LARSEN & TOUBRO LIMITED

Power Project Management


Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 1 of 103

MONTHLY PROGRESS REPORT


Progress Report No- 11
Sep 2010

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT, (2 X 660 MW)


STEAM TURBINE GENERATORS & AUXILIARIES PACKAGE

OWNER:
JAIPRAKASH POWER VENTURES LIMITED
OWNERS CONSULTANT:

DEVELOPMENT CONSULTANTS PRIVATE LIMITED


EPC CONTRACTOR:
LARSEN & TOUBRO LIMITED

L&TS CONSULTANT:
L&T-SARGENT & LUNDY LIMITED

Issued for
Information

PS

SP/VP

VL

25/09/2010

Description

Prepared

Checked

Approved

Date

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 2 of 103

INDEX
SECTION
1

CONTENTS
Executive Summary

PAGE
NO.
4

1.1

Project Details

1.2

Progress Statistic

1.3

Major Achievements During The Month

1.4

S Curves

6-7
8

1.4.1

Overall S Curve

1.4.2

Engineering S Curve

10

1.4.3

Procurement S Curve

11

1.4.4

S Curve Trend Analysis

12

1.5

Areas of Support Required

13-14

1.6

Calendar of Major Events

15

Detail Project Status


2.1

Engineering Status

16
17

2.1.1

Engineering Progress Statistics

2.1.2

Engineering Progress for The Month

17-21

2.1.3

Cumulative Major Engineering Completed Till Sep10 ( Action 2)

21-25

2.1.4

Summary of Document Approval Status

26

2.1.5

Detail Figures of Engineering Drawings/Documents

27

2.1.6

List of Documents On Which Comments Awaited

2.2

Procurement Status

17

28-31
32

2.2.1

Procurement Progress Statistics

32

2.2.2

Procurement Progress for The Month

32

2.2.3

Vendor Progress for Major Packages

33-36

2.4

Milestone Status

37

2.4.1

L&Ts Plan # Unit 1

37

2.4.2

L&Ts Plan # Unit 2

38

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 3 of 103

2.4.3

Client Obligation Construction Phase # Unit 1 & 2

39

2.4.4

Client Obligation Commissioning Phase # Unit 1 & 2

40

Activities Planned For Next Month

41

3.2

Engineering Plan

42-44

3.3

Procurement Plan

44

Annexure

45

4.1

Document Control Index

46-58

4.2

Procurement Status

59

4.2.1

Ordering Status

60-64

4.2.2

Manufacturing Status

65-68

4.3

Project WBS Structure, Weightage Principle and Basis of Progress


Measurement

69-70

4.4

Primavera Schedule Level 2

71-99

4.5

Project Photographs

100-103

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 4 of 103

SECTION -1
EXECUTIVE SUMMARY

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 5 of 103

1.1 Project Details:


Project

: 2 x 660 MW Steam Turbine Generators & Auxiliaries


Package for Jaypee Nigrie Super Thermal Power Project

Owner

: Jaiprakash Power Ventures Limited, New Delhi

Owners Consultant: Development Consultants Private Limited, Kolkata

EPC Contractor

: Larsen & Toubro Limited,

Scope of Work

: Design, Engineering, Manufacture, Supply, Transportation,


Insurance, Erection, Testing, Commissioning, Performance
Guarantee Tests for 2x660 MW Steam Turbine Generators &
Auxiliaries

Project Key Dates

: LOI/NTP: - July 23, 2009

Project Completion

: Unit 1:- 45 months from NTP (April 22, 2013)


Unit 2:- 51 months from NTP (Oct 22, 2013)

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 6 of 103

1.2 Progress Statistics :

Overall Project (100%)


During the Month (%)
S.No

Description

Sch

Sch

Cumulative Till Sep (%)


Sch

Sch

(Early)

(Late)

Actual
(Early)

(Late)

Actual

Engineering

10%

0.33

0.27

0.39

5.03

4.01

4.90

Procurement

75%

2.69

2.56

1.92

20.79

19.74

18.49

Construction

15%

0.21

0.09

0.06

0.51

0.29

0.06

Overall

100%

3.23

2.92

2.37

26.33

24.04

23.45

1.3 Major Achievements During The Month:


1.3.1 General :
1) Kickoff Meeting for Condensate Extraction Pump held with M/s KSB, India at Pune

1.3.2 Engineering:
A) Documents Approved:
1) Calculation for LP Bypass Steam System Sizing (Rev C) Action 2
2) Crab drawing for 40/10T BFP Bay EOT Crane (Rev A) Action 2
3) DCD for Piping Stress Analysis (Rev E) Action 2

With this Approval, All DCDs have been approved in Action 2

B) Documents Submitted:
1) Single Line Diagram for Generator Circuit (Rev C)
2) Schematic Diagram of Generator Circuit (Rev B)
3) Schematic Diagram of Generator Auxiliaries (Rev B)
4) Condenser Datasheet (Rev D)

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 7 of 103

5) Technical Datasheet for HP Closed Feed Water Heater (Rev D), LP Closed Feed
Water Heaters (Rev C) and Duplex LP Closed Feed Water Heaters (Rev C)
8) GA Drawing for 115/15T x 31.20M Span TG Hall D/G EOT Crane (1&2) (Rev D)
9) Crab Sub Assembly for 115/15T x 31.20M Span TG Hall D/G EOT Crane
(1&2) (Rev D)

1.3.3 Procurement:
1) Order Finalized on M/s Siemens , India for Condenser Polishing Unit
2) RFQ for Erection Services released

Critical Forthcoming Client Obligation


Schedule Date
1) Service bay readiness for EOT crane erection
2) Clearance for insitu condenser
3) Turbine building readiness for STG erection

21-MAY-11
22-SEP-11
22-SEP-11

Requested Date
21-Apr-11
22-July-11
22-Aug-11

Note:- Requested date are given with reference to the JPVLs suggestion for adopting insitu
erection of condenser (Ref :- LTH-JPVLO-JNSTPP-T209001-10-L-0005, 18TH August 2010)

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 8 of 103

1.4 S - CURVES

Apr/13

Mar/13

Feb/13

Jan/13

Dec/12

45

Nov/12

55

Oct/12

Sep/12

Aug/12

Jul/12

Jun/12

May/12

Apr/12

Mar/12

Feb/12

Jan/12

Dec/11

Nov/11

Oct/11

Sep/11

Aug/11

Jul/11

Jun/11

May/11

Apr/11

Mar/11

Feb/11

Jan/11

Dec/10

Nov/10

Oct/10

Sep/10

Aug/10

Jul/10

Jun/10

May/10

Apr/10

Mar/10

Feb/10

Jan/10

Dec/09

Nov/09

Oct/09

Sep/09

Aug/09

Jul/09

OverallSCurveJaypeeNigrie2X660MWProject

100

95

90

85

80

75

70

65

60

EarlyCurve
Early Curve

50

LateCurve

40

35

ActualProgress

30

25

20

15

10

Apr/13

Mar/13

Feb/13

Jan/13

Dec/12

Nov/12

Oct/12

40

Sep/12

Aug/12

Jul/12

Jun/12

May/12

Apr/12

Mar/12

Feb/12

Jan/12

Dec/11

Nov/11

Oct/11

Sep/11

Aug/11

Jul/11

Jun/11

May/11

Apr/11

Mar/11

Feb/11

Jan/11

Dec/10

Nov/10

Oct/10

Sep/10

Aug/10

Jul/10

Jun/10

May/10

Apr/10

Mar/10

Feb/10

Jan/10

Dec/09

Nov/09

Oct/09

Sep/09

Aug/09

Jul/09

EngineeringSCurveJaypeeNigrie2X660MWProject

100

90

80

70

60

50

EarlySchedule

LateSchedule

ActualProgress

30

20

10

Apr/13

Mar/13

Feb/13

Jan/13

Dec/12

Nov/12

40

Oct/12

50

Sep/12

Aug/12

Jul/12

Jun/12

May/12

Apr/12

Mar/12

Feb/12

Jan/12

Dec/11

Nov/11

Oct/11

Sep/11

Aug/11

Jul/11

Jun/11

May/11

Apr/11

Mar/11

Feb/11

Jan/11

Dec/10

Nov/10

Oct/10

Sep/10

Aug/10

Jul/10

Jun/10

May/10

Apr/10

Mar/10

Feb/10

Jan/10

Dec/09

Nov/09

Oct/09

Sep/09

Aug/09

Jul/09

ProcurementSCurveJaypeeNigrie2X660MWProject

100

90

80

70

60

EarlyCurve
LateCurve
ActualPRogress

30

20

10

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 12 of 93

1.4.1 S Curve Trend Analysis:

Engineering
As far as cumulative progress is concerned the actual progress is below early curve
(well ahead of late curve) however monthly progress is ahead of scheduled progress
for this period
The cumulative actual progress is 49.04% against scheduled early (50.4%) and late
basis (40.1%) of Engineering progress respectively
Delay reasons are as follows:

Ordering of BFP and Drive Turbine for BFP had been delayed which is
hampering downstream Engineering
There were delay in final issue of Deaerator datasheet because of
Deaerator sizing criteria finalization
There were delay in sending comments from client side on 1st submission
of Datasheets & GAs of Condenser and Heaters which hampered
downstream progress of drawing review
There is delay in receipt of data regarding TG Building by DCPL/JPVL
(Refer Section 1.5) which is causing delay in 3D Modeling and LMTG
Engineering
There were delay in sending comments from client side on various LMTG
documents which caused delay in progress of drawing review

Procurement
As far as cumulative progress is concerned the actual progress is below late curve
The cumulative actual progress is 24.66% against scheduled early (27.7%) and late
basis (26.3%) of procurement progress respectively
Delay reasons are as follows

Ordering of BFP and Drive Turbine for BFP had been delayed which in turn
hampering downstream manufacturing progress
There were delay in final issue of Datasheets & GAs of Deaerator,
Condenser and Heaters which is hampering their downstream product
engineering ,sub ordering and other manufacturing activities

Overall
During the reporting period curve is below early curve. The cumulative actual progress
is 23.45% against scheduled early (26.3%) & late basis (24%) of overall progress
respectively

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 13 of 93

1.5 Areas of Support Required


S.No

Area of Concern

Constraint

Impact on

Action

Action

Target

Schedule

Plan

By

Date

Remarks

Engineering :1

Layout of Cable Trays within TG Building

Impact on 3D modeling

required from DCPL/JPVL

Delay in

JPVL/

Engineering &

DCPL

Immediate

Procurement
Progress
2

TG Building Beam .Brace bay sizes etc.

Major impact on Pipe routing and

Delay in

JPVL/

Piping Support Design

Engineering &

DCPL

Immediate

Firm inputs required

Immediate

Template's Manufacturing

Procurement
Progress
3

Structure Frame drawings and Concrete

Template Design

Layout Drawings of turbine deck design

Approval on MHI/MELCO documents

Manufacturing

JPVL/

Progress

DCPL

- Vendor Drawing review


- Downstream manufacturing
activities
(Refer section 2.1.6 for detail list)

DCPL

lead time is 4-5 months

Immediate

58 nos (A- 7,I -51 )

- Delay in

MHI/Melco documents

Procurement

are pending for approval

progress

for more than 30 days

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 14 of 93

Approval on HED documents

- Vendor Drawing review

- Delay in

DCPL

Immediate

11 nos (I -11 ) of HED

- Downstream manufacturing

Procurement

documents are pending

(Refer section 2.1.6 for detail list)

progress

for approval for more than


30 days

Approval on LTSL documents

DCPL
(Refer section 2.1.6 for detail list)

Approval on KSB (CEP) &,Flowserve (MD &


TD BFP) & AIL (EOT) documents

08 nos (I -8)of LTSL

- Delay in

documents are pending

Detail

for approval for more than

Engineering

30 days

- Delay in
(Refer section 2.1.6 for detail list)

Immediate

DCPL

Immediate

-01 no (A-1) of KSB(CEP)

Detail

-05 nos ( A-3, I-2)

Engineering

Flowserve(MD&TD BFP)
-13 nos (A-2 , I-11) AIL
(EOT) documents are
pending for approval for
more than 30 days

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 15 of 103

Calendar of Major Events :

Letter of Intent/ Notice To Proceed date

: 23/07/2009

LOI finalization meeting at Delhi

: 23/07/2009

Post LOI meeting with JPVL

: 27/07/09-28/07/09

Initial site visit

: 29/07/2009

Contract finalization meeting at JPVL , Delhi

: 03/08/09-11/08/09

Invoice submitted for first 5% advance payment

: 05/08/2009

Official contract signing & press meet at JPVL, Delhi

: 12/08/2009

First 5% Advance payment received

: 26/08/2009

Invoice submitted for second 5% advance payment

: 03/09/2009

L1 schedule approved

: 11/09/2009

Kick off meeting held at L&T Faridabad

: 23/09/2009

Layout finalization meeting held at DCPL, Kolkata

: 21/10/09-22/10/09

Contract review meeting at L&T, Vadodara

: 05/11/2009

Contract Coordination Procedure finalized @ JPVL,Noida

: 01/12/2009

Meeting regarding Project Insurance at JPVL, Noida

: 11/12/2009

Technical review meeting with JPVL, DCPL


at L&T Faridabad

: 07/01/10-08/01/10

L2 schedule finalized on

: 21/01/10

Technical review meeting with JPVL/DCPL


at DCPL, Kolkata

: 27/01/10-28/01/10

Technical Co-ordination meeting with JPVL/DCPL


at L&T Baroda

: 06/04/10-08/04/10

Jaypee Nigrie Site Visit by L&T personnel

: 19/04/10-23/04/10

PAC issued from client

: 01/05/10

TCM held with JPVL/DCPL at L&T Faridabad

: 15/06/10-18/06/10

Kick off Meeting for EOT crane with M/s Anupam Cranes,
India

: 01/7/10

Kick off Meeting for MDBFP & TDBFP with M/s Flowserve

: 28/07/10 29/07/10

TCM held & 3D Model Review Completed with JPVL / DCPL : 05/08/10 06/08/10

at L&T, Vadodara
Hazira Manufacturing Location Visit by JPVL senior official : 07/08/10

Kick off Meeting for Condensate Extraction Pump with M/s KSB held at Pune : 14/Sep/10

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 16 of 103

SECTION-2
DETAIL PROJECT STATUS

PROGRESS WEIGHTAGE

10%

15%

75%

Engineering10%
Procurement75%
Construction15%

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 17 of 103

2.1 ENGINEERING STATUS:


2.1.1 Engineering Progress Statistics

Engineering (100%)
During The Month (%)

Cumulative Till Sep10 (%)

Early Sch (%)

Late Sch. (%)

Actual (%)

Early Sch (%)

Late Sch. (%)

Actual (%)

3.3

2.6

3.9

50.4

40.1

49

2.1.2 Engineering Progress for the Month:A) Documents Approved:


Sl
No.

Document No.

Description

Rev
No

Action Cat.

LTSL Drawings/Documents
1.0

DCD
LTSL-M0-00115

2.0

DCD - Piping Stress Analysis

Calculation
LTSL-M0-00305

3.0

Calculation for LP Bypass Steam System Pipe


Sizing

List
LTSL-M1-00701

List -Pipeline

LTSL-M1-00702

List-Valve

LTSL-M1-00703

Specialty Item List

LMTG Drawings/Documents
1.0

Turbine
LMTG-M0-01004

Oil Piping Diagram

LMTG-M0-01017

Equipment List for Steam Turbine

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 18 of 103

2.0

Generator
LMTG-E0-02005

Electrical Load List

LMTG-E0-02315

Turbine Generator Terminal & CT Assembly

LMTG-E0-02102

Specification & Schematic Diagram of AVR


Cubicle

LMTG-E0-02311

Turbine Generator H2 Gas Dryer Outline

LMTG-E0-02313

Turbine Generator Vapour Extractor Outline

LMTG-E0-02314

Turbine Generator Loop Seal Tank Outline

AIL Drawings / Documents


1.0

EOT
AIL-M0-03255
AIL-M0-03215
AIL-E0-03272-76

Crab Drawing for 40/10T BFP Bay EOT Crane


Electrical Equipment Layout in Cabin for 115/15 T
TG Hall EOT Crane
GA Drawing of Control panel for 40/10T BFP Bay
EOT Crane

KSB Drawings / Documents


1.0

CEP
KSB-M0-03504

P&ID for Condensate Extraction Pump

B) Documents Submitted During Reporting Period:


Sl No

Document No

Description

Rev
No

Cat.

LTSL Drawings/Documents
1.0

P&ID
1)

LTSL-M1-00209

P&ID for Circulating Water System

HED Drawings/Documents
1.0

Condenser

1
(IFC)

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 19 of 103

1)

LT-M0-03000-DS

Condenser Datasheet

2)

LT-M0-03025

Painting Scheme for Condenser

2.0

Deaerator
1)

LT-M0-03100-DS

Data Sheet for Deaerator

2)

LT-M0-03117

Painting Scheme for Deaerator

3.0

Heaters
1)

LT-M0-03057

2)

LT-M0-03070

3)

LT-M0-03079

4)

LT-M0-03094

Technical Datasheet for HP closed Feed Water


Heaters
Technical Datasheet for LP closed Feed Water
Heaters
Technical Datasheet for Duplex LP closed Feed Water
Heaters
Painting Scheme for Feed Water Heaters

LMTG Drawings/Documents
1.0

Turbine
1)

LMTG-I0-01302

Drive List for TCS and TPS

2)

LMTG-M0-01013

Utility List for Steam Turbine

3)

LMTG-M0-01014

Electrical Load List for Steam turbine

2.0

Generator
1)

LMTG-E0-02333

Turbine Generator Foundation Embedded Materials


layout (1/4)

2)

LMTG-E0-02005

Electrical Load List

3)

LMTG-E0-02011

Painting Color List (MELCO Portion)

4)

LMTG-E0-02315

Turbine Generator terminal and CT assembly

5)

LMTG-E0-0232302325

Turbine Generator Auxiliary Equipment Wiring Diagram


(3 sheets)

6)

LMTG-E0-02326

Turbine Generator Foundation Conduit arrangement

7)

LMTG-E0-0233002331

Turbine Generator Method of Mounting ( 2 sheets)

8)

LMTG-E0-02361

Turbine Generator grout retainer arrangement

9)

LMTG-E0-02362

Embedded plate arrangement for neutral cover support

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 20 of 103

10)

LMTG-E0-02007

Single Line diagram Generator Circuit

11)

LMTG-E0-02016

Outline drawing of generator control & synchronization


panel

12)

LMTG-E0-02017

Outline drawing of generator Auxiliary panel

13)

LMTG-E0-02023

Assembly drawing of Generator bushing CT terminal


box

14)

LMTG-E0-02031

Specification for Motor Local control panel

15)

LMTG-E0-02036

16)

LMTG-E0-02034

17)

LMTG-E0-02302

Turbine Generator H2 & CO2 gas diagram

18)

LMTG-E0-02601

Outline dimensions and unit datasheet of Unit 1 & 2


DC Motor starter

19)

LMTG-E0-02024

Schematic diagram of generator circuit

20)

LMTG-E0-02025

Schematic diagram of generator auxiliaries

21)

LMTG-E0-02602

22)

LMTG-E0-02035

23)

LMTG-E0-02807

24)

LMTG-E0-02808

25)

LMTG-E0-02809

Outline dimension of AC Motor for EH oil pump(A)

26)

LMTG-E0-02810

Outline dimension of AC Motor for EH oil pump(B)

27)

LMTG-E0-02605

General specification for unit 1& 2 distribution board

28)

LMTG-E0-02801

Outline dimension of AC Motor for Turning gear

29)

LMTG-E0-02802

Outline dimension of AC Motor for Auxiliary oil pump

30)

LMTG-E0-02803

Outline dimension of AC Motor for Jacking oil pump(A)

31)

LMTG-E0-02804

32)

LMTG-E0-02805

33)

LMTG-E0-02806

34)

LMTG-E0-02807

35)

LMTG-E0-02808

Outline drawing of Direct Current Motor for ST Jacking


oil pump (B)
Outline drawing of Direct Current Motor for ST
Emergency oil pump

Outline dimensions and unit datasheet of Unit 1 & 2


distribution board
Outline dimension of three phase induction motor for
ST turning oil pump
Outline dimension of AC Motor for main oil tank vapor
extractor fan(A)
Outline dimension of AC Motor for main oil tank vapor
extractor fan(B)

Outline dimension of AC Motor for Main oil tank oil


transfer pump
Outline dimension of AC Motor for storage tank oil
transfer pump
Outline dimension of AC Motor for polishing pump
Outline dimension of AC Motor for main oil tank vapor
extractor fan(A)
Outline dimension of AC Motor for main oil tank vapor
extractor fan(B)

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 21 of 103

36)

LMTG-E0-02809

Outline dimension of AC Motor for EH oil pump(A)

37)

LMTG-E0-02810

Outline dimension of AC Motor for EH oil pump(B)

38)

LMTG-E0-02605

General specification for unit 1& 2 distribution board

Other Vendors Drawings/Documents


1.0

Anupam Industries Limited - EOT Crane


1)

AIL-M0-03257

DSL System arrangement for 40/10T x 9M span BFP


Bay D/G EOT Crane

2)

AIL-M0-03206

Gantry rail installation for 115/15T TG Hall EOT Crane

3)

AIL-M0-03208

115T Main Hook block assembly for TG Hall EOT


Crane

4)

AIL-M0-03209

15T Aux. Hook block assembly for TG Hall EOT Crane

5)

AIL-M0-03210

LT drive Wheel Assembly for TG Hall EOT Crane

6)

AIL-M0-03211

LT Idle Wheel Assembly for TG Hall EOT Crane

7)

AIL-M0-03212

CT drive Wheel Assembly for TG Hall EOT Crane

8)

AIL-M0-03213

CT Idle Wheel Assembly for TG Hall EOT Crane

9)

AIL-M0-03214

LT Machinery Assembly for TG Hall EOT Crane

10)

AIL-M0-03230

11)

AIL-M0-03281

12)

AIL-M0-03204

13)

AIL-M0-03205

Typical Arrangement for Centralized Lubrication with


Hand pump for TG Hall EOT Crane
Structure Calculation for 40/10T x9M span BFP Bay
EOT Crane
GA Drawing for 115/15T x 31.20M span TG Hall D/G
EOT Crane (Crane no.-1 & 2)
Crab Sub Assembly for 115/15T x 31.20M span TG
Hall D/G EOT Crane (Crane no.-1 & 2)

2.1.3 Cumulative Major Engineering Completed Till Sep10 (Action-2)


SL No.

Drawing/Document No

Description

LTSL Drawings/Documents
1.0

Design Criteria Documents


1)

LTSL-M0-00102

DCD - Feed Water System

2)

LTSL-M0-00101

DCD - Condensate System

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 22 of 103

3)

LTSL-M0-00105

DCD - LP Bypass Steam System

4)

LTSL-M0-00103

DCD - Extraction Steam System

5)

LTSL-M0-00104

DCD - Heaters, Vents, & Drains System

6)

LTSL-M0-00107

DCD - Auxiliary Steam System

7)

LTSL-M0-00109

DCD - Circulating Water System

8)

LTSL-M0-00113

DCD - Service Water Distribution System

9)

LTSL-E0-00100

DCD - Electrical System

10)

LTSL-I0-00100

DCD - C&I System

11)

LTSL-M0-00108

DCD - Condenser Air Removal System

12)

LTSL-M0-00110

DCD - Closed Cooling Water System

13)

LTSL-M0-00111

DCD - DM Water Distribution System

14)

LTSL-M0-00112

DCD Instrument Air / Service Air Distribution


System

15)

LTSL-I0-00100

DCD-Condensate Polishing Unit

16)

LTSL-M0-00115

DCD-Piping Stress Analysis

2.0

Calculations
1)

LTSL-M0-00333

Calc - Feed Water Pump Sizing

2)

LTSL-M0-00332

Calc - Condensate Extraction Pump Sizing

3)

LTSL-M0-00302

Calc - Feed Water System Pipe Sizing

4)

LTSL-M0-00304

Calc - Heater Drain & Vent Pipe Sizing

5)

LTSL-M0-00308

Calc - Condenser Air Removal System

6)

LTSL-M0-00309

Calc - Circulating Water System Pipe Sizing

7)

LTSL-M0-00311

Calc - DM Water distribution system Pipe Sizing

8)

LTSL-M0-00301

Calc - Condensate System Pipe Sizing

9)

LTSL-M0-00305

Calc LP Bypass Steam System Pipe Sizing

3.0

P&IDs
1)

LTSL-M1-00200

P&ID - Index, Legends & Symbols

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 23 of 103

2)

LTSL-M1-00208

P&ID - Condenser Air Removal System

3)

LTSL-M1-00205

P&ID - LP Bypass steam System

4)

LTSL-M1-00207

P&ID - Auxiliary Steam System

5)

LTSL-M1-00201

P&ID-Condensate System

6)

LTSL-M1-00202

P&ID - Feed Water System

7)

LTSL-M1-00203

P&ID - Extraction Steam System

8)

LTSL-M1-00204

P&ID - Heaters, Vents, & Drains System

9)

LTSL-M1-00209

P&ID - Circulating Water System

10)

LTSL-M1-00211

P&ID - DM Water Distribution System

11)

LTSL-M1-00213

P&ID - Service Water Distribution System

12)

LTSL-M1-00210

13)

LTSL-M1-00212

P&ID - Closed Cooling Water System


P&ID - Instrument Air / Service Air Distribution
System

LMTG Drawings/Documents
1.0

Turbine
1)

2.0

LMTG-Q0-01000

QAP - Steam Turbine

Generator
1)

LMTG-E0-02016

Outline Drawing of Generator Control &


Synchronization Panel

2)

LMTG-E0-02017

Outline Drawing of Generator Auxiliary Panel

HED Drawings/Documents
1.0

2.0

Heaters
1)

LT-M0-03057

Technical Datasheet for HPH8A/8B,7A/7B,6A/6B

2)

LT-M0-03070

Technical Datasheet for LPH-4,LPH-3,

3)

LT-M0-03079

Technical Datasheet for Duplex Heaters

4)

LT-QO-00001

QAP - HP Heater

5)

LT-QO-03002

QAP - LP Heater

Condenser

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 24 of 103

1)

LT-M0-03000-DS

Condenser Datasheet

2)

LT-QO-03000

QAP - Condenser

3.0

Deareator
1)

LT-QO-03003

QAP - Deaerator

Other Vendors Drawings/Documents


1.0

Anupam Industries Limited EOT Crane


1)

AIL-M0-03255

Crab drawing for 40/10T BFP Bay EOT Crane

QAP Drawings/Documents
1.0

QAP
1)

LT-QO-00002

QAP - Boiler Feed Water Pump & Booster Pump

2)

LT-Q0-00003

QAP - BFP Drive Turbine

3)

LT-QO-00004

QAP - Condensate Extraction Pump

4)

LT-Q0-00011

QAP - HT Motor

5)

LT-QO-00001

QAP - HP Heater

6)

LT-QO-03002

QAP - LP Heater

7)

LT-QO-03003

QAP - Deaerator

8)

LT-QO-03000

QAP - Condenser

9)

LT-Q0-00009

QAP - Condensate Polishing Unit

10)

LT-QO-00012

QAP - Vacuum Pump

11)

LT-QO-00013

QAP - DMCW Pump

12)

LT-QO-00014

QAP - Plate Heat Exchanger

13)

LT-Q0-00010

QAP - EOT Crane

14)

LT-Q0-00020

QAP - Online tube Cleaning System

15)

LT-Q0-00019

QAP - Vibration Monitoring System

16)

LT-Q0-00021

QAP - Control Valve

17)

LT-Q0-00015

QAP - LP Bypass Valve

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 25 of 103

18)

LT-Q0-00016

QAP - HP Heater three way Bypass Valve

19)

LT-Q0-00018

QAP - Butterfly Valve

20)

LT-Q0-00017

QAP - Rubber Expansion Joint

21)

LT-Q0-00022

QAP - Metallic Expansion Joint

22)

LMTG-Q0-01000

QAP - Steam Turbine

23)

LMTG-Q0-00021

QAP-Control Valves

LARSEN & TOUBRO LIMITED

DOC NO:- LT-P0-00003

JAYPEE NIGRIE
SUPER THERMAL POWER PROJECT

POWER PROJECT MANAGEMENT


SERVICES, VADODARA

JOB NO: T209001

PAGE: - 26 of 103

2x660 MW STEAM TURBINE GENERATOR & AUXILIARIES

DOCUMENTAPPROVALSTATUS
SR.NO.

GENERATINGAGENCYOF
DOCUMENTS

LTSL Generated Document

CAT.
APP.
INFO.

TOTAL
2

MHI (Steam Turbine)

APP.
INFO.

TOTAL
3

APP.
INFO.

MELCO (Generator)

TOTAL
4

HED (Condenser, Deaerator & Hetars)

APP.
INFO.

TOTAL
5

ANUPAM (EOT Cranes)

APP.
INFO.

TOTAL
6

FLOWSERVE (Boiler Feed Pump)

APP.
INFO.

TOTAL
7

KSB (Condensate Extractionm Pump)

APP.
INFO.

TOTAL

GRANDTOTAL=
8

QAP

APP.
INFO.

TOTAL

TOTALNO.OF
DRG/DOC

SUBMITTEDTO
DCPL

APP.

APP.CAT.4

PENDINGFROM
DCPL

27
98
125
14
71
85
68
116
184
15
61
76
2
85
87
5
149
154
2
46
48

23
38
61
8
22
30
42
60
102
13
27
40
2
60
62
5
2
7
2
1
3

23
23
46
3
18
21
17
26
43
10
2
12
0
11
11
0
0
0
0
0
0

0
9
9
5
0
5
18
10
28
1
22
23
2
5
7
0
0
0
0
0
0

0
6
6
0
4
4
7
24
31
2
3
5
0
44
44
5
2
7
2
1
3

557

295

133

72

90

24
0
24

24
0
24

23
0
23

1
0
1

0
0
0

JAIPRAKASH POWER VENTURES


LIMITED

LARSEN & TOUBRO LIMITED


Power Project Mangement Services, Vadodara

Document No: - LT-P0-00003


Progress Report No: - 11

2 X 660 MW Steam Turbine Generator & Auxiliaries

Page No- 27 of 103

3.1.3 SUMMARY STATUS OF ENGINEERING DRAWINGS /DOCUMENTS


S.NO
A

DOCUMENT NAME

TOTAL NO OF
DOCUMENTS

A
I
Total
A
I
Total
A
I
Total
A
I
Total
A
I
Total
A
I
Total

DRAWINGS RELEASED
DURING THE MONTH
CUMULATIVE

CLIENT'S APPROVAL STATUS


CODE2

CODE3

CODE4

CODE5

CODE6

8
1
9
0
0
0
2
3
5
0
0
0
0
0
0
10
4
14

13
3
16
2
5
7
7
4
11
0
0
0
0
0
0
22
12
34

0
0
0
0
1
1
0
1
1
0
0
0
1
0
1
1
2
3

0
0
0
0
6
6
0
1
1
0
2
2
0
0
0
0
9
9

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
2
2
0
0
0
0
7
7
0
0
0
0
9
9

7
11
18
27
27
54
9
8
17
0
0
0
0
0
0
0
0
0
43
46
89
66
71
137

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
10
4
14

1
0
1
2
0
2
8
0
8
0
0
0
0
0
0
0
0
0
11
0
11
33
12
45

2
5
7
1
5
6
2
0
2
0
2
2
0
0
0
0
0
0
5
12
17
6
14
20

5
0
5
18
10
28
1
22
23
2
5
7
0
0
0
0
0
0
26
37
63
26
46
72

0
0
0
1
1
2
0
0
0
0
20
20
2
0
2
0
0
0
3
21
24
3
21
24

0
13
13
14
21
35
0
2
2
0
9
9
0
0
0
0
0
0
14
45
59
14
54
68

24
0
24

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

1st SUB

>1st SUB

FINAL SUB

1st SUB

>1st SUB

FINAL SUB

13
3
16
2
18
20
7
6
13
0
15
15
5
56
61
27
98
125

0
0
0
0
0
0
0
0
0
0
0
0
0
1
1
0
1
1

0
1
1
0
4
4
2
0
2
0
2
2
0
0
0
2
7
9

0
0
0
0
0
0
0
1
1
0
0
0
0
0
0
0
1
1

13
3
16
2
17
19
7
6
13
0
10
10
1
2
3
23
38
61

13
3
16
2
11
13
7
6
13
0
5
5
1
0
1
23
25
48

A
I
Total
A
I
Total
A
I
Total
A
I
Total
A
I
Total
A
I
Total
A
I
Total
A
I
Total

14
71
85
68
116
184
15
61
76
2
85
87
5
149
154
2
46
48
106
528
634
133
626
759

0
4
4
0
8
8
3
1
4
1
20
0
4
2
0
0
0
0
8
35
43
8
36
44

0
4
4
6
29
35
6
4
10
1
19
20
0
0
0
0
0
0
13
56
69
15
63
78

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
1
1

8
22
30
42
60
102
13
27
40
2
60
62
5
2
7
2
1
3
72
172
244
95
210
305

A
I
Total

24
0
24

0
0
0

0
0
0

0
0
0

24
0
24

LTSL DOCUMENTS

1.1

Design Criteria Documents

1.2

Calculation

1.3

P&IDs

1.4

Lists

1.5

Other LTSL Documents

Subtotal LTSL
C

MAJOR VENDOR DRG REVIEWS

MHI (Steam Turbine)

MELCO (Generator)

HED (Condenser, Deaerator & Heaters)

ANUPAM (EOT Cranes)

FLOWSERVE (Boiler Feed Pump)

KSB (Condensate Extraction Pump)

Subtotal of Vendor Drawing Reviews

Grand Total

L&T QUALITY DOCUMENTS

QAP

Note :-

DOCUMENT
CATEGORY
(A/I)

For Detail Enginerring list refer annexure 5.1 'Overall Engineering Status'

REMARKS

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara.

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR &
AUXILIARIES

JOB NO: - T209001

Document No:- LT-P000003


Progress Report No: - 11
Annexure No: Page No:- 28 of 103

2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
Approval Category
Sr No. Drawing No
1

Description

Rev No

Category

L&T DTN No.

DTN Date

LMTG-P1-01003

Heat Balance Diagram

DT0153

1-Jun-10

LMTG-M0-01020

Control and Lubricating oil System


Diagram

DT0153

1-Jun-10

LMTG-E0-02018

DT0156

4-Jun-10

LMTG-E0-02019

DT0155

4-Jun-10

LMTG-E0-02021

Outline Drawing of generator Seal


Oil Control Panel
Outline Drawing of Generator
Stator Coil Cooling Water Control
Panel
Arrengement Drawing of Generator
Seal Oil Control Panel

DT0155

4-Jun-10

DT0155

4-Jun-10

LMTG-E0-02022

Arrengement Drawing of Generator


Stator Coil Cooling Water Control
Panel

LMTG-E0-02014

LOGIC DIAGRAM OF
GENERATOR AUXILIARIES

DT096

16-Mar-10

AIL-M0-03201

Data sheet of 115/15 T TG Hall


EOT Crane (Double Girder)

DT0231

17-Aug-10

AIL-M0-03251

Data sheet of 40/10 T BFP Bay


EOT Crane (Double Girder)

DT0231

17-Aug-10

10

FPD-M0-03311

Complete Grout Pump Datasheet

240

23-Aug-10

11

FPD-M0-03466

Motor Sizing Calculation

240

23-Aug-10

12

FMD-M0-03311

Complete Grout Pump Datasheet

240

23-Aug-10

KSB-M0-03503

CEP GA drawing common for


pump & motor access

DT-0205

23-Jul-10

13

Information Category
Sr No. Drawing No

Description

Rev No

Category

L&T DTN No.

DTN Date

DT0136

23-Apr-10

LTSL-M0-00310

Calculation for Closed Cooling


Water System Pipe Sizing

LTSL-E0-00301

24 V DC Battery & Battery Charger


Sizing calculation

DT0128

23-Apr-10

LTSL-M1-00700

List - Equipment

DT0206

23-Jul-10

LTSL-I1-00700

List - Instrument

DT0208

23-Jul-10

LTSL-M0-00313

Calculation for Service Water


Distribution System Pipe Sizing

DT0232

13-Aug-10

LTSL-M1-00704

Interface/terminal point list

DT0236

23-Apr-10

LTSL-M0-00303

Calculation for Extraction Steam


System Pipe Sizing

DT0219

11-Aug-10

LTSL-M0-00335

Calculation for Closed Cooling


Water Pump Sizing

DT0219

11-Aug-10

LT-M0-03059

Complete Mechanical Design


Calculation for HPH-8A/8B

DT0180

14-Jul-10

10

LT-M0-03063

Complete Mechanical Design


Calculation for HPH-7A/7B

DT0180

14-Jul-10

11

LT-M0-03067

Complete Mechanical Design


Calculation for HPH-6A/6B

DT0181

14-Jul-10

12

LT-M0-03072

Complete Mechanical Design


Calculation for LP4

DT0181

14-Jul-10

13

LT-M0-03076

Complete Mechanical Design


Calculation for LP3

DT0179

14-Jul-10

14

LT-M0-03081

Complete Mechanical Design


Calculation for Duple Heater

DT0179

14-Jul-10

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara.

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR &
AUXILIARIES

JOB NO: - T209001

Document No:- LT-P000003


Progress Report No: - 11
Annexure No: Page No:- 29 of 103

2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
15

LT-M0-03003

Loading Data for Condenser

DT0143

4-Jan-10

16

LT-M0-03016

Procedure for Surface preparation


& Painting

DT-0237

20-Aug-10

17

LT-M0-03018

Hydrostatic Test Procedure

DT-0237

20-Aug-10

18

LT-M0-03022

Post Weld Heat Treatment


Procedure

DT-0237

20-Aug-10

19

LT-M0-03015

WPS & PQR

DT-0237

20-Aug-10

20

LMTG-P0-01025

Steam Purity Recommendation

DT0090

22-Feb-10

21

LMTG-M0-01016

Valve List

DT0121

16-Apr-10

22

LMTG-E0-02316

Turbine Generator CT Terminal


Box & Coduits Arrengement

DT0201

20-Jul-10

23

LMTG-E0-02338

Turbine Generator Exhaust Piping


(1 / 2)

DT0201

20-Jul-10

24

LMTG-E0-02339

Turbine Generator Exhaust Piping


(2 / 2)

DT0201

20-Jul-10

25

LMTG-E0-02340

Turbine Generator Cooling Water


Piping (1 / 5)

DT0201

20-Jul-10

26

LMTG-E0-02341

Turbine Generator Cooling Water


Piping (2 / 5)

DT0201

20-Jul-10

27

LMTG-E0-02342

Turbine Generator Cooling Water


Piping (3 / 5)

DT0201

20-Jul-10

28

LMTG-E0-02343

Turbine Generator Cooling Water


Piping (4 / 5)

DT0201

20-Jul-10

29

LMTG-E0-02344

Turbine Generator Cooling Water


Piping (5 / 5)

DT0201

20-Jul-10

30

LMTG-E0-02345

Turbine Generator Gas & Seal Oil


Piping (1 / 10)

DT0201

20-Jul-10

LMTG-E0-02346

Turbine Generator Gas & Seal Oil


Piping (2 / 10)

DT0201

20-Jul-10

32

LMTG-E0-02347

Turbine Generator Gas & Seal Oil


Piping (3 / 10)

DT0201

20-Jul-10

33

LMTG-E0-02348

Turbine Generator Gas & Seal Oil


Piping (4 / 10)

DT0201

20-Jul-10

34

LMTG-E0-02349

Turbine Generator Gas & Seal Oil


Piping (5 / 10)

DT0201

20-Jul-10

35

LMTG-E0-02350

Turbine Generator Gas & Seal Oil


Piping (6 / 10)

DT0201

20-Jul-10

36

LMTG-E0-02351

Turbine Generator Gas & Seal Oil


Piping (7 / 10)

DT0201

20-Jul-10

37

LMTG-E0-02352

Turbine Generator Gas & Seal Oil


Piping (8 / 10)

DT0201

20-Jul-10

38

LMTG-E0-02353

Turbine Generator Gas & Seal Oil


Piping (9 / 10)

DT0201

20-Jul-10

39

LMTG-E0-02354

Turbine Generator Gas & Seal Oil


Piping (10 / 10)

DT0201

20-Jul-10

40

LMTG-E0-02355

Turbine Generator Gas Feed


Piping (1 / 2)

DT0201

20-Jul-10

41

LMTG-E0-02356

Turbine Generator Gas Feed


Piping (2 / 2)

DT0201

20-Jul-10

42

LMTG-P0-01026

Performance Curves of STG

DT0195

19-Jul-10

43

LMTG-E0-02004

Utility List

DT0154

1-Jun-10

44

LMTG-E0-02012

Painting Procedure (MELCO


PORTION)

DT0159

8-Jun-10

45

LMTG-E0-02327

Turbine Generator Foundation Bolt


Arrengement

DT0096

16-Mar-10

46

LMTG-M0-01022

Plan for Arrangement of Foundation


Bolt

DT0166

21-Jun-10

31

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara.

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR &
AUXILIARIES

JOB NO: - T209001

Document No:- LT-P000003


Progress Report No: - 11
Annexure No: Page No:- 30 of 103

2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
47

LMTG-M0-01023

Plan for Arrangement of Anchor


Bolt

DT0166

21-Jun-10

48

LMTG-M0-01019

Turbine Generator Outline

DT0167

24-Jun-10

49

LMTG-M0-01008

TG foundation design criteria

DT0167

24-Jun-10

50

LMTG-P0-01036

System description for steam


turbine

DT0171

2-Jul-10

51

LMTG-I0-01308

Instrument List For Steam Turbine

DT0213

30-Jul-10

52

LMTG-M0-01210

Embedded Metal Plan Around


Storage Tank

R0

DT0215

2-Aug-10

53

LMTG-M0-01209

Foundation Of Lube Oil Storage


Tank

R0

DT0215

2-Aug-10

54

LMTG-M0-01206

Details Of Embedded Materials

DT0215

2-Aug-10

55

LMTG-M0-01201

Oil Piping And Equipment


Arrangement

DT0217

7-Aug-10

56

LMTG-M0-01202

Foundation Of Lubricating Oil


Equipment

R2

DT0217

7-Aug-10

57

LMTG-M0-01205

Foundation Embedded Material For


Piping

DT0217

7-Aug-10

58

LMTG-M0-01207

R2

DT0217

7-Aug-10

59

LMTG-E0-02326

DT0124

20-Apr-10

60

LMTG-E0-02038

DT0177

13-Jul-10

61

LMTG-E0-02039

DT0177

13-Jul-10

62

LMTG-E0-02040

DT0177

13-Jul-10

63

LMTG-E0-02357

DT0201

20-Jul-10

64

LMTG-E0-02332

DT0201

26-Jul-10

65

LMTG-E0-02302

DT0216

7-Aug-10

66

LMTG-Q0-02202

DT0218

9-Aug-10

67

LMTG-Q0-02203

DT0218

9-Aug-10

68

LMTG-E0-02309

DT0224

12-Aug-10

69

LMTG-E0-02310

DT0224

12-Aug-10

70

LMTG-E0-02312

Embedded Metal Plan Around Lube


Oil Purifier
Turbine Generator Foundation
Embedded Conduit Layout
Electrical Equipment General
Arrangment (El.+0.00M)
Electrical Equipment General
Arrangment (El.+9.00M)
Lectrical Equipment General
Arrangment (El.+17.00M)
Plan Of Scaffolding For Turbine
Generator Maintenance
Turbine Generator Hydrogen Gas
Temperature Control Valve Outline
Turbine Generator H2&Co2 Gas
Diagram
Shop Test And Inspection
Procedure For Control Panels
Shop Test And Inspection
Procedure For Control Panels
Turbine Generator Co2 Gas
Vaporizer Outline
Turbine Generator H2 Gas
Pressure/Purity Monitoring Unit
Outline
Turbine Generator Water Detector
Outline

DT0224

12-Aug-10

DT0231

17-Aug-10

71

AIL-M0-03231

Structural calculations for 115/15 T


TG Hall crane

72

AIL-M0-03253

Mechanism Sizing Calculation for


40/10 T BFP Bay EOT cranes

DT0228

13-Aug-10

73

AIL-M0-03256

Gantry Rail installation for 40/10 T


BFP Bay EOT cranes

DT0241

23-Aug-10

74

AIL-M0-03258

40T main hook block assembly

DT0241

23-Aug-10

75

AIL-M0-03259

10 T Aux Hook Block Assembly

DT0241

23-Aug-10

76

AIL-M0-03260

LT Drive wheel assembly

DT0241

23-Aug-10

77

AIL-M0-03261

LT idle wheel assembly

DT0241

23-Aug-10

78

AIL-M0-03262

CT Drive wheel assembly

DT0241

23-Aug-10

79

AIL-M0-03263

CT idle wheel assembly

DT0241

23-Aug-10

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara.

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR &
AUXILIARIES

JOB NO: - T209001

Document No:- LT-P000003


Progress Report No: - 11
Annexure No: Page No:- 31 of 103

2.1.6 List of Documents On Which Comments Awaited From Client For More Than 30 Days
80

AIL-M0-03264

Long travel Machinery Assembly


for 40/10 T TGHall EOT crane

DT0241

23-Aug-10

81

AIL-M0-03280

Crane lubrication

DT0241

23-Aug-10

82

FPD-C0-03305

Complete Grout General


Arrangement

235

23-Aug-10

83

FMD-M0-03372

Complete Grout General


Arrangement

235

23-Aug-10

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 32 of 103

2.2 Procurement Status:


2.2.1 Procurement Progress Statistics:
Procurement (100%)
During The Month (%)

Cumulative Till Sep 10 (%)

Early Sch (%)

Late Sch. (%)

Actual (%)

Early Sch (%)

Late Sch. (%)

Actual (%)

3.6

3.4

2.6

27.7

26.3

24.7

2.2.2 Procurement Progress for the Month:

Order Finalized for CPU on M/s Siemens,India


Enquires Floated for the following items
a) Erection Services
b) LP Valves

Offers Received for the following items:


a) Butterfly Valve

Bid Evaluation of the following items are in progress


a)
b)
c)
d)
e)

Elevators
OLTCS
VMS
DCS
HP Valve

Bid Evaluation completed for Vacuum Pump

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 33 of 103

2.2.3 Vendor Progress for Major Packages (Up to Sep 2010)

Sl
No

1)

2)

Ordering Status
Equipment

Vendor

Unit-1

Deaerator

Condenser

L&T HED

L&T HED

Carbon
Steel Plates
Spray
Nozzles
Nozzle
Flanges
Carbon
Steel Plates

3)

4)

LP-Heaters
Duplex,LP 3&4

L&T HED

L&T HED

Unit-2

Unit-1

Unit-2

Ordered

In Progress

Ordered

In Progress

Enquiries Sent
Ordered

Received

SS Plates

Ordered

In Progress

Tube Sheets

Ordered

Received

Tubes

Enquiries Sent

Nozzle
Flanges
Carbon
Steel Plates
HP-Heaters
HPH-6,HPH-7&
HPH-8

Receiving Status

Manufacturing

Items

Enquiries Sent
Under Finalization

SS Plates

Under Finalization

Tube Sheets

Ordered

Tubes

Under Finalization

Nozzle
Flanges
Carbon
Steel Plates
SS Plates

Under Finalization
Under Finalization
Under Finalization

In Progress

Unit-1

Unit-2

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 34 of 103

Sl
No

4)

5)

6)

Ordering Status
Equipment

Vendor

Unit-1

LP-Heaters
Duplex,LP 3&4

Turbine

Generators

L&T HED

LMTG

LMTG

Receiving Status

Manufacturing

Items
Unit-2

Tube Sheets

Ordered

Tubes

Under Finalization

Nozzle
Flanges
HIP & LP
Rotor
Forging
HIP Outer
Casing
Casting
Stationary
and ordinary
blade
material
LP inner
casing
Rotor
Forging
Retaining
Ring
Material
Through Bolt
Material &
Core Bolt
Material
Steel Plate
for
Generator
Stator

Unit-1

Unit-2

Unit-1

Unit-2

In Progress

Under Finalization
Ordered

Received

Ordered

Received

Ordered

Received

Ordered

In Progress

Ordered

In Progress

Ordered

In Progress

Ordered

In Progress

Ordered

In Progress

-> LP-1,LP-2 &HP


Rotor machining in
progress
->Stationary &
Rotating Blades
machining in
progress
->HIP casing
machining started

->Generator Stator
manufacturing in
progress
->Generator Rotor
machining in
progress

->LP-1 ,LP-2 &HP


Rotor machining in
progress
->Stationary &
Rotating blades
machining in
progress

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 35 of 103

Sl
No

7)

8)

Ordering Status
Equipment

Vendor

Unit-1

EOT Crane for


TG Hall Bay

EOT Crane for


BFP

AIL

AIL

Receiving Status

Manufacturing

Items
Unit-2

Unit-1

Unit-2

Motor

Ordered

Brake

Ordered

In Progress

Forgings

Ordered

In Progress

Bearing

Ordered

In Progress

Wire Rope

Ordered

In Progress

Spring
Buffer

Ordered

In Progress

Hook

Ordered

In Progress

Rope Drum
Pipe

Ordered

In Progress

Motor

Ordered

In Progress

Brake

Ordered

In Progress

Forgings

Ordered

In Progress

Bearing

Ordered

In Progress

Wire Rope

Ordered

In Progress

Hook

Ordered

In Progress

Rope Drum
Pipe

Ordered

In Progress

Unit-1

Unit-2

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 36 of 103

Sl
No

9)

10)

11)

Ordering Status
Equipment

Vendor

Unit-1

MDBFP

TDBFP

CEP

Flowserve

Flowserve

KSB

Receiving Status

Manufacturing

Items
Unit-2

Unit-1

Unit-2

Motor

Ordered

In Progress

Booster
Pump

Ordered

In Progress

Hydraulic
Coupling

Ordered

In Progress

Shaft
Material
Mechanical
Seal
Booster
Pump

Ordered

In Progress

Ordered

In Progress

Ordered

In Progress

Gear Box

Ordered

In Progress

Ordered

In Progress

Ordered

In Progress

Ordered

In Progress

Shaft
Material
Mechanical
Seal
Motor

Unit-1

Unit-2

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 37 of 103

2.4 Major Milestone Status :2.4.1 L&TS Plan Unit # 1


Sr
No
1

MILESTONE
DESCRIPTION
Opening of site office &
mobilization (For unit 1 & 2)

MONTH

SCHEDULED
DATE

15

22-Oct-10

Supply of embedded parts for TG

17

22-Dec-10

Start of EOT crane erection

22

23-May-11

Receipt of MDBFP at site

26

22-Sept-11

Commencement of insitu
Condenser Erection

26

23-Sep-11

Receipt of Deaerator at Site

27

22-Oct-11

Receipt of LP turbine at Site

29

22-Dec-11

Commencement of TG Erection

29

23-Dec-11

Receipt of Generator at Site

32

22-Mar-12

10

Readiness of TG/C&I system

38

22-Sep-12

11

Commissioning MDBFP

39

22-Oct-12

12

TG Boxing-up

39

22-Oct-12

13

TG oil Flushing Completion

39

22-Oct-12

14

Steam blowing completion

41

22-Dec-12

15

Completion of Governing System

41

22-Dec-12

16

TG on Barring Gear

41

22-Dec-12

43

16-Feb-13

43

22-Feb-13

45

22-Apr-13

17
18
19

TG Rolling & Synchronization


( On Oil )
TG Rolling & Synchronization
( On Coal )
Completion of Trial Operation of
Unit

EXPECTED
DATE

ACTUAL
DATE

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 38 of 103

2.4.2 L&TS Plan Unit # 2

Sr
No

MILESTONE
DESCRIPTION

MONTH

SCHEDULED
DATE

Supply of embedded parts for TG

23

22-Jun-11

Start of EOT crane erection

28

23-Nov-11

Receipt of MDBFP at site

32

22-Mar-12

Commencement of insitu
Condenser Erection

32

23-Mar-12

Receipt of Deaerator at Site

33

22-Apr-12

Receipt of LP turbine at Site

35

22-Jun-12

Commencement of TG Erection

35

23-Jun-12

Receipt of Generator at Site

38

22-Sep-12

Readiness of TG/C&I system

44

22-Mar-13

10

Commissioning MDBFP

45

22-Apr-13

11

TG Boxing-up

45

22-Apr-13

12

TG oil Flushing Completion

45

22-Apr-13

13

Steam blowing completion

47

22-Jun-13

14

Completion of Governing System

47

22-Jun-13

15

TG on Barring Gear

47

22-Jun-13

49

16-Aug-13

49

22-Aug-13

51

22-Oct-13

16
17
18

TG Rolling & Synchronization


( On Oil )
TG Rolling & Synchronization
( On Coal )
Completion of Trial Operation of
Unit

EXPECTED
DATE

ACTUAL
DATE

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 39 of 103

2.4.3 Clients Obligation - Construction Phase

Sr
No.

Customer Input

Unit # 1
Month

Sch

14

Unit # 2
Actual

Month

Sch

22-Sep-10

14

22-Sep-10

16

22-Nov-10

22

22-May-11

Availability of leveled & graded


land, water & electricity for site
infrastructure (Office, Stores,
Workshop & Colony)
Readiness of site access road
for transportation of heavy eqpt

Service bay readiness for EOT


crane erection

22

21-May-11

28

21-Nov-11

Readiness of foundation/floor
@ 9 mtrs

25

22-Aug-11

31

22-Feb-12

26

22-Sep-11

32

22- Mar-12

26

22-Sep-11

32

22-Mar-12

26

22-Sep-11

32

22-Mar-12

28

22-Nov-11

34

22-May-12

28

22-Nov-11

34

22-May-12

30

21-Jan-12

36

22-July-12

5
6
7
8

Clearance for insitu condenser


erection
Turbine building readiness for
STG erection
Readiness of 0 mtr foundations
(BFPs, CPU ,PHE, etc)
Readiness of foundation/floor
@ 17 mtrs

10

Readiness of strand jack


foundation for generator lifting
Readiness of floor @ 31 mtrs
( Deaerator foundation)

11

Main & Service building


readiness for Elevator erection

32

22- Mar-12

38

22-Sep-12

12

Readiness of electrical &


instrumentation earth grids

32

22- Mar-12

38

22-Sep-12

13

Readiness of AC/DC/UPS
panel & Battery bank floor

32

22- Mar-12

38

22-Sep-12

33

21-Apr-12

39

21-Oct-12

14

Readiness of Control room for


DCS & Marshalling panel
erection

Actual

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 40 of 103

2.4.4 Clients Obligation Commissioning Phase

Sr
No.

Customer Input

Unit # 1
Month

Sch

Unit # 2
Actual

Month

Sch

Readiness of 415V supply for


EOT & Elevator

25

22-Aug-11

31

22-Feb-12

Availability of DM water

34

22-May-12

40

22-Nov-12

34

22-May-12

40

21-Nov-12

36

21-July-12

42

21-Jan-13

36

21-July-12

42

21-Jan-13

36

21-July-12

42

21-Jan-13

3
4
5
6

Availability of trained O&M


manpower for commissioning
etc.
Readiness of HVAC system for
DCS commissioning
Readiness of 415V,3.3
kV,11kV & emergency power
supply
Readiness of 220V & 24 DC
power supply

Readiness of fire protection,


detection, & alarm system

36

21-July-12

42

21-Jan-13

Availability instru & service air

36

21-July-12

42

21-Jan-13

Availability of auxiliary cooling


water

36

21-July-12

42

21-Jan-13

10

Availability of condenser
cooling water

38

22-Sept-12

44

22-Mar-13

11

Readiness of GT , UAT, GCB


& switchyards

41

22-Dec-12

47

22-Jun-13

Actual

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 41 of 103

SECTION-3
ACTIVITIES PLANNED FOR NEXT MONTH

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 42 of 103

3.1 Engineering Plan


Sl. No.

Document No.

Description

LTSL Drawings/Documents
1.0

Calculations
1)

LTSL-E0-00300

LV Cable Sizing Calculation

LMTG Drawings/Documents
1.0

Turbine
Cable Schedule
1)

T3101MGP101

Gland Steam and Steam Drain Piping Arrangement

2)

61000-1010

Turbine Auxiliary Machine Control - Logic Diagram

3)

61000-1011

Control Loop & Control Logic Diagram

4)

61000-1021

Turbine Supervisory Instrument Diagram

5)

61000-1031

Turbine Interlock Diagram

6)

61000-3022

SOE List for TPS

7)

61140-1001

Steam Turbine Governor Control Diagram

8)

92250-0681

Specification of Terminal Box

9)

92250-8121

Layout of Terminal Box

10)

LMTG-P0-01025

Steam Purity Recommendation

11)

T3101ADAC850

Painting Schedule

12)

T3101AAAA410

Dimensions & Weight of Turbine Major Part

13)

92250-8401

Arrangement of Embedded Conduit (Turbine Internal)

14)

61000-3001

Instrument List for Steam Turbine

15)

61140-3016-1,
61140-3016-2

TCS/TPS I/O List

16)

92250-1601

Cable Connection Diagram of Terminal Box

17)

92250-4111

Earthing Requirement

2.0

Generator
1)

LMTG-E0-02008

Instrument List

2)

LMTG-E0-02360

Generator Design Datasheet

3)

LMTG-E0-02015

Signal interface list with DCS

4)

LMTG-E0-02103

External terminal of AVR Cubicle

5)

LMTG-E0-02359

Erection Procedure for Reference Plant (Generator & its Auxiliaries)

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 43 of 103

EOT Drawings/Documents
1.0

TG Hall EOT Crane


1)

AIL-M0-03201

Data sheet of 115/15 T TG Hall EOT Crane (Double Girder)

2)

AIL-M0-03203

Mechanism Sizing Calculation for 115/15 T TG Hall EOT cranes

3)

AIL-M0-03215

Electrical equipment layout in cabin for 115/15 T TG Hall EOT crane

4)

AIL-M0-03206

Gantry Rail installation for 115/15 T TG Hall EOT cranes

5)

AIL-M0-03207

6)

AIL-M0-03208

115T main hook block assembly

7)

AIL-M0-03209

15 T Aux Hook Block Assembly

8)

AIL-M0-03214

Long travel Machinery Assembly for 115/15 T TG Hall EOT crane

9)

AIL-M0-03231

Structural calculations for 115/15 T TG Hall crane

10)

AIL-M0-03233

Painting procedure

11)

AIL-M0-03230

Crane lubrication

12)

AIL-M0-03210

LT Drive wheel assembly

13)

AIL-M0-03211

LT idle wheel assembly

14)

AIL-M0-03212

CT Drive wheel assembly

15)

AIL-M0-03213

CT idle wheel assembly

2.0

General arrangement for PVC shrouded conductor type DSL for 115/15T TG
Hall EOT crane

BFP EOT Crane


1)

AIL-M0-03284

Make of Bought Out Item List

2)

AIL-M0-03253

Mechanism Sizing Calculation for 40/10 T TG Hall EOT cranes

3)

AIL-M0-03251

Data sheet of 40/10 T TG Hall EOT Crane (Double Girder)

4)

AIL-M0-03254

General arrangement for 40/10 T TG Hall EOT crane

5)

AIL-M0-03255

Crab sub assembly for 40/10T TG Hall EOT crane

6)

AIL-M0-03256

Gantry Rail installation for 40/10 T TG Hall EOT cranes

7)

AIL-M0-03257

8)

AIL-M0-03258

115T main hook block assembly

9)

AIL-M0-03259

15 T Aux Hook Block Assembly

10)

AIL-M0-03264

Long travel Machinery Assembly for 40/10 T TG Hall EOT crane

11)

AIL-M0-03283

Painting procedure

12)

AIL-M0-03260

LT Drive wheel assembly

General arrangement for PVC shrouded conductor type DSL for 40/10T TG Hall
EOT crane

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 44 of 103

13)

AIL-M0-03261

LT idle wheel assembly

14)

AIL-M0-03262

CT Drive wheel assembly

15)

AIL-M0-03263

CT idle wheel assembly

16)

AIL-M0-03280

Crane lubrication

17)

AIL-M0-03281

Structural calculations for 40/10 T TG Hall crane

BFP Drawings /Documents


1.0

MDBFP
1)

FPD-M0-03311

Complete Group Pump Performance

2)

FPD-Q0-03332

Performance test procedure for Booster Pump

3)

FPD-M0-03466

Motor Sizing Calculation

2.0

TDBFP
1)

FMD-M0-03311

Complete Group Pump Performance

2)

FQD-Q0-03332

Performance test procedure for Booster Pump

3.2 Procurement Plan

Enquires shall be floated for the following items


a) Control Valves

Offers shall be received for the following items:


a) LP Valves
b) Erection Services

Orders shall be placed for the following items :


a) Vacuum Pump
b) HP Valves

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 45 of 103

SECTION-4
ANNEXURES

LARSEN & TOUBRO LIMITED


Power Project Management
Services, Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 46 of 103

4.1 DOCUMENT CONTROL INDEX

LARSEN&TOUBROLIMITED
POWERPROJECTMANEGEMENT
SERVICES,VADODARA

JOBNO:T209001

JAYPEENIGRIE
SUPERTHERMALPOWERPROJECT
2X660MWSTEAMTURBINEGENERATOR&AUXILIARIES

DOCUMENTNO.:LTP000003
PROGRESSREPORTNO.:11
PAGES:12

DISTRIBUTION OF WTG. POINTS WITHIN ENGINEERING STATUS ANNEXURES BASED ON WBS STRUCTURE

ENGINEERING (100%)
% of Overall Project = 10%
Total Weightage Points (Per Unit Basis) = 100000

BASIC ENGINEERING
% of Overall Project =
Total Weightage Points (Per Unit Basis) =

35%

3.50%
35000

% OF WEIGHTAGE

WTG POINTS

ANNEXURE NO.

DESIGN CRITERIA DOCUMENTS

20%

7000

ANNEXURE - 4.1

CALCULATIONS

10%

3500

ANNEXURE - 4.1

P&IDS

30%

10500

ANNEXURE - 4.1

PROCUREMENT ASSISTANCE

40%

14000

ANNEXURE - 4.1

DESCRIPTION

DETAIL ENGINEERING
% of Overall Project =
Total Weightage Points (Per Unit Basis) =

65%

6.50%
65000

% OF WEIGHTAGE

WTG POINTS

ANNEXURE NO.

TG BUILDING GA & PIPING COMPOSITE DRGs

20%

13000

ANNEXURE - 4.1

VENDOR DRAWING & DOCUMENTS REVIEW

20%

13000

ANNEXURE - 4.2

PIPING STRESS ANALYSIS, ISOMETRICS & LIST

30%

19500

ANNEXURE - 4.1

PIPE SUPPORT DRAWINGS

15%

9750

ANNEXURE - 4.1

O&M MANUALS & PG TEST PROCEDURE

3%

1625

ANNEXURE - 4.1

ELECTRICAL DOCUMENTS

3%

1625

ANNEXURE - 4.1

C&I DOCUMENTS

10%

6500

ANNEXURE - 4.1

DESCRIPTION

TOTAL POINTS =

100000

LARSEN & TOUBRO LIMITED

DOCUMENT NO.
ANNEXURE REV. NO:

POWER PROJECT MANAGEMENT SERVICES , VADODARA

JNSTPP

L&T

L&T

JNSTPP

JNSTPP

L&T

Release
Date
DTN No.

Receive
Date
I/W No.

Recd aftr
Long Time

FLAG
4th Submission (Rev. D)

Last Wk
Recd
To Rcvd
Next Wk

Receive
Date
I/W No.

Subm.
Next Wk
Last Wk
Submited

Release
Date
DTN No.

FLAG
Recd aftr
Long Time

3rd Submission (Rev. C)

Last Wk
Recd
To Rcvd
Next Wk

Receive
Date
I/W No.

Subm.
Next Wk
Last Wk
Submited

Release
Date
DTN No.

FLAG

FLAG
Recd aftr
Long Time

FLAG
2nd Submission (Rev. B)`

Last Wk
Recd
To Rcvd
Next Wk

Receive
Date
I/W No.

Subm.
Next Wk
Last Wk
Submited

Release
Date
DTN No.

FLAG
Recd aftr
Long Time

L&T

1st Submission (Rev. A)

Last Wk
Recd
To Rcvd
Next Wk

Drawing / Doc. No.

FLAG

FLAG
Subm.
Next Wk
Last Wk
Submited

Description

Category (A/I)

Sr. No.

Schedule
First
Submission
Date

Latest Approval
Status from
Client

Unit No.

JOB No. T209001

:LT-P0-00003
:4.1
:A

JNSTPP

5th Submission (Rev. E)

Release
Date
DTN No.

Receipt Date
of Approval

Receive
Date
I/W No.

TRANSMITTAL WITH CUSTOMER

DCD - Electrical System

LTSL-E0-00100

16-Dec-09

A2

1.2.4

DCD - C&I System

LTSL-I0-00100

22-Dec-09

A2

C
C

1.2.5
1.2.6

DCD - Condenser Air Removal System


DCD - Closed Cooling Water System

LTSL-M0-00108
LTSL-M0-00110

17-Nov-09
23-Nov-09

A
A

A2
A2

1.2.7

DCD - DM Waer Distribution System

LTSL-M0-00111

28-Nov-09

A2

1.2.8

DCD - Instrument Air / Service Air


Distribution System

LTSL-M0-00112

4-Dec-09

A2

1.2.9

2
2.1
C
C

2.1.1
2.1.2

DCD - Piping Stress Analysis

LTSL-M0-00115

10-Dec-09

Calculations

3500.0

10.00%

Power System

2625.0

75.00%

LTSL
LTSL-M0-00551
M0 00551

14
14-Jan-10
Jan 10

Calc - Turbine Building Piping Load Data


Calc - Feed Water Pump Sizing

LTSL-M0-00333

24-Oct-09

A2

A2

2.1.3

Calc - Feed water System Pipe Sizing

LTSL-M0-00302

24-Oct-09

2.1.4

Calc - Condensate Extraction Pump Sizing

LTSL-M0-00332

30-Oct-09

A2

2.1.5

Calc - Condensate System Pipe Sizing

LTSL-M0-00301

30-Oct-09

2.1.6

Calc - Heaters, Vents, Drain, System Pipe


Sizing

LTSL-M0-00304

16-Dec-09

2.1.7

Calc - Extraction Steam System Pipe Sizing

LTSL-M0-00303

10-Dec-09

2.1.8

Calc - LP Bypass Steam System Pipe Sizing

LTSL-M0-00305

2-Jan-10

2.1.9

Calc - Driver Rating Calculation

LTSL-M0-00340

11-Nov-09

2.1.10

Calc - Auxiliary Steam System Pipe Sizing

LTSL-M0-00307

28-Dec-09

2.1.11

Calc - Turbine Building Equipment Weight


Data

LTSL-M0-00550

14-Jan-10

875.0

25.00%

LTSL-M0-00308

10-Dec-09

2.2
C

2.2.1

BOP System
Calc - Condenser Air Removal System
Sizing

2.2.2

Calc - Circulating Water System Pipe Sizing

LTSL-M0-00309

20-Jan-10

2.2.3

Calc -Closed Cooling Water Pump Sizing

LTSL-M0-00335

16-Dec-09

2.2.4

225
2.2.5

2.2.6

2.2.7

2.2.8

2.2.9

3
3.1
1
1
1

3.1.1
3.1.2
3.1.3

Calc -Closed Cooling Water System pipe


Sizing
Calc - DM Water Distribution System pipe
Sizing
Calc - Service Water Distribution System
pipe Sizing
Calc - Instrument Air / Service Air
Distribution System Pipe
Calc - 24 V DC Battery & Battery Charger
Sizing

LTSL-M0-00310

16-Dec-09

LTSL-M0-00311
LTSL M0 00311

22 D 09
22-Dec-09

LTSL-M0-00313

4-Dec-09

LTSL-M0-00312

28-Dec-09

LTSL-E0-00301

8-Mar-10

LTSL-E0-00300

5-May-10

P&IDs

10500.0

30.00%

Up to Release for Construction

10237.5

97.50%

LTSL-M0-00200

1-Oct-09

Calc - LV Cable

P&ID - Index, Legends & Symbols


P&ID - Feed Water System
P&ID - Condensate System

LTSL-M1-00202
LTSL-M1-00201

10-Dec-09
23-Nov-09

I
A
A

3
A2
A2

3.1.4

P&ID - Heaters, Vents, & Drains System

LTSL-M1-00204

8-Jan-10

A2

3.1.5

P&ID - Closed Cooling Water System

LTSL-M1-00210

16-Dec-09

3.1.6

P&ID - Extraction Steam System

3.1.7

P&ID - Circulating Water System

LTSL-M1-00209

28-Dec-09

3.1.8

P&IDs - Condenser Air Removal System

LTSL-M1-00208

10-Dec-09

A2

3.1.9
3
19

Service
Water
Distribution
System
P&ID - S
i W
t Di
t ib ti S
t

LTSL
M1 00213
LTSL-M1-00213

4-Dec-09
4
D 09

3.1.10

P&ID - LP Bypass Tseam System

LTSL-M1-00203

LTSL-M1-00205

2-Jan-10

2-Jan-10

A2

A2

3.1.11

P&IDs - Auxiliary Steam System

LTSL-M1-00207

28-Dec-09

A2

3.1.12

P&ID - Instrumnent Air / Service Air


Distribution System

LTSL-M1-00212

22-Dec-09

3.1.13

P&ID - DM Water Distribution System

LTSL-M1-00211

22-Dec-09

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

28-Dec-09
11-Jan-10
3-Jan-10
11-Jan-10
9-Jan-10
9-Feb-10

DCPl 0031
DCPL 0028
DCPL 0039

DCPLODT0051
DCPLODT0014
DCPLODT0014
DCPLODT0021
DCPLODT0025
DCPLODT0029
DCPLODT0022
DCPLODT0028
DCPLODT0079
DCPLODT0149
DCPLODT0085

13-Feb-10
15 Mar 10
15-Mar-10
23-Nov-09
8-Dec-09
23-Nov-09
11-Jan-10
29-Nov-09
24-Dec-09
29-Nov-09
11-Jan-10
15-Jan-10
12-Feb-10
9-Jan-10
15-Feb-10
1-Feb-10
15-Feb-10
11-Dec-09

DCPl 0070
DCPL 0010
DCPL 0033
DCPL 0012
DCPL 0032
DCPL 0045
DCPL 0047
DCPL 0047

27-Jan-10
17-Jul-10
13-Feb-10
15-Mar-10

DCPL 0147
DCPL 0070

10-Dec-09
18-Dec-09
20-Jan-10
18-Dec-09
16-Dec-09
23-Apr-10
16-Dec-09
23-Apr-10
22-Dec-09
25-Dec-09
4-Dec-09
10-Feb-10
28-Dec-09
25-Feb-10
8-Mar-10
23-Apr-10
5-May-10

DCPLODT0026
DCPLODT0026
DCPLODT0136
DCPLODT0136
DCPLODT0033
DCPLODT0082
DCPLODT0091
DCPLODT0128

9-Jan-10
24-Apr-10
19-Feb-10
3-Apr-10
15-Jan-10
26-Jul-10
15-Jan-10

DCPL 0094
DCPL 0079
DCPL 0153

21-Jan-10
3-May-10
3-Jan-10
3-May-10
27-Jan-10
24-Apr-10
7-Apr-10

DCPL 0103
DCPL 0104
DCPL 0097

1-Oct-09
1-Oct-09
10-Dec-09
31-Dec-09
23-Nov-09
31-Dec-09
8-Jan-10
19-Jan-10
16-Dec-09
10-Feb-10
2-Jan-10
18-Jan-10
28-Dec-09
10-Feb-10
10-Dec-09
16-Jan-10
4-Dec-09
4
Dec 09
10-Feb-10
2-Jan-10
19-Jan-10
28-Dec-09
18-Jan-10
22-Dec-09
10-Feb-10
22-Dec-09
10-Feb-10

JPVLODT0002
DCPLODT0041
DCPLODT0041
DCPLODT0059
DCPLODT0082
DCPLODT0049
DCPLODT0082
DCPLODT0048
DCPLODCPLO
DT0083
DCPLODT0054
DCPLODT0050
DCPLODT0082
DCPLODT0082

Nt Come

4-Jun-10

31-Oct-09
30-Nov-09
9-Jan-10
2-Mar-10
23-Dec-09
2-Mar-10
7-Feb-10
5-Mar-10
15-Jan-10
10-May-10
1-Feb-10
2-Mar-10
27-Jan-10
9-Jan-10
8-Mar-10
3-Jan-10
3
Jan 10
1-Feb-10
8-Mar-10
27-Jan-10
8-Mar-10
21-Jan-10
21-Jan-10
17-May-10

DCPL 0008
DCPL 0057
DCPL 0057
DCPL 0062
DCPL 0108
DCPL 0059
Nt Come
DCPl 0067
Come
Nt C
DCPL 0067
DCPL 0067
Nt Come
DCPL 0115

18-Mar-10
9-Apr-10
30-Jan-10

DCPLODT0117-0

17-Apr-10
23-Apr-10
1-Mar-10

DCPL 0092

11-Mar-10

10-Apr-10

6-Mar-10
9-Apr-10
12-Mar-10

DCPLODT0118-1

5-Apr-10
24-Apr-10
11-Apr-10

DCPL 0096

15-Apr-10

15-May-10

21-Apr-10

21-May-10

5-Feb-10
9-Apr-10
11-Feb-10
9-Apr-10
16-Feb-10
9-Apr-10
22-Feb-10
9-Apr-10
28-Feb-10
21-Apr-10

DCPLODT0117-0
DCPLODT0117-0
DCPLODT0117
DCPLODT0117-0
DCPLODT0125

7-Mar-10
23-Apr-10
13-Mar-10
23-Apr-10
18-Mar-10
23-Apr-10
24-Mar-10
23-Apr-10
30-Mar-10

DCPL 0092
DCPL 0092
DCPL 0092
DCPl 0092

17-Mar-10

DCPLODT0108
DCPLODT0184
DCPLODT0108
DCPLODT0200

11-Feb-10
23-Apr-10
11-Feb-10
30-Aug-10
17-Feb-10
23-Apr-10
17-Feb-10
30-Aug-10
5-Apr-10

DCPLODT0118
DCPLODT0080
DCPLODT0082
DCPLODT0082
DCPLODT0082
DCPLODT0087

23-Feb-10
3-Dec-09
31-Dec-09
3-Dec-09
26-Feb-10
9-Dec-09
31-Dec-09
9-Dec-09
25-Feb-10
25-Jan-10
16-Jul-10
19-Jan-10
11-Aug-10
11-Feb-10
20-Jul-10
21-Dec-09

DCPLODT0040
DCPLODT0092
DCPLODT0041
DCPLODT0091
DCPLODT0184
DCPLODT0219
DCPLODT0200

6-Feb-10

DCPLO0102
DCPL 0057
DCPl 0078
DCPL 0074
DCPl 0078
DCPL 0075

25-Mar-10

4-Apr-10

2-Jan-10

12-Jan-10
30-Mar-10
12-Jan-10
16-Jul-10
18-Jan-10
30-Mar-10
18-Jan-10
20-Jul-10
6-Mar-10

2-Jan-10
5-Apr-10
8-Jan-10
8-Jan-10
5-May-10
24-Feb-10
30-Aug-10
18-Feb-10

Nt Come
DCPL 0080
Nt Come
DCPL 0107
DCPL 0173

13-Mar-10

21-Feb-10
16-Apr-10
27-Feb-10

DCPLODT0120-1

23-Mar-10
1-Jun-10
29-Mar-10

DCPL 0093
DCPL 0173
DCPL 0093
DCPL 0173

12-Jun-10

6-Apr-10

23-Mar-10

22-Apr-10

13-May-10

12-Jun-10

6-Apr-10

28-Mar-10

27-Apr-10

13-May-10

12-Jun-10

6-Apr-10

3-Apr-10

3-May-10

13-May-10

12-Jun-10

DCPLODT0191

31-Jan-10
24-May-10
13-Jan-10
19-Jul-10
6-Feb-10

DCPLODT0149
DCPLODT0191

24-Feb-10

6-Mar-10

2-Mar-10

8-Mar-10

12-Mar-10
19-Jul-10
22-Feb-10
18-Aug-10
18-Mar-10

17-Apr-10

17-May-10

27-May-10

14-Jun-10

14-Jul-10

24-Jul-10

12-Feb-10

10-Dec-09

Nt Come

18-Feb-10
2-Mar-10
1-Feb-10
2-Mar-10
19-Mar-10
5-Mar-10
24-Feb-10

DCPL 0057
DCPL 0057
DCPL 0062

13-Mar-10
2-Mar-10
8-Mar-10
24-Apr-10
18-Feb-10
8-Mar-10
12-Feb-10
12
Feb 10
12-May-10
13-Mar-10
8-Mar-10
8-Mar-10
8-Mar-10
2-Mar-10
4-Jun-10
2-Mar-10

DCPL 0059
DCPL 0095
DCPL 0067
DCPL 0116
DCPL 0067
DCPL 0067
DCPL 0124

5-Apr-10
DCPLODT0191
DCPLODT0232

13-Jun-10
13-May-10

12-Jun-10

21-Feb-10

23-Mar-10

19-Sep-10

19-Oct-10

27-Feb-10

29-Mar-10

13-May-10

12-Jun-10

27-Feb-10

29-Mar-10

19-Sep-10

19-Oct-10

15-Apr-10

15-May-10

9-Apr-10

9-May-10

2-May-10

1-Jun-10

26-Sep-10

26-Oct-10

19-Sep-10

19-Oct-10

19-Sep-10

19-Oct-10

19-Sep-10

19-Oct-10

15-May-10

21-Apr-10

21-May-10
3-May-10

26-Jun-10

6-Jul-10

5-Aug-10

23-Aug-10

2-Sep-10

2-Oct-10

29-Jan-10

28-Feb-10

DCPLO9-Apr-10
24-May-10 DT0147
23-Mar-10 DCPLO24-May-10 DT0147
8-May-10
DCPLO24-May-10 DT0148-0
15-Apr-10 DCPLO11-Aug-10 DT0222
2-May-10
DCPLO24-Jun-10
DT0169
27-Apr-10 DCPLODT0253
7-Sep-10
9-Apr-10

9-May-10

11-Apr-10
DCPLODT0148

9-May-10

15-May-10

11-Apr-10
9-Jul-10

DCPl 0145

7-Jun-10
15-May-10
DCPL 0145

9-May-10

16-Jun-10
24-Jun-10
16-Jun-10
24-Jun-10
1-Jun-10

DCPLODT0169
DCPLODT0169

16-Jul-10
9-Jul-10
16-Jul-10
9-Jul-10
1-Jul-10

12-Aug-10

11-Sep-10

16-Jun-10

16-Jul-10

18-Jun-10
18-Jun-10
12-May-10

18-Jun-10

28-Aug-10

24-Apr-10

13-Jun-10

24-Apr-10
12-May-10
12
May 10

3-May-10
3
May 10

29-Jul-10
29
Jul 10

28-Aug-10
28
Aug 10

1-Jun-10

14-May-10

13-Jun-10

27-Apr-10

27-May-10
21-May-10
30-Aug-10
21-May-10

DCPL 0145
DCPL 0145

29-Jul-10

3-Apr-10
3
Apr 10

DCPLODT0222

15-Mar-10

14-May-10

2-May-10

21-Apr-10
11-Aug-10
21-Apr-10

23-Apr-10

30-Nov-09

22-Apr-10

1-Jun-10
9-Jul-10
27-May-10

23-Apr-10

15-Mar-10

19-Jun-10

15-Apr-10

15-Sep-10

Not Rqrd

9-Apr-10

15-Apr-10

6-Apr-10
DCPL 0181

15-Mar-10

20-May-10

27-May-10

DCPL 0120
DCPL 0120
DCPL 0116
DCPL 0151
DCPL 0120
DCPl 0145
DCPL 0095
DCPl 0145
DCPL 0095

15-Sep-10

23-Mar-10

3-Apr-10

30-Mar-10
27-May-10
13-Mar-10
27-May-10
28-Apr-10
12-May-10
5-Apr-10
23-Jul-10
22-Apr-10
27-May-10
17-Apr-10
9-Jul-10
30-Mar-10
24-Apr-10
24-Mar-10
24
Mar 10
9-Jul-10
22-Apr-10
24-Apr-10
17-Apr-10

12-Aug-10

DCPLODT0223

21-Feb-10

27-Apr-10

19-Jan-10
DCPLODT0128
DCPLODT0129
DCPLODT0128
DCPLODT0173
DCPLODT0125
DCPLODT0148-0
DCPLDT0123
DCPLODCPLO
DT0148-0
DCPLDT0123

12-Mar-10
12-Mar-10
24-May-10

DCPL 0173

17-Apr-10

20-Dec-09
28-Feb-10
23-Apr-10
11-Feb-10
23-Apr-10
29-Mar-10
23-Apr-10
6-Mar-10
3-Jul-10
23-Mar-10
21-Apr-10
18-Mar-10
24-May-10
28-Feb-10
17-Apr-10
22-Feb-10
22
Feb 10
24-May-10
23-Mar-10
17-Apr-10
18-Mar-10

11-Apr-10
30-Aug-10
24-Mar-10

30-Apr-10

14-May-10

13-Jun-10

DCPL 0173
DCPL 0173

6-Apr-10

9-May-10

14-May-10

30-Mar-10
30-Aug-10
10-May-10
30-Aug-10
5-Apr-10

6-Apr-10

13-May-10

4-May-10

DCPLODT0200
DCPLODT0191

2-Aug-10

16-Apr-10

4-Apr-10

28-Feb-10
20-Jul-10
10-Apr-10
19-Jul-10
6-Mar-10

6-Apr-10
DCPl 0158

6-Apr-10

10-Apr-10

DCPL 0134
DCPL 0134

31-Jul-10
2-Aug-10

13-Jun-10

27-May-10

18-Feb-10
18-Jun-10
31-Mar-10
18-Jun-10
24-Feb-10

12-Jun-10
DCPLODT0170

6-Apr-10
6-Apr-10

14-May-10

27-Apr-10

DCPLODT0149
DCPLODT0149
DCPLODT0219

DCPl 0173

6-Apr-10

11-Mar-10

19-Jan-10
24-May-10
1-Mar-10
24-May-10
25-Jan-10
11-Aug-10
25-Jan-10

1-Jul-10
1-Jul-10

3-Apr-10
30-Aug-10
21-Apr-10

12-Jun-10

17-Apr-10

25-Mar-10

DCPLODT0221

13-May-10
DCPL 0123

27-May-10

18-Mar-10

DCPL 0174

4-Mar-10
11-Aug-10
22-Mar-10

13-May-10

9-Apr-10
19-Jul-10

30-Mar-10

DCPL 0092

18-Mar-10

8-Mar-10
DCPLODT0163

DCPLODT0036-0
DCPLODT0081
DCPLODT0081
DCPLODT0081
DCPLODT0136
DCPLODT0081
DCPLODT0123
DCPLODT0081
DCPLODCPLO
DT0129
DCPLODT0081
DCPLODT0081
DCPLODT0125
DCPLODT0125

4-Apr-10
23-Apr-10
12-Mar-10

20-Jan-10

23-Feb-10
10-Jun-10

10-Nov-09
29-Dec-09
19-Jan-10
10-Feb-10
2-Jan-10
10-Feb-10
17-Feb-10
10-Feb-10
25-Jan-10
23-Apr-10
11-Feb-10
10-Feb-10
6-Feb-10
17-Apr-10
19-Jan-10
10-Feb-10
13-Jan-10
13
Jan 10
23-Apr-10
11-Feb-10
10-Feb-10
6-Feb-10
10-Feb-10
31-Jan-10
21-Apr-10
31-Jan-10
21-Apr-10

DCPLODT0080
DCPLODT0117

23-Mar-10
13-Aug-10
30-Jan-10

DCPLODT0230

22-Apr-10
6-Sep-10
1-Mar-10

5-Mar-10
10-Feb-10
10-Feb-10
9-Apr-10
16-Feb-10

27-Apr-10

4-May-10

28-Feb-10

6-Apr-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

Nt Come

DCPL 0074
DCPL 0078
DCPL 0064

6-Apr-10

12-Jun-10

14-Jan-10
18 Jan 10
18-Jan-10
24-Oct-09
18-Nov-09
24-Oct-09
18-Nov-09
30-Oct-09
9-Dec-09
30-Oct-09
17-Dec-09
16-Dec-09
21-Dec-09
10-Dec-09
9-Dec-09
2-Jan-10
19-Dec-09
11-Nov-09
10-Feb-10
28-Dec-09
24-May-10
14-Jan-10
12-Feb-10

DCPl 0022
DCPl 0031

8-Mar-10
29-Mar-10
20-Jan-10
3-Apr-10
24-Feb-10
8-Mar-10
2-Mar-10
30-Apr-10
26-Jan-10
2-Mar-10
1-Feb-10
3-Apr-10
6-Feb-10
29-Mar-10
12-Feb-10
3-Apr-10
18-Feb-10
31-Mar-10

Sch.
Act
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

DCPLODT0012
DCPLODT0018
DCPLODT0019
DCPLODT0018
DCPLODT0019
DCPLODT0028

DCPLODT0082
DCPLODT0117
DCPLODT0082-0

12-Jun-10

13-May-10

1.2.3

DCPL 0011

13-May-10

6-Mar-10

DCPLODT0011

28-Feb-10

4-Feb-10

29-Jan-10

6-Feb-10
10-Feb-10
21-Dec-09
9-Apr-10
25-Jan-10
10-Feb-10
31-Jan-10
9-Apr-10
27-Dec-09
10-Feb-10
2-Jan-10
10-Feb-10
7-Jan-10
10-Feb-10
13-Jan-10
10-Feb-10
19-Jan-10
19-Feb-10

11-Nov-09

DCPL 0031
DCPL 0078

LTSL-M0-00113

27-Jan-10
11-Jan-10
11-Dec-09
3-Apr-10
15-Jan-10
9-Dec-09
21-Jan-10
5-Jan-10
17-Dec-09
11-Jan-10
23-Dec-09

DCD - Service Water Distribution System

DCPLODT0018
DCPLODT0082

1.2.2

28-Dec-09
27-Nov-09
11-Nov-09
10-Feb-10
16-Dec-09
7-Nov-09
22-Dec-09
16-Nov-09
17-Nov-09
27-Nov-09
23-Nov-09
30-Nov-09
28-Nov-09
27-Nov-09
4-Dec-09
30-Nov-09
10-Dec-09
19-Dec-09

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

17-Feb-10

28-Dec-09

DCPL 0092
DCPL 0092
DCPL 0049
DCPL 0057
DCPL 0092

LTSL-M0-00109

19-Jan-10
23-Apr-10
25-Jan-10
23-Apr-10
23-Feb-10
12-Feb-10
31-Jan-10
2-Mar-10
6-Feb-10
23-Apr-10
11-Feb-10

DCD - Circulating Water System

1.2.1

25.00%

BOP System

1750.0

1.2

A2

A2

30-Oct-09

24-Oct-09

LTSL-M0-00107

LTSL-M0-00106

DCD - Auxiliary Steam System

DCD - Condensate Polishing System

1.1.7

1.1.6

DCPLODT0117
DCPLODT0117
DCPLODT0054
DCPLODT0080
DCPLODT0117
DCPLODT0117-0

20-Dec-09
9-Apr-10
26-Dec-09
9-Apr-10
24-Jan-10
19-Jan-10
1-Jan-10
10-Feb-10
7-Jan-10
9-Apr-10
12-Jan-10
9-Apr-10
18-Jan-10

A2

DCPL 0040
DCPl 0038
DCPL 0031
DCPL 0049
DCPL 0042
DCPL 0061
DCPL 0049

A2

10-Dec-09
9-Feb-10
16-Dec-09
6-Feb-10
14-Jan-10
11-Jan-10
22-Dec-09
17-Feb-10
28-Dec-09
12-Feb-10
2-Jan-10
5-Mar-10
8-Jan-10
12-Feb-10

19 O t 09
19-Oct-09

DCPLODT0059
DCPLODT0049
DCPLODT0026
DCPLODT0049
DCPLODT0059
DCPLODT0082
DCPLODT0050

13-Oct-09

LTSL
M0 00104
LTSL-M0-00104

10-Nov-09
19-Jan-10
16-Nov-09
18-Jan-10
15-Dec-09
18-Dec-09
22-Nov-09
18-Jan-10
28-Nov-09
19-Jan-10
3-Dec-09
10-Feb-10
9-Dec-09
18-Jan-10

LTSL-M0-00103

Vents,
DCD - Heaters,
H t
V t & Drains
D i System
S t

DCD - Extraction Steam System

1
15
1.1.5

1.1.4

A2

A2

5-Nov-09

7-Oct-09

LTSL-M0-00105

DCPL 0010
DCPL 0010
DCPL 0012
DCPL 0014
DCPL 0014
DCPL 0030
DCPL 0016

LTSL-M0-00101

DCD - LP Bypass Steam System

31-Oct-09
8-Dec-09
6-Nov-09
8-Dec-09
5-Dec-09
24-Dec-09
12-Nov-09
29-Dec-09
18-Nov-09
29-Dec-09
23-Nov-09
11-Jan-10
29-Nov-09
29-Dec-09

DCD - Condensate System

1.1.3

JPVLODT0004
DCPLODT0012
DCPLODT0018
DCPLODT0016
DCPLODT0016
DCPLODT0018
DCPLODT0020

1.1.2

1-Oct-09
21-Sep-09
7-Oct-09
16-Nov-09
5-Nov-09
27-Nov-09
13-Oct-09
20-Nov-09
19-Oct-09
20-Nov-09
24-Oct-09
27-Nov-09
30-Oct-09
5-Dec-09

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

75.00%
1-Oct-09

5250.0
LTSL-M0-00102

Power System
DCD - Feed Water System

35.00%
20.00%

1.1.1

35000.0
7000.0

Design Criteria Document

BASIC Engineering
1
1.1

24-Apr-10
Send to LMB

DCPl 0173

5-Aug-10
29-Jul-10

28-Aug-10

22-Jun-10
Page 02 of 12

LARSEN & TOUBRO LIMITED

DOCUMENT NO.
ANNEXURE REV. NO:

POWER PROJECT MANAGEMENT SERVICES , VADODARA

23-Jul-09

4.1.1.4

BFP (TD & MD)

LTSL-M0-00603-SP

24-Oct-09

4115
4.1.1.5

Condensate Extraction Pump

LTSL M0 00604 SP
LTSL-M0-00604-SP

4 Dec 09
4-Dec-09

4.1.1.6

EOT Crane

LTSL-M0-00624-SP

2-Jan-10

4.1.1.7

Steam Turbine Drive

LTSL-M0-00602-SP

28-Nov-09

4.1.1.8

Vacuum Pump

LTSL-M0-00605-SP

10-Dec-09

4.1.1.9

Condensate Polishing Unit

LTSL-M0-00610-SP

26-Jan-10

C 4.1.1.10 DMCW Pump

LTSL-M0-00608-SP

16-Dec-09

C 4.1.1.11 Piping & Valves Material

LTSL-M0-00712 - SP

17-Apr-10

C 4.1.1.12 Plate Heat Exchanger

LTSL-M0-00609-SP

16-Dec-09

C 4.1.1.13 Shop Fabricated Tanks - Steel

LTSL-M0-00612-SP

20-Jan-10

Power Cycle Valves - Gate, Globe,


C 4.1.1.14
Check(HP Valve)

LTSL-M0-00618-SP

29-Apr-10

C 4.1.1.15 Piping & Fittings

LTSL-M0-00628-SP

29-Apr-10

C 4.1.1.16 OLTC System & Debris Filter

LTSL-M0-00613-SP

28-Dec-09

C 4.1.1.17 Butterfly Valves

LTSL-M0-00620-SP

17-May-10

C 4.1.1.18 LP Bypass Valve

LTSL-M0-00614-SP

18-Feb-10

C 4.1.1.19 Piping Specialities

LTSL-M0-00617-SP

3-Jun-10

C 4.1.1.20 LP Valves - Gate, Globe, Check.

LTSL M0 00619 SP
LTSL-M0-00619-SP

21-Jun-10
21 Jun 10

C 4.1.1.21 Hp Heater Three Way Bypass Valve

LTSL-M0-00621-SP

3-Jun-10

C 4.1.1.22 Elevators

LTSL-M0-00626-SP

2-Jan-10

C 4.1.1.23 Chemical Feed System (DMCW)

LTSL-M0-00611-SP

C 4.1.1.24 Mechanical Shop Fabricated Piping

26-Jul-10

30-Aug-10

C 4.1.1.25 Expansion Joints (Metallic & Rubber)

LTSL-M0-00616-SP

26-Jul-10

C 4.1.1.27 Extraction Steam Check Valve

LTSL-M0-00622-SP

12-Aug-10

C 4.1.1.28 Safety & Relief Valve

LTSL-M0-00623-SP

30-Aug-10

C 4.1.1.30 Strainers

LTSL-M0-00615-SP

16-Sep-10

C 4.1.1.32 Misc. Chain Pully Block, Hoists HOT, etc.

LTSL-M0-00625-SP

13-Nov-10

4.1.2.1

Water Cooled Surface Condenser

LTSL-M0-00601-BR

24-Aug-09

4.1.2.2

Deaerator

LTSL-M0-00606-BR

24-Aug-09

4.1.2.3

Feed Water Heaters

LTSL-M0-00607-BR

24-Aug-09

4.1.2.4

BFP (TD & MD)

LTSL-M0-00603-BR

30-Jan-10

4.1.2.5

Steam Turbine Drive

LTSL-M0-00602-BR

24-Mar-10

4126
4.1.2.6

Condensate E
Extraction
traction P
Pump
mp

LTSL M0 00604 BR
LTSL-M0-00604-BR

5-Apr-10
5
Apr 10

4.1.2.7

EOT Crane

LTSL-M0-00624-BR

9-Apr-10

4.1.2.8

Vacuum Pump

LTSL-M0-00605-BR

27-May-10

4.1.2.9

Condensate Polishing Unit

LTSL-M0-00610-BR

14-Jun-10

JNSTPP

L&T

Release
Date
DTN No.

Receive
Date
I/W No.

JNSTPP

Release
Date
DTN No.

Receive
Date
I/W No.

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
A t
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

23-Jul-09
15-Oct-09
23-Jul-09
15-Oct-09
23-Jul-09
15-Oct-09
24-Oct-09
13-Nov-09
4-Dec-09
4
Dec 09
27-Nov-09
2-Jan-10
24-Dec-09
28-Nov-09
19-Feb-10
10-Dec-09
8-Feb-10
26-Jan-10
11-Feb-10
16-Dec-09
16-Feb-10
17-Apr-10
13-Jan-10
16-Dec-09
12-Feb-10
20-Jan-10
25-Mar-10
29-Apr-10
25-Mar-10
29-Apr-10
19-Jul-10
28-Dec-09
24-Feb-10
17-May-10
21-May-10
18-Feb-10
14-Mar-10
3-Jun-10
24-May-10
21-Jun-10
29
29-Apr-10
A 10
3-Jun-10
25-Mar-10
2-Jan-10
2-Jan-10
26-Jul-10
25-Mar-10
30-Aug-10
19-Jul-10
26-Jul-10
24-May-10
12-Aug-10
10-May-10
30-Aug-10
23-Aug-10
16-Sep-10
21-May-10
13-Nov-10
23-Aug-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

24-Aug-09
4-Dec-09
24-Aug-09
4-Dec-09
24-Aug-09
28-Nov-09
30-Jan-10
15-Mar-10
24-Mar-10
15-Jun-10
5-Apr-10
5
Apr 10
15-Mar-10
9-Apr-10
8-Apr-10
27-May-10
17-Aug-10
14-Jun-10
21-Aug-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

10-Sep-09
4-Dec-09
10-Sep-09
4-Dec-09
10-Sep-09
4-Dec-09
11-Feb-10
24-May-10
10-Apr-10
15-Jun-10
20-May-10
24-May-10
27-May-10
24-May-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

10-Aug-10
15-Jun-10
1-Oct-10
20-Jul-10
10-Dec-10
19-Jul-10
1-Feb-11
21-Aug-10

15-Oct-09
15-Oct-09
15-Oct-09
13-Nov-09
27-Nov-09
27 Nov 09
24-Dec-09
19-Feb-10
8-Feb-10
11-Feb-10
16-Feb-10
13-Jan-10
12-Feb-10
25-Mar-10
25-Mar-10
19-Jul-10
24-Feb-10
21-May-10
14-Mar-10
24-May-10
29-Apr-10
25-Mar-10
2-Jan-10
25-Mar-10
19-Jul-10
24-May-10
10-May-10
23-Aug-10
21-May-10
23-Aug-10

4-Dec-09
4-Dec-09
28-Nov-09
15-Mar-10
15-Jun-10
15-Mar-10
15 Mar 10
8-Apr-10
17-Aug-10
21-Aug-10

PERCHASE SPECIFICATION

4.1.3.1

Water Cooled Surface Condenser

LTSL-M0-00601-PS

10-Sep-09

4.1.3.2

Deaerator

LTSL-M0-00606-PS

10-Sep-09

4.1.3.3

Feed Water Heaters

LTSL-M0-00607-PS

10-Sep-09

4.1.3.4

BFP (TD & MD)

LTSL-M0-00603-PS

11-Feb-10

4.1.3.5

Steam Turbine Drive

LTSL-M0-00602-PS

10-Apr-10

4.1.3.6

EOT Crane

LTSL-M0-00624-PS

20-May-10

4.1.3.7

Condensate Extraction Pump

LTSL-M0-00604-PS

27-May-10

700.0

5.00%

4.2

PROC. ASSI. - ELECTRICAL SYSTEM

4.2.1

SPECIFICATION

4.2.1.1

AC & DC Distribution Board

LTSL-E0-00600-SP

10-Aug-10

4.2.1.2

24 V DC System

LTSL-E0-00602-SP

1-Oct-10

4.2.1.3

LV Power & Control Cables

LTSL-E0-00603-SP

10-Dec-10

4.2.1.4

Erection & Installation

LTSL-E0-00604-SP

1-Feb-11

4.2.2
4.2.3

Receive
Date
I/W No.

Receipt Date
of Approval

BID EVALUATION REPORT

4.1.3

Release
Date
DTN No.

5th Submission (Rev. E)

SPECIFICATION

4.1.2

L&T

Recd aftr
Long Time

LTSL-M0-00607-SP

JNSTPP

4th Submission (Rev. D)

Last Wk
Recd
To Rcvd
Next Wk

Feed Water Heaters

Receive
Date
I/W No.

Subm.
Next Wk
Last Wk
Submited

4.1.1.3

Release
Date
DTN No.

FLAG

FLAG
Recd aftr
Long Time

L&T

3rd Submission (Rev. C)

Last Wk
Recd
To Rcvd
Next Wk

90.00%

JNSTPP

Subm.
Next Wk
Last Wk
Submited

40.00%

12600.0

Receive
Date
I/W No.

FLAG

FLAG
Recd aftr
Long Time

23-Jul-09

14000.0

Release
Date
DTN No.

FLAG
2nd Submission (Rev. B)`

Last Wk
Recd
To Rcvd
Next Wk

23-Jul-09

LTSL-M0-00606-SP

PROCUREMENT ASSISTANCE
PROC. ASSI. - MECHANICAL
SYSTEM

L&T

Subm.
Next Wk
Last Wk
Submited

LTSL-M0-00601-SP

Deaerator

4.1.1

Drawing / Doc. No.

FLAG

FLAG
1st Submission (Rev. A)

Recd aftr
Long Time

Water Cooled Surface Condenser

4.1.1.2

4
4.1

Description

FLAG

Last Wk
Recd
To Rcvd
Next Wk

4.1.1.1

Sr. No.

Schedule
First
Submission
Date

Subm.
Next Wk
Last Wk
Submited

Category (A/I)

Unit No.

Latest Approval
Status from
Client

JOB No. T209001

:LT-P0-00003
:4.1
:A

4-Dec-09
4-Dec-09
4-Dec-09
24-May-10
15-Jun-10
24-May-10
24-May-10

15-Jun-10
20-Jul-10
19-Jul-10
21-Aug-10

BID EVALUATION REPORT


PERCHASE SPECIFICATION

Page 03 of 12

LARSEN & TOUBRO LIMITED

DOCUMENT NO.
ANNEXURE REV. NO:

POWER PROJECT MANAGEMENT SERVICES , VADODARA

20.00%

12675.0

97.50%

LTSL-M0-0001

19-Sep-09

Pipe Stress Analysis, Isometrics,


& Lists

15000.3

23.08%

6.1

Piping Stress Analysis

2000.0

13.33%

6.1.1

Pipe Load Data of Stress Analysed Systems


for Civil Design (Feed Water System)

LTSL-M0-00920

1-Oct-10

6.2

Isometric Drawings

2620.3

Large Bore Isometric


Large Bore Isometric / 3D Model
6.2.1.1
Preparation
6.2.2 Smoll Bore Isometric

1069.4

17.47%
7.13%

LATER

7-Jul-10

6.2.1

6.4
1

6.4.1

Lists
List - Equipments

3250.0

21.67%

LTSL-M1-00700

6-Feb-10

4-Nov-10

4-Dec-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act
Act.
Sch.
Act.
Sch.
Act.

6-Feb-10
21-Apr-10
12-Feb-10
23-Apr-10
12-Feb-10
23-Apr-10
1-Mar-10
23 Apr 10
23-Apr-10
18-Feb-10
21-Apr-10
10-May-10
23-Apr-10

27-Apr-10

27-May-10

6-Jun-10

6-Jul-10

3-Jul-10

3-May-10

2-Jun-10

12-Jun-10

12-Jul-10

5-Aug-10

Sch.
Act.
Sch.
Act.
Sch.
Act.

12-Feb-10

I
I

6.4.4

List
Specialities
st - Spec
a t es

LTSL-M1-00703
S
00 03

1-Mar-10
a 0

6.4.5

List - Interface / Terminal Points

LTSL-M1-00704

18-Feb-10

LTSL-M1-00711

10-May-10

LTSL-E0-00702

1-Feb-10

DCPL 0143

DCPLODT0136
DCPLODT0136
DCPLODT0125
DCPLODT0128

8-Mar-10
3-Jul-10
14-Mar-10
30-Jun-10
14-Mar-10
30-Jun-10
31-Mar-10
30 Jun 10
30-Jun-10
20-Mar-10
2-Aug-10
9-Jun-10
18-May-10

1-Feb-10
17-Apr-10
23-Feb-10
21-Apr-10
26-May-10
23-Apr-10

DCPLODT0123
DCPLODT0125
DCPLODT0128

3-Mar-10
30-Apr-10
25-Mar-10
30-Apr-10
25-Jun-10
18-May-10

DCPLO DT0101
DCPL 0099
DCPL 0117

DCPLODT0125
DCPLODT0136

List - Feeder List for UPS DB

6.5.2

List - Feeder List for 220V DCDB

LTSL-E0-00703

23-Feb-10

6.5.3

List - Consolidated Load List

LTSL-E0-00704

26-May-10

LTSL-I1-00700

10-May-10

Sch.
Act.

10-May-10
23-Jul-10

DCPLODT0208

9-Jun-10

Sch.
Act.

12-Feb-10
23-Apr-10

DCPLODT0128

14-Mar-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
S h
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

1-Oct-09
1-Oct-10
4-Nov-09
4-Nov-09
21-Sep-09
21-Sep-09
1-Oct-09
21-Sep-09
12-Feb-10
12-Feb-10
12-Feb-10
12-Feb-10
12-Feb-10
12-Feb-10
1-Feb-10
1-Feb-10
1-Feb-10
1-Feb-10
18-Mar-10
18-Mar-10
19-Jan-10
19-Jan-10
16-Sep-09
16-Sep-09
22-Dec-09
22-Dec-09
6-Jan-10
6-Jan-10
6-Jan-10
6-Jan-10
10-Jun-10
10 J 10
10-Jun-10
10-Jun-10
10-Jun-10
10-Jun-10
10-Jun-10
14-Jul-10
14-Jul-10

JPVLODT0004
DCPLODT0009
JPVLODT0004
JPVLODT0004
DCPLODT0085
DCPLODT0085
DCPLODT0085
DCPLoDT0073
DCPLODT0073
DCPLODT0098
DCPLODT0056
JPVLO0001
JPVLODT0009
DCPLODT0045
DCPLODT0045
DPCLO
DPCLODT0161
DPCLODT0162
DCPLoDT0162
DCPLODT0178

31-Oct-09

Pipe Support Drawings

9750.0

15.00%

O&M Manual & PG Test Procedure

1625.0

2.50%

ELE SCHEM & Cable Sched etc.

1625.0

2.50%

Up to Release for Construction

1584.4

97.50%

LTSL-E0-00200

12-Feb-10

6500.0
0.00

10.00%
0.00%

LTSL-P0-00200

1-Oct-09

10
13
C
C

List - Instruments

9.1.1

13.1
13.2

24 V DC System SLD

C&I Schem & Cable Sched


Extra Documents
Drawing & Document Numbering Procedure
Engineering Deliverable List

13.3

Project Co-Ordination Procedure

13.4

Plant Tagging Procedure

13.5

13.6

13.7

13.8

Loading Data for Rectangular Surface


Condenser
GA-Rectangular Surface Condenser
(Condenser - 1)
GA-Rectangular Surface Condenser
(Condenser - 2)
Foundation Layout for BFPs

LTSL-JPN:E-0019

4-Nov-09

I
I

LT-P0-00001

21-Sep-09

LTSL-P0-00201

1-Oct-09

592201-LOAD

12-Feb-10
12-Feb-10

592301.0

12-Feb-10

LT-JPN-EN-PPM-006

1-Feb-10

13.10

Notes on Inputs Required for PHE & ACW


Pump Design

LTSL-M0-00908

18-Mar-10

13.11

Wheel Load Diagram for EOT Cranes

JPN-SK-M-007

19-Jan-10

LT-JPN-EN-PPM-007

1-Feb-10

13.12

Unit 1 STG Package L1 Schedule

16-Sep-09

13.13

Unit 1 STG Package L2 Schedule

22-Dec-09

13.14

13.15

13.16

13.17

C
C

13.18
13.19

Note on Condensate Polishing Plant


Feed Water Piping Arrangement upto El. +
17.00 M
Response Sheet for DCPL Comments on
Sketch no. JPN-SK-M-019, Modified
Note on Interface of TG Building Auxiliary
Column with Equipment / Piping

592201.0

Foundation Layout for CEPs

WDC Drain information (LMB Document for


Information purpose)
Information for Boiler feed pump design
(LMB Document for Information purpose)

13.9

18-Mar-10
23-Jul-10
24-Mar-10
11-Aug-10
24-Mar-10
23-Jul-10
10-Apr-10
26 Jul 10
26-Jul-10
30-Mar-10
23-Aug-10
19-Jun-10

DCPL 0141
DCPL 0141
DCPL 0157
DCPL 0117

28-Nov-09
5-Jan-10

DCPLODT0206

17-Apr-10

DCPLODT0221

23-Apr-10
30-Aug-10
23-Apr-10
30-Aug-10
10-May-10
30 Aug 10
30-Aug-10
29-Apr-10

DCPLODT0206
DCPLODT0210
DCPLODT0236

DCPL 0020

DCPL 0173
DCPL 0173
DCPL 0173

19-Jul-10

8-Dec-09
19-Jan-10

DCPLODT0057

7-Jan-10
26-Feb-10

DCPL 0055

17-Jan-10
23-Apr-10

DCPLODT0135

16-Feb-10
8-Jun-10

DCPL 0126

18-Mar-10
9-Jul-10

DCPLODT0175

17-Apr-10

3-May-10

2-Jun-10

12-Jun-10

12-Jul-10

5-Aug-10

20-May-10

19-Jun-10

29-Jun-10

29-Jul-10

5-Aug-10

9-May-10

8-Jun-10

18-Jun-10

18-Jul-10

29-Jul-10

28-Aug-10

7-Sep-10

7-Oct-10

18-May-10

30-Apr-10

13-Mar-10

12-Apr-10

22-Apr-10

22-May-10

1-Jun-10

1-Jul-10

4-Apr-10

4-May-10

14-May-10

13-Jun-10

23-Jun-10

23-Jul-10

5-Jul-10

4-Aug-10

14-Aug-10

13-Sep-10

23-Sep-10

23-Oct-10

19-Jun-10

19-Jul-10

29-Jul-10

28-Aug-10

7-Sep-10

7-Oct-10

24-Mar-10

23-Apr-10

3-May-10

2-Jun-10

12-Jun-10

12-Jul-10

20-Dec-09

19-Jan-10

29-Jan-10

28-Feb-10

23-Jan-10

22-Feb-10

4-Mar-10

3-Apr-10

9-Jan-10

19-Jan-10

18-Feb-10

18-May-10

Lists / C&I

97000-2381-8

6-Jan-10

97000-2311-1

6-Jan-10

10-Jun-10

JPN-SK-M-021

10-Jun-10

LTSL-M0-00637

10-Jun-10
14-Jul-10

LTSL-M0-00635

I
I

DCPL 0141

DCPLODT0013

Lists / Electrical

9.1

Recd aftr
Long Time

25-Oct-10

12-Feb-10

6.6.1

Last Wk
Recd
To Rcvd
Next Wk

25-Sep-10

LTSL-M1-00702

Subm.
Next Wk
Last Wk
Submited

15-Sep-10

LTSL-M1-00701

6.6

Recd aftr
Long Time

16-Aug-10

List - Pipelines

6.5.1

Last Wk
Recd
To Rcvd
Next Wk

6-Aug-10

List - Valves

Subm.
Next Wk
Last Wk
Submited

7-Jul-10
26-May-10

6.4.3

List - Electrical Load List

Recd aftr
Long Time

Sch.
Act.

6.4.2

6.5

Last Wk
Recd
To Rcvd
Next Wk

6.4.6

Subm.
Next Wk
Last Wk
Submited

28-Feb-11

Recd aftr
Long Time

29-Jan-11

29-Oct-09
18-Nov-09

DCPL 0001

Last Wk
Recd
To Rcvd
Next Wk

19-Jan-11

A3

4-Dec-09
5-Jan-10
21-Oct-09

GA - Turbine Building Plan & Sections

5.1.1

21-Apr-10
14-Mar-10

Receive
Date
I/W No.

21-Jul-10

13000.0

Up to Release for Construction

Release
Date
DTN No.

30-Jun-10

Turbine Building Layout - GA /


Piping Composite Drawings

JNSTPP

20-Dec-10

Receive
Date
I/W No.

10-Dec-10

20-Oct-10

5.1

Release
Date
DTN No.

10-Nov-10

LTSL-I0-00606-SP

65.00%

L&T

31-Oct-10

Vibration Monitoring System

65000.3

JNSTPP

DCPLODT0258

4.3.1.3

Detail Engineering

Receive
Date
I/W No.

1-Oct-10
9-Sep-10

PERCHASE SPECIFICATION

Release
Date
DTN No.

Sch.
Act.

4.3.3

L&T

JNSTPP

28-Jun-10

24-Nov-10

Receive
Date
I/W No.

19-Oct-09
23-Oct-09

LTSL-I0-00602-SP

LTSL-I0-00600-SP

Release
Date
DTN No.

Receipt Date
of Approval

DCPLODT0005

Flow Elements

DCS

L&T

5th Submission (Rev. E)

19-Sep-09
16-Oct-09

6-Apr-10

4.3.1.2

BID EVALUATION REPORT

JNSTPP

4th Submission (Rev. D)

Sch.
Act.

LTSL-I0-00601-SP

4.3.2

Receive
Date
I/W No.

FLAG

FLAG

6-Apr-10
21-Jul-10
28-Jun-10
30-Jun-10
20-Oct-10
21-Apr-10
24-Nov-10
14-Mar-10

4.3.1.1

4.3.1.4

Release
Date
DTN No.

3rd Submission (Rev. C)

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

L&T

FLAG

FLAG

SPECIFICATION
Control Valves & Pneumetic ON / OFF
Valves

5.00%

4.3.1

700.0

FLAG
2nd Submission (Rev. B)`

PROC. ASSI. - C&I SYSTEM

FLAG

FLAG
1st Submission (Rev. A)

4.3

Drawing / Doc. No.

FLAG
Subm.
Next Wk
Last Wk
Submited

Description

Category (A/I)

Sr. No.

Schedule
First
Submission
Date

Latest Approval
Status from
Client

Unit No.

JOB No. T209001

:LT-P0-00003
:4.1
:A

DCPL 0021

31-Oct-09
14-Mar-10
14-Mar-10
17-May-10
14-Mar-10
17-May-10
3-Mar-10
15-Mar-10
3-Mar-10
15-Mar-10
17-Apr-10

DCPL 0115
DCPL 0115
DCPL- 0071
DCPl 0071

18-Feb-10
9-Feb-10
16-Oct-09

DCPL 0041

21-Jan-10
5-Feb-10
5-Feb-10
10-Jul-10
10 J l 10
18-Jun-10
10-Jul-10
10-Jul-10
13-Aug-10

DCPL 0139

10-Nov-09
1-Oct-09
14-Dec-09

JPVLODT0002

31-Oct-09
5-Nov-09
10-Nov-09
5-Nov-09
24-Mar-10

DCPLODT0010
DCPLODT0010

10-Dec-09
30-Nov-09
13-Jan-10
30-Nov-09

DCPL 0008

10-Dec-09

10-Dec-09
6-Jan-10
20-Dec-09

19-Jan-10

29-Jan-10

28-Feb-10

23-Apr-10

3-May-10

2-Jun-10

12-Jun-10

12-Jul-10

24-Mar-10

23-Apr-10

3-May-10

2-Jun-10

12-Jun-10

12-Jul-10

24-Mar-10

23-Apr-10

3-May-10

2-Jun-10

12-Jun-10

12-Jul-10

13-Mar-10

12-Apr-10

22-Apr-10

22-May-10

1-Jun-10

1-Jul-10

13-Mar-10

12-Apr-10

22-Apr-10

22-May-10

1-Jun-10

1-Jul-10

27-Apr-10

27-May-10

6-Jun-10

6-Jul-10

16-Jul-10

15-Aug-10

JPVLODT0011

28-Feb-10

30-Mar-10

9-Apr-10

9-May-10

19-May-10

18-Jun-10

26-Oct-09

25-Nov-09

5-Dec-09

4-Jan-10

14-Jan-10

13-Feb-10

2-Mar-10

12-Mar-10
25-Jan-10
27-Mar-10

11-Apr-10

21-Apr-10

21-May-10

26-Apr-10

6-May-10

5-Jun-10

31-Jan-10
16-Jan-10
15-Feb-10
5-Jun-10
15-Feb-10
5-Jun-10
20-Jul-10
20 J l 10

JPVLODT0012
DCPLODT0158
DCPLODT0158

20-Jul-10
14-Jun-10
20-Jul-10

DPCLODT0164

23-Aug-10
23-Jul-10

DCPLODT0207

17-Mar-10

JPVLODT0013

17-Mar-10

27-Mar-10

26-Apr-10

6-May-10

5-Jun-10

19-Aug-10
19 A 10

29-Aug-10
29 A 10

28-Sep-10
28 S 10

8-Oct-10
8 O t 10

7-Nov-10
7 N 10

19-Aug-10

29-Aug-10

28-Sep-10

8-Oct-10

7-Nov-10

19-Aug-10

29-Aug-10

28-Sep-10

8-Oct-10

7-Nov-10

22-Sep-10

2-Oct-10

1-Nov-10

11-Nov-10

11-Dec-10

Page 04 of 12

LARSEN & TOUBRO LIMITED

DOCUMENT NO.
ANNEXURE REV. NO:

POWER PROJECT MANAGEMENT SERVICES , VADODARA

13.20

13.21

C
C
C

13.22
13.23
13.24

13.25

13.26

13.27

Sketch Interface of Auxiliary Columns


(Along row a1, a2& a3) with Equipment /
Note on Piping Corridor for Condensate
Polishing Plant
Sketch Part Copy of Plot Plan (K6A24-DWGM-002-REV-4)
Sketch on Interface tie beams with
Condenser Tube removal
Power house unit - 1 _ Column Schedule
(Commented)
TG Building Floor Opening for Unit # 1
Along with the Row B & C
Sketch Showing RC Slab & Grating Floor
Requirement for Mazzanine Floor Elevation
Note on Support Structure Requirement for
Pipes Connecting to Deaerator
Steam Turbine & Generator Componant
layout plan at operating Floor EL. (+) 17M

13.28

13.29

Start up Curve for Steam Turbine

13.30

Piping Load Data for Stress Analysis


System for CIVIL Design (Feed Water

Abbreviation:
A - Approval
I - Information
N - Not for Submission
x

JPN-SK-M-023

14-Jul-10

LTSL-M0-00638

16-Jul-10

JPN-SK-M-024
-

16-Jul-10
23-Jul-10
23-Jul-10

I
I
I

JPN-SK-M-026

12-Aug-10

JPN-SK-M-027

23-Aug-10

LTSL-M0-00641

30-Aug-10

LTSL-M0-00552

27-Aug-10

LMTG-P0-01037

10-Sep-10

LTSL-M0-00920

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

L&T

10-Sep-10

24-Sep-10

4-Oct-10

24-Sep-10

4-Oct-10

1-Sep-10

1-Oct-10

22-Aug-10

1-Sep-10

11-Sep-10

21-Sep-10

4th Submission (Rev. D)

Release
Date
DTN No.
11-Nov-10

Receive
Date
I/W No.
11-Dec-10

3-Nov-10

13-Nov-10

13-Dec-10

3-Nov-10

13-Nov-10

13-Dec-10

11-Oct-10

10-Nov-10

20-Nov-10

20-Dec-10

1-Oct-10

11-Oct-10

10-Nov-10

20-Nov-10

20-Dec-10

21-Oct-10

31-Oct-10

30-Nov-10

10-Dec-10

9-Jan-11
20-Jan-11

15-Aug-10

25-Aug-10

15-Aug-10

25-Aug-10

22-Aug-10

L&T

JNSTPP

JNSTPP

L&T

22-Sep-10

2-Oct-10

1-Nov-10

11-Nov-10

11-Dec-10

21-Dec-10

29 Sep 10
29-Sep-10

9 Oct 10
9-Oct-10

8 Nov 10
8-Nov-10

18 Nov 10
18-Nov-10

18 Dec 10
18-Dec-10

28 Dec 10
28-Dec-10

27 Jan 11
27-Jan-11

26-Sep-10

6-Oct-10

5-Nov-10

15-Nov-10

15-Dec-10

25-Dec-10

24-Jan-11

10-Oct-10

20-Oct-10

19-Nov-10

29-Nov-10

29-Dec-10

8-Jan-11

7-Feb-11

Last Wk
Recd
To Rcvd
Next Wk

Receive
Date
I/W No.
1-Nov-10

Receive
Date
I/W No.
22-Sep-10

L&T

FLAG

FLAG
Subm.
Next Wk
Last Wk
Submited

Release
Date
DTN No.
2-Oct-10

Release
Date
DTN No.
23-Aug-10

JNSTPP

Last Wk
Recd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

3rd Submission (Rev. C)

Recd aftr
Long Time

FLAG

FLAG

Recd aftr
Long Time

FLAG
2nd Submission (Rev. B)`

Last Wk
Recd
To Rcvd
Next Wk

Receive
Date
I/W No.
13-Aug-10

Recd aftr
Long Time

Release
Date
DTN No.
DCPLO14-Jul-10
DT0178
14-Jul-10
DCPLO16-Jul-10
DT0187
16-Jul-10
DCPLO16-Jul-10
DT0187
16-Jul-10
DCPLO23-Jul-10
DT0207
23-Jul-10
DCPLO23-Jul-10
DT0207
23-Jul-10
DCPLO12-Aug-10
DT0223
12-Aug-10
DCPLO23-Aug-10
DT0238
23-Aug-10
DCPLO
DCPLO30 Aug 10
30-Aug-10
DT0246
30-Aug-10
DCPLO27-Aug-10
DT0244.
27-Aug-10
DCPLO10-Sep-10
DT0261
10-Sep-10

Subm.
Next Wk
Last Wk
Submited

FLAG

FLAG
1st Submission (Rev. A)

Last Wk
Recd
To Rcvd
Next Wk

Drawing / Doc. No.

FLAG
Subm.
Next Wk
Last Wk
Submited

Description

Category (A/I)

Sr. No.

Schedule
First
Submission
Date

Latest Approval
Status from
Client

Unit No.

JOB No. T209001

:LT-P0-00003
:4.1
:A

JNSTPP

5th Submission (Rev. E)

Release
Date
DTN No.

Receipt Date
of Approval

Receive
Date
I/W No.

DCPLODT0261

I/W No. - Inward No.


DTN No. - Document Transmittal No.
- Weightage Point not considered
x
x
x
x
x

Unit type: C - Common for both Units


1 - For Unit No. 1 only
2 - For Unit No. 2 only
x
x
x
x
x

Sch. - Schedule Date for Submission


Act. - Actual Date of Submission
x

Page 05 of 12

DOCUMENT NO.
ANNEXURE REV. NO:

Early Start

L&T

JNSTPP

L&T

JNSTPP

L&T

Receive
Date
I/W No.

JNSTPP

Subm.
Next Wk
Last Wk
Submited

Release
Date
DTN No.

FLAG

FLAG
Recd aftr
Long Time

3rd Submission (Rev. C)

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Receive
Date
I/W No.

Recd aftr
Long Time

Release
Date
DTN No.

FLAG

FLAG

FLAG
2nd Submission (Rev. B)

Last Wk
Rcvd
To Rcvd
Next Wk

Receive
Date
I/W No.

Subm.
Next Wk
Last Wk
Submited

Release
Date
DTN No.

Recd aftr
Long Time

Drawing / Doc. No.

1st Submission (Rev. A)

Last Wk
Rcvd
To Rcvd
Next Wk

Description

FLAG

FLAG

FLAG
Subm.
Next Wk
Last Wk
Submited

Sr. No.

Schedule
First
Submission
Date

Category
(A/I/N)

Unit No.

JOB No. T209001

:LT-P0-00003
:4.2
:A

L&T

4th Submission (Rev. D)


Release
Date
DTN No.

Receive
Date
I/W No.

Recd aftr
Long Time

POWER PROJECT MANAGEMENT SERVICES , VADODARA

Last Wk
Rcvd
To Rcvd
Next Wk

LARSEN & TOUBRO LIMITED

JNSTPP

As Built

Receipt Date
of Approval

Release
Date-Unit 1 DTN No

TRANSMITTAL WITH CUSTOMER

Mechanical Documents

13.2.1

Turbine Generator Outline

13.2.2

Control and Lubricating oil System Diagram

13.2.3

Oil Piping Diagram

13.2.4

Gland Steam and Drain Piping Diagram

13.2.5

Oil Purifier Oil Piping Diagram


Turbine Sectional Assembly

13.2.8

Utility List for Steam Turbine

13.2.9

Electrical Load List

13.2.11 T/G Foundation Design Criteria

13.2.12 Plan for Turbine Enclosure

13.2.13 Plan for Arrangement of T/G Foundation Deck

13.2.14 Plan for Arrangement of Foundation Bolt

13.2.15 Plan for Arrangement of Anchor Bolt

13.2.17 Valve List

13.2.19 Motor List for Steam Turbine


13.2.20 Oil Piping Arrengement

15-Dec-09

15-Dec-09

15-Dec-09
14-Feb-10

I
I

15-Feb-10

15-Dec-09

15-Dec-09

15-Dec-09

15-Mar-10

15-Jan-10

15-May-10

15-Mar-10

14-Nov-09
4-Nov-09
15-Dec-09
29-Dec-09
13-Jan-10
22-Feb-10
13-Jan-10
22-Feb-10
16-Mar-10
26-Mar-10
13-Jan-10
16-Mar-10
13-Jan-10
22-Feb-10
13-Jan-10
22-Feb-10
13-Jan-10
16-Mar-10
15-Feb-10
16-Mar-10
15-Feb-10
1-Feb-10
15-Feb-10
1-Feb-10
15-Feb-10
1-Feb-10
15-Feb-10
1-Feb-10
15-Apr-10
13-Apr-10
15-Apr-10
13-Apr-10
15-Apr-10
13-Apr-10

14-Apr-10
1-Jun-10
14-Apr-10
7-Apr-10
15-May-10

DCPL 0122
DCPL 0087

15-May-10
15-Sep-10
5 Sep 0

DCPL 0178

DCPLODT0009
DCPLODT0034
DCPLODT0090
DCPLODT0090
DCPLODT0106
DCPLODT0096
DCPLODT0090
DCPLODT0090
DCPLODT0096
DCPLODT0096
DCPLODT0063
DCPLODT0063
DCPLODT0063
DCPLODT0063
DCPLODT0119
DCPLODT0119
DCPLODT0119

14-Dec-09
5-Jan-10
14-Jan-10
19-Jan-10
12-Feb-10

DCPL 0024
DCPl 0035

12-Feb-10
8-Mar-10
15-Apr-10
7-Apr-10
12-Feb-10
30-Apr-10
12-Feb-10
10-May-10
12-Feb-10
10-May-10
12-Feb-10
10-May-10
17-Mar-10

DCPL 0064
DCPL 0085
DCPLO0100
DCPL 0113
DCPL 0113
DCPL 0112

17-Mar-10
12-Feb-10
17-Mar-10
12-Feb-10
17-Mar-10
12-Feb-10
17-Mar-10
12-Feb-10
15-May-10
5-May-10
15-May-10
10-May-10
15-May-10
10-May-10

DCPL 0044
DCPL 0044
DCPL 0044
DCPL 0044
DCPL 0106
DCPL 0110
DCPL 0109

DCPLODT0075
DCPLODT0153
DCPLODT0153
DCPLODT0153
DCPLODT0153

15-Mar-10

13-Feb-10
15-Mar-10
13-Feb-10
15-Mar-10
13-Feb-10
12-Feb-10
15-Apr-10

DCPLODT0095
DCPLODT0095-C
DCPLODT0085-0

30-Mar-10
30-Mar-10
30-Aug-10
30-Mar-10
30-Aug-10
30-Mar-10
30-Aug-10
15-Mar-10

DCPL 0172
DCPL 0172
DCPL 0172

15-Mar-10
7-Apr-10
15-Mar-10
7-Apr-10
15-Mar-10

DCPL 0084
DCPL 0084

12-Aug-10

1
1

14-May-10
29-May-10

13-Jun-10
3-Feb-10
28-Jun-10

29-Apr-10

29-May-10

28-Jun-10

28-Jul-10

29-Apr-10

29-May-10

28-Jun-10

28-Jul-10

29-Apr-10

29-May-10

28-Jun-10

28-Jul-10

14-Apr-10

14-May-10

13-Jun-10

13-Jul-10

DCPLODT0167

14-Apr-10
22-Mar-10
14-Apr-10
22-Mar-10
14-Apr-10
22-Mar-10
13-Jul-10

DCPLODT0103
DCPLODT0103
DCPLODT0103

15-May-10
1-Jun-10
12-Sep-10

DCPLODT0153

DCPL 0084

13-Aug-10

15-Mar-10

15-Apr-10
7-Apr-10
13-Aug-10

11-Oct-10

28-May-10

13-Feb-10

DCPLODT0099

13-Sep-10

14-Jul-10

15-Jun-10

16-Mar-10
18-Mar-10
14-Jul-10

28-Apr-10

14-Apr-10
24-Jun-10
29-Apr-10

13-Jun-10

28-May-10

14-Jun-10

16-May-10

15-Mar-10

1
1

29-Mar-10

16-Apr-10

15-Mar-10

19-Jun-10

27-Feb-10

15-May-10

DCPLODT0166
DCPLODT0166

11-Sep-10

5-Jan-10

15-May-10

14-Apr-10
22-Mar-10
14-Apr-10
31-May-10
14-Apr-10
15-Mar-10
14-Jun-10

13-Feb-10
21-Jun-10
13-Feb-10
21-Jun-10
14-May-10

DCPLODT0153

13-Jul-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

DCPLODT0077
DCPLODT0095
DCPLODT0243
DCPLODT0239

13-Feb-10
3-Feb-10
28-Feb-10
1-Jun-10
28-Feb-10
1-Jun-10
28-Feb-10
1-Jun-10
28-Feb-10
1-Jun-10
13-Feb-10

DCPL 0142

28-Apr-10
1-Jun-10
14-Aug-10

DCPL 0063

DCPL 0140

15-Mar-10
5-Feb-10
15-Mar-10
15-Mar-10
15-Apr-10
27-Aug-10
15-Apr-10
28-Aug-10
8 ug 0

DCPL 0043
DCPL 0150

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
ct

14-Feb-10
12-Feb-10
14-Jun-10
17-Jul-10

28-Jan-10
3-Jul-10

Submittal Drawing List (MELCO PORTION)


Equipment List (MELCO PORTION)

14.4

Utility List

14.5

Electrical Load List

14.6

Motor List of Turbine Generator

14.7

Single line Diagram Generator Circuit

14.11

Painting Colour List (MELCO PORTION)

14.12

Painting Procedure (MELCO PORTION)

14.13

Logic Diagram of Generator Control

14.14

Logic Diagram of Generator Auxiliaries

14.16

Outline Drawing of Generator Control & Syncronization


Panel

14.17

Outline Drawing of Generator Auxiliary Panel

14.18

Outline Drawing of generator Seal Oil Control Panel

14.19

14.20

14.21

Arrengement Drawing of Generator Seal Oil Control Panel

14.22

Arrengement Drawing of Generator Stator Coil Cooling


Water Control Panel

Outline Drawing of Generator Stator Coil Cooling Water


Control Panel
Arrengement Drawing of Generator Control &
Synchronization Panel

14-Nov-09

14-Jul-10

DCPLODT0103
DCPLODT0152-D
DCPLODT0095-B

14-May-10
7-Apr-10
14-May-10
18-Jun-10
14-May-10
15-Jun-10
14-Jul-10

13-Jun-10
18-May-10
13-Jun-10
11-Aug-10
13-Jun-10
14-May-10
13-Aug-10

DCPL 0084
DCPL 0135
DCPL 0132

15-Jul-10
14-May-10
17-Jul-10
14-May-10

DCPL 0150

14-May-10
12-Aug-10
14-Jun-10
18-Jun-10
12-Oct-10

DCPL 0135

DCPLODT0075

DCPLODT0144
DCPLODT0220
DCPLODT0142-B

13-Jul-10
15-Jun-10
28-Jul-10

13-Jul-10
18-Jun-10
13-Jul-10
26-Aug-10
13-Jul-10
15-Jun-10
12-Sep-10

DCPL 0132

DCPl 0137
DCPl 0168
DCPl 0132

2-Jan-10

30-Apr-10

15-Jun-10

14-Jun-10

5-Jan-10

18-Jun-10

1
1

15-Jun-10

15-Jun-10

14-Aug-10

13-Sep-10

15-Jun-10

13-Jun-10

13-Jul-10

2-Jan-10

13-Jun-10

13-Jul-10

2-Jan-10

13-Jun-10

13-Jul-10

2-Jan-10

11-Sep-10

11-Oct-10

14-Jul-10
12-Jul-10
11-Nov-10

DCPLODT0176

13-Aug-10
26-Jul-10
11-Dec-10

DCPL 0152

18-Jun-10

15-Jun-10

1-Jun-10

13-Jul-10

12-Aug-10

11-Sep-10

11-Oct-10

13-Jul-10

12-Aug-10

11-Sep-10

11-Oct-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

918.6
LMTG-E0-02001
GAE-KN-E120
LMTG-E0-02003
GAE-KN-E-147
LMTG-E0-02004
GAE-KN-E146
LMTG-E0-02005
GAE-KN-E240
LMTG-E0-02006
GAE-KN-E400
LMTG-E0-02007
JEK79164
LMTG-E0-02011
GAE-KN-E162
LMTG-E0-02012
GAE-KN-E163
LMTG-E0-02013
JEZ2V682
LMTG-E0-02014
JEZ2V683
LMTG-E0-02016
JEJ62354
LMTG-E0-02017
JEJ62355
LMTG-E0-02018
JEJ62356
LMTG-E0-02019
JEJ62357
LMTG-E0-02020
JEJ62358
LMTG-E0-02021
JEJ62359
LMTG-E0-02022
JEJ62360

15-Dec-09

13-Jan-10

13-Jan-10

16-Mar-10

13-Jan-10

13-Jan-10

13-Jan-10

13-Jan-10

15-Feb-10

15-Feb-10

15-Feb-10

15-Feb-10

15-Feb-10

15-Apr-10

15-Apr-10

15-Apr-10

13-Jan-10

12-Feb-10

13-Feb-10
5-Feb-10
14-Mar-10
1-Jun-10
14-Mar-10
2-Jul-10
15-May-10

DCPLODT0077
DCPLODT0154
DCPLODT0172

14-Mar-10
4-Jun-10
14-Mar-10
1-Jun-10
14-Mar-10
8-Jun-10
14-Mar-10
5-Jun-10
16-Apr-10

DCPLODT0156
DCPLODT0154
DCPLODT0159
DCPLODT0157

16-Apr-10
4-Jun-10
16-Apr-10
4-Jun-10
16-Apr-10
4-Jun-10
16-Apr-10
4-Jun-10
14-Jun-10

DCPLODT0156
DCPLODT0155
DCPLODT0156
DCPLODT0155

14-Jun-10
4-Jun-10
14-Jun-10
4-Jun-10

DCPLODT0155
DCPLODT0155

14-Mar-10

15-Mar-10
8-Mar-10
13-Apr-10

DCPL 0064

13-Apr-10
26-Jul-10
14-Jun-10

DCPL 0152

13-Apr-10
17-Jul-10
13-Apr-10
18-Jun-10
13-Apr-10

DCPL 0149
DCPl 0136

13-Apr-10
26-Jul-10
16-May-10

DCPL 0154

16-May-10
17-Jul-10
16-May-10
17-Jul-10
16-May-10

DCPL 0149
DCPL 0148

16-May-10
14-Jul-10
17-Jul-10
14-Jul-10
14-Jul-10

DCPL 0149

13-Apr-10

14-Apr-10
24-Mar-10
13-May-10

DCPLODT0105

13-May-10
7-Sep-10
14-Jul-10
17-Jul-10
13-May-10
10-Sep-10
13-May-10
7-Sep-10
13-May-10

DCPLODT0252
DCPLODT0189
DCPLODT0260
DCPLODT0252

14-May-10
7-Apr-10
12-Jun-10

13-May-10
DCPL 0085

12-Jun-10
13-Aug-10
28-Jul-10
12-Jun-10

13-Jun-10
11-May-10
12-Jul-10
12-Jul-10

DCPL 0156

12-Jun-10
DCPLODT0140

13-Jul-10
24-May-10
11-Aug-10

DCPL 0119

5-Jan-10

7-Apr-10

11-Aug-10

8-Mar-10

12-Sep-10

12-Oct-10

28-Jul-10

12-Jul-10

11-Aug-10

12-Jun-10

12-Jul-10

11-Aug-10

12-Jun-10

12-Jul-10

11-Aug-10

10-May-10

13-May-10

12-Jun-10

12-Jul-10

11-Aug-10

15-Jun-10

15-Jul-10

14-Aug-10

13-Sep-10

15-Jul-10

14-Aug-10

13-Sep-10

17-Jul-10

15-Jul-10

14-Aug-10

13-Sep-10

17-Jul-10

15-Jun-10
10-Sep-10
15-Jun-10
10-Sep-10
15-Jun-10

DOCUMENTS FOR GENERATOR

14.1

15-Apr-10

14-Jun-10

13.2
C

DCPL 0170

13.3.4

15-Apr-10

13-Jun-10
26-Aug-10
14-Jul-10

TCS / TPS System Configuration

15-Mar-10

13-Jun-10
DCPLODT0220

Drive List for TCS / TPS

14-May-10
14-May-10
11-Aug-10
14-Jun-10

Drive Control Philosophy

13.3.3

LMTG-I0-01300
61000-0020
LMTG-I0-01301
61000-0030
LMTG-I0-01302
61000-0040
LMTG-I0-01303
61000-0110
6 000 0 0

13.3.2

15-Dec-09

DCPLODT0095

Basic Plan for TCS / TPS System

14.3

15-Apr-10

29-Dec-09
15-Mar-10

29-Mar-10
8-Mar-10
15-Jul-10

13-Jun-10

29-May-10
19-Jun-10
13-Aug-10

C&I Documents

30-Dec-09

DCPl 0021
DCPL 0129
DCPL 0089
DCPL 0069
DCPL 0053
DCPl 0021
DCPL 0023
DCPL 0023
DCPL 0018
DCPL 0132
DCPL 0132
DCPL 0017
DCPL 0017
DCPL 0017

13-Jul-10

13.3.1

30-Dec-09

14-Jan-10
5-Jan-10
29-Jan-10
14-Jun-10
29-Jan-10
12-Apr-10
29-Jan-10
15-Mar-10
29-Jan-10
23-Feb-10
14-Jan-10
5-Jan-10
14-Jan-10
5-Jan-10
14-Jan-10
5-Jan-10
14-Jan-10
2-Jan-10
16-Mar-10
15-Jun-10
17-Mar-10
15-Jun-10
14-Jan-10
2-Jan-10
14-Jan-10
2-Jan-10
14-Jan-10
2-Jan-10
14-Apr-10

DCPLODT0023
DCPLODT0065-0
DCPLODT0065
DCPLODT0076
DCPLODT0078
DCPLODT0023
DCPLODT0023
DCPLODT0023
DCPLODT0006-0
DCPLODT0152-C
DCPLODT0065
DCPLODT0023
DCPLODT0023
DCPLODT0023
DCPLODT0121
DCPLODT0065
DCPLODT0141-0

13.3

30-Dec-09

15-Dec-09
10-Dec-09
30-Dec-09
28-Jan-10
30-Dec-09
28-Jan-10
30-Dec-09
3-Feb-10
30-Dec-09
6-Feb-10
15-Dec-09
10-Dec-09
15-Dec-09
10-Dec-09
15-Dec-09
10-Dec-09
15-Dec-09
23-Oct-09
14-Feb-10
31-May-10
15-Feb-10
28-Jan-10
15-Dec-09
10-Dec-09
15-Dec-09
10-Dec-09
15-Dec-09
10-Dec-09
15-Mar-10
16-Apr-10
15-Jan-10
28-Jan-10
15-May-10
12-May-10

30-Dec-09

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

13.2.10 T/G Foundation Loading Diagram

T3101AAAA001
LMTG-M0-01013
T3101ADAC110
LMTG-M0-01014
T3101ADAC950
LMTG-M0-01007
T3101AAAA310
LMTG-M0-01008
T3101AAAA311
LMTG-M0-01011
T3101AAAA450
LMTG-M0-01009
T3101AAAA330
LMTG-M0-01022
T3101AAAA340
LMTG-M0-01023
T3101AAAA370
LMTG-M0-01016
T3101ADAC990
LMTG-M0-01015
T3101ADAC960
LMTG-M0-01204
T3101PLPE101

15-Dec-09

13.2.7

16-Mar-10
DCPL 0008

LMTG-M0-01019
T3101AAAA003
LMTG-M0-01020
T3101AAAA210
LMTG-M0-01004
T3101AAAA220
LMTG-M0-01005
T3101AAAA230
LMTG-M0-01006
T3101AAAA250

30-Oct-09

14-Feb-10
29-Nov-09
30-Nov-09

DCPLODT0061

28-May-10
DCPLODT0143

13.2
C

14-May-10

13.1.24 DataSheet for Steam Turbine & Its Auxiliaries

15-Jan-10

13-Jun-10

28-Apr-10
29-Apr-10
15-May-10
14-Jul-10

DCPL 0052

T3101ADAC810
LMTG-P0-01027
T3101AYAC010

15-Mar-10

27-Feb-10
25-Jan-10
15-Jun-10

30-Mar-10
22-Feb-10
14-Jun-10

Equipment Numbering Procedure for Steam Turbine &


Generator

16-May-10

29-Mar-10
DCPLODT0064

13.1.11

28-Feb-10
1-Feb-10
15-May-10
14-Apr-10

13.1.10 Steam Purity Recommendation

27-Feb-10
DCPL 0015
DCPL 0172
DCPL 0133

30-Oct-09
15-Feb-10

29-Jan-10
29-Dec-09
15-Apr-10
30-Aug-10
15-Mar-10
15-Jun-10
28-Jan-10

Performance Curves of STG

DCPL 0017
DCPL 0005
DCPLO 0098

28-Jan-10
DCPLODT0023
DCPLODT0146
DCPLO DT0137
DCPLODT0046
DCPLODT0195

Heat Balance Diagram

13.1.7

14-Jan-10
2-Jan-10
29-Nov-09
6-Nov-09
17-Mar-10
30-Apr-10
14-Apr-10

30-Dec-09
10-Dec-09
16-Mar-10
24-May-10
13-Feb-10
29-Apr-10
29-Dec-09
6-Jan-10
16-Apr-10
19-Jul-10
14-May-10

13.1.6

29-Dec-09

15-Dec-09

DCPL 0021
DCPL 0007

scope of Supply of TG Foundation

29-Nov-09
5-Jan-10
5 J 10
30-Nov-09
19-Nov-09
14-Feb-10

13.1.5

DCPLODT0030
DCPLODT0007
DCPLODT0065
DCPLODT0023
JPVLODT0002
DCPLODT0093
DCPLODT0090
DCPLODT0001
JPVLODT0002

31-Oct-09
15-Jan-10

30-Oct-09
22
22-Dec-09
D 09
31-Oct-09
31-Oct-09
15-Jan-10
28-Jan-10
15-Dec-09
10-Dec-09
30-Oct-09
1-Oct-09
15-Feb-10
3-Mar-10
15-Mar-10
22-Feb-10
15-Jan-10
2-Oct-10
30-Oct-09
2-Oct-09

Equipment List

Sch.
A t
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

QAP - Steam Turbine

13.1.4

13.1.2

30-Oct-09
30
Oct 09

LMTG-P0-01001
T3101AABBOIO
LMTG-Q0-01000
QAT-P300
LMTG-M0-01017
T3101ADAC800
LMTG-M0-01028
T3101AAAA380
LMTG-P1-01003
T3101AAAB110
LMTG-P0-01026
T3101AAAB111
LMTG-P0-01025
T3101ADAC010

Drawing & Document List

13.1
13.1.1

1273.4

Up To Release for Construction


General Documents

Documents for Steam Turbine

13.1

2192.1

VDR - Steam Turbine Generator & its


Auxiliaries

13

VENDOR DRAWING REVIEW

13000.10

DCPLODT0260
DCPLODT0260

15-Jul-10

14-Aug-10

13-Sep-10

15-Jun-10

15-Jul-10

14-Aug-10

13-Sep-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

26-Jul-10

Page 06 of 12

DOCUMENT NO.
ANNEXURE REV. NO:

14.44

14.46

14.47

C
C
C
C
C

14.48
14.77
14.78
14.79
14 80
14.80

14.81

14.82

14.83

14.84

C
C

14.85
14.86

14.87

14.88

14.89

14.90

14.91

14.92

14.93

C
C
C
C
C

14.94
14.95
14.96
14.97
14.98

14.99

14.100

14.101

C
C

14.102
14.103

14.104

14.105

14.106

14.107

14.108

14.109

C
C

14.110
14.111

15-Apr-10

15-Jul-10

15-Apr-10

15-Aug-10

15-Aug-10
13-Mar-10
13-Mar-10
13-Mar-10
13-Mar-10
15-Dec-09

A
A
A
A
A
I

1-May-10

1-May-10

1-May-10
1-May-10
1-May-10

I
I
I

1-May-10

1-May-10

1-May-10

1-May-10

27-Mar-10

15-Jul-10

27-Mar-10

27-Mar-10
27-Mar-10
27-Mar-10
27-Mar-10

A
A
A
A

27-Mar-10

1-May-10

1-May-10

1-May-10

9-Jan-10
9-Jan-10

I
I

9-Jan-10

9-Jan-10

1-May-10

1-May-10

1-May-10

31-Mar-10

31-Mar-10
31-Mar-10

I
I

14-Sep-10
12-Apr-10
24-Apr-10
12-Apr-10
11-Jun-10
12-Apr-10

DCPL 0095
DCPL 0127

12-Apr-10
p
25-Aug-10
14-Jan-10
5-Jan-10
31-May-10
25-Aug-10
31-May-10
25-Aug-10
31-May-10
25-Aug-10
31-May-10
8-Jun-10
31-May-10
8-Jun-10
31-May-10
30-Aug-10
31-May-10
8-Jun-10
31-May-10
30-Aug-10
31-May-10
30-Aug-10
26-Apr-10
20-Apr-10
14-Aug-10

DCPL 0166
DCPL 0021
DCPl 0167
DCPl 0167
DCPl 0167
DCPL 0125
DCPL 0125
DCPL 0172
DCPL 0125
DCPL 0172
DCPL 0172
DCPl 0090

26-Apr-10
3-May-10
26-Apr-10
3-May-10
26-Apr-10
3 May 10
3-May-10
26-Apr-10
3-May-10
26-Apr-10
3-May-10
26-Apr-10
3-May-10
31-May-10

DCPL 0105
DCPL 0105
DCPL 0105
DCPL 0105
DCPL 0105
DCPL 0105

31-May-10
17-Jul-10
31-May-10
3-Aug-10
31-May-10

DCPL 0150
DCPL 0159

30-Apr-10
17-Jul-10
30-Apr-10
17-Jul-10
30-Apr-10
17-Jul-10

DCPL 0150
DCPL 0150
DCPL 0150

Subm.
Next Wk
Last Wk
Submited

FLAG
Recd aftr
Long Time

Receive
Date
I/W No.
12-Sep-10

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

DCPLODT0088

Recd aftr
Long Time

14-Jun-10
22-Feb-10
14-Oct-10

3rd Submission (Rev. C)

FLAG
4th Submission (Rev. D)

As Built

Receipt Date
of Approval

Release
Date
DTN No.
12-Oct-10

Receive
Date
I/W No.
11-Nov-10

12-Oct-10

11-Nov-10

12-Sep-10

12-Oct-10

11-Nov-10

15-Jul-11

14-Aug-11

13-Sep-11

12-Dec-10

11-Jan-11

10-Feb-11

Release
Date
DTN No.
DCPLO13-Aug-10
DT0260
10-Sep-10
13-Aug-10

12-Sep-10

13-Aug-10
15-Jun-11
12-Nov-10

JNSTPP

L&T

JNSTPP

Release
Date-Unit 1 DTN No
1

18-Jul-10

17-Aug-10

16-Sep-10

16-Oct-10

28-Jul-10

18-Jul-10

17-Aug-10

16-Sep-10

16-Oct-10

28-Jul-10
28-Jul-10

DCPL 0024
DCPl 0136
DCPl 0136
DCPl 0136

14-Jul-10
7-Apr-10
13-Oct-10

DCPL 0085

14-Jul-10
8-Mar-10
13-Nov-10

DCPL 0066

18-Jul-10

17-Aug-10

16-Sep-10

16-Oct-10

5-May-10

4-Jun-10

4-Jul-10

3-Aug-10

3-Jun-10

3-Jul-10

2-Aug-10

1-Sep-10

18-Jun-10

3-Jun-10

3-Jul-10

2-Aug-10

1-Sep-10

18-Jun-10

3-Jun-10

3-Jul-10

2-Aug-10

1-Sep-10

18-Jun-10

2-Aug-10

1-Sep-10

12-Feb-10

3-Jun-10
1-Jun-10
11-Jun-10

DCPLODT0154

3-Jul-10

13-Aug-10
17-Jul-10
12-Nov-10

DCPLODT0189

12-Sep-10
28-Jul-10
12-Dec-10

11-Jul-10
DCPl 0156

5-Apr-10
5-Jan-10
4-May-10
18-Jun-10
4-May-10
18-Jun-10
4-May-10
18-Jun-10
4-May-10

18-Jun-10

12-May-10

10-Aug-10

9-Sep-10

12-Feb-10

12-Oct-10

11-Nov-10

28-Jul-10

11-Jan-11

10-Feb-11

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

13-Dec-10

12-Jan-11

11-Feb-11

13-Mar-11

13-Nov-10

13-Dec-10

12-Jan-11

11-Feb-11

13-Mar-11

12-May-10

11-Jun-10

11-Jul-10

10-Aug-10

9-Sep-10

9-Oct-10

11-Jun-10

11-Jul-10

10-Aug-10

9-Sep-10

9-Oct-10

11-Jun-10

11-Jul-10

10-Aug-10

9-Sep-10

9-Oct-10

11-Jun-10

11-Jul-10

10-Aug-10
g

9-Sep-10
p

9-Oct-10

13-Jun-10

13-Jul-10

DCPLODT0264

12-May-10
y
13-Feb-10
16-Mar-10
30-Jun-10

DCPLODT0096-A

17-Jul-10

18-Jun-10

14-Oct-10

12-May-10
17-Sep-10
12-May-10

17-Jul-10

18-Jun-10

DCPLODT0096

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

31-May-10
DCPL 0150
DCPL 0018
DCPL 0076

14-Jun-10
16-Mar-10
13-Sep-10

15-Mar-10
7-Apr-10
30-Jul-10

14-Apr-10
11-May-10
29-Aug-10

DCPL 0085-A

DCPLODT0140-B

14-May-10
24-May-10
28-Sep-10

DCPL 0119

24-May-10

28-Oct-10

27-Nov-10

30-Jun-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

30-Jun-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

8-Jun-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

8-Jun-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

30-Jun-10
12-Aug-10
30-Jun-10
12-Aug-10
30-Jun-10

DCPLODT0224
DCPLODT0224

30-Jun-10
12-Aug-10
30-Jun-10

DCPLODT0224

30-Jul-10
30-Jul-10
30-Jul-10
30-Jul-10

30-Jun-10
26-May-10
17-Jul-10
13-Sep-10

31-May-10

8-Feb-10
17-Jul-10
8-Feb-10
2-Jan-10
8-Feb-10
31-Mar-10
8-Feb-10

DCPLODT0260
DCPLODT0266
DCPLODT0260
DCPLODT0030
DCPLODT0154
DCPLODT0154
DCPLODT0154
DCPLO 0105

DCPL 0148

19-May-10
10-Sep-10
19-May-10
17-Sep-10
19-May-10
10-Sep-10
6-Mar-10
22-Dec-09
4-Apr-10
1-Jun-10
4-Apr-10
1-Jun-10
4-Apr-10
1-Jun-10
4-Apr-10
24-Mar-10
12-Apr-10

14-Jul-10
16-May-11
17-Jul-10
13-Oct-10

14.43

14-Jul-10

30-Jul-10
DCPLODT0189

25-Jun-10
28-Jul-10
13-Oct-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

28-Sep-10

28-Oct-10

27-Nov-10

24-Aug-10

23-Sep-10

23-Oct-10

12-Dec-10

11-Jan-11

10-Feb-11

29-Aug-10
25-Jul-10
7-Sep-10
12-Nov-10

DCPl 0156

DCPLODT0252

26-May-10

25-Jun-10

25-Jul-10

24-Aug-10

23-Sep-10

23-Oct-10

26-May-10

25-Jun-10

25-Jul-10

24-Aug-10

23-Sep-10

23-Oct-10

26-May-10

25-Jun-10

25-Jul-10

24-Aug-10

23-Sep-10

23-Oct-10

26-May-10

25-Jun-10

25-Jul-10

24-Aug-10

23-Sep-10

23-Oct-10

26-May-10

25-Jun-10

25-Jul-10

24-Aug-10

23-Sep-10

23-Oct-10

26-May-10

25-Jun-10

25-Jul-10

24-Aug-10

23-Sep-10

23-Oct-10

30-Jun-10
7-Sep-10
30-Jun-10
7-Sep-10
30-Jun-10
7-Sep-10
10-Mar-10
7-Sep-10
10-Mar-10
16-Mar-10
10-Mar-10

DCPLODT0252
DCPLODT0252
DCPLODT0252
DCPLODT0252
DCPLODT0096

10-Mar-10
12-Feb-10
30-Jun-10
7-Sep-10
30-Jun-10
7-Sep-10
30-Jun-10

DCPLODT0085-0
DCPLODT0252
DCPLODT0252

30-May-10
1-Sep-10
30-May-10

DCPLODT0248

30-May-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

9-Apr-10

9-May-10

8-Jun-10

8-Jul-10

7-Aug-10

9-Apr-10

9-May-10

8-Jun-10

8-Jul-10

7-Aug-10

9-May-10

8-Jun-10

8-Jul-10

7-Aug-10

3-Feb-10
11-Feb-10

DCPLODT0264
DCPLODT0265
DCPLODT0155

L&T

9-Apr-10
9-Apr-10
15-Jun-10
30-Jul-10

8-Jun-10

9-May-10

8-Jun-10

8-Jul-10

7-Aug-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

30-Jul-10

29-Aug-10

28-Sep-10

28-Oct-10

27-Nov-10

29-Jun-10

29-Jul-10

28-Aug-10

27-Sep-10

27-Oct-10

15-Jun-10

29-Jun-10

29-Jul-10

28-Aug-10

27-Sep-10

27-Oct-10

15-Jun-10

29-Jun-10

29-Jul-10

28-Aug-10

27-Sep-10

27-Oct-10

15-Jun-10

DCPL 0132

14.42

14-Jun-10
17-Sep-10
14-Jun-10
17-Sep-10
16-Apr-11
4-Jun-10
13-Sep-10

JNSTPP

14.41

3-Feb-10

Receive
Date
I/W No.
14-Jul-10

3-Feb-10

Release
Date
DTN No.
14-Jun-10

FLAG

FLAG

FLAG
2nd Submission (Rev. B)

14.40

14.39

3-Feb-10

14.38

5-Jan-10

14.37

20-Mar-10

DCPL 0156
DCPL 0156
DCPL 0156
DCPL 0002
DCPL 0044
DCPL 0044
DCPL 0044
DCPL 0044
DCPL 0044
DCPL 0024
DCPL 0175
DCPL 0023

20-Mar-10

19-Apr-10
28-Jul-10
19-Apr-10
28-Jul-10
19-Apr-10
28-Jul-10
4-Feb-10
23-Oct-09
5-Mar-10
12-Feb-10
5-Mar-10
12-Feb-10
5-Mar-10
12-Feb-10
5-Mar-10
12-Feb-10
13-Mar-10
12-Feb-10
15-May-10
5-Jan-10
14-Aug-10
6-Sep-10
15-May-10
5-Jan-10
14-Sep-10

14.36

14.35

15-Jul-10
20-Mar-10

14.34

14.31

15-Feb-11

14.30

15-Apr-10

L&T

JNSTPP

14.25

15-Apr-10

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

14.24

L&T

15-Apr-10

Receive
Date
I/W No.
DCPL 15-May-10
0148
17-Jul-10
DCPL 15-May-10
0106
5-May-10
DCPL 15-May-10
0109
10-May-10
DCPL 17-Mar-11
0084
7-Apr-10
14-Aug-10

Early Start
LMTG-E0-02023
JEU51963
LMTG-E0-02024
Schematic Diagram of Generator Circuit
JEZ2V684
LMTG-E0-02025
Schematic Diagram of Generator Auxiliaries
JEZ2V685
General Specification of Electrical Control Paneland Cubicle LMTG-E0-02030
(MELCO PORTION)
GAE-KN-E157
LMTG-E0-02031
Specification for Motor Local Control panel
GAE-KN-E401
Outline Drawing of Direct Current Motor for ST Emergency
LMTG-E0-02034
Oil Pump
GAE-KN-E801
LMTG-E0-02035
Outline Drawing of Three Phase Induction Motor for ST
Turning Oil Pump
GAE-KN-E802
LMTG-E0-02036
Outline Drawing of Direct Motor for ST Jacking Oil Pump (B)
GAE-KN-E803
LMTG-E0-02037
Datasheet for Generator & Accessories
GAE-K N-E901
LMTG-E0-02038
Electrical Equipments General Arrangements (EL+0.00M)
JEK79173
LMTG-E0-02039
Electrical Equipments General Arrangements (EL+9.00M)
JEK79174
LMTG-E0-02040
Electrical Equipments General Arrangements (EL+17.00M)
JEK79175
LMTG-E0-02041
Loading Diagram for MELCO Equipments (EL+0.00M,
EL+9.00M, EL+17.00M)
JEK79176
LMTG-E0-02042
Phase Disposition of General Busduct
JEU51974
LMTG-E0-02101
Outline Drawing AVR Cubicle
JEJ63766
Specification & Schemetic Diagram of Brushless Excitation LMTG-E0-02102
JEZ2Z308
System
LMTG-Q0-02201
QAP - Generator
JEVM-8F38-02
LMTG-Q0-02202
Shop Test and Inspection Procedure for Control Panel
JEVM-8F38-11
LMTG-Q0-02203
Shop Test and Inspection Procedure for AVR Cubicle
JEVM-8F38-12
LMTG-E0-02301
Turbine Generator Cooling Water Diagram
A11K933
LMTG-E0-02302
Turbine Generator H2 & CO2 Gas Diagram
A11K934
LMTG-E0-02303
Turbine Generator Seal Oil Diagram
A11K935
LMTG-E0-02304
Turbine Generator Stator Coil Cooling Water Diagram
A11K936
LMTG-E0-02305
Turbine Generator Outline
A11K768
LMTG-E0-02306
Turbine Generator Seal Oil Supply Unit Outline
A11K937
Turbine Generator Stator Coil Cooling Water Supply unit
LMTG-E0-02307
outline
A11K938
LMTG-E0-02308
Turbine Generator H2 Gas Supply Unit Diagram
ASO2382
LMTG-E0-02309
Turbine Generator CO2 Gas Supply Unit Diagram
ASO2383
Turbine Generator H2 Has Pressure / Purity Monitoring Unit LMTG-E0-02310
Outline
ASO2384
LMTG-E0-02311
Turbine Generator H2 Has Drayer Outline
ASO2385
LMTG-E0-02312
Turbine Generator Water Detector Outline
ASO2386
LMTG-E0-02313
Turbine Generator Vapour Extractor Outline
ASO2387
LMTG-E0-02314
Turbine Generator Loop Seal Tank Outline
ASO2388
LMTG-E0-02315
Turbine Generator Terminal and CT Assembly
A11K775
LMTG-E0-02316
Turbine Generator CT Terminal Box & Coduits Arrengement
A11K967
LMTG-E0-02317
Turbine Generator Instrument Wiring Arregement (1 / 6)
A11K769
LMTG-E0-02318
Turbine Generator Instrument Wiring Arregement (2 / 6)
A11K770
LMTG-E0-02319
g Arregement
g
( / 6))
Turbine Generator Instrument Wiring
(3
A11K771
LMTG-E0-02320
Turbine Generator Instrument Wiring Arregement (4 / 6)
A11K772
LMTG-E0-02321
Turbine Generator Instrument Wiring Arregement (5 / 6)
A11K773
LMTG-E0-02322
Turbine Generator Instrument Wiring Arregement (6 / 6)
A11K774
Turbine Generator Auxiliary Equipment Wiring Diagram (1 / LMTG-E0-02323
A11K939
3)
Turbine Generator Auxiliary Equipment Wiring Diagram (2 / LMTG-E0-02324
A11K940
3)
Turbine Generator Auxiliary Equipment Wiring Diagram (3 / LMTG-E0-02325
A11K941
3)
LMTG-E0-02326
Turbine Generator Foundation Conduit Arrengement
AS02549
LMTG-E0-02327
Turbine Generator Foundation Bolt Arrengement
A11K776
LMTG-E0-02328
Turbine Generator Ground Connection Terminal
AS02551
Arrengement
LMTG-E0-02329
Turbine Generator Anchor for Pulling Out Rotor
AS02550
LMTG-E0-02330
Turbine Generator Method of Mounting (1 / 2)
A11K777
LMTG-E0-02331
Turbine Generator Method of Mounting (2 / 2)
A11K778
Turbine Generator Hydragen Gas Temperature Control
LMTG-E0-02332
Valve Outline
AS02389
Turbine Generator Foundation Embedded Materials Layout LMTG-E0-02333
(1 / 4)
A11K942
Turbine Generator Foundation Embedded Materials Layout LMTG-E0-02334
A11K943
((2 / 4))
Turbine Generator Foundation Embedded Materials Layout LMTG-E0-02335
A11K944
(3 / 4)
Assembly Drawing of Generator Bushing CT Terminal Box

Release
Date
DTN No.
DCPLO15-Apr-10
DT0155-B
4-Jun-10
DCPLO15-Apr-10
DT0119
13-Apr-10
DCPLO15-Apr-10
DT0119
13-Apr-10
DCPLO15-Feb-11
DT0096
16-Mar-10
DCPLO15-Jul-10
DT0260
10-Sep-10
DCPLO20-Mar-10
DT0189
17-Jul-10
DCPLO20-Mar-10
DT0189
17-Jul-10
DCPLO20-Mar-10
DT0189
17-Jul-10
JPVLO5-Jan-10
DT0002
2-Oct-09
DCPLO3-Feb-10
DT0063
1-Feb-10
DCPLO3-Feb-10
DT0063
1-Feb-10
DCPLO3-Feb-10
DT0063
1-Feb-10
DCPLO3-Feb-10
DT0063
1-Feb-10
DCPLO11-Feb-10
DT0063
1-Feb-10
DCPLO15-Apr-10
DT0030
22-Dec-09
DCPLO15-Jul-10
DT0224
12-Aug-10
DCPLO15-Apr-10
DT0007
31-Oct-09
DCPLO15-Aug-10
DT0218
9-Aug-10
DCPLO15-Aug-10
DT0218
9-Aug-10
DCPLO13-Mar-10
DT0102
22-Mar-10
DCPLO13-Mar-10
DT0102
22-Mar-10
DCPLO13-Mar-10
DT0155
4-Jun-10
DCPLO13-Mar-10
DT0155
4-Jun-10
DCPLO15-Dec-09
22-Dec-09 DT0030-0
DCPLO1-May-10
DT0138
29-Apr-10
DCPLO1-May-10
DT0138
29-Apr-10
DCPLO1-May-10
DT0138
29-Apr-10
DCPLO1-May-10
DT0126
23-Apr-10
DCPLO1-May-10
DT0126
23-Apr-10
DCPLO1-May-10
DT0126
23-Apr-10
DCPLO1-May-10
DT0126
23-Apr-10
DCPLO1-May-10
DT0126
23-Apr-10
DCPLO1-May-10
DT0126
23-Apr-10
DCPLO27-Mar-10
DT0100
18-Mar-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO27-Mar-10
DT0113
5-Apr-10
DCPLO27-Mar-10
DT0113
5-Apr-10
DCPLO27-Mar-10
DT0113
5 Apr 10
5-Apr-10
DCPLO27-Mar-10
DT0113
5-Apr-10
DCPLO27-Mar-10
DT0113
5-Apr-10
DCPLO27-Mar-10
DT0113
5-Apr-10
1-May-10
1-May-10
1-May-10
DCPLO9-Jan-10
DT0044-0
6-Jan-10
DCPLO9-Jan-10
29-Dec-09 DT0034-0
DCPLO9-Jan-10
DT0044
6-Jan-10
DCPLO9-Jan-10
DT0044
6-Jan-10
DCPLO1-May-10
DT0127
23-Apr-10
DCPLO1-May-10
DT0127
23-Apr-10
DCPLO1-May-10
DT0209
26-Jul-10
DCPLO31-Mar-10
DT0124
20-Apr-10
DCPLO31-Mar-10
DT0124
20-Apr-10
p
DCPLO31-Mar-10
DT0124
20-Apr-10

14.23

Drawing / Doc. No.

1st Submission (Rev. A)

Last Wk
Rcvd
To Rcvd
Next Wk

Description

FLAG

FLAG

FLAG
Subm.
Next Wk
Last Wk
Submited

Sr. No.

Schedule
First
Submission
Date

Category
(A/I/N)

Unit No.

JOB No. T209001

:LT-P0-00003
:4.2
:A
Recd aftr
Long Time

POWER PROJECT MANAGEMENT SERVICES , VADODARA

Last Wk
Rcvd
To Rcvd
Next Wk

LARSEN & TOUBRO LIMITED

15-Jun-10

Page 07 of 12

DOCUMENT NO.
ANNEXURE REV. NO:

C
C

14.115 Turbine Generator Exhaust Piping (2 / 2)


14.116 Turbine Generator Cooling Water Piping (1 / 5)
14.117 Turbine Generator Cooling Water Piping (2 / 5)

14.118 Turbine Generator Cooling Water Piping (3 / 5)

14.119 Turbine Generator Cooling Water Piping (4 / 5)

14.120 Turbine Generator Cooling Water Piping (5 / 5)

14.121 Turbine Generator Gas & Seal Oil Piping (1 / 10)

C
C
C
C
C

14.122 Turbine Generator Gas & Seal Oil Piping (2 / 10)


14.123 Turbine Generator Gas & Seal Oil Piping (3 / 10)
14.124 Turbine Generator Gas & Seal Oil Piping (4 / 10)
14.125 Turbine Generator Gas & Seal Oil Piping (5 / 10)
14.126 Turbine Generator Gas & Seal Oil Piping (6 / 10)

14.127 Turbine Generator Gas & Seal Oil Piping (7 / 10)

14.128 Turbine Generator Gas & Seal Oil Piping (8 / 10)

14.129 Turbine Generator Gas & Seal Oil Piping (9 / 10)

C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C
C

14.130 Turbine Generator Gas & Seal Oil Piping (10 / 10)
14.131 Turbine Generator Gas Feed Piping (1 / 2)
14.132 Turbine Generator Gas Feed Piping (2 / 2)
14.133 Plan of Scaffolding for Turbine Generator Maintenance
14 137
14.137
14.138

Turbine Generator Grout Retainer Arrengement


Embedded Plate Arrengement for Natural Cover Support

A11K947
LMTG-E0-02339
A11K948
LMTG-E0-02340
A11K949
LMTG-E0-02341
A11K950
LMTG-E0-02342
A11K951
LMTG-E0-02343
A11K952
LMTG-E0-02344
A11K953
LMTG-E0-02345
A11K954
LMTG-E0-02346
A11K955
LMTG-E0-02347
A11K956
LMTG-E0-02348
A11K957
LMTG-E0-02349
A11K958
LMTG-E0-02350
A11K959
LMTG-E0-02351
A11K960
LMTG-E0-02352
A11K961
LMTG-E0-02353
A11K962
LMTG-E0-02354
A11K963
LMTG-E0-02355
A11K964
LMTG-E0-02356
A11K965
LMTG-E0-02357
A11K966
LMTG-E0-02361
AS02552
LMTG-E0-02362
AS02553

LMTG-E0-02363
A35E036
LMTG-E0-02601
Outline Dimensions and unit Data sheet of Unit 1 & 2 DC
09JNG723A0B00
motor Starter
Outline Dimensions and Datasheet of Unit 1 & 2 Distribution LMTG-E0-02602
14.161
Board
09JNG723F0B00
LMTG-E0-02605
14.164 General Specification of Unit 1 & 2 Distribution Board
JNM005C682P31
LMTG-E0-02801
14.179 Outline Dimensions of AC Motor for Turning Gear
BC22689
LMTG-E0-02802
14.180 Outline Dimensions of AC Motor for Auxiliary Oil Pump
BC22690
LMTG-E0-02803
14.181 Outline Dimensions of AC Motor for Jacking Oil Pump (A)
BC22691
Outline Dimensions of AC Motor for Main Oil Tank Oil
LMTG-E0-02804
14.182
Transfer Pump
BC22692
Outline Dimensions of AC Motor for Storage Tank Oil
LMTG-E0-02805
14.183
Transfer Pump
BC22693
LMTG-E0-02806
14.184 Outline Dimensions of AC Motor for Polishing Pump
BC22694
LMTG-E0-02807
Outline Dimensions of AC Motor for Main Oil Tank Vapour
14.185
Extractor Fan (A)
BC22695
LMTG-E0-02808
Outline Dimensions of AC Motor for Main Oil Tank Vapour
14.186
Extractor Fan (B)
BC22696
14.139

Turnine Generator Load on Foundation

14.160

15

VDR - Boiler & its Auxiliaries

31-Mar-10

15-Jul-10

15-Jul-10
15-Jul-10
15-Jul-10

I
I
I

15-Jul-10

15-Jul-10

15-Jul-10

15-Jul-10

15-Jul-10
15-Jul-10
15-Jul-10
15-Jul-10
15-Jul-10

I
I
I
I
I

15-Jul-10

15-Jul-10

15-Jul-10

15-Jul-10
15-Jul-10
15-Jul-10
31-Mar-10
9-Jan-10
9-Jan-10

I
I
I
A
I
I

9-Jan-10

16-Mar-10

16-Mar-10

16-Mar-10
20-Mar-10
20-Mar-10
20-Mar-10
20-Mar-10

A
A
A
A
A

20-Mar-10

20-Mar-10

20-Mar-10

20-Mar-10

Information of Boiler Drain to Turbine Atmospheric Flash


Tankk
T

97000
97000-2381-7
2381 7

6-Jan-10
6
Jan 10

15.2

WDC Valve Drain Information

97000-2381-8

6-Jan-10

15.3

Boiler Feed Water Quality

97000-2281

6-Jan-10

15.4

Legend for P&I Diagram

15.4

16-Mar-10

14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
14-Aug-10
30-Apr-10
8-Feb-10
16-May-10
8-Feb-10
16-May-10
8-Feb-10
16-May-10
15-Apr-10

DCPL 0132
DCPL 0132
DCPL 0132

15-Apr-10

16-Mar-10
23-Mar-10
20-Mar-10
5-Jun-10
20-Mar-10
5-Jun-10
20-Mar-10
5-Jun-10
20-Mar-10
18-May-10
20-Mar-10
18-May-10
20-Mar-10
18-May-10
20-Mar-10
18-May-10
20-Mar-10
18-May-10

DCPLODT0104
DCPLODT0157-B
DCPLODT0157-B
DCPLODT0157-B
DCPLODT0145
DCPLODT0145
DCPLODT0145
DCPLODT0145
DCPLODT0145

15-Apr-10
7-Apr-10
19-Apr-10
18-Jun-10
19-Apr-10
18-Jun-10
19-Apr-10
18-Jun-10
19-Apr-10
18-Jun-10
19-Apr-10
18-Jun-10
19-Apr-10
18-Jun-10
19-Apr-10
18-Jun-10
19-Apr-10
18-Jun-10

6-Jan-10
6
6-Jan-10
J 10
6-Jan-10
6-Jan-10
6-Jan-10
6-Jan-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10

DCPLODT0045
DCPLODT0045
DCPLODT0045

DCPL 0086
DCPL 0138
DCPL 0138
DCPL 0138
DCPL 0138
DCPL 0138
DCPL 0138
DCPL 0138
DCPL 0138

L&T

29-Jul-10

13-Sep-10

13-Oct-10

13-Sep-10

13-Oct-10

13-Sep-10

Subm.
Next Wk
Last Wk
Submited

29-Jun-10

Recd aftr
Long Time

Receive
Date
I/W No.
28-Aug-10

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

30-May-10

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

JNSTPP

Release
Date
DTN No.
29-Jul-10

FLAG

FLAG
4th Submission (Rev. D)

As Built

Receipt Date
of Approval

Release
Date
DTN No.
27-Sep-10

Receive
Date
I/W No.
27-Oct-10

28-Aug-10

27-Sep-10

27-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

13-Sep-10

13-Oct-10

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

30-May-10

29-Jun-10

29-Jul-10

28-Aug-10

27-Sep-10

27-Oct-10

JNSTPP

L&T

JNSTPP

L&T

JNSTPP

Release
Date-Unit 1 DTN No
1

15-Jun-10

10-Mar-10
7-Sep-10
10-Mar-10
7-Sep-10
10-Mar-10

DCPLODT02852
DCPLODT0252

9-Apr-10
p

9-May-10
y

8-Jun-10

8-Jul-10

7-Aug-10
g

15-Jun-10

9-Apr-10

9-May-10

8-Jun-10

8-Jul-10

7-Aug-10

15-Jun-10

9-Apr-10

9-May-10

8-Jun-10

8-Jul-10

7-Aug-10

15-Jun-10

15-May-10
17-Sep-10
15-May-10
17-Sep-10
15-May-10
17-Sep-10
19-May-10
19-Jul-10
19-May-10
19-Jul-10
19-May-10
19-Jul-10
19-May-10
19-Jul-10
19-May-10
19-Jul-10
19-May-10
19-Jul-10
19-May-10
19-Jul-10
19-May-10
19-Jul-10

DCPLODT0264
DCPLODT0266
DCPLODT0267
DCPLODT0192
DCPLODT0192
DCPLODT0192
DCPLODT0192
DCPLODT0192
DCPLODT0192
DCPLODT0192
DCPLODT0192

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

18-Jul-10

17-Aug-10

18-Jul-10

17-Aug-10

18-Jul-10

17-Aug-10

18-Jun-10
28-Jul-10
18-Jun-10
28-Jul-10
18-Jun-10
28-Jul-10
18-Jun-10
28-Jul-10
18-Jun-10
28-Jul-10
18-Jun-10
28-Jul-10
18-Jun-10
28-Jul-10
18-Jun-10
28-Jul-10

16-Oct-10

28-Jul-10

16-Oct-10

28-Jul-10

16-Oct-10

28-Jul-10

16-Oct-10

28-Jul-10

DCPLODT0268
DCPLODT0268
DCPLODT0268

17-Aug-10
17-Aug-10

16-Sep-10

16-Oct-10

28-Jul-10

17-Aug-10

16-Sep-10

16-Oct-10

28-Jul-10

DCPLODT0267
DCPLODT0267

17-Aug-10

16-Sep-10

16-Oct-10

28-Jul-10

17-Aug-10

16-Sep-10

16-Oct-10

28-Jul-10

5-Feb-10

13-May-10

5-Feb-10

13-May-10

5-Feb-10

13-May-10

18-Jul-10
17-Sep-10
18-Jul-10
17-Sep-10
18-Jul-10
17-Sep-10
18-Jul-10
17-Sep-10
18-Jul-10
17-Sep-10

DCPLODT0268
DCPLODT0268
DCPLODT0268

12-Oct-10

16-Sep-10
17-Sep-10
16-Sep-10
17-Sep-10
16-Sep-10
17-Sep-10
16-Sep-10

DCPL 0155
DCPL 0155
DCPL 0155
DCPL 0155
DCPL 0155
DCPL 0155
DCPL 0155
DCPL 0155

168.4

15.1

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

Receive
Date
I/W No.
29-Jun-10

3rd Submission (Rev. C)

A11K946
LMTG-E0-02338

L&T
I

Release
Date
DTN No.
30-May-10

FLAG

FLAG

FLAG
2nd Submission (Rev. B)

14.114 Turbine Generator Exhaust Piping (1 / 2)

LMTG-E0-02337

31-Mar-10

14.113 Turbine Generator Foundation Embedded Conduit Layout

A11K945

Receive
Date
I/W No.
DCPL 30-Apr-10
0150
17-Jul-10
30-Apr-10

LMTG-E0-02336

Release
Date
DTN No.
DCPLO31-Mar-10
DT0124
20-Apr-10
DCPLO31-Mar-10
DT0124
20-Apr-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO15-Jul-10
DT0201
20-Jul-10
DCPLO31-Mar-10
DT0201
20-Jul-10
DCPLO9-Jan-10
DT0044-0
6-Jan-10
DCPLO9-Jan-10
DT0044-0
6-Jan-10
DCPLO9-Jan-10
DT0044-0
6-Jan-10
16-Mar-10

Early Start
Turbine Generator Foundation Embedded Materials Layout
(4 / 4)

1st Submission (Rev. A)

Last Wk
Rcvd
To Rcvd
Next Wk

14.112

Drawing / Doc. No.

Subm.
Next Wk
Last Wk
Submited

Description

FLAG

FLAG

FLAG

Sr. No.

Schedule
First
Submission
Date

Category
(A/I/N)

Unit No.

JOB No. T209001

:LT-P0-00003
:4.2
:A
Recd aftr
Long Time

POWER PROJECT MANAGEMENT SERVICES , VADODARA

Last Wk
Rcvd
To Rcvd
Next Wk

LARSEN & TOUBRO LIMITED

97000-2110

28-Jun-10

P&ID - Main Steam & Reheat Steam

97000-2111-1

28-Jun-10

15.4

P&ID - Chemical Injection System

97000-2135-1

28-Jun-10

15.4

P&ID - Oxygen Injection System

97000-2135-1-2

28-Jun-10

15.4

P&ID - Auxiliary System

97000-2112-1

28-Jun-10

15.4

P&ID - Start-up System

97000-2111-2

28-Jun-10

15.4

P&ID - SAH System

97000-2112-2

28-Jun-10

Sch.
A t
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10

LMB-531
Rev - 1
LMB-531
Rev - 1
LMB-531
Rev - 0
LMB-531
Rev - 0
LMB-531
Rev - 0
LMB-531
Rev - 1
LMB-531
Rev - 0

28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10
28-Jun-10

Page 08 of 12

DOCUMENT NO.
ANNEXURE REV. NO:

Early Start

L&T

16.1.1.3 QAP - HP Heater

LT-QO-03001

15-Oct-09

16.1.1.4 QAP - LP Heater

LT-QO-03002

15-Oct-09

LT-M0-03059

14-Apr-10

LT-M0-03060

14-Feb-10

LT-M0-03062

30-Jan-10

30-Jan-10

LT-M0-03070

12-Jan-10

LT-M0-03071

30-Jan-10

LT-M0-03072

14-Apr-10

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

DCPLODT0114

12-Apr-10
23-Apr-10
30-Apr-10

DCPL 0091

14-Feb-10
15-Apr-10

DCPLODT0122

16-Mar-10
1-Jun-10

DCPL 0121

30-Jan-10
22-Jan-10
14-Apr-10

DCPLODT0071

1-Mar-10
14-May-10
14-May-10

DCPL 0114

14-Feb-10
15-Apr-10

DCPLODT0122

16-Mar-10
1-Jun-10

DCPL 0121

30-Jan-10
22-Jan-10
14-Apr-10

DCPLODT0071

1-Mar-10
14-May-10
14-May-10

DCPL 0114

14-Feb-10
15-Apr-10

DCPLODT0122

16-Mar-10
1-Jun-10

DCPL 0121

12-Jan-10
4-Jan-10
30-Jan-10
22-Jan-10
14-Apr-10

DCPLODT0043
DCPLODT0071-0

11-Feb-10
15-Mar-10
1-Mar-10
24-May-10
14-May-10

DCPL 0068
DCPL 0118

14-Feb-10
15-Apr-10

DCPLODT0122

16-Mar-10
1-Jun-10

DCPL 0121

30-Jan-10
22-Jan-10
14-Apr-10

DCPLODT0071+0

1-Mar-10
24-May-10
14-May-10

DCPL 0118

14-Feb-10
15-Apr-10

DCPLODT0122

16-Mar-10
1-Jun-10

DCPL 0121

Sch.
Act.
Sch.
Act.
Sch.
Act.

12-Jan-10
4-Jan-10
30-Jan-10
22-Jan-10
14-Apr-10

DCPLODT0043
DCPLODT0071-0

11-Feb-10
24-Mar-10
1-Mar-10
24-May-10
14-May-10

DCPL 0073
DCPL 0118

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
A t
Act.
Sch.
Act.

12-Jan-10
4-Jan-10
25-Dec-09
4-Jan-10
15-Oct-09
15-Oct-09
30-Jan-10
22-Jan-10
30-Jan-10
22-Jan-10
12-Jan-10
4-Jan-10
15-Apr-10
15-Apr-10
15-Apr-10
15-Apr-10
15-Apr-10
15
15-Apr-10
A 10
15-Apr-10
15-Apr-10

DCPLODT0043
DCPLODT0043
DCPLODT0004
DCPLODT0071
DCPLODT0071
DCPLODT0043-0
DCPLODT0122-0
DCPLODT0122-0
DCPLODT0122-0
DT0122
0
DCPLODT0122-0

11-Feb-10
4-Mar-10
24-Jan-10
25-Aug-10
14-Nov-09
6-Nov-09
1-Mar-10
17-May-10
1-Mar-10
17-May-10
11-Feb-10

DCPL 0060
DCPl 0166
DCPL 0003
DCPL 0115
DCPL 0115

15-May-10
15-Jun-10
15-May-10
15-Jun-10
15-May-10
11-Jun-10
11 J 10
15-May-10
11-Jun-10

DCPL 0130
DCPL 0130
DCPL 0128
DCPL 0128

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

15-May-10
20-Aug-10
15-Apr-10
25-May-10
15-Apr-10
25-May-10
15-Apr-10
25-May-10
15-Apr-10
25-May-10
15-Apr-10
25-May-10
15-Apr-10
25-May-10
15-Apr-10
25-May-10
20-Sep-10
20-Sep-10
20-Sep-10
20-Sep-10
20-Sep-10
20-Sep-10

DCPLODT0237
DCPLODT0150
DCPLODT0150
DCPLODT0150
DCPLODT0150
DCPLODT0150
DCPLODT0150
DCPLODT0150
DCPLODT0272
DCPLODT0272
DCPLODT0272

12-Jan-10
1 Feb 10
1-Feb-10
30-Jan-10
10-May-10

DCPLODT0072
DCPLODT0139-1

Sch.
Act.
Sch.
Act.
Sch.
Act.

14-Mar-10

13-Apr-10

13-May-10

5-Dec-10

12-Feb-10

14-Mar-10

13-Apr-10

13-May-10

5-Dec-10

12-May-10

11-Jun-10

23-Apr-10

29-Jun-10

11-Jul-10
18-Sep-10
29-Jul-10

10-Aug-10

30-May-10

28-Aug-10

13-Jul-10

15-Apr-10

15-May-10

12-Aug-10
14-Jul-10
14-Jun-10

31-Mar-10

30-Apr-10

30-May-10

29-Jun-10

13-Jul-10

12-Aug-10

11-Sep-10

15-May-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

30-Apr-10

30-May-10

29-Jun-10

29-Jul-10

28-Aug-10

13-Jul-10

12-Aug-10

11-Sep-10

11-Oct-10

10-Nov-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

11-Jul-10
18-Sep-10
29-Jul-10

10-Aug-10

28-Aug-10

DCPLODT0180

11-Sep-10

DCPLODT0273

13-Jun-10

13-Jun-10
14-Jul-10
15-Apr-10

DCPLODT0180

31-Mar-10

Sch.
Act.
Sch.
Act.
Sch.
Act.

16.1.5.4 Safety Valve Sizing Calculation

LT-M0-03073

14-Feb-10

LT-M0-03075

30-Jan-10

13-Jun-10
14-Jul-10
15-Apr-10

DCPLODT0181

13-Mar-10
9-Apr-10
31-Mar-10

DCPLODT0114

13-Jun-10
14-Jul-10
15-Apr-10

DCPLODT0181

15-May-10

14-Jul-10

29-Jun-10

13-Jul-10

11-Jun-10

30-May-10

12-May-10

30-Apr-10

DCPL 0091

12-Apr-10

11-Oct-10

10-Nov-10

13-Aug-10

12-Sep-10

29-Jul-10

28-Aug-10

11-Oct-10

10-Nov-10

DCPLODT0273

11-Sep-10

11-Oct-10

10-Nov-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

30-Apr-10

30-May-10

29-Jun-10

29-Jul-10

28-Aug-10

13-Jul-10

12-Aug-10

11-Sep-10

11-Oct-10

10-Nov-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

10-Aug-10

28-Aug-10

12-Aug-10

15-May-10

(Including Sectional View & Internal Details)

16.1.5.3 Complete Mechanical Design Calculation

GA Drawing for LPH-4

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

23-Apr-10

14-Feb-10

LT-M0-03079

12-Jan-10

DCPLODT0179

13-Mar-10
9-Apr-10
31-Mar-10

DCPLODT0114

13-Jun-10
14-Jul-10

DCPLODT0179

13-Mar-10
18-Feb-10
23-Feb-10

DCPLODT0086

14-Dec-09
23-Nov-09
31-Mar-10

DCPLODT0017

14-Apr-10

LT-M0-03077

13-Jun-10
14-Jul-10
14 J l 10
15-Apr-10

LT-M0-03076

16.1.6.3 Safety Valve Sizing Calculation

31-Mar-10

16.1.6.2 Complete Mechanical Design Calculation

Sch.
Act.
Sch.
A
Act.
Sch.
Act.

GA Drawing for LPH-3


(Including Sectional View & Internal Details)

LP Heater 3

15-May-10

VDR - Condenser

LT-M0-03080

30-Jan-10

LT-M0-03081

14-Apr-10

13-Jul-10

11-Sep-10

11-Oct-10

12-Aug-10

12-May-10
9-Apr-10
24-Apr-10

DCPLODT0114

12-Feb-10
18-Sep-10
30-May-10

DCPLODT0273

11-Jul-10
18-Sep-10
29-Jul-10

29-Jun-10

11-Jun-10

30-May-10

DCPL 0091

(Including Sectional View & Internal Details)

12-May-10

30-Apr-10

16.1.7.3 Complete Mechanical Design Calculation

12-Apr-10

16.1.7.2

GA Drawing for Duplex LP Heater

Duplex Haeter

16.1.7.1 Technical Datasheet for Duplex Heaters

DCPLODT0273

23-Apr-10

10-Nov-10

596.0

15-Oct-09

16.2.1.4 GA Drawing of Surface Condenser - 1

LT-M0-03000

30-Jan-10

16.2.1.5 GA Drawing of Surface Condenser - 2

LT-M0-03001

30-Jan-10

16.2.1.6 Foundation Loading Data

LT-M0-03003

12-Jan-10

16.2.1.7 Standpipe Detail Drawing for condenser-1

LT-M0-03004

15-Apr-10

16.2.1.8 Standpipe Detail Drawing for condenser-2

LT-M0-03005

15-Apr-10

16.2.1.9 Name Plate (condenser-1)


(condenser 1)

LT-M0-03006
LT
M0 03006

15-Apr-10
15
Apr 10

C 16.2.1.10 Name Plate (condenser-2)

LT-M0-03007

15-Apr-10

LT-M0-03015

15-May-10

13-Jan-10
5-Dec-09
30-Apr-10

DCPL 0009

11-Jun-10
23-Apr-10
24-May-10

DCPL 0091

LT-QO-03000

25-Mar-10

16.2.1.3 QAP - Condenser

12-Apr-10

25-Dec-09

12-Jan-10

LT-M0-03002

LT-M0-03000-DS

16.2.1.2 Condenser Performance Curves

16.2.1.1 Filled - in - Datasheet

Engg. Drawing & Documents

11-Jul-10
18-Sep-10
23-Jun-10

DCPLODT0273

10-Aug-10

23-Jul-10

14-Mar-10

13-Apr-10

13-May-10

29-Jun-10

29-Jul-10

28-Aug-10

1
1

23-Apr-10

5-Dec-10

31-Mar-10

30-Apr-10

30-May-10

29-Jun-10

29-Jul-10

28-Aug-10

13-Mar-10

12-Apr-10

12-May-10

11-Jun-10

11-Jul-10

10-Aug-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

11-Jun-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

11-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

11-Dec-10

14-Jun-10

14-Jul-10

13-Aug-10
20-Aug-10
13-Aug-10

Manufacturing Documents

16.2.2.8 Radiographic Test Procedure

LT-M0-03019

15-Apr-10

16.2.2.9 Magnetic Test Procedure

LT-M0-03020

15-Apr-10

C 16.2.2.10 Dye Penetrant Test Procedure

LT-M0-03021

15-Apr-10

C 16.2.2.11 Post weld Heat Treatment Procedure

LT-M0-03022

15-Apr-10

C 16.2.2.12 Tube Expansion Procedure

LT-M0-03023

15-Apr-10

C 16.2.2.13 Painting Scheme for Condenser

LT-M0-03025

20-Sep-10

C 16.2.2.14 Painting Scheme for Deaerator

LT-M0-03117

20-Sep-10

C 16.2.2.15 Painting Scheme for Feed Water Heaters

LT-M0-03094

20-Sep-10

12-Jan-10

VDR - Deaerator

15-May-10
6-Jul-10
15-May-10
6-Jul-10
15-May-10
6-Jul-10
15-May-10
6-Jul-10
15-May-10
6-Jul-10
15-May-10
6-Jul-10
15-May-10
6-Jul-10
20-Oct-10

14-Jun-10
20-Aug-10
14-Jun-10

DCPLODT0237

14-Jul-10

DCPLODT0237

12-Sep-10

15-Apr-10

15-Apr-10

LT-M0-03018

12-Sep-10

12-Oct-10

11-Nov-10

12-Oct-10

11-Nov-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

6-Jul-10

14-Jun-10

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

6-Jul-10

14-Jun-10
20-Aug-10
14-Jun-10
18-Sep-10

DCPLODT0237
DCPLODT0273

14-Jul-10

LT-M0-03016

16.2.2.7 Hydrostatic test Procedure

DCPL 0144
DCPL 0144
DCPL 0144
DCPL 0144
DCPL 0144
DCPL 0144
DCPL 0144

16.2.2.5 Procedure for Surface Preparation & Painting

14-Jun-10

16.2.2.4 WPS & PQR

14-Jul-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

13-Aug-10

12-Sep-10

12-Oct-10

11-Nov-10

20-Oct-10

Extra

Extra

20-Oct-10

Extra

254.0

16.3.1.2 GA drawing of Deaerator

LT-M0-03100

30-Jan-10

Sch.
Act
Act.
Sch.
Act.

11-Feb-10
3 Apr 10
3-Apr-10
1-Mar-10
9-Jul-10

DCPL 0078
DCPL 0146

13-Mar-10
2 Feb 10
2-Feb-10
31-Mar-10

DCPLODT0074

12-Apr-10
3 Apr 10
3-Apr-10
30-Apr-10

DCPL 0078

12-May-10
10 May 10
10-May-10
30-May-10

DCPLODT0139

11-Jun-10
15 Jun 10
15-Jun-10
29-Jun-10

DCPL 0131

11-Jul-10
30-Aug-10
30
Aug 10
29-Jul-10

DCPLODT0245

10-Aug-10
28-Aug-10

LT-M0-03100-DS

Engg. Drawing & Documents

16.3.1.1 Filled-in-Datasheet with Technical schedule

13-Mar-10
9-Apr-10
31-Mar-10

12-Feb-10

LP Haeter 4

16.1.5.2

DCPL 0073
DCPL 0114

14-Feb-10

16.3
16.3.1

11-Feb-10
24-Mar-10
1-Mar-10
14-May-10
14-May-10

14-Apr-10

LT-M0-03068

DCPLODT0043
DCPLODT0071

LT-M0-03067

16.1.4.3 Safety Valve Sizing Calculation

16.1.5.1 Technical Datasheet for LPH-4

12-Jan-10
4-Jan-10
30-Jan-10
22-Jan-10
14-Apr-10

(Including Sectional View & Internal Details)

16.1.4.2 Complete Mechanical Design Calculation

16.2.2

JNSTPP

Receipt Date
of Approval

Release
Date-Unit 1 DTN No

Hp Heater 6A / 6B
GA Drawing for HPH-6A/6B.

Sch.
Act.
Sch.
Act.
Sch.
Act
Act.
Sch.
Act.

LT-M0-03066

16.2
16.2.1

DCPL 0009
DCPL 0009

I
I

13-Jan-10
5-Dec-09
13-Jan-10
5-Dec-09

14-Apr-10
14-Feb-10

16.1.7

DCPLODT0017
DCPLODT0017

(Including Sectional View & Internal Details)

LT-M0-03064

16.1.6.1

14-Dec-09
23-Nov-09
14-Dec-09
23-Nov-09

GA Drawing for HPH-7A/7B.

LT-M0-03063

Receive
Date
I/W No.

Hp Heater 7A / 7B

16.1.3.3 Safety Valve Sizing Calculation

16.1.6

DCPL 0003
DCPL 0003

30-Jan-10

16.1.3.2 Complete Mechanical Design Calculation

L&T

12-Jan-10

16.1.5

14-Nov-09
6-Nov-09
14-Nov-09
6-Nov-09

(Including Sectional View & Internal Details)

LT-M0-03057
LT-M0-03058

16.1.4

DCPLODT0004
DCPLODT0004

GA Drawing for HPH-8A/8B.

16.1.2.4 Safety Valve Sizing Calculation

16.1.4.1

JNSTPP

Release
Date
DTN No.

As Built

16.1.2.3 Complete Mechanical Design Calculation

C
C
C
C
C
C

L&T

Receive
Date
I/W No.

FLAG
4th Submission (Rev. D)

16.1.3.1

15-Oct-09
15-Oct-09
15-Oct-09
15-Oct-09

16.1.2.2

Sch.
Act.
Sch.
Act.

16.1.2.1 Technical Datasheet for HPH-8A/8B

16.1.3

JNSTPP

Release
Date
DTN No.

FLAG

HP Heater 8A / 8B

L&T

Receive
Date
I/W No.

3rd Submission (Rev. C)

General documents

16.1.2

JNSTPP

Release
Date
DTN No.

FLAG

FLAG

FLAG
2nd Submission (Rev. B)

1204.9
355.0

16.1
16.1.1

VDR - HED Items


VDR - Heaters

Receive
Date
I/W No.

16

Release
Date
DTN No.

Recd aftr
Long Time

Drawing / Doc. No.

1st Submission (Rev. A)

Last Wk
Rcvd
To Rcvd
Next Wk

Description

FLAG

FLAG

FLAG
Subm.
Next Wk
Last Wk
Submited

Sr. No.

Schedule
First
Submission
Date

Category
(A/I/N)

Unit No.

JOB No. T209001

:LT-P0-00003
:4.2
:A
Recd aftr
Long Time

POWER PROJECT MANAGEMENT SERVICES , VADODARA

Last Wk
Rcvd
To Rcvd
Next Wk

LARSEN & TOUBRO LIMITED

1
1

Page 09 of 12

DOCUMENT NO.
ANNEXURE REV. NO:

VDR - Boiler Feed Pump (TD & MD)


Motor Driven Boiler Feed Pump

399.7

17.1
17.1.3

Complete Group General Arrnagment drawing

FPD-C0-03305

Complete Group Pump Datasheet

FPD-M0-03311

1-Sep-10

1-Sep-10

17.1.15 Complete Group P&ID

FPD-M0-03317

1-Sep-10

17 1 76 Motor Sizing Calculation


17.1.76

FPD-M0-03466

5-Sep-10

FPD-M0-03372

1-Sep-10

25Jun10

18

VDR - Steam Turbine Drive

469.0

19

VDR - EOT Cranes


VDR - EOT Crane for TG Building

10.2
18.4

Datasheetof115/15TTGHallEOTCrane(DoubleGirder)
MechanismSizingCalculationfor115/15TTGHallEOTcranes

AILM003201
AILM003203

25Jun10

19.4

Generalarrangementfor115/15TTGHallEOTcrane

AILM003204

27Jun10

19.5

Crabsubassemblyfor115/15TTGHallEOTcrane

AILM003205

27Jun10

GantryRailinstallationfor115/15TTGHallEOTcranes

AILM003206

15Jul10

19.7

GeneralarrangementforPVCshroudedconductortypeDSLfor
115/15TTGHallEOTcrane

AILM003207

15Jul10

19.8

115Tmainhookblockassembly

AILM003208

15Jul10

19.9

15TAuxHookBlockAssembly

AILM003209

15Jul10

19.10
19 10

LTDrivewheelassembly

AILM003210

15Jul10
l

19.11

LTidlewheelassembly

AILM003211

15Jul10

19.12

CTDrivewheelassembly

AILM003212

15Jul10

C
C

19.13
19.14

19.15

19.16

19.17

C
C
C
C
C
C

19.18
19.19
19.20
19.21
19.22

CTidlewheelassembly
LongtravelMachineryAssemblyfor115/15TTGHallEOTcrane
Electricalequpmentlayoutincabinfor115/15TTGHallEOT
crane
Schematiccircuitdiagramofprotectivepanelandlightingcircuit
for115/15TTGHallcrane
SchematiccircuitdiagramofMainhoistpanelfor115/15T
TGHallcrane
SchematiccircuitdiagramofAux.hoistpanelfor115/15TTGHall
crane
SchematiccircuitdiagramofCrossTraverseandMicroCross
Traversepanel&BOMfor115/15TTGHallcrane
SchematiccircuitdiagramofLongTraversepanelforfor115/15
TTGHallcrane
BillofmaterialforMain,Aux.Hoist,CTcircuit,LTcircuitand
main(Pro)circuitfor115/15TTGHall
G.A.drawingofProtectivepanel&transformerenclosurefor
115/15TTGHallcrane

AILM003213
AILM003214

15Jul10
15Jul10

I
I

AILM003215

27Jun10

AILE003216

27Jun10

AILE003217

27Jun10

AILE003218
AILE003219
AILE003220
AILE003221
AILE003222

27Jun10
27Jun10
27Jun10
27Jun10
27Jun10

I
I
I
I
I

19.23

G.A.ofMainhoistpanelfor115/15TTGHallcrane

AILE003223

27Jun10

19.24

G.A.ofAux.hoistpanelfor115/15TTGHallcrane

AILE003224

27Jun10

19.25

G.A. of Cross Traverse panel for 115/15 T TGHall crane


G.A.ofCrossTraversepanelfor115/15TTGHallcrane

AILE003225

27Jun10

C
C

19.26
19.27

G.A.ofLongTraversepanelfor115/15TTGHallcrane
CableSchedulefor115/15TTGHallcrane

AILE003226
AILE003227

27Jun10
15Jul10

I
I

19.28

Cranecontrlolwriteup

AILE003228

27Jun10

19.29

Cablesizecalculationfor115/15TTGHallcrane

AILE003229

27Jun10

19.30

Cranelubrication

AILM003230

15Jul10

19.31

Structuralcalculationsfor115/15TTGHallcrane

AILM003231

15Jul10

19.34

MakeofBoughtOutItemList

AILM003234

15Jul10

19.35

Electricalfeederdiagram

AILM003235

27Jun10

19.36

Earthingdetails

AILM003236

19.44

DSLSizingCalculationfor115/15TTGHallEOTCrane

VDR - EOT Crane for BFP


C

19.1

Datasheetof40/10TTGHallEOTCrane(DoubleGirder)

AILM003243

15Jul10

13Aug10

AILM003251

28-Jul-10

19.3

MechanismSizingCalculationfor40/10TTGHallEOTcranes

AILM003253

28-Jul-10

19.4

Generalarrangementfor40/10TTGHallEOTcrane

AILM003254

26-Jul-10

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

Last Wk
Rcvd
To Rcvd
Next Wk

13-Apr-10

13-May-10

L&T

JNSTPP

Release
Date-Unit 1 DTN No
1

30-Nov-10

30-Dec-10

29-Jan-11

28-Feb-11

30-Mar-11

30-Nov-10

30-Dec-10

29-Jan-11

28-Feb-11

30-Mar-11

31-Oct-10

30-Nov-10

30-Dec-10

29-Jan-11

28-Feb-11

30-Mar-11

4-Nov-10

4-Dec-10

3-Jan-11

2-Feb-11

4-Mar-11

3-Apr-11

5-Dec-10

19.5

Crabsubassemblyfor40/10TTGHallEOTcrane

19.7

GeneralarrangementforPVCshroudedconductortypeDSLfor
G
l
t f PVC h d d
d t t
DSL f
40/10TTGHallEOTcrane

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

25-Jun-10
25-Jun-10
27-Jun-10
27-Jun-10

1-Oct-10
1-Oct-10
15-Sep-10
1-Oct-10

DCPL 0180

25-Jul-10
DCPLODT0186
DCPLODT0190
DCPLODT0190

31-Oct-10

30-Nov-10

30-Dec-10

29-Jan-11

28-Feb-11

30-Mar-11

31-Oct-10

30-Nov-10

30-Dec-10

29-Jan-11

28-Feb-11

30-Mar-11

31-Oct-10

30-Nov-10

30-Dec-10

29-Jan-11

28-Feb-11

30-Mar-11

22-Dec-10

21-Jan-11

22-Dec-10

21-Jan-11

24-Aug-10
16-Jul-10
24-Aug-10
16-Jul-10
26-Aug-10

25-Jul-10
27-Jul-10
27-Jul-10

26-Aug-10

15-Jul-10

14-Aug-10

13-Sep-10
30-Aug-10
13-Sep-10
18-Aug-10
13-Sep-10
30-Aug-10
13-Sep-10
30-Aug-10
13-Sep-10
30-Aug-10
13-Sep-10
30-Aug-10
13-Sep-10
30-Aug-10
13-Sep-10
30-Aug-10
13-Sep-10
30-Aug-10
26-Aug-10
18-Aug-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
26-Aug-10
16-Jul-10
13-Sep-10
20-Jul-10
26-Aug-10
20-Jul-10
26-Aug-10
16-Jul-10
13-Sep-10
30-Aug-10
13-Sep-10

15-Jul-10

14-Aug-10

15-Jul-10

14-Aug-10

15-Jul-10

14-Aug-10

15-Jul-10

14-Aug-10

15-Jul-10

14-Aug-10

15-Jul-10

14-Aug-10

15-Jul-10

14-Aug-10

15-Jul-10

14-Aug-10

27-Jun-10

27-Jul-10

27-Jun-10

27-Jul-10

27-Jun-10

27-Jul-10

27-Jun-10

27-Jul-10

27-Jun-10

27-Jul-10

27-Jun-10

27-Jul-10

27-Jun-10

27-Jul-10

27-Jun-10
27-Jun-10
27-Jun-10
27-Jun-10
27-Jun-10

DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT018
DT0185
DCPLODT0185

27-Jul-10
27-Jul-10
27-Jul-10
27-Jul-10
27-Jul-10

15-Jul-10

14-Aug-10

27-Jun-10

27-Jul-10

27-Jun-10

DCPLODT0186

15-Jul-10
15-Jul-10
17-Aug-10
15-Jul-10

DCPLODT0231

27-Jun-10

DCPLODT0186
DCPLODT0203

15-Jul-10

27-Jul-10
14-Aug-10

13-Aug-10

14-Aug-10
14-Aug-10

13-Sep-10

27-Jul-10

26-Aug-10
16-Jul-10
13-Sep-10
20-Jul-10
12-Oct-10
12-Aug-10

14-Aug-10
12-Sep-10

DCPLODT0185
DCPLODT0186

23-Sep-10
10-Aug-10
23-Sep-10
15-Sep-10
25-Sep-10

DCPL 0164
DCPL 0182

25-Sep-10
DCPLODT0247
DCPLO DT0234
DCPLODT0247
DCPLODT0247
DCPLODT0247
DCPLODT0247
DCPLODT0247
DCPLODT0247
DCPLODT0247
DCPLODT0234
DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT0185
DCPLODT018
DT0185
DCPLODT0185
DCPLODT0203
DCPLODT0203
DCPLODT0186
DCPLODT0247

DCPLODT0186
DCPLODT0203
DCPLODT0227

13-Oct-10
13-Oct-10
15-Sep-10
13-Oct-10

DCPl 0177

13-Oct-10
13-Oct-10
13-Oct-10
13-Oct-10
13-Oct-10
13-Oct-10
25-Sep-10
15-Sep-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
13-Oct-10
3-Aug-10
25-Sep-10
3-Aug-10
25-Sep-10
3-Aug-10
13-Oct-10

23-Oct-10
17-Aug-10
23-Oct-10

DCPLODT0231

25-Oct-10
17-Jul-10
25-Oct-10
17-Jul-10
12-Nov-10

DCPLODT0190
DCPLODT0190

DCPL 0164
DCPL 0164

24-Dec-10
7-Sep-10
24-Dec-10
7-Sep-10
11-Jan-11

DCPLODT0251
DCPLODT0251

23-Jan-11
23-Jan-11
10-Feb-11

12-Dec-10

11-Jan-11

10-Feb-11

12-Dec-10

11-Jan-11

10-Feb-11

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

12-Nov-10

12-Dec-10

11-Jan-11

10-Feb-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

24-Dec-10

23-Jan-11

3-Aug-10

11-Jan-11

10-Feb-11

3-Aug-10

24-Dec-10

23-Jan-11

25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
12-Nov-10
12-Aug-10
25-Oct-10
12-Aug-10
25-Oct-10
12-Aug-10
12-Nov-10
12-Nov-10

13-Oct-10

12-Nov-10
12-Aug-10
25-Oct-10
12-Aug-10
12-Nov-10
12-Aug-10
11-Dec-10

DCPL 0161
DCPL 0162

24-Nov-10
10-Aug-10
24-Nov-10
10-Aug-10
12-Dec-10

12-Nov-10

13-Oct-10

25-Sep-10
3-Aug-10
13-Oct-10
3-Aug-10
11-Nov-10

DCPL 0179

12-Nov-10

25-Oct-10

DCPL 0177
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0160
DCPL 0162
DCPL 0160
DCPL 0161

22-Nov-10
15-Sep-10
22-Nov-10

24-Nov-10
DCPLODT0225
DCPLODT0225
DCPLODT0225
DCPLODT0225
DCPLODT0226
DCPLODT0226
DCPLODT0226
DCPLODT0226
DCPLODT0226
DCPLODT0226
DCPLODT0226
DCPLODT0226
DCPLODT0226
DCPLODT0226

24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
12-Dec-10
25-Aug-10
24-Nov-10
25-Aug-10
24-Nov-10
25-Aug-10
12-Dec-10

DCPl 0165
DCPl 0165
DCPl 0165
DCPl 0165
DCPl 0165
DCPL 0165
DCPl 0165
DCPl 0165
DCPl 0165
DCPl 0165
016
DCPl 0165
DCPl 0165
DCPl 0165
DCPl 0165

12-Dec-10
DCPLODT0227
DCPLODT0227
DCPLODT0227

12-Dec-10
25-Aug-10
24-Nov-10
25-Aug-10
12-Dec-10
26-Aug-10
10-Jan-11

DCPl 0165
DCPL 0165
DCPl 0165

24-Dec-10

23-Jan-11

11-Jan-11

10-Feb-11

11-Jan-11

10-Feb-11

11-Jan-11

10-Feb-11

24-Dec-10

23-Jan-11

11-Jan-11

10-Feb-11

9-Feb-11

11-Mar-11

15-Sep-10

3-Aug-10

8.7

14-Mar-10

JNSTPP

Receipt Date
of Approval

Receive
Date
I/W No.
10-Aug-10

1-Sep-10

19.6

12-Feb-10

As Built

Release
Date
DTN No.
11-Jul-10

1-Sep-10

FPD-M0-03311

Receive
Date
I/W No.
11-Jun-10

FLAG
4th Submission (Rev. D)

31-Oct-10

FPD-M0-03384

17.2.69 Complete Group Pump Datasheet

19.3

Release
Date
DTN No.
12-May-10

FLAG

31-Oct-10

17.2.14 Complete Group P&ID

DCPL 0009

Complete Group General Arrnagment drawing

19.1

L&T

3rd Submission (Rev. C)

Turbine Driven Boiler Feed Pump

JNSTPP

Subm.
Next Wk
Last Wk
Submited

DCPLODT0235
DCPLODT0235
DCPLODT0240

13-Jan-10
5-Dec-09

DCPLODT0017

Recd aftr
Long Time

1-Sep-10
23-Aug-10
1-Sep-10
23-Aug-10
1-Sep-10
23-Aug-10

14-Dec-09
23-Nov-09

Last Wk
Rcvd
To Rcvd
Next Wk

Sch.
Act.
Sch.
Act.
Sch.
Act.

Receive
Date
I/W No.
12-Apr-10

17.2.3

1-Oct-10
15-Sep-10
5-Oct-10

DCPL 0180

Release
Date
DTN No.
13-Mar-10

FLAG

FLAG

FLAG
2nd Submission (Rev. B)

1-Oct-10

17.2

1-Oct-10

Subm.
Next Wk
Last Wk
Submited

DCPLODT0235
DCPLODT0240
DCPLODT0235
DCPLODT0240

L&T

1-Sep-10
23-Aug-10
1-Sep-10
23-Aug-10
1-Sep-10
23-Aug-10
5-Sep-10
23-Aug-10

17.1.9

JNSTPP

15-Oct-09

Recd aftr
Long Time

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

L&T
I

AILM003255
AILM003257

26-Jul-10
9-Aug-10

I
I

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.

28-Jul-10
17-Aug-10
28-Jul-10
13-Aug-10
26-Jul-10
23-Aug-10
26-Jul-10
23-Aug-10
9 Aug 10
9-Aug-10
27-Aug-10

DCPLODT0231
DCPLODT0228
DCPLODT0234
DCPLODT0234
DCPLO
DCPLODT0242

27-Aug-10
15-Sep-10
27-Aug-10

DCPL 0179

17
C

LT-QO-03003

12-Jan-10

16.3.1.6 QAP - Deaerator

Early Start
LT-M0-03101

Receive
Date
I/W No.
DCPL 11-Feb-10
0078
3-Apr-10
DCPL 14-Nov-09
0003
6-Nov-09

Sch.
Act.
Sch.
Act.

Release
Date
DTN No.
DCPLO12-Jan-10
DT0074
2-Feb-10
DCPLO15-Oct-09
DT0004
15-Oct-09

16.3.1.3 Foundation Loading Data

Drawing / Doc. No.

1st Submission (Rev. A)

Last Wk
Rcvd
To Rcvd
Next Wk

Description

FLAG

FLAG

FLAG
Subm.
Next Wk
Last Wk
Submited

Sr. No.

Schedule
First
Submission
Date

Category
(A/I/N)

Unit No.

JOB No. T209001

:LT-P0-00003
:4.2
:A
Recd aftr
Long Time

POWER PROJECT MANAGEMENT SERVICES , VADODARA

Last Wk
Rcvd
To Rcvd
Next Wk

LARSEN & TOUBRO LIMITED

25-Aug-10
25-Aug-10
8-Sep-10
8
Sep 10
6-Sep-10

DCPL 0176

26-Sep-10

26-Oct-10

25-Nov-10

25-Dec-10

24-Jan-11

23-Feb-11

26-Sep-10

26-Oct-10

25-Nov-10

25-Dec-10

24-Jan-11

23-Feb-11

24-Sep-10

24-Oct-10

23-Nov-10

23-Dec-10

22-Jan-11

21-Feb-11

24-Sep-10

24-Oct-10

23-Nov-10

23-Dec-10

22-Jan-11

21-Feb-11

8 Oct 10
8-Oct-10

7 Nov 10
7-Nov-10

7 Dec 10
7-Dec-10

6 Jan 11
6-Jan-11

5 Feb 11
5-Feb-11

7 Mar 11
7-Mar-11

Page 10 of 12

DOCUMENT NO.
ANNEXURE REV. NO:

JOB No. T209001

C
C
C

19.11
19.12
19.13
19.14

19.16

19.17

19.18

C
C
C
C
C

19.19
19.20
19.21
19.22
19.26

LTDrivewheelassembly
LTidlewheelassembly
CTDrivewheelassembly
CTidlewheelassembly
LongtravelMachineryAssemblyfor40/10TTGHallEOTcrane
Schematic circuit diagram of protective panel and lighting circuit
Schematiccircuitdiagramofprotectivepanelandlightingcircuit
for40/10TTGHallcrane
SchematiccircuitdiagramofMainhoistpanelfor40/10TTGHall
crane
SchematiccircuitdiagramofAux.hoistpanelfor40/10TTGHall
crane
SchematiccircuitdiagramofCrossTraverseandMicroCross
Traversepanel&BOMfor40/10TTGHallcrane
SchematiccircuitdiagramofLongTraversepanelforfor40/10T
TGHallcrane
BillofmaterialforMain,Aux.Hoist,CTcircuit,LTcircuitand
main(Pro)circuitfor40/10TTGHall
G.A.drawingofProtectivepanel&transformerenclosurefor
40/10TTGHallcrane
G.A.ofLongTraversepanelfor40/10TTGHallcrane

AILM003260
AILM003261
AILM003262
AILM003263
AILM003264

9-Aug-10
9-Aug-10
9-Aug-10
9-Aug-10
9-Aug-10

I
I
I
I
I

AILE003266

30-Jul-10

AILE003267

30-Jul-10

AILE003268

30-Jul-10

AILE003269
AILE003270
AILE003271
AILE003272
AILE003276

30-Jul-10
30-Jul-10
30-Jul-10
1-Aug-10
1-Aug-10

I
I
I
I
I

19.27

CableSchedulefor40/10TTGHallcrane

AILE003277

1-Aug-10

19.28

Cranecontrlolwriteup

AILE003278

1-Aug-10

19.29

Cablesizecalculationfor40/10TTGHallcrane

AILE003279

1-Aug-10

19.30

Cranelubrication

AILM003280

9-Aug-10

19.31

Structuralcalculationsfor40/10TTGHallcrane

AILM003281

30-Jul-10

19.34

MakeofBoughtOutItemList

AILM003284

30-Jul-10

19.35

Electricalfeederdiagram

AILE003285

1-Aug-10

19 36
19.36

Earthing details
Earthingdetails

AILE003286

1-Aug-10

19.44

DSLSelection&VoltagedropCalculationfor40/10TBFPEOT
Crane

20.1

20

C
C

20.5
20.6

VDR - Condensate Extraction Pump


Pump Data Sheet (Technical Schedule)
CEP GA Drawing common for pump & motor & acces. (INSTA
CEP P&I diagram with list of components

AILM003294

25-Aug-10

8-Aug-10

1-Aug-10
13-Aug-10
1-Aug-10
g
13-Aug-10
25-Aug-10
13-Aug-10

DCPLODT0228
DCPLODT0228
DCPLODT0228

8-Aug-10
23-Jul-10
11-Aug-10
23-Jul-10
11-Aug-10
23-Jul-10

DCPLODT0205
DCPLODT0205
DCPLODT0205

8-Sep-10
8-Sep-10
8-Sep-10
8-Sep-10
29-Aug-10
26-Aug-10
29-Aug-10
26-Aug-10
29-Aug-10
26-Aug-10
29-Aug-10
26-Aug-10
29-Aug-10
26-Aug-10
29-Aug-10
26-Aug-10
31-Aug-10

DCPL 0171
DCPL 0171
DCPL 0171
DCPL 0171
DCPL 0171
DCPL 0171

31-Aug-10
15-Sep-10
31-Aug-10
26-Aug-10
31-Aug-10
26-Aug-10
31-Aug-10
26-Aug-10
8-Sep-10

DC PL 0183
DCPL 0171
DCPL 0171
DCPL 0171

29-Aug-10
29-Aug-10
31-Aug-10
26-Aug-10
31-Aug-10
g
26-Aug-10
24-Sep-10
26-Aug-10

DCPl 0171
DCPl 0171
DCPl 0171

7-Dec-10

7-Nov-10

7-Dec-10

8-Oct-10

7-Nov-10

8-Oct-10

Subm.
Next Wk
Last Wk
Submited

7-Nov-10

Recd aftr
Long Time

8-Oct-10

Last Wk
Rcvd
To Rcvd
Next Wk

8-Oct-10

Subm.
Next Wk
Last Wk
Submited

Receive
Date
I/W No.
6-Jan-11

FLAG

FLAG
4th Submission (Rev. D)
Release
Date
DTN No.
5-Feb-11

Receive
Date
I/W No.
7-Mar-11

6-Jan-11

5-Feb-11

7-Mar-11

6-Jan-11

5-Feb-11

7-Mar-11

7-Dec-10

6-Jan-11

5-Feb-11

7-Mar-11

7-Nov-10

7-Dec-10

6-Jan-11

5-Feb-11

7-Mar-11

8-Oct-10

7-Nov-10

7-Dec-10

6-Jan-11

5-Feb-11

7-Mar-11

8-Oct-10

7-Nov-10

7-Dec-10

6-Jan-11

5-Feb-11

7-Mar-11

28-Sep-10

28-Oct-10

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

28-Sep-10

28-Oct-10

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

28-Sep-10

28-Oct-10

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

28-Sep-10

28-Oct-10

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

28-Sep-10

28-Oct-10

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

28-Sep-10

28-Oct-10

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

30-Sep-10

30-Oct-10

29-Nov-10

29-Dec-10

28-Jan-11

27-Feb-11

30-Sep-10

30-Oct-10

29-Nov-10

29-Dec-10

28-Jan-11

27-Feb-11

30-Sep-10

30-Oct-10

29-Nov-10

29-Dec-10

28-Jan-11

27-Feb-11

30-Sep-10

30-Oct-10

29-Nov-10

29-Dec-10

28-Jan-11

27-Feb-11

30-Sep-10

30-Oct-10

29-Nov-10

29-Dec-10

28-Jan-11

27-Feb-11

8-Oct-10

7-Nov-10

7-Dec-10

6-Jan-11

5-Feb-11

7-Mar-11

28-Sep-10

28-Oct-10

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

27-Nov-10

27-Dec-10

26-Jan-11

25-Feb-11

29-Nov-10

29-Dec-10

28-Jan-11

27-Feb-11

28-Sep-10
12-Aug-10
30-Sep-10

DCPLODT0227

28-Oct-10
26-Aug-10
30-Oct-10

DCPL 0171

JNSTPP

L&T

JNSTPP

L&T

30-Sep-10
p

30-Oct-10

29-Nov-10

29-Dec-10

28-Jan-11

27-Feb-11

24-Oct-10

23-Nov-10

23-Dec-10

22-Jan-11

21-Feb-11

23-Mar-11

JNSTPP

As Built

Receipt Date
of Approval

Release
Date-Unit 1 DTN No

15-Sep-10

392.8
KSB-M0-03533
KSB-M0-03503
KSB-M0-03504

21

VDR - Vacuum Pump

304.0

22

VDR - Condensate Polishing Units

532.0

23

VDR - DMCW Pumps

292.0

24

VDR - Plate Heat Exchangers

177.0

25

VDR - Butter Fly Valves

152.0

26

VDR - LP Bypass Valves

292.0

27

VDR - Shop Fabricated Tanks - Steel

152.0

28

VDR - AC & DC Distribution Board

127.0

29

VDR - El
Elevators
t

190 0
190.0

30

VDR - OLTCs & Debris Filter

330.0

31

VDR - HP Heaters 2/3 Way Bypass Valves

152.0

32

VDR - Misc.

152.0

33

VDR - Power Cycle Valves

469.0

34

VDR - Control Valves & Pneumetic ON / OFF


Valves

228.0

35

VDR - Shop Fabricated Piping

583.0

11-Aug-10
11-Aug-10

I
A

Sch.
Act.
Sch.
Act.
Sch.
Act.

7-Sep-10
10-Sep-10
10-Sep-10

19.10

8-Sep-10

8-Sep-10

3rd Submission (Rev. C)


Release
Date
DTN No.
7-Dec-10

Receive
Date
I/W No.
7-Nov-10

Recd aftr
Long Time

9-Aug-10

Release
Date
DTN No.
8-Oct-10

FLAG

FLAG

FLAG
2nd Submission (Rev. B)

Last Wk
Rcvd
To Rcvd
Next Wk

AILM003259

Subm.
Next Wk
Last Wk
Submited

15TAuxHookBlockAssembly

L&T

19.9

JNSTPP

L&T
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.

Recd aftr
Long Time

9-Aug-10

Early Start

AILM003258

Receive
Date
I/W No.
8-Sep-10

115Tmainhookblockassembly

Release
Date
DTN No.
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO30-Jul-10
DT0229
13-Aug-10
DCPLO30-Jul-10
DT0229
13-Aug-10
DCPLO30-Jul-10
DT0229
13-Aug-10
DCPLO30-Jul-10
DT0229
13-Aug-10
DCPLO30-Jul-10
DT0229
13-Aug-10
DCPLO30-Jul-10
DT0229
13-Aug-10
DCPLO1-Aug-10
DT0229
13-Aug-10
DCPLO1-Aug-10
DT0229
16-Aug-10
DCPLO1-Aug-10
DT0228
13-Aug-10
DCPLO1-Aug-10
DT0228
13-Aug-10
DCPLO1-Aug-10
DT0228
13-Aug-10
DCPLO9-Aug-10
DT0241
23-Aug-10
DCPLO30-Jul-10
DT0247
30-Aug-10
30-Jul-10

19.8

Drawing / Doc. No.

1st Submission (Rev. A)

Last Wk
Rcvd
To Rcvd
Next Wk

Description

Subm.
Next Wk
Last Wk
Submited

Category
(A/I/N)

Sr. No.

FLAG

FLAG

FLAG

Unit No.

Schedule
First
Submission
Date

:LT-P0-00003
:4.2
:A
Recd aftr
Long Time

POWER PROJECT MANAGEMENT SERVICES , VADODARA

Last Wk
Rcvd
To Rcvd
Next Wk

LARSEN & TOUBRO LIMITED

7-Oct-10

6-Nov-10

6-Dec-10

5-Jan-11

4-Feb-11

6-Mar-11

10-Oct-10

9-Nov-10

9-Dec-10

8-Jan-11

7-Feb-11

9-Mar-11

10-Oct-10

9-Nov-10

9-Dec-10

8-Jan-11

7-Feb-11

9-Mar-11

Page 11 of 12

DOCUMENT NO.
ANNEXURE REV. NO:

POWER PROJECT MANAGEMENT SERVICES , VADODARA

Early Start
36

VDR - Chain Pully Blocks, HOT, etc..

152.0

37

VDR - Gas Cylinders

152.0

38

VDR - Strainers

203.0

39

VDR - Safety & Relief Valves

152.0

40

VDR - 24 V DC System

76.0

41

VDR - DCS

254.0

42

VDR - Flow Elements

228.0

43

VDR - Expansion Joints (Metallic & Rubber)

203.0

44

VDR - Vibration Monitoring System

114.0

45

VDR - Supports & Hangers

596.0

46

VDR - LP Valves

469.0

47

VDR - Extraction Steam Check Valves

165.0

48

VDR - LV power & Control Cables

76.0

49

VDR - C&I Cables

139.0

50

VDR - Insulation

139.0

51

GENERAL DOCUMENTS

17.7

C
C

17.8
17.9

17.10

C
C
C

Sketch Showing Cable Tray Exit Along Grid 12 & Electrical


Equipment Erection
Sketch Showing Cable Tray Exit Along Grid C & Electrical
Equipment Erection

29-Dec-09

4-Jan-10

JPN-SK-E-003

18-Jan-10

JPN-SK-E-001

19-Jan-10

19-Jan-10

97140-08-DS-0001

Mail

97140-01-DS-0001

17.11

DS-Gas Paremeters at Chimney Inlet-2

97140-01-DS-0002

Mail

17.12

Note on Surge Capacitor Value Recommendation from


MELCO

GAE-KN-T001

13-Apr-10

17.13

Embedded Metal Plan Around Lube Oil Conditioner

12-May-10

Details of Embedded Materials

17.15

Foundation Embedded Materials for Piping

17.16

Oil Piping & Equipment Arrangement

17.17

System Description of Steam Turbine

17.18

Foundation of Lubrication Oil Equipment

17.17

Observation on Sketch of Crane Span - AB bay

17.18

Outline Dimention of AC Motor EH Oil Pump (A)

17.17
17.18

LMTG-M0-01207
LMTG-M0-01207
LMTG-M0-01206
LMTG-M0-01206
LMTG-M0-01205
LMTG-M0-01205
T3101PLPA101
LMTG-M0-01201
LMTG-P0-01036
LMTG-M0-01202
LMTG-M0-02809

Outline Dimention of AC Motor EH Oil Pump (B)


Grout Material for TG Foundation

Abbreviation:
A - Approval
I - Information
N - Not For Submission
- Weightage Point not considered
x
x

Mail

DS-Gas Paremeters at Chimney Inlet-1

17.14

JPN-SK-M-006

JPN-SK-E-002

DS-ESP

LT-M0-03092

Sketch showing IPBD Run Arrangement for YND1 Scheme

L&T

Receive
Date
I/W No.

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

Subm.
Next Wk
Last Wk
Submited

Recd aftr
Long Time

Last Wk
Rcvd
To Rcvd
Next Wk

Subm.
Next Wk
Last Wk
Submited

Last Wk
Rcvd
To Rcvd
Next Wk

JNSTPP

Release
Date
DTN No.

JNSTPP

Receipt Date
of Approval

Release
Date-Unit 1 DTN No

LMTG-M0-02810
-

12-May-10

12-May-10

1-Feb-10

2-Jul-10

29-Apr-10

17-Jul-10

23-Jul-10

23-Jul-10
11-Aug-10

A
I

DCPLODT0037
DCPLODT0038
DCPLODT0038
DCPLODT0043
DCPLODT0053
DCPLODT0058
DCPLODT0058
By Mail
By Mail
By Mail
DCPLODT0119
DCPLODT0141
DCPLODT0141
DCPLODT0141
DCPLO_D
T0069
DCPLODT0171
DCPLODT0137
DCPLODT0188
DCPLODT0204
DCPLO
DCPLODT0204
DCPLODT0220

28-Jan-10
28-Jan-10
28-Jan-10
3-Feb-10
15-Mar-10
17-Feb-10
15-Feb-10
18-Feb-10

DCPl 0071
DCPl 0046

18-Feb-10
Mail
2-Mar-10
Mail
2-Mar-10
Mail
2-Mar-10
13-Apr-10
5-May-10
12-May-10
15-Jun-10
12-May-10
15-Jun-10
11-Jun-10
15-Jun-10
1-Feb-10
17-Jul-10
2-Jul-10

DCPL 0058
DCPL 0058
DCPL 0058
DCPL 0106
DCPL 0132
DCPL 0132
DCPL 0132
DCPL 0150

29-Apr-10
15-Jun-10
17-Jul-10

DCPl 0132

23-Jul-10
6-Aug-10
23 Jul 10
23-Jul-10
6-Aug-10
11-Aug-10

DCPL 0163
DCPL 0163

20-Jul-10

20-Jul-10

17-Sep-10
17-Sep-10

DCPLODT0202

DCPLODT0202

17.6

L&T

Receive
Date
I/W No.

As Built

GA Sketch & Load Data for Feed Water Heaters

29-Dec-09

29-Dec-09
29-Dec-09
29-Dec-09
29-Dec-09
29-Dec-09
29-Dec-09
4-Jan-10
4-Jan-10
18-Jan-10
19-Jan-10
19-Jan-10
19-Jan-10
19-Jan-10
19-Jan-10
Mail
10-Oct-09
Mail
10-Oct-09
Mail
10-Oct-09
13-Apr-10
13-Apr-10
12-May-10
12-May-10
12-May-10
12-May-10
12-May-10
12-May-10
1-Feb-10
1-Feb-10
2-Jul-10
2-Jul-10
29-Apr-10
29-Apr-10
17-Jul-10
17-Jul-10
23-Jul-10
23-Jul-10
23
Jul 10
23-Jul-10
23-Jul-10
11-Aug-10
11-Aug-10

17.5

K6A24-009-DWG-M-002

Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch.
Act.
Sch
Sch.
Act.
Sch.
Act.

Sketch of Transformer & CW Pipe Interface

29-Dec-09

17.4

JNSTPP

Release
Date
DTN No.

FLAG
4th Submission (Rev. D)

TXH1A-090XX1

Plant Lay-Out

Receive
Date
I/W No.

FLAG

17.3

Release
Date
DTN No.

3rd Submission (Rev. C)

0.0

L&T

Heat & Mass Balance Diagram for HP-LP Baypass

JNSTPP

17.2

Receive
Date
I/W No.

FLAG

FLAG

FLAG
2nd Submission (Rev. B)

DCPLODT0267
DCPLODCPLO
DT0267

L&T

Release
Date
DTN No.

Recd aftr
Long Time

Drawing / Doc. No.

1st Submission (Rev. A)

Last Wk
Rcvd
To Rcvd
Next Wk

Description

FLAG

FLAG

FLAG
Subm.
Next Wk
Last Wk
Submited

Sr. No.

Schedule
First
Submission
Date

Category
(A/I/N)

Unit No.

JOB No. T209001

:LT-P0-00003
:4.2
:A
Recd aftr
Long Time

LARSEN & TOUBRO LIMITED

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Extra

Total:
Unit type: C - Common for both Units
1 - For Unit No. 1 only

I/W No. - Inward No.


DTN No. - Document Transmittal No.

2 - For Unit No. 2 only


x
x
x
x

Sch. - Schedule Date for Submission


Act. - Actual Date of Submission

Page 12 of 12

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 59 of 103

4.2 PROCUREMENT STATUS

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda.

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED

PAGE NO. :- 60 of 103

2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

JOB NO: - T209001

4.2.1 ORDERING ( 10% )


Release Date of
Orders

% Progress for the Month


SR. NO.

System Description

Enq.
Float

Rcpt
Quote

LOI/PO
Issue

Vendor

LOI Date

%
Progress
for Month

% Cum.
Progress

17-Jun-10 12-May-10

0.00%

100.00%

2-Sep-10 17-May-10

0.00%

100.00%

PO Date
Sch.

COMMON SYSTEM

EOT Crane for Tg Building

100.00% 100.00% 100.00% Anupam Cranes,India

12-May-10

EOT Crane for BFP

100.00% 100.00% 100.00% Anupam Cranes,India

17-May-10

Elevator for Main & Service Building

100.00% 100.00%

Insulation

0.00%

Paints

Misccellaneous Items for Commom System

STG SYSTEM

Steam Turbine

100.00% 100.00% 100.00%

L&T-MHI

25-Aug-09

Generator

100.00% 100.00% 100.00%

L&T-MHI

25-Aug-09

Turbine Preservation System

0.00%

0.00%

0.00%

Miscellaneous Items for STG System

0.00%

0.00%

0.00%

FEED WATER SYSTEM

Deaerator

100.00% 100.00% 100.00%

MDBFP

TDBFP

27-May-10

Act.
(LOI Date)

0.00%

25-Apr-11

0.00%

30.00%

0.00%

0.00%

18-Feb-12

0.00%

0.00%

0.00%

0.00%

0.00%

13-Apr-12

0.00%

0.00%

0.00%

0.00%

0.00%

14-Jun-11

0.00%

0.00%

19-Jan-10

25-Aug-09

0.00%

100.00%

19-Jan-10

25-Aug-09

0.00%

100.00%

24-Aug-11

0.00%

0.00%

14-Jun-11

0.00%

0.00%

21-Sep-09

0.00%

100.00%

L&T-HED

21-Sep-09

19-Jan-10

100.00% 100.00% 100.00% Flowserve, India/Spain

14-Jun-10

22-Feb-10 14-Jun-10

0.00%

100.00%

100.00% 100.00% 100.00% Flowserve, India/Spain

14-Jun-10

22-Feb-10 14-Jun-10

0.00%

100.00%

21-Apr-10

0.00%

100.00%

21-Sep-09

19-Jan-10

21-Sep-09

0.00%

100.00%

0.00%

14-Jun-11

0.00%

30.00%

Drive Turbine for BFP

100.00% 100.00% 100.00%

Siemens,
Germany/India

HPH

100.00% 100.00% 100.00%

L&T-HED

HP valve of Feed Water System

100.00% 100.00%

LP Piping & Fitting of Feed Water System

LP Valve of Feed Water System

9
10

0.00%

0.00%

0.00%

23-Aug-11

0.00%

0.00%

100.00%

0.00%

0.00%

23-Aug-11

20.00%

20.00%

Hangers & Support of Feed Water System

0.00%

0.00%

0.00%

23-Aug-11

0.00%

0.00%

Miscellaneous Items for Feed Water System

0.00%

0.00%

0.00%

23-Aug-11

0.00%

0.00%

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda.

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED

PAGE NO. :- 61 of 103

2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

JOB NO: - T209001

4.2.1 ORDERING ( 10% )


Release Date of
Orders

% Progress for the Month


SR. NO.

System Description

Enq.
Float

Rcpt
Quote

LOI/PO
Issue

Vendor

LOI Date

PO Date
Sch.

%
Progress
Act.
for Month
(LOI Date)

% Cum.
Progress

11

Hp piping & Fittings of Feedwater System

0.00%

0.00%

0.00%

14-Jun-11

0.00%

0.00%

12

Expansion Joints of Feed Water System

0.00%

0.00%

0.00%

14-Jul-11

0.00%

0.00%

12

Butterfly Valve for Feed Water System

0.00%

11-Dec-10

10.00%

30.00%

13

2/3 Way Valve for Feed Water System

0.00%

30-May-11

0.00%

0.00%

CONDENSATE SYSTEM

Condenser

100.00% 100.00% 100.00%

L&T-HED

21-Sep-09

19-Jan-10

21-Sep-09

0.00%

100.00%

Condensate Extraction Pump

100.00% 100.00% 100.00%

KSB,India

7-Jun-10

15-Jun-10

7-Jun-10

0.00%

100.00%

Condensate Polishing Unit

100.00% 100.00%

Siemens, India

24-Aug-10

100.00%

100.00%

LPH

100.00% 100.00% 100.00%

L&T-HED

21-Sep-09

19-Jan-10

21-Sep-09

0.00%

100.00%

Gland Steam Condenser

100.00% 100.00% 100.00%

L&T-MHI

25-Aug-09

19-Jan-10

25-Aug-09

0.00%

100.00%

LP Valve of Condensate System

100.00%

0.00%

0.00%

23-Aug-11

20.00%

20.00%

Hangers & Support of Condesate System

0.00%

0.00%

0.00%

23-Aug-11

0.00%

0.00%

Miscellaneous Items of Condensate System

0.00%

0.00%

0.00%

23-Aug-11

0.00%

0.00%

LP piping & Fittings of Condensate System

0.00%

0.00%

0.00%

23-Aug-11

0.00%

0.00%

VACUUM SYSTEM

Vacuum Pump

100.00% 100.00%

0.00%

6-Aug-10

0.00%

30.00%

LP Valves of Vacuum System

100.00%

0.00%

0.00%

7-Sep-11

20.00%

20.00%

Hangers & Supports of Vacuum Ssytem

0.00%

0.00%

0.00%

7-Sep-11

0.00%

0.00%

Miscellaneous Items of Vacuum System

0.00%

0.00%

0.00%

7-Sep-11

0.00%

0.00%

LP Piping & Fittings of Vacuum System

0.00%

0.00%

0.00%

7-Sep-11

0.00%

0.00%

CLOSED COOLING WATER SYSTEM

DMCW Pump

100.00% 100.00%

0.00%

4-Nov-10

0.00%

30.00%

Plate Heat Exchanger

100.00% 100.00%

0.00%

4-Nov-10

0.00%

30.00%

100.00% 100.00%
0.00%

0.00%

0.00%

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda.

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED

PAGE NO. :- 62 of 103

2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

JOB NO: - T209001

4.2.1 ORDERING ( 10% )


Release Date of
Orders

% Progress for the Month


SR. NO.

System Description

Enq.
Float

Rcpt
Quote

LOI/PO
Issue

Vendor

LOI Date

PO Date
Sch.

%
Progress
Act.
for Month
(LOI Date)

% Cum.
Progress

DMCW Expansion Tanks

100.00% 100.00%

0.00%

31-Jan-11

10.00%

30.00%

LP Valves of Closed Cooling Water System

100.00%

0.00%

0.00%

1-Sep-11

20.00%

20.00%

Hangers & Supports of Closed Cooling Water Syst 0.00%

0.00%

0.00%

1-Sep-11

0.00%

0.00%

Miscellaneous Items of Closed Cooling Water Sys 100.00%

0.00%

0.00%

1-Sep-11

0.00%

20.00%

LP Piping & Fittings of Closed Cooling Water Syste 0.00%

0.00%

0.00%

1-Sep-11

0.00%

0.00%

DRAIN SYSTEM

HP & LP Flash Tanks

100.00% 100.00% 100.00%

21-Sep-09

21-Sep-09

0.00%

100.00%

HP valves of Drain System

100.00% 100.00%

0.00%

28-Jul-11

0.00%

30.00%

LP Piping & Fittings of Drain System

LP Valves of Drain System

L&T-HED

0.00%

0.00%

0.00%

1-Sep-11

0.00%

0.00%

100.00%

0.00%

0.00%

1-Sep-11

20.00%

20.00%

Hangers & Supports of Drain System

0.00%

0.00%

0.00%

1-Sep-11

0.00%

0.00%

Miscellaneous Items of Drain System

0.00%

0.00%

0.00%

1-Sep-11

0.00%

0.00%

HP Piping & Fittings of Drain System

0.00%

0.00%

0.00%

28-Jul-11

0.00%

0.00%

EXTRACTION STEAM SYSTEM

FCNRV

100.00% 100.00% 100.00%

25-Aug-09

19-Jan-10

25-Aug-09

0.00%

100.00%

HP valves of Extraction System

100.00% 100.00%

0.00%

1-Aug-11

0.00%

30.00%

LP Piping & Fittings of Extraction System

LP Valves of Extraction System

L&T-MHI

0.00%

0.00%

0.00%

5-Sep-11

0.00%

0.00%

100.00%

0.00%

0.00%

5-Sep-11

20.00%

20.00%

Hangers & Supports of Extraction System

0.00%

0.00%

0.00%

5-Sep-11

0.00%

0.00%

Miscellaneous Items of Extraction System

0.00%

0.00%

0.00%

5-Sep-11

0.00%

0.00%

HP Piping & Fittings of Extraction System

0.00%

0.00%

0.00%

1-Aug-11

0.00%

0.00%

LP BYPASS STEAM SYSTEM

LP Bypass Valve

0.00%

0.00%

0.00%

28-Jan-11

0.00%

0.00%

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda.

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED

PAGE NO. :- 63 of 103

2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

JOB NO: - T209001

4.2.1 ORDERING ( 10% )


Release Date of
Orders

% Progress for the Month


SR. NO.

System Description

Enq.
Float

HP valves of LP Bypass Steam System

LP Piping & Fittings of LP Bypass Steam System

0.00%

Hangers & Supports of LP Bypass Steam System

Rcpt
Quote

100.00% 100.00%

LOI/PO
Issue

Vendor

LOI Date

PO Date
Sch.

%
Progress
Act.
for Month
(LOI Date)

% Cum.
Progress

0.00%

1-Aug-11

0.00%

30.00%

0.00%

0.00%

5-Sep-11

0.00%

0.00%

0.00%

0.00%

0.00%

5-Sep-11

0.00%

0.00%

Miscellaneous Items of LP Bypass Steam System

0.00%

0.00%

0.00%

5-Sep-11

0.00%

0.00%

HP Piping & Fittings of LP Bypass Steam System

0.00%

0.00%

0.00%

1-Aug-11

0.00%

0.00%

CIRCULATING WATER SYSTEM

Rubber Expansion Joints

0.00%

0.00%

0.00%

6-Aug-11

0.00%

0.00%

Butterfly Valve for Circulating Water System

100.00% 100.00%

0.00%

11-Jun-11

10.00%

30.00%

OLTCs

100.00% 100.00%

0.00%

11-Jun-11

0.00%

30.00%

LP Valves of Circulating Water System

100.00%

0.00%

0.00%

8-Sep-11

20.00%

20.00%

Hangers & Supports of Circulating Water System

0.00%

0.00%

0.00%

8-Sep-11

0.00%

0.00%

Miscellaneous Items of Circulating Water System

0.00%

0.00%

0.00%

8-Sep-11

0.00%

0.00%

LP Piping & Fittings of Circulating Water System

0.00%

0.00%

0.00%

8-Sep-11

0.00%

0.00%

ELECTRICAL SYSTEM

AC, DC, UPS Distribution Board

0.00%

0.00%

0.00%

7-Apr-11

0.00%

0.00%

Battery Bank & Chargers

0.00%

0.00%

0.00%

12-Jul-11

0.00%

0.00%

Power Cables

0.00%

0.00%

0.00%

16-Sep-11

0.00%

0.00%

Miscellaneous Items of Electrical System

0.00%

0.00%

0.00%

16-Sep-11

0.00%

0.00%

C&I SYSTEM

Vibration Monitoring System

100.00% 100.00%

0.00%

24-Aug-11

0.00%

30.00%

DCS System & Panel

100.00% 100.00%

0.00%

20-Jul-11

0.00%

30.00%

C&I Cables

0.00%

0.00%

0.00%

2-Dec-11

0.00%

0.00%

Field Instruments

0.00%

0.00%

0.00%

20-Jul-11

0.00%

0.00%

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda.

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED

PAGE NO. :- 64 of 103

2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

JOB NO: - T209001

4.2.1 ORDERING ( 10% )


Release Date of
Orders

% Progress for the Month


SR. NO.

System Description

Miscellaneous Items of C&I System

Enq.
Float

Rcpt
Quote

LOI/PO
Issue

0.00%

0.00%

0.00%

Vendor

LOI Date

PO Date
Sch.

2-Dec-11

%
Progress
Act.
for Month
(LOI Date)
-

0.00%

% Cum.
Progress

0.00%

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda
JOB NO: - T209001

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

PAGE NO :- 65 of 103

4.2.2 MANUFACTURING ( 90% )


SR. NO.

System Description

Vendor

Manufacturing / Delivery
Progress
% Progress for
% Cum.
Month
Progress

LOI Date

LOI / PO Date

12-May-10

27-May-10

0.00%

18.00%

17-May-10

0.00%

18.00%

COMMON SYSTEM

EOT Crane for Tg Building

EOT Crane for BFP

Elevator for Main & Service Building

0.00%

0.00%

Insulation

0.00%

0.00%

Paints

0.00%

0.00%

Misccellaneous Items for Commom System

0.00%

0.00%

STG SYSTEM

Steam Turbine

L&T-MHI

25-Aug-09

19-Jan-10

4.93%

52.95%

Generator

L&T-MHI

25-Aug-09

19-Jan-10

4.99%

55.32%

Turbine Preservation System

0.00%

0.00%

Miscellaneous Items for STG System

0.00%

0.00%

FEED WATER SYSTEM

Deaerator

21-Sep-09

19-Jan-10

0.50%

9.00%

14-Jun-10

4.00%

18.00%

14-Jun-10

4.00%

18.00%

0.00%

0.00%

21-Sep-09

19-Jan-10

2.00%

19.00%

Anupam
Cranes,India
Anupam
Cranes,India

L&T-HED
Flowserve,
India/Spain
Flowserve,
India/Spain
Siemens,
Germany/India

MDBFP

TDBFP

Drive Turbine for BFP

HPH

HP valve of Feed Water System

0.00%

0.00%

LP Piping & Fitting of Feed Water System

0.00%

0.00%

LP Valve of Feed Water System

0.00%

0.00%

Hangers & Support of Feed Water System

0.00%

0.00%

10

Miscellaneous Items for Feed Water System

0.00%

0.00%

11

Hp piping & Fittings of Feedwater System

0.00%

0.00%

L&T-HED

Qty
Despatched

Site Rcpt
Date

Delivery
Details

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda
JOB NO: - T209001

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

PAGE NO :- 66 of 103

4.2.2 MANUFACTURING ( 90% )


SR. NO.

System Description

Vendor

LOI Date

LOI / PO Date

Manufacturing / Delivery
Progress
% Progress for
% Cum.
Month
Progress

12

Expansion Joints of Feed Water System

0.00%

0.00%

12

Butterfly Valve for Feed Water System

0.00%

0.00%

13

2/3 Way Valve for Feed Water System

0.00%

0.00%

CONDENSATE SYSTEM

Condenser

L&T-HED

21-Sep-09

19-Jan-10

3.00%

32.00%

Condensate Extraction Pump

KSB,India

7-Jun-10

14.00%

20.00%

Condensate Polishing Unit

Siemens, India

0.00%

0.00%

LPH

L&T-HED

21-Sep-09

19-Jan-10

2.00%

19.00%

Gland Steam Condenser

L&T-MHI

25-Aug-09

19-Jan-10

0.00%

0.00%

LP Valve of Condensate System

0.00%

0.00%

Hangers & Support of Condesate System

0.00%

0.00%

Miscellaneous Items of Condensate System

0.00%

0.00%

LP piping & Fittings of Condensate System

0.00%

0.00%

VACUUM SYSTEM

Vacuum Pump

0.00%

0.00%

LP Valves of Vacuum System

0.00%

0.00%

Hangers & Supports of Vacuum Ssytem

0.00%

0.00%

Miscellaneous Items of Vacuum System

0.00%

0.00%

LP Piping & Fittings of Vacuum System

0.00%

0.00%

CLOSED COOLING WATER SYSTEM

DMCW Pump

0.00%

0.00%

Plate Heat Exchanger

0.00%

0.00%

DMCW Expansion Tanks

0.00%

0.00%

LP Valves of Closed Cooling Water System

0.00%

0.00%

Qty
Despatched

Site Rcpt
Date

Delivery
Details

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda
JOB NO: - T209001

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

PAGE NO :- 67 of 103

4.2.2 MANUFACTURING ( 90% )


SR. NO.

System Description

Vendor

LOI Date

LOI / PO Date

Manufacturing / Delivery
Progress
% Progress for
% Cum.
Month
Progress

Hangers & Supports of Closed Cooling Water System

0.00%

0.00%

Miscellaneous Items of Closed Cooling Water Syste

0.00%

0.00%

LP Piping & Fittings of Closed Cooling Water System

0.00%

0.00%

DRAIN SYSTEM

HP & LP Flash Tanks

21-Sep-09

1.00%

7.00%

HP valves of Drain System

0.00%

0.00%

LP Piping & Fittings of Drain System

0.00%

0.00%

LP Valves of Drain System

0.00%

0.00%

Hangers & Supports of Drain System

0.00%

0.00%

Miscellaneous Items of Drain System

0.00%

0.00%

HP Piping & Fittings of Drain System

0.00%

0.00%

EXTRACTION STEAM SYSTEM

FCNRV

25-Aug-09

19-Jan-10

0.00%

0.00%

HP valves of Extraction System

0.00%

0.00%

LP Piping & Fittings of Extraction System

0.00%

0.00%

LP Valves of Extraction System

0.00%

0.00%

Hangers & Supports of Extraction System

0.00%

0.00%

Miscellaneous Items of Extraction System

0.00%

0.00%

HP Piping & Fittings of Extraction System

0.00%

0.00%

LP BYPASS STEAM SYSTEM

LP Bypass Valve

0.00%

0.00%

HP valves of LP Bypass Steam System

0.00%

0.00%

LP Piping & Fittings of LP Bypass Steam System

0.00%

0.00%

Hangers & Supports of LP Bypass Steam System

0.00%

0.00%

L&T-HED

L&T-MHI

Qty
Despatched

Site Rcpt
Date

Delivery
Details

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Baroda
JOB NO: - T209001

DOCUMENT NO.: - LT:JNSTPP:CON:PPM:003


PROGRESS REPORT NO.: - 11
ANNEXURE NO.: -

JAIPRAKASH POWER VENTURES


LIMITED
2 X 660 MW STEAM TURBINE GENERATOR & AUXILIARIES

PAGE NO :- 68 of 103

4.2.2 MANUFACTURING ( 90% )


SR. NO.

System Description

Vendor

LOI Date

LOI / PO Date

Manufacturing / Delivery
Progress
% Progress for
% Cum.
Month
Progress

Miscellaneous Items of LP Bypass Steam System

0.00%

0.00%

HP Piping & Fittings of LP Bypass Steam System

0.00%

0.00%

CIRCULATING WATER SYSTEM

Rubber Expansion Joints

0.00%

0.00%

Butterfly Valve for Circulating Water System

0.00%

0.00%

OLTCs

0.00%

0.00%

LP Valves of Circulating Water System

0.00%

0.00%

Hangers & Suuports of Circulating Water System

0.00%

0.00%

Miscellaneous Items of Circulating Water System

0.00%

0.00%

LP Piping & Fittings of Circulating Water System

0.00%

0.00%

ELECTRICAL SYSTEM

AC, DC, UPS Distribution Board

0.00%

0.00%

Battery Bank & Chargers

0.00%

0.00%

Power Cables

0.00%

0.00%

Miscellaneous Items of Electrical System

0.00%

0.00%

C&I SYSTEM

Vibration Monitoring System

0.00%

0.00%

DCS System & Panel

0.00%

0.00%

C&I Cables

0.00%

0.00%

Field Instruments

0.00%

0.00%

Miscellaneous Items of C&I System

0.00%

0.00%

Qty
Despatched

Site Rcpt
Date

Delivery
Details

Remarks

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 69 of 103

4.3 PROJECT WBS STURCTURE,


WEIGHTAGE PRINCIPLE AND BASIS OF
PROGRESS MEASUREMENT

LARSEN & TOUBRO LIMITED, PPMS,


BARODA

DOCUMENT NO :
PROGRESS REPORT NO :
REV. NO :

JAIPRAKASH POWER VENTURE LIMITED


(2 X 660 MW JAYPEE NIGRIE SUPER THERMAL POWER PROJECT)

JOB NO :- T209001

WORK BREAK - DOWN STRUCTURE, WEIGHTAGE PRINCIPLE AND BASIS OF PROGRESS MEASUREMENT

STG PACKAGE - 2 X 660 MW JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

LEVEL : I

LEVEL :II

10%

ENGINEERING

LEVEL : III

WTG PT

PROCUREMENT

65%
DETAIL ENGINEERING
WTG PT

35000

1000000

75%

100000

35%
BASIC ENGINEERING
WTG PT

WTG PT

65000

WTG PT

10%
ORDERING
WTG PT

15%

750000

CONSTRUCTION

90%
MANUFACTURING / DELIVERY
WTG PT
675000

75000

WTG PT

3000

2%

3%
ENABLING WORKS
WTG PT
4500

ORDER ON ERECTION
CONTRACTOR

100%

OPENING OF SITE
OFFICE
100%

TENDERING

WTG PT

150000

80%
ERECTION / SITE WORKS
WTG PT
120000

15%
COMMISSIONING
WTG PT
22500

LEVEL : IV
DESIGN CRITERIA DOCUMENTS
DCD POWER SYSTEM - 75%
DCD BOP SYSTEM - 25%
CALCULATION
CALC. POWER SYSTEMS - 75%
CALC. BOP SYSTEMS - 25%
P & IDs
UPTO REL FOR CONSTRUCTION - 97.5%
AS BUILT - 2.5%
PROCUREMENT ASSISTANCE
MECHANICAL - 90%
ELECTRICAL - 5%
C & I - 5%
TOTAL

LEVEL : V

20%

10%

30%

40%

TG BUILDING GA, PIPING LAYOUT &


COMPOSITE DRGS
VENDOR DRGs REVIEW
PIPING STRESS ANALYSIS, ISOMETRIC & LISTS
PIPE SUPPORT DRGs
O & M MANUALS, PG TEST PROCEDURE
ELECTRICAL SCHEMATICS, FEEDER,
CABLE SCHEDULE & TERMINATIONS ETC
C & I CONTROL SCHEMES, INSTAL DRGs
CABLE SCHEDULE & TERMINATIONS ETC
TOTAL

20%
20%
30%
15%
2.5%
2.5%

ROTATING EQUIPMENTS
STATIC EQUIPMENTS
BOP / MISCELLANEOUS ITEMS
PIPES
VALVES
ELECTRICAL ITEMS
INSTRUMENTATION ITEMS
TOTAL

25%
20%
17%
10%
10%
8%
10%
100%

ROTATING EQUIPMENTS
STATIC EQUIPMENTS
BOP / MISCELLANEOUS ITEMS
PIPES
VALVES
ELECTRICAL ITEMS
INSTRUMENTATION ITEMS
TOTAL

35%
20%
15%
10%
10%
5%
5%
100%

10%
100%
NOTE :
Rotating Equipment Includes :- Turbine & Auxillieries, Generator & Auxillieries, GSC, BFP, Drive Turbine, Motor for MDBFP, CEP, Vacuum pump, DMCW pump.
Static Equipment lncludes :- Deaerator, HPH, LPH, Condenser, PHE, DMCW Expansion Tank, HP Flash Tank, LP Flash Tank
BOP/Miscellaneous items :- Turbine Preservation System, CPU, OLTC & Debris filter, EOT cranes, Elevators, Expansion Joints, Insulation,Paints etc

100%

STG SYSTEM
FEED WATER SYSTEM
CONDENSATE SYSTEM
VACUUM SYSTEM
CLOSED CW SYSTEM
DRAIN SYSTEM
EXTRACTION SYSTEM
LP BYPASS SYSTEM
CONDENSER CW SYSTEM
C & I SYSTEM
ELECTRICAL SYSTEM
COMMON SYSTEM
INSULATION
PAINTING
TOTAL

45%
13%
21%
1.00%
3.00%
2.00%
2.00%
1.00%
2.00%
3.00%
3.00%
1.00%
2.00%
1.00%
100.00%

PRE COMM.
UNIT COMM.
TOTAL

FURTHER EACH DISCIPLINE / GROUP TO BE BROKEN DOWN INTO ACTIVITIES IN THE DETAILED PROJECT SCHEDULE WITH WEIGHTAGES.

BASIS OF WEIGHTAGE :
ENGINEERING - MANHOUR / EFFORTS

ORDERING- EFFORTS

MANUFACTURING / DELIVERY

CONSTRUCTION - COST/ WORK VOLUME/RESOURSE & MANPOWER UTILISATION

BASIS OF PROGRESS MEASUREMENT :


BASIC & DETAIL ENGINEERING
BASIC ENGINEERING
DCD
1st Submission to Jaypee / DCPL
2nd Submission Incorporating Comments
Approval
P & IDs
1st Submission to Jaypee / DCPL
2nd Submission Incorporating Comments
Approval
As built
Procurement Assistance
Specification
Bid Evaluation
Purchase Specification

80%
15%
5%
70%
15%
12.5%
2.5%
45%
45%
10%

DETAIL ENGINEERING
DRGS/DOCS to be submitted for Approval
1st Submission to Jaypee / DCPL
2nd Submission Incorporating Comments
Released for Construction
As built
DRGS/DOCS to be submitted for Information
1st Submission to Jaypee / DCPL
Released for Construction
As built

PROCUREMENT

70%
15%
12.5%
2.5%
85%
12.5%
2.5%

ORDERING / TENDERING
Standard Milestones for Progress
measurement of ITEMs / MRs
For all items
Enquiry
RCPT of Quote
LOI / Order

20%
10%
70%

MANUFACTURING / DELIVERY
Standard Milestones for Progress
measurement of ITEMs / MRs
RCPT / Approval of MFG DRGs
Sub order of Major Material
Prorata RCPT of Major Material
Prorata Manufacturing
Inspection
Despatch
Receipt at site
Bulk Material
MFG / Testing
Despatch
Receipt at site

CONSTRUCTION
PROGRESS WILL BE MEASURED PRORATA BY WORK ACHIEVED
AGAINST TOTAL WORK VOLUME. THE PROGRESS SHALL
BE CALCULATED AT SITE AS THE WORK COMMENCES ON SITE
10%
10%
20%
40%
5%
5%
10%
90%
5%
5%

INFORMATION

DATE :

DOC NO :

ISSUED FOR

VP

PG

VL

PREP BY :

CHKD BY :

APPROVED BY :

90%
10%
100%

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No- 71 of 103

4.4 PRIMAVERA SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

MILESTONE
MILESTON
L&T MILESTONE
MILE

Original Start
Duration

Finish

1475 23-Jul-09 A

05-Aug-13

1475 23-Jul-09 A

05-Aug-13

ML100

Date of "Notice To Proceed"

0 23-Jul-09 A

ML101

Opening of Site office & Mobilization

03-Jan-11*

ML102

Unit-1 Supply of Embedded parts for TG

03-Jan-11*

ML104

Unit-1 Commencement of EOT erection

0 23-May-11*

ML106

Unit-1 Commencement of insitu Condenser erection

0 12-Oct-11*

ML107

Unit-1 MDBFP receipt at site

ML110

***Unit-1 Commencement of TG erection

0 26-Dec-11

ML109

Unit-1 Receipt of LP Turbine at site

24-Jan-12*

ML111

Unit-1 Receipt of Generator at site

22-Mar-12*

ML108

Unit-1 Receipt of Deaerator at site

27-Mar-12*

ML113

Unit-1 TG oil flushing completion

06-Nov-12*

ML112

Unit-1 Readiness of TG/C&I system

24-Jan-13*

ML118

Unit-1 Completion of Governing system

09-Feb-13*

ML115

Unit-1 TG boxing up

09-Feb-13*

ML116

Unit-1 Boiler Light up readiness

26-Mar-13*

ML114

Unit-1 Commissioning of MDBFP

26-Mar-13*

ML119

Unit-1 TG on Barring Gear

12-Apr-13*

ML117

Unit-1 Steam Blowing completion

25-Apr-13*

ML121

Unit-1 TG Synchronization on Coal

24-Jun-13*

ML120

Unit-1 TG Synchronization on Oil

24-Jun-13*

ML123

Unit-1 Completion of Trial operation

05-Aug-13*

CLIENT INPUTS
IN
CONSTRUCTION PHASE
CONSTRU
ML200

Availability of leveled & graded land,water & electri...

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

20-Dec-11*

821 24-Sep-10

22-Dec-12

576 24-Sep-10

21-Apr-12

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

24-Sep-10*

Page 1 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

ML201

Unit-1 Readiness of site access road for transporta...

22-Nov-10*

ML202

Unit-1 Service (AB) bay readiness for erection of E...

21-May-11*

ML215

***Unit-1 Service (BC) bay readiness for erection o...

11-Jul-11*

ML216

***Unit-1 Readiness of GSC structural foundation (...

22-Aug-11*

ML204

Unit-1 Readiness of '9' mtrs floor

22-Aug-11*

ML225

***Unit-1 Readiness of BFP foundations (at '0' mtr ...

22-Sep-11*

ML207

Unit-1 TG bldg readiness for STG erection

22-Sep-11*

ML205

Unit-1 Clearance for insitu Condenser erection

22-Sep-11*

ML219

***Unit-1 Readiness of Vacuum pump foundations(...

22-Sep-11*

ML206

Unit-1 Readiness of '0' mtr floor

22-Sep-11*

ML224

***Unit-1 Readiness of CEP foundations (at '(-)5' m...

22-Sep-11*

ML221

***Unit-1 Readiness of PHE foundations (at '0' mtr ...

22-Sep-11*

ML222

***Unit-1 Readiness of DMCW Pump foundations (...

22-Sep-11*

ML223

***Unit-1 Readiness of CPU foundations (at '0' mtr ...

22-Sep-11*

ML220

***Unit-1 Readiness of HP/LP Flash tank foundatio...

22-Sep-11*

ML227

***Unit-1 Readiness of Turbine Preservation sys fd...

22-Nov-11*

ML228

***Unit-1 Readiness of HPH 6A & 6B structural fou...

22-Nov-11*

ML209

Unit-1 Readiness of Strand Jack foundation for Ge...

22-Nov-11*

ML226

***Unit-1 Readiness of LPH 3 & 4 structural founda...

22-Nov-11*

ML208

Unit-1 Readiness of '17' mtrs floor

22-Nov-11*

ML218

***Unit-1 Readiness of CW BF v/vs & Pipe support...

22-Dec-11*

ML231

***Unit-1 Readiness of DMCW Expansion tank fou...

21-Jan-12*

ML210

Unit-1 Readiness of '31' mtrs floor

21-Jan-12*

ML230

***Unit-1 Readiness of Deaerator foundation (at '3...

21-Jan-12*

ML229

***Unit-1 Readiness of HPH 7A,7B,8A & 8B struct...

21-Jan-12*

ML213

Unit-1 Readiness of electrical & instrumentation ea...

22-Mar-12*

ML211

Unit-1 Readiness of AC/DC/UPS Panel & Battery b...

22-Mar-12*

ML212

Unit-1 Main & Service building readiness for Elevat...

22-Mar-12*

ML214

Unit-1 Readiness of Control room for DCS & Mars...

21-Apr-12*

COMMISSIONING PHASE
COMMISS
Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone

488 22-Aug-11

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

22-Dec-12

Page 2 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

ML300

Unit-1 Readiness of 415V supply for EOT & Elevator

22-Aug-11*

ML301

Unit-1 Availability of trained O&M manpower for co...

22-May-12*

ML302

Unit-1 Availability of DM water at terminal points at...

22-May-12*

ML308

Unit-1 Availibility of Auxillary cooling water at termi...

21-Jul-12*

ML304

Unit-1 Readiness of 415V,3.3KV,11KV & Emergen...

21-Jul-12*

ML303

Unit-1 Readiness of HVAC system for DCS commi...

21-Jul-12*

ML305

Unit-1 Readiness of 220V & 24V DC power supply ...

21-Jul-12*

ML306

Unit-1 Readiness of Fire protection, detection & al...

21-Jul-12*

ML307

Unit-1 Availability of Instru & Service air at terminal...

21-Jul-12*

ML309

Unit-1 Availability of Condenser cooling water at te...

22-Sep-12*

ML310

Unit-1 Readiness of GT, UAT, GCB & Switchyards

22-Dec-12*

LAYOUT & LOADING SUBMISSION

487 23-Sep-09 A

22-Jan-10 A

EN200

TG hall Main & Aux. Column

105 23-Sep-09 A

22-Jan-10 A

EN204

Other equipments, Floors & Control room

236 23-Dec-09 A

22-Jan-10 A

EN201

TG Foundation including deck

104 23-Dec-09 A

19-Jan-10 A

EN202

Condenser Pit

104 23-Dec-09 A

19-Jan-10 A

EN203

BFP & CEP

130 23-Dec-09 A

19-Jan-10 A

COMMON SYSTEM
ENGINEERING
ENGINEE

1389 23-Jul-09 A

11-May-13

815 23-Jul-09 A

02-Jan-12

EN100

Major Engineering

324 23-Jul-09 A

26-Nov-10

EN101

Balance Engineering

575 15-Dec-09 A

02-Jan-12

587 25-Jan-10 A

12-Oct-11

EOT CRANE
CRA
FOR TG BUILDING
CMN10

Ordering

75 25-Jan-10 A

24-May-10 A

CMN20

Product Engineering

48 01-Jun-10 A

29-Sep-10

CMN30

Manufacturing

CMN70
CMN80

160 01-Jul-10 A

07-Mar-11

Supply of Main Girder for Crane-2

52 07-Mar-11

06-May-11

Supply of Trolley for Crane-2

52 07-Mar-11

06-May-11

CMN90

Supply of Balance & Misc items for Crane-2

52 07-Mar-11

06-May-11

CMN60

Supply of Balance & Misc items for Crane-1

52 07-Mar-11

06-May-11

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 3 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

CMN40

Supply of Main Girder for Crane-1

52 07-Mar-11

06-May-11

CMN50

Supply of Trolley for Crane-1

52 07-Mar-11

06-May-11

CMN100

Mounting of L T. wheels with the individual Girders

30 06-May-11

10-Jun-11

CMN110

Lifting and placement of Girders,End carriage on t...

50 10-Jun-11

08-Aug-11

CMN120

Erection of Electrical panels and completing other ...

41 08-Aug-11

24-Sep-11

CMN130

Assembling Wire Rope with Hooks and weaving o...

41 08-Aug-11

24-Sep-11

CMN140

Commissioning of Crane No 1 & 2

15 24-Sep-11

12-Oct-11

490 25-Jan-10 A

05-Sep-11

EOT FOR BFP


CMN150

Ordering

90 25-Jan-10 A

24-May-10 A

CMN160

Product Engineering

45 01-Jul-10 A

29-Sep-10

CMN170

Manufacturing

145 02-Aug-10 A

19-Feb-11

CMN190

Supply of Trolley

60 19-Feb-11

30-Apr-11

CMN200

Supply of Balance & Misc items

60 19-Feb-11

30-Apr-11

CMN180

Supply of Main Girder

60 19-Feb-11

30-Apr-11

CMN210

Mounting of L T. wheels with the individual Girders

15 12-Jul-11

28-Jul-11

CMN220

Lifting and placement of Girders, End carriage on t...

16 29-Jul-11

16-Aug-11

CMN230

Erection of Electrical panels and completing other ...

10 17-Aug-11

27-Aug-11

CMN240

Assembling Wire Rope with Hooks and weaving o...

10 17-Aug-11

27-Aug-11

CMN250

Commissioning of Crane

7 29-Aug-11

05-Sep-11

756 24-Mar-10 A

31-Dec-12

ELEVATOR FOR MAIN & SERVICE BUILDING


ELEVATO
CMN260

Ordering

90 24-Mar-10 A

06-Dec-10

CMN270

Product Engineering

60 07-Dec-10

14-Feb-11

CMN280

Manufacturing

172 15-Feb-11

02-Sep-11

CMN290

Supply of Counterweights

60 03-Sep-11

11-Nov-11

CMN300

Supply of Lift Cars

60 03-Sep-11

11-Nov-11

CMN310

Supply of Winding units

60 03-Sep-11

11-Nov-11

CMN320

Supply of Electrical Motors & accessories

60 03-Sep-11

11-Nov-11

CMN330

Supply of Balance & Misc items

60 03-Sep-11

11-Nov-11

CMN340

Installation of Steel guides for Elevator car

45 08-Jun-12

31-Jul-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 4 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

CMN350

Installation of Counterweight guard, Cocounterwei...

30 31-Jul-12

04-Sep-12

CMN360

Installation of Elevator car alongwith doors and oth...

55 04-Sep-12

07-Nov-12

CMN370

Installation of Electrical and Control equipments

45 15-Sep-12

07-Nov-12

CMN380

Commissioning of Main & Service Building Elevators

INSULATION
INSULAT
CMN390

Ordering

CMN400

Manufacturing

CMN410

Supply

CMN420

Application

PAINTS

70 10-Oct-12

31-Dec-12

454 05-Jan-12

03-Apr-13

90 05-Jan-12

19-Apr-12

100 19-Apr-12

14-Aug-12

90 10-Jul-12

23-Oct-12

139 23-Oct-12

03-Apr-13

437 29-Feb-12

11-May-13

CMN430

Ordering

90 29-Feb-12

13-Jun-12

CMN440

Manufacturing

60 13-Jun-12

22-Aug-12

CMN450

Supply

100 22-Aug-12

17-Dec-12

CMN460

Application

MISC ITEM
ITE FOR COMMON SYSTEM

92 25-Jan-13

11-May-13

500 10-May-11

21-Sep-12

CMN470

Ordering

90 10-May-11

23-Aug-11

CMN480

Product Engineering

60 23-Aug-11

01-Nov-11

CMN490

Manufacturing

189 01-Nov-11

08-Jun-12

CMN500

Supply for Unit-1 & 2

180 24-Feb-12

21-Sep-12

1475 23-Jul-09 A

05-Aug-13

1398 23-Jul-09 A

20-May-13

1050 23-Jul-09 A

06-Jun-12

STG SYSTEM
SYST
TURBINE
MANUFACTURING & SUPPLY
MANUFAC

856 23-Jul-09 A
29 23-Jul-09 A

25-Nov-11
25-Aug-09 A

STG1 Product Engineering

500 26-Aug-09 A

06-May-11

STG2 Procurement of Raw Material, Forgings & Castings...

260 13-Jan-10 A

09-Oct-10

STG3 Machining of Rotors

337 01-Mar-10 A

11-Dec-10

STG4 Stationary/Rotating Blades & Blade rings

334 26-Apr-10 A

19-Jan-11

STG5 Diaphragms

311 26-Apr-10 A

24-Mar-11

MANUF
MANUFACTURING
STG8 Ordering

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 5 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

STG6 Machining of Castings

287 26-Jul-10 A

24-Mar-11

STG8 HIPT Pedestal

217 24-Sep-10

03-Jun-11

STG7 Balance & Misc items including Electrical & C&I ite...

237 24-Sep-10

27-Jun-11

STG9 Assembly & Testing of Turbine

130 28-Jun-11

25-Nov-11

535 20-Dec-10
26 20-Dec-10

06-Jun-12
18-Jan-11

STG1 LPT-1 & 2 Casings

59 17-Nov-11

24-Jan-12

STG1 Bearing Pedestal for HIPT

33 17-Nov-11

24-Dec-11

STG1 LPT-1 & 2 Rotors

55 22-Nov-11

24-Jan-12

STG1 HIPT Rotor

53 24-Nov-11

24-Jan-12

STG1 HIPT Casings

57 24-Nov-11

28-Jan-12

STG1 LPT-1 & 2 other miscellaneous items

95 26-Nov-11

15-Mar-12

STG1 HIPT other miscellaneous items

85 26-Nov-11

03-Mar-12

STG1 Other auxiliaries & systems like Lube oil system, Pi...

122 26-Nov-11

16-Apr-12

STG1 Balance & Misc items including Electrical & C&I ite...

106 04-Feb-12

06-Jun-12

590 23-Sep-11

04-May-13

STG200 HIPT Brg Pedestal and LPT 1&2- Chipping of fdn ...

52 23-Sep-11

22-Nov-11

STG210 HIPT Brg Pedestal and LPT 1&2- Fixing of Seatin...

30 26-Dec-11

28-Jan-12

STG220 HIPT- Placement of bottom half, internals and leve...

60 30-Jan-12

07-Apr-12

STG230 LPT 1- Placement of bottom half, internals and lev...

60 10-Feb-12

19-Apr-12

STG240 LPT 2- Placement of bottom half, internals and lev...

60 22-Feb-12

01-May-12

SUPPLY
STG1 Embedded parts for HIPT, LPT-1 and LPT-2

ERECTION

STG250 HIPT- Placement of Rotor in Position and its cente...

80 09-Apr-12

10-Jul-12

105 16-Apr-12

15-Aug-12

STG260 LPT 1- Placement of Rotor in Position and its cent...

70 20-Apr-12

10-Jul-12

STG270 LPT 2- Placement of Rotor in Position and its cent...

60 02-May-12

10-Jul-12

STG290 Erection of MSV/GVs & RSV/ICVs

92 14-May-12

28-Aug-12

STG300 Alignment of HIPT, LPT-1 & LPT-2 Rotors

39 11-Jul-12

24-Aug-12

STG310 Coupling of Turbine Rotors

30 25-Aug-12

28-Sep-12

STG320 Setting of Steam path clearances and boxing up

48 29-Sep-12

23-Nov-12

STG330 Erection of Turning gear motor

33 09-Feb-13

20-Mar-13

STG280 Erection of Lube, Jacking, EH Oil System

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 6 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name
STG340 Erection of Turbine enclosure

Original Start
Duration

Finish

19 12-Apr-13

04-May-13

265 29-Aug-12

20-May-13

60 29-Aug-12

06-Nov-12

STG360 Turning gear operation

5 06-Apr-13

12-Apr-13

STG370 Steam rolling & overspeed testing

6 13-May-13

20-May-13

COMMISSIONING
COMMISS
STG350 Lube oil flushing and normalisation

1475 23-Jul-09 A

05-Aug-13

971 23-Jul-09 A

19-Mar-12

820 23-Jul-09 A
29 23-Jul-09 A

20-Oct-11
25-Aug-09 A

STG3 Product Engineering

500 26-Aug-09 A

12-May-11

STG3 Procurement of Raw Material, Forgings & Castings...

260 13-Jan-10 A

03-Nov-10

STG4 Stator Machining & Winding

200 20-Feb-10 A

18-Nov-10

STG4 Rotor Machining & Winding

185 20-Feb-10 A

20-Nov-10

STG4 Manufacturing of Other Auxiliries

140 01-Sep-10 A

09-Feb-11

STG4 Manufacturing of Balance & Miscellaneous items

217 09-Feb-11

20-Oct-11

456 20-Dec-10
26 20-Dec-10

19-Mar-12
18-Jan-11

STG4 Stator

129 20-Oct-11

19-Mar-12

STG4 Rotor

114 20-Oct-11

01-Mar-12

STG4 Bearing Pedestal

99 20-Oct-11

13-Feb-12

STG4 Exciter

84 24-Nov-11

01-Mar-12

STG4 Control panels

84 24-Nov-11

01-Mar-12

STG5 Balance & Misc items including Electrical & C&I ite...

84 24-Nov-11

01-Mar-12

367 23-Nov-11

23-Nov-12

STG510 Erection of Strand Jack lifting arrangement

50 23-Nov-11

19-Jan-12

STG520 Lifting of Stator and its placement in position

10 23-Mar-12

03-Apr-12

STG770 Preparation for Rotor threading and electrical testi...

30 04-Apr-12

08-May-12

STG530 Rotor threading

10 09-May-12

19-May-12

STG780 Lowering of Generator Rotor on Bearings

15 21-May-12

06-Jun-12

STG790 Mounting of Fan blades on Rotor

10 07-Jun-12

18-Jun-12

GENERATOR
GENERA
MANUFACTURING & SUPPLY
MANUFAC
MANUF
MANUFACTURING
STG8 Ordering

SUPPLY
STG4 Embedded parts for Generator

ERECTION

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 7 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

STG550 Erection of Seal oil System

25 14-Jun-12

13-Jul-12

STG800 Runout of Coupling half of Generator rotor at both ...

10 19-Jun-12

29-Jun-12

STG560 Erection of Generator Gas (H2, CO2) system

25 13-Jul-12

11-Aug-12

STG540 Erection of Stator Cooling water System

25 11-Aug-12

10-Sep-12

STG570 Alignment of Generator Rotor with Turbine Rotor

26 25-Aug-12

24-Sep-12

STG580 Coupling of Gen. Rotor with Turbine Rotor

14 25-Sep-12

10-Oct-12

STG590 Erection of Exciter

15 11-Oct-12

27-Oct-12

STG600 Boxing up of Bearing Pedestal of Generator

23 29-Oct-12

23-Nov-12

329 10-Sep-12

05-Aug-13

STG610 Flushing of Stator water cooling system

10 10-Sep-12

21-Sep-12

STG620 Tightness test of Generator (Air & H2)

20 12-Apr-13

06-May-13

STG650 STG full loading & Stabilisation

36 07-Jun-13

19-Jul-13

COMMISSIONING
COMMISS

STG630 Synchronization on Oil

07-Jun-13*

STG640 Synchronization on Coal

07-Jun-13*

STG660 Trial run

TURBINE PRESERVATION SYSTEM

14 19-Jul-13

05-Aug-13

581 31-May-11

31-Dec-12

STG670

Ordering

90 31-May-11

12-Sep-11

STG680

Product Engineering

60 13-Sep-11

21-Nov-11

STG690

Manufacturing

189 22-Nov-11

28-Jun-12

STG700

Supply of Turbine Preservation system & its acces...

150 25-May-12

15-Nov-12

STG710

Erection

75 22-Sep-12

19-Dec-12

STG720

Commissioning

MISC ITEM
ITE FOR STG SYSTEM

10 19-Dec-12

31-Dec-12

500 10-May-11

21-Sep-12

STG730

Ordering

90 10-May-11

23-Aug-11

STG740

Product Engineering

60 23-Aug-11

01-Nov-11

STG750

Manufacturing

189 01-Nov-11

08-Jun-12

STG760

Supply for Unit-1 & 2

FEED WATER
WAT
SYSTEM
ENGINEERING
ENGINEE
Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone

180 24-Feb-12

21-Sep-12

1400 23-Jul-09 A

22-May-13

815 23-Jul-09 A

02-Jan-12

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 8 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

EN102

Major Engineering

339 23-Jul-09 A

29-Nov-10

EN103

Balance Engineering

575 15-Dec-09 A

02-Jan-12

DEAERATOR
DEAERAT

1270 23-Jul-09 A

12-Jan-13

FW100

Ordering

FW10

Product Engineering

208 22-Sep-09 A

16-Feb-11

FW20

Procurement of Raw Material, Nozzles, Flanges etc

276 01-Jun-10 A

18-Jun-11

FW40

Fabrication of Shells

136 12-Mar-11

18-Aug-11

FW30

Forming of Dish ends

136 12-Mar-11

18-Aug-11

FW50

Assembly of Deaerator

100 18-Aug-11

13-Dec-11

FW1050

Readiness of Strand Jack foundation for Deaerator...

FW70

Supply of Balance & Miscellaneous items

166 13-Dec-11

23-Jun-12

FW60

Supply of Deaerator & its accessories

166 13-Dec-11

23-Jun-12

FW80

Erection of Strand Jack lifting arrangement

50 13-Mar-12

10-May-12

FW90

Placement, Leveling, Centering, Preassembly & A...

70 23-Jun-12

13-Sep-12

FW110

Hydraulic test of Deaerator

10 13-Sep-12

25-Sep-12

FW120

Commissioning of Deaerator

25 15-Dec-12

12-Jan-13

1181 29-Dec-09 A

26-Mar-13

MDBFP

52 23-Jul-09 A

21-Sep-09 A

30-Sep-11*

FW130

Ordering

FW140

Product Engineering

120 26-Jul-10 A

07-Oct-10

FW150

Manufacturing

338 09-Aug-10 A

06-Sep-11

FW160

Supply of MDBFP-1 & its accessories

90 06-Sep-11

20-Dec-11

FW170

Supply of MDBFP-2 & its accessories

90 06-Sep-11

20-Dec-11

FW180

Erection of MDBFP-1 including all its accessories

80 20-Dec-11

22-Mar-12

FW200

Erection of MDBFP-2 including all its accessories

80 22-Mar-12

23-Jun-12

FW210

Erection of Oil system

30 23-Jun-12

28-Jul-12

FW220

Erection of Cooling water system for Motor

30 28-Jul-12

01-Sep-12

FW230

Cleaning of Oil pipes & Normalization

15 01-Sep-12

19-Sep-12

FW240

Trial run of Motors

15 24-Sep-12

11-Oct-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

45 29-Dec-09 A

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

24-May-10 A

Page 9 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name
FW250

Commissioning of MDBFPs

TDBFP

Original Start
Duration

Finish

45 02-Feb-13

26-Mar-13

1238 29-Dec-09 A

22-May-13

FW260

Ordering

FW270

Product Engineering

120 26-Jul-10 A

07-Oct-10

FW280

Manufacturing

338 09-Aug-10 A

06-Sep-11

FW300

Supply of TDBFP-1 & Accessories

90 06-Sep-11

20-Dec-11

FW290

Supply of TDBFP-2 & Accessories

90 06-Sep-11

20-Dec-11

FW310

Erection of TDBFP-1 including all its accessories

80 20-Dec-11

22-Mar-12

FW330

Erection of TDBFP-2 including all its accessories

80 22-Mar-12

23-Jun-12

FW340

Erection of Oil System

30 07-Sep-12

11-Oct-12

FW350

Cleaning of Oil pipes & Normalization

15 12-Oct-12

29-Oct-12

FW360

Commissioning of TDBFP

49 27-Mar-13

22-May-13

1185 14-Apr-10 A

22-May-13

DRIVE TURBINE
TU
(FOR TDBFP)

45 29-Dec-09 A

24-May-10 A

FW370

Ordering

FW380

Product Engineering

120 24-Sep-10

10-Feb-11

FW390

Manufacturing

395 03-Dec-10

07-Mar-12

FW400

Supply of Drive Turbine-1 & Accessories

142 08-Mar-12

20-Aug-12

FW410

Supply of Drive Turbine-2 & Accessories

142 08-Mar-12

20-Aug-12

FW420

Chipping of Foundation and fixing of packers and ...

20 21-Jun-12

13-Jul-12

FW430

Placement, levelling and centering of Turbine module

22 14-Jul-12

08-Aug-12

FW440

Alignment of Turbine with BFP & Gear box

25 09-Aug-12

06-Sep-12

FW450

Erection of Oil System

30 07-Sep-12

11-Oct-12

FW1080

Cleaning of Oil pipes & Normalization

15 12-Oct-12

29-Oct-12

FW460

Turning Gear operation of Drive turbines

10 30-Oct-12

09-Nov-12

FW470

Commissioning of Drive Turbines

49 27-Mar-13

22-May-13

1282 23-Jul-09 A

24-Jan-13

1053 23-Jul-09 A

09-Jun-12

HPH
MANUFACTURING & SUPPLY
MANUFAC
FW1090 Ordering
FW480

Product Engineering

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

50 14-Apr-10 A

52 23-Jul-09 A
200 22-Sep-09 A

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

23-Aug-10 A

21-Sep-09 A
16-Oct-10

Page 10 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

FW490

Procurement of Raw Material, Tubes, Forgings etc

186 03-Feb-10 A

15-Feb-11

FW500

Fabrication of Shells

199 16-Dec-10

05-Aug-11

FW510

Machining and Drilling of Tube sheets

120 15-Feb-11

05-Jul-11

FW520

Forming of Dish ends

147 15-Feb-11

05-Aug-11

FW530

Tubing

50 05-Jul-11

01-Sep-11

FW540

Assembly

152 01-Sep-11

25-Feb-12

FW550

Supply of HPH 6A & 6B with accessories

90 27-Dec-11

10-Apr-12

FW570

Supply of HPH 8A & 8B with accessories

90 25-Feb-12

09-Jun-12

FW560

Supply of HPH 7A & 7B with accessories

90 25-Feb-12

09-Jun-12

289 10-Apr-12

24-Jan-13

Erection of HPH 6A

45 10-Apr-12

01-Jun-12

FW1060 Erection of HPH 6B

45 01-Jun-12

24-Jul-12

FW590

Erection of HPH 7A & 7B

45 09-Jun-12

01-Aug-12

FW1070 Erection of HPH 8A & 8B

45 01-Aug-12

22-Sep-12

FW600

Mounting of Acessories (safety valves,vents and d...

50 22-Sep-12

20-Nov-12

FW610

Commissioning of HPHs

ERECTION & COMMISSIONING


ERECTIO
FW580

HP VALVE
VALV OF FEED WATER SYSTEM

35 15-Dec-12

24-Jan-13

400 17-May-10 A

10-Jan-12

FW680

Ordering

90 17-May-10 A

06-Dec-10

FW690

Product Engineering

60 07-Dec-10

14-Feb-11

FW700

Manufacturing

193 15-Feb-11

27-Sep-11

FW710

Supply for Unit-1 & 2

180 15-Jun-11

10-Jan-12

435 19-Jul-11

26-Sep-12

LP PIPING & FITTING OF FEED WATER SYST...


FW720

Ordering

90 19-Jul-11

01-Nov-11

FW730

Product Engineering

53 01-Nov-11

02-Jan-12

FW740

Manufacturing

140 02-Jan-12

13-Jun-12

FW750

Supply for Unit-1 & 2

180 29-Feb-12

26-Sep-12

330 21-Sep-10 A

11-Nov-11

LP VALVE
VALV OF FEED WATER SYSTEM
FW760

Ordering

90 21-Sep-10 A

16-Dec-10

FW770

Product Engineering

53 17-Dec-10

16-Feb-11

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 11 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

FW780

Manufacturing

140 17-Feb-11

29-Jul-11

FW790

Supply for Unit-1 & 2

180 16-Apr-11

11-Nov-11

435 19-Jul-11

26-Sep-12

90 19-Jul-11

01-Nov-11

H&S OF F
FEED WATER SYSTEM
FW800

Ordering

FW810

Product Engineering

53 01-Nov-11

02-Jan-12

FW820

Manufacturing

140 02-Jan-12

13-Jun-12

FW830

Supply for Unit-1 & 2

180 29-Feb-12

26-Sep-12

435 19-Jul-11

26-Sep-12

90 19-Jul-11

01-Nov-11

MISC ITEM
ITE OF FEED WATER SYSTEM
FW1010

Ordering

FW1020

Product Engineering

53 01-Nov-11

02-Jan-12

FW1030

Manufacturing

140 02-Jan-12

13-Jun-12

FW1040

Supply for Unit-1 & 2

180 29-Feb-12

26-Sep-12

633 10-May-11

01-Feb-13

HP PIPING
PIPIN & FITTING OF FEED WATER SYS...
FW620

Ordering

90 10-May-11

23-Aug-11

FW630

Product Engineering

60 23-Aug-11

01-Nov-11

FW640

Manufacturing

193 01-Nov-11

13-Jun-12

FW650

Supply for Unit-1 & 2

210 25-Jan-12

26-Sep-12

FW660

Erection of FW System piping (along with LP Pipin...

85 07-Sep-12

14-Dec-12

FW670

Commissioning of FW System piping (Hydro test,C...

42 15-Dec-12

01-Feb-13

490 09-Jun-11

11-Oct-12

EXPANSION JOINT (DRIVE TURBINE EXHAU...


EXPANSI
FW840

Ordering

90 09-Jun-11

22-Sep-11

FW850

Product Engineering

60 22-Sep-11

01-Dec-11

FW860

Manufacturing

174 01-Dec-11

21-Jun-12

FW870

Supply for Unit-1 & 2

150 12-Apr-12

04-Oct-12

FW880

Erection

BUTTERFLY VALVE (DRIVE TURBINE EXHA...


BUTTERF

30 07-Sep-12

11-Oct-12

742 25-Jun-10 A

30-Oct-12

FW890

Ordering

90 25-Jun-10 A

06-Dec-10

FW900

Product Engineering

60 07-Dec-10

14-Feb-11

FW910

Manufacturing

344 15-Feb-11

21-Mar-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 12 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

FW920

Supply for Unit-1 & 2

180 12-Jan-12

08-Aug-12

FW930

Erection

20 26-Sep-12

18-Oct-12

FW940

Commissioning

10 19-Oct-12

30-Oct-12

592 25-Apr-11

07-Dec-12

2/3 WAY VALVES (FOR HPH ISOLATION IN F...


FW950

Ordering

90 25-Apr-11

08-Aug-11

FW960

Product Engineering

60 08-Aug-11

17-Oct-11

FW970

Manufacturing

225 17-Oct-11

05-Jul-12

FW980

Supply for Unit-1 & 2

180 17-Apr-12

13-Nov-12

FW990

Erection

34 18-Oct-12

26-Nov-12

FW1000

Commissioning

10 27-Nov-12

07-Dec-12

CONDENSATE SYSTEM
CONDENS
ENGINEERING
ENGINEE
EN104

Major Engineering

EN105

Balance Engineering

CONDENSER
CONDEN
MANUFACTURING & SUPPLY
MANUFAC

1319 23-Jul-09 A

02-Mar-13

815 23-Jul-09 A

02-Jan-12

324 23-Jul-09 A

26-Nov-10

575 15-Dec-09 A

02-Jan-12

1115 23-Jul-09 A

10-Aug-12

1000 23-Jul-09 A

17-Apr-12

822 23-Jul-09 A
52 23-Jul-09 A

22-Oct-11
21-Sep-09 A

CND1 Product Engineering

200 22-Sep-09 A

02-Dec-10

CND2 Procurement of Raw Material,Tubes etc

226 10-May-10 A

06-Nov-10

CND3 Machining & Drilling Tube Sheets & Tube Support ...

162 02-Oct-10

09-Apr-11

CND4 Fabrication & Machining of Water Boxes at Shop

300 06-Nov-10

22-Oct-11

496 08-Dec-10
90 08-Dec-10

17-Apr-12
23-Mar-11

114 09-Apr-11

20-Aug-11

CND7 Tube sheets & Tube Support plates

67 09-Apr-11

27-Jun-11

CND6 Lower exhaust neck parts

86 30-Apr-11

09-Aug-11

CND1 Expansion bellows

86 30-Apr-11

09-Aug-11

190 22-Jul-11

29-Feb-12

MANUF
MANUFACTURING
CND1 Ordering

SUPPLY
CND5 Hotwell parts & Shell panels
CND8 Tubes

CND1 Balance & Miscellaneous items


Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 13 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name
CND9 Water boxes & accessories

ASSEMBLY,ERECTION & COMMISSIONING


ASSEMBL
CND120 Assembly of Shell panels & Hotwell parts
CND130 Tube sheets & Tube support plates assembly
CND140 Tubebundles assembly
CND830 Preassembly of Lower exhaust necks & Expansion...
CND145 Condenser insitu erection start
CND820 Hanging of Condesnser neck & Expansion bellow ...

Original Start
Duration

Finish

152 22-Oct-11

17-Apr-12

541 16-Feb-11

10-Aug-12

90 16-Feb-11

01-Jun-11

97 01-Jun-11

22-Sep-11

110 06-Jun-11

12-Oct-11

30 09-Aug-11

13-Sep-11

0 12-Oct-11
10 12-Oct-11

24-Oct-11

106 24-Oct-11

24-Feb-12

CND190 Piping & Miscellaneous work

66 29-Feb-12

16-May-12

CND170 Erection of LPH 1A/2A & 1B/2B

20 10-Apr-12

03-May-12

CND180 Expansion bellows & Lower Exhaust neck erection...

60 03-May-12

12-Jul-12

CND200 Water box assembly

15 12-Jul-12

30-Jul-12

CND210 Hydro test of Steam and Waterside

10 30-Jul-12

10-Aug-12

1078 13-Jan-10 A

04-Feb-13

CND160 Shell Panels, Hotwell & Tubebundles erection

CEP
CND220

Ordering

CND230

Product Engineering

120 26-Jul-10 A

24-Sep-10 A

CND240

Manufacturing

308 16-Aug-10 A

02-Aug-11

CND250

Supply of CEP-1and its accessories

60 28-Jun-11

06-Sep-11

CND270

Supply of CEP-3 and its accessories

60 28-Jun-11

06-Sep-11

CND260

Supply of CEP-2 and its accessories

60 28-Jun-11

06-Sep-11

CND280

Erection CEP-1and its accessories

45 23-Sep-11

14-Nov-11

CND790

Erection CEP-2 and its accessories

45 15-Nov-11

05-Jan-12

CND290

Erection CEP-3 and its accessories

45 06-Jan-12

27-Feb-12

CND300

Trial run of Motors

15 23-Aug-12

10-Sep-12

CND310

Commissioning of CEPs

17 15-Jan-13

04-Feb-13

1034 15-Apr-10 A

02-Mar-13

CPU (3 X 50%)
CND320

Ordering

CND330

Product Engineering

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

90 13-Jan-10 A

90 15-Apr-10 A
120 24-Sep-10

24-May-10 A

24-Sep-10 A
10-Feb-11

Page 14 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

CND340

Manufacturing

218 07-Jan-11

17-Sep-11

CND350

Supply of Skid with Pumps & its accessories

90 15-Aug-11

26-Nov-11

CND360

Supply of Vessels & Tanks with its accessories

90 15-Aug-11

26-Nov-11

CND370

Supply of Balance & Miscellaneous items

120 19-Sep-11

04-Feb-12

CND380

Erection of CPU-1 & its accessories including Elec...

45 24-Oct-11

14-Dec-11

CND800

Erection of CPU-2 & its accessories including Elec...

45 15-Dec-11

04-Feb-12

CND810

Erection of CPU-3 & its accessories including Elec...

45 06-Feb-12

28-Mar-12

CND390

Commissioning

LPH
MANUFACTURING & SUPPLY
MANUFAC
CND840 Ordering

23 04-Feb-13

02-Mar-13

1273 23-Jul-09 A

15-Jan-13

993 23-Jul-09 A

10-Apr-12

52 23-Jul-09 A

21-Sep-09 A

CND400 Product Engineering

200 22-Sep-09 A

16-Oct-10

CND410 Procurement of Raw Material,Tubes,Forgings etc

186 03-Feb-10 A

15-Feb-11

CND420 Fabrication of Shells

199 16-Dec-10

05-Aug-11

CND440 Forming of Dish ends

147 15-Feb-11

05-Aug-11

CND430 Machining and Drilling of Tube sheets

120 15-Feb-11

05-Jul-11

CND450 Tubing

50 05-Jul-11

01-Sep-11

100 01-Sep-11

27-Dec-11

CND480 Supply of LPH-4 and its accessories

90 27-Dec-11

10-Apr-12

CND490 Supply of LPH-1A/2A and its accessories

90 27-Dec-11

10-Apr-12

CND500 Supply of LPH-1B/2B and its accessories

90 27-Dec-11

10-Apr-12

CND460 Assembly

CND470 Supply of LPH-3 and its accessories

90 27-Dec-11

10-Apr-12

ERECTION & COMMISSIOING


ERECTIO

280 10-Apr-12

15-Jan-13

CND510 Erection of LPH-3 & 4

110 10-Apr-12

16-Aug-12

60 16-Aug-12

25-Oct-12

30 11-Dec-12

15-Jan-13

CND520 Erection of Drains, Vents and safety Valves


CND530 Commissioning of LPHs

GSC (L&T-MHI
(L&T
SCOPE)

1319 23-Jul-09 A

02-Mar-13

CND850

Ordering

27 23-Jul-09 A

22-Aug-09 A

CND540

Product Engineering

90 22-Dec-10

05-Apr-11

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 15 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

CND550

Manufacturing

188 06-Apr-11

10-Nov-11

CND570

Supply of Exhauster and its accessories

60 11-Nov-11

19-Jan-12

CND560

Supply of Gland Steam Cooler and its accessories

60 11-Nov-11

19-Jan-12

CND580

Erection of Gland Steam Cooler & Exhausters

60 20-Jan-12

29-Mar-12

CND590

Erection of seal steam regulating valve & Piping

60 30-Mar-12

07-Jun-12

CND600

Commissioning of GSC

23 04-Feb-13

02-Mar-13

333 21-Sep-10 A

14-Nov-11

90 21-Sep-10 A

16-Dec-10

LP VALVES
VALV
OF CONDENSATE SYSTEM
CND670

Ordering

CND680

Product Engineering

53 17-Dec-10

16-Feb-11

CND690

Manufacturing

142 17-Feb-11

01-Aug-11

CND700

Supply for Unit-1 & 2

150 24-May-11

14-Nov-11

437 19-Jul-11

28-Sep-12

90 19-Jul-11

01-Nov-11

H&S OF C
CONDENSATE SYSTEM
CND710

Ordering

CND720

Product Engineering

53 01-Nov-11

02-Jan-12

CND730

Manufacturing

142 02-Jan-12

15-Jun-12

CND740

Supply for Unit-1 & 2

150 06-Apr-12

28-Sep-12

437 19-Jul-11

28-Sep-12

MISC ITEMS
ITE
OF CONDENSATE SYSTEM
CND750

Ordering

90 19-Jul-11

01-Nov-11

CND760

Product Engineering

53 01-Nov-11

02-Jan-12

CND770

Manufacturing

142 02-Jan-12

15-Jun-12

CND780

Supply for Unit-1 & 2

150 06-Apr-12

28-Sep-12

546 19-Jul-11

15-Jan-13

LP PIPING & FITTING OF CONDENSATE SYS...


CND610

Ordering

90 19-Jul-11

01-Nov-11

CND620

Product engineering

53 01-Nov-11

02-Jan-12

CND630

Manufacturing

142 02-Jan-12

15-Jun-12

CND640

Supply for Unit-1 & 2

180 02-Mar-12

28-Sep-12

CND650

Erection of Condensate System piping (along with ...

100 16-Aug-12

11-Dec-12

CND660

Commissioning of Condensate Sys piping (Hydro t...

30 11-Dec-12

15-Jan-13

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 16 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

VACUUM SYSTEM
S
ENGINEERING
ENGINEE

Original Start
Duration

Finish

1287 23-Jul-09 A

29-Jan-13

815 23-Jul-09 A

03-Jan-12

EN106

Major Engineering

332 23-Jul-09 A

27-Nov-10

EN107

Balance Engineering

576 14-Dec-09 A

03-Jan-12

1020 25-Feb-10 A

29-Jan-13

90 25-Feb-10 A

06-Dec-10

VACUUM PUMP
VAC10

Ordering

VAC20

Product Engineering

120 07-Dec-10

25-Apr-11

VAC30

Manufacturing

203 15-Feb-11

08-Oct-11

VAC70

Supply of Vacuum pump-4 & its accessories

90 10-Oct-11

21-Jan-12

VAC60

Supply of Vacuum pump-3 & its accessories

90 10-Oct-11

21-Jan-12

VAC50

Supply of Vacuum pump-2 & its accessories

90 10-Oct-11

21-Jan-12

VAC40

Supply of Vacuum pump-1 & its accessories

90 10-Oct-11

21-Jan-12

VAC80

Erection of Vacuum pump-1

45 23-Jan-12

14-Mar-12

VAC90

Erection of Vacuum pump-2

45 22-Feb-12

13-Apr-12

VAC100

Erection of Vacuum pump-3

45 22-Mar-12

12-May-12

VAC110

Erection of Vacuum pump-4

45 14-May-12

04-Jul-12

VAC120

Trial run of Motors

19 23-Aug-12

14-Sep-12

VAC130

Commissioning of Vacuum pumps

LP VALVE
VALV OF VACUUM SYSTEM

60 21-Nov-12

29-Jan-13

378 21-Sep-10 A

29-Dec-11

VAC190

Ordering

90 21-Sep-10 A

16-Dec-10

VAC200

Product engineering

53 17-Dec-10

16-Feb-11

VAC210

Manufacturing

151 17-Feb-11

11-Aug-11

VAC220

Supply for Unit-1 & 2

180 03-Jun-11

29-Dec-11

483 20-Jul-11

14-Nov-12

H&S OF V
VACUUM SYSTEM
VAC230

Ordering

90 20-Jul-11

02-Nov-11

VAC240

Product engineering

53 02-Nov-11

03-Jan-12

VAC250

Manufacturing

151 03-Jan-12

27-Jun-12

VAC260

Supply for Unit-1 & 2

180 18-Apr-12

14-Nov-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 17 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

MISC ITEM
ITE OF VACUUM SYSTEM

Original Start
Duration

Finish

483 20-Jul-11

14-Nov-12

VAC270

Ordering

90 20-Jul-11

02-Nov-11

VAC280

Product Engineering

53 02-Nov-11

03-Jan-12

VAC290

Manufacturing

151 03-Jan-12

27-Jun-12

VAC300

Supply for Unit-1 & 2

180 18-Apr-12

14-Nov-12

483 20-Jul-11

14-Nov-12

LP PIPING & FITTING OF VACUUM SYSTEM


VAC140

Ordering

90 20-Jul-11

02-Nov-11

VAC150

Product engineering

53 02-Nov-11

03-Jan-12

VAC160

Manufacturing

151 03-Jan-12

27-Jun-12

VAC170

Supply for Unit-1 & 2

180 18-Apr-12

14-Nov-12

VAC180

Erection of Vacuum System piping (along with LP ...

60 01-Sep-12

09-Nov-12

CLOSE COOLING
CO
WATER SYSTEM
ENGINEERING
ENGINEE

1196 23-Jul-09 A

30-Oct-12

815 23-Jul-09 A

02-Jan-12

EN108

Major Engineering

324 23-Jul-09 A

26-Nov-10

EN109

Balance Engineering

575 15-Dec-09 A

02-Jan-12

860 18-Feb-10 A

30-Oct-12

100 18-Feb-10 A

14-Dec-10

90 15-Dec-10

29-Mar-11

156 23-Feb-11

23-Aug-11

DMCW PUMP
PU
CCW10

Ordering

CCW20

Product Engineering

CCW30

Manufacturing

CCW50

Supply of DMCW Pump-2 & its accessories

60 24-Aug-11

01-Nov-11

CCW60

Supply of DMCW Pump-3 & its accessories

60 24-Aug-11

01-Nov-11

CCW40

Supply of DMCW Pump-1 & its accessories

60 24-Aug-11

01-Nov-11

CCW70

Erection of DMCW Pump-1

45 02-Nov-11

23-Dec-11

CCW80

Erection of DMCW Pump-2

45 24-Dec-11

14-Feb-12

CCW90

Erection of DMCW Pump-3

45 15-Feb-12

06-Apr-12

CCW100

Trial run of Motors

5 23-Aug-12

29-Aug-12

CCW110

Commissioning of DMCW Pumps

18 09-Oct-12

30-Oct-12

860 12-Feb-10 A

30-Oct-12

PHE
Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 18 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name
CCW120

Ordering

CCW130

Product Engineering

CCW140

Manufacturing

CCW150
CCW160

Original Start
Duration

Finish

100 12-Feb-10 A

14-Dec-10

75 15-Dec-10

11-Mar-11

141 12-Mar-11

23-Aug-11

Supply of PHE-1 & its accessories

60 24-Aug-11

01-Nov-11

Supply of PHE-2 & its accessories

60 24-Aug-11

01-Nov-11

CCW170

Supply of PHE-3 & its accessories

60 24-Aug-11

01-Nov-11

CCW180

Erection of PHE-1

30 02-Nov-11

06-Dec-11

CCW190

Erection of PHE-2

30 07-Dec-11

10-Jan-12

CCW200

Erection of PHE-3

30 11-Jan-12

14-Feb-12

CCW210

Commissioning of PHEs

18 09-Oct-12

30-Oct-12

DMCW EXPANSION
EX
TANK
CCW220

Ordering

CCW230

Product Engineering

CCW240

Manufacturing

CCW250

761 10-May-10 A

30-Oct-12

90 10-May-10 A

06-Dec-10

75 07-Dec-10

03-Mar-11

170 04-Mar-11

17-Sep-11

Supply of DMCW Expansion tank & its accessories

60 19-Sep-11

26-Nov-11

CCW260

Erection of DMCW Expansion tank

30 23-Jan-12

25-Feb-12

CCW270

Commissioning of DMCW Expansion tank

18 09-Oct-12

30-Oct-12

LP VALVES
VALV
OF CLOSE CW SYSTEM

337 21-Sep-10 A

18-Nov-11

CCW340

Ordering

90 21-Sep-10 A

16-Dec-10

CCW350

Product engineering

52 17-Dec-10

15-Feb-11

CCW360

Manufacturing

147 16-Feb-11

05-Aug-11

CCW370

Supply for Unit-1 & 2

180 23-Apr-11

18-Nov-11

442 19-Jul-11

03-Oct-12

H&S OF C
CLOSE CW SYSTEM
CCW380

Ordering

90 19-Jul-11

01-Nov-11

CCW390

Product engineering

52 01-Nov-11

31-Dec-11

CCW400

Manufacturing

147 31-Dec-11

20-Jun-12

CCW410

Supply for Unit-1 & 2

180 07-Mar-12

03-Oct-12

337 10-May-10 A

18-Nov-11

90 10-May-10 A

16-Dec-10

MISC ITEMS
ITE
OF CLOSE CW SYSTEM
CCW420

Ordering of Chemical Pot Feeder Tank

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 19 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

CCW430

Product engineering

52 17-Dec-10

15-Feb-11

CCW440

Manufacturing

147 16-Feb-11

05-Aug-11

CCW450

Supply for Unit-1 & 2

180 23-Apr-11

18-Nov-11

469 19-Jul-11

30-Oct-12

LP PIPING & FITTING OF CLOSE CW SYSTEM


CCW280

Ordering

90 19-Jul-11

01-Nov-11

CCW290

Product engineering

52 01-Nov-11

31-Dec-11

CCW300

Manufacturing

147 31-Dec-11

20-Jun-12

CCW310

Supply for Unit-1 & 2

180 07-Mar-12

03-Oct-12

CCW320

Erection of CCW piping (along with LP Valves and ...

95 20-Jun-12

09-Oct-12

CCW330

Commissioning of CCW piping (Hydro testing & Fl...

18 09-Oct-12

30-Oct-12

DRAIN SYSTEM
SYS

1241 23-Jul-09 A

14-Dec-12

ENGINEERING
ENGINEE

815 23-Jul-09 A

02-Jan-12

324 23-Jul-09 A

26-Nov-10

575 15-Dec-09 A

02-Jan-12

EN110

Major Engineering

EN111

Balance Engineering

HP & LP FLASH TANK (L&T-HED SCOPE)

1241 23-Jul-09 A
52 23-Jul-09 A

14-Dec-12

DRN320

Ordering

DRN10

Product Engineering

120 28-Jan-10 A

04-Nov-10

DRN20

Fabrication

180 15-Oct-11

11-May-12

DRN30

Supply HP & LP Flash tanks & its accessories

60 07-Apr-12

15-Jun-12

DRN40

Erection of HP & LP Flash tanks & its accessories

60 16-Jun-12

24-Aug-12

DRN50

Commissioning

19 23-Nov-12

14-Dec-12

HP VALVES
VALV
OF DRAIN SYSTEM

392 17-May-10 A

02-Jan-12

21-Sep-09 A

DRN120

Ordering

90 17-May-10 A

06-Dec-10

DRN130

Product Engineering

60 07-Dec-10

14-Feb-11

DRN140

Manufacturing

171 15-Feb-11

01-Sep-11

DRN150

Supply for Unit-1 & 2

180 07-Jun-11

02-Jan-12

462 19-Jul-11

23-Oct-12

90 19-Jul-11

01-Nov-11

LP PIPING & FITTING OF DRAIN SYSTEM


DRN160

Ordering

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 20 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

DRN170

Product Engineering

52 01-Nov-11

31-Dec-11

DRN180

Manufacturing

149 31-Dec-11

22-Jun-12

DRN190

Supply for Unit-1 & 2

180 27-Mar-12

23-Oct-12

357 21-Sep-10 A

08-Dec-11

LP VALVES
VALV
OF DRAIN SYSTEM
DRN200

Ordering

90 21-Sep-10 A

16-Dec-10

DRN210

Product Engineering

52 17-Dec-10

15-Feb-11

DRN220

Manufacturing

149 16-Feb-11

08-Aug-11

DRN230

Supply for Unit-1 & 2

180 13-May-11

08-Dec-11

462 19-Jul-11

23-Oct-12

H&S OF D
DRAINS SYSTEM
DRN240

Ordering

90 19-Jul-11

01-Nov-11

DRN250

Product Engineering

52 01-Nov-11

31-Dec-11

DRN260

Manufacturing

149 31-Dec-11

22-Jun-12

DRN270

Supply for Unit-1 & 2

180 27-Mar-12

23-Oct-12

462 19-Jul-11

23-Oct-12

90 19-Jul-11

01-Nov-11

MISC ITEMS
ITE
OF DRAINS SYSTEM
DRN280

Ordering

DRN290

Product Engineering

52 01-Nov-11

31-Dec-11

DRN300

Manufacturing

149 31-Dec-11

22-Jun-12

DRN310

Supply for Unit-1 & 2

180 27-Mar-12

23-Oct-12

549 14-Jun-11

14-Dec-12

90 14-Jun-11

27-Sep-11

HP PIPING
PIPIN & FITTING OF DRAINS SYSTEM
DRN60

Ordering

DRN70

Product Engineering

60 27-Sep-11

06-Dec-11

DRN80

Manufacturing

171 06-Dec-11

22-Jun-12

DRN90

Supply for Unit-1 & 2

180 27-Mar-12

23-Oct-12

DRN100

Erection of Drain piping (along with LP Piping & Fit...

77 25-Aug-12

22-Nov-12

DRN110

Commissioning of Drain piping (Hydro testing, Che...

19 23-Nov-12

14-Dec-12

EXTRACTION SYSTEM
EXTRACTI
ENGINEERING
ENGINEE
EN112

Major Engineering

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

1298 23-Jul-09 A

09-Feb-13

815 23-Jul-09 A

02-Jan-12

324 23-Jul-09 A

26-Nov-10

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 21 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name
EN113

Balance Engineering

FCNRV ( L&T - MHI SCOPE)

Original Start
Duration
575 15-Dec-09 A
1295 23-Jul-09 A

Finish
02-Jan-12
06-Feb-13

EXT580

Ordering

29 23-Jul-09 A

25-Aug-09 A

EXT10

Product Engineering

90 24-Sep-10

06-Jan-11

EXT20

Manufacturing

EXT30

Supply

90 16-Jan-12

28-Apr-12

EXT40

Erection of all FCNRVs in Extraction lines

30 01-Dec-12

05-Jan-13

EXT50

Commissioning

27 05-Jan-13

06-Feb-13

HP VALVES
VALV
OF EXTRACTION SYSTEM

200 01-Jul-11

18-Feb-12

413 17-May-10 A

23-Jan-12

EXT110

Ordering

90 17-May-10 A

06-Dec-10

EXT120

Product Engineering

60 07-Dec-10

14-Feb-11

EXT130

Manufacturing

182 15-Feb-11

14-Sep-11

EXT140

Supply for Unit-1 & 2

180 28-Jun-11

23-Jan-12

483 19-Jul-11

13-Nov-12

90 19-Jul-11

01-Nov-11

53 01-Nov-11

02-Jan-12

LP PIPING & FITTING OF EXTRACTION SYST...


EXT150

Ordering

EXT160

Product Engineering

EXT170

Manufacturing

159 02-Jan-12

05-Jul-12

EXT180

Supply for Unit-1 & 2

180 17-Apr-12

13-Nov-12

378 21-Sep-10 A

29-Dec-11

90 21-Sep-10 A

16-Dec-10

LP VALVES
VALV
OF EXTRACTION SYSTEM
EXT190

Ordering

EXT200

Product Engineering

53 17-Dec-10

16-Feb-11

EXT210

Manufacturing

159 17-Feb-11

20-Aug-11

EXT220

Supply for Unit-1 & 2

180 03-Jun-11

29-Dec-11

483 19-Jul-11

13-Nov-12

90 19-Jul-11

01-Nov-11

53 01-Nov-11

02-Jan-12

H&S OF E
EXTRACTION SYSTEM
EXT230

Ordering

EXT240

Product Engineering

EXT250

Manufacturing

159 02-Jan-12

05-Jul-12

EXT260

Supply for Unit-1 & 2

180 17-Apr-12

13-Nov-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 22 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

MISC ITEM
ITE OF EXTRACTION SYSTEM

Original Start
Duration

Finish

483 19-Jul-11

13-Nov-12

EXT270

Ordering

90 19-Jul-11

01-Nov-11

EXT280

Product Engineering

53 01-Nov-11

02-Jan-12

EXT290

Manufacturing

159 02-Jan-12

05-Jul-12

EXT300

Supply for Unit-1 & 2

180 17-Apr-12

13-Nov-12

606 14-Jun-11

09-Feb-13

HP PIPING
PIPIN & FITTING OF EXTRACTION SYST...
EXT60

Ordering

90 14-Jun-11

27-Sep-11

EXT70

Product Engineering

60 27-Sep-11

06-Dec-11

EXT80

Manufacturing

182 06-Dec-11

05-Jul-12

EXT90

Supply for Unit-1 & 2

180 17-Apr-12

13-Nov-12

EXT100

Erection of Extraction piping (along with LP Piping ...

120 22-Sep-12

09-Feb-13

1200 23-Jul-09 A

03-Nov-12

825 23-Jul-09 A

02-Jan-12

LP BYPASS
BYPAS SYSTEM
ENGINEERING
ENGINEE
EN114

Major Engineering

332 23-Jul-09 A

27-Nov-10

EN115

Balance Engineering

575 24-Dec-09 A

02-Jan-12

597 02-Dec-10

21-Jul-12

LP BYPASS
BYPA
VALVES
EXT310

Ordering

90 02-Dec-10

17-Mar-11

EXT320

Product Engineering

60 17-Mar-11

26-May-11

EXT330

Manufacturing

238 21-Apr-11

24-Jan-12

EXT340

Supply

90 24-Jan-12

08-May-12

EXT350

Erection

60 08-May-12

17-Jul-12

EXT360

Commissioning

4 17-Jul-12

21-Jul-12

413 17-May-10 A

23-Jan-12

HP VALVES
VALV
OF LP BYPASS SYSTEM
EXT420

Ordering

90 17-May-10 A

06-Dec-10

EXT430

Product Engineering

60 07-Dec-10

14-Feb-11

EXT440

Manufacturing

182 15-Feb-11

14-Sep-11

EXT450

Supply for Unit-1 & 2

180 28-Jun-11

23-Jan-12

483 09-Jul-11

03-Nov-12

LP PIPING & FITTING OF LP BYPASS SYSTEM


Project Baseline Bar
Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 23 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

EXT460

Ordering

90 09-Jul-11

22-Oct-11

EXT470

Product Engineering

60 22-Oct-11

31-Dec-11

EXT480

Manufacturing

152 31-Dec-11

26-Jun-12

EXT490

Supply for Unit-1 & 2

180 07-Apr-12

03-Nov-12

483 09-Jul-11

03-Nov-12

H&S OF L
LP BYPASS SYSTEM
EXT500

Ordering

90 09-Jul-11

22-Oct-11

EXT510

Product Engineering

60 22-Oct-11

31-Dec-11

EXT520

Manufacturing

152 31-Dec-11

26-Jun-12

EXT530

Supply for Unit-1 & 2

180 07-Apr-12

03-Nov-12

MISC ITEM
ITE OF LP BYPASS SYSTEM

483 09-Jul-11

03-Nov-12

EXT540

Ordering

90 09-Jul-11

22-Oct-11

EXT550

Product Engineering

60 22-Oct-11

31-Dec-11

EXT560

Manufacturing

152 31-Dec-11

26-Jun-12

EXT570

Supply for Unit-1 & 2

180 07-Apr-12

03-Nov-12

518 04-Jun-11

03-Nov-12

HP PIPING
PIPIN & FITTING OF LP BYPASS SYSTEM
EXT370

Ordering

90 04-Jun-11

17-Sep-11

EXT380

Product Engineering

60 17-Sep-11

26-Nov-11

EXT390

Manufacturing

182 26-Nov-11

26-Jun-12

EXT400

Supply for Unit-1 & 2

180 07-Apr-12

03-Nov-12

EXT410

Erection of LP Bypass piping (along with LP Piping...

CONDENSER COOLING WATER SYSTEM


CONDENS
ENGINEERING
ENGINEE

75 21-Jul-12

17-Oct-12

1309 23-Jul-09 A

20-Feb-13

815 23-Jul-09 A

02-Jan-12

EN116

Major Engineering

324 23-Jul-09 A

26-Nov-10

EN117

Balance Engineering

575 15-Dec-09 A

02-Jan-12

571 06-Jun-11

28-Dec-12

RUBBER EXPANSION JOINT OF CONDENSE...


CWS10

Ordering

90 06-Jun-11

19-Sep-11

CWS20

Product Engineering

60 19-Sep-11

28-Nov-11

CWS30

Manufacturing

180 28-Nov-11

25-Jun-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 24 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

CWS40

Supply for Unit-1 & 2

180 16-Apr-12

12-Nov-12

CWS50

Erection of Rubber expansion bellows for Condnse...

60 10-Aug-12

19-Oct-12

CWS360

Erection of Rubber expansion bellows for Condnse...

60 19-Oct-12

28-Dec-12

807 25-Jun-10 A

20-Feb-13

BUTTERFLY VALVE OF CONDENSER CW SY...


BUTTERF
CWS60

Ordering

90 25-Jun-10 A

06-Dec-10

CWS70

Product Engineering

90 07-Dec-10

21-Mar-11

CWS80

Manufacturing

198 22-Mar-11

07-Nov-11

CWS90

Supply for Unit-1 & 2

180 30-Aug-11

26-Mar-12

CWS100

Erection of Butterfly valves for Condenser-1

60 10-Aug-12

19-Oct-12

CWS370

Erection of Butterfly valves for Condenser-2

60 19-Oct-12

28-Dec-12

CWS110

Commissioning

16 01-Feb-13

20-Feb-13

807 26-Apr-10 A

20-Feb-13

90 26-Apr-10 A

06-Dec-10

OLTC
CWS120

Ordering

CWS130

Product Engineering

CWS140

Manufacturing

CWS150

90 07-Dec-10

21-Mar-11

159 22-Mar-11

22-Sep-11

Supply OLTC & its accessories

90 19-Aug-11

01-Dec-11

CWS160

Erection of OLTC-1

75 10-Aug-12

06-Nov-12

CWS380

Erection of OLTC-2

75 06-Nov-12

01-Feb-13

CWS170

Commissioning

LP VALVES
VALV
OF CONDENSER SW SYSTEM

16 01-Feb-13

20-Feb-13

377 21-Sep-10 A

28-Dec-11

CWS240

Ordering

90 21-Sep-10 A

16-Dec-10

CWS250

Product Engineering

53 17-Dec-10

16-Feb-11

CWS260

Manufacturing

159 17-Feb-11

20-Aug-11

CWS270

Supply for Unit-1 & 2

180 02-Jun-11

28-Dec-11

482 19-Jul-11

12-Nov-12

H&S OF C
CONDENSER CW SYSTEM
CWS280

Ordering

90 19-Jul-11

01-Nov-11

CWS290

Product Engineering

53 01-Nov-11

02-Jan-12

CWS300

Manufacturing

159 02-Jan-12

05-Jul-12

CWS310

Supply for Unit-1 & 2

180 16-Apr-12

12-Nov-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 25 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

MISC ITEMS
ITE
OF CONDENSER CW SYSTEM

Original Start
Duration

Finish

482 19-Jul-11

12-Nov-12

CWS320

Ordering

90 19-Jul-11

01-Nov-11

CWS330

Product Engineering

53 01-Nov-11

02-Jan-12

CWS340

Manufacturing

159 02-Jan-12

05-Jul-12

CWS350

Supply for Unit-1 & 2

180 16-Apr-12

12-Nov-12

582 19-Jul-11

20-Feb-13

LP PIPING & FITTING OF CONDENSER CW S...


CWS180

Ordering

90 19-Jul-11

01-Nov-11

CWS190

Product Engineering

53 01-Nov-11

02-Jan-12

CWS200

Manufacturing

159 02-Jan-12

05-Jul-12

CWS210

Supply for Unit-1 & 2

180 16-Apr-12

12-Nov-12

CWS220

Erection of Condenser CW piping (along with LP V...

105 10-Aug-12

11-Dec-12

CWS230

Water circulation in Condenser CW line

16 01-Feb-13

20-Feb-13

1245 23-Jul-09 A

18-Dec-12

815 23-Jul-09 A

02-Jan-12

ELECTRICAL SYSTEM
ELECTRIC
ENGINEERING
ENGINEE
EN118

Major Engineering

324 23-Jul-09 A

26-Nov-10

EN119

Balance Engineering

575 15-Dec-09 A

02-Jan-12

560 22-Feb-11

04-Sep-12

AC,DC,UPS DIST. PANELS


AC,DC,UP
ELE10

Ordering

90 22-Feb-11

07-Jun-11

ELE20

Product Engineering

90 07-Jun-11

20-Sep-11

ELE30

Manufacturing

180 20-Sep-11

17-Apr-12

ELE40

Supply of AC,DC,UPS Dist Panels & its accessorie...

180 07-Feb-12

04-Sep-12

ELE50

Erection

ELE60

Panels Charging

BATTERY BANK & CHARGER

53 22-May-12

23-Jul-12

4 23-Jul-12

27-Jul-12

482 28-May-11

21-Sep-12

90 28-May-11

10-Sep-11

ELE70

Ordering

ELE80

Product Engineering

90 10-Sep-11

24-Dec-11

ELE90

Manufacturing

128 24-Dec-11

22-May-12

ELE100

Supply of Battery bank, Charger & its accessories f...

150 13-Mar-12

04-Sep-12

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 26 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name

Original Start
Duration

Finish

ELE110

Erection of Battery bank, Charger & its accessories

45 22-May-12

13-Jul-12

ELE200

Cabling work of Battery bank, Charger & its access...

30 13-Jul-12

17-Aug-12

ELE120

Commissioning

30 17-Aug-12

21-Sep-12

503 03-Aug-11

18-Dec-12

POWER C
CABLE
ELE130

Ordering

90 03-Aug-11

16-Nov-11

ELE140

Manufacturing

191 16-Nov-11

26-Jun-12

ELE150

Supply of Power Cable & its accessories for Unit-1...

210 13-Mar-12

13-Nov-12

ELE160

Cabling work (Power cables)

120 31-Jul-12

18-Dec-12

468 03-Aug-11

13-Nov-12

MISC ITEMS
ITE
OF ELECTRICAL SYSTEM
ELE170

Ordering

90 03-Aug-11

16-Nov-11

ELE180

Manufacturing

191 16-Nov-11

26-Jun-12

ELE190

Supply for Unit-1 & 2

210 13-Mar-12

13-Nov-12

1433 23-Jul-09 A

24-Jun-13

815 23-Jul-09 A

02-Jan-12

C&I SYSTEM
SYSTE
ENGINEERING
ENGINEE
EN120

Major Engineering

324 23-Jul-09 A

26-Nov-10

EN121

Balance Engineering

575 15-Dec-09 A

02-Jan-12

821 26-Apr-10 A

06-Mar-13

VIBRATION MONITORING SYSTEM


VIBRATIO
C&I10

Ordering

90 26-Apr-10 A

06-Dec-10

C&I20

Product Engineering

75 07-Dec-10

03-Mar-11

C&I30

Manufacturing

226 04-Mar-11

22-Nov-11

C&I40

Supply of Vib Monitoring system & its accessories ...

150 14-Sep-11

06-Mar-12

C&I50

Erection

30 07-Sep-12

11-Oct-12

C&I60

Commissioning

28 02-Feb-13

06-Mar-13

931 26-Apr-10 A

24-Jun-13

90 26-Apr-10 A

06-Dec-10

DCS SYSTEM
SYS
& PANEL
C&I70

Ordering

C&I80

Product Engineering

90 07-Dec-10

21-Mar-11

C&I90

Manufacturing

147 22-Mar-11

08-Sep-11

C&I100

Supply DCS System, Panel & its accessories for U...

150 01-Jul-11

22-Dec-11

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 27 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

2x660 MW JPVL NIGRIE STPP - UNIT#1 L2 SCHEDULE


Activity ID

Activity Name
C&I110

Erection

C&I120

Checking and Setting of Interlocks and Protection

C&I CABLE
CABL

Original Start
Duration

Finish

40 23-Apr-12

07-Jun-12

129 25-Jan-13

24-Jun-13

449 19-Oct-11

10-Jan-13

90 19-Oct-11

01-Feb-12

C&I130

Ordering

C&I140

Manufacturing

176 01-Feb-12

24-Aug-12

C&I150

Supply of C&I Cables & its accessories for Unit-1 & 2

180 11-May-12

07-Dec-12

C&I160

Laying & Termination of Control Cables

119 24-Aug-12

10-Jan-13

598 06-Jun-11

24-Jan-13

90 06-Jun-11

19-Sep-11

FIELD INSTRUMENTS
INS
C&I170

Ordering

C&I180

Product Engineering

90 19-Sep-11

02-Jan-12

C&I190

Manufacturing

203 02-Jan-12

25-Aug-12

C&I200

Supply of Various Field instruments & its accessori...

240 07-Apr-12

12-Jan-13

C&I210

Installation/Mounting

43 06-Dec-12

24-Jan-13

415 19-Oct-11

07-Dec-12

90 19-Oct-11

01-Feb-12

MISC ITEMS
ITE
OF C&I SYSTEM
C&I220

Ordering

C&I230

Manufacturing

176 01-Feb-12

24-Aug-12

C&I240

Supply for Unit-1 & 2

180 11-May-12

07-Dec-12

133 04-Sep-10 A

03-Jan-11

105 04-Sep-10 A

16-Dec-10

90 04-Sep-10 A

16-Dec-10

18 17-Dec-10

03-Jan-11

TENDERING & ENABLING


TENDERIN
TENDERING
TENDERI
TND100

Order on Erection Contractor

ENABLING
ENABLIN
ENB100

Opening of Site Office

SPARES

15 17-Dec-10

03-Jan-11

547 23-Oct-12

22-Apr-14

SPR20

Supply of Mandatory Spares for Unit-2

469 23-Oct-12*

22-Apr-14

SPR10

Supply of Mandatory Spares for Unit-1

313 23-Oct-12*

22-Oct-13

Project Baseline Bar


Actual Work
Remaining Work
Critical Remaining Work
Milestone

2009
2010
2011
2012
2013
2014
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q23

Page 28 of 28
Date
28-SEP-10

Particulars

UNIT 1 STG PACKAGE - L2 SCHEDULE

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No-100 of 103

4.5 PROJECT PHOTOGRAPHS

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No-101 of 103

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No-102 of 103

LARSEN & TOUBRO LIMITED


Power Project Management Services,
Vadodara
JOB NO: T209001

JAIPRAKASH POWER VENTURES


LIMITED

Document No:
LT-P0-00003
Progress Report
No-11

2x660 MW Steam Turbine Generators


and Auxiliaries

Page No-103 of 103