STEEL PLANT SUPPLY AND DEMAND BALANCED PLANNING

Eric Meta(1) Pierre Beghin(1) Pascal Moinier(1) Luc Van Nerom(1) ABSTRACT A Steel plant scheduling is a complex process which requires taking into account several competing constraints. Also, as occurs in other industries, an unbalance between the supply and demand is cause of cost rise or loss in profit. Complexity, in addition to the lack of appropriate tools, led in the past to a fragmented solution of the problem. A scheduling department could be organized by production units (primary steelmaking, hot rolling, cold rolling, finishing), in some cases performing their tasks without sharing an effective view of the goals of the scheduling system as a whole. A volume planning provides a necessary condition to have a well balance between supply and demand as well as appropriate stock levels. We purpose layer architecture for accomplishing this planning task, allowing the incorporation of the best-suited scheduling system for each steel process. A balanced supply and demand planning can be achieved, solving the trade-off between specific process optimizations and global coordination reaching an appropriate balance between the service level, stocks level and capacity usage. As a result, will lead to ship better and more quickly, and doing so with less inventory. Keywords: scheduling, planning, supply chain, inventory

(1)

A. I. Systems, Researchdreef, 65, 1070 Bruxelles, Belgium. www.steelplanner.com www.aisystems.be 17th IAS Rolling Conference, 2008, Rosario, Argentina

104

STEEL PLANT SUPPLY AND DEMAND BALANCED PLANNING


Eric Meta(1) Pierre Beghin(1) Pascal Moinier(1) Luc Van Nerom(1)

1. INTRODUCTION A Steel plant scheduling is a complex process which requires take into account several competing constraints. Also, as occurs in other industries, an unbalance between the supply and demand is cause of cost rise or loss in profit. Software solutions that support scheduling operations on a daily basis are well known today in the steel industry and companies that are using automated tools to optimize their continuous casters or rolling mills would never accept to come back to the old fashioned manual approach to solve these complex problems. On top of its proven scheduling packages, A.I.Systems has introduced solutions that implement a complementary layer, allowing for the definition and optimization of schedules over a longer time horizon (weeks), ranging up to several weeks. The benefit of these extensions is the increased visibility of the production plan allowing have a better balance between supply and demand and reducing the difficulty to deal with mix problems. 2. SUPPLY AND DEMAND UNBALANCE When supply and demand are not balanced, several consequences are observed. In case the demand exceeds the supply, customer service suffers because the steel plant is not able to deliver the product when is required by the customer, costs rises because of freight costs increases and quality often is compromised. In case supply exceeds the demand, inventories increase, carrying cost rise, and cash flow can become a problem. Also, profit margins decrease and prices are cut and discounting increase. Complexity, in addition to the lack of appropriate tools, led in the past to a fragmented solution of the problem. A scheduling department could be organized by production units (primary steelmaking, hot rolling, cold rolling, finishing), in some cases performing their tasks without sharing an effective view of the goals of the scheduling system as a whole. Since many years, an important number of publications have insisted on the fact that production optimization should aim for a global approach, avoiding the temptation of only looking for local optima. Obviously, cross-line synchronization is required to handle the over-all production planning and scheduling problem, as the objective is to determine the optimal trade-off between the work-in-progress inventory, the quality of each of the individual schedules, the due date performance.

In the steel industry, such a cross-line system needs to rely on a proven detailed scheduling foundation, as it must integrate detailed constraints coming from steel production equipment. Building a cross-line solution is a complex problem as: individual facilities (casters, hot strip mills, cold mills, pickling lines) have many technological constraints to be respected each of these constraints has significant differences from one line to another production rates and rhythms may differ significantly between lines

As a result, a buffer stock between lines will always be necessary, on top of a minimum level of security stock. (slab yards, coil yards). This tradeoff is represented in Figure 1.

17th IAS Rolling Conference, 2008, Rosario, Argentina

105

Figure 1. Tradeoff in a balanced supply and demand plan A.I.Systems has developed several decision support systems for the scheduling of Continuous Casters, Hot Strip Mills and Mini Mills. These tools improve the programmer ability to create larger programs and have a better due date performance, as part of the whole planning process, but looking at the local planning problem of each line. Then, a global view is necessary to guide the local solvers in order to be able to have a good balance between supply and demand.

3. FLOW PLAN: VOLUME PLANNING A volume planning provides a necessary condition to have a well balance between supply and demand as well as appropriate stock levels. As a result, will generate constraints for the detailed scheduling of each process to be sure the line will provide the enough material to avoid stops and have a good due date performance. After a flow plan is done, the detailed scheduling for each line is performed. The flow plan offers a global view of the plant, and is initialized with the current situation of the plant considering initial stocks, present demand and production in progress. It will also consider as constraints minimum and maximum stock levels as well as the residence time necessary for the arrival of the material to the line previous to being consumed and its maximum time to relay in the stock before being consumed. The flow plan configuration is made by product families, representing the different flows of material trough the lines and the stocks we want to control and predict. The product families not necessary are the same in all the lines, instead we can build a tree-like structure were product families are spitted into more detailed level to let downstream lines have the necessary level of detail which is not required in upstream lines. Once the flow is done, a mapping can be done to the orders, to have an initial view of the due date performance previous to the detailed programming of the lines. Figure 2 illustrates the flow planning configuration.

17th IAS Rolling Conference, 2008, Rosario, Argentina

106

Figure 2. Flow Planning configuration

After generating the flow plan, each local scheduler will receive the flow constraints generated in the flow plan and will deal with the specific mix of orders and restrictions of each line as shown in Figure 3.

P ro d u ctio n G oa ls

M a ster P la n n in g M a teria l F lo w P la n n in g D eta iled S ch ed u lin g


L in e 1 L in e 2 L in e 3 L in e 4

P ro d u ctio n D eta ils

P ro d u ctio n

Figure 3. Layer representation of the production plan

Later, when each detailed schedule is generated, all the schedules can be loaded back in the flow planning system and have a more realistic prediction of order fulfilment and stock levels. In some cases, we will need a joint flow constraint for groups of lines, instead of a flow constraint per line. This is the case for example when several lines share the same stock yard, and the produced material goes also to the same stock yard. In that case, even if both lines require its specific detailed schedule, from the flow point of view is only one line where the productivity is the result of adding the capacity of both lines. The model should be able to solve situation in which the flow plan of a given line depends on the flow plan of another line. This kind of relations can be found very often in steel plants, and then the solution should be able to solve all the lines with related flow plans at the same time, and take into account the cross effects of the flow plans. Figure 4 shows a possible plant configuration in which a global planning is necessary as a consequence of the routing between the lines.

17th IAS Rolling Conference, 2008, Rosario, Argentina

107

In the plant shown in Figure 4, there is a plant with only one product family, which can be delivered by lines Line 4 and Line 3. Then, the material produced by Line 3 should not be produced by Line 4. Even more, the stocks in front of Line 2 and Line 4 will depend on the material provided by Line 1 and their flow plans. Thus, we can see interdependency between flow plans of Line 4, Line 2 and Line 3, which all together affect the flow plan of Line 1. The situation described above, can only be solved with a global solution which takes into account all the lines at the same time.

Figure 4. Plant diagram example 4. CONCLUSION The logistics and processes in the steel industry are complex. This complexity calls for dedicated models and solutions in order to ensure schedules feasibility, and bottlenecks optimization. In the steel industry, production details are so important that they must be considered not only on the detailed scheduling level, but also at the higher global level, where planning is necessary to avoid cost rises and inventories increase due to an unbalanced supply and demand planning. The proposed open architecture allows incorporating the best-suited scheduling system for each steel process. On top, balanced supply and demand planning, managed by MFC, solves the trade-off between specific process optimizations and global coordination and ensure appropriate balance between the service level, stocks level and capacity usage. As a result, will lead to ship better and more quickly, and doing so with less inventory.

REFERENCES 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. Wallace, Stahl. Sales & Operations Planning. T. F. Wallace & Company, 2008. Demidchuk, Molinari and Eleno. Scheduling in the Steel Industry: A Pragmatic Approach. Iron & Steel, 1998. Adams, Balas, and Zawack.. The shifting bottleneck procedure for job shop scheduling. Management Science, 34(3):391-401,1988. Akers. A graphical approach to production scheduling problems. Operations Research, 4:244-245, 1956 Baker. Manufacturing Control with a Market-Driven Contract Net. PhD thesis, 1991. Baker. Metaphor or Reality: A case study where Agents Bid with Actual Costs to Schedule a Factory. Addison Wesley, 1996. Baker. A survey of factory control algorithms which can be implemented in a multiagent heterarchy. Submitted to Journal of Manufacturing Systems, 1997. Balas and Vazacopoulos. Guided loacal search with shifting bottleneck for shop scheduling. Management Science, 44 (2):262-275, 1998. Baker and McMahon. Scheduling the general job-shop. Management Science, 31(5):594-598, 1985. Brucker, Jurisch, and Sievers. A branch and bound algorithm for the job-shop scheduling problem. Discrete Applied Mathematics, 49:107-127, 1994 Carlier. The one machine sequencing problem. European Journal of Operational Research, 11:42-47, 1982. Dauzre-Peres and Lassere. A modifed shifting bottleneck procedure for job-shop scheduling. International Journal of Production Research, 31(4):923-932, 1993. Dauzre-Pres and Lasserre. Integration of lotsizing and scheduling decisions in a job-shop. European Journal of Operation Research, 75:413-426, 1994. Dauzre-Pres and Lasserre. Lot streaming in job-shop scheduling. preprint, 1999. DellAmico and Trubian. Applying tabu search to the job-shop scheduling problem. Annals of Operations Research, 41:231-252, 1993. Goldratt. Theory of Constraints.

17th IAS Rolling Conference, 2008, Rosario, Argentina

108

17. Gou, Hasegawa, Luth, Tamura, and Oblak. Holonic planning and scheduling for a robotic assembly testbed. In Proc. 4th Intl. Conf.Computer Integrated Manufacturing and Automation Technology, Troy ( NY), pages 142149, 1994. 18. Kane. Cooperative scheduling systems. In Principals of Autonomous Systems Proc., Ann Arbor (MI), 1992. 19. Lasserre. Ann integrated model for job-shop planning and scheduling. Management Science, 38(8): 12011211, 1992. 20. Luh and Hoitmont. Scheduling of manufacturing systems using the lagrangian relaxation technique. IEEE Trans. Automatic Control, 38(7) :1066-1079, 1993. 21. Mattfeld. Evolutionary Search and Job Shop. Physica Verlag, 1994. 22. Mensch. Generalization of akerstwo-dimensional job shop scheduling model to j dimensions. SIAM Journal on Applied Mathematics, 18(2):462-466, 1970. 23. Ow and Smith. Viewing scheduling as an opportunistic problem-solving process. Annals of Operations Research, 12:85-108,1988. 24. Ow,Smith, and Howie. A cooperative scheduling. In Proc. 2nd Intl. Conf. Expert Systems and the Leading Edge in Production Planning and Control, Charleston (SC), pages 43-56, 1988. 25. Ramaswamy and Joshi. Distributed control of automated manufacturing systems. In Proc. 27th CIRP Intl. Seminar on Manufacturing Systems, Ann Arbor (MI), 1995. 26. Ramudhim and Marier. The generalized shifting bottleneck procedure. European Journal of Operational research, 93:34-48, 1996. 27. Roux, Dauzre-Pre, and Lasserre. Planning and scheduling in a multi-site environment. Preprint, 1999. 28. Silver. Operations research in inventory Management: A review and critique. Operations Research, 29(4):628645, 1981. 29. Szwarc. Solution of the akers-friedman scheduling problem. Operations Research, 8:782-788, 1960. 30. Tanaev, Sotskov, and Strusevich. Scheduling Theory. Multi-Stage Systems.Kluwer Academic Publishers, 1994. 31. Weisser and Cochran. Modeling temporal relations in task hierarchies for job-shop scheduling. In Proc. 2nd Intl. Conf. Computer Integreted Manufacturing, Troy(NT), pages 39-49, 1990. 32. Weisser and Howie. A cooperative approach to large-scale production planning. In Proc. AAAI Workshop in Prod. Planning and Scheduling, St Paul (MN), 1988. 33. Weisser and Howie. Distributed scheduling and temporal reasoning. In AIAA Computers in Aerospace VII Proc., Monterey (CA), 1989.

17th IAS Rolling Conference, 2008, Rosario, Argentina

109