Sie sind auf Seite 1von 5

538 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO.

1, FEBRUARY 2004

Distribution Network Configuration for


Minimum Energy Supply Cost
Miguel Arias-Albornoz, Senior Member, IEEE, and Hernán Sanhueza-Hardy

Abstract—This paper describes a model for the economic op- From the optimization point of view, the reconfiguration tech-
eration of primary distribution networks fed from several substa- nique has mainly been used for loss reduction using different
tions, where the energy purchase prices are different. Several as- techniques [4]–[7]. On the other hand, from the service restora-
pects involved in the model formulation are discussed. An example
is shown to illustrate the difference between a network operation tion point of view, the reconfiguration allows to relocate loads
based on a minimum loss criterion and the operation based on a by using an appropriate sequence of switching operations, while
minimum energy cost criterion. operating constrains are taken into account [8], [9].
Index Terms—Distribution systems, feeder reconfiguration, op- In some countries, as in Chile [10], electric utilities are under
timization techniques. a legal regulation frame, which fixes the energy prices at the
main nodes of the transmission network. It also fixes the en-
ergy price at the final consumer through the “distribution ag-
I. INTRODUCTION gregated value” and taking as a reference a distribution model
optimally managed. Therefore, in addition to supplying good
I N a distribution network, two voltage levels can be identi-
fied: the primary distribution network (which is the objec-
tive of this paper), and the secondary distribution network or low
quality energy, the utilities should develop important efforts to
reduce costs and obtain a maximum income. It means that a very
voltage network. To assure the service continuity at the primary important issue is to reduce losses and energy buying.
network, two or more main feeders covering the same service In this paper, a model is proposed to include the economic
area are usually considered to make possible a partial or total effect of different supply energy prices using different feeder
load transfer. In addition, to improve the network operation and configurations during the operation of distribution networks. To
the consumers’ energy quality, control devices are incorporated, this end, the paper has been ordered according to the following
such as tap changer transformers, voltage regulators, capacitor sections.
banks, etc. In Section II, the main aspects of the Chilean rate structure
The operating conditions of a distribution network depend on are shown. In Section III, an optimization model for distribu-
many factors. Several models have been proposed to assess the tion networks is proposed, which allows the energy cost to be
influence of a number of operation variables, usually assuming a included in the objective function. Finally, in Section IV, a basic
single feeder. Computer programs are used to study topics such example is presented to illustrate the influence of the energy cost
as power flow, reactive power control, and feeder reconfigura- in the optimal feeder configuration.
tions, seeking to improve the distribution network performance.
Nowadays, the optimal operation of a distribution network II. RATE STRUCTURE
has become an engineering challenge. The main reason of
The basis of Chilean rate structure takes into account the
applying optimization techniques is to minimize costs [1].
power and energy prices at the main substations of the transmis-
By using a phase-stage decomposition technique, an overall
sion network. Since, in practice, most of the distribution utili-
optimization procedure has been proposed, taking into account
ties buy energy from these substations, usually located far away
network control devices, load behavior, and economic factors
from the load centers, the supply cost is determined by consid-
[2]. Also, a combined method for the determination of the
ering the following charges:
overall optimal operating condition of any type of distribution
system has been presented [3]. It is based on the minimization • Transportation charge: It takes into account the losses be-
of losses by network reconfiguration and reactive power con- tween the main substations and the distribution network
trol, and optimization of the protective scheme of the network. feeding points;
However, it is supposed that the distribution network is fed by • Transformation charge: It takes into account the voltage
only one substation. levels used to interconnect the main substations and the
distribution network feeding points.
In addition, if a given distribution system is fed by two or
more substations, the energy cost is billed independently. The
Manuscript received March 12, 2003. This work was supported in part by
Fondecyt Project 1980034, and in part by DICYT—Universidad de Santiago de distribution utilities have the following options to buy energy
Chile. from a bulk system: a) on a maximum demand basis, b) on a
The authors are with the Department of Electrical Engineering, Universidad take-and-pay basis for a given quantity of power. In each case,
de Santiago de Chile, Santiago 10233, Chile (e-mail: m-arias@lauca.usach.cl;
hsanhueza@lauca.usach.cl). there are legal regulations to determine the price incident fac-
Digital Object Identifier 10.1109/TPWRS.2003.820697 tors, such as maximum peak load, power factor during the peak
0885-8950/04$20.00 © 2004 IEEE
ARIAS-ALBORNOZ AND SANHUEZA-HARDY: DISTRIBUTION NETWORK CONFIGURATION 539

load, etc. As a final result of these rate regulations, power and On the other hand, if the losses at each feeder are known,
energy prices are different at each substation feeding a given the cost of energy losses can be expressed as
distribution network.
From now on, to simplify the analysis without loosing gener-
(4)
ality, only the energy price in a given substation (S/Ei) will be
considered, according to the following equation:
Therefore, from (3) and (4), the total energy cost of the entire
(1) network will be given by the following equation:

where (5)
energy price at substation S/Ei (in dollars per
Alternatively, the total energy cost can also be calculated from
megawatt-hour);
the total demand at each substation, as follows:
energy supplied to S/Ei from a main node (in
megawatt-hours);
transportation and transformation charges at S/Ei (in (6)
per unit per megawatt-hours);
energy price at the main node (in dollars per megawatt- where
hour). average power at a feeding substation S/Ei.
In practice, it should be noted that (5) and (6) can give dif-
III. ECONOMIC OPERATION MODEL ferent results due to energy robbery, not taken into account in
Normally, it is understood that a distribution network is op- (5). Therefore, (6) is more convenient for cost evaluation pur-
erating at optimal conditions when it presents minimum losses, poses.
minimum voltage deviation at the consumer’s feeding point, and By taking into consideration the network operating restric-
maximum reliability. However, when a distribution network is tions, the operation optimization problem can be formulated as
fed by two or more substations, the energy cost at each one of follows:
them must be considered for an economic operation.
From the energy cost point of view, the problem can be stated min (7)
as follows: for a primary distribution network fed by several
substations from a bulk system, it is required to determine the Subject to (8)
power quantity that each substation should deliver to the net- (9)
work during a given time interval in order to minimize the total
energy cost, while maintaining the service quality and relia- where (8) corresponds to the power flow equations for the dis-
bility. tribution network, and (9) takes into account the practical oper-
If the network losses were zero, the solution for the above ation limits. In addition, restrictions on the topological structure
stated problem would be immediate: each substation should be of the network must be considered.
utilized in a sequence according to the energy cost, starting from The solution of this optimization problem can be obtained
the lowest one. However, in a real case, losses must be taken into according to the following steps:
account, and a special procedure must be developed to obtain a • determine the network configuration for minimum total
solution which minimizes the total energy buying cost. energy supply cost;
In a given substation, the demand has two components: the • utilize the network control devices to improve operation
consumer’s loads and the feeder losses. The total cost supply conditions.
to the load of the distribution systems during a time
interval T, will be given by the following equation: IV. ILLUSTRATIVE EXAMPLE
This example illustrates the economic effect of different
(2) feeder configurations when different supply energy prices
are considered. Fig. 1 shows an elementary distribution
network fed by two substations, the scheduled bus loads
where are shown in Table I. The feeder has a uniform impedance
k is the number of loads at feeder “i”; ., on bases 10 MVA and 12 kV.
power of load k, at a time t; The energy prices at each substation are
i is the number of substation feeders.
By assuming constant loads during the time interval T, or al-
ternatively, by considering an average power of each load k
during the T interval, (2) can be written as follows: If the radial condition is imposed on the topological structure
of the network, four schemes are possible. The best one must
(3) be determined according to (7) [i.e., the minimum total energy
cost configuration]. A 24-h period will be considered.
540 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 1, FEBRUARY 2004

4 1 2 3 5 TABLE II
S2 S3 S4 SUBSTATION POWER DELIVERY AND LOSSES FOR CONFIGURATION CS
S1
S/E1 0 + j0 [MVA]
S/E1 S/E2 S/E2 13.689 + j 9.398 [MVA]
S – total 13.689 + j 9.398 [MVA]
Losses 3.291 + j 4.701 [MVA]
Sc1 Sc2 Sc3

TABLE III
SUBSTATION POWER DELIVERY AND LOSSES FOR CONFIGURATION CS
Fig. 1. Example of a distribution network.

4 1 2 3 5 S/E1 3.962 + j 2.731 [MVA]


S1 S2 S3 S4 S/E2 7.077 + j 2.881 [MVA]
S – total 11.039 + j 5.613 [MVA]
S/E1 S/E2 Losses 0.639 + j 0.913 [MVA]

TABLE IV
Sc1 Sc2 Sc3
SUBSTATION POWER DELIVERY AND LOSSES FOR CONFIGURATION CS

Fig. 2. Configuration CS : S open. S/E1 6.934 + j 4.263 [MVA]


S/E2 4.133 + j 1.390 [MVA]
4 1 2 3 5 S – total 11.067 + j 5.653 [MVA]
S1 S2 S3 S4 Losses 0.667 + j 0.953 [MVA]

S/E1 S/E2 TABLE V


SUBSTATION POWER DELIVERY AND LOSSES FOR CONFIGURATION CS

Sc1 Sc2 Sc3 S/E1 13.145 + j 8.621 [MVA]


S/E2 0 + j 0 [MVA]
Fig. 3. Configuration CS : S open. S – total 13.145 + j 8.621 [MVA]
Losses 2.747 + j 3.924 [MVA]
4 1 2 3 5
S1 S2 S3 S4
A. Cost Evaluation of the Different Configurations

S/E1 S/E2
1) Configuration :
open
Sc1 Sc2 Sc3 closed
Fig. 4. Configuration CS : S open. Partial costs

4 1 2 3 5
S1 S2 S3 S4

S/E1 S/E2
Total cost
Sc1 Sc2 Sc3

Fig. 5. Configuration CS : S open. 2) Configuration :


TABLE I open
BUS LOADS
closed
Bus Active Power [MW] Reactive Power [MVAR]
1 3.8 2.5 Partial costs
2 2.6 1.0
3 4.0 1.2

Also, the minimum energy cost criterion will be compared


with the minimum loss criterion. The four different possibilities
to feed the loads will be denoted by , , , and Total cost
(Tables II–V), according to the open position of sectionalizing
circuit breakers , , , and (Figs. 2–5).
ARIAS-ALBORNOZ AND SANHUEZA-HARDY: DISTRIBUTION NETWORK CONFIGURATION 541

TABLE VI
SUMMARY OF RESULTS FOR DIFFERENT CONFIGURATIONS

Configurations P + j Q at each S/E Losses at each S/E Total cost, losses not Total losses Total cost, losses
[MVA] [MVA] included (103) $ [MVA] included (103) $
CS1: S/E1 0+j0 0+j0 2870.4 3.291 3778.16
13.689 + j 9.398 3.291 + j 4.701
S/E2
CS2: S/E1 3.962 + j 2.731 0.162 + j 0.231 2852.16 0.639 3027.75
S/E2 7.077 + j 2.881 0.477 + j 0.681
CS3: S/E1 6.934 + j 4.263 0.534 + j 0.763 2839.68 0.667 3021.21
S/E2 4.133 + j 1.390 0.133 + j 0.190
CS4: S/E1 13.145 + j 8.621 2.747 + j 3.924 2820.48 2.747 3564.92
S/E2 0+j0 0+j0

3) Configuration : It represents the most economical alternative to feed the


loads.
open
closed It should be noted that in each configuration previously con-
sidered, voltage regulation problems might arise. Thus, some of
Partial costs the configurations could require additional control actions, such
as reactive power injection.

V. CONCLUSION
An overall economic optimization model that minimizes the
energy buying cost in distribution networks has been proposed.
Total cost
In this model, the reconfiguration technique has been consid-
ered as a means to get an economical load distribution between
feeding substations. By considering the economic topological
4) Configuration : structure, other parameters such as voltage quality and protec-
tive schemes can be included to improve the network operating
open conditions.
closed To illustrate the difference between the network operation
based on a minimum loss criterion and the operation based on
Partial costs a minimum energy cost criterion, a basic example has been pre-
sented.
It can be foreseen that in real cases, the topological struc-
ture selection of a primary distribution network on a minimum
energy cost basis will be a powerful tool to analyze its optimal
operation when it is fed by several substations with different en-
Total cost ergy buying costs.

REFERENCES
[1] H. L. Willis, H. Tram, M. V. Engel, and L. Finley, “Optimization appli-
B. Comparison of Different Configurations and Selection of cations to power distribution,” IEEE Comput. Applicat. Power, vol. 8,
the Best One pp. 12–17, Oct. 1995.
[2] G. Garrido and J. I. Pérez Arriaga, “Explotación óptima de redes de
The main figures to be compared are shown in Table VI. distribución en entornos de competencia,” in 4 Jornadas Luso-Espan-
When the price of energy at the supply substation is considered, holas de Engenharia Electro-técnica, vol. 2, Porto, Portugal, 1995, pp.
the following conclusions result. 803–812.
[3] G. J. Peponis, M. P. Papadopoulus, and N. D. Hatziargyriou, “Optimal
• If losses are not taken into account, is the most conve- operation of distribution networks,” IEEE Trans. Power Syst., vol. 11,
nient alternative. It implies that all loads will be fed from pp. 59–67, Feb. 1996.
[4] R. J. Sarfi, M. M. A. Salama, and A. Y. Chikhani, “A survey of the state
the minimum energy cost substation. of art in distribution system reconfiguration for system loss reduction,”
• If a reconfiguration is made on a minimum loss basis, the Electric Power Systems Research, vol. 31, no. 1, pp. 61–70, 1994.
best configuration is . [5] R. J. Sárfi, M. M. A. Salama, and A. Y. Chikhani, “Distribution system
reconfiguration for loss reduction: an algorithm based on network par-
• Finally, if a reconfiguration is made on a minimum energy titioning theory,” IEEE Trans. Power Syst., vol. 11, pp. 504–510, Feb.
cost basis, including losses, the best configuration is . 1996.
542 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 1, FEBRUARY 2004

[6] D. Bouchard, M. Salama, and A. Chikhani, “A survey of modern tech- Miguel Arias-Albornoz (SM’01) received the Dipl.
niques for distribution feeder reconfiguration for loss minimization,” Ing. degree from the State Technical University of
Eng. Intell. Syst., vol. 6, no. 3, pp. 173–182, Sept. 1998. Chile, Santiago, Chile, in 1980, and the M.Sc. and
[7] M. A. Kashem, G. B. Jasmon, and V. Ganapathy, “A new approach of Ph.D. degrees in electrical engineering from the
distribution system reconfiguration for loss minimization,” Elect. Power Federal University of Rio de Janeiro, Rio de Janeiro,
Energy Syst., vol. 22, pp. 269–276, 2000. Brazil, in 1987 and 1990, respectively.
[8] D. Shirmohamadi, “Service restoration in distribution networks via Currently, he is a Professor with the Department of
network reconfiguration,” IEEE Trans. Power Delivery, vol. 7, pp. Electrical Engineering at the University of Santiago
952–958, Apr. 1992. of Chile, Santiago, Chile, where he has been since
[9] K. N. Miu, H. D. Chiang, and R. J. McNulty, “Multi-Tier service restora- 1980. His main research areas of interests are anal-
tion through network reconfiguration and capacitor control for large- ysis, operation, and control of electric power and dis-
scale radial distribution networks,” IEEE Trans. Power Syst., vol. 15, tribution systems.
pp. 1001–1007, Aug. 2000.
[10] Ministry of “Economía, Fomento y Reconstrucción—Chile” De-
crees 445–447 published in 31/10/1988. Decrees 571, 572 dated in
27/10/1992, published in the Office Records of Republic of Chile Hernán Sanhueza-Hardy received the Dipl. Ing. de-
29/4/95, Santiago, Chile. gree from the State Technical University of Chile,
Santiago, Chile, in 1961, and the M.E. degree from
the University of Toronto, Toronto, ON, Canada, in
1969.
Currently, he is Full Professor in the Department of
Electrical Engineering at the University of Santiago
of Chile, Santiago, Chile. His research interests are
power systems analysis and distribution power sys-
tems.

Das könnte Ihnen auch gefallen