production rates for normal operation conditions

ITEM FINISHING block work 4" or 8" hollow block work 4" or 8" hollow ( high level, above lentel level) block around (bath tub) inter lock PLASTER WORK internal plaster exterior plaster curb stone (heavy duty) curb stone (light duty) ceramic work rush coat wall ceramic limited area wall ceramic extended area floor ceramic for bath rooms last ceramic layer + bathtub ceramic fixing

QT/DAY unit

GROUP

O/T

REMARKS

180 150 5 35

BLOCK 1GM+1H block L/S M2 1GM+1H 1M+1H 1M+1H

2 2 2 2

adjust the rate /day for block size

22 15 25 55

M2 M2 R/M R/M

1PM+1H 1PM+1H 1M+1H 1M+1H

2 2 2 2

150 12 15 16 6

M2 M2 M2 M2 toilets

1M 1M+1H 1M+1H 1M+1H

2 2 2 2 2

# # # terrazzo tile skirting floor ceramic in open in spacious area ceramic grouting fixing threshold fixing threshold + repairing and closing around fixing floor trap cover FALSE CEILING FALSE CEILING Gibson board FALSE CEILING 60x60 duct ( 60x30) PAINT WORK interior paint up to stucco (primer,lines and 2 stucco coat) any roll applied paint one coat including sand paper final coat

3 1 4 20 70 22 100 20 12 25

kitchen flat bath M3 R/M M2 M2 L/S L/S L/S 1M+1H 1M 1M+1H 1H 1M 1M 1M 1m+1H

2 2 2 2 2 2 2 2 2 2 (1toil+1bath+1kit)

20 30 7

M2 m2 L/s

2C 2C 1C+1H

2 2 2

50 400 400

M2 m2 m2

1p

crew of 2p

2P+1HPN 2 1P 2

external paint primer one coat epoxy texture (applied by gun) top coat ( one coat) door paint complete door paint 7 door 1P+1H 2 200 300 400 m2 m2 m2 1H 1P+1H 1P+1H 2 2 2

DOORS fixing frame fixing door shutter normal (type interior) fixing door shutter (fire rated) fixing articlif (2SIDES) fixing door lock 15 10 4 10 8 L/S L/S L/S L/S L/S 1C+1H 1C+1H 1C+1H 1C 1C 2 2 2 2 2

M&T protection preparing wet area for liquid brush applied w/p w/p 1coats liquid brush applied insulation sheet covering for columns 30 80 20 m2 m2 m2 1H 1H 2C 2 2 2

CONCRETE WORK SLAB WORK (kwikstage RMD scaffolding) Erect Scaffolding 150 M2 R/M M2 L/S R/M L/S R/M R/M m2 M2 PCS m2 m2 2C+1H 2C+1H 1C+2H 2C+1H 2C+1H 2C+1H 2C+1H 2C+1H 1C+2H 2C+1H 2H 2c+1h 1c+2h 2 2 3 2 2 2 2 2 2 2 2 2 2

Remove And Fix one Side And Bottom Of Beams Depth 80cm 20 LAY PLY WOOD CLOSING AROUND COLUMNS Closing Beams One Side Closing Around Col Below Slab Closing Slab Sides 1 Remove And Fix Cantilever Removing Ply Wood And Reshoring Removing Slab Shuttering All Ply Wood Shifting From One Level To The Next Leveling slab scaffolding Bracing 504 15 20 15 80 42 160 110 170 1200 400

Other R.C. Work stair case (5*3)m lift (4* 2) arch .partitions 10 cm thick walls (LONG WALLS) arch .partitions 10 cm thick walls (SHORT WALLS) col form work shear wall form work R.C columns steel work 1 1 8 6 4 8 3 stair case8C+4H lift R/M R/M L/S r/m m3 6C+3H 2C+1H 2C+1H 2C+1H 2C+1H 2S 2 2 2 2 2 2 2 (2c+1h) x 4 days (2c+1h) x 3 days (core for 2 lifts)