Beruflich Dokumente
Kultur Dokumente
Ian Bradley Manager P&C Programs Hydro One Networks Inc. January 22, 2009
Outline
Anti-Islanding Protection Requirement Transfer Trip Requirement New technologies being studied DG Interconnection Transformer New Requirements Hydro One Feeder Protections Resynchronization of DG facilities to Hydro One Example of sequence of events for temporary and
permanent faults
Conclusions
2
Anti-Islanding Requirement
Electric island DG continues to supply HONI customers after HONI has disconnected via breaker/recloser
CB2 CB1
F1
CB4
CB3
TS
F2 F3
DG Recloser/Breaker Closed Recloser/Breaker Open
DG
Anti-Islanding Requirement
Electric island DG continues to supply HONI customers after HONI has disconnected via breaker/recloser
Anti-Islanding Requirement
Reasons for Anti-Islanding protection
Prevent Power Quality problems to HONIs customers Prevent Out-of-Phase Reclosing Mitigate safety hazards
HONI requires that all exporting DGs be equipped with a Transfer Trip (TT) signal unless:
the maximum generation is less than 50% of the minimum feeder load not able to sustain island
Transfer Trip may be costly for smaller DG installations especially when multiple devices need TT to the DG Facility
Hydro One is working on solutions which will replace the Transfer Trip Requirements for DG facilities interconnecting sized 500kW and below, which include:
Pulse-based Signaling (Connectivity-based) Rate-of-change-of-frequency (ROCOF) local based Vector Surge (Vector Jump) local based
Each technology will be evaluated and tested to determine its suitability for use as Anti-Islanding Protection for these projects
7
Hydro One has initiated a task force of experts to determine the most efficient, safe and reliable method of connecting generation to the distribution system
New standards have been created and will apply to all future DG interconnections
Hydro One will utilize distance protection for low set instantaneous phase and ground protection If the low set protections operate, the DGIT and DG shall trip via Transfer Trip or other approved Anti-Islanding Protections DGIT is removed from system ground source is also removed Overcurrent protection will then operate as required DGs will not impede feeder protections Using this approach and the combination of DGIT configurations, both TOV and ground protection problems have been eliminated May enable quicker connections as standard modules are being developed
11
Resynchronization
Following a protection operation, the DGIT shall reclose into the distribution system within 10 seconds
This will limit the power quality issues associated with DGIT energization for Hydro One customers
The generator shall stay offline until voltage and frequency has been stabilized and within limits for at least a period of 5 minutes
If voltage and frequency are not restored within a period of 5 minutes, resynchronization shall lockout and the generators shall be kept offline until Hydro One operators contact the DG facility
The DGIT and generator reconnection may need to be staggered if multiple DGs are present on feeder
12
F1 TS F2 F3
DG Recloser/Breaker - Closed Fuse (Closed) Recloser/Breaker - Open Fuse (Blown) Transfer Trip
13
HVI
Fault
Wye
Delta
Low Set Instantaneous Feeder Protections senses fault Opens feeder breaker (Fuse Saving Scheme)
14
F1 TS F2 F3
DG Recloser/Breaker - Closed Fuse (Closed) Recloser/Breaker - Open Fuse (Blown) Transfer Trip
15
HVI
Fault
Wye
Delta
16
F1 TS F2 F3
DG Recloser/Breaker - Closed Fuse (Closed) Recloser/Breaker - Open Fuse (Blown) Transfer Trip
17
HVI
Fault
Wye
Delta
F1 TS F2 F3
DG Recloser/Breaker - Closed Fuse (Closed) Recloser/Breaker - Open Fuse (Blown) Transfer Trip
18
HVI
Fault
Wye
Delta
19
Low Set Instantaneous Feeder Protections senses fault Opens feeder breaker
F1 TS F2 F3
Fault
HVI Wye
Delta
DGIT and generator breakers open Fault is not cleared after reclose attempts Hydro One crews are dispatched to repair line After 5 minutes the generator resynchronization will lockout
21
Hydro One repairs line Fault is cleared Operators close Feeder breaker energizing the line DGIT recloses within 10 seconds - Generator stays offline
22
Operators contact DG facility Generators are restarted manually and synchronized to Hydro One
23
Summary
The new requirements presented here will allow DGs to connect with fewer problems, and allow a quicker turn around time.
They have eliminated two of the major technical barriers faced with interconnection of DGs TOV and feeder protections
Hydro One is working hard to determine best practices and ideal solutions to technical problems faced with interconnection of DGs
Focused on safety, reliability, and minimizing cost to DG Proponents Creating modular equipment which can be implemented quickly and efficiently to reduce wait times
Future
The new DG Interconnection Requirements Standard shall be provided to the public shortly
Hydro One will continue to develop solutions to enable more generation and overcome other technical and financial obstacles such as Anti-Islanding Protection for smaller DGs
Questions