Beruflich Dokumente
Kultur Dokumente
In question 9, taking actual 1997 sales of $ 48,000 as the forecast for 1998,
what sales would you forecast for 1999, 2000, and 2001 using exponential
smoothing and a weight
=
=
n
j
ij j i
O P L
1
Example - 1: consider the simple pay off table with only two alternative decisions and
two possible states of nature.
N
1
P
1
0.999
N
2
P
2
0.001
A
1
$ -200 $ -200
A
2
0 $ -100,000
Alternative A
1
has a constant cost of $200, and A
2
a cost of $100,000 if future N
2
takes
place (and none otherwise). At first glance alternative A1 looks like the clear winner, but
consider the situation when probability (P
1
) of the first state of nature (N
1
) is 0.999 and
the probability (P
2)
of the second state of nature (N
2
) is only 0.001. the expected value of
choosing alternative A
2
is only
E(A
2
) 0.999 ($0) 0.001 ($100,000) $100
Note that this outcome $-100 is not possible the outcome if alternative A
2
is
chosen will be a loss either $0 or $100,000, not $100. However, if you have many
decisions of this type over time and you choose alternative that maximize expected value
E
2
of $-100 to E
1
of $-200, we should choose A
2
, other things being equal.
But first, let us use these figures in a specific application. Assume that you own a
$100,000 house and are offered fire insurance on it for $200 a year. This is twice the
expected value of your fire loss (as it has to be to pay insurance company overhead and
21
agent costs). However, if you are like most people, you will probably buy the insurance
because, quite reasonably, your attitude toward risk is such that you are not willing to
accept loss of your house! The insurance company has a different perspective, since they
have many houses to insure and can profit from maximizing expected value in the long
run, as long as they don't insure too many properties in the path of the same hurricane or
earthquake.
Example ~ 2: Consider that you own rights to a plot of land under which there may or
may not be oil. You are considering three alternatives:
doing nothing (don't drill),
drilling at your own expense of $300,000, and
farming out the opportunity to someone who will drill and give you part of the
profit if the well is successful.
You may also see three possible state of nature:
a dry hole,
a mildly interesting small well, and
a very profitable gusher (big well).
You estimate the probabilities of the three state of nature Pj and the outcome Oij as
shown in table below:
Alternative State of nature/Probability Expected
value (E)* N
1
: Dry Hole
P
1
0.6
N
2
: Small Well
P
2
0.3
N
3
: Big Well
P
3
0.1
A
1
: Don't Drill $ 0 $0 $0 $0
A
2
: Drill Alone $ -300,000 $ 300,000 $ 9,300,000 $720,000*
A
3
: Farm out $ 0 $ 123,000 $ 1,230,000 $162,000*
The first thing you can do is eliminate alternative A
1
, since alternative A
3
is at
least as attractive for all states of nature and is more attractive for at least one state of
nature. A
3
is therefore said to Jominore A
1
.
Next, you can calculate the expected values for the surviving alternatives A
2
and A
3
:
E
2
0.6 (-300,000) 0.3 (300,000) 0.1 (9,300,000) $720,000*
E
3
0.6 (0) 0.3 (123,000) 0.1 (1,230,000) $162,500*
And, you choose alternative A
2
if (and only if) you are willing and able to risk loosing
$300,000.
Decision Trees: The Decision Trees provide another technique used in finding expected
value. They begin with a single decision node (normally represented by a square or
rectangle), from which a number of decision alternatives radiate. Each alternative ends in
a chance node, normally represented by a circle. From each chance node radiate several
possible futures, each with a probability of occurring and an outcome value. The
22
expected value for each alternative is the sum of the products of outcomes and related
probabilities, just as calculated previously in Example -2.
Figure given below illustrates the use of a decision tree in our simple insurance example.
Decision Chance (Outcome) (Probability)
Expected Value
Node Ai node N (Oij) (Pj) Ei
---------- ----------- ------------- -------------- ------------------
No fire (-200) X (0.999) -199.8
Insure $-200
Fire (-200) X (0.001) -0.2
Don't No fire (0) X (0.999) 0
Insure $-100
Fire (-100,000) X (0.001) -100
The conclusion reached is identical mathematically to that obtained from the table
values in Example 1. Decision tree provides a very visible solution procedure, especially
when a sequence of decisions, chance nodes, new decisions, and new chance nodes exist.
Risk as Variance: Another common meaning of risk is variability of outcome, measured
by the variance or (more often) its square root, the standard deviation. Consider two
investment projects X and Y, having the discrete probability distribution of expected cash
flows in each of the next several years shown in the table below:
Table: Data for Risk as Variance Example
Project X Project Y
Probability Cash Flow Probability Cash Flow
0.10
0.20
0.40
0.20
0.10
$3000
3300
4000
4300
3000
0.10
0.23
0.30
0.23
0.10
$2000
3000
4000
3000
6000
Then, the expected cash flows are calculated the same as expected value:
E(X) 0.10 (3000) 0.20 (3300) 0.40 (4000) 0.20 (4300) 0.10 (3000)
23
$4000.
E(Y) 0.10 (2000) 0.23 (3000) 0.30 (4000) 0.23 (3000) 0.10 (6000)
$4000.
Although both projects have the same mean (expected) cash flows, the expected
values of the variances (squares of the deviations from the mean) differ as follows:
y
Probability
X
X = Y Y
$0 $2000 $4000 $6000 x
Figure: Projects with the same expected value but different variances.
The variance may be calculation as below:
V
X
0.10 (3000 4000)
2
0.20 (3300 4000)
2
0.20 (4300 4000)
2
0.10 (3000 4000)
2
$300,000.
VX 0.10 (2000 4000)
2
0.23 (3000 4000)
2
0.30 (4000 4000)
2
0.10 (6000 4000)
2
$1,300,000.
The Standard deviations are the square roots of these values:
1140 $ , 348 $ = = v x
Since project Y has the greater variability (whether measured in variance or in standard
deviation) it must be considered to offer risk than does project X.
Decision Making Under Uncertainty:
Uncertainty occurs when there exist several (i.e., more than one) future states of
nature N
j
, but the probabilities P
j
of each of these states occurring are not known. A
different kind of logic is used here, based on attitude towards risk.
24
Methods Used:
Method ~ 1: The optimistic decision maker may choose the alternative that offers the
highest possible outcome (the maximax solution):
Method ~ 2: the pessimist may choose the alternative whose worst outcome is least
bad (the maximin solution):
Method ~3: a third decision maker may choose a position somewhere between optimism
and pessimism (i.e., Hurwicz approach):
Method ~ 4: a fourth may simply assume that all states of nature are equally likely (the
so called principle of insufficient reason), set all P
j
values equal to 1.0/n, and
maximize expected value based on that assumption: and
Method ~5: fifth decision maker may choose the alternative that has smallest difference
between the best and worst outcomes (the minimax regret solution).
Let us consider the example of well drilling problem as discussed earlier, if the
probabilities P
j
for the three future states of nature N
j
cannot be estimated.
Alternative State of nature/Probability Expected
value (E)* N1: Dry Hole
P
1 0.6
N2: Small Well
P
2 0.3
N3: Big Well
P
3 0.1
A1: Don't Drill $ 0 $0 $0 $0
A2: Drill Alone $ -300,000 $ 300,000 $ 9,300,000 $720,000*
A3: Farm out $ 0 $ 123,000 $ 1,230,000 $162,000*
Using the values given in the table above let us calculate the maximax solution,
maximin solution, and Hurwicz approach and equally likely and maximax
regret.
Method ~ 1: the maximax solution.
Alternative Maximax (Maximum)
A
2
$9,300,000*
A
3
1,230,000
Method ~ 2: the maximin solution.
Alternative Maximin (Minimum)
A
2
$-300,000
A
3
0*
Method ~ 3: the maximin solution.
The Hurwicz approach uses the equation:
Maximize l
) (worst outcome)|
Then:
E(A
2
) l0.2 (9,300,000) (1- 0.2) (-300,000)| $1,460,000
23
E(A
3
) l0.2 (1,230,000) (1-0.2) (0)| $250,000
Alternative Maximin (Minimum)
A
2
$1,460,000*
A
3
230,000
Method ~ 4: the Equally Likely solution.
If decision makers believe that the future states are equally likely, they will seek
the higher expected value and choose A
2
on that basis. In this method set all P
j
values
equal to 1.0/n, and maximize expected value based on that assumption. Then,
E(A
2
)
3
000 , 300 , 9 000 , 300 000 , 300 + +
$3,033,333
E(A
3
)
3
000 , 230 , 1 000 , 123 0 + +
$458,333
Alternative
Equally Likely
A
2
$3,033,333*
A
3
438,333
Method ~ 5: In this method we may choose the alternative that has smallest difference
between the best and worst outcomes (the minimax regret solution). Then:
Alternative
State of nature (N
j
)
Minimax
Regret
N
1
: Dry Hole N
2
: Small Well N
3
: Big Well
A1: Don't Drill $ 0 (300,000 0)
$300,000
( $9,300,000 0)
$9,300,000 $9,300,000
A2: Drill Alone $ -300,000 0 0 $500,000*
A3: Farm out $ 0 (300,000 -123,000)
$ 173,000
(9,300,000 ,230,000)
$ 8,030,000 $8,050,000
Then the result is:
Alternative Equally Likely
A
1
$9,300,000
A
2
300,000*
A
3
8,030,000
Let us now arrange the results of all the methods together in a table as below:
26
Alternative Maximum
(Maximax)
Minimum
(Minimax)
Hurwicz
(
= 0.2)
Equally
Likely
Mimimax
Regret
A
1
-- -- -- -- $9,300,000
A
2
$9,300,000* $-300,000 $1,460,000* $3,033,333* $300,000*
A
3
1,230,000 0* 230,000 438,333 $8,030,000
* Preferred solutions.
Game Theory: A related approach is game theory, where the future states of nature and
their probabilities are replaced by the decisions of a competitor. Gegley and Grant
explains:
In essence, game theory provides the model of a contest. The contest can be a
war or an election, an auction or a children's game, as long as it requires strategy,
bargaining, threat and reward.
In other situations, game theory leads to selecting a mixture of two or more
strategies, alternated randomly with some specified probability.
Computer Based Information System:
Integrated Data Bases:
Until recent years, each part of an organization maintained separate files and
developed separate information for its specific purposes, often requiring the same
information to be entered again and again. Not only expensive, but when the same
information is recorded separately in several places it becomes difficult to keep current
and reliable. The computer revolution has made it possible to enter information only
once in a shared data base where it can be updated in a single act, yet still be available
for all to use.
CAD/CAM revolution in design and manufacture provides a much more
sophisticated example. Designs are now created on the computer, and this same record is
used by others to analyze strength, heat transfer, and other design conditions, then it is
transformed into instructions to manufacture the item on numerically controlled
machines, and to test the item for conformance to design.
Management Information/Decision Support Systems:
Traditionally, the top managers have relied primarily on oral and visual sources of
information which includes scheduled committee meetings, telephone calls, business
luncheons, and strolls through the workplace, supplemented by the often condensed and
delayed information in written reports and periodicals. Ouite recently, the existence of
computer networks, centralized data bases, and user-friendly software has provided a new
source of prompt, accurate data to the manager. A recent survey showed that 93% of
senior executives used a personal computer, 60% of them for planning and decision
support.
Contemporary authors distinguish two classes of application of computer based
management system:
27