Beruflich Dokumente
Kultur Dokumente
Activity Description
Orig Dur
Early Start
2008 J A
2009 J
PROJECT D
MOBILIZATION
Subtotal A31 A41 SITE POSSESSION FOR MOBILIZATION AND SITE SET UP 0 0 01MAR08A 30 01MAR08A 03APR08A 29FEB08A SITE POSSESSION FOR MOBILIZATION AND SITE SET UP
AUTHORITIES INSPECTION
Subtotal A181 A541 A551 A561 DUBAI MUNICIPALITY INSPECTION SUB STATION INSPECTION AND HANDING OVER TO DEWA CIVIL DEFENCE INSPECTION DEWA INSPECTION AND ENERGIZATION TO BUILDING 403 02JUN08 390 02JUN08 0 0 0 14SEP09 30AUG09 24NOV08 07SEP09 14SEP09 14 14 14 14 14
DUBAI MUNICIPA SUB STATION INSPECTION AND HANDING OVER TO DEWA CIVIL DEFENCE INSPECTION DEWA INSPECTION AND ENERGIZATION TO BUILDING
SUMMERY OF WORK
Subtotal SUMM010 SUMM020 SUMM030 SUMM040 SUMM050 SUMM060 SUMM070 SUMM080 SUMM090 SUMM100 SUMM110 SUMM120 SUMM125 SUMM130 SUMM140 SUMM150 SUMM160 SUMM170 SUMM180 SUMM190 RAFT,WATER TANK &GROUND SLAB GROUND FLR COLUMNS TO ROOF & UPPER ROOF SLABS BLOCKWORK GROUND TO ROOF FLOOR INTERNAL PLASTER GR,FLOOR - ROOF FLOOR TILING (DRY & WET AREAS) WALL TILING FALSE CEILING WORKS-GR FLR TO ROOF INTERNAL PAINTING WORKS- GR FLR TO ROOF FLR COMPLETE PLUMBING & DRAINAGE SYSTEM & SNAGGING COMPLETE HVAC SYSTEM AND SNAGGING COMPLETE ELECTRICAL SYSTEM & SNAGGING FIRE ALARM & FIRE FIGHTING WORKS ID WORKS WOODEN DOORS - COMPLETE WITH SHUTTERS DOORS&WINDOWS,CURTIAN WL ALUM-CLADDING SKYLIGHTS 120SWIMMING POOL DECK SLAB TO FINISHES GRANITE / MARBLE & LANDSCAPING WORKS SANITARY WARE FIXING WORKS ELEVATOR WORKS (LIFTS) WATER PROOFING WORKS 497 01MAR08 99* 01MAR08 214* 24JUN08 201* 13AUG08 207* 04SEP08 216* 22SEP08 208* 22SEP08 213* 14OCT08 225* 11OCT08 242* 30AUG08 242* 30AUG08 341* 30AUG08 242* 30AUG08 401 20MAY08 270* 27SEP08 230* 20NOV08 120* 14MAR09 60* 16JUN08 207* 01NOV08 120* 30MAR09 206* 16SEP08 30SEP09 23JUN08 28FEB09 04APR09 03MAY09 31MAY09 21MAY09 18JUN09 29JUN09 07JUN09 07JUN09 30SEP09 07JUN09 30AUG09 06AUG09 15AUG09 30JUL09 24AUG08 29JUN09 16AUG09 13MAY09 0 0 7 7 4 25 33 4 0 4 4 0 4 27 39 39 39 26 0 39 30 120SWIMMING POOL DECK SLAB TO FINISHES GRANITE / MARBLE & LANDSCAPING WORKS SANITARY WARE FIXING WORKS ELEVATOR WORKS (LIFTS) WATER PROOFING WORKS RAFT,WATER TANK &GROUND SLAB
GROUND FLR COLUMNS TO ROOF & UPPER RO BLOCKWORK GROUND TO ROOF FLOOR
COMPLETE
WOODEN DOORS - C
DOORS&WINDOWS
SUBMITTALS
Subtotal SUB010 SUB020 SUB030 SUB040 SUB050 SUB060 SUB070 SUB-STRUCTURE SHOP DRAWINGS SUB-STRUCTURE ( STRUCTURAL RELATED MATERIAL ) MEP SHOP DRAWINGS MEP MATERIAL ( 1ST,2ND & FINAL FIX ) SUPER-STRUCTURE ( STRUCTURAL RELATED MATERIALS ) ALUMINIUM SHOP DRAWINGS FINISHING MATERIAL LAST PHASE ( FITTINGS ) 173 01MAR08 26 01MAR08 26 16MAR08 26 24MAR08 26 24MAR08 26 28APR08 26 11MAY08 26 10MAY08 17SEP08 30MAR08 14APR08 22APR08 22APR08 27MAY08 09JUN08 08JUN08 23 30 30 23 23 23 23 23 SUB-STRUCTURE SHOP DRAWINGS SUB-STRUCTURE ( STRUCTURAL RELATED MATERIAL ) MEP SHOP DRAWINGS MEP MATERIAL ( 1ST,2ND & FINAL FIX ) SUPER-STRUCTURE ( STRUCTURAL RELATED MATERIALS ) ALUMINIUM SHOP DRAWINGS FINISHING MATERIAL LAST PHASE ( FITTINGS )
BA02
AL GHAITH BUILDING CONSTRUCTION LLC G+11 TYPICAL < GREEN DESERT VENTURE>
Activity ID SUB080 SUB090 SUB100 SUB110 SUB120 SUB125 SUB130 SUB140 SUB150 SUB160 WOODEN DOOR
Activity Description
Orig Dur
Early Start
EarlyResource Total Finish IDFloat 08JUN08 11JUN08 29JUN08 22JUL08 26JUL08 02AUG08 27AUG08 08SEP08 11SEP08 17SEP08 23 23 23 23 23 23 23 23 23 23
2008 J A
2009 J
26 10MAY08 26 13MAY08 26 31MAY08 26 23JUN08 26 26JUN08 26 03JUL08 26 29JUL08 26 10AUG08 26 13AUG08 26 19AUG08
WOODEN DOOR SANITARY FITTINGS SAMPLES KITCHEN CABINET SUPER STRUCTURE SHOP DRAWINGS LIGHT FITTINGS ( SAMPLES ) FINISHING RELATED MATERIALS ( 1ST PHASE ) LIFT SHOP DRAWINGS BUILDERS WORK ARCHITECHTURAL SHOP DRAWINGS MAJOR EQUIPMENTS
SANITARY FITTINGS SAMPLES KITCHEN CABINET SUPER STRUCTURE SHOP DRAWINGS LIGHT FITTINGS ( SAMPLES ) FINISHING RELATED MATERIALS ( 1ST PHASE ) LIFT SHOP DRAWINGS BUILDERS WORK ARCHITECHTURAL SHOP DRAWINGS MAJOR EQUIPMENTS
APPROVALS
Subtotal APR010 APR020 APR030 APR040 APR050 APR060 APR070 APR080 APR090 APR100 APR110 APR120 APR130 APR140 APR150 APR160 APR170 SUB-STRUCTURE SHOP DRAWINGS SUB-STRUCTURE ( STRUCTURAL RELATED MATERIAL ) MEP SHOP DRAWINGS MEP MATERIAL ( 1ST,2ND & FINAL FIX ) SUPER-STRUCTURE ( STRUCTURAL RELATED MATERIALS ) ALUMINIUM SHOP DRAWINGS FINISHING MATERIAL LAST PHASE ( FITTINGS ) WOODEN DOOR SANITARY FITTINGS SAMPLES KITCHEN CABINET SUPER STRUCTURE SHOP DRAWINGS LIGHT FITTINGS ( SAMPLES ) FINISHING RELATED MATERIALS ( 1ST PHASE ) LIFT SHOP DRAWINGS BUILDERS WORK ARCHITECHTURAL SHOP DRAWINGS MAJOR EQUIPMENTS 177 15MAR08 26 15MAR08 26 12APR08 26 12APR08 26 12APR08 26 17MAY08 26 02JUN08 26 01JUN08 26 01JUN08 26 04JUN08 26 22JUN08 26 30JUN08 26 20JUL08 26 21JUL08 26 14AUG08 26 16AUG08 26 20AUG08 26 07SEP08 06OCT08 13APR08 11MAY08 11MAY08 11MAY08 15JUN08 01JUL08 30JUN08 30JUN08 03JUL08 21JUL08 29JUL08 18AUG08 19AUG08 13SEP08 14SEP08 18SEP08 06OCT08 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 30 SUB-STRUCTURE SHOP DRAWINGS SUB-STRUCTURE ( STRUCTURAL RELATED MATERIAL ) MEP SHOP DRAWINGS MEP MATERIAL ( 1ST,2ND & FINAL FIX ) SUPER-STRUCTURE ( STRUCTURAL RELATED MATERIALS ) ALUMINIUM SHOP DRAWINGS FINISHING MATERIAL LAST PHASE ( FITTINGS ) WOODEN DOOR SANITARY FITTINGS SAMPLES KITCHEN CABINET SUPER STRUCTURE SHOP DRAWINGS LIGHT FITTINGS ( SAMPLES ) FINISHING RELATED MATERIALS ( 1ST PHASE ) LIFT SHOP DRAWINGS BUILDERS WORK ARCHITECHTURAL SHOP DRAWINGS MAJOR EQUIPMENTS
PROCUREMENT
Subtotal PROC010 PROC020 PROC030 PROC040 PROC050 PROC060 PROC070 PROC080 PROC090 PROC100 PROC110 PROC120 PROC130 PROC140 MEP WORKS DRAINAGE SYSTEM WATER SUPPLY SYSTEM FIRE FIGHTING ELECTRICAL LIGHTING SYSTEM HVAC SYSTEM ALUMINIUM WORKS DOORS FRAME TILES SANITARY WARE KITCHEN CABINETS & WARDROBES MAJORE EQUIPMENTS LIFTS IRON MONGERY 297 08MAY08 250 08MAY08 200 15MAY08 250 21MAY08 250 31MAY08 167 02JUN08 187 04JUN08 105 02JUL08 60 01JUL08 90 01JUL08 120 07JUL08 120 23JUL08 120 04OCT08 120 25OCT08 90 05JAN09 19APR09 23FEB09 03JAN09 08MAR09 17MAR09 13DEC08 07JAN09 01NOV08 08SEP08 13OCT08 23NOV08 09DEC08 19FEB09 12MAR09 19APR09 39 39 39 39 39 39 39 39 39 39 39 39 39 39 39 MEP WORKS DRAINAGE SYSTEM WATER SUPPLY SYSTEM FIRE FIGHTING ELECTRICAL LIGHTING SYSTEM HVAC SYSTEM ALUMINIUM WORKS DOORS FRAME TILES SANITARY WARE KITCHEN CABINETS & WARDROBES MAJORE EQUIPMENTS LIFTS IRON MONGERY
PROVITIONAL SUM
Subtotal PROV010 PROV020 PROV030 PROV040 PROV050 PROV060 PROV070 PROV080 PROV090 PROV100 PROV110 PROV120 PROV130 PROV140 PROV150 PROV160 PROV170 PROV180 PROV190 PROV200 PROV210 PROV220 PROV230 PROV240
Start Date Finish Date Data Date Run Date
258 11NOV08 TRANSFORMER SANITARY WARE AND FIXTURES KITCHEN CABINET WORKS SWIMMING POOL WORKS GENERATOR AIR CONDITIONING LIFT WORKS LIGHT FITTINGS FOR ALL BUILDING WARDROBES SAUNA MAST AT PARAPET LANDSCAPING LOCKERS IN GYM STEAM INSTALLATION OF GATE BARRIER GARBAGE CHUTE SYSTEM WORKS AUDIO INTERCOM SYSTEM TRAFFIC SIGNS WALL MOUNTED DIRECTORY BOARD IN LOBBY INSTALLATION OF BMS SYSTEM SIGN LIGHT AT ELEVATOR MUSICAL SYSTEM INSTALLATION OF CCTV SYSTEM RECEPTION COUNTER FOR ENTRANCE & HEALTH CLUB
01MAR08 30SEP09 01MAR08 18JAN09 08:40 Early Bar Progress Bar Critical Activity
07SEP09 30MAR09 21JUN09 30JUN09 15JUL09 24JUN09 25JUN09 01AUG09 18AUG09 19JUL09 25AUG09 09JUN09 09AUG09 23JUN09 08JUL09 18JUL09 23JUL09 23AUG09 14JUL09 25AUG09 01SEP09 04AUG09 10AUG09 26AUG09 18AUG09
20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
Sheet 2 of 6 Date Revision Checked Approved
120 11NOV08 174 01DEC08 174 10DEC08 120 26FEB09 100 01MAR09 100 02MAR09 120 15MAR09 120 01APR09 90 06APR09 100 02MAY09 30 06MAY09 60 01JUN09 20 01JUN09 30 04JUN09 35 08JUN09 40 08JUN09 60 15JUN09 25 16JUN09 60 17JUN09 60 24JUN09 30 01JUL09 30 07JUL09 40 12JUL09 30 15JUL09
BA02
TRANSFORMER SANITARY WARE AND FIXTURES KITCHEN CABINET WORKS SWIMMING POOL WORKS GENERATOR AIR CONDITIONING LIFT WORKS LIGHT FITTINGS FOR ALL BUILDING WARDROBES SAUNA MAST AT PARAPET LANDSCAPING LOCKERS IN GYM STEAM INSTALLATION OF GATE BARRIER GARBAGE CHUTE SYSTEM WORKS AUDIO INTERCOM SYSTEM TRAFFIC SIGNS WALL MOUNTED DIRECTORY BOARD IN LOBBY INSTALLATION OF BMS SYSTEM SIGN LIGHT AT ELEVATOR MUSICAL SYSTEM INSTALLATION OF CCTV SYSTEM RECEPTION COUNTER FOR ENTRANCE & HEALTH CLUB
AL GHAITH BUILDING CONSTRUCTION LLC G+11 TYPICAL < GREEN DESERT VENTURE>
Orig Dur
Early Start
2008 J A
2009 J
40 23JUL09 30 02AUG09
CONCRETE WORKS
SUB STRUCTURE
Subtotal STR010 STR020 STR030 STR040 STR050 STR060 STR070 STR080 STR090 EXCAVATION WORK PCC FOR RAFT SOLID BLOCK WORK AS PERMANENT STRUCTURE WATER PROOFING MEMBRANE & PROTECTION SCREED RAFT REINFORCEMENT INSPECTION AND POURING RCC WALL & NECK COLUMN UNDER GROUND WATER TANK GROUND FLOOR SLAB 99 01MAR08 26 01MAR08 4 31MAR08 10 05APR08 10 16APR08 20 28APR08 4 21MAY08 15 31MAY08 16 31MAY08 8 15JUN08 23JUN08 30MAR08 03APR08 15APR08 27APR08 20MAY08 25MAY08 16JUN08 17JUN08 23JUN08 0 0 0 0 0 0 0 0 0 0 EXCAVATION WORK PCC FOR RAFT SOLID BLOCK WORK AS PERMANENT STRUCTURE WATER PROOFING MEMBRANE & PROTECTION SCREED RAFT REINFORCEMENT INSPECTION AND POURING RCC WALL & NECK COLUMN UNDER GROUND WATER TANK GROUND FLOOR SLAB
SUPER STRUCTURE
Subtotal 214 24JUN08 28FEB09 7
1 ST FLOOR
STR100 STR110 FLOOR COLUMN & CORE WALLS 1ST FLOOR SLAB 8 24JUN08 15 03JUL08 02JUL08 20JUL08 0 0 FLOOR COLUMN & CORE WALLS 1ST FLOOR SLAB
2 ND FLOOR
STR120 STR130 FLOOR COLUMNS & CORE WALLS 2ND FLOOR SLAB 8 21JUL08 12 30JUL08 29JUL08 12AUG08 0 0 FLOOR COLUMNS & CORE WALLS 2ND FLOOR SLAB
3 RD FLOOR
STR140 STR150 FLOOR COLUMNS& COREWALL 3 RD FLOOR SLAB 8 13AUG08 9 23AUG08 21AUG08 01SEP08 0 0 FLOOR COLUMNS& COREWALL 3 RD FLOOR SLAB
4 TH FLOOR
STR160 STR170 FLOOR COLUMNS & CORE WALLS 4TH FLOOR SLAB 7 02SEP08 9 10SEP08 09SEP08 20SEP08 0 0 FLOOR COLUMNS & CORE WALLS 4TH FLOOR SLAB
5 TH FLOOR
STR180 STR190 FLOOR COLUMNS & CORE WALLS 5TH FLOOR SLAB 7 21SEP08 9 29SEP08 28SEP08 08OCT08 4 4 FLOOR COLUMNS & CORE WALLS 5TH FLOOR SLAB
6 TH FLOOR
STR200 STR210 FLOOR COLUMNS & CORE WALLS 6TH FLOOR SLAB 7 09OCT08 9 18OCT08 16OCT08 27OCT08 4 4 FLOOR COLUMNS & CORE WALLS 6TH FLOOR SLAB
7 TH FLOOR
STR220 STR230 FLOOR COLUMNS & COREWALLS 7TH FLOOR SLAB 7 28OCT08 9 05NOV08 04NOV08 15NOV08 4 4 FLOOR COLUMNS & COREWALLS 7TH FLOOR SLAB
8 TH FLOOR
STR240 STR250 FLOOR COLUMNS & COREWALLS 8TH FLOOR SLAB 7 16NOV08 9 24NOV08 23NOV08 03DEC08 4 4 FLOOR COLUMNS & COREWALLS 8TH FLOOR SLAB
9 TH FLOOR
STR260 STR270 FLOOR COLUMNS & COREWALLS 9TH FLOOR SLAB 7 04DEC08 9 13DEC08 11DEC08 22DEC08 4 4 FLOOR COLUMNS & COREWALLS 9TH FLOOR SLAB
10 TH FLOOR
STR280 STR290 FLOOR COLUMNS & COREWALLS 10TH FLOOR SLAB 7 23DEC08 9 31DEC08 30DEC08 10JAN09 4 4 FLOOR COLUMNS & COREWALLS 10TH FLOOR SLAB
11 TH FLOOR
STR300 STR310 FLOOR COLUMNS & COREWALLS 11TH FLOOR SLAB 7 11JAN09 9 19JAN09 18JAN09 28JAN09 4 4 FLOOR COLUMNS & COREWALLS 11TH FLOOR SLAB
ROOF
STR320 STR330 STR340 FLOOR COLUMNS & COREWALLS ROOF SLAB UPPER ROOF WORKS 7 29JAN09 9 07FEB09 10 17FEB09 05FEB09 16FEB09 28FEB09 4 4 7 FLOOR COLUMNS & COREWALLS ROOF SLAB UPPER ROOF WORKS
FINISHING WORKS
BLOCK WORK
Subtotal BA4112 BA4212 BA4312 BA4412 BA4512 BA4612 BA4712 BA4812 BA4912 BA5012 BA5112 BA5212 BA5312 GR - FLOOR BLOCK WORK IST - FLOOR BLOCK WORK 2ND - FLOOR BLOCK WORK 3RD- FLOOR BLOCK WORK 4TH - FLOOR BLOCK WORK 5TH - FLOOR BLOCK WORK 6TH - FLOOR BLOCK WORK 7TH -FLOOR BLOCK WORK 8TH- FLOOR BLOCK WORK 9TH - FLOOR BLOCK WORK 10TH- FLOOR BLOCK WORK I1TH- FLOOR BLOCK WORK ROOF BLOCK WORK 201 13AUG08 14 13AUG08 14 31AUG08 14 20SEP08 14 14OCT08 14 30OCT08 14 16NOV08 14 03DEC08 14 22DEC08 14 10JAN09 14 28JAN09 14 16FEB09 14 07MAR09 10 24MAR09 04APR09 28AUG08 15SEP08 05OCT08 29OCT08 15NOV08 01DEC08 18DEC08 06JAN09 25JAN09 12FEB09 03MAR09 22MAR09 04APR09 7 7 6 5 0 2 4 5 5 5 5 5 4 7 GR - FLOOR BLOCK WORK IST - FLOOR BLOCK WORK 2ND - FLOOR BLOCK WORK 3RD- FLOOR BLOCK WORK 4TH - FLOOR BLOCK WORK 5TH - FLOOR BLOCK WORK 6TH - FLOOR BLOCK WORK 7TH -FLOOR BLOCK WORK 8TH- FLOOR BLOCK WORK 9TH - FLOOR BLOCK WORK 10TH- FLOOR BLOCK WORK I1TH- FLOOR BLOCK WORK ROOF BLOCK WORK
MEP 1 ST FIX
Subtotal 204 30AUG08 23APR09 4
BA02
AL GHAITH BUILDING CONSTRUCTION LLC G+11 TYPICAL < GREEN DESERT VENTURE>
Activity ID 1A411 1A421 1A431 1A441 1A451 1A461 1A471 1A481 1A491 1A501 1A511 1A521 1A531 GR FLOOR MEP 1ST FIX IST FLOOR MEP 1ST FIX 2ND FLOOR MEP 1ST FIX 3RD FLOOR MEP 1ST FIX 4TH FLOOR MEP 1ST FIX 5TH FLOOR MEP 1ST FIX 6TH FLOOR MEP 1ST FIX 7TH FLOOR MEP 1ST FIX 8TH FLOOR MEP 1ST FIX 9TH FLOOR MEP 1ST FIX
Activity Description
Orig Dur
Early Start
EarlyResource Total Finish IDFloat 14SEP08 01OCT08 21OCT08 15NOV08 01DEC08 17DEC08 04JAN09 22JAN09 10FEB09 01MAR09 19MAR09 07APR09 23APR09 7 6 5 0 2 4 5 5 5 5 5 4 4
2008 J A
2009 J
14 30AUG08 14 16SEP08 14 06OCT08 14 30OCT08 14 16NOV08 14 02DEC08 14 20DEC08 14 07JAN09 14 26JAN09 14 14FEB09 14 04MAR09 14 23MAR09 14 08APR09
GR FLOOR MEP 1ST FIX IST FLOOR MEP 1ST FIX 2ND FLOOR MEP 1ST FIX 3RD FLOOR MEP 1ST FIX 4TH FLOOR MEP 1ST FIX 5TH FLOOR MEP 1ST FIX 6TH FLOOR MEP 1ST FIX 7TH FLOOR MEP 1ST FIX 8TH FLOOR MEP 1ST FIX 9TH FLOOR MEP 1ST FIX 10TH FLOOR MEP 1ST FIX I1TH FLOOR MEP 1ST FIX ROOF MEP 1ST FIX
10TH FLOOR MEP 1ST FIX I1TH FLOOR MEP 1ST FIX ROOF MEP 1ST FIX
PLASTER WORK
Subtotal 2A411 2A421 2A431 2A441 2A451 2A461 2A471 2A481 2A491 2A501 2A511 2A521 2A531 GR - FLOOR PLASTER WORK IST - FLOOR PLASTER WORK 2ND - FLOOR PLASTER WORK 3RD- FLOOR PLASTER WORK 4TH - FLOOR PLASTER WORK 5TH - FLOOR PLASTER WORK 6TH - FLOOR PLASTER WORK 7TH -FLOOR PLASTER WORK 8TH- FLOOR PLASTER WORK 9TH - FLOOR PLASTER WORK 10TH- FLOOR PLASTER WORK I1TH- FLOOR PLASTER WORK ROOF PLASTER WORK 207 04SEP08 15 04SEP08 15 24SEP08 15 14OCT08 15 08NOV08 15 24NOV08 15 10DEC08 15 28DEC08 15 15JAN09 15 03FEB09 15 22FEB09 15 12MAR09 15 31MAR09 15 16APR09 03MAY09 21SEP08 11OCT08 30OCT08 24NOV08 10DEC08 27DEC08 13JAN09 01FEB09 19FEB09 10MAR09 29MAR09 16APR09 03MAY09 4 7 6 5 0 2 4 5 5 5 5 5 5 4 GR - FLOOR PLASTER WORK IST - FLOOR PLASTER WORK 2ND - FLOOR PLASTER WORK 3RD- FLOOR PLASTER WORK 4TH - FLOOR PLASTER WORK 5TH - FLOOR PLASTER WORK 6TH - FLOOR PLASTER WORK 7TH -FLOOR PLASTER WORK 8TH- FLOOR PLASTER WORK 9TH - FLOOR PLASTER WORK 10TH- FLOOR PLASTER WORK I1TH- FLOOR PLASTER WORK ROOF PLASTER WORK
WATER PROOFING
Subtotal C2A411 C2A421 C2A431 C2A441 C2A451 C2A461 C2A471 C2A481 C2A491 C2A501 C2A511 C2A521 C2A531 GR - FLOOR WATER PROOFING IST - FLOOR WATER PROOFING 2ND - FLOOR WATER PROOFING 3RD- FLOOR WATER PROOFING 4TH - FLOOR WATER PROOFING 5TH - FLOOR WATER PROOFING 6TH - FLOOR WATER PROOFING 7TH -FLOOR WATER PROOFING 8TH- FLOOR WATER PROOFING 9TH - FLOOR WATER PROOFING 10TH- FLOOR WATER PROOFING I1TH- FLOOR WATER PROOFING ROOF WATER PROOFING 206 16SEP08 14 16SEP08 14 06OCT08 14 26OCT08 14 25NOV08 14 11DEC08 14 28DEC08 14 14JAN09 14 02FEB09 14 21FEB09 14 09MAR09 14 30MAR09 14 18APR09 14 28APR09 13MAY09 01OCT08 21OCT08 10NOV08 10DEC08 27DEC08 12JAN09 29JAN09 17FEB09 08MAR09 24MAR09 14APR09 03MAY09 13MAY09 30 54 51 48 36 36 36 35 33 31 31 27 25 30 GR - FLOOR WATER PROOFING IST - FLOOR WATER PROOFING 2ND - FLOOR WATER PROOFING 3RD- FLOOR WATER PROOFING 4TH - FLOOR WATER PROOFING 5TH - FLOOR WATER PROOFING 6TH - FLOOR WATER PROOFING 7TH -FLOOR WATER PROOFING 8TH- FLOOR WATER PROOFING 9TH - FLOOR WATER PROOFING 10TH- FLOOR WATER PROOFING I1TH- FLOOR WATER PROOFING ROOF WATER PROOFING
WALL TILES
Subtotal 5A421 5A431 5A441 5A451 5A461 5A471 5A481 5A491 5A501 5A511 5A521
Start Date Finish Date Data Date Run Date
208 22SEP08 GR - FLOOR WALL TILES 1ST - FLOOR WALL TILES 2ND- FLOOR WALL TILES 3RD - FLOOR WALL TILES 4TH - FLOOR WALL TILES 5TH - FLOOR WALL TILES 6TH -FLOOR WALL TILES 7TH- FLOOR WALL TILES 8TH - FLOOR WALL TILES 9TH- FLOOR WALL TILES I0TH- FLOOR WALL TILES
01MAR08 30SEP09 01MAR08 18JAN09 08:40 Early Bar Progress Bar Critical Activity
21MAY09 08OCT08 28OCT08 17NOV08 11DEC08 29DEC08 15JAN09 02FEB09 19FEB09 09MAR09 28MAR09 15APR09
33 46 44 42 36 36 36 36 36 36 35 34
Sheet 4 of 6 Date Revision Checked Approved
15 22SEP08 15 12OCT08 15 01NOV08 15 25NOV08 15 13DEC08 15 30DEC08 15 17JAN09 15 03FEB09 15 21FEB09 15 11MAR09 15 30MAR09
BA02
GR - FLOOR WALL TILES 1ST - FLOOR WALL TILES 2ND- FLOOR WALL TILES 3RD - FLOOR WALL TILES 4TH - FLOOR WALL TILES 5TH - FLOOR WALL TILES 6TH -FLOOR WALL TILES 7TH- FLOOR WALL TILES 8TH - FLOOR WALL TILES 9TH- FLOOR WALL TILES I0TH- FLOOR WALL TILES
AL GHAITH BUILDING CONSTRUCTION LLC G+11 TYPICAL < GREEN DESERT VENTURE>
Activity ID 5A531 5A533 11TH- FLOOR WALL TILES ROOF WALL TILES
Activity Description
Orig Dur
Early Start
2008 J A
2009 J
15 18APR09 15 05MAY09
MEP 2 ND FIX
Subtotal A4112 A4212 A4312 A4412 A4512 A4612 A4712 A4812 A4912 A5012 A5112 A5212 A5312 GR - FLOOR MEP 2ND FIX IST - FLOOR MEP 2ND FIX 2ND - FLOOR MEP 2ND FIX 3RD- FLOOR MEP 2ND FIX 4TH - FLOOR MEP 2ND FIX 5TH - FLOOR MEP 2ND FIX 6TH - FLOOR MEP 2ND FIX 7TH -FLOOR MEP 2ND FIX 8TH- FLOOR MEP 2ND FIX 9TH - FLOOR MEP 2ND FIX 10TH- FLOOR MEP 2ND FIX I1TH- FLOOR MEP 2ND FIX ROOF MEP 2ND FIX 222 22SEP08 30 22SEP08 30 12OCT08 30 01NOV08 30 25NOV08 30 11DEC08 30 28DEC08 30 14JAN09 30 02FEB09 30 21FEB09 30 11MAR09 30 30MAR09 30 18APR09 30 04MAY09 07JUN09 26OCT08 15NOV08 04DEC08 29DEC08 14JAN09 31JAN09 17FEB09 08MAR09 26MAR09 14APR09 03MAY09 21MAY09 07JUN09 4 23 21 19 13 14 15 15 14 13 11 8 5 4 GR - FLOOR MEP 2ND FIX IST - FLOOR MEP 2ND FIX 2ND - FLOOR MEP 2ND FIX 3RD- FLOOR MEP 2ND FIX 4TH - FLOOR MEP 2ND FIX 5TH - FLOOR MEP 2ND FIX 6TH - FLOOR MEP 2ND FIX 7TH -FLOOR MEP 2ND FIX 8TH- FLOOR MEP 2ND FIX 9TH - FLOOR MEP 2ND FIX 10TH- FLOOR MEP 2ND FIX I1TH- FLOOR MEP 2ND FIX ROOF MEP 2ND FIX
FALSE CEILING
Subtotal 7A411 7A421 7A431 7A441 7A451 7A461 7A471 7A481 7A491 7A501 7A511 7A521 7A531 GR - FLOOR FALSE CEILING IST - FLOOR FALSE CEILING 2ND - FLOOR FALSE CEILING 3RD- FLOOR FALSE CEILING 4TH - FLOOR FALSE CEILING 5TH - FLOOR FALSE CEILING 6TH - FLOOR FALSE CEILING 7TH -FLOOR FALSE CEILING 8TH- FLOOR FALSE CEILING 9TH - FLOOR FALSE CEILING 10TH- FLOOR FALSE CEILING I1TH- FLOOR FALSE CEILING ROOF FALSE CEILING 213 14OCT08 15 14OCT08 15 03NOV08 15 23NOV08 15 17DEC08 15 04JAN09 15 21JAN09 15 08FEB09 15 25FEB09 15 15MAR09 15 02APR09 15 21APR09 15 10MAY09 10 08JUN09 18JUN09 30OCT08 19NOV08 09DEC08 03JAN09 20JAN09 07FEB09 24FEB09 14MAR09 31MAR09 19APR09 07MAY09 26MAY09 18JUN09 4 23 21 19 13 13 13 13 13 13 12 11 10 4 GR - FLOOR FALSE CEILING IST - FLOOR FALSE CEILING 2ND - FLOOR FALSE CEILING 3RD- FLOOR FALSE CEILING 4TH - FLOOR FALSE CEILING 5TH - FLOOR FALSE CEILING 6TH - FLOOR FALSE CEILING 7TH -FLOOR FALSE CEILING 8TH- FLOOR FALSE CEILING 9TH - FLOOR FALSE CEILING 10TH- FLOOR FALSE CEILING I1TH- FLOOR FALSE CEILING ROOF FALSE CEILING
PAINTING PREPARATION
Subtotal 8A411 8A421 8A431 8A441 8A451 8A461 8A471 8A481 8A491 8A501 8A511 8A521 8A531 GR - FLOOR PAINTING PREPARATION IST - FLOOR PAINTING PREPARATION 2ND - FLOOR PAINTING PREPARATION 3RD- FLOOR PAINTING PREPARATION 4TH - FLOOR PAINTING PREPARATION 5TH - FLOOR PAINTING PREPARATION 6TH - FLOOR PAINTING PREPARATION 7TH -FLOOR PAINTING PREPARATION 8TH- FLOOR PAINTING PREPARATION 9TH - FLOOR PAINTING PREPARATION 10TH- FLOOR PAINTING PREPARATION I1TH- FLOOR PAINTING PREPARATION ROOF PAINTING PREPARATION 213 11OCT08 14 11OCT08 14 30OCT08 14 19NOV08 14 14DEC08 14 01JAN09 14 20JAN09 14 08FEB09 14 26FEB09 14 17MAR09 14 05APR09 14 23APR09 14 12MAY09 14 31MAY09 15JUN09 26OCT08 15NOV08 04DEC08 29DEC08 17JAN09 04FEB09 23FEB09 14MAR09 01APR09 20APR09 09MAY09 27MAY09 15JUN09 2 29 26 23 16 14 12 10 8 6 4 2 0 2 GR - FLOOR PAINTING PREPARATION IST - FLOOR PAINTING PREPARATION 2ND - FLOOR PAINTING PREPARATION 3RD- FLOOR PAINTING PREPARATION 4TH - FLOOR PAINTING PREPARATION 5TH - FLOOR PAINTING PREPARATION 6TH - FLOOR PAINTING PREPARATION 7TH -FLOOR PAINTING PREPARATION 8TH- FLOOR PAINTING PREPARATION 9TH - FLOOR PAINTING PREPARATION 10TH- FLOOR PAINTING PREPARATION I1TH- FLOOR PAINTING PREPARATION ROOF PAINTING PREPARATION
PAINTING FINAL
Subtotal A8A411 A8A421 A8A431 A8A441 A8A451 A8A461 GR - FLOOR PAINTING FINAL COAT IST - FLOOR PAINTING FINAL COAT 2ND - FLOOR PAINTING FINAL COAT 3RD- FLOOR PAINTING FINAL COAT 4TH - FLOOR PAINTING FINAL COAT 5TH - FLOOR PAINTING FINAL COAT 211 27OCT08 14 27OCT08 14 16NOV08 14 06DEC08 14 30DEC08 14 18JAN09 14 05FEB09 29JUN09 11NOV08 01DEC08 21DEC08 14JAN09 02FEB09 21FEB09 0 29 26 23 16 14 12 GR - FLOOR PAINTING FINAL COAT IST - FLOOR PAINTING FINAL COAT 2ND - FLOOR PAINTING FINAL COAT 3RD- FLOOR PAINTING FINAL COAT 4TH - FLOOR PAINTING FINAL COAT 5TH - FLOOR PAINTING FINAL COAT
BA02
AL GHAITH BUILDING CONSTRUCTION LLC G+11 TYPICAL < GREEN DESERT VENTURE>
Activity Description 6TH - FLOOR PAINTING FINAL COAT 7TH -FLOOR PAINTING FINAL COAT 8TH- FLOOR PAINTING FINAL COAT 9TH - FLOOR PAINTING FINAL COAT 10TH- FLOOR PAINTING FINAL COAT I1TH- FLOOR PAINTING FINAL COAT ROOF PAINTING FINAL COAT
Orig Dur
Early Start
EarlyResource Total Finish IDFloat 11MAR09 30MAR09 18APR09 06MAY09 25MAY09 13JUN09 29JUN09 10 8 6 4 2 0 0
2008 J A
2009 J
6TH - FLOOR PAINTING FINAL COAT 7TH -FLOOR PAINTING FINAL COAT 8TH- FLOOR PAINTING FINAL COAT 9TH - FLOOR PAINTING FINAL COAT 10TH- FLOOR PAINTING FINAL COAT I1TH- FLOOR PAINTING FINAL COAT ROOF PAINTING FINAL COAT
ALUMINIUM WORKS
HANDING OVER
5A581 SNAGGING , CLEANING AND HANDING OVER 30 27AUG09 30SEP09 0 SNAGGING , CLEANING AND HANDING OVER
COMPLETION OF PROJECT
A21 PROJECT COMPLETION 0 30SEP09 0 PROJECT COMPLETION
BA02
AL GHAITH BUILDING CONSTRUCTION LLC G+11 TYPICAL < GREEN DESERT VENTURE>