BUILDING
ISOLATED,
SHIELDED
ELEC-
I I I I I
I
TWO BRIDGEWIRES IN EACH OF THE TWO INITIATORS IN EACH MOTOR PROVIDED FOUR SEPARATE FIRING PATHS FOR EVERY MOTOR (12-50-2 & ON).
C-6062-124
Figure
3-14.
Block
Diagram
- Ignition
System
- Single
Stage
3-17
ALL GROUND
CON-
TROLS WERE SIMILAR | TO THOSE USED FOR SINGLE STAGE FIRING. I_ SEQUENCE TIMERS I _ WERE IN THE VEHICLE.J I
I
' STSTAGE CONTROL _--
Ii =,.0 I t
POWER BLDG. DUEl VEHICLECJRCUI I R_ PREVENTED LOSS c)R PREMATURE IGNllION DUE TO ANY SINGLE FAILURE.
_I
'I
MOTOR DRIVEN
"_
SWITCHES PROVIDED | POSITIVE CONTROL | FOR SECOND STAGE ARMING. BOTH STAGES| WERE ARMED PRIOR | TO LIFT-OFF. j
-0,i, _J _,,orAo_ !A s /
/ CONTROL I'-
#1 TIMER
TIMER
#1
CONTROL ___2NOII STAGE #2 , ,.._ 15 A/H, 28 BATTERIES SUPPLIED POWER FOR SECOND STAGE IGNITION.
C-6062-125
Figure 3-18
3-15.
Block
Diagram,
Two-Stage
Ignition
System
Controls and monitors for the ignition circuits were in the blockhouse console, The controls enabled arming of the firing lines and control of the launch sequence timer which initiated firing. Console lights were used to monitor all relays and timer operation. The timer, arming relays, and firing relays were located in a power building equipment rack. A launch sequence timer was developed to perform the primary function of ignition and the secondary function of sequencing events required just prior to ignition; see Figure 3-16. The timer employed a temperature-controlled, solid state oscillator to trigger rotary stepping switches. One- second pulses were provided by the timer for ignition, pre-lift-off functions and console lights. Output pulse times for the various functions could be changed by selection of external connections. Throughout the program, the timer was started sixteen seconds prior to lift-off (T - 16) and provided three-second pulses for ignition. The timer design was improved gradually throughout the program. The initial model w a s installed in the power building and was qualified to GSE requirements. Qualification tests for flight usage resulted in improved sealing techniques and addition of shock mounts for vehicle usage. With the introduction of new EM1 requirements, transient suppression circuitry was added. This version was flown in Vehicle 12-51-1 as a backup for RF command. Additional circuitry was added to prevent early, o r fast, timing. This final version was used for ignition in Vehicles 12-51-2 and 12-51-3.
C-6062-126
Figure 3-16.
- Internal Assembly
3- 19
made recruit
to the
ignition Console
subsystem were changed stop was would two-stage ignition first circuits stage
the program. 3-17) in the dual. and a HOLD event of a in the and 12-51-1,
countdown
propulsion;
stages;
second-stage
In the block-
were
on Vehicles
configuration. affected and exacting vehicles. resistance task. readings The ignition
Checkout subsystem D.
problems
verification satisfactorily
of circuits
on all five
CONTROL control flight system maintained the the pitch launch attitude attitude for of the vehicle flight in yaw trajec-
and programmed
the desired
DESIGN General - The system was composed control subsystem, monitor components, and subassemblies; of an autopilot subsystem, associated power, see Figure 3-18. an aerodynamic control and
(Figure 3-19) sensed vehicle motion and provided a pitch command error signals from the see and reaction control subsystems;
autopilot provided control to the aerodynamic Figure 3-20. The aerodynamic of the movable control subsystem
surfaces (elevons) on the four fins; see Figure 3-21. supplemented the aerodynamic the aerodynamic control subsystem, forces were low
providing attitudecontrol for the launch vehicle during the initial low-velocity phase of flightand during very-high-altitude flight,where or nonexistent; see Figure 3-22. subsystem The general arrangement of the reaction control with each module located
within fairlngs at the root of each fin. Operating controls and monitors were located at the blockhouse dual console; see Figure 3-23. All attitudecontrol functions were located on the left console.
Parameters
- The obtainable errors in the vehicle flighttrajectory can be and The maximum drift rates for the three axes were as
attributed dtrectly to the glmbal drift rate of the free gyros used for pitch, yaw, roll attitudeinformation. follows: pitch 0.50 /min; yaw 0.09 /min; and roll 0.50 /min.
3-20
t
I
VEHICLE
BATT. I
EQUIP. RACK TIMER & CONTROLS
I I
11i
12-50-1
II
ARM BOX (REF)
I
I I
I I I
12-50-2
I
Figure 3-17. Recruit Initiation
C-b002-127
3-21
FIN II
A
LOGIC AND CONTROL AMPLIFIER GYRO CONTROL RELAY OX
/
SIGNAL NOISE/ /
_,
/ /MAST
LAUNCHER (REF)
SIGNALNOIS
t +Z AXIS (YAW)
/
RATE GYRO PACKAGE
PITCH PROGRAMMER
/ / -Z AXIS
/ \ +Y AXIS (PITCH)
VIEW
LOOKING AFT
VVERTER (REF)
FIN IV
I
VEHICLE STATION 0.00 ---.-q-VEHIC LE STATION 34.75
\
RCS VACUUM DRY REACTION CONTROL SYSTEM FAIRING (4) ACS HYDRAULIC SERVICE PANEL RCS GN2 FILL QUICK-DISCONNECT S PANEL (4) (ACCUMU LATOR-HYD FILTER) QUICK-DISCONNECT STATION 227.0
FIN Ill
FIN IV
FIN I C--6062-128
Figure 3-22
3-18.
Attitude
Control
Z 0 m I--
o
UJ_J
o
rsl
r/1 r_
<
I
m=l
o 0
I o
e,-I
o
<<w_o_
_0_
_
<J
_
_>_?<
=_=
<_
__
_o_
3-23
THE AERODYNAMIC SERVO LOOP CONSISTED OF THE AERODYNAMIC CONTROL SUBSYSTEM AND THE POWER AMPLIFIER STAGE IN THE LOGIC AND CONTROL AMPLIFIER. SINCE ALL OF THE SIGNAL ERROR SHAPING WAS ACCOMPLISHED PRIOR TO THIS POINT IN THE SYSTEM, ALL FOUR OF THE SERVO LOOPS WERE IDENTICAL. /
r---
I I
I I I
FIN
I / /
/
I I :
I
ACTUATOR 11.25/SEC/ma SERVO VALVEt
I I \ \ I I
I
I
I I I
SURFACE I
I I
I I I I
POTENTIOMETER FEEDBACK .388 VOLTS/DEG
I I
I
I
I
_i _
/
I
I I I I \ I / I I I
I
1 OVERALL LOOP GAIN - 20/SEC
REACTION MOTORS
\
REACTION CONTROL THRESHOLD - THE LOGIC AND CONTROL AMPLIFIER WAS DESIGNED WITH THRESHOLD OR DEADBAND CIRCUITS FOR ACTUATING THE REACTION CONTROL MOTORS AS A FUNCTION OF COMMAND ERROR SIGNAL AMPLITUDE. EACH OF THE FOUR COMMAND ERROR SIGNALS WAS FED TO A SEPARATE PAIR OF AMPLIFIER STAGES WHICH OPERATED AS POLARITYSENSITIVE SWITCHES. WHEN THE COMMAND SIGNAL AMPLITUDE WAS EQUIVALENT TO 0.7 DEGREE OF SURFACE, ONE OF THE POLARITY-SENSITIVE ELECTRONIC SWITCHES WAS TRIGGERED, DEPENDING UPON SIGNAL POLARITY. THE SWITCHES CLOSED INDIVIDUAL RELAY CONTACTS WHICH THEN APPLIED 2B-VOLT DC POWER FROM THE REACTION CONTROL TIMING BUS TO THE APPROPRIATE MOTOR SOLENOIDS. REACTION CONTROL ON-OFF TIMING - THE 28-VOLT DC REACTION CONTROL TIMING BUS OBTAINED ITS POWER FROM THE VEHICLE POWER BUS. THE ON-OFF TIMING OF THE BUS WAS ACCOMPLISHED THROUGH THE USE OF TIME DELAY RELAYS. ON THE TWO VEHICLES IN WHICH THE REACTION CONTROL SUBSYSTEM WAS USED (VEHICLES 12-51-1 AND -2), THE BUS WAS ACTIVATED PRIOR TO LIFT-OFF, DE-ACTIVATED AND AGAIN ACTIVATED DURING THE COURSE OF THE FLIGHT.
C-6062=130
Figure 3-24
3-20.
Autopilot
Command
Diagram
LEGEND ==:,= HIGH PRESSURE GN 2 am= REGULATED PRESSURE GN2 HYDRAULIC CONTROL FLOW HYDRAULIC DISCHARGE "" SYSTEM FLOW .... ELECTRICAL CIRCUIT
FILLER CHECK VALVE " ......................... BLEED VALVE :[ RELIEF VALVE PRESS. SWITCH
] ""=,.-_._
AIR-OIL (GN 2) BOTTLE PSI) 400 CU. IN. FILLER CHECK VALVE BLEED VALVE RELIEF VALVE PRESS. SWITCH FILTER HYDRAULIC FILLER /'_ IT R OGEN" CHECK VALVES;VENT_N ////;"ii IRE REGULATOR (3000 SERVICE CHECK MANIFOLD_ _ll_
: =-------------_-..-------:_:
(5000
' i
PSI)
CONTROL
ACCUMULATOR PRESSURE
J_
CONTROL SUBSYSTEM WAS POWERED (GN 2) BY A FIXED CHARGE ACCUMULATOR HYDRAULIC BY GASEOUS NITROGEN
THE HYDRAULIC ACTUATOR ASSEMBLY CONSISTED OF A CONTROL SURFACE ACTUATING CYLINDER, SPECIFICALLY TAILORED FOR THE VEHICLE, AND A CONVENTIONAL SERVO VALVE AND FEEDBACK POTENTIOMETER. THE AERODYNAMIC SYSTEM
PRESSURIZED
THE SYSTEM HELD THE HYDRAULIC FLUID AND HIGH PRESSURE GAS FOR EXTENDED PERIODS OF TIME PRIOR TO ACTIVATION; HOWEVER, ONCE THE SUPPLY WAS ACTIVATED, HOLDING TIME WAS LIMITED. DURING AN ACTUAL LAUNCH OPERATION, THE SUPPLY WAS ACTIVATED DURING THE COUNTDOWN AT T-B SECONDS BY THE LAUNCH SEQUENCE TIMER. THE PORTION OF THE SCHEMATIC NOT IN PHANTOM REPRESENTS ONE-HALF OF THE TOTAL SYSTEM SUPPLY AND FORMED A COMPLETE SYSTEM. THIS CONFIGURATION WAS ORIGINAL DESIGN ANDWAS
USED
IN VEHICLE 12-51=1; DUE TO THE STRUCTURAL BENDING PROBLEM ENCOUNTERED DURING THAT MISSION, THE HYDRAULIC CAPACITY IN LATER VEHICLES WAS DOUBLED BY ADDING AN IDENTICAL SYSTEM IN PARALLEL TO THE ORIGINAL SYSTEM. THE ADDED COMPONENTS WERE PALLET-MOUNTED AND LOCATED ON THE AFT BODY SECTION ABOVE THE FIN LEADING EDGE, IN THE RCS FAIRINGS.
C-6062-131
Figure
3-21.
Aerodynamic
Control
Subsystem
3-25
CW AND
CCW ASSEMBLY
TYPICAL
FOR EACH
12-51
FIN
17 /
,,20
,_ 19
.-. j--_
,11 i0 12 13
386
CU. IN.
GN2
STORAGE
BOTTLE
GN2 PRESSURE SWITCH GN2 FILLER QUICK DISCONNECT GN 2 PRESS. CONTROL VALVE AND VENT GN2 REG. PRESS. TRANSDUCER LOW-PRESSURE N2 RUPTURE DISK 850 CO. IN. (USABLE FUEL) TANKS (40 LB. USABLE H202) CHAMBER PRESSURE TRANSDUCER FUEL-FILL QUICK-DISCONNECT H202 H202 FUEL OVERFLOW: OVERFLOW: HI-PRESSURE RELIEF VALVE (GSE) QUICK-DISCONNECT RELIEF VALVE (4)
OVERBD. THRUST
CHAMBER
VALVE (GSE)
HIGH-PRESS. N2 RELIEF VALVE FUEL PRESSURE TRANSDUCER VACUUM DRYING SERVICE PORT ELECTRICAL SEQUENCER
21. 22.
TION SIGNAL ELECTRICAL HARNESS FROM AUTOPILOT FOR MOTOR OPERATION BLADDER (4)
LEGEND: i_r"r'r_ I_'--'_[_ HIGH PRESSURE GN2 REGULATED PRESSURE SERVO PRESSURE GN 2 H202 OVERFLOW 90'/oH202 GN 2
C-6062-132-1
Figure
3-22.
Reaction
Control
Subsystem
(Sheet
1 of 2)
3-26
OPERATION: THE NITROGEN STORAGE TANKS WERE CHARGED TO 3600PSIG. THE FUEL TANKS WERE THEN SERVICED WITH 90/ STRENGTH HYDROGEN-PEROXIDE UNTIL COMPLETELY FILLED WITH LIQUID; THEN 5PERCENT WITHDRAWN TO ASSURE ADEQUATE ULLAGE, THE ULLAGE PRESSURE WAS MONITORED TO 08SERVE THE STABILITY OF THE FUEL. THE SYSTEM WAS MADE OPERATIONAL BY ENERGIZING THE PRESSURE CONTROL VALVE (PCV) TO PRESSURIZE THE SYSTEM AT T-4 SECONDS DURING COUNTDOWN. THIS PUT REGULATED NITROGEN PRESSURE BEHIND THE BLADDERS IN THE FUEL TANKS AND INCREASED THE FUEL PRESSURE TO THE OPERATIONAL LEVEL. FUEL PRESSURE WAS MONITORED ON THE LAUNCH CONSOLE. THE REACTION MOTORS WERE FIRED BY ELECTRICAL SIGNALS TO THE MOTOR VALVES; THRUST LEVEL AND RESPONSE WAS MEASURED BY RECORDING MOTOR CHAMBER PRESSURE ON A VISICORDER FOR RAPID EVALUATION OF PERFORMANCE_ (SEE LANDLINES). EACH REACTION MODULE CONTAINED AN INDEPENDENT MONOPROPELLANT SYSTEM CONSISTING OF TWO NEAR-IDENTICAL SUPPLEMENTARY ASSEMBLIES. THE UNITIZED ASSEMBLY ON EACH FIN HAD A 386-CUBIC-INCH NITROGEN STORAGE TANK, TWO 40-POUND HYDROGEN-PEROXIDE POSITIVE-EXPULSION FUEL TANKS AND A REACTION MOTOR POSITIONED TO PROVIDE A 600POUND THRUST VECTOR NORMAL TO THE FIN SURFACE. APRESSURE REGULATOR, RELIEF VALVES, NITROGEN AND HYDROGEN-PEROXIDE SERVICING PORTS WERE DIVIDED BETWEEN THE ASSEMBLIES AND HAD INTERCONNECTING HOSES, TO FORM COMPLETELY INTEGRATED MONOPROPELLANT REACTION THRUST SUBSYSTEM. (SEE SUBSYSTEM SPECIFICATION 12-02603 FOR DETAILS.)
H202 DECOMPOSITION NICKEL-SILVER PREHEAT SIGNAL HARNESS FROM AUTOPILOT OR SCROLL SCREEN CATALYST CATALYST
CHAMBER
(TYPICAL)
C-0062-132 -2
Figure
3-22.
Reaction
Control
Subsystem
(Sheet
2 of 2) 3-27
VIOAR
510
M_W_[ . MONITOR RCS RATE (4) GYRO SPIN l (3)L ) I'_ . RATEGYRO FOR ALL _ .
CAUtmATE M(*m
III
RE-
,v
ACTIVATION HYDRAULIC
NITROGEN
PRESSURE
MONITOR
RCS CONTROL
HYDRAULIC
CONTROL
o,
_E_u.,zt
o, o, 'L_ o, C'
PRESSURIZE VENT
AND
PREPULSE ACTIVATE
YAWATTITUDEGYROH'-"-
\R
.... i//
\_
..... I//
\\
........ "//
\\
.....
"//
_'\
......
'_"
_IISIGNALS(4)
"
......
,.........
, ,Pos, ,o
I ....
:::
<.o
ATTITUDE
GYROS.
......
['_)"_'_.
,,F-';;*"-lo...,(_ ':'_'_'-I
....
"I PROGRAMMER
"_TORQUE GIMBALS
ATTITUDE
GYRO
C-6062-133
Figure
3-23.
Blockhouse
Console
- Attitude
Control
System
3-28
the up
capability with an
of pitching exponential
the
vehicle
over having
at
a specific
rate
and and
command
a preset
amplitude
see
Major aerodynamic DIB 12- I. 014: Elevon Surface Hinge Regulated Nitrogen Reaction deflection rate moment (per
control
subsystem
limits
were
as
follows;
for
further
details
+24
degrees. (nominal).
on
Figure
3-24.
A timer-controlled reaction through were time; period extent relays listed control various energized, the second flight. the employed 3-25, subsystem relays one relay
bus
which
programmed from When and the the launch the then bus and 12-51-2 which two
activated
a motor-driven relays after closed a delay used made of two. with for
opened during -2
powered
circuits was
Vehicles
12-51-1
redundant The
instead along
also for
Figure
variations
parameters
vehicle.
SPEC LIMITS THRUST: - SEA LEVEL ......... - lOO,O00 FT. ALT ....... (HOT): - FROM VALVE SIGNAL APPLIED: - TO 10% RATED THRUST - TO 90% RATED THRUST - FROM VALVE SIGNAL REMOVED: - TO 90% RATED THRUST - TO 10% RATED THRUST SPECIFIC IMPULSE (Isp): TOTAL IMPULSE (IT) (PER FIN): EXPENDABLE FUEL (PER FIN): SYSTEM WEIGHT: FUEL: PRESSURIZATION GAS: - DRY - WET ........... ....... - STEADY STATE - CYCLIC ..........
RESPONSE
75 MILLISECONDS 85 MILLISECONDS
MAX. MAX.
MAX. MAX.
.......
20,800 LB-SECS (@ 100,000 FT. ALT.) 160 POUNDS 175 POUNDS (PER FIN) 350 POUNDS (PER FIN) 90% HYDROGEN PEROXIDE (MIL-H-16005C) GASEOUS NITROGEN (MIL-P-27401) AT 3600 PSIG
.....
C-6062-134
Figure
3-24.
RCS
Parameters
3-29
0-1
(.3
q.) (1)
,-4
(..J
o o r_
q,)
.<
C',,1 I CO q3
_,,,=_
3-30
DEVELOPMENT Since tion meet was the Although the most launch of the vehicle concepts needs was a new design, the designed much attitude of the control this hardware system specific was configuraairframe. to developed
assemblage
of components were standard, of the program. and were package firing, pick-off required
to control
make
however,
changes and
design
the
or consent partial
of a redesign
microsyn
the package assembly. to the Vehicle 12-51-1 Notch filters packages. trolled hydraulic frequency the vehicle during any due to lack other vehicle, systems of the body Filters than During
was
designed
without
the
use
of signal in the attitude when 22 cps), occurred system, gyro conthe with resonant
that
activated. with
(approximately stand
the feedback
This
phenomena
fin test
an autopilot
developed
for the
system
by Convair
had
characteristics:
tw
\
FREQ c-6062-136
The relationship Vehicle correct the below caused respond; the Apollo
in all
attitude
the was
and attitude to be satisfactory had the cps). rate trajectory been The in-flight
configuration
mass escape
elevon
movement.
of elevon was
not impaired.
3-31
were
depleted
to the this
extent bending
maneuver
at the
confin to on
a large
amount
To overcome low-pass
notch-type attenuaoverall
and attitude
amplitude
roll-offs
and relatively
characteristics. + second-order)
transfer
the combined
is as follows:
AIR
FREQ
C-6062-137
E
O
E.
1
notch however,
filter
was
flown records
termination
did not allow on control of both filter package potting was The
of filter
analysis being
frequency
surface
commands. were using large The were packaging accomplished epoxy were with design and
production
both
inductors potted
be changed
in qualification
Logic and Control amplifier circuits was control amplifier integrating, PP 65 and amplifier gain program, that could
Amplifier - The design and development accomplished by Convair. In the early was made of the commercial market for the task of amplification,
of the logic and control phases of the attitude for a dc operational subtraction, amplifiers A breadboard such as
a survey be used
etc. From the results of the survey, Philbrick PP 66 were selected as the most suitable for the package was built and tested to determine threshold,
adjustment Subsequent
stand
fin and
subsystem system
to perform and
and closed
ZZC-63-011 Integrated,
Finally, attitude
integrated
hardware
in integrated
System,
Tests,
GD/C-64-332.
the
The unit,
production packaging, and the qualification manufacturer. was these seven that to the individual the unit
design of the production testing were accomplished One major test stages design problem not meet the encountered desired would
15-volt dc power by C. E.S. Inc., during null module drift was and flown this
subjected
qualification amplifier
of a 40 F to summing was
160 F environment.
requirements,
a temperature-controlled configuration
temperature 12-51-1 and During the the stability command in the types should The loop system. and Prior package while that the that were all with solder The expanding components board number the this location see loose. electronic assembly RTV numerous frequency It was stages various newer back stages. a first-order closed of the stages limitations existing
of 150 F. This original -2; see Figure 3-26. the checkout of Vehicle package when the
on Vehicles
12-51-3 was
with on
of the error
- approximately determined
amplifier
vehicle
amplifier package were of loading. Collaboration had a higher around gain each were a break was stages also in those be added frequency function servo
susceptible to self-oscillation with Philbrick Research than those originally stages used, amplifier power to ensure capacitive stage (3.2 affect cps), the feedback 1300 was the
amplifiers amplifier
capacitive All
feed-
packages with
response
frequency
25 cps. overall
response amplifier The change response flight being was of the 3-27. joints module was
20 radians/sec capacitive
characteristics
to approximately while command signal. was module circuit employed the aluminum end with assembly components. action each completely units, bench-checking error including inside from boards
the
it was
signals
were
intermittent
temperature-controlled in the
module;
solder The
contained The
two boards.
installed
in a rectangular sealed on each with caused potting feedback these in the sandwich
of the joint
summing
spanned
failures
failures and
of the thermal
due
to
in all units
rebuilt the
modification;
however,
3-33
*-y:
C-6062-138
Figure 3-26.
Figure 3-27.
3- 34
had been
while allow the the
at an elevated modules material separate cycle unit was In this had from
temperature cured
been the
at room at room
to contract configuration
relatively
abnormal
and repackaged. instead area, isolators of the of the the 75F in the isolators, potting
to alleviate
expansion
excursions
to which
constructed
and tested
on vibration
effort,
a new
packaging
design
was
initiated
for
the
temperatureof
controlled module. The new design provided the resistors and capacitors into two identical modules, operational encapsulated amplifiers. circuit in epoxy, The board, were similar two subassemblies installed
for the subassembly three-dimensional in construction and in the the same other and
of practically all modules. These size to the were and then PP 65 components tube,
mounted on a single foam potted. A module last for for vehicle the build-up future use. Reaction subsystem Applicable costs and built launch.
rectangular
to the
was
enough
to support and
the stored
However,
subassemblies fabricated
required
of three
Little
Joe
RCS produced system tank design Little motor were see Figure
to minimize
development
gain
the
existing
large
Minimum changes were made to meet the environment requirements. The reaction higher thrust requirement. to complete All components the system; checkout hoses
Joe H envelope, nozzle was remounted 3-28. on two This at the factory
interconnecting
concept permitted complete and simplified installation The simultaneous components of 2 cps The level complete, while Little Joe engine of the cps,
system operation and on the launch vehicle. environment a more 10 minutes was vibrated requalified for was severe the and
by the vendor
to the Joe
Scout
except
that
the
to 2000 firing.
to 30-(]
on each
assembled
successfully
3-35
I__
RCS FAIRING
ACS GN2 VENT O O ACSGN2 F'LL ACS HYDRAULIC _TI II "-"-" _ ACS GN2 F,LTER_W_,_/_ PALLET_ "_1 / --_ _'_l _'-' _..._ !_ I _ _CS GN2_ ACS ACS GN 2 PRESSURE GN2 ANIFOLD IJ I___..._ I_, _ _'-_1_ _ {_ _ I, BOTTLE PALLET - FiN _. _ J ,L_ J ACCUMULAToRACS A'R-OIL ACS GN2 RELIEF VALVE
SWITCH
I_.L_
_ _r_
TUBEBRACKET
RCS
QUICK-DISCONNECT
GN2
H202 BOTTLE
H202
SUPPLY HOSE_
HYDRAULIC
PRESSURE
SWITCH
- FIN
INTERCONNECT
FUEL MANIFOLD FIN RCS CONTROL ., ;_ RCS MOTOR '/,' HYDRAULIC PRESSURE POTENTIOMETER
:I'"
ACS GN 2 MOTOR CHAMBER PRESSURE TRANSDUCER
'!?
..::..:
AERODYNAMIC CONTROL SYSTEM REACTION CONTROL SYSTEM CLOCKWISE COUNTERCLOCKWISE GASEOUS NITROGEN HYDROGEN PEROXIDE
TO ELEVON INBD
ELEVON
HINGE (4)
Figure 3-36
3-28.
Reaction
Control
System
(Sheet
1 of 2)
c_o62-z40-_
AERODYNAMIC CONTROL SYSTEM REACTION CONTROL SYSTEM CLOCKWISE COUNTERCLOCKWISE GASEOUS HYDROGEN NITROGEN PEROXIDE
BOTTLE
ADS HYDRAULIC
PRESSURE HOSE
ACS HYDRAULIC OVERBOARD RETURN PORT ACS ACTUATOR CYLINDER ACS SERVO VALVE
1202 BOTTLE
(2)
MANIFOLD
ROL VALVE
MOTOR
ELEVON ACCESS
HINGE (TYP)
ONE
Figure
3-28.
Reaction
Control
System
(Sheet
2 of 2)
3-37
problem showed
qualification catalyst essentially mesh requirements test initial test of tanks and used
motor under
catalyst
Initial
a silver-plate
screen
all performance
satisfactorily
withstood level.
to establish
a confidence
in locating however,
test
equipment was
completed
the following
tank-to-tank
and damping),
rigid
incorporated. was designed configlife cycle, The in turn test reis as areas.
Hydraulic
Assembly
assembly
see Figure 3-29. dynamic cycling, pressure, test column repeated required listing
unit in its final flight and dust, salt spray, and burst times redesigns failures tests. which due to problem and redesign
partially
of the testing.
A brief
The actuator rod end fractured Examination of the rod end disclosed and bending instituted The but, as a result lubricating to lubricate hydraulic for of bearing the bearings of not properly
during the initial life cycle test (10,000 that the rod fractured under combined seizure. prior periods was The The bearing to start of storage a closed loop body, Joe II. seizure of testing. and prior system was The several was a direct
specimen after
control surface
potentiometer required
potentiometer
the vibration
configuration
the potentiometer had a flexible contacts under vibration. This tested; The sisted a rubber of a solid coupling rod with The in lieu the self results of both modifications wiper
of the shaft to allow failed and two other a combination The final supplied to make
self alignment configurations and wire configuration stronger. mounted points tube this
negative. provisions
by a slip-joint
redesigned
and the feedback Consequently, was to the and made removed were
components
extremely original
the potentiometer
to the
isolators
developed
extrusions
3-38
C-6062.141
Figure 3-29.
Actuator Assembly
3-39
the actuator under vibration. These isolators were attached to the aft end cap on the actuator and to the fin skin surface. Previously, the only attachment points for the actuator were the two rod ends; with the introduction of this third point, which was preloaded to snub the actuator to the fin surface, scratching and galling of the actuator rod developed; see Figure 3-30. This galling was traced to improper quality control in breaking the edges of the glands of the actuator. When the units were reworked to the drawing, the galling did not occur. All units were reworked and the supplier was changed. Considerable additional vibration testing was accomplished on the actuator assembly. The assembly was originally qualified to the 2043 level (later qualified to 30 G's) specified for fin-mounted assemblies. The assembly also passed off-limit testing at 40 G's and 50 GIs. System Tests - An integrated attitude control system test program was conducted to establish optimum gains, verify hardware compatibility and demonstrate that the Little Joe It attitude control system was capable of controlling the vehicle. The test configuration consisted of the autopilot electronic logic, the rate and attitude gyros mounted on a three degree of freedom servo table, a hydraulic aerodynamic control surface, and reaction control motors, all tied in with the analog computer simulating vehicle dynamics. The capability of the system was demonstrated, and knowledge derived from the testing resulted in two design changes and one procedural change; refer to Section 2. F.
.
C-hOh2-142
Figure 3-30.
3- 40
This was the largest test series undertaken on the Little Joe II project in t e r m s of physical size and number of tests. Simultaneously, H202 reaction control motors were fired in one location, and a pneumatic/hydraulic operated fin and elevon was controlled in another location (Figure 3-31), the gyro packages were operated on the servo table in a third location, and the other autopilot components in a fourth location, all being controlled by the analog computer. Several tests were performed in different configurations, both at Convair and at NASA/MSC, Houston. Aerodynamic control subsystem testing was also accomplished at this time. The pneumaticallyhydraulically controlled fin was exercised extensively to obtain information on duration of the hydraulic fluid supply; linearity, frequency response, etc
The aerodynamic control and autopilot subsystems were tested under qualification s t r e s s e s to prove operation a s subsystems. The aerodynamic control vibration test consisted of vibration of an aerodynamic fin minus elevon but with a complete, operating pneurnatic/hydraulic system. The test was performed in three axes with a combined sinusoidal and random input to qualification levels. The unit successfully operated in all three axes during vibration. During testing, two failures of mounting brackets occurred. One of the brackets was a pneumatic line clamp and the other attached the GN2 bottle to the fin. Both brackets were replaced with phenolic clamps and the test continued. The change was then effected on all production fins.
C-6062-143
Figure 3-31.
3-41
The autopilot vibration test demonstrated proper operation under vibration of a complete autopilot system consisting of an attitude gyro package, a rate gyro package, a logic and control amplifier, a static inverter, a pitch programmer, and two filters. These specimens were mounted on two vibration exciters and subjected to a combined sinusoidal and random vibration inthe three orthogonal axes; see Figure 3-32. Overall operation of the system under vibration was acceptable, with the following two anomalies: 1) the pitch programmer would not function in one axis and operated slowly in another axis, and 2) the drift rate of the yaw attitude gyro was excessive in the pitch axis. It was determined that the magnetic field produced by these large shakers was adequate to cause these anomalies when the field was up and the shakers not vibrating. This test was performed at Wyle Laboratory because it required two synchronized vibration exciters of 32,000 force pound output. Refer to Autopilot System Little Joe II 12-51 Vehicle, Vibration Qualification Test Report for, GD/C-64340, for test details. An aerodynamic fin structural response test was performed to determine the frequency and amplitude characteristics of a Little Joe 1 fin assembly when subjected 1 to limited mechanical excitation. Multiple accelerometers recorded fin response to different frequency and amplitude input to the fin at two locations. From this information it was possible to plot the transmissibility ratios over a selected bandwidth. The results of the test were used to better determine the vibratory input to different hydraulic components mounted on the fin.
.
C-6062-144
Figure 3-32.
3-42
AND FIXES engineers during resulting only the from in-flight worked Little the not previously joint failure roll after closely together in solving A summary follows with attitude of the control more
hardware corrective
and problems
a description
Vehicle on Vehicle deflecting continued increased due to the tation flight surface and could The IV elevon after the broad effect area
12-51-2 12-51-2.
-- The
system
occurred
lift-off, built
as q forces
structure
centrifugal
No forces Although along indicated autopilot deflected was the and with
the measured
of recovered operated
for a fully
never exact
confined
exhaustive
simulation, included:
study, changes
corrective
of contamination; 3) mounting of logic test 6) change requirement damaged stringent procedures; and and to provide
changes locking
to hydraulic method
of contamination;
to allow stability;
a more control
hardware;
and limited
stress
of hardware 7) change
to reduce
probability accumulator
and limited
contamination;
harness; of more
9) increased
requirements of training
on vendors;
10) establishcleanliness
dust-free
of OCP's; in revised
Subsystem gyro
of twelve
Failure see
were cycle
written
the rate
Gyro); balls;
had a limit
caused
of the units
null was
3-43
C-6062-145
Figure 3-33.
Rate Gyro
was reworked at the vendor's facility. The second unit was opened for trimpot adjustment and the null drift was apparently caused by mechanical shift after calibration and testing. The procedure was changed to include a vibration sweep to seat mechanical components prior to the final sealing. Null drift in the third unit was caused by aging of electronic components in the demodulator. Aging was normal and w a s compensated for in the amplifiers, o r by shimming. The fourth unit had a portion of the coil turns shorted in the microsyn. The problem was corrected by replacing the microsyn and instituting higher quality control during manufacture. The unit with the short, caused by solder balls, was cleaned and reassembled. The oil filler closure was changed to prevent recurrence and the manufacturing process instructions were revised for disassembly and resealing. The limit cycle oscillation was caused by excessive capacitance in the system, resulting in a phase lag and by excessive damping ratio. The filter and damping ratios were revised. The high phase lag was corrected by a capacitance change in the demodulator. The excessive drift during vibration was caused in one case by excessive frame amplification and in the other by spin motor bearings roughened from repeated vibration testing (exceeding vibration life expectancy) at component, subassembly and assembly levels. The frame was redesigned and the unit requalified. The broken lead wire was corrected by an engineering change, wherein the new parts in the wiper assembly had the lead wires potted. The unit that caged inconsistently was found to have intermittent amplifiers and the inner gimbal stops damaged. The damage was caused by high angular rate input from improper operation of the servo table; the probable cause of the amplifier 3-44
1 .
problem was gyro action after the stop damage. New operating procedures for the servo table were instituted and limit switches installed to prevent recurrence. The failure of the unit that would not torque o r cage was caused by an open lead wire which supplied power to the torquer fixed phase. A procedure was initiated to limit-stresstest all units, to detect marginal o r incipient failures. Manufacturing e r r o r was the cause of malfunction of the unit with reversed polarity in the pitch channel. The unit was repaired and a phasing check included in the system test. The excessive drift of the unit rejected in Receiving Inspection was caused by an incorrect location of NORTH in the lab. The lab was resurveyed and the correct location of NORTH verified for future testing. No damage was found in the unit that had been torqued while caged. Personnel involved were cautioned about the possible results of this action.
A total of eight Failure Analysis Reports were written against the attitude gyro package (American Gyro); see Figure 3-34. Failures included: loss of output during the vibration, failure to start, excessive drift, broken lead wires, gimbal oscillation, torquing, and reversed polarity. One unit had the torquing switch inadvertently turned on while the gyro was caged. The package was removed f o r checkout.
The short was caused by a bent wiper resulting in marginal seating on the slip ring. An inspection opening was provided in the wiper assembly to permit visual inspection of the wiper to slip ring mating prior to closing of the unit.
C-6062-146
Figure 3-34.
the start
up when
capacitance all procedures Pitch temperature a unit potting ground, output. and the WSMR, pot cover seconds. magnesium a new used trimpot for
addition was
of the
momentary
instructions
to ensure and
were after
due
control.
During
testing normal.
pitch
indicated material
full voltage
a few
temperature compound.
an electronic from
of a sealing lift the to full changed at rate trimbelow 65 with The gasket
subjected
manufacturing
allowed while
potting
to migrate to remove
units the
compound.
operations
screw. When the Teardown revealed particles installed, in lieu and one
unit was retested, the rate could not be adjusted the interior of the case was heavily contaminated end of the unit steel rate was cover trim cleaned, screws sealant for pot was the shorted casting the cover with plugged and screws.
particles. and
retapped,
installed,
a rubber
cement
During various PAT excessive and inconsistent. cases, servo porate effects amplifier found the amplifiers signals amplifier drifted
runs at San Diego, the pitch Units were found which failed to function. attitude Failure sensor. rise. analysis Also, after
run time was test and in some capacitive operations coupling the
on the input
due to temperature
redesigned
to incor-
an isolation transformer of temperature on the overcame a failed the megger capacitor filter to have
and to use an unpotted servo amplifier, to reduce the amplifier. Additional mica insulation in the base of the problem. The amplifiers that failed to operate were in the primary (Genistron) of the interstage composition drift precision proved change remained with transformer. resistors after original All film metal in the three receipt. carbon resistors. stable. by
The channel
autopilot output
signal
carbon
bridges response
negative
The frequency composition Metal After This film unit rework, was
of the filters
in tolerance.
at 3.5
C PS in the pitch
channel.
the wiring. vehicle The power analysis resistor, checkout at WSMR, Fluctuations board revealed erratic was voltages and were present on the +15 vdc troublenormal. X-ray 3-35.
supply
in the unit.
during became
regulation showing
in San Diego
a magnified in Figure
of this
the discontinuity,
is presented
3-46
C-6062-147
Figure 3-35.
Insp ction of the vendor's facility and manufacturing methods revealel this to be a basic deficiency. The fine wire that connects the resistor lead to the wire wound coil was completely unsupported through a cavity, which made it extremely susceptible to mechanical stresses.
During autopilot OCP's at San Diego and WSMR, transients were noted on command, r a t e and attitude signals in the data station and in the vehicle (12-51-3). These transients occurred during switching operations a t the blockhouse console, primarily during operations of the cage/uncage and inner gimbal yaw torque switches. The transients were generated by relay operations and were coupled from the relay power lines into the autopilot signal leads. The vehicle wire routing was revised to provide separation of power and signal leads, and twisting of ac power wires. This reduced the transients considerably but did not elimiinate them completely due to the common routing of power and signal wires in the umbilical cables.
Actuator Assembly - During a MAE OCP run, a Moog servo valve exhibited an excessive drift rate. Several servo valves were returned to the vendor because of suspected exposure to contaminated hydraulic fluid. Teardown of the valve revealed that the excessive drift was caused by a particle lodged in the No. 2 inlet orifice from the poroloy filter. This particle partially blocked the orifice, causing pressure unbalance i n the first stage. The resulting increase in null current was responsible f o r the excessive drift. Teardown of the suspected contaminated valves revealed no problems.
3-47
Directives were
that all valve current sive established Feedback - Rough shift degradation assembly
issued would
were
and exces-
be accomplished
A null ma was
for null
potentiometers
had rejections
as follows:
- not repeatable. - not repeatable. lead - cracked time. ramp showed in X-ray.
- orange
with time. factory condition including to an acceptable of alignment. monitoring condition. Four spare of resistance Five units
Six units were were limited Five failed X-rayed X-rayed stress
at the tested,
in place vibration.
to determine
potentiometers during
and functionally
switch
(TAVCO) Two
units units
12-51-2
developed hole,
problems one
at San Diego
and NASA/MSC.
through
the vent
overtravel the
proved leaking
filtering
and cleanliness
contamination
and resultant
of the switches. Circuits -- The The RCS time delay was relays was suppressed with relay One were initially to the Zener no effect was was to the coil. defective three revealed circuit, initiated as during susceptible Zener on the regulating relay. one to bus circuit. This set of records shipped. the relays sharp to of renot the unit
Co_rol voltage voltage The change contacts During remained edge remain checking such timing punctured
pulsing
capacitor levels
reconnected
regulated
transient
by the
relay
at transient and
of 75 volts units.
shorted inspection
a set of contacts showed that insulation Vendor procedures This and was after
shorted
at the vendor's
discovered
approximately
Teardown
of a resistor
had punctured
causing
occurrences,
that the
insulation
had been
in either
to the power
3-48
CONCLUSIONS The 12-51-3. 12-51-2 Other detailed during E. attitude A failure caused than
RECOMMENDATIONS system the performed aerodynamic condition associated as designed servo loop and ultimately with the were due on Vehicles on fin No. resulted 12-51-1 4 elevon in vehicle of the system and test and of Vehicle destruction. that aids were used
development to test
previously, the main problems autopilot system checkout. SYSTEM system installation, scope of the control provided control system. cables
equipment
electrical
power
certain the
vehicle
systems,
to do with 1) electrical
covered
and distribution
for checkout,
of electrical
AND
return lines were routed to ground at the power building source to vehicle structure near the power source.
only; the complete power distribution system was otherwise isolated from ground. Vehicle power return lines were common
The basic electrical system concept was developed for Vehicle 12-50-1 and remained fairly constant throughout the program. accommodate exception mentation bility. all planned system changes. first vehicle, required on which bleed circuit of the a battery Growth capability was built in to in the adapter instrucompati-
This capability proved adequate with the substitution to provide additions operational
subsystem
and power
in the the
was future
accomplished vehicles,
by constand
switchconreadre-
Although parameters
of read-out
instruments, The
monitored
be reduced
less
CABLES cables cables were 3) enable access were was designed with to: 1) provide this from isolation isolation); the between 2) permit launcher-to(large provided strips systems ease of
used
cables); boxes
to mission
connections
- terminal
in the vehicle).
3-49
FACILITY POWER IS USED FOR ALL GROUND MONITOR AND CONTROL FUNCTIONS AND MAY BE USED TO POWER VEHICLE SYSTEMS.
EMERGENCY FACILITY POWER SERVES AS A BACK-UP TO NORMAL POWER SUPPLY LOSS. THE BATTERIES ARE LOCATED IN THE POWER BUILDING BATTERY ROOM AND COME ON THE LINE AUTOMATICALLY WHEN NORMAL POWER IS LOST.
J'NORMAL FAC;I.ITY POWER IS J DERIVED FROM A 28 VDC POWER /]SUPPLY OPERATING FROM THE J / L60CYCLE LINE.
/ /
I
E/R #1
FACILITY
POWER
fl ' owER' i
INSTRUMENT SYSTEM I I
CHANGEOVER
_
"VEHICLE
PRIMARY SYSTEM
I \ \
i J
BATTERY SUBSYSTEMS. ONE SET OF BATTERIES SUPPLIES POWER TO INSTRUMENTATION, THE OTHER SET SUPPLIES POWER TO THE ATTITUDE CONTROL SYSTEM AND OTHER VEHICLE CIRCUITS. (SECOND STAGE IGNITION BATTERIES AND THE THREE COMMAND SYSTEM BATTERIES ARE NOT INCLUDED.) SEE TABLEI. EACH BATTERY SUBSYSTEM CONSISTS OF TWO 15 A/H, 28 VDC YARDNEY BATTERIES WITH DIODE ISOLATION AND RETURN LINE SHUNTS FOR CURRENT MONITORING.
CONTROL AND MONITORING ARE DONE AT THE BLOCKHOUSE CONTROL PANEL. BATTERIES CAN BE MONITORED BEFORE AND DURING APPLICATION OF LOAD. THE VOLTAGE FROM EACH POWER SOURCE CAN BE READ ON THE CONSOLE METER. A SERIES SENSING CIRCUIT IN THE VEHICLE PROVIDES RED LIGHT WARNING IF ANY VEHICLE BATTERY VOLTAGE FALLS BELOW SPECIFICATION. CONTROLS INCLUDE FACILITY POWER ON/OFF, EXTERNAL POWER TO VEHICLE ON/OFF, AND CHANGEOVER FROM FACILITY TO VEHICLE POWER.
C-6062-148
Figure
3-36.
Power
Distribution
3-50
The basic concept of using standard parts was closely followed, a good example being the launch vehicle umbilicals, which provided control and monitor connections to all vehicle systems and to some spacecraft systems; see Figure 3-37. A s many as seven connectors were used, the maximum connector size having 72 pins. A l l connectors were standard lanyard disconnect types which separated upon lift-off. The use of several standard connectors precluded the cost of large special-order umbilicals and resulted in versatility at low cost. The launch vehicle provided an internal interface with NAA circuitry at Station 0.
*
In addition to the normal abort function performed by the launch vehicle (see RF command), a number of redundant monitor and control functions from the spacecraft were routed through the launch vehicle to permit monitoring until lift-off. (The
external spacecraft umbilical was ejected at T
- 8 seconds.)
NAA junction boxes and umbilical functions were added for Vehicle 12-50-2. A redundant umbilical was added to the vehicle base approximately 180" from the normal umbilical location. Lanyard lengths were adjusted to ensure that the power side of the dc supply voltages would be broken by lift-off prior to separation of the return lines; see Figure 3-38. Adjustments were made to the NAA interface configuration on each subsequent vehicle.
t
I
1;\!
jt
C-6062-149
Figure 3-37.
3- 51
SEPARATION
(4)
4" 10"
_,
t_
12"
ROD ] ,-
EXPENDABLE
HARNESS
(4)
VEHICLE
SUPPORT
JACK SHIELDING
MOTOR
C-6062-150
Figure
3-38.
Expendable Connections
Harnesses -- Vehicle
Grounding
3-52
12-51-1
the
Cannon
umbilical
connectors addition
(48 pin
were of
re-
(72 pin capability) occasioned made amount. in the Deutsch this on all spring stated pins clips. by the for growth,
control
Although
an allowance systems During loose push pushed together satisfactory. their difficult special reasons inserts. The together mate for mating plant from test; stallation. loose with
had initially an extraordinary checkout, the this insert. test at less was than Manufacturer
changes
had expanded
two pins
found
pulled in-
happened
in all
initiated, at by a
and were tooling made were for seated other with new it very
caused
on the
vehicle replaced
at WSMR
to the
Connectors
at Convair,
engagement with
on while
Vehicle The
attempting
frequency change
A method to ensure
connectors
to flight to the
was
integral
mechanism,
material
alumintun
to steel,
and increasing
BONDING All beneath was given The problems was F. the installations the launch sufficient vehicle after most time and hardware pad and blockhouse. to break system were task; after slack electrical initial consuming were bonded The separation properly 3-39. to the copper grounding bonding see grids connection Figure Checkout of batteries 3-38.
launcher-to-vehicle
proofing
nonexistent.
radar. The out by the vehicle battery. received system radar White Three performed beacon Sands antennas, system Missile The radar spaced energy used in Vehicle 12-50-1 was around transponder. See Diagram (QTV) was were the installed made by a 9-volt, vehicle, The radar in Figure coupled, beacon 3-40. and checked launch 40 A/H
Range. beacon
provisions
in the
powered
satisfactorily
3-53
RF COMMAND
2NDSTAGE IGNITION -
12 -50-2
12-51-1
(2)28V 15 A/H
(I) 26V 80 ma/H (I) 26V 80 ma/H (I) 26V 80 ma/H (2) 26V 15 A/H (2) 26V 15 A/H
C-6062-151
12-51-2
12-51-3
(2)28V 15 A/H
Figure
3-39.
Vehicle
Battery
Summary
(3)
_--_
ANTE_NNA COUPLER
ANTENNAS
BATTERY
TRANSPONDER
I I I I
GROUNDCONTROLS AND MONITORS
C-6062-152
Figure
3-40.
Block
Diagram
-- Radar
Beacon
System
(All
Parts
GFE)
3-54
G.
SYSTEMS command events systems evolved forward The range. Surveillance in the thrust range Office At WSMR, course safety this of the system system program: command was was flight the system installed under functions. the system The command range for to
system the
and the RF
in-flight
or sequences.
cognizance
(MFSO). certain
The RF
was designed to NASA specifications for accomplishing following indicates system usage in the launch vehicles. Vehicle 12-50-1 12-50-2 12-51-1 The the three type signals. Vehicle antenna antenna was used range & On safety system was were systems, commands Range Safety System
System
Destruct
Safety
and RF command identical in design in the as follows: Safety installed which were Range Tones
frequency
necessitated
of the
By vehicle,
RF Command Tones ...... ...... 1, 3 S/A S/A Arm Fire & Function
3 1, 5
Destruct -----
-----
1, 5
Destruct
3 3, 3 3, 5 5
Test
3 1, 3
Test
3 1, 3
Destruct
1, 7
3-55
parts
inventory,
a shortened
events action
or
sequences to
was
RF command antenna
Figure operated
3-41.
Each
half
con-
of the
at 309 mc,
and a control relay box. The checkout on the RF Command was single placed failure The on reliability would cause
command system was monitored located in the blockhouse. The The abort dual or fail system was so arranged abort. termination
of operation. premature
to enable
functional
and operational of tests. first bed The charges test firings during were of the
performance
of two thrust
systems
was
by a series firings Figure with one that although of the in a test 3-42. anomaly; all
series,
the
Vehicle 96 inches
configuration, Little purpose and Joe II foreof the test was testing not led to
performed
simulating the
investigation
conclusion
stopped,
of travel,
irregularity. these the tests abort installed included signal the and training proofing of personnel of operation in pro-
system,
establishment
No RF command System). The was cal S/A added base was However, thrust
in Vehicle with
philosophy system than rather indications. These control circuits, relay and safety arranged
originated installed
vehicle. can be considered termination used provided measured on/off battery were receiver firing depth accomplished an
a range than
safety.
All possible included initiator were system. to provide ) battery (2). complete. position
indicated
voltage
A separate
monitoring
of the
installations
of monitoring
range
were
simultaneous
to the initiators; and abort NAA interface at Station 0. to back up relay opening.
termination
were
successfully
initiated.
3-56
9
U
Q_
r0 p_
o_ 0
J_ _Q
l
00
_p
_ll
m_ -
r,,_n
_,>m
l-
o_
3-57
I"
I
't
3- 58
termination since
was it was
deleted
from
the RF command for followed abort. for later The successful by abort
for relay
firing
of delay.
installed
functions data
successfully
telemetered performed
all functions
in the RF command
to the
added was
the
flight (Timers
installed However,
wire/primacord on this
wrap-around commanded flight. broke 12-51-3 due changes either was added was pitch-up abort Abort apart. the
function. was
successfully
initiated
by breaking
command also
was
unit
Communications) Minor designed abort-only flight delayed path monitoring to provide mode and the abort
in the event
to stray The
allowed
performed
properly.
Failure One failure other caused which was the burrs two
written against three Aerojet Safe and Arm Units. of the detonator being out of tolerance. The condition. The high resistance reading was of 5 ma was drawn by the tester, The resistance tolerance was changed The was failure caused strict to obtain the armed of the control rotor of the signal shaft squib in and by preloading quality
units
failed
the armed
by the caused
test values used the out-of-tolerance value for The the test preloading was proper Reports 3-43. Three of a detent,
where a current resistance. current caused of the routing. written would would which during used. by burrs shaft by initiating
by the routing
wiring.
problem
to eliminate
and to provide Failure Analysis see vibration Test very crystal caused with Functional units Figure
four the
command 3 relay
destruct upon had units Also, quality units. command of a were one
not pick
up the
Tone other
successfully which
requirements.
Inspection
transistor, imposed
replaced. to ensure
requirements
on the vendor
3-59
C-6062-155
Figure 3-43.
Three REPCO command destruct receivers were rejected at Convair due t o frequency deviation sensitivity being out of tolerance. In two units, the failure was not confirmed and the third unit w a s adjusted into specification. One unit was rejected for failure of the Channel 3 relay. This problem was caused by a cracked crystal in the Channel 3 oscillator. The cracked crystal was replaced and the unit checked out satisfactorily. The crystal failure was probably caused by mishandling during checkout. One unit w a s rejected for faulty operation of a relay. When the unit was opened, a shorted wire to the relay coil was found. The w i r e was crushed due to harness routing. The crushed wire w a s replaced and the wiring rerouted in all units to preclude recurrence of the problem. Two units would not produce an output. When the units were opened, it was found that relays were crushed by the relay harness during closing of the cases. The harness to the relays w a s rerouted, allowing the units to b e closed without damage to the relays. A l l units were opened, inspected and reworked to bring the units into an acceptable flight configuration. Since more satisfactory units were desired, steps were initiated to replace the REPCO receiver with those from another manufacturer.
3-60
The RF
missions; The high REPCO voltage. the
for
with was
system
peroxide
voltage
battery;
was
checkout,
RF command
lance from
The range safety system (RSS) (Figure 3-44) enabled the Missile Flight Office (MFSO) to terminate vehicle thrust in the event of a hazardous the planned flight path. signal receiver initiators Algol from the ground 28-volt Upon station was trains detected to two which of the by the safe and were shaped motor
Surveildeviation
com(S/A) the
dc power detonation
the primacord
motor cases would split (generally breaking pressure, which would result in a cessation The and S/A design units was were with dictated supplied mounting by MFSO by MFSO. provisions
apart), and thus relieve of forward thrust. The provided The command the antenna major
receiver, parameters
battery were
and primacord
Parameters Receiver - Frequency - Tone Safe & Arm (S/A) Channels Unit - No-Fire - All-Fire Primacord - PETN - RDX Shaped Charge
-- Range
Safety
System
309 mc 2 required Current Current 80 ma. 150 ma. - 100 grains/foot - 100 grains/foot of 200 grain/foot 180 on each motor. RDX charges as a RDX
- (For
- (For
Algol
ID MOD I)
5-inch
provided
detachable
3-61
_
_
_o
O_ tO U-
u_>.
Z I,'-" _ OOL_i
0 Ld>=" --
o_o
t_
u,.I ...I zO OLO t.O'_
II
=,9<o
,_
u.l u'l
#-.E_
_ ._
gefg
3-62
Reliable operation of proven components primacord vided trains additional backup. and
of the pyrotechnic and dual routing. shaped charges S/A installation methods;
portion of the system Two initiators in each on each included motor. covers, and primacord these routing
was ensured by the S/A block fired two networks conduit, incorporated splitters, several
use
Crossover
proand
testing, functions
power,
signal, current
and
arming Report
control
unit over-
and destruct,
measurements,
load capabilities, and continuity. dated 8 April 1963 contains details A Beckman as intended The test, during ment. destructor, sand entered rotation; causing by shipping The oped of the featured was the by MFSO. use physical blown for Convair. and the the unit and the The the under failed test; and Whitley the expected properly test, the was unit used due to arm humidity when lacquer and was dust, rotor rotor and basic Vehicle Although vehicle, electrical to use At the revised the a slight
as required;
VC & I - 73,
to verify
that prior
the test,
unit the
lacquer
hardened, coating took against exposure of these bags. destruct between flight
to installation
removed
and humidity housing, corrosive to bind storing range the safety a safety system arming an arming request
and dust
occurred
to high problems
12-50-1
of coordination
(MFSO)
original was
unit
complete
of RDX from
primacord.
dual
due the
RDX primacord
the S/A
and did not ignite. involved into flexing the the primacord blocks. shock of the primacord and This wave. conduit stripping allowed and the entry into back the bottom the the RDX protective grains to condidestruct block
destruct
Contributing
required
to allow
System system
was was
(refer the
in Vehicle
12-51-1.
Since
range
safety
routing connection
two Algol
motors,
and PETN
to the
3-63
units.
The
MFSO-furnished tests in flight. S/A revised A new This unit was time to bring
parts
(receiver,
battery, levels
S/A
unit)
were
to was
environmental not required A second routing was required. installation. The motors, was used
the qualification
up to standard.
system Algol
primacord tested
" which
and installed,
in flight. 12-51-3 from These necessity. to accommodate three-channel were system This was changes four required not Algol
primacord
receiver rather
a REPCO
model
to an advanced due to hardware used in flight. During units tests, deep-cut result further action flowed lacquer and test, analysis wire. matter four
communications
four-channel
than functional
test Safe
seven
high-temperature as a direct to preclude corrective on one viscous cooled, to the end of and the sand
could
screw; were
of the units
control
of the procuring of the primer The the test. against of failure rejected on Vehicle Since with the problems; high temperature and housing. following to bind cause were rotor
the primer
to aid in positioning the rotor failed caused under to arm the burned, the probable the rotor
bonded which
dust test
The units the housing. the booster was in X-ray 12-50-1, system
to contain Preliminary
foreign
a light
charge
of a lot of 60 units from exists been the initial to operate concerning resolved
for light
safety problems
never could H.
required have
by MFSO,
no docu-
mentation
a different
of coordination.
INSTRUMENTATION instrumentation and subsystem evaluation was 3-45. Abloek of mission diagram PAM/FM/FM system sensed performance. sharing airborne and transmitted to telemetry The measurements ground telemetry stations, concept and FM/FM system to utilized for is of
vehicle enable
measurements
instrumentation
3-64
_
(/1 (/) ::).J
oon,. 1i
v I(JZ O0 --If..) rn
o_
O_ r/l
(.J O_ bd Fh.
o I_
Z n, i
I I
o_
oz
t"-
o
iJ
oe_
_l--m n N
I I
L_
1
nO
_-
go
L_J LIJ
I.-
3-65
vary
with
each
vehicle
because
the
acquiring
the vehicle's
reaction
measurements
requirements Algol and propulsion relay 12-51-1 system. and control requirements verification
instrumentation command.
12-50-2
were
that
of
accomplished
by measuring
the
attitude relay
vehicle
response
environment,
measurements voltages.
for of the
were system.
reduced This
to propulsion
by measuring 12-51-3, control system, and eliminated. closures summarizes system vehicle. to the for the
airborne
designed system,
to and
attitude ignition
command mode
second-stage
bending
coupling accelerations,
accomplished voltages.
by measuring
body
Figure
airborne of measure-
instrumentation ments for each In addition vehicle changes are were peculiar The from missile for the DC-DC unit the wave prior facturer's testing. ratios corrected damaged 3-66 that
changes
that
took there
place were
from
vehicle changes,
experience, design
as parameter significant
variations
instrumentation components and which subcarrier on the and for Due to the A considerable changes quality used vendor the
for
Vehicle of the
was
standard
previously
on various regulated
to installation
by improving
control
antennas
Vehicle antenna
to be improperly
control.
on installation.
ATTITUDE
CONTROL
SYSTEM
50-1 .... .... .... .... .... .... .... -.... ....
50-2
51-1 1 1 2 5 4 4 4
51-5 1 1 2 5 4 4 4
1. PITCH ATTITUDE 2. SUM PITCH ATTITUDE & PITCH 3. ATTITUDE: ROLL, YAW 4. 5. 6. 7. 8. 9. 10.
PROGRAMMER
RATE: ROLL, PITCH, YAW QUAD COMMAND ERROR FIN ACTUATOR HYDRAULIC PRESSURE FIN CONTROL SURFACE POSITION FIN REACTION FIN RCS REG. FIN REACTION CONTROL VALVE SIGNAL NITROGEN PRESSURE MOTOR CHAMBER PRESSURE
--
8 4 8
AERODYNAMIC 1. BODY BASE PRESSURE 2. ACCELERATION PROPULSION 1. ALGOL MOTOR CHAMBER PRESSURE 2. RECRUIT MOTOR BODY TEMPERATURE STRUCTURAL AND ENVIRONMENTAL 4 2 1 4 1 2 1 PRESSURE 4 ........ ........ ........ ........ ........ ........ ........ ........ 1 6 1 2 ........ 6 4 12 1 ........ ........
1. THRUST STRUCTURE DIAGONAL STRESS 2. BODY BASE CALORIMETER 3. BODY BASE STRUCTURE TEMPERATURE 4. 5. 6. 7. FIN TE CHORD TEMPERATURE EQUIPMENT TEMPERATURE COMPARTMENT TEMPERATURE BODY INTERNAL PRESSURE MODULE VIBRATORY INTERNAL RESPONSE
1. FIN FLUTTER 2. ACCELERATION 3. ACCELERATION, 4. ACCELERATION, 5. ALGOL MOTOR BODY SERVICE MODULE TOWER OSC. CHAMBER PRESSURE
4 4 6 2 ....
RF COMMAND SYSTEM, THRUST TERMINATION AND/OR PITCH-UP ABORT SEQUENCE 1. 2. 3. 4. RELAY CLOSURES TIMER BATTERY VOLTAGE RECEIVING SIGNAL STAGE IGNITION 2 2 .... .......... .......... 4 2 -.... 4
STRENGTH SYSTEM
SECOND
1. SECOND 2. ALGOL
STAGE SQUIB
........ ..........
MISCELLANEOUS 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. INSTRUMENTATION BATTERY, LJ-II INSTRUMENTATION BATTERY, SERVICE INSTRUMENTATION SYSTEM VOLTAGE REFERENCE BATTERY VOLTAGE CALIBRATE 0 VOLTS CALIBRATE 5 VOLTS LIFTOFF, CONTINUOUS CHANNEL LIFTOFF, COMMUTATED VEHICLE ELECTRICAL SYSTEM VOLTAGE INVERTER BUS VOLTAGE TOTAL MEASUREMENTS 1 1 1 1 1 1 1 1 .... .... 66 ........ ........ -------
MODULE
1 1 1 1 1 1 1 1
----.... --.... 13
1 1 1 1 1 1
59
59 C-6062-158
Figure
3-46.
Airborne
Measurements
3-67
SUBSYSTEM T/M 3 BLADE A TYPE T/M 3 BLADE B TYPE T/M 2 BLADE AT141 C TYPE A/ARC
DM AK 3 INTO DIVIDER SMAMI 120" APART 12-,51-1 12-51-3 CARRIER VEHICLE 12-50-1 12-51-1 12-51-3 IRIG BANDS VEHICLE 12-50-1 12-51-1 12-51-3 COMMUTATOR VEHICLE 12-50-1 12-51-1 12-51-3 _, T/M E E E A T/M A E FREQUENCY T/M 229.9 225.7 225.7 A MC MC MC SAME SAME AS ABOVE AS ABOVE
180 APART --
B MC MC
T/M 258.5 --
C MC
T/M 10-18 --
12-14 E
90
x 10 T/M
PAM SOLID B
STATE. T/M C
........ E ........
....
C-6062-159
Figure
3-47.
Parameters
three
that
were
required
for
Vehicle
12-50-2
were
routed
to
telemetry
an interface
connector;
no operational
problems
were
significant This
design design
change
was
the
use
and transducer change requirement change drift. during the was of the the This
DC converter Included relay. redundant thus The manufacturer's preventing The ever, the assembly. to prevent A major change factory into 3-68 the in the
initial subcarrier's
by a of the
countdown
in flight,
malfunctioned.
not recovered,
Vehicle change
also
VSWR; at the
howfield
to be in a small
connector assembly
damaged
during
A minor
occurrences. in instrumentation procedures. the time test Other for evaluation It was essentially system testing tests and at WSMR were was inaugurated with for breaking by a of the
change checkout
verification necessity
checkout system
instrumentation
equipment.
unused four
to meet
monitored
No problems
encountered on this
were
essentially was a
checkout,
that there
difference
ground.
that
amplifiers only
system impedance
autopilot
isolation,
a small
sacrifice
corrected
system degree
performed
of success of Measurements 62 3 58 13 39
Number
Totals I. LANDLINE The permanent ments typical The and landline analog subsystem landline data INSTRUMENTATION instrumentation recordings parameters instrumentation obtained from the
175
for
the that
of environof a
time
is shown were
used
for
of the
solid-
propellant rocket motors and failure analysis of subsystems. measurements varied with each vehicle because the mission with vehicle configuration, dictated different landline recording Figure 3-49 summarizes the measurement requirements the total amount of recorded landline measurements for
The number and type of objectives of flight, along requirements. and presents
3-69
A 8
.O
)
0 !
3-70
50-2 6 3
51-1 6 3
51-2 18 3
51-3 12 3
FIRING CURRENTS
ALGOL FIRING CURRENTS LIFTOFF IGNITION TIMER RANGE TIMING RCS PRE-PULSE RCS PRESSURE TOTALS TIMER
19 26
Figure
3-49.
Landline
Recorded
Measurements
In addition measurements measurements monitoring not vary For was Throughout maintained measurements data for Satisfactory Also the
were
many
real-time systems
displayed
or light
indicators.
recording
significantly Vehicle
12-50-1, from
assembled
by WSMR.
recorder
problems
temperature inconclusive
producing
by NASA personnel.
ignition
recorder
for
complete failure analysis lines, but did not provide firing sequences. data These was obtaining Satisfactory a new recorder
information. It recorded current delivery to the firing accurate current amplitudes or positive assurance of proper problems with were revolved sensitivity for Vehicle and vehicles. response 12-50-2 and on by adequate characteristics.
received
on all subsequent
3-71
LANDLINE MEASUREMENT LIFTOFF DESTRUCT UMBILICAL SUPPORT SUPPORT LAUNCH LAUNCHER GROUND VEHICLE VEHICLE BATTERY GROUND CONVERTER RECORDER FIRING COMMIT IGNITION LINE TIME SIGNALS SYSTEM ARM ARM SYSTEM RETRACT (3)
INDICATOR
AZIMUTH
POSITION POSITION
VOLTAGES POWER
(2)
VOLTAGE
C-6O62-162
Figure
3-50.
Real
Time
Monitoring
Measurements
Vehicles
12-51-1
and -2,
the
major
design
change
to landlines
instrumentation
addition of a blockhouse oscillograph for the pressures. No problems were encountered. for Vehicle 12-51-3, which did not have
an RCS
3-72
LAUNCH
SUPPORT
LAUNCH
SUPPORT
A.
LAUNCH Launch
36 originally designed pad The II and the (Figure a cable station, referred Little 4-1), trench and launch Joe constructed for and Apollo Joe service firing east abort H effort between transfer half tower with blockhouse, missiles. bisected half of the erecting After blockhouse gantry comwere
pad
program.
blockhouse
programs. included tracks the pad and power Building," a new to move and the room launch the near contained pad service the pad. junction 1,150 tower (Figure The
Requirements feet 4-2), transfer west new of the launch and power to the
permanent
blockhouse
a facility
boxes, regulated ment for extensive Little 63 feet 4-3. Joe II and in lieu high. the pad),
equipment. There tower to enlarge its and launch 98 feet, complex was 5 feet, 10 inches
was also a requireenvelope for a high (above and in Figure in diameter shown
4 inches are
Details
altered
in the
design
with NASA.
the
Army
Corps
of
& Associates
architectural
designers),
North
Industries, over
requirements assisted participation design, to the Convair coordination during area, beneath the the adequacy
for the
necessary i.e.,
coordination,
active
of launch
operations
personnel, of the
entire
and activation complex. engineer "action" and separate complete and high
In December permanent The only transfer 1) two tunnel basis, major and power rooms, - rejected
assigned
considered: type
of construction
4-1
AREA
e_
~
-*r
C -6 062 - 163
Figure 4-1.
11111%.
lh4
t
I
**
c
Figure 4-3.
Launch Complex
C-6062-165
building adjacent to the pad and protected by a sandbag barricade - rejected because of probability of damage during launch; and 3) a reinforced concrete structure at the south edge of the pad, with three individual rooms. The third was finally selected, but major revisions to the original form were required. These revisions involved i? complete re-layout of the junction boxes, equipment racks, power supplies and associated areato-area wiring. In addition, there was the extra burden to the launch operations activation task of design and procurement of such items as structural attach brackets, conduits, and rack supports. Some of the decisions made, which later proved very beneficial, included the following minimum requirements: 1) all conduits between the pad and the transfer and power room were to have a minimum four-inch diameter; 2) all electrical cables were t o have a minimum of 15% spare wires; 3) pad dimensions w e r e to be adequate, but not extravagantly so, for equipment movement with such vehicles as Algol motor transport erectors and low-boy tractor-trailers; and 4) there must be compatibility between the service tower and the Convair-provided launcher. These decisions resulted in limiting the modification required for the pad, service tower, power building and launch complex. The NASA Vehicle Assembly Building (Figure 4-4) was completed in time to support the launch of Launch Vehicle 12-50-2 on 13 May 1964. Convair used this building to unload the vehicle upon its arrival from San Diego and occasionally to store an Algol motor overnight. Later, a portable "clean room" was added in the building to permit 4-3
C-6062-166
Figure 4-4. Vehicle Assembly Building final installation of the reaction control and hydraulic actuation systems in each fin, under controlled environment. In general, the Vehicle Assembly Building (VAB) served its purpose well. There were minor interferences between Convair and NAA, which w e r e quickly resolved at the working level. There were a few specific areas which warrant comment: because of narrow doors, no more than two Algol motors could be stored in the area provided, while the intent had been to store as many as seven. The special 15-ton capacity hoist, provided for use with the Algol motors, w a s never used for that purpose due t o incompatibility of the Algol hoisting beam and the hoist hook height. However, the room was used to good advantage by NAA to prepare the launch escape motors and towers for installation on the command module. Also, the hoists in both the low and high bays would have been much more useful had they been capable of lateral motion as well as motion along the longitudinal centerline of the building. Permanent office space for operations personnel was not constructed because of the relatively short duration of the program. Therefore, mobile office trailers were provided during vehicle assembly and checkout activity; ultimately, four 10-foot by 50-foot trailers were occupied by Convair personnel: two at the launch pad for operations engineering quality control and for support personnel; one at the CSTF t o support test activity in that area; and one at t h e blockhouse to provide quarters for personnel associated with instrumentation, data, and preparation of integrated operations procedures.
4-4
moved following
area launch.
the
ability
immediately
to the
was
moved
to the
Complex vehicles.
to support Pyrotechnic
and
subsequent
up to 1/8 pound of explosives could be checked out in this and cooling of the trailer were excellent. Unfortunately, heating, B. making cold weather working conditions less than
LAUNCHER The launcher was a mechanical It was structure, structure fabricated which designed for the final assembly and heavy
of seven vehicles. forming the major launches. launcher position. for support swiveled Two elevation arms view was
motor driven
driven, screwjacks
crane-type pivoted
trucks the
to achieve support
electric
vehicle
structure Vehicle
payload
umbilical
were
mounted 4-5.
on the
launcher's
mast. The trailers; vation remote controls pneumatic The ical the lists
of the a portable
4-6.
The 4-8.
and position
indicators support
and indication for the systems; see Figure launcher during diagram major mast, assembly build-up for attached (Figure and design support capability 4-14.
umbila 4-13
stabilizing
lift-off and
schematic
the umbilical
support
retract
parameters. arm test was static conducted mast loads to demonstrate assembly were are sustained under the without structural loading damage or
of the Critical
launcher
critical
distortion A detailed
and the unit operated successfully test description and test results materials the Materials engine erosion were were and tested structure exposed 5200F for
during simulated launching concontained in Report SL-62-065. of one as a suitable rocket exit motor of a scale - and the exhaust model then measurSix V44) 4-5 material. (GenGard matetem-
protection lagging
launcher
to the at the
- approximately
of surface based
the temperature
through
compounds,
a Butadiene
Acrylonitrile
compound
C-6062-167
Figure 4-5.
4- 6
~-6062-168
Figure 4-6.
and a concrete-asbestos compound (Transite) were tested. The GenGard V44 and Transite had the lowest erosion rate and temperature rise. All materials tested exhibited effective heat blockage characteristics. The GenGard V44 was most effective with the grain of the material parallel to the exhaust gas centerline. Bonding of t h e materials was not affected. Factors such as fabrication techniques and ease of maintenance were not evaluated; Report R T 62-039 dated 19 October 1962 gives detailed results. Transite and Flameastic were selected for use on the exposed launcher surfaces.
During engineering proofing inspection prior to the first launch and after the original design, a number of minor changes were made. The vehicle support a r m s were redesigned, mechanically and electrically, to simplify the original design and improve reliability; covers were added over limit switches to protect from rain and other environmental elements; and the electrical junction box was revised to provide greater physical separation of 480-volt ac and 115-volt ac terminations.
Based on the operating experience of the first launch, a light was added to the console to indicate when the support a r m pneumatic system valve was in the "vent'! configuration. The support a r m pneumatic cylinder pressure switch was revised after a failure occurred due to corrosion. One pressure switch (P/N 98-62805-022) was rejected in Receiving Inspection for e r r a t i c contact resistance; two units operating out of tolerance were found to contain 4- 7
metal slivers andcorrosion. The unit with erratic contact resistance had a thin oxide film on the contacts which was dissipated when rated current was passed through the contacts; the switches with metal slivers and corrosion contaminants were cleaned. The shoe andspring were removed from all units, which eliminated wear on the Mylar diaphragm. The switches could then be adjusted to pressure tolerances. For Vehicle 12-51-2, the payload umbilical system was redesigned to accommodate the repositioned umbilical of the Apollo spacecraft; see Figures 4-10 and 4-15. For Vehicle 12-51-3, a launcher mast extension was incorporated dueto the more forward location of the spacecraft umbilical. The launcher performed as designed for all five launches. All mechanisms performed smoothly both before and after each launch; refurbishment was held to a minimum. Actual launcher positioning accuracy was better than 6 minutes in azimuth and 1.5 minutes in elevation. C. CONTROLSYSTEMTEST FACILITY (CSTF)
The control system test facility (CSTF) was an isolated site for functional test of the attitude control fin systems; see Figure 4-16. The CSTF had all the equipment required to test and service the reaction control system and the hydraulic-powered aerodynamic control system. Environmental and safety provisions associated with hydrogen peroxide handling were included. The permanent site consisted of a 30-foot by 30-foot concrete test pad with a 16-foot by 32-foot prefabricated steel building. The building and pad were separated by a distance of 45 feet for operator safety. The building was designed to withstand 42 lbs/ft 2 overpressure, equivalent to all four RCStanks exploding simultaneously. The pad included floodlights for night operations, showers and water flushing for H202 safety, tie-downs for the fin stand, and electrical power outlets. The GSEused for fin servicing was placed on a paved area of the facility; see Figure 4-17. The hydrogen peroxide trailer could be placed in the building, which was environmentally controlled to 70 (5) F, for H202 surveillance. Fin testing was controlled and monitored from the attitude control fin test console; see Figure 4-18. Portable recording equipment was used to monitor fin system performance; see Figure 4-19. Equipment andwork space were available in the building to enable componenttest andrepair. Complete specifications are provided in Invitation for Bids INV No. ENG (NASA)-29-005-64-9, issued by the Corps of Engineers of Albuquerque, N.M.
D. GROUND GSE SUPPORT EQUIPMENT (GSE)
was provided for handling, servicing, testing and maintaining the launch I_artsand subassemblies. In general, the GSE performed
4-8
.o
o
0 0
@
_Pt I
i.-. 0 ,Y
i-. 0 0
__>
i,i I-I--
N,._
Z _'_N
%
0
n-r_
--m_o
_o_
o_
A PLUG-IN, PORTABLE REMOTE CONTROLLER WITH POWER ON INDICATOR LIGHTS AND PUSHBUTTON CONTROL SWITCHES PROVIDES BI-DIRECTIONAL CONTROL OF LAUNCHER AZIMUTH AND ELEVATION POSITIONING AT THE LAUNCH PAD. THE UNIT PLUGS INTO A RECEPTACLE LOCATED ADJACENT TO THE MAIN JUNCTION BOX ON THE VEHICLE SUPPORT PLATFORM CAN BE OPERATED FROM ANY POSITION ON THE LAUNCH PAD ACCESSIBLE WITH THE 50-FOOT CABLE LENGTH. THE PORTABLE REMOTE CONTROLLER W I L L OVERRIDE THE CONTROL CONSOLE IN THE BLOCKHOUSE WHEN THE UNIT I S PLUGGED INTO THE LAUNCHER RECEPTACLE.
C-6062-170
Figure 4-8.
SUPPORT ARM
UMB PLUG
UMB MAST
SUPPORT ARM
I
Figure 4-9. Console Controls for Support Arms and Umbilical
I
C-6062-171
4-11
UM BI L ICAL ARM UM BlLlCAL ARM PIVOT ACTUATING CYLINDER BLAST SHIELD UM BlLlCAL
THE SUPPORT ARM FOR THE PAYLOAD UMBILICAL HARNESS WAS P I V O T - M O U N T E D T O T H E T O P O F T H E L A U N C H E R M A S T . THE ARM WAS FABRICATED FROM 3-INCH TUBING APPROXIMATELY 10 FEET LONG. A PNEUMATIC ACTUATING CYLINDERANDCONTROLVALVEOPERATEDTHEARMTHROUGH A 20-DEGREE ARC AWAY FROM THE PAYLOAD. FOR VEHICLE 1 2 - 5 0 - 1 LAUNCHING, THE UMBILICAL ARM ACTUATING CYLINDER WAS MECHANICALLY LOCKED IN THE F U L L Y EXTENDED POSITION BY A LOCKING SLEEVE TO PREVENT ACTUATION.
CYLINDER
4
THE RETRACTION SYSTEM IS MOUNTED ON THE TOP OF THE LAUNCHER MAST AND INCLUDES ARECTANGULAR SUPPORT FRAME, LEVERS, CABLES AND ACTUATING CYLINDER. LEVERS PIVOTED BY THE CYLINDER ACTUATE CABLES AND PULLEYS TO RETRACT THE DISCONNECT BLOCK; ADDITIONAL CABLES W I L L UNLOCK THE DISCONNECT BLOCK IF THE PRIMARY SYSTEM FAILS. THE PNEUMATIC SEPARATION SYSTEM INCLUDES A THREEWAY, TWO-POSITION SOLENOID VALVE, A RESERVOIR AND CHARGING PANEL WITH TUBING, GAUGES AND VALVES. THE UMBILICAL SEPARATION AND RETRACTION IS ACCOMPLISHED BY TWO SEPARATE BUT INTERCONNECTED SYSTEMS; (1) PNEUMATIC SEPARATION SYSTEM WHICH ACTA UATES PLUNGERS IN THE DISCONNECT BLOCKAND FORCES THE BLOCK AWAY FROM THE VEHICLE PANEL, ( 2 ) A RETRACTION SYSTEM WHICH PULLS THE DISCONNECT BLOCK OUT OF THE WAY OF THE VEHICLE. THIS SYSTEM ALSO CONTAINS BACKUP SEPARATION LEVERS AND CABLES WHICH ASSURE DISCONNECT.
C-6062-172
EACH OF THE ARMS WAS " SUPPORTED ON THE MAST BY TWO RECIRCUI_ATING, BALL-TYPE TRUNNION BEARINGS.
SUPPORT ARMS PNEUMATIC CONTROL SYSTEM WAS ACTIVATED PRIOR TO VEHICLE LIFT-OFF BY DEPRESSING THE UNLOCK PUSHBUTTON ON THE BLOCKHOUSE CONTROL CONSOLE. ATENSION LOAD THEN APPLIED ON THE SUPPORT ARMS; AS THE VEHICLE LIFTED OFF THE LAUNCHER AND THE VEHICLE HOOKS CLEARED THE ARMS, THE ARMS RETRACTED A MINIMUM OF 10 INCHES IN APPROXIMATELY 0.6 SECONDS, CONTINUING TO 20 INCHES AT 1.4 SECONDS TO PREVENT INTERFERENCE WITH THE VEHICLE.
TWO RETRACTING VEHICLE SUPPORT WERE MOUNTED ON EACH SIDE OF THE LAUNCHER MAST AT APPROXIMATELY THE 30-FOOT LEVEL AND ATTACHED TO HOOKS ON THE lAUNCH VEHICLE FOREBODY. THESE ARMS SUPPORTED THE LAUNCH VEHICLE WHEN THE SUPPORT PLATFORM WAS TILTED TO AN ANGLE WHERE THE C.G OF THE VEHICLE/PAYLOAD FELL OUTSIDE THE VEHICLE BASE FOOT PRINT AND RESISTED LOADS DUE TO WINDS AND SEISMIC DISTURBANCES.
THE VEHICLE SUPPORT ARMS RETRACTED STRAIGHT BACK FROM THE VEHICLE. THE SUPPORT ARMS WERE SPRING LOADED TO ACCEPT VERTICAL CHANGES IN THE VEHICLE DUE TO TEMPERATURE AND DISTORTION DUE TO C.G. SHIFT IN INCLINATION. THIS FEATURE ALSO PERMITTED THE ARMS TO FOLLOW THE VEHICLE APPROXIMATELY ONE (1) INCH AT RISE OFF ASSURING THAT THE VEHICLE WOULD NOT FALL IF THRUST BUILT UP SLOWLY. THE SUPPORT ARM DESIGN ALSO PERMITTED ADJUSTMENT FOR VEHICLE MISALIGNMENT IN ALL AXES.
C-6062-173
Figure
4-11.
Support
Arms
Mechanism
systems Every
mission made
surveillance GSE was or 248 items and commeritems for the purchased checkout 70 were
of
to use NASA
through used
of
not including in OCP by Convair. standard H program. The major the and air items
tools 12-86009.
purchased The
by NASA, items
standard specifically
purLittle
remaining
manufactured
areas
were for
the
consoles the
and motor
used
for
system and
conditioning and
maintaining items
equipment, multi-use
environmental generally
miscellaneous CONSOLES The rack and receptacle counters concerned control panel were with
connectors.
catalog basic
or subsystems.
4-13
o_-,I
r_ I r/l
_j o ,_ .._ n,_
.J
t/l
z ..I-
I
_,-I
4-14
ADJUSTMENT E LEVATI ON AZIMUTH FOR BUILD-UP FOR LAUNCHING POINTING ACCURACY ELEVATION AZIMUTH LOAD CAPACITY STABILITY IN WIND (ANY LJ-II-S/C COMBINATION) 30 MPH 60 MPH 100 MPH SPEC. +15' +30' VARIABLE FROM 90 TO 75
90 TRUE .315 TO 45 TRUE MANUAL INFINITE INFINITE 270,000 REMOTE +i0' :_ 6' LBS SPEED 5/MIN 18/MIN
PAIR - STATIC PAIR - DYNAMIC EACH - DYNAMIC PROCEDURE - TALLEY WEIGHT SHIPPING
LBS
NUMBER OF TRAILER LOADS MAXIMUM MODULE WEIGHT PRINCIPAL STRUCTURAL ALLOWABLE STRESS FOR DESIGN MATERIAL
3 33,000
LBS
PLANAR AND SINGLE CURVATURE IRREGULAR SHAPES SUPPORT ARMS ENGAGEMENT AFTER LAUNCH TIME TO 10 INCH CLEARANCE FROM VEHICLE TIME TO 20 INCH CLEARANCE FROM VEHICLE MATERIAL TEST REPORTS UMBILICAL RETRACTING SYSTEM
TRANSITE FLAMEAST!C
700
--_-1"
NOT APPLICABLE ON ON + X AXIS OFF + Z AXIS TEST REPORT - A-O01 & A-O02 TEST REPORT - A-O03 & A-O04
Figure
4-13.
Parameters
4-15
"_I
...
4-16
C-6062-177
Figure 4-15.
_----I_
"_
_ _ -
Figure 4-16.
4-17
Figure 4-17.
C-6mz-180
Figure 4-18.
4-18
NO.
1 2 3 4 5 6 7 8 9 10
MEASUREMENT FIN REACTION MOTOR CHAMBER PRESSURE REACTION CONTROL VALVE INPUT SIGNAL REACTION MOTOR FUEL PRESSURE HYDRAULIC VALVE INPUT SIGNAL AIR TEMPERATURE FUEL MANIFOLD TEMPERATURE FUEL TANK TEMPERATURE MOTOR FUEL TUBE TEMPERATURE FIN CONTROL SURFACE POSITION
12-51-1 2 1 1 1 3 2 2 2 1
12-51-2
12-5-3
2 1
1 1
1 1
C-6062-181
Figure
4-19.
Fin
Test
Stand
Measurements
basic
used
the only
to accommodate
12-50-1
RF command
Vehicle
12-51-1
control console.
console was used. Figure The left-hand module was and vehicle systems were
4-20 shows the dual console with the devoted to attitude control and instrucontrolled and monitored by the right-
mentation; launcher hand module. For was control With One tance set operations systems; the was see
at the
CSTF
for
the
last
three the
vehicles, hydraulic
provided
to permit
and monitoring
of both
were
manufactured. Accep-
Manufacturing
Evaluation
Predelivery
Acceptance
4-19
Figure 4-20.
Blockhouse Consoles
4-20
EQUIPMENT The pad used. cuit delivery building. The following where a single power
BUILDING) structure) could items for for the other was the nearest For location the first two to the racks launch were and was cirthe
equipment catalog
two vehicles,
remainder components.
vehicles,
facility-furnished
ing switching
arrangement
summarizes
the
functions 12-50-1
performed & 2
X
in the 12-51-1
X
equipment 12-51-2
X
racks: 12-51-3
X
1st stage ignitioncontrol 1st stage ignitioncurrent monitors Launch RCS sequence timing
prepulse timing AIR CONDITIONING The air conditioning Engineers, in a trailer or 229,000 was the 34% relative concept the since was the for see and van, BTU unit was
a recirculating (*). The New Mexico. to deliver heating air and module 7480
with
of Engineers
designer
Bridgers 338,000
Consulting
equipment, BTU per hour on and unwhen to it was was The tower plan was
to maintain
humidity to mount command and for QTV interfered for 4-23. Missions use Short, ducting
hot day
equipment range to retain the see vehicle, and air air Figure
on the Little
to integrate satisfactory ment the Little found servicing designated tower; ducting were tower Joe that
command
module
requirements. conditioning
require-
it was and
Flexible
with A-002,
servicing A-003,
emergency tower
ducting
installed
connections conditioning
vehicle-to-tower
Report T-12-10,
4-21
-Figure 4-21.
4-22
l,,lt,,'
I!' I
Equipment Racks
C-6062-184
Figure 4-22.
Air Conditioning
Original Configuration
Initial planning for support of the reaction control system anticipated that Redstone o r Project Mercury GSE would be suitable, but the vehicle system required larger and different equipment. Some vessels and components from the Project Mercury trailer were used on the hydrogen peroxide servicing trailer and the pneumatic trailer. The principal changes in the hydrogen peroxide trailer, shown in Figure 4-24, were installation of a scale and 80-gallon capacity scale tank to weigh the hydrogen peroxide instead of measuring from a calibrated sight glass. The scale weighed the feed peroxide, the overboard return, and the fuel removed to provide ullage, thus eliminating sources of e r r o r in reading several gauges, as experienced on other programs. The peroxide transfer to the reaction control systems was accomplished by nitrogen pressure; however, the transfer from the shipping drums t o the trailer was successfully accomplished with a positive displacement pump.
Other GSE t o service the reaction control system included Teflon-lined servicing hoses , emergency showers , vent and defueling adapters , dump tank, maintenance tools , a high pressure nitrogen trailer, a dust-free enclosure for conditioning peroxide components, and a vacuum drying system. The vacuum drying system, shown in Figure 4-25, used a Kinney vacuum pump and liquid nitrogen cold traps to reduce pressure inside the reaction control systems to 1 millimeter of mercury absolute press u r e , s o that all peroxide would evaporate and be removed from the system between checkout, servicing, and launch.
4-23
C-6062.185
Figure 4-23.
Air Conditioning
Final Configuration
C-6062-186
C-6062-187
Figure 4- 25.
AERODYNAMIC CONTROL SYSTEM EQUIPMENT The pneumatic trailer (Figure 4- 26) provided nitrogen for the aerodynamic control system as well as for the reaction control system. The trailer had four, 6OOO-psi, one-cubic-foot nitrogen bottles and four dispensing systems furnishing nitrogen at nominal pressures of 25, 450, 3000, and 5000 psi. The bottles and many of the valves, regulators, and gauges were salvaged from the original trailer. Wet gas posed a problem on Vehicle 12-51-1 in spite of an existing drier system used in charging the storage bottles; therefore, an additional dryer was installed on the pneumatic trailer between the storage bottles and the regulators, to eliminate freezing of the regulators. Increased size of the aerodynamic control system in Vehicle 12-51-2 made it nece s s a r y to supplement the pneumatic trailer gas supply with large high-pressure storage bottles. Two bottles with a capacity of 1 2 cubic feet each at 8500 psi were furnished, to reduce the number of times it was necessary to call upon the WSMR Propellant Service Section to recharge the storage bottles. These bottles were connected to the pneumatic trailer by flexible hoses to utilize its pressure reduction and drying facilities. Servicing hoses were provided with the trailer. High pressure nitrogen of -100" F dew point was obtained by use of a Sprague S-3600 WB-100 booster, which was used to pump nitrogen from a 2000-psi tube trailer to a pressure of 6000 psi for the pneumatic trailer and 8500 psi for the high pressure storage bottles. The booster was 4-25
C-6062-188
Figure 4-26.
Pneumatic Trailer
powered by compressed air. The air compressor, nitrogen tube trailer and gas dryer were furnished and operated by WSMR personnel. Two hydraulic service units were provided. The first unit was an Ordnance Corps unit originally furnished for the Nike program; see Figure 4-27. This unit had a capacity of 3 gpm at 3000 psi and was used to test individual ACS at the CSTF and for servicing the ACS for launch. When performing vehicle integrated Operational Checkout Procedures a larger Ruckers hydraulic unit was used; see Figure 4-28. This Convair-furnished unit had a capacity adjustable between 40 gpm at 0 psi to 10 gpm at 3000 psi. The necessary servicing hoses and test manifold were furnished as GSE. Since there was a possibility that oil contamination could have caused failure of Mission A-003 the cleanness requirements for hydraulic oil were made more stringent. As a consequence: 1) a new test manifold was furnished for the integrated testing, and indiuidual system GSE filters were installed at the factory and remained in place until launch preparations were complete; 2) the GSE Military Standard type hydraulic hoses were replaced with Teflon tube hoses and new sampling p a r t s were provided for u s e of Millipore Bomb Sampling; 3) the hydraulic c a r t s were dismantled, cleaned, filtration rearranged and Bomb Sampling parts were provided - NASA furnished Bomb Samplers; and 4) hydraulic oil cleanness requirements w e r e increased along with education and surveillance.
4-26
i
I
I
I i
c
i
k f
ta
C-6062-189
Figure 4-27.
A plastic shelter was set up at the Control System Test Facility (CSTF) r preparation of the Millipore Bomb monitors and for quick microscopic examination of the exposed monitors. Official analyses of the monitors and bomb samples w e r e made by the Chemistry-Metallurgical Laboratory of the Army Missile Test and Evaluation Directorate. These contamination control efforts were very effective. OTHER GSE A dust-free, controlled area was required at White Sands for installation of reaction control systems on the fin structures. As no suitable facilities were available, Convair furnished a 15-fOOt diameter by 15-foot high air-supported vinyl fabric tent which would accommodate a complete fin mounted on a fin test stand, and the necessary work platforms; see Figure 4-29. The tent was designed for use inside a factory building and was assembled with Velcro zippers. The tent could be readily dismantled and folded for storage o r shipping. Convair furnished slings and handling dollies for handling the vehicle airframe and all components except Algol engines; see Figures 4-30 and 4-31. (All handling equipment for Algols was furnished by Aerojet through NASA.) Stress analysis and design margins f o r handling equipment a r e given in Stress Analysis, Ground Handling Equipment, Little Joe II Vehicle, GD/C-63-041. Special work platforms were used for installation of the destruct system and for servicing the ACS and RCS on the launcher.
4-27
Figure 4-28.
4-28
C - 6 0 4 2 -19 1
Figure 4-29.
Figure 4-30.
C-6062-193
Figure 4-31.
4-30
application ladder
for for
Vehicle access
12-51-2 in the
was
the
adaptation
of a Coast primacords
Guard and
Standard shaped
vehicle
to the destruct
among and
the
GSE was
60 mph; standard
of alignment
special
GSE DOCUMENTATION One field and of the most significant for improvements Standard each to commercial items. military item standard Early in the program was required requirement were taken implemented a Performance caused to avoid unnecessary these highin the
of GSE Interface
of GSE.
duplication documentation cost traps; as vehicle the material documentation, NASA mum cost, Directive
and unreasonable
tools (jumpers, switches, lights, etc.) were categorized than GSE; component test aids were considered part of These a loss the efforts of cost problem produced accountability. of providing for the GSE following support new equipment Program at miniManual the equipment without high-cost
accordingly.
Convair-Pecttliar Interface acceptance Standard standard description. Specification. Non-Standard test This harnesses category drawing 6 receptacles, included and was GSE of more items and Performance testing. GSE The
detail 8 hours
Specifications,
Test was
- This testing
which
by a blanket
Test
- This Test
category more
25 wires by a blanket
6 lights covered
in Functional Interface
performance. Specification
Performance
requirements. Low-Cost tool, This GSE - This work was category or test was covered box, consisted where of a simple configuration and the Interface design and conversion control task was was less
mechanism, category
close-tolerance
Performance
Specification.
4-31
FTI Tools - This category consisted of test harnesses of less than 25 wires and a black box having no more than 6 switches, 6 receptacles and 6 lights used in FTI performance. No specification covered this category. These tasks were not charged to the GSE budget.
Figure 4-32.
C - 6 Ob2 - 194
4-32
LAUNCH
OPERATIONS
LAUNCH
OPERATIONS
A.
ORGANIZATION The Convair Launch Operations Predelivery Launch managerial of whom were carried Range one Missile The Organization Acceptance Vehicle concept had the out Operation, applied responsibility at the New factory Mexico. at the checkout there Off-Site test crew would launch site anticipated be used was that that for about factory of the organized continuity operations. Engineermaintained Instrucand on Little at the Factory, and other to this for Joe II performed Assembly activities launch the at Launch of Convair for see launch at Deputy
functions Site, WSMR Program Figure site, White The one would final facility month be for
Vehicle
program
in San Diego
at the
(WSMR),
early
concept
of the
would at close
assembly
launchings
operations the
checkout between
and launch
and that
Department
as an administrative of operations custody. Other ing, tions functions Operations the were A Site
temporary was
at WSMR,
and material
in Convair's
program.
initiation
Departmental personnel
established
guidelines
of responsibilities
to be followed. program recognized, crew; used for and developed, the during as permanent the support the amount and last of activity at WSMR. year of the material between supervisors, Later, program control, launchings with a permanent facility two engineers increased. crew, added of were crew
inspection
a small
personnel
refurbishment,
maintenance. procedures were used large throughout variations the provide entire a good
of the operations
Departmental requiring
Instructions
of manpower
operations.
5-1
I
LAUNCH OPERATIONS I DEPUTY PROGRAM MANAGER
1
I
l
SITE ADMIN ISTRATION OPERATIONS
I
ENGINEERING
I I OPERATIONS SUPPORT l
Figure 5-1. Launch Operations
I I
Management
During Sands (GOM). modified The Detailed prior and issue gram Control Test
the
NASA
Operations operations,
later Department
identified
and issued
of General Joe
Operating Instructions
Since
to Little
]1 operations. primarily early in the section devoted program. of NASA a full details time to PERT. Just requested Program and pro-
original networks
documentation for reporting Operation crew 4 for and daily Operations Section Test
developed
to the authorized
schedules; more
to develop,
maintain concerning
Refer
to Volume
By NASA assists nance tainers; analysis; components for the project specialized to the items;
the
US Army These
specialized of ordcon-
operations.
assists GN 2 and
of high-pressure
storage
storage and analysis of H202; performance of hydraulic and assist to the contractor in the functional test and requiring nature. specialized equipment test equipment. and staff for This to provide moderately-used
arrangement
5-2
All post-launch reports, with the exceptionof the QTV Post-Launch Report, were prepared and edited by NASA personnel, with Contractor liaison. The QTV PostLaunch Report was prepared by Convair. B. PLANNING
A Facilities Plan defined the support neededfrom or through NASA for the conduct of the launch vehicle portion of the program. Requirements for the five launch vehicles were contained in the Facilities Plan, Report GD/C 62-166, changesA thru C, and SupplementsI andII. The material for eachvehicle was presented in the format required by WSMR. NASA integrated the launch vehicle requirements into a project level Operations Requirement for implementation. A planning activity was carried out at SanDiego on a continuousbasis. Launch crews reviewed the details of the configuration changeson the next vehicle andplans were developed and scheduledfor the tasks indicated for both facility modifications andthe assembly and checkout of the vehicle. Requirements for new or revised test equipment and spares, plus vehicle expendablesand spares, were determined. The objectives of upcoming missions were reviewed and measurement requirements for both airborne and ground instrumentation were established andcoordinated with
NASA/MSC. C. PREDELIVERY Shortly Acceptance to verify assigned which nance. did that before Testing the functions. not require Secondary ACCEPTANCE factory (PAT) vehicle This objectives completion was was introduced were effected were those subsystems TESTING of Vehicle into the 12-51-1, program. capable payload field the concept The all facility procedures of Predelivery of PAT their OCPs of orddeveloping exeron this stand. was
purpose
by accomplishing of proofing
integrated
operations
field test personnel proficiency representatives monitored the cised vehicle PAT yard and equipment 36 at WSMR used directly, the covered, in their was for and tasks conducted Vehicles and launch with during in the 12-51-2 spare complex only minor revised
in execution of the tests. NASA field operations program and exercised controls similar to those launch operations yard, was in the using field. PAT vehicle factory activity support experimental and 12-51-3 a special in the employed field
actual
employed were
the vehicle.
Ground at Launch
provided
procedures field.
deficiencies in the
OC Ps were
and reissued
5-3
D.
ASSEMBLY
The vehicle was transported by low-boy truck from San Diego to WSMR a s an assembled unit, less fins and specified components; see Figure 5-2. The structure was enclosed in a protective cover and supported at the ends by cradles. Off-loading (Figure 5-3) and de-mating (Figure 5-4) were accomplished in the VAB, using overhead cranes for all vehicles except 12-50-1; this vehicle was offloaded and de-mated at Building 1540, using mobile cranes, since the VAB was not ready for occupancy. The fins were transported on storage cradles in a covered van, and the off-loading was accomplished by fork lift; see Figure 5-5. The fins were then removed from the cradles and installed on work stands. PRE-ASSEMBLY BUILD-UP The only vehicle pre-assembly build-up required was installation of primacord in the forebody for vehicles with motor configurations which limited accessibility to routing areas. Fins for Vehicle 12-50-1 and -2 and 12-51-3 did not require pre-installation buildup. For Vehicles 12-51-1 and 12-51-2 the RCS systems were installed on the fins at the VAB, in an environment-control test. A spare attitude control fin w a s maintained at WSMR and modified to the proper configuration for each vehicle.
C -6 062 -2 1 0
Figure 5-3.
The motors w e r e stored in bunkers at the WSMR Ammo Area prior to installation. Algol motors were stored in the horizontal position on storage dollies; Recruit Motors were retained in their shipping crates. Build-up of the motors was accomplished at the WSMR Ammo Area except for the Vehicle 12-50-1 and 12-50-2 Algol motors, which were built up in a mobile environmental shroud temporarily located adjacent to the launch pad. Algol motor pre-installation assembly included: 1) bore-scoping of propellant burn surface; 2) pressure check of motors with canted nozzles; 3) igniter installation; 4) bracketry installation; and 5) thermocouple plug mounting and checkout; see Figures 5-6 and 5-7. Shaped charges were also installed for motors using adhesive bonding instead of bracket mounting. Recruit motor igniters were fit-checked and the nozzle installation and alignment indexing verified. VEHICLE ASSEMBLY
The afterbody was the first vehicle structure installed on the launcher. This section was transported to the launch pad by truck and positioned for off-loading, then hoisted with the service tower crane up and over the launcher mast, rotated f o r proper position, and lowered to the launcher support pads; s e e Figure 5-8. The support pads, pre-set for preliminary body level, were readjusted for final leveling. During installation of Vehicle 12-50-1 it was found that the service tower sealing,skirts interfered with the vehicle during the lowering operation. The skirts were subsequently sectioned to eliminate contact with the vehicle.
5-5
C-6062-211
Figure 5-4.
5-6
C-6062-212
Figure 5-5.
C-6062-213
Figure 5-6.
5-7
Figure 5-7.
C-6062-214
The motors were installed after the afterbody was positioned on the launcher; s e e Figure 5-9. The Algol motors were moved to the launch pad on transport erectors or storage cradles via flat-bed trucks. Motors on the transport erector required only the service structure crane f o r installation but motors on the storage dollies required use of an additional mobile crane for an interim transfer to the transport erectors. A Hydra-Set, connected as part of the hoisting train t o permit precise movement of the motor, w a s helpful but not mandatory. Recruit motors were moved in their shipping crates and hoisted into position by the service structure crane. The sequence of installation and motor positioning was predetermined to provide the best weight and balance relationship and maximum work space inside the afterbody. Generally the recruit motors were inserted first and all motors mounted with the minimum required attach bolts to permit all motors to be positioned and the forebody mated on the same day. The installations were completed after all motors were in place. The motor installation was completed by torquing the mounting bolts, securing firing lines to the motor cases, mounting shaped charges and connecting and routing primacord not previously installed, installing recruit motor nozzles and igniters, canting and pressure testing Algol nozzles, installing Algol nozzle boots and covers and installing Algol motor chamber pressure transducers. Algol nozzle canting and pressure testing boots and covers were applicable only to multiple-motor Vehicles 12-51-1, -2, and -3. Motor initiators were installed and connected to the firing lines as part of the countdown.
5- 8
'
.
Figure 5-8.
/-
P
I'
r
C-6062-218 -1
Figure 5-9.
5-10
Figure 5-9.
After
were the
the then
vehicle lowered
was with
moved the
and positioned and positioned the afterbody; was positioning forebody pad deck. forebody Fixed
service motors
Algol
launcher, to the
to the
attached
in alignment without
lowering checkout.
were
installed
and
hy-
draulic pallets for Vehic!es checkout at the CSTF. The pad. removed hoist fairings Movement from was mounted by Hyster the work on the service stand
12-51-2 and -3 were installed following fins were installed on work stands and was found to be the see most practical vehicle 5-11. for flight. The at the motor and positioned structure; after system for attitude vehicle ballast, case with a fabricated mounted the 12-51-3 Recruit manufacture launcher. at the Figure attach Final
applicable system moved to the launch The fins were a chain of the points, using
method.
installation
accomplished was was required different Vehicle Algol The ballast 12-51-2 The
Ballast the ballast during sisted nozzle. plates body below visions added for mating. the after
only for
location appropriate
of
assembly 0 and
installed The
were
remaining provisions
on the fins
the vacated Convair and command responsible Vehicle ment body was
entire
vehicle, missions
12-50-1.
above
alignsplice
by leveling afterbody
support
positioning.
afterbody/forebody
surface (Station 227) was checked. from level at Vehicle Station 0 was fied the for fixed-fin vehicles; Additional vertical alignment relationship procedures of the
of the service module, recorded. Fin alignment control center-line fins was on the
on attitude vehicle
5-12
--
P&w.
C-6062-216
Figure 5-10.
C-6062-217
Figure 5-11.
5- 14
Vehicle support andtie-down equipmentconsisted of forebody support arms mounted on the launcher mast, andtie-down cables. The support arms, rigged to the vehicle when the forebody was installed, were pneumatically retractable, but were maintained in an unpressurized/mechanically-locked condition until the countdown. The afterbody tie-down cables were installed to secure the vehicle to the launcher, but weather conditions never required their use. Six tie-down cables secured the vehicle to pad deadmen, but only the north and south cables were generally required. The cables were installed at the vehicle attach fittings below Station 0 after the forebody and afterbody were mated. Following forebody installation the vehicle was prepared for
ture covers nected, conditioning were and the and monitoring. the was GSE air temperature Vent seals, system air conditioning installed, system platforms work below installed of shaped conditioning ducts activated. temperatures were installed equipment access Algol motor were of the the GSE prescribed temperaconair limits. adapters and weather
recording initiated
to provide
checkout
charges for
of electrical
umbilical jumpers
harnesses
ground
edge
heat
insulation basis
was during
completed vehicle
and
the
umbilical
reinstalled TEST
on a noninterference
checkout.
section used
at WSMR on the
was Little
established Joe
to inspect
and
test, satis-
as
applicable, factory
II Program,
to ensure
accomplishment. functional defined, receipt check it was of equipment prior decided 90 days that removed to shipment; all of installation from as the the level be would in the
As originally vehicle after of reliability functionally vehicle. The ence project) with the schedules, to do all do only Figures those 5-13
equipment
WSMR
these was
tests
for and
the
first
Experi(to the
demonstrated
sporadic,
often
and could not always be accomplished desired schedule. To minimize the a Convair-staffed routine and less tests through requiring 5-15. checkout sophisticated specialized area testing.
in accordance serve project and called project; equipped upon see 5-15 to
was
equipment
not available
i
C-6062-205
Figure 5-12.
I
C - 6 0 h 2 .Ob
Figure 5-13.
5- 16
C-6062-207
Figure 5-14. r
I
C-6062-208
Figure 5-15.
(normal} Instructions.
receiving Test
was
performed test
in NASA-approved performed was systems in accordance by the engineers. etc., Test was witauthorized
of components
Functional Sheet
Preparation Testing
nessed were
by the documented
engineers
and
NASA Quality
Assurance.
results
assigned Assistance
technicians
flight from
2100 of those
items tested
plus and
removed Little
received
II Program.
at WSMR: Type All types All types All types All types Regulators A/C A/C inspection level & D/C & D/C program and Item Gyros Gyros Autopilot Autopilot Type Rate Attitude Logic & Control
at the bench
improving
reliability
of installed
FIN CHECKOUT Integrated functional 4.C. safety fins The testing control CSTF of the system was reaction was located control away from system for the other and the first time structures hydraulic at the and porCSTF; roadways
tion refer
of the
aerodynamic
performed
requirements. and RCS modules This build-up were tent each testing. for received the the within fin was and built first VAB up at the of the a clean Vehicle fin and work
represented
RCS modules.
separately
on a special
5-18
testing
precedence, testing
RCS testing
be readily marizes
a minimum
on schedules.
System
GN 2 Leak
Hydraulic System
Check
H202 Servicing, Conditioning, and Surveillance Motor Vacuum Bladder Routine Troubleshooting Sheets (TPS's). ing compressed sion of these G. VEHICLE Little 2) Motor 5) Vehicle checked was cedure tingencies. The (OCP). letter quirements 4) Safety data sheets. and and basic The document OCP and was used for checkout Joe tests or were Performance Drying Leak Check controlled tests Tests
Fin Response
De-Fueling
special
The WSMR
laboratories
GN 2 and performing hydraulic fluid tests the fins were ready for installation CHECKOUT H Launch Vehicle Checkout was
At the vehicle.
categorized Facility
as:
1) Launch (CSTF); the facilities Motor checkouts after schedule and the
and Installation; and 6) Integrated motors during assembled vehicle was launch Integrated
4) Fin Checkout;
In general, assembly. initiated test plan fin and vehicle were basic
accomplished as required
for operational
was
the
Checkout controlled
release Special
procedures Station
Equipment; Test
Post-Test
5) Step-by-Step by Test
Special
Preparation
5-19
Field were, format. with test vidualized facility at WSMR. cedures Each WSMR mance
checkout This
of the
first
was revision
which
checkout equipment,
to a standard compatibility with 12-51-1 same vehicle. by NASA/ the perforindithe procompliance identical
resulted
in extensive
Starting Apollo
to that
prepared
of the
at the Subsystem
reviewed
approved authorized
personnel of the
Managers.
A TPS
Deviations
OC P were
on Document
Deviation
Sheets.
Deviation usually resulted and deletion of power-up next nent. OCP The and review Change permanent
additional engineering monitoring, to conserve time in starting the classified into the as Temporary issued document or by Perma-
changes
incorporated
Engineering
(ECN). configuration original was TPS. eliminated Convair solutions, event changes Originally, maintained associated a separate all a Daily and with TPS an OCP was associated Record configurawere required test
Troubleshooting delineated for each for activities (DOR) tion by Mod operation detailing
and resultant Sheets but this problems to the method In addition, and
so as to maintain correlation
as a package.
Operation component
histories. Pre-test briefings and status of additional procedures personnel, was were under of results, were review. held for OCP familiarization, the OCP another incorporation briefing was of known held results, for genand
Following
and troubleshooting
and
mechanics
by of
of system
engineers.
identified
by Engineering
signature
stamp-off. of each vehicle (including The power preparation the the fins as applicable} included and OCP's: control, the launcher launch facil-
checks
of long-run positioncalibration.
distribution following
validation,
instrumentation
5-20
Console
Command
- Facility The
verification
Following individual system checkout the overall for integrated operation by an integrated vehicle out at the checkout CSTF OCP's
- Instrumentation - Algol Motor Chamber and Pressure Transducers - Signal Complex - RF Link - RF Command Safety - Lanyard - System System System Pull Test Checkout Accelerometers
- Ignition System - Resistance - Firing - Attitude - Logic - Autopilot and Integration - Integrated - Pneumatic - Electrical - Integrated
Measurements
Currents System Sensors Control with System Leak Check System Unit Fins
Control
- Range
Power Vehicle
H.
OPERATIONS completion basically with test of initiators, the proofing of the ready the range that etc., above integrated for was and flight. conducted NASA. vehicle The OC P the testing of flight as Integrated During Vehicle this Test period launch vehicle which with station staffed installatest were
was
further
payload,
installation
batteries,
payload
assignments organizationally by NASA personnel. The format viding launch the and for test procedures used of Apollo of Electronic
of Launch
Engineer
for
the
were 2. made
The
organizations,
refinement
published
of integrated
operations.
on-station,
5-21
the
the
as operating directly
or control
case vehicle
spacecraft vehicle
used the
as a control Simulated
procedure. the
and Countdown, and sequenced procedures. testing. progressed, refined. to summarize on the progressed. is given
of separate
identifies
procedures
during
As the test ational the best purpose emphasis Notation achieved phase techniques model of this has is made of the
operthe
operation
(on Vehicle
became
plans
and goals
the latter
placed
integrated
test
series. in this
as necessary
to illustrate in Figure
improvements
A listing
procedures
FINAL SYSTEM VEHICLE 12-50-1 12-50-2 INTERFACE N/A OCP-A-1099-BP12 INTEG N_/A OCP-A-0008-BP12 SYSTEM SIMCOUNT GD/C GD/C 63-072 63-085A B CHECK N/A N/A N/A COUNTDOWN GD/C GD/C 63-072B 63-085A
OCP-A-0059-1-BP12
OCP-A-0010-1-BP12 0CP-I-12-08901
Z2-51-1
OCP-A-1099-BP23
0CP-12-86019(51-1) OCP-A-0008-BP23
_ _
Z
o
Z O O
12-51-2
0CP-I-12-86025 OCP-A-1099-BP22/TD
N/A
_ (3
(J
m LLI N/A
m LIJ
12-51-3 OCP-A-1099-SCOO2/TD
Figure
5-16.
Integrated
Operations
Procedures
5-22
INTERFACE
TESTING test operations for each vehicle (except for the checkout. These Interface Tests demonstrated vehicle vehicle. concluding in the and spacecraft with and verified with circuit simulated configuration. spacecraft ring-out, mission, Flight Starting QTV) was a suitable isocircuitry progressing these with tests of these connection through
The initial integrated launch vehicle/spacecraft lation routed power-up verified between through systems the the launch launch and operation
Beginning fully-assembled
conditions
a modified
INTEGRATED The the and Interface spacecraft of demonstrating payload. and mission,
Tests used with the first two vehicles (12-50-2 and 12-51-1} did not include satisfactory To fulfill that provided amount the heart was simultaneous requirement, the of test of the required effort test. the overall
involving integrated a simulated mission operation Systems - this the configuration of eliminating the of the Test test
Integrated
repetition
redundant Interface
testing, later in the program a simulated Test and the Integrated Systems Test was SIMULATED By this vehicle/spacecraft testing of the range minimal substitution simulated ficiency had final was stage COUNTDOWN of the operation, was adequate
assurance
gained
that
combination
in flight-ready
Nominally,
all previous
been conducted system checks between significant; with minor concerned of a gas the the
on a non-time-sensitive and Countdown procedure operations Countdown, filled for reaction that as deletion Simulated items
basis. There remained the to be used for launch where and the essentially support a copy These installation operation, provided of the final deviations provision
by the
and connection,
blow-down
lift-off signal in lieu of pulling umbilicals, etc. In each case, crew was increased and minor refinements for the procedure established. CHECKS AND COUNTDOWN required the countdown; of the hydraulic, The system, of other flight stray for launching Figures checks, and each 5-17 system and proper reaction vehicle and initiator provided checks, control for were the Final simulated installation. systems final final
systems
see
5-18.
voltage
flight
as applicable.
and arming of the ignition system, The countdown resulted in a successful results is presented in Section 1.
A summary
of flight
5-23
I
v
r_ 0
0 ,=
_,_
5-24
I.
ASSIST (Figure 5-19) for with consisted office, five IRIG the and 5-24) PAM/PDM back two equipment of two telemetry workshop FM receivers, standard capability included: bargraph telemetered and had of electric displays; data; two vans the and data capability from speed tape four r_uL-u_r_; ........... calibrators and an anteroom displays of detwo compen-
which
space equipped
real-time signals
subcarrier
simultaneously,
two complete
magentic
communications:
36-charon.e! required
Visicorder;
Kennedy new
were
shipped was
Missile
modified,
equipment
All real-time and were spacecraft fication flight were NASA. flight pen calibrated checkout tapes verification copied Also tape recorders after were
displays
set
station, vehicle and veriand tapes and the and also re-
and operated and launching played back by NAA and each flight, by NASA
All NAA on-board station each flight, personnel extracted recorded telemetry by Convair all on-board for the
station
analysis data
Convair at WSMR
for use
Houston.
In some stations
accomplished by using corded on the on-board J. RECOVERY Recovery flight of the sonnel. the tools preservation salvage hardware. launch and Customer teams The vehicle, and equipment
by WSMR
locate, control
inspect
and assigned
all Convair
personnel
range
teams
to make
evaluation
hardware
positioned selected
in the areas.
vicinity safety,
of the the
area.
on personnel
information, operations
Following
vehicle:
5-26
C-6062-199
Figure 5-19.
Trailer Complex
Figure 5-20.
Service Area
C-6062-200
5-27
<
Figure 5-21.
Monitoring Equipment
Figure 5-22.
5-2 8
Receiving Antenna
Manually Tracked
C-6062 -203
Figure 5-23.
Recording Rack
C-6062-204
Figure 5-24.
Vehicle downrange
QTV, feet
Launched
1963 of the
- Impact launch
occurred heading.
48,300 The
cross-range
vehicle
first and the wreckage was were fin accelerometers, was made of the base recovery necessitated system. Apollo Mission A-001
An in-flight
of the
of components
and pyrotechnics
12-50-2,
(BP-12),
Launched
13 May
1964
- Earth
impact for the vehicle base of the vehicle were scattered hardware, Recovered batteries Vehicle main to the area; were almost mand launch predicted see Figure deactivated all the destruct Vehicle vehicle feet was from impact downrange. formed their Upon burned impact. System pilot ered ingful which was declared were: components and two relay 12-51-1, vehicle recovery
occurred 11,592 feet downrmnge; see over an estimated seven-square-mile to have one a post-flight one engineering antenna coupler, antenna,
F_"_rc 5-26. Pieces area. All flight value, was returned. two one S&A unit,
boxes. Apollo Mission area location; was A-002 however, fins were A search most (BP-23), the debris Launched 20,000 was feet 8 December downrange, over 1964 very a large - The close
impact
approximately
scattered
5-27. The four and recovered. required module items assembly. Apollo over to the stations. second-stage propellant located, (CSTF) for
located and the reaction control subsystems of the area resulted in the recovery of of the boost protective cover and the com-
except
12-51-2, occurred
1965 2000
Therefore,
revised original
recovery
and the
equipment
motors of hydrogen
ignited
and
great the
of
to a distance analysis.
from returned
peroxide The
Control autorecovthat
instrumentation
systems, with the exception and returned for analysis. damage analysis Vehicle and contamination difficult. 12-51-3, intact Apollo
pitch programmer and a relay box, the post-flight investigations it was during recovery operations
shipping
occurring
made
mean-
1966
- The
fell
approximately
100 yards.
impact, Disposal
two hours.
Ordnance
slightly
by the explosion of a destruct no anomalies and the following sequence and fin timer, RF command servovalve.
and control
5-30
rl I
0
I
I n
cy
%I -
5-31
Figure 5-26.
l/+,ilt>''
ii
>
K.
REFURBISHMENT The blast damage items was some number, Damage to the are launcher classed size as a result severe, these under from of vehicle major, categories to launch, motors for: for exposed arm actuators; ignition - refer probably ignited the and lift-off Typical by the (Figure and expan-
may There
be categorized
in three variation
classes: launch
and position
structure on the
assemblies,
or otherwise support
- including jumpers;
any exposed wiring such fire brick (miscellaneous). Major the vendor, or Blast Damage actuator
on the
grounding
- The for
support
arms,
arm
actuators, return to
and
NAA umbilical
refurnishment inspection from and were the and protected It was repaint
(involving
down, cables
rewrapping
sand
serviceable.
to sandblast to the
SUPPORT
A material function was maintained at the test site as a part of the administrative task. The areas covered included the following:
Shipping/Receiving - Packaging and manifesting was accomplished at Building 1540 in the WSMR Technical Area. Vehicular schedules were maintained to the terminal points for the several commercial procurement carries was used in the program's for logistic certain net. items
- Local when
accomplished schedule
standard
necessary
commitments. were company maintained. was policy; see Storage accomplished Figures 5-31 of
- Stocks including
spares,
of government
regulations
5 -33
I '
%$' . _.
A
b
e
J1.Y
.
C-6062-224
,.Pl*l-
Figure 5-28.
5-34
C-6062.225
Figure 5-29.
The off-site launch operations activities required efficient and timely logistics support from the factory in order to meet the desired schedules. A Test Base office was established at San Diego to support the field logistics requirements. Operations of this office, while within the framework of company standard procedures, w e r e on an expedited basis and covered the several aspects of shipping, receiving, procurement and dispatching. Telegraphic documentation was used to authorize logistic action. The following a r e typical of the actions expedited o r monitored to support field schedules: procurement of spares; follow-up and shipping--critical shortages; repair of Convair-rejected equipment; shipment of facility and ground support equipment; shipment of parts and material per planning card specification; shipment of engineering releases; procurement and forwarding of operating and office supplies; maintenance of mail bag service via air freight; maintenance of centralized area for receipt and shipping of Convair parts, material, mail and documentation; direction and manifesting of special shipments via expeditious methods; performance of coordinating activities as requested between test site and all factory departments; and scheduling of OCP test tools to support field operations.
5-35
L-OUbL-Llh
Figurc 5-30.
5-36
Lmncher Eleva ion Jack Boot and Wiring A f t e r Exposurc to LiftOff Environment
. . -_. __.
-. .
Figure 5-31.
C-6062-197
Figure 5-32.
RELIABILITY
RELIABILITY
A.
GENERAL Reliability was was the prime The extensive engineering. backing and directing consideration through program One from was in the a Reliability in the major management execution Specialist field of the by a group of design for given program. reasons the Little Joe II prodirectly test and in
This
implemented
of hardwareof reliability
experience of the
the unqualified
to the Reliability
the reliability
RELIABILITY A reliability
PLAN program was features planning Office of each reliability selection, included review reliability of failure; with planned active of this to achieve participation plan were: the specific reliability testing upon contact and goal reliability with the for in MSC 3) estab4) detailed on the program in all and phases at predetermined maintainability - this system cause and to 8) collection status to of subefforts to of the inte-
Joe
through
and vehicle
Joe
including
and
component
- design
considerations;
7) an effective
correction
analyzed every failure insure that immediate and analysis of reliability and vendors project contractors requirements; the earliest ability training management
or functional performance degradation corrective action was taken to preclude data - all and reporting reliability monitoring specifications and NASA; 9) continual procurement of the possible actions
problems contained
reliability
10) a test program designed to expose moment, which thereby reduced redesign and indoctrination in all critical areas.
6-1
C.
FAILURE
ANALYSIS
PROGRAM
that hardware
active failure reporting and analysis system was institutedon this program. During the LittleJoe II program, prepared. a total of 311 Failure Analysis Reports were or system functional failures which
have been grouped into 8 general categories; see Figure 6-1. Quality Control Discrepancies - Thirty percent of the functional failures were directly attributedto a lack of satisfactory quality of workmanship. Component Design Discrepancies - Thirty percent of the component up to an acceptable level. rejections resulted rejections re-
test or system checkout. Mishandling - Ten percent of the rejections were because of shipping damage, faulty installation,faultytest setup or human Unconfirmed or Cause Unknown error.
where the exact cause of failure could not be determined. Contamination - Five percent of the failures were due to foreign material contam-
OF TOTAL FAILURES 40
I
20
i
30
!
50
I
60
i
m BB
C..6062-207
Figure
6-1.
Component
Failure
Summary
6-2
Adjustment tolerance
Failures that
percent be corrected
of the
component
failures
were
due to out-of-
conditions Failures
percent
exceeded
LIMITED
STRESS
TESTING
Beginning with Vehicle 12-51-1, all mission significantflighthardware jected to a limited stress test program. tion, temperature, This program
and altitudetests which went beyond a standard functional check but reliabilitywould not be degraded.
were less severe than a qualificationtest. Care was exercised in selecting environmental levels to ensure that the inherent component The purpose by uncovering those component's accomplished and as deemed checks were operation. of these tests was to provide increased confidence in the flightcomponents having manufacturing or quality defects such as tests were Functional
deficient solder joints, loose connections, intermittent shorts, etc. These necessary following repair or modification of components. made
following successful completion of the functional test instructions (FTI's) also accomplished following the limited stress tests to assure proper a portion of the did not potted or hermetically sealed components
In some
tests unnecessary.
receive the altitudetest. The components tests to be accomplished approval. Limited stress test procedures
to be tested, the stress levels, and specific for LittleJoe II components FTI's. during the program specific tests were not be determined they are are listed in Figure not performed, which noted test with the they rejecare defined in
DIB 12-1.027 and in the applicable component The results of all component 6-2. are tion noted resulted as NA (not from resulted of all the applicable); tests made when temperature it could
when the failure was limited stress tests. are 6-2, These nature, The the were More shown
during functional checks environment which caused columns. tested, the were because tests monitoring 47 were expense vibration function which rejected, and effort until
in the
out of 632 components results only altitude discovered functional more these than justify would tests only the and failures tests. basis during checks confidence
rejection
not have
occurred
environment. resulted was some the for accomplished failures test. increased
productive
Component
on a limited
component
on future
6-3
P/N 12-03100-3 12-03101-1, 12-03102-1, 12-04101-1 12-04102-3 12-04103-3 12-04104-1, 12-32044-1 12-61325-3, 90-03500-003, 90-15075-004, 93-78000-009, 93-783.04-002, 94-43002-001 95-10501-001 96-47701-015 97-36606-001 97-37001-023 97-37008-010 97-37042-003, 97-37225-012 97-53050-005 97-54002-025, -044, -046 97-95511-001 98-62775-002, 99-00502-013 99-04807-003 99-34914-003 -004, -005
NAME ALTITUDE GYRO L/C AMPLIFIER PITCH PROGRAMMER SERVO VALVE PRESS REG. VALVE CONTROL VALVE SOLENOID PRESS. SWITCH RECEIVER TIMER ACCUMULATOR DC AMPLIFIER FILTER, HYDRAULIC AND PNEUMATIC 004 FILTER AUDIO RATE GYRO STATIC INVERTER OSCILLATOR VOLT REGULATOR RELAY RELAY RELAY RELAY POTENTIOMETER POTENTIOMETER MULTICORDER SWITCH-POWER TRANSDUCER TRANSMITTER RELIEF VALVE TOTALS
TOTAL REJECTED 1 1 1 6 2 0 5 0 0 1 9 0 0 2 1 O 0 0 0 0 0 3 0 1 1 5 0 8 47
VIB. 0 0 0 * * 0 * 0 0 NA 1 0 0 * 1 0 0 0 0 0 0 3 0 * 1 * 0 * 6*
TEMP. 1 1 1 * * 0 * 0 0 1 1 0 0 1 0 O 0 NA NA NA NA 0 NA * 0 * 0 * 6*
ALT. 0 0 0 NA NA NA NA 0 NA NA NA NA NA 0 0 0 0 NA NA NA NA NA 0 * NA NA NA 0 C-6062-208
-3 -3
4.
THRU-024
NA *
Figure
6-2.
Results
of All Component
Tests
Made
During
PrOgram
E.
COMPONENT During
BURN-IN the failure were occurring failures the first time expended. analysis when occurred 50 hours. history available A study reporting very little of component during Results might 12-51-3. a burn-in results failures five study hours indicated was hours are time was that usable made most life which in somefor of of
the
component
of the predicted
the component indicated Figure what; autopilot F. and 95% occurred 6-3. however, system
complete
alter
information
components CONTROL
for Vehicle
SUPPLIER
One of the major design problems purchased specifically to vendor's designed. specifications, In the future,
involved the use of off-the-shelf parts, in an application to limit for which the part was and not early the development problems
6-4
arising The
from There
this, must
detailed call
specification parameters vendor critical and and application based while and nature
to the
vendor
is com-
out realistic liaison involving to stress during of the a thorough the stages
component
classes
should
be maintained understanding
production his
and to obtain to acceptance and reliability supplier's stage, to the for the
vendor
surveillance of manufacturing
of each and
maintained
to meet should
program be demanded. an
specifications.
fabrication,
pertinent
information
component;
vendor
not constitute
withholding
information.
TIME
OF FAILURE (HOURS) 0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 41-45 46-50 51-55 56-60 61-65 66-70 71-75 76-80 81-85 86-90 91-95 96-100 101-105 106-110 TOTAL
NUMBER FAILURES 48 2 1 3 2 3 0 1 1 0 1
OF 7 75.0 3.1 1.6 4.6 3.1 4.6 1.6 1.6 1.6 CUMULATIVE 75.0 78.1 79.7 84.3 87.4 92.0 93.6 95.2 96.8 %
1.6
98.4
1 64
1.6 100.0
100.0
C-6062-209
Figure Preacceptance and environmental modes test and failure tests to a level article inspection include that must
6-3.
Summary
of Failures determination, performance tailored tailored. testing. and design verification to check The A complete
must adequate
margins.
qualification disassembly
be a production be a part
of preacceptance
6-5
procedures or event
be basically be used
be specified component.
in all test
to enable
on each
6-6
]RECOMMENDATIONS
RECOMMENDATIONS
Knowlege
gained
through
experiences of a similar
realized nature.
during The
the
Little
Joe
II program
can
possibly be applied to programs some specific recommendations. Customer's key for a clear action, change tions. Technical communications minimizes the
following
paragraphs
outline
Direction link.
- Single Clear
source
direction efficient
field rapid
the to
communication
fog factor
and promotes
economical
Design Base criteria for results specific e.g., margin reduced servicing the ground increased
Criteria rules
design
over-design Continually a design giving be determined on customer benefits have testing could and
is the product. review maximum by reviewing requirements the program; excessive significantly in the been margin the latitude test for
growth.
possible, time
due to the
Conversely, provided
servicing pressure
for greater
volume
Functional patibility organization thrust Bench the count Convair factory. systems and testing and
- Thorough repeatability numerous initially confidence. Test conducted during the final
of systems
to assure
comproper the
is highly for
termination
mock-up Tests
provided
of having
the field
benefited recognition
of system response
checkout, fixes.
immediate
of problems
Design
usage approach
costs
rather
than
the
design to the
should systems
determine
Servicing
the vehicle's
previously
Consideration
7-1
use of automated checkoutequipment. Automatic checkout equipment would shorten ignition system checkout time significantly.
Component with quality gram this mance same the and made Control - Vendor liaison. so-called to provide soon repeatability integration From cannot has been treated standpoint, components. credibility "off-the-shelf" item. control change surveillance Quality control procedure. in component in the circuitry incompatible extend must Changes performance or internal with the sysbeyond include must of the in Volume component The Early components Little in the I and Joe deals II properforrequired the philosophy functional use tended It was surveillance recommends supplier supplier's documented. find that the of this and and of the that of the a technical reliability, program
be over-emphasized.
of many
"off-the-shelf" unwarranted that developed and suppliers including has had can make noted made
components'
quality his
the
component
include procedures
to eventually
component. A change tem's function. Vendor verify further cludes that and buyer all parameters assurance
a component
test
and
equipment test
should areas.
quality limited
by a test burn-in.
environmental Control
of Testing efficiency
and activity
of one group,
and economy
inherent
guardianship
Requirements whether
specifications and contractual requirements cost and schedule effect. For example, In many
GSE specificationMSC-GSE-IA
preparing specifications and drawings and obtaining approval of them far outweighs the cost of the individual piece of GSE. Waivers to specifications and the use of blanket specifications can materially reduce end item cost and realization time. Joe II resolution of this problem GSE Documentation, is discussed in detail in Volume of this report. The Little If, Section 4. D,
Configuration Status - A configuration audit was required upon completion of each vehicle manufactured by NASA at WSMR. and checked out at San Diego, and again at the time of acceptance This configuration audit was maintained by a manual For future programs method of that and
individual recording and filingof each shop task as reflected on the completed approved planning card. of this nature, it is recommended the configuration status be maintained through a system 7-2
from
original
to establish by Quality recorded tapes rate, could timely Use grams particular, erative
record.
As factory
tasks
so that and
at vehicle would
be compared
to provide final
status.
recommends are
that
more
excellent, is of a high
management
is efficient dedicated
resident
in accomplishing
efficiently
and to schedule.
,fi
7-3
[ CONCLUSIONS
I CONCLUSIONS
O _
Joe
was
adaptable launch
of mission
requirements.
recent
successfully of the
II not only
enabled a capability
of a major sub-orbital
program
8-1
I BIBLIOGRAPHY
BIBLIOGRAPHY
for
Little
Joe 7,
on Wind
Tunnel
Tests,
Revision Joe
H with
Module
and 50 Ft 2 Fins,
Document Heating-Little
LJ-004, Joe
25 September II Booster,
Aerodynamic 1963. Air Loads for 1963; Revision Attitude Joe II,
Convair
Memo
Report
T-12-25,
20 May
Joe
II,
Convair
Report
GD/C-63-102,
May
Control Convair
Project 2 July
Test
Launch
Vehicle
- Little
Base Heating-Little 1962. Convair Convair Vehicle, Convair Convair Convair Convair on Little Convair Corps Data Installation Memo Report
Convair
Report
T-12-17,
13 November
0-09001. Guidance 5 July Little Stability Little The A-002), Joe Effect 1963). Joe II Failure Analysis Analysis, - Little Joe 1 October H, 23 July 1964. Malfunction 1963. 1963. Accuracy Study of the Little Joe II
1963
II Autopilot of Reaction
7 April System
14 September
SL-62-028. Specifications of an 0.3 Transonic December & Blitzer, Scale Pressure 1963. Exterior Ballistics of Rockets (D. Van Nostrand Co., Inc., ENG-(NASA)-29-005-63-1, Model of a Little Test Joe No. II/LEM 288) dated 28 January 1963.
and
Analysis 8-Foot
Configuration Report
Tunnel
Convair
Follin
9-1
BIBLIOGRAPHY
(CONTINUED)
Plan, Attitude
Report
GD/C
62-166,
Changes Little
A through Joe
C and
Supplements Project,
I and
II.
Control
System
If, NASA
Apollo
Convair
Joe
IT Vehicle
51-2,
NASA
Apollo
Criteria
GD/C-62-278A,
Invitation
ENG
(NASA)-29-005-64-9,
of Albuquerque, Launch Launch Launch Vehicle Launcher Little Joe Vehicle Vehicle Vehicle 12-50-1,
Convair
28 October
1963.
Maintenance If/Apollo
Vehicle, 1962.
Fixed
Flutter
19 October If/Apollo
Fin
Ground
Vibration
Test
Results,
Convair
Analysis
Using
Ground
Vibration
Test
Modes,
29 January Flutter
II/Apollo
Results,
Convair
Report
SL-63-024,
15 October Failure
12 November Little Convair Little Convair Little Convair 9-2 Joe Joe
Thrust
Misalignment 29 June
for
Mission
"J"
(NASA
Mission
A-002),
DC-12-023, Thrust
Misalignment 13 April
D-65-15, Thrust
Joe
II Design Report
Misalignment 1 November
Memo
D-65-40,
BIBLIOGRAPHY
(CONTINUED)
Joe
II Ground
Air
Conditioning,
Convair
Memo
Report
T-12-10,
15 November
Joe
II Nonlinear BP-22),
Stability Convair
Analysis Memo
of Apollo Report
Mission
A-003 5 April
(Little 1965.
Joe
II Vehicle
12-51-2/Apollo Little 1963, Little 1963. Little 1962. Little Joe and Joe
Vehicle I-III
Stress
Analysis,
19 August
12 March Convair
respectively). 3 January
Vibration
Joe
II Ground
Air
Conditioning,
GD/Convair
Report
T-12-10,
dated
15 November
Joe
II Rocket Convair
Grain
Temperature 12 June
Variation 1963.
with
Air
Conditioning
T-12-26, Air
II - Summary
Conditioning
Requirements,
Convair
Memo
T-12-14, Joe
22 October 51-2,
II Vehicle
Mission
A-003,
Failure
_na,y_,l .....
Convair
_-_ .......
D-65-17, Joe
23 April 51-3,
II Vehicle
Mission
A-004,
Failure
Analysis,
Convair
Memo
D-65-39,
29 October
Longitudinal Attack Materials RT-62-040, MIL-STD-810. June 1962. Military Military Missile Convair Monthly Base, July 1961.
Joe
II - Apollo
of
Number Joe
to 2.86, Thermal
NASA,
Protection,
Environmental
Test
Methods
for
Aerospace
and
Ground
Equipment,
and MSC-ASPO-EMI-10
Addendum.
Heating-Little Report
II Mission 10 April
Algol
Rocket
Configuration,
T-12-20, Wind
Annual Canaveral,
Distribution Florida, by J.
as a Function W. Smith
of Attitude and Wo W.
for Vaughan,
Patrick
Air
Force
NASA TN D-610,
9-3
BIBLIOGRAPHY
(CONTINUED)
Postlaunch 28 June
Report
for Apollo
Mission
A-003
(BP-22),
NASA
Report
MSC-A-R-65-2,
1965 (LJ-II 12-51-2). Apollo Mission A-003 Flight, Convair Report GD/C-65-143,
1965 (LJ-II 12-51-2). Report 1965. Report for Apollo Mission A-001 (BP-12), NASA Repo_L MSC-R-A-64-1, for Apollo Mission A-002 (BP-23), NASA Report MSC-R-A-65-1,
1964
(LJ-II 12-50-2). for Apollo Mission A-004 (CSM-002), NASA Report MSC-A-R-66-3
Postlaunch
Report
(LJ-II 12-51-3). Results Attitude of the Ground Control Fin, Vibration Convair Test and Associated GD/C-64-023, A-003 Stiffness Tests i0 January of the Little Joe II
Report
of Apollo
Mission
Report
D-65-9,
3 March
Static Longitudinal with Control 1079, Stress Revision 12-51-3, Stress Stress 28 June Vibration Vehicle, Vibration White Wind Report
Surfaces
Project
2 July 1963. Analysis A, of Little Joe II Attitude Control and Addendum Fins, Convair Report GD/C-63-037,
7 December
1965,
I, Ballast
15 October
GD/C-63-036,
Qualification Report
Tests
Installed in the Little Joe 1964, and Addendum 1963. 104-63. Convair
II I,
DF-12-101,
If, 23 June
Environment Missile
12-50,
Sands Tunnel
Reference
Little Joe
If-Apollo
GDC-63-025,
C-6062-II 9-4
(200)