Beruflich Dokumente
Kultur Dokumente
Cable Technology
1960s-1980s: 1980s-1990s: 1970s-1990s: Fluid filled systems for HV and EHV Low loss PPL systems to match the paper laminates performance for EHV Parallel development of XLPE system from MV up to EHV 275kV XLPE cables in service. In Japan 500 kV XLPE cables installed. 1970s-1990s: Gas-filled (SF6) short lengths installed. Many lab models for higher voltages, including three phase designs in a single duct. Also, SF6/N2 mixtures attempted. 1970s-1990s: Low temp. cryogenic/supercon. designs tried. witnessed the phenomenal growth in HTS technology.
2.
3.
PPL fluid-filled
XLPE
Superconducting cables.
GIS ASSEMBLY
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Bus bar Circuit Breaker Disconnector (line or bus) Earthing switch (line or bus) Current transformer (feeder / bus) Voltage transformer (feeder/ bus) Feeder Disconnector Feeder Earthing switch Lightning / Surge Arrester Cable termination Control Panel.
Limitations of AIS
Large dimensions due to statutory clearances and poor dielectric strength of air Insulation deterioration with ambient conditions and susceptibility to pollutants. Wastage of space above Life of steel structures Seismic instability Large planning & execution time Grounding-mat is essential for containing touch and step potentials Hot line washing and regular maintenance of the substation is essential, requires spares inventory and man-power.
12/13/2010 12
Expansion / up-rating of existing s/s Non availability of sufficient space for s/s Difficult climatic and seismic conditions at site Urban site (high rise bldg.) High altitudes Limitations of AIS
12/13/2010
13
GITL
In addition to the advantages listed above for GIS, there is a need for non-aerial transmission lines near urban areas.
GITL, compared to underground cables, have the additional advantage of reduced ground surface magnetic fields.
Clearances
Phase to ground clearance for 132 kV systems is ~1200 mm in air, compared to 80 mm in SF6 gas at 4.0 bar(g).
This gives a direct reduction in dimensions of the high- voltage equipment- by 15
Consequently the size of SF6 insulated equipment is around 6% that of air insulated equipment for this voltage class (132kV)
Equipment size
To 30% for 33kV and below To 15% for 66kV To 6% for 132 kV to 170 kV and To 4-5% for >245kV
GIS
AIS
Under refurbishment
switches
The phase conductor is of aluminium / copper. The outer enclosure is also of aluminium, although
earlier designs used mild steel / Stainless steel. For lower voltages, stainless steel has also been used.
Growth of GIS
Voltage Class 1 2 3 4 5 6 60 100 kV 100 200 kV 200 300 kV 300 500 kV 500 700 kV >700 kV
Bus
CT
CB
300 kV GIS
VT
CB
400 kV GIS
800 kV GIS
Cone Insulator
Expansion joint
Concept of GIS
Design of GIS
12/13/2010
HT Conductor
Enclosure
Cone Insulator
Design of GIS
Minimum Isolating Distances
Critical stress (Ecr) at gas pressure, P = 5.3(1+0.46P)[1+(1/rc0.5)*(2.82-2.29/P)] kV/mm Geometric constant (K) for co-axial geometry =shell dia. / conductor dia. Field Factor (Ff) = (K-1)/ln K Safe Working Stress, Es = Ecr/Ef Minimum isolating distance (x) = applied voltage / safe working stress mm
Design of GIS
The gas-insulated equipment works under two major stresses: 1. Electrical stress 2. Mechanical stress The electrical design results in basic clearances between HT conductor and the enclosure. Controlling of electrical stresses on high voltage electrodes is also an objective of the electrical design.
The mechanical design comprising of equipment dimensions, support structures and the operating systems like drives for switching components.
Design Philosophy
12/13/2010
Safety
Safety is introduced by optimising operating electrical stresses to safe levels by better interelectrode spacing Safety is reinforced by increasing the gas volume and the thermal inertia of the system to enhance cooling and retain insulation strength
12/13/2010
High Reliability
Reliability is ensured By superior contact systems for CB, and disconnectors Multi-contact and friction free surfaces are incorporated for long operating cycles Rugged, time proven operating drives are used
12/13/2010
12/13/2010
In-service fault rate (faults/station-year) vs. years in service for 25 North American GIS.
Comparison of GITL dimensions for manufacturers. The dimensions selected reflect the manufacturers design and manufacturing philosophy including design testing, quality control and manufacturing tolerances.
Typical design of compressed gas insulated transmission line. Shipping module is 18 m long with insulators every 6 m. Other designs may use only disc or conical insulators. Drawing not to scale.
Required specifications.
Cost breakdown of 60 foot CGIT shipping module (including assembly, labour and testing).
Optimum dimensions for three conductor cable: Re = 5.56 Rc, R1 = 2.78 Rc.
Designs of threeconductor CGIT systems. Post insulators a-c are attached to metallic ring which moves inside enclosure, insulators d-f are attached by welding to inside of enclosure.
12/13/2010
29
12/13/2010
30
Bay formation
12/13/2010
32
12/13/2010
33
BUS BAR
12/13/2010
CABLE BOX
INSULATOR
34
GVM 36
CB Enclosure
Mechanism
Cable Connection
12/13/2010 35
12/13/2010
36
High & Ultra High Voltage Gas Insulated Equipment and Systems
12/13/2010
37
GIS Bay
145 kV GIS
12/13/2010
39
300 kV GIS
12/13/2010
40
12/13/2010
41
12/13/2010
42
12/13/2010
43
Enclosure
Rib Insulator
12/13/2010 45
12/13/2010
46
Housing
12/13/2010
Mechanism
Load side
47
ISOLATOR / DS
HT shield
Fixed Contact
12/13/2010
Moving Contact
48
12/13/2010
50
12/13/2010
51
12/13/2010
52
12/13/2010
Moving Contact 53
12/13/2010
54
12/13/2010
55
12/13/2010
56
LT Terminal
145 kV
72.5 kV 52 kV 33 kV
12/13/2010
Surge arrester
57
12/13/2010
59
Technological Advancements
Fast response surge arresters A break-through in SA technology Patented arrangement of MOV elements help reducing the inductance of the system. Uniform voltage distribution on elements (~3-6%)
12/13/2010
60
12/13/2010
61
Current Transformer
12/13/2010 62
12/13/2010
Barrier Insulator
63
Cable-to-gas termination
Barrier Insulator
XLPE
64
12/13/2010
65 Next
GAS-TO-AIR BUSHING
12/13/2010
66
12/13/2010
67
12/13/2010
Support Insulator
68
12/13/2010
69
12/13/2010
72
12/13/2010
73
Advantages: The charging current is substantially reduced. The dielectric losses are negligible. The comparatively large diameters of conductor and enclosure result in low resistive and heat losses. The power carrying capability is more than conventional lines at a particular system voltage. The configuration provides highly effective screening.
TEST FACILITIES
12/13/2010
76
Cascade Transformer :
12/13/2010
Impulse Generator 77
Test Transformer
Test Object
12/13/2010
78
PD level (min- max, current & power) PD Count, Repetition rate, Phase-angle, Q-rate and Phase plots
12/13/2010 79
12/13/2010
82
Gas insulated modules with welded steel enclosures tested for 2.3 x normal pressure. Record of strain. No distortion in shape of enclosure.
12/13/2010
83
12/13/2010
84
12/13/2010
85
0.1 sec, 40 kA
1. The test has been conducted in two phases, confirming the main and back-up protection as per IEC 62271-103. 2. For the time duration of main protection (< 0.1 sec), no external effects of the enclosure except the operation of suitable pressure 12/13/2010 relief devices. 86
0.3 sec, 40 kA 1. For the duration of back-up protection (< 0.3 sec), no fragmentation except burn- through of the enclosure. 2. Certification of GIS modules for the arc fault test enhances the business potential of the 145 kV GIS equipment. Now, BHEL became one of a few GIS suppliers, who can offer the equipment with this certification. 12/13/2010 87
12/13/2010
88
12/13/2010
89
12/13/2010
90
Design Principle
The electrostatic field with the insulator should not exceed the field at the central conductor surface without the insulator.
Very difficult to achieve!
GASES
GEOMETRY
Epoxy Teflon
MATERIALS
VOLTAGE
Enclosure
Rib Insulator
12/13/2010 7
Technological Advancements
Support Insulators specially designed to avoid external pipe connection for gas
Cone Insulators
Non-communicating Communicating
Rib Insulators
For 3-phase systems
12/13/2010 8
Cone Insulators
145 kV GIS
245 kV GIS
Rib-Type
(145 kV GIS)
12/13/2010
420 kV GIS
Critical Problems
1. 2. 3. 4. 5. 6. Triple-junction design Tangenital vs. normal field at the insulator Surface discharges from partial discharges Presence of metallic particles on the insulator surface For D.C. applications - the problem of bulk charging of insulator Poor quality material - voids & other defects
Even a small protrusion on the central conductor near a spacer would deposit a line charge on the spacer. The local field at the tips of such a line charge could be high enough to initiate a local discharge. A trapped charge of, say, 0.8 pu on a 550kV GIS is equivalent to a sustained DC voltage of ~340kV in the bus.
The question of trapped DC charge on a GIS bus bar should not be ignored. Such a line charge may be particularly dangerous when the disconnect switch operates. The combined transient field plus the line charge filed may be sufficient to cause spacer flashover.
Typical sequential variations of the breakdown voltage of a coaxial conductor without and with a cone spacer.
The application of DC pre-stressing will approximate conditions resulting from disconnect operation or lightning/switching surge. Work was undertaken to determine the changes, if any, in the early stages of the surface breakdown under lightning impulse voltage when there is a prior direct stress.
The results obtained with the combined dc and impulse voltages have indicated that a dc voltage alters the electric field distribution along the surface of a spacer.
Comparison of streak image of surface flashover and gap breakdown in the air. (a) gap breakdown, (b) surface flashover
Pre-discharge development in SF 6.
t=0 is the start of the voltage breakdown at the gap.
It is evident that the pre-discharge formation occurs in the space between disturbance and cathode. As the discharge proceeds in cathode direction the gap between anode and the disturbance in this case is also bridged simultaneously.
Pre-discharge development at an insulator surface with a disturbance near the cathode. It is evident that the pre-discharge formation occurs in the space between disturbance and anode. As the discharge proceeds in cathode direction the remaining gap between cathode and the disturbance in this case is bridged very late.
Pre-discharge development at an insulator surface with a protruding disturbance near the anode.
Pre-discharge development at an insulator surface with a protruding disturbance near the cathode.
Particle dimensions Ambient field non-uniformity Gas composition Particle deformation Number of particles - free
Surface conditioning of the enclosure is essential. Any surface conditioning process must address: oxide layers, die marks, burrs and loosely attached machining debris.
Loss of dielectric strength of SF 6 in the presence of a 0.45/6.4 mm wire particle in a coaxial system subject to direct voltages.
Hjk
L;l
L;l
L;l
H
L L L
Comparison of the effect of coefficient of restitution on the calculated maximum bounce height for 0.45/6.4 mm copper particles, field strength 2.5 kV/mm peak, 60 Hz.
Q-control of machining of components Ultra-sonic cleaning of components Adhesive tapes/coatings Particle traps Dielectric coatings Conditioning
Flexible CGIT system with double corrugated conductor and injection molded insulators
BUT A metallic particle on a dielectric coating may acquire charge by: conduction through coating by partial discharge between particle and coating
OR by contact charging from and already charged surface
Effect of applied voltage on maximum height reached by an aluminum wire particle (0.45 mm dia./6.4 mm long) in a 70/90 mm GIS/GITL system (_______ uncoated, - - - coated) for a coefficient of restitution of 0.95.
Comparison of calculations and measurements: Particle motion from calculations and videotape observation.
12/13/2010
33
12/13/2010
34
hj
Smoothed curves of lifting field vs. pressure for spherical SS particles 1.5 mm diameter.
Very Fast Transient Over voltages (VFTO) and Transient Enclosure Voltages (TEV) During GIS Operation
Dr. M. Mohana Rao
BHEL Corporate R&D Hyderabad E-mail: mmrao@bhelrnd.co.in
What is VFT?
In a GIS, Very Fast Transient Over voltages (VFTO) are generated mainly due to switching operations. The voltage collapse across switching contacts takes place in 3 to 20 ns depending on breakdown voltage, electric field nonuniformity and operating gas pressure. The short-rise time pulse (i.e., voltage collapse) starts at the switching contacts that propagate along the gas insulated bus sections/components and take reflections at different terminations. Because of superposition of the original pulse with the reflected pulse, VFTO are developed. The waveform of these transients depends on the configuration of the GIS. The VFTO levels are found to be on the higher side for the following conditions of the switching configurations: (1) Small length of bus sections on the load side of the switch. (2). High surge capacitance components on source side of switch (3.0 P.u.).
DS Operation
GENERATION OF VFTO
Load voltage
Opening Operation
Source voltage
Earthing of GIS
GIS Earthing is possible in Two ways:
In single point earthing each enclosure is isolated from next one and grounded each enclosure at only one point so that no loop currents.
In multiple point earthing enclosures are electrically connected and grounded at many locations. In addition the enclosures of the different phases are connected by shunts.
12/13/2010 6
Earthing of GIS
multiple point earthing
Earthing of GIS
1. Return Conductors 2. Earthing conductors 3. Return and Earthing Conductors 4. GIS earthing mat.
12/13/2010 8
Earthing of GIS
Multipoint Earthing is advantageous than single point earthing because of the following:
Reliability of grounding
Low magnetic field intensity outside the enclosure VFT related Flashovers Can be controlled.
12/13/2010
Earthing of GIS
In Multipoint Earthing the following aspects are Important: 1. Only small portion of the return current flow through the earthing conductors.
2. The current induced in the enclosure could be up to 90 to 95 % of the rated current. 3.To avoid excessive currents in grounding grid (earthing net) the enclosures are connected by inter-phase shunts.
4. Due to multiple eathing connections loops are formed which carry very high induced currents due to strong electromagnetic field coupling and low impedances.
12/13/2010 10
VFTO LEVELS?
Characteristics of VFT
VFTC LEVELS ?
Such transient voltages on the grounded enclosure arise from an internal collapse of voltage in the SF6 gas, internal re-strikes across circuit breaker or disconnect switch contacts, or flashover of external insulation close to GIS, e.g., and air-SF6 bushing.
GIS enclosure is electrically continuous. GIS enclosure is grounded at several points. Induced magnetic field on the metallic structures and the control circuits are reduced due to the flow of major portion of return current in the GIS enclosure.
GIS data:
.
Z1 = 60 - 450
For a bushing transient the TEV ~ (S1) (Trav. wave) where S1 = - _2Ze_ Z1+Z2+Ze Voltage going out to line is ~ (S2) (Trav. wave) where S2 = - 2Zg_ 2Zg+Ze Zg = surge imp. of ground connection Ze = surge imp. of enclosure S1 = 0.54 to 0.78 S2 = 0.54 to 0.75 Note: Significant over voltages can develop on the enclosure!
(For earthing practices in GIS installation see: W G 21.03 Rep. in Electra, No. 151, Dec., 1993, PP. 3152)
Distribution of degree of importance assigned by users to the development of technology to monitor parameters
Distribution of major failure causes reported by users for all voltage classes.
Major failure frequency (FF) 2nd GIS survey total population and comparison between the 1st and the 2nd survey results.
Identification of main component involved in the failure from GIS voltage class point of view.
CIGRE Survey 2000: Identification of main component involved in the failure from GIS age point of view (5 most involved components).
12/13/2010
17
145 kV GIS
12/13/2010 Pre-fabricated Cable Connection 19
12/13/2010
20
145 kV GIS
VT
T-Isolator
21
145 kV GIS
12/13/2010
22
300
CURRENT, A
200
VOLTAGE, kV
100
POWER, MVA
0 0 500 1000 1500 2000 2500
TIME, HRS
12/13/2010 145
SOF4
SiF4
0.085
0.085
S2F10
SO2F2 SO2 HF
0.026
0.006 0.002 1.0
Compound SOF2
SO2
HF S2F10
2
3 0.01
decomposition source
toxicity (weighted)
hot contacts
partial discharges
SOF2 SF4
gas gas
low low
high medium
medium high
decomposition source
toxicity (weighted)
medium high high non toxic medium non toxic non toxic
internal arcs
Chemical measurements. Example of chromatographic measurements. Defect a): PD level of 10-15 pC. SOF2 and SO2F2 by-products as a function of the time under voltage.
Chemical measurements. SOF2 and SO2F2 by-products measured after various events. *High sensitivity (0.1 ppmv) chromatography (TCD + FPD/SSD) **Lower sensitivity (50 ppmv) chromatography (TCD only)
A comprehensive catalogue of guidelines for the handling and management of SF6 is available from the US EPA.
B.
By itself SF6 is non-toxic and the TLV level is about 1000 ppmv.
However, many organizations require a much lower level. Three levels of personnel protection recommended are:
Low 1000 ppmv Intermediate 200 ppmv High 20 ppmv Breakdown by-products arise, both under arcing and under low-energy discharges, such as corona. Above ~500C SF6 begins to break up and at ~3000C dissociation is complete. During the cooling period, at ~1000C, many chemical reactions occur. H2O is a major factor.
SF6 As a Greenhouse Gas SF6 concentration in upper atmosphere has doubled in the past decade. Increasing at ~8.7% / year. Elect. industry uses ~80% of world production of SF6 (~7000 metric tons in 1993), and the production is expected to grow to ~10,000 metric tons by 2010. SF6 is 25000x more effective than CO2 as a Greenhouse gas. Environmental activists, however, argue that for estimating a worst case impact we must assume that ALL SF6 will eventually leak into the global atmosphere. Estimates show that SF6 concentration in upper atmosphere is rising at 8.7% per year. Approx. doubled in a decade. Could reach 10 parts in 1012 by vol. by 2010.
If the present usage trends continue SF6 contribution to the greenhouse effect could reach 0.1% by the end of the 21st century. No reliable estimates of how much actually leaks into the Earths atmosphere. No inventory check or validation of used gas stockpile is maintained. SF6 can be destroyed by incineration at 1100C in waste disposal plants.
The measurements were made using two polished brass spheres of diameter 1 inch contained in a glass cell which could be evacuated. The spark gap was generally 0.015 to 0.020 inch. The apparatus was checked frequently by the measurement of the relative electric strength of SF6. The average value of this was 2.5.
So, there is concern in industry about the long-term prospects for its continued use in switchgear and GIS. Hence, the interest in mixtures.
Measured and calculated 60 Hz ac breakdown voltage values for SF6/N2 mixtures. Similar behavior is exhibited under lightning and switching impulse voltages
Improved one-break circuit breakers for transmission voltage GIS for urban
compact centers.
Replacement of existing AIS by GIS will accelerate, especially near urban centers.
New Developments
UHF partial discharge detection HVDC GIS SF6/N2 mixtures Long GITL installations Compact substations
Simulated 50 year life. Renewed interest in flexible lines. However, the biggest challenge is the design of long 100 m sections. How to mechanically support the conductor?
Switching impulse tests for SF 6/N2 mixture confirm theoretical models. Recycling guidelines for SF 6 and extracting SF6 from SF6/N2 mixtures are now available. Three phase rectangular enclosures for 500 kV class have been tested (~200 cm x 200 cm). Long-term field tests for GIL: minimum 1 year on a 100 m section.
Recent Developments
Leakage of SF6 <0.5% / yr Combined VT/CT Single-break CB for 550 kV 1100/1200 kV Prototype GIS Refurbishing of old GIS Replacement of AIS in urban areas Mechanical design to allow for SF 6/N2 mixtures
RE: Maintenance several categories may be defined and equipment classified, e.g.
Routine inspection Preventive maintenance Repair maintenance Corrective/special maintenance and component categories may be: Active or Passive Primary Secondary equipment
Most major utilities have codes of practice for delivering maintenance services for GIS
Field Test of 1000kV Gas Insulated Switchgear Basic specifications and ratings
Field Test of 1000kV Gas Insulated Switchgear Field test items on switchgear
Technology AIS
Type
Termination
Space Reqt.
GIS
Indoor/ outdoor
H-GIS
12/13/2010
Medium
14
12/13/2010
16
12/13/2010
17
12/13/2010
18
Hybrid GIS
12/13/2010
19
12/13/2010
20
12/13/2010
21