PETRO JET

Project Client Job Location Document Description

Egyptian LNG Project Site Preparation BECHTEL IDKU - EGYPT


Special Safety Procedure for Radiographic Testing

.Job No 24807

.Rev 01

Date Sep 2002 1

Sheet of 5

Special Safety Procedure For Radiographic Testing

01 .Rev
Date Prepared Checked Approved

INDEX
PAGE
1- PURPOSE 2- SCOPE 3- PROCEDURE 4- ATTACHED 5- HANDLING 3 3 3 3 4

PAGE 2 OF 5 PTJ-600M-SAF-006 REV.01

1-Purpose
The Purpose Of This Procedure Is To Describe The Necessary Action To Be Taken At Petrojet site preparation To Safe Guard Its Employees And Others And To Conserve The Environment

2-Scope
This Procedure Is Established To Assure That The Safety Precautions Which Deemed Necessary To Carry Out Radiographic Test Has Been Taken (IR 192 Is The Used Isotope ) .

3- Procedure
3.1 Qa / Qc Dept. Shall Notify Safety Dept. By Enough Time (Three Hours Minimum ) 3.2 Safety Dept. Will Issue Work Permit Which Will Include All The Necessary Caution Which Includes : A-Continuous Alarm During Shooting . B- Determine The Safe Area According To The Attached Figure (Radiation Level Is Below 7.5 Sv /Hr.) The Area Will Be Determined In Cooperation With The {Q. C / Department} C-Light Alarm To Be Used. {In Case Of Night Shit Activities}. 3.3 Up On Determining The Supervised Area Safety Staff Will Start To Evacuate All Personnel Within This Area . 3.4 Radiation Level Shall Be Monitored By Survey Meter In Supervised Area (Radiation Level Below 7.5 Sv /Hr. ). 3.5 Radiation Area ( Radiation Level Over 60 Sv/Hr .) Shall Be Circled By Rope Or Any Other Mean Before Starting. 3.6- Shielding Shall Be Used Whenever It Is Possible{Collimator Or Any Other Shielding Means } To Reduce The Radiation Area And Will Be Taken In Consideration When Determining The Areas Of Concerns. 3.7- The Continuous Alarm Shall Be Stopped At The End Of The Shooting.

4-Attached :
*Diagram Illustrates The Requirement For Site Radiography.
PAGE 3 OF 5 PTJ-600M-SAF-006 REV.01

Controlled Area ( Radiation Level Up To 60 Sv / Hr )

Radiation Area

Source

Supervised Area ( Radiation Level Up To 7.5 Sv / Hr )


The Distance Of The A/M Area To Be Determined According Source To Strength Shielding Used ( Ci ) And The

PAGE 4 OF 5 PTJ-600M-SAF-006 REV.01

5-Handling of the Gamma-Ray Camera


The used Gamma-ray Camera is stored in Petrojet Gamma-ray equipments store in Brulus station project. The technician works with the Camera should has a survey meter to be sure that the Gamma-ray Camera is completely closed before transport it from the store. The Gamma-ray Camera should be transported on open car (pick up car). The Gamma-ray Camera should be put in s lined lead box, this lined lead box should be closed with a key during transportation before using the Camera. The Camera should be tied in any side of the car box with a good way.

The survey meter reading at the box surface should not be more than 50 sv/hr. and for persons on the car not more than 20 sv/hr.

PAGE 5 OF 5 PTJ-600M-SAF-006 REV.01