Sie sind auf Seite 1von 7

International Journal of Project Management 20 (2002) 221–227

www.elsevier.com/locate/ijproman

Combining value and project management into an effective


programme management model
Michel Thiry
Boulevard G. Van Haelen, 193, 1190, Brussels, Belgium

Abstract
In this paper, I will suggest that the current Programme Management paradigm is strictly performance-based. I will aim to
demonstrate that there is a need for both a performance and a learning process in the management of programmes. Following this
demonstration, I will suggest that value management can be combined with project management to form an integrated learning-
performance programme management model. I will further develop this concept by identifying some specific methods and techni-
ques which can be used to implement such a model. I will also recommend the iterated application of the model, throughout the
programme life cycle from strategic choice, to business objectives and feasibility, through planning and appraisal, and finally ter-
mination. # 2002 Published by Elsevier Science Ltd and IPMA. All rights reserved.
Keywords: Programme management; Project management; Value management; Performance; Learning; Uncertainty; Ambiguity.

1. An emerging paradigm in programme management 1.1. The current programme paradigm

There are a number of definitions of programme Roland Gareis [5] of the University of Vienna, affirms
management; most of them, by organisations that are that any project lasting longer than 2 years should be
heavily into project management like PMI (Project called a programme; a number of project managers, like
Management Institute), APM (Association for Project Gareis, associate programmes with large projects. Other
Management) or CCTA (Central Computer and Tele- authors associate it to multi-project co-ordination or
communications Agency). All these definitions have portfolio management, which is often associated with
both, things in common and differences. The main resource management; [6] or account-client manage-
common points are that programmes usually cover a ment; this view is also emphasised by ‘‘Programme
group of projects; that their management must be co- Management’’ computer software, which is essentially
ordinated; and that they create a synergy, which will designed to support resource management, planning
generate greater benefits than projects could do indivi- and cost/time control.
dually. The main differences are: the fact that they also Another view is that of Becker [7], Pellegrinelli [8],
cover ongoing operations (PMI [1]); that the elements Reiss [9] and Bartlett [10] who link programmes with
must have a common objective (APM [2]) and the fact organisational change, often IT-based. Although a
that their impact is at the organisational level and con- number of programmes are about change. Even those
cerns change (CCTA [3]). who advocate that programmes are more than just large
Ruth Murray-Webster and I [4] have tried to integrate projects and need to address strategic benefits, still pro-
those three elements in our definition: ‘‘A collection of mote a project paradigm to run programmes. For
change actions (projects and operational activities) pur- example, the recently developed Programme Manage-
posefully grouped together to realise strategic and/or ment Maturity Model (PMMM) [11] points out that
tactical benefits’’. The concept of purposefulness is most organisations still consider ‘organisation’, ‘issues
related to the objectives, which need to be defined; the and risk’, ‘planning’ and ‘accounts and finance’ as key
word ‘actions’, refers to ongoing operations, as well as to the success of programmes, whereas ‘achievement of
projects; and the benefits can be both strategic or tac- benefits’, ‘stakeholders management’, ‘communications’
tical, but are always measured at organisational level. and ‘configuration management’ seem less important.
Partington [12] cites studies by Wateridge [13] and Pinto
E-mail address: michel.thiry@chello.be and Millet [14], to emphasise the fact that failures in
0263-7863/02/$22.00 # 2002 Published by Elsevier Science Ltd and IPMA. All rights reserved.
PII: S0263-7863(01)00072-2
222 M. Thiry / International Journal of Project Management 20 (2002) 221–227

large IT/IS projects are due to a ‘failure to address logical background in addition to tools; and taking into
people issues’. By concentrating only on performance account of the interrelatedness of projects. I would
issues, organisations are missing a key element of suc- argue, that programme management can provide those,
cess. but only if it encompasses a strategic decision perspec-
The concepts of learning organisations and manage- tive, which is ‘ambiguous and complex; fundamental
ment of emergent change stem from the works of lead- and organisation-wide and has long-term implications’
ing strategic management authors like Mintzberg et al. (Johnson & Scholes [23]).
[15], Weick [16], Senge [17] or Porter [18]. Currently, the Wijnen and Kor [24] write that a programme strives
concept of learning, including knowledge management, for the achievement of a number of, sometimes con-
and the capability to integrate and transform itself are flicting, aims and has a broader corporate goal than
key elements of successful organisations, programme projects, which aim to achieve single predetermined
management still ignores them. results. Görög and Smith [20], argue that strategic
Thiry [19] and Weick [16] (and similarly Daft and management is based on the continuous re-formulation
Lengel) have made a clear distinction between uncer- and is a form of continuous adjustment, whereas pro-
tainty and ambiguity/equivocality. Uncertainty is defined jects concentrate on achieving one single particular
by the difference between the data required and the data result within set time and cost constraints. Partington
already possessed; it is a ‘lack of information’. Ambi- [12] argues that programmes require integration across
guity, on the other hand, means the existence of multi- strategic levels, controlled flexibility, team-based struc-
ple and conflicting interpretations; it is linked to tures and especially, an organisational learning per-
confusion and lack of understanding. Whereas uncer- spective, which is able to accept paradox and
tainty leads to the acquisition of objective information uncertainty. Murray-Webster and Thiry [4] advocate a
and the answering of specific questions, ambiguity leads vision, which includes mechanisms to identify and
to sensemaking, the exchange of views and the defini- manage emergent change; they use an idea developed by
tion of situations/problems. Hurst [25] to promote the concept of a ‘learning loop’,
Generally, organisation, planning and cost manage- which completes the ‘performance loop’.
ment are key elements of uncertainty reduction, as well These concepts must be supported by an ‘ambiguity-
as risk management, which has become a key process in reduction’ process that needs to take place before any
the new ‘PMBOK# Guide’. Benefits, stakeholders, and attempt is made at uncertainty reduction (Fig. 1). It is
communications are softer issues, linked with the supported by: learning, value management, sensemak-
reduction of ambiguity, which project managers still do ing, information sharing, group decision support and
not apply explicitly Configuration management, as cur- ‘shared construction’ of statements. In management,
rently stated, is about the product, not the process, this process uses a range of ‘soft’ methodologies and
project managers traditionally direct a process and do techniques like stakeholder analysis, functional analysis,
not feel responsible for configuration beyond delivering ideation-creativity-innovation, soft systems analysis and
what was asked. Görög and Smith [20], argue that pro- others.
ponents of the current project (performance-based) Additionally, in the current organisational context
paradigm concentrate on describing tools and techni- and culture, of e-business and accelerated change, man-
ques, rather than, when to use the most appropriate for agers are required to process a large flow of often-con-
the situation, as do Thomas et al. [21]. tradictory information in a short time. Programme
I would therefore argue that the current programme managers, in particular, are caught right between the
paradigm is a ‘performance’ paradigm. It is about clear ambiguous, soft, ‘fuzzy’ realm of strategic management
objectives and deliverables and robust control techni- and the concrete, hard place of implementation. They
ques embedded in an ‘uncertainty-reduction’ process of have to deal with both high ambiguity and high uncer-
plan-execute-control with which Winch et al. [22] have tainty at the same time.
already associated to projects.

1.2. The emerging programme paradigm

Görög and Smith [20], who advocate the use of PM in


strategy implementation of organisations, imply that
project management needs to move towards a more
strategic-oriented paradigm, or as Thomas et al. [21] put
it: ‘promise-centric values (rather than product-centric)’.
They argue that this new paradigm involves: a cycle
which encompasses both strategic objectives and strate-
gic benefits evaluation; the development of a methodo- Fig. 1. The uncertainty–ambiguity relationship in change situations.
M. Thiry / International Journal of Project Management 20 (2002) 221–227 223

Decision-making and change situations often mean meters, or whether it is the circumstances that initiate a
that multiple stakeholders, with conflicting needs and whole new series of actions. The learning loop addresses
expectations, are competing with each other. The the processes required to manage both the emergent
expectations need to be brought out in he open and inputs and the decision-making process leading to its
discussed (Kirk [26]), stakeholders need to ‘make sense’ resolution.
of the situation (Weick [16]) and construct a shared As stated earlier, project management processes cover
understanding of it (Thiry [19]) before they can progress only the implementation part of the strategy process.
towards an agreed decision. It is a context where the aim There are three other important elements in strategy
is to identify and understand needs and expectations and management, which need to be taken into account; they
reduce ambiguity through negotiation before attempting are: (1) the making of the decision itself; (2) the apprai-
to use any kind of uncertainty-reduction process. sal of its benefit during implementation and; (3) the
To be adopted by progressive organisations, thriving changes that may influence its execution. These changes
in a complex, continually changing environment, a pro- will be triggered by either emergent inputs or the failure
gramme management paradigm would require to to achieve the stated benefits. It does not matter whe-
include both a learning, and a performance loop; to ther it is a strategic, portfolio or incremental pro-
address both uncertainty-reduction and ambiguity- gramme; these principles still apply.
reduction. Murray-Webster and Thiry [4] have described
this integrated process as the programme ‘eco-cycle’, 2.1. The learning loop
which Thiry [27,28] has later called a ‘Decision Man-
agement Cycle’ (Fig. 2). Some theorists associate learning purely to the acqui-
sition of knowledge. Bramley [30] defines it as ‘‘acquir-
ing the ability to behave in new kinds of ways’’. In
2. The proposed model Chinese ‘‘learning’’ literally means ‘‘study and practice
constantly’’ (in Senge [17]); finally Nevis, Di Bella and
The model developed in this paper acknowledges that Gould [31] define learning as ‘‘the capacity or processes
there are ‘deliberate’ (or planned) strategies and ‘emer- [. . .] to maintain or improve performance based on
gent’ (or unplanned) strategies [29]. experience’’. The Society of Learning defines it as:
Projects are triggered by a conscious decision to
undertake an action; they are based on clear, well- . . .individual and collective capabilities to under-
defined objectives and deliverables; they are a deliberate stand complex, interdependent issues; engage in
strategy. The project management process is initiated reflective, generative conversation; and nurture
with a high level of uncertainty at the beginning (high personal and shared aspirations.’’ (The Society for
assumptions/facts ratio); it then uses tools and techniques Organizational Learning (SoL) [32])
like work breakdown, risk analysis and planning, fol-
lowed by quality, time and cost control. All those methods In the context of this paper, ‘learning’ will be defined
are designed to accelerate the knowledge of the project as: ‘the capability to self-assess and feedback to improve
situation through information gathering and simulation; and innovate’ and consider that there is both a social
they are aimed at the reduction of uncertainty. process and a need for improvement involved in learning.
But, deliberate strategy is just the part of the process The learning cycle of programmes cannot be based on
that takes place after a decision has been made. The the same principles as the performance cycle; time,
‘emergent’ inputs, which will trigger the need for focus, decision and leadership take different dimensions.
change, should also concern the programme manager; Whereas, once a decision has been made, implementa-
whether they are a simple adjustment in a project para- tion time should be as short as possible, as it becomes a
success factor; more time is required for the interaction
leading to the decision. Whereas planning and execution
must be rational, analytical and efficient, the process
leading to decision making will rely more on sensemaking
and intuition, it will require innovation and creativity.
Leadership, during the performance cycle is more
deliberate, during the learning cycle; leadership requires
a more consultative approach. In the performance cycle,
the project needs to be broken down into work packa-
ges, and roles and responsibilities clearly allocated so
that resources can be focused on simple specific tasks
without questioning. In the learning cycle, the same
Fig. 2. The integrated programme management cycle model. resources will need a holistic approach of the project in
224 M. Thiry / International Journal of Project Management 20 (2002) 221–227

order to be able to identify a wide range of opportu-


Note 1: In programme management, this would mean
nities; the project has to be viewed as a system of com-
to identify the stakeholders.
plex interactions to which everybody can contribute.
In line with the decision management model, I have
2.2. Value management and learning grouped points (a), (c), (d) and (e) under ‘sensemaking’;
(b) and (f), under ‘ideation’ and (g) under ‘evaluation’.
I personally believe Value Management (VM) can Point (h) is partly the actual decision and, with (i) and (j)
offer programme managers the tools and techniques part of the performance loop review and change processes.
that are missing in project management to tackle the
learning loop of the programme cycle. As Kaufman [33]
stated: ‘‘The problem with most problem-solving dis- 2.3. Sensemaking
ciplines [. . .] is that they assume that the stated problem
is the real problem’’; VM is a problem identification, as The first premise of good programme management is
well as a problem-solving, methodology. to fully understand stakeholder needs and expectations.
The new VM Standard (BSEN-12973:2000) states Sensemaking has been described by a number of
that: ‘‘Value lies in achieving a balance between the authors. Louis [34] described it as: ‘‘a recurring cycle
satisfaction of many differing needs and the resources comprised of a sequence of events occurring over time.
used in doing so. The fewer resources used or the The cycle begins as individuals form unconscious and
greater the satisfaction of need, the greater is the value.’’ conscious anticipations and assumptions, which serve as
It also continues: ‘‘Value Management integrates the predictions about future events.’’ (p. 241). Weick [16]
operational managers’ efforts with those of higher suggests that ‘sensemaking is partially under the control
management [. . .] by concentrating objectively on out- of expectations’; it is ‘an interpretive process’. As for
comes which are in line with overall corporate objec- myself (Thiry [19]), I summarised it as ‘‘a system of
tives, in preference to local or short-term priorities.’’ interactions between different actors who are [. . .]
These are exactly the requirements bestowed upon the building a collective understanding of a situation,
programme manager by the proponents of a new para- developing a strategic model of the intervention and
digm. The standard describes a number of tools and defining a shared [. . .] desired outcome’’.
techniques which can be applied in the following steps In ambiguous situations, Quinn [35] advocates what
he calls: ‘good conversation’. It can be associated to
A Value Management study involves the applica- sensemaking and requires the following features:
tion of one or more methods to a specific subject
‘issues-oriented’, focusing on specific problems and
[. . .]. The Value Management study will, regardless
alternative courses of action;
of the level at which the study is being undertaken,
‘rational’, meaning ‘intelligible, reasonable and well
follow the sequence set out [. . .] below:
argued’;
a) define the objective(s) of the [. . .] study in relation ‘imaginative’ in the sense that they encourage ‘open
to the [. . .] Policy and Programme ; social interaction’ and;
b) identify the methods and the supporting processes ‘honest’ in that inputs must be true and agreed out-
needed to achieve the objectives and select the teams puts ‘honored’.
(see note 1) [. . .];
Sensemaking is triggered by expectations: ‘beliefs or
c) identify the functions which are essential to achieve
assumptions about the future’ [25], and the realisation
the objectives and which together will result in the
that the current situation is inconsistent with this vision.
objective being attained;
Stakeholders then need to enter a sensemaking process,
d) identify how to measure changes in performance
which, in the context of organisations, I [19] have
and use of resources;
defined as ‘an individual process grounded in social
e) set targets for performance and use of resources for
interaction’. In the paper, ‘Sensemaking in Value Man-
each of the functions identified above in the most
agement’ [19], I have described how VM can provide the
effective manner for the organisation as a whole;
methodology to achieve positive sensemaking and, ulti-
f) apply the methods and supporting processes to
mately, agreement on the benefits, success factors and
identify innovative ways of achieving the targets;
objectives of a solution to a complex situation.
g) select and validate proposals for improvement;
h) implement the proposals which have been chosen
2.3.1. Functional analysis (FA)
by the decision maker;
Specifically, I have recommended the use of FA as a
i) monitor and measure the outcomes and compare
technique to achieve positive sensemaking. The VM
with targets;
Standard states that: ‘‘FA is an essential component for
j) feed back results for continuous improvement [. . .].’’
quantifying value and is therefore at the heart of the
M. Thiry / International Journal of Project Management 20 (2002) 221–227 225

VM approach, at any strategic or technical level.’’ [36]. 2.5. Review, evaluation, change and feedback process
It states that a function ‘‘expresses the effect of a pro-
duct (see note 2) or of one of its constituents and is Once the decision to undertake a programme, sup-
accompanied by performance indications (see note 3) ported by a ‘collection of change actions’ is taken, the
(levels and flexibilities)’’. programme enters the performance loop.
The latest revision of the EFQM# Excellence Model
Note 2: a product describes both goods and/or
[38] now includes a ‘learning and innovation’ loop.
services.
Most proponents of the learning/performance paradigm
Note 3: performance indications corresponds to ‘key
[4,20,24] argue for a continuous re-evaluation or ‘re-
performance indicators’
formulation’ of the programme, in regards of the
Görög and Smith [20], describe functions as that achievement of organisational benefits, an inductive
which has to be ‘provided by the project results during (based on emergent inputs) and ‘formative’ (to improve)
the operating phase.’ type of evaluation/control. This view can be associated
‘‘FA, is used to: with a transformational leadership perspective [39,40],
or what Argyris and Schon [41] have called ‘double loop
. identify the functions of a product, a system or an
learning’. Quinn [35] argues that when the relationship
organisation;
between means and ends is not well defined, control will
. quantify the performances to be reached;
operate through ‘self organisation’ and encourage peo-
. [. . .] improve communication between those
ple to ‘speak up and to challenge received wisdom’. He
involved in the definition, design and development
sees ‘good conversation’ as a way to exercise control in
of the product.’’ (CEN36)
a positive, or should we say, ‘proactive’, way and states
Note that, in a programme environment, functions can that whatever perspective is taken, ‘extensive discussion
be expressed as benefits or objectives. should occur between parties involved in the control
The FA method requires stakeholders ‘to think in process’ (p. 387).
terms of objectives and end results’. It also requires an On the other hand, proponents of the performance
identification of all those who may ‘have particular paradigm (Bartlett [10]; CCTA [3]; Reiss [9]) argue for a
requirements or expectations with regard to the pro- deductive (based on set parameters) and ‘summative’ (to
duct’: a stakeholder analysis. FA, if well conducted, assess) type of control, based on performance para-
generally achieves a ‘comprehensive description of the meters such as time, cost, resources, risks, etc. This
functions and of their relationships, which may be sys- perspective is more associated with transactional lea-
tematically characterised, classified and evaluated’ [36]. dership [39,40], or ‘single loop learning’ [41]. Quinn [35]
The FA process usually involves the development of a defines it as: ‘‘a ‘warning bell’, a signal [. . .] that all is
function model, which I have previously called Function [. . .] not going according to plan leading to a discussion
Breakdown Structure [37]; it provides a representation of of the causes of deviation from anticipated performance
the agreed understanding of the expected functional and necessary remedies.’’ (p. 384). I would argue that it
benefits of the programme by the stakeholders. The is therefore not appropriate to programme manage-
FBS, because it classifies functions/benefits/objectives ment, as it does not allow for the flexibility necessary to
from the more abstract ‘strategic objective’ [20] to the the management of programmes.
more concrete ‘project solutions’, can become the fra-
mework of the programme, in the same way as the WBS 2.5.1. Programme appraisal
is the framework of the project. Programmes are usually long-term processes; most
programme management authors advocate, as part of
2.4. Ideation and evaluation the control process, ongoing re-evaluation of the pro-
gramme benefits and objectives, as the programme’s
I will not delve into details concerning those two expected benefits may change over time [3,10,20]. Fol-
aspects of the learning loop, only to say that pro- lowing the writings of strategic management authors
gramme managers would apply a creative thinking pro- [15,17] who advocate a continuous appraisal/learning
cess, promoted by VM, where creativity, imagination process, authors like Partington [12], Murray-Webster
and lateral thinking are to idea generation what eva- and Thiry [4], Wijnen and Kor [24] add the concept of a
luation, analysis and vertical thinking are to options formal programme appraisal process, the objective of
appraisal. Creative thinking promotes the alternative which is to reassess the programme’s critical success
use of those two techniques in order to produce a factors on a regular basis.
greater quantity of more innovative ideas and apply a The learning loop of the full programme cycle is
better selection and validation of alternatives. For more therefore repeated at regular intervals. In order to
information on this process, see Thiry [37]; Kaufmann achieve stakeholders’ satisfaction at the time of delivery
[33] or CEN [36]. [42], it is paramount that a sensemaking process be
226 M. Thiry / International Journal of Project Management 20 (2002) 221–227

included at each appraisal phase and that, when change better suited to deal with complicated, uncertain situa-
is required, alternatives be sought and evaluated to tions than complex, ambiguous ones.
maximise opportunities throughout the process. I have therefore suggested that value management, as
The VM Standard reinforces this concept in stating: defined in the new VM Standard BS EC 12973:2000,
‘‘The kind of FA and the kind of functions that are can offer the methods and techniques suited to complex
worked on may change during the progress of [the pro- and ambiguous situations. I have proposed a pro-
gramme], beginning with the formalisation of the mar- gramme management model, which integrates a learn-
keting objectives and ending with the validation of a ing/value loop with a performance/project loop to form
proposal, which ensures that the reliability and safety a full programme management framework. I have also
necessary for the fulfilment of the objectives will be suggested that the learning loop should be part of both
met.’’ [36] project reviews and programme appraisals in order to
The programme appraisal can be planned on a reg- achieve strategic benefits and stakeholders’ satisfaction
ular basis, but allowance must be made for ad hoc at delivery.
learning loops, when required by exceptional circum-
stances or emergent inputs. The appraisal can typically
lead to continuation, re-orientation or termination.
References
2.5.2. Project reviews
[1] PMI. Guide to the PMBOK#. Sylva, NC: Project Management
Project, or sponsor, reviews are quite well described in Institute, 2000.
the project management literature [1] under Scope Ver- [2] APM. Body of knowledge. In: Dixon M. High Wycombe, UK:
ification, Integrated Change Control and Quality Con- Association for Project Management, 2000.
trol. They basically consist of evaluating project [3] CCTA (Central Computer and Telecommunications Agency)
deliverables in regards of the stated project objectives. (1999) Guide to programme management ‘HMSO Publications’
Norwich.
In addition, in the emergent programme management [4] Murray-Webster R, Thiry M. Managing programmes of projects’
paradigm, it involves assessing those results against the Gower handbook of project management, 3rd edition. In:
critical success factors of the programme and, in gen- Turner, Simister, editors. Chapter 3. Aldershot, UK: Gower
eral, against the organisational benefits, determined by Publishing, 2000.
[5] Gareis, R. (1999) ‘‘May the PMBOKTM guide be challenged by a
the strategy. These requirements can be met by steps i)
new project management paradigm? Proceedings of the 30th PMI
and j) of the VM process described above. The use of Seminars and Symposium, PMI HQ Publishing, Newton Square,
VM in this instance enables the programme manager to PA.
ascertain that the project deliverables are still in line [6] Patrick (1999) ‘‘Program Management—Turning many projects
with the programme’s expected benefits.A typical step- into few priorities with TOC’’, PMI-99 30th annual seminars and
by-step process would include: symposiums proceedings, PMI HQ Publishing, Newton Square,
PA.
. reassess critical success factors (CSFs); [7] Becker M. Project or program management?, PM Network,
. identify changes in user needs and/or expectations; Vol.13- No.10. Drexel Hill, PA: PMI Communications, 1999.
[8] Pellegrinelli S. Programme management: organising project-
. assess probability-impact of deviation (risk analysis); based change. International Journal of Project Management
. generate change solutions; 1997;15:141–9.
. analyse value of alternatives: [9] Reiss, G. (1996) Programme management demystified, Spon
 business benefits; critical success factors; Press, London.
[10] Bartlett J. Managing programmes of business change. Woking-
 cost; time; quality/performance; resources;
ham: Project Manager Today Publications, 1998.
 contractual commitments and contingencies; [11] Reiss, G. and Rayner, P. (2001) ‘‘Programme management
 recommend corrective measures; maturity model’’, lecture presented on 22 February through the
APM Programme Management SIG.
. prepare change requests (if needed). [12] Partington D. Implementing strategy through programmes of
projects’ Gower handbook of project management, 3rd edition.
In: Turner, Simister, editors. Chapter 2. Aldershot, UK: Gower
Publishing, 2000.
3. Conclusions [13] Wateridge JF. IT projects: a basis for success. International
Journal of Project Management 1995;13(3).
[14] Pinto JK, Millet L. Successful information systems implementa-
For all those programme managers who believe that tion: the human side, 2nd Ed. Sylva, NC: Project Management
programmes are more than just bigger projects or a Institute, 1999.
portfolio of projects, there is a need to acknowledge [15] Mintzberg H, Ahlstrand B, Lampel J. Strategy safari. London:
that the main difference between programmes and pro- Prentice Hall, 1998.
[16] Weick KE. Sensemaking in organizations. London: Sage Pub-
jects is the complexity and ambiguity of the issues. As I lications, 1995.
have demonstrated in this paper, performance-based, [17] Senge PM. The fifth discipline—the art & practice of the learning
uncertainty-reduction project tools and techniques are organization. New York, NY: Currency Doubleday, 1994.
M. Thiry / International Journal of Project Management 20 (2002) 221–227 227

[18] Porter M. Competitive advantage. New York: Simon and Schus- [30] Bramley P. Evaluating training effectiveness. 2nd Ed. London:
ter, 1985. McGraw-Hill, 1996.
[19] Thiry M. Sensemaking in value management practice. Interna- [31] Nevis, E. C. Di Bella, A. J. and Gould, J. M. (1997)
tional Journal of Project Management 2001;19 2001:71–7. Understanding organizations as learning systems. The Society
[20] Görög M, Smith N. Project management for managers. Sylva, for Organizational Learning Website/Working Papers http://
NC: Project Management Institute, 1999. www.solonline.org/res/wp/learning-sys.html.
[21] Thomas, J., Delisle, C., Jugdev, K, Buckle, P. (2000) Selling [32] SoL (The Society of Learning) (1999) About SoL, reflections: the
Project Management to Senior Executives: What’s the hook? sol journal on knowledge, learning and change. MIT Press Jour-
Project management research at the turn of the millennium: pro- nals, Cambridge, MA. Vol.1–1, p. 2.
ceedings of PMI Research Conference 2000. PMI HQ Publishing, [33] Kaufman, J. (1998) Value management: creating competitive
Newton Square, PA. advantage. Crisp Management Library, Crisp Publications, Bal-
[22] Winch G, Usmani A, Edkins A. Towards total project quality: a dock, UK.
gap analysis approach. Construction Management and Econom- [34] Louis M. Surprise and sensemaking: What newcomers experience
ics 1998;16:193–207. in entering unfamiliar organizational settings. Administrative
[23] Johnson G, Scholes K. Exploring corporate strategy (4th Ed.). Science Quarterly 1980;25:226–51.
Hemel Hempstead, UK: Prentice Hall Europe, 1997. [35] Quinn JJ. The role of ‘good conversation’ in strategic control.
[24] Wijen, G. and Kor, R. (2000) Managing unique assignments. Journal of Management Studies 1996;33(3):381–4.
Gower Publishing, Aldershot, UK. [36] CEN (European Committee for Standardization). Value man-
[25] Hurst DK. Crisis and renewal: meeting the challenge of organi- agement, European standard BS EN 12973:2000. Chiswick: Brit-
zational change. Boston: Harvard Business School Press, 1995. ish Standards Institution (BSI), 2000.
[26] Kirk D. Managing expectations, PM Network, August 2000. [37] Thiry M. Value management practice. Sylva NC: Project Man-
Sylva, NC: Project Management Institute, 2000. agement Institute, 1997.
[27] Thiry, M. (2000) Successfully integrating value and project man- [38] EFQM (1999) The EFQM#excellence model. European Foun-
agement into a complete strategic decision making-implementing dation for Quality Management, Brussels.
cycle. Proceedings of the international business and corporate [39] Burns J. Leadership. New-York: Harper and Row, 1978.
strategy and planning congress 2000, Amsterdam. [40] Bennis W, Nanus B. Leaders: the strategies for taking charge.
[28] Thiry. M. (2001b) Strategic decision management in organisations: New-York: Harper and Row, 1985.
towards an integrative model of decision making and implementa- [41] Argyris C, Schon DA. Organizational learning: a theory of action
tion. Unpublished Research, Birkbeck College, London. perpective. Wokingham: Addison-Wesley, 1978.
[29] Mintzberg H, Waters JA. Of strategies, deliberate and emergent. [42] Neal RA. Project definition: the soft-systems approach. Interna-
Strategic Management Journal 1985;6-3:257–72. tional Journal of Project Management 1995.

Das könnte Ihnen auch gefallen