Contacts
Councilmember Various
Progress
Architect
T.B.D
Project Manager Capitol View, Cleveland Park, Shepherd Park, Lamond Riggs, Palisades, Southwest, West End and Woodridge The Library has received Federal Stimulus Money for energy enhancements. Projects will take place at the above locations, focusing on window replacements, energy efficient lighting, and automated building heating and cooling controls Contractor
DCPL PM Firm
Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Hess Construction
Progress
Steel work is complete Light weight concrete floor slabs complete Curtain wall installation underway
Design of the new Francis Gregory Library will include community input on planning and programming phase. Project is fully funded.
DCPL PM Firm
Contacts
Councilmember Ward 1 Jim Graham 202.724.8181
Progress
Architect
Core Architects
Dale Stewart 202.466.6116 Project Manager Contractor Phase II of Mount Pleasant Renovation. Interior work will consist of total upgrade and modernization of all mechanical equipment as well as provide additional and functional library program space. Chris Wright 202.727.4913 T.B.D
Selective Demolition work is COMPLETE. Excavation for addition is COMPLETE Addition is complete Zoning Variance Hearing September 17th
Smoot Construction
Contacts
Councilmember Ward 6 Tommy Wells 202.724.8072
Progress
Architect
N/A
Cost Benefit Analysis and Pre-design Due Diligence Reports - Complete Design and Construction Funding for interior renovation is in Mayors FY 12 Capital Budget RFP for Design-Builder expected for issue September 20, 2011
Pre-design due diligence work includes a hazardous materials survey, a Phase 1 and Phase 2 Environmental Site Assessment and a Cost Benefit Analysis Study.
Contacts
Councilmember Ward 8 Marion Barry 202.724.8045 Architect Wiencek/Adjaye Scott Knudson 301.948.6220 Project Manager Contractor Lisa Deanes 202.727.5181 Coakley-Williams
Progress
Concrete Structure work complete Concrete work schedule to be complete in early April. 3 pavillians are complete Curtain wall installation underway
Design of the new Washington Highlands will include community input on planning and programming phase. Project is fully funded. DCPL is partnering with the DC Department of Housing and Community Development.
DCPL PM Firm
Contacts
Councilmember Ward 5 Harry Thomas Jr. (202) 724-8028
Progress
Architect
N/A
Pre-design due diligence work includes a hazardous materials survey, a Phase 1 and Phase 2 Environmental Site Assessment, Existing Topographical Survey, Geotechnical Report and a Cost Benefit Analysis.
Cost Benefit Analysis and Pre-Design Due Diligence Reports are Complete
Chris Wright 202.727.4913 Hill and Argos Gilberto Cardenas 202.379.4889
Design and Construction funding identified in Mayors Capital Budget. Design funding in FY 13.
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
The Freelon Group
Progress
Space planning for Business, Science and Technology Complete Design is nearing completion 7 bids for construction manager received Sept. 2nd Funding for building out indentified in Mayors FY 12 Capital Budget.
Improvements and upgrades to west reading room. Entire first floor is under the Historic Landmark Designation. The MLK Design Guidelines will be utilized.
Completed Projects
Anacostia Library New Building Construction Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect Freelon Group Philip Freelon 919.941.9790 Project Manager Dedric Boyd 202.727.1127 Contractor Forrester Construction Tom Willerton 301.816.1700 New State of the Art Library on Good Hope Road SE is open. DCPL PM Firm Hill International
Progress
Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Davis, Brody, Bond & Aedas Peter Cook 202.449.1190 Project Manager Contractor Kim Fuller 202.442.6069 Forrester Jon McGee 301.255.1750
Progress
Architect
New State of the Art Library located at 3935 Benning Road NE is open.
DCPL PM Firm
A-1 Consulting
Contacts
Councilmember Ward 3 Mary Cheh 202.724.8062 Architect
N/A
Progress
Project Manager
Ed Hampton 202.442.6067
Project Complete
Eagle Construction
Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect EEK Sean ODonnell
Progress
Project is a partnership with the Department of Parks and Recreation to co-locate a 10,000 square foot library within a 54,000 square foot aquatic center and community center. Library and Community Center would share such space as computer lab, senior rooms, tutor rooms and community meeting rooms. Project location is 49th and Quarles St. NE
Contacts
Councilmember Ward 7 Yvette Alexander 202.724.8068 Architect
Progress
Project Manager
Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets
DCPL PM Firm
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
Martinez & Johnson
Progress
Tom Johnson 202.333.4480 Project Manager Contractor Chris Wright 202.272.4913 N/A
Renovation complete and Library open to the public. DCPL PM Firm Smoot Construction
Contacts
Councilmember Ward 1 Jim Graham 202.724.8181
Progress
Architect
Core Architects
Dale Stewart 202.466.6116 Project Manager Contractor Project consists of building a 3,600 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets Dedric Boyd 202.727.1127 MCN Build Bassem Boustany 202.333.3424
Opened to the public April 26, 2010 Re-opened to the public May 15, 2010
Contacts
Councilmember Ward 6 Tommy Wells 202.724.8072
Progress
Architect
Bell Architects
David Bell 202.548.7570 Project Manager Chris Wright 202.727.4913 Contractor Monarc Construction C. McDermott, Project consists of Exterior Improvements to windows, doors, security lighting, masonry restoration, landscaping and signage. 703.201.1747
Construction
Substantial completion May 15, 2010
Contacts
Councilmember Ward 6 Tommy Wells
Progress
Architect
Reagan Assoc
Forrester
Project consists of 6,500 SQ FT Library facility as part of Elementary School and Recreation Center. This facility replaces the Sursum Corda kiosk.
Contacts
Councilmember Ward 8 Marion Barry 202.724.8045
Progress
Architect
Mood Nolan - DC
Patrick Williams 202.244. Project Manager Contractor Project to fit out approximately 5,000 Sq Ft of storefront space to replace the existing Parklands-Turner kiosk. The storefront library is similar in size, scope, computers, and collections to the Georgetown Interim and Tenley-Friendship Interim Libraries. Dedric Boyd 202.727.1129 Lexx Group Ken Postell 202.393.
10
Contacts
Councilmember Ward 4 Muriel Bowser 202.724.8052 Architect N/A
Progress
Project Manager Contractor Project consists of building a 4,200 square foot interim library to serve the community during construction; the interim will have 30 computers, books on CD as well as traditional collection material for all age sets
DCPL PM Firm
Contacts
Councilmember Councilmember Ward 4 Architect Muriel Bowser 202.724.8052
Frank and Loshen
Progress
Fletcher Farr Anoyte Project Manager Contractor Project updates the interior of the Petworth Library to be a fully functional state of the art 21st Century Library, while still being respectful of the buildings historic character.
DCPL PM Firm
11
Contacts
Councilmember Ward 3 Mary Cheh 202.724.8062 Architect Freelon Group Philip Freelon 919.941.9790 Project Manager Contractor Dedric Boyd 202.727.1113 Forrester. Joe Ockershausen 301.255.1794 DCPL PM Firm Hill International
Progress
Design of the new Tenley Branch Library will include community input on planning and programming phase. Design and construction is fully funded.
Contacts
Councilmember Ward 8 Marion Barry 202.724.8045 Architect Cooper Carry
Progress
Project Manager Contractor Project consists of building a 5,000 square foot interim library for the Washington Highlands Community; the interim will have 20 computers, books on CD as well as traditional collection material for all age sets.
DCPL PM Firm
12
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Davis, Brody Bond & Aedas Peter Cook 202.449.1190 Project Manager Contractor Kim Fuller 202.442.6069 Forrester. Joe Ockershausen 301.255.1794 DCPL PM Firm A-1 Construction
Progress
Architect
Martin Luther King Jr. Library New Teen Spot and College Information Center
Contacts
Councilmember Ward 2 Jack Evans 202.724.8058 Architect
Sorg Associates
Progress
Suman Sorg Project Manager New Teen Spot and College Information Center is a destination for teens. It provides stimulating learning opportunities that support their success in life. This destination provides opportunities to meet their need for homework help, exam preparation, and using computers and software applications. High quality program events are a key to the success of the library in assisting teens. Contractor
Project Complete
13