ENI - IRAQ ZUBAIR OIL FIELD DEVELOPMENT PROJECT

TECHNICAL SPECIFICATION FOR FIBER OPTIC CABLE

CD-FE CD-FE CD-FE CD-FE CD-FE

04 03 02 01 00

08/06/11

Modified for Addendum

20/01/11 Issue for Tender 12/10/10 04/08/10 15/07/10 Date Final Issue Issue for Approval Issue for Approval Description

Federico Maggi Federico Maggi Federico Maggi Federico Maggi Federico Maggi Prepared by

Giacomo Campanelli Giacomo Campanelli Giacomo Campanelli Giacomo Campanelli Giacomo Campanelli Checked by

Andrea Gasparini Andrea Gasparini Andrea Gasparini Andrea Gasparini Andrea Gasparini Approved by

Richelmo Chiorrini Richelmo Chiorrini Richelmo Chiorrini Richelmo Chiorrini Richelmo Chiorrini Contractor Approval Company Approval

Validity Rev. Status number Revision Index

Company logo and business name

exploration & Pproduction division


Contractor logo and business name

Project name ZUBAIR OIL FIELD DEVELOPMENT PROJECT

Company Document ID

00250600BCST49042
Job N. Contractor Document ID

022026-2506-HA-E- 49042
Vendor logo and business name Contract N. Vendor Document ID Order N. Scale n.a.

Facility Name Document Title

Location ONSHORE

Sheet of Sheets 1 of 38

Supersedes N. XXX (SOC NUMBER) Superseded by N. Plant Area

TECHNICAL SPECIFICATION FOR FIBER OPTIC CABLE

Plant Unit

Software: Microsoft Word 97-2003

File No. 00250600BCST49042_CDFE04_38.doc

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 2 / 38

e & p division

03

REVISION HISTORY

Rev. CD-FE 00 CD-FE 01 CD-FE 02 CD-FE 03 CD-FE 04

Date 15/07/2010 04/08/2010 12/10/2010 20/01/2011 06/06/2011

Nr. of sheets 33 35 37 37 38

Description Issue for Approval Issue for Approval Final Issue Issue for Tender Modified for Addendum

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 3 / 38

e & p division

03

INDEX

PROJECT DESCRIPTION............................................................................................................... 5 1.1 General....................................................................................................................................... 5 1.2 Objective..................................................................................................................................... 5 2 DEFINITION AND ABBREVIATIONS ............................................................................................. 7 2.1 Language and unit of measurement .......................................................................................... 7 2.2 Definition..................................................................................................................................... 7 2.3 Abbreviations.............................................................................................................................. 9 3 CODES, STANDARDS AND REFERENCE.................................................................................. 12 3.1 International Telecommunication Union (ITU).......................................................................... 12 3.2 Institute of Electrical and Electronic Engineers (IEEE) ............................................................ 12 3.3 International Electrotechnical Committee (IEC) ....................................................................... 12 3.4 ENI Standards .......................................................................................................................... 13 3.5 Reference Project Documents ................................................................................................. 13 3.6 Environmental conditions ......................................................................................................... 16 4 OVERALL REQUIREMENTS ........................................................................................................ 17 4.1 General..................................................................................................................................... 17 5 TECHNICAL REQUIREMENTS .................................................................................................... 18 5.1 General..................................................................................................................................... 18 5.2 Fiber Optical Cable Type 1....................................................................................................... 18 5.3 Fiber Optical Cable Type 2....................................................................................................... 19 5.4 Fiber Optical Cable Type 3....................................................................................................... 20 5.5 Fiber Optical Cable Joint Splice and Enclosure ....................................................................... 21 6 DOCUMENTATION ....................................................................................................................... 22 6.1 General..................................................................................................................................... 22 6.2 Engineering Design Documentation (Not Applicable).............................................................. 22 6.3 Construction Drawings and Documentation............................................................................. 22 6.4 Test and Commissioning Procedures ...................................................................................... 22 6.5 As-Built Drawings ..................................................................................................................... 23 6.6 System Documentation ............................................................................................................ 23 7 INSTALLATION ............................................................................................................................. 24 8 BEDDING PADDING AND BACKFILLING OF TRENCH ............................................................ 25 8.1 Trench Bed Preparation ........................................................................................................... 25 8.2 Padding and Backfilling ............................................................................................................ 25 8.3 Installation of Warning Tape..................................................................................................... 26 8.4 Line Markers............................................................................................................................. 26 8.5 Manhole for Joint Splice Closure ............................................................................................. 26 9 SPECIAL TOOLS AND TEST EQUIPMENT................................................................................. 28 9.1 Special tools ............................................................................................................................. 28 9.2 Test Equipment ........................................................................................................................ 28 10 TEST AND COMMISSIONING ................................................................................................ 29 10.1 General ................................................................................................................................ 29 10.2 Factory Acceptance Test (FAT) ........................................................................................... 29 10.3 Cable Testing ....................................................................................................................... 29 10.4 Shop Inspection Testing ...................................................................................................... 30 10.5 Site Acceptance Test ........................................................................................................... 30 10.6 Certificate of Acceptance ..................................................................................................... 31 11 ATTACHMENTS ...................................................................................................................... 32 11.1 Optical Requirements Fiber Optic Cable Data Sheet Type 1, and Type 2 and Type 3....... 32 11.2 Construction Requirements for Fiber Optic Cable Type 1................................................... 33 11.3 Construction Requirements for Fiber Optic Cable Type 2................................................... 34 1
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 4 / 38

e & p division

03

11.4 Construction Requirements for Fiber Optic Cable Type 3................................................... 35 11.5 Joint Splice Enclosure for Fiber Optic Cable ....................................................................... 36 12 ESTIMATED QUANTITIES OF FIBER OPTIC CABLE AND SPLICE CLOSURE................. 37

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 5 / 38

e & p division 1
1.1

03

PROJECT DESCRIPTION
General ENI has been awarded the Zubair project for the development of an oil field (ZUBAIR FIELD) in joint venture with Occidental, Korea Gas and Missan Oil COMPANY (as state partner), with Eni as operator. The Zubair Field is located in the southern area of Iraq, 20 km from Basra city. The structure of the Zubair Field is a relatively gentle anticline oriented NNW SE, approximately 60 km long and 10-15 km wide. The Zubair project is a brown field project in which two main phases can be defined: Rehabilitation Phase (or RP) in which includes the revamping of existing facilities to maximise production capacity of the existing treatment plants in order to achieve an oil production rate of 700 kBOPD at Q3 2013, after rehabilitation of wells, gathering network and overall facilities, plus installation of new facilities as required. These activities should be concluded within 36 month starting from the CED. Enhanced Re-Development Phase (or EP). During this phase the installation of new permanent production facilities to achieve the plateau rate of 1200 kBOPD of oil production has been foreseen. The oil will be produced from reservoir with natural flowing and artificial lift systems requiring also water injection to support reservoir pressure and maintain it above saturation pressure. This second phase should be finished within 6 years from the CED.

1.2

Objective The primary objective of this document is to define the minimum requirements for the design, manufacturing, delivery, installation and testing of the FIBER OPTIC CABLE for the following SITES: Zubair Degassing Station; Zubair Mishrif Degassing Station; Hammar Degassing Station; Hammar Mishrif Degassing Station; Rafidiya Degassing Station; Safwan flow station; Power Generation Plant; Gas Treatment Plant; New Tankfarm; Sea Water Intake; River Water Intake (To Be Defined); Field Office District; Radio Shelter; Fiscal Metering Site (If located outside DGS); New Remote Wells and Manifolds;
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 6 / 38

e & p division

03

The FIBER OPTIC CABLE shall be the physical support to the WAN and LAN Systems that provides communications for voice and data services within Zubair Field SITES and FACILITIES. The FIBER OPTIC CABLE shall be installed by CONTRACTOR within the Degassing Station and Main SITES and remote FACILITIES areas, along new Gas and Water pipelines and between Degassing Station and new wells and manifolds SITES along new trunklines and flowlines. All CONTRACTOR ITEMS necessary for the safe and satisfactory operation of the system shall be included notwithstanding exclusions or omissions from the specification.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 7 / 38

e & p division 2
2.1

03

DEFINITION AND ABBREVIATIONS


Language and unit of measurement All TECHNICAL DOCUMENTATION exchanged on this PROJECT shall be in the English language. Units of measurement shall be in accordance with the International System (IS). Safety labels or announce shall be English and Arabic languages.

2.2

Definition COMMISSIONING Means that the functional systems of the FACILITY are mechanically completed and have been tested and pre-commissioned in accordance with the requirements of the CONTRACT and are therefore in readiness for commencement of the associated commissioning activities, as described in the applicable Appendix. Means the Company designated as such in the FORM OF AGREEMENT Means equipment and material to be supplied by COMPANY to CONTRACTOR Means all materials, supplies, plant (floating or otherwise), vessels, machinery, equipment, tools, buildings and structures, including warehouses, offices, docks, berths, moorings, camps, garages, workshops, scaffolding, temporary work and all other items supplied, used and/or consumed by CONTRACTOR and its SUBCONTRACTORS in the performance of the WORK/SERVICE, but not incorporated into or forming part of the FACILITY Means the documents listed in the FORM OF AGREEMENT and any amendments, supplements and alterations thereto in writing signed by the PARTIES Means the legal entity defined as such in the FORM OF AGREEMENT Means any and all itemised and non itemised equipment and materials, including construction spares, special tools, commissioning spares and consumables to be incorporated into the FACILITY or used during the plant commissioning, start up or operations and necessary for the due performance of the

COMPANY COMPANY ITEMS CONSTRUCTION EQUIPMENTS

CONTRACT

CONTRACTOR CONTRACTOR ITEMS

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 8 / 38

e & p division

03

WORK/SERVICE, in order to allow the complete realisation of the FACILITY and to be supplied by CONTRACTOR as set out in the CONTRACT and excluding only COMPANY ITEMS and CONSTRUCTION EQUIPMENT FACILITY Means the facility, associated utilities, machinery, apparatus, articles, and supporting infrastructure to be designed, constructed and warranted in accordance with this CONTRACT, as is more fully specified in the applicable Appendix Means the document titled as such which is a part of this CONTRACT Means the equipment, machinery, materials and/or supplies to be provided directly or indirectly by CONTRACTOR in accordance with the CONTRACT Means either COMPANY or CONTRACTOR and the expression PARTIES shall be construed accordingly Means technical services and related activities for the rehabilitation and improved production and enhanced recovery of petroleum from Zubair Oil Field located in the Republic of Iraq Means all the activities as better specified in the applicable Appendix, to be rendered by CONTRACTOR pursuant to the CONTRACT Means the location where the FACILITY is to be commissioned and the surrounding vicinity, as may be further delineated and altered in writing from time to time by COMPANY REPRESENTATIVE Means any person, including any vendor or supplier, with whom CONTRACTOR has entered into any contract to perform any part of the WORK/SERVICE, or to provide any materials to or on behalf of CONTRACTOR, including any person at any tier with whom any SUBCONTRACTOR has further contracted any part of the WORK/SERVICE, and their legal successors and assigns Means all documents including but not limited to drawings, designs and calculation data, process documents, technical indices, operation and maintenance manuals and other documentation relating to the CONTRACTOR ITEMS, the FACILITY or the WORK/SERVICE to be supplied

FORM OF AGREEMENT GOODS

PARTIES

PROJECT

SERVICE

SITE

SUBCONTRACTOR (SUBSUPPLIER)

TECHNICAL DOCUMENTATION

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 9 / 38

e & p division

03

by CONTRACTOR to COMPANY WORK Means all of the works and services required to be performed by CONTRACTOR under this CONTRACT for the full and complete realisation of the FACILITY as are more fully described in the applicable Appendix and as may be modified by VARIATION ORDER(S), including but not limited to the provision of all labour, facilities, equipment, services and works as may be reasonably inferred therefrom unless specifically excluded in this CONTRACT

2.3

Abbreviations AC or ac ACS ACSR ATEX BOPD BSTB Cat-6 CCD CD CCR CCTV CED CLI CMCS COE CPI dB DC or dc DHCP DISA DVR DGS DTMF DVD EExe EIA EMC EMI EP EPC Fps FAX FO FOC FOD FOPIMS GUI Ex Alternating Current Access Control System Aluminum Conductor Steel Reinforced Atmospheres Explosive (Directive 94/9/EC) Barrels of Oil per Day Billion of Stock Tank Barrels Category 6 Charge Coupled Device Compact Disc Central Control Room Closed Circuit Television Contract Effective Date Calling Line Identifier Central Monitoring Communication System Common Operating Environment Corrugated Plate Interceptor Decibel Direct Current Dynamic Host Configuration Protocol Direct Inward System Access Digital Video Recorder DeGassing Station Dual Tone Multi Frequency Digital Versatile Disc European Area of Use Standard Increased Safety EN50019 Electronics Industries Alliance Electromagnetic Compatibility Electromagnetic Interference Enhanced Phase Engineering, Procurement and Construction Frames Per Second Facsimile document transmission Fiber Optic Fiber Optic Cable Field Operation Division Fiber Optic Pipeline Monitoring System Graphic User Interface Certification for Hazardous Area

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 10 / 38

e & p division
HF HMI HOFR Hz I/O ICSS IDF IDS IEC IEEE IP IPTV IR IS ISO ISP IT ITU kHz kV LAN LCD LCR LED LER LS0H LSB LSC Mb/s MAC MDF MF MHz MLV MPEG MPS MSDC MTBF MTG MTTR NMS NTP NTSC NVR OHL OPGW OSI PAGA PAL PoE PS PSTN PTZ RF RFI

03

High Frequency Human Machine Interface Heat and Oil Flame Resistant Hertz Input/Output Integrated Control & Safety System Intermediate Distribution Frame Intrusion Detection System International Electro technical Committee Institute of Electrical & Electronic Engineers Internet Protocol Internet Protocol TeleVision Infra-Red International System International Organization for Standardization Internet Service Provider Information Technology International Telecommunication Union Kilo Hertz Kilo Volt Local Area Network Liquid Crystal Display Least Cost Routing Light Emitting Diode Local Equipment Room Low Smoke Zero Halogen Life Support Base Life Support Camp Megabits per second Media Access Control Main Distribution Frame Medium Frequency Mega Hertz Main Valve Line Station Moving Pictures Expert Group Main Pumping Station Main Supervisory Dispatching Centre Mean Time Before Failure Main Telecom Ground Mean Time To Repair Network Management System Network Time Protocol National Television System Committee Network Video Recorder Over Head Line OPtical Ground Wire Open System Interconnection Public Address & General Alarm Phase Alternation Line Power over Ethernet Pump Station Public Switched Telephone Network Pan Tilt Zoom Radio Frequency Radio Frequency Interference
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 11 / 38

e & p division
SDH SFP SIL SNMP STM-1 STM-4 STM-16 TCP/IP TER TFT TG TIA TPI UPS V VLAN VPN VSAT VoIP WAN WEE

03

Synchronous Digital Hierarchy Small Form-factor Pluggable Safety Integrity Level Simple Network Management Protocol Synchronous Transmission Mode 1 (155 Mb/s) Synchronous Transmission Mode 4 (622 Mb/s) Synchronous Transmission Mode 16 2488 Mb/s) Transmission Control Protocol/Internet Protocol Telecommunications Equipment Room Thin Film Transistor Telecom Ground Telecommunications Industries Association Third Party Interference Uninterruptible Power Supply Volt Virtual Local Area Network Virtual Private Network Very Small Aperture Terminal Voice Over Internet Protocol Wide Area Network Waste Electronic & Electrical Equipment

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 12 / 38

e & p division 3

03

CODES, STANDARDS AND REFERENCE


Any CONTRACTOR ITEMS or systems installed shall comply with all relevant International Standards, Specifications, Industry Codes, Iraqi Laws and Company Standards. CONTRACTOR ITEMS and systems should normally comply with the relevant national and international recommendations of the ITU and should be typeapproved by the national authority for use in the application proposed. The following is the List of applicable Codes and Standards:

3.1

International Telecommunication Union (ITU) Document Number ITU-T G series ITU-T Q series ITU-T G.651 ITU-T G.652 ITU-T G.655 ITU-T L.43 ITU-T L.10 Description Transmission systems and media, digital systems and networks Switching and signalling Characteristics of a 50 125m Multimode Graded Index Optical Fibre Cable Characteristics of a Single-Mode Optical Fibre and Cable Characteristics of a non-zero dispersion shifted single-mode optical fibre and cable Optical fibre cables for burial application Optical Fibre Joints

3.2

Institute of Electrical and Electronic Engineers (IEEE) Document Number IEEE 802s Series Description Local & Metropolitan Area Networks (LAN/MAN)

3.3

International Electrotechnical Committee (IEC) Document Number IEC 60332 Series IEC 60205 IEC 60495 IEC 60529 IEC 60793 Series IEC 60794 Series Description Test on Electric and Optical Fibre Cables under Fire Conditions Calculation of the magnetic piece parts effective parameters of

Single Sideband Power-Line Carrier Terminals Degree of Protection provided by enclosure (IP Code) Optical Fibres Optical Fibres Cables

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 13 / 38

e & p division

03

Document Number IEC 60834-1 IEC 61000 IEC 61089 IEC 61280-4-2 IEC 60950 IEC 60079

Description Teleprotection Equipment of Power System Electromagnetic Compatibility Round wire concentric lay overhead electrical stranded conductors Field Testing method for measuring single-mode cabling Safety of information technology equipment including electrical business equipment Electrical apparatus atmospheres for explosive gas

3.4

ENI Standards Document Number 20532.EQP.STA.FUN Description Earthing systems for instrumentation plants

3.5

Reference Project Documents CONTRACTOR shall refer to appropriate engineering drawings specifications for the design, manufacture, testing, installation, commissioning of the Telecommunication Systems. and and

Below is a preliminary list of engineering drawings to be developed. This list shall be update during engineering design Document Number 00250600BGSG09005 00250600BIFB48001 00250600BISG50001 00250600BCRB49001 00250600BCSA49050 00250600BCST49080 00250600BCSG49000 00250600BCST49081 00250600BCST49082 00250600BCST49083 00250600BCST49084 Description Site and climatic Conditions ICSS Architecture (Block Diagram) Instrumentation and Control Philosophy Telecommunication Systems Basis of Design Technical Specification for Telecommunication Works Technical Specification For WAN System Telecommunication System Philosophy Technical Specification For Telephone System Technical Specification For PAGA System Technical Specification For CCTV System Technical Specification For RADIO System

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 14 / 38

e & p division

03

Document Number 00250600BCST49085 00250600BCST49086 00250600BCST49087 00250600BCST49089 00250600BCST49092 00250600BCST49093 00250600BCFB49100 00250600BCDQ49101 00250900BCDD49140 00251000BCDD49141 00251100BCDD49142 00251200BCDD49143 00251300BCDD49144 00251400BCDD49145 00252000BCDD49146 00252200BCDD49147 00251900BCDD49154 00250600BCDD49155 00250600BCFB49180 00250600BCFB49181 00250600BCFB49182 00250600BCFB49183 00250600BCFB49184 00250600BCFB49185 00250600BCFB49186 00250600BCFB49187 00250600BCST49189 00250600BCST49190

Description Technical Specification for pipelines and main site Intrusion Detection System Technical Specification for LAN and Structured Cabling Systems Technical specification for ACS System Technical specification for Radio Tower Technical specification for Process CCTV System Technical specification for Pipeline Intrusion Detection System Telecom System Overview Typical Installation Details For FOC Zubair Degassing Station - Preliminary Telecom Equipments Layout Zubair Mishrif Degassing Station - Preliminary Telecom Equipments Layout Hammar Degassing Station - Preliminary Telecom Equipments Layout Hammar Mishrif Degassing Station - Preliminary Telecom Equipments Layout Rafidiyah Degassing Station Telecom Equipments Layout Preliminary

Safwan Degassing Station - Preliminary Telecom Equipments Layout Gas Treatment Plant - Preliminary Telecom Equipments Layout Tank Farm - Preliminary Telecom Equipments Layout Power Plant - Preliminary Telecom Equipments Layout FOD - Telecom Equipments Layout WAN Block Diagram Telephone System Block Diagram PAGA Block Diagram CCTV Block Diagram Radio Communication Block Diagram (Radio System for Existing Remote Facilities) LAN and Structured Cabling System Block Diagram ACS System Block Diagram Intrusion Detection System Block Diagram Process CCTV Block Diagram Pipeline Intrusion Diagram (FOPIMS) Detection System Block

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 15 / 38

e & p division

03

Document Number 00250900BCEB49200 00251000BCEB49201 00251100BCEB49202 00251200BCEB49203 00251300BCEB49204 00251400BCEB49205 00252000BCEB49206 00252200BCEB49207 00251900BCEB49214 00250600BCEB49215

Description Zubair Degassing Station - Preliminary Telecom Material Take Off Zubair Mishrif Degassing Station - Preliminary Telecom Material Take Off Hammar Degassing Station - Preliminary Telecom Material Take Off Hammar Mishrif Degassing Station - Preliminary Telecom Material Take Off Rafidiyah Degassing Station Telecom Material Take Off Preliminary

Safwan Degassing Station - Preliminary Telecom Material Take Off Gas Treatment Plant - Preliminary Telecom Materials Take-Off Tank Farm - Preliminary Telecom Materials TakeOff Power Plant - Preliminary Telecom Materials Take-Off FOD Preliminary Telecom Materials Take-Off

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 16 / 38

e & p division
3.6

03

Environmental conditions CONTRACTOR and SUBCONTRACTOR environmental condition. shall pay attention to the

Please refer to document n 00250600BGSG09005 Site and climatic Conditions for more information.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 17 / 38

e & p division 4
4.1

03

OVERALL REQUIREMENTS
General This specification details the design and characteristics for the FIBER OPTICAL CABLE used for Zubair Field. The FIBER OPTICAL CABLE used for Zubair Field shall be used for data and voice connection between within various site. RTUs, ICSS, Telephones, WAN over FOC, LAN, security, video, trunkline monitoring and integrity signals shall be exchanged between within sites through backbone of fiber optical cables. The FIBER OPTICAL CABLE should be the preferred engineering solution for data exchange of above mentioned services. The function of the Fiber Optical System is to provide a physical layer of connectivity for the distribution of Telecommunications and Automation services along the pipelines, between within the Zubair Field DGSs, main SITES and FACILITIES for both Process and Non-Process areas. The FOC shall also facilitate telecom fiber optic connectivity to the Wells and Manifolds area. Along new oil trunklines, FIBER OPTICAL CABLE shall also be used for pipeline monitoring systems, for that purpose, three cables shall be laid along trunklines: n 1 (one) cable shall be used for LAN/WAN over FOC n 2 (two) cables shall be used for pipeline monitoring system (FOPIMS) This section gives the minimum requirements, reference standards, test and supply conditions for the supply of the fiber optical cables for Zubair Field. The supply shall include but not limited to: Fiber Optical Cables FOC joint splicing enclosures

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 18 / 38

e & p division 5
5.1

03

TECHNICAL REQUIREMENTS
General Three Two types of Fiber Optical Cables (here called FOC Type 1, FOC type 2 and FOC Type 3) shall be supplied by SUBCONTRACTOR suitable for direct buried installation together with Oil trunklines/flowlines and Gas pipelines (FOC Type 1), Water Pipelines (FOC Type 2) and Over Head Lines (FOC Type 3). Type 1 FOC shall be suitable to be installed close to Oil trunklines/Flowlines and Gas pipelines while Type 2 FOC shall be suitable to be installed close to water Flowlines/pipelines. Type 3 FOC shall be suitable for Optical Ground Wires installation over power supply lines. Type 1 FOC shall also be suitable for installation within DGS and Main SITES and remote FACILITIES area for data/voice/video/CCTV signals distribution. Type 2 FOC shall be suitable for installation within DGS and Main SITES and remote FACILITIES area for CCTV Cameras signals distribution. Type 1, and Type 2 and Type 3 FOC quantities shall be defined by CONTRACTOR during engineering design considering at least 10% of spare quantities plus quantities above considered plus at least 10m for each manhole during installation. Type 1 and Type 2 FOC shall be included in the FOC SUBCONTRACTOR scope of supply. Type 3 FOC shall be included in the SUBCONTRACTOR supply of the Over Head Lines package.

5.2

Fiber Optical Cable Type 1 The Fibre Optical Cables Type 1 shall be of Corrugated Steel Tape Armoured, Loose Tubes Single Mode type (SM), suitable for direct burial installation. The number of cable cores shall be 24 The tubes shall be filled with filling compound and stranded, together with fibres, around a central dielectric strength member (FRP) to form a compact and circular core. Loose tube with 6 or 8 fibres shall be acceptable. Around the loose tube and fillers, polyester tape shall be applied. Over the cable core a 1st intermediate black PVC sheath shall be applied. Over the 1st intermediate sheath, to prevent cable from petrochemical and chemical compounds an inner jacket of Aluminium tape (coated on both side with a copolymer), HDPE and Nylon (PA) shall be applied. Cable armouring shall consist of a corrugated steel tube (copolymer coated on both side) located between the Nylon (PA) inner jacket and FR PVC outer jacket. The outer jacket along with the corrugated steel armouring shall protect the fibres from rodents and termites. Each single mode Optical fibre shall be designed to provide good performance at both 1310nm and/or 1550nm. The geometric and transmission characteristics shall fully comply with ITU-T-G-652D (06/2005).

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 19 / 38

e & p division

03

Colour coding and labelling shall be according to IEC 60304. The colour-coding system shall be discernible throughout the design life of the cable. Cable markings shall be printed on the outer fibre cable jacket. The markings shall be permanent, insoluble in water and shall be legible for the duration of the cable life. Markings shall be printed at intervals not exceeding 2m. The outer jacket of fibre optical cable shall be printed as follow: Manufacturer name (MMMMM) Date of fabrication (mm/yyyy) Project name (Zubair Field Development Project) Fibre type (FO24 SM) The fibre optical cables mechanical characteristics shall comply with the following: Maximum Crush Resistance 4000 N/10cm (short term); Tensile Strength in Short term 3000 N (fibre strain < 0,33%)

Drum length shall be no shorter than 4000 m. The FO Cable Drum Schedule shall be provided by CONTRACTOR. The service life for fibre Optical cable shall be 25 years minimum. F.O.C. SUBCONTRACTOR shall provide the Fibre Optical Cable Technical Data Sheets for supplied FO cable and the Recommendations for FO Cable Installation and Laying. For more details on FOC see Fibre Optical Cable Data Sheet at par. 11.1.and 11.2

5.3

Fiber Optical Cable Type 2 The Fibre Optical Cables Type 2 shall be of the Corrugated Steel Tape Armoured Loose Tubes Single Mode type (SM), suitable for direct burial. The number of cable cores shall be 24 4. The tubes shall be filled with filling compound and stranded, together with fibres, around a central dielectric strength member (FRP) to form a compact and circular core. Loose tube with 6 or 8 fibres shall be acceptable. Around the loose tube and fillers, core wrap tape and reinforcement yarns shall be applied. Around the loose tube and fillers, polyester tape shall be applied. Over the cable core a 1st intermediate black PVC sheath shall be applied. Over the 1st intermediate sheath, to prevent cable from petrochemical and chemical compounds an inner jacket of Aluminium tape (coated on both side with a copolymer), HDPE and Nylon (PA) shall be applied. Cable armouring shall consist of a corrugated steel tube located between the polyethylene inner and outer jacket. The FR PVC outer jacket along with the
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 20 / 38

e & p division

03

corrugated steel armouring shall protect the fibres from rodents and termites. Each single mode Optical fibre shall be designed to provide good performance at both 1310nm and/or 1550nm. The geometric and transmission characteristics shall fully comply with ITU-T-G-652D (06/2005). Colour coding and labelling shall be according to IEC 60304. The colour-coding system shall be discernible throughout the design life of the cable. Cable markings shall be printed on the outer fibre cable jacket. The markings shall be permanent, insoluble in water and be legible for the duration of the cable life. Markings shall be printed at intervals not exceeding 2m. The outer jacket of fibre optical cable shall be printed as follow: Manufacturer name (MMMMM) Date of fabrication (mm/yyyy) Project name (Zubair Field Development Project) Fibre type (FO24 SM) The fibre optical cables mechanical characteristics shall comply with the following: Maximum Crush Resistance 3000 N/10cm (short term); Tensile Strength in Short term 3000 N (fibre strain < 0,33%)

Drum length shall be no shorter than 4000 m. The FO Cable Drum Schedule shall be provided by CONTRACTOR. The service life for fibre Optical cable shall be 25 years minimum. F.O.C. SUBCONTRACTOR shall provide the Fibre Optical Cable Technical Data Sheets for supplied FO cable and the Recommendations for FO Cable Installation and Laying. For more details on FOC see Fibre Optical Cable Data Sheet.

5.4

Fiber Optical Cable Type 3 The Fibre Optical Cables Type 3 shall be of the Galvanized Steel Wire Armoured Loose Tube Single Mode type (SM), suitable for overhead installation on high voltage electric lines. The number of cable cores shall be 24 The tube shall be filled with filling compound. Around the loose tube and fillers, reinforcement yarns and protections jackets shall be applied. Multiple tubes should be acceptable. Galvanized steel wires shall be stranded around central loose tube and protections to form a compact and circular cable armouring. Each single mode Optical fibre shall be designed to provide good performance at both 1310nm and/or 1550nm. The geometric and transmission characteristics shall fully comply with ITU-T-G-652D (06/2005).

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 21 / 38

e & p division

03

The colour-coding system shall be discernible throughout the design life of the cable. The fibre optical cables mechanical characteristics shall comply with the following: Maximum Recommended Load: 16 kN Rated Tensile Strength: 500 kN

The service life for fibre Optical cable shall be 25 years minimum. F.O.C. SUBCONTRACTOR shall provide the Fibre Optical Cable Technical Data Sheets for supplied FO cable and the Recommendations for FO Cable Installation and Laying. For more details on FOC see Fibre Optical Cable Data Sheet. FOC SUBCONTRACTOR shall also provide termination cables and accessories for interconnection between OPGW cables to Optical Distribution Frames.

5.5

Fiber Optical Cable Joint Splice and Enclosure The splice enclosures shall be suitable for a single mode FOC according to the Fibre Optical Cable Accessories Data Sheets indicated. In every splice enclosure, the cables shall be marked upon entry indicating the destination of each cable end. The recommended protection degree is IP67 according to IEC 60529. The service life for splice enclosures for aboveground and underground applications shall be 25 years minimum. The splicing enclosures for all FOCs covered by this Specification are included in the scope of supply of the F.O.C. Vendor. Joint splice closure quantities for FOC Type 1 and Type 2 shall be defined during engineering design phase with following criteria: n1 joint splice closure shall be considered every 4 km plus 10% spare of the total quantities. For FOC Type 3 joint splice closure, CONTRACTOR shall in charge to determinate appropriate criteria based on FOC Type 3 cable drums length.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 22 / 38

e & p division 6
6.1

03

DOCUMENTATION
General TECHNICAL DOCUMENTATION, as essential part of the system, shall be submitted to COMPANY/CONTRACTOR with specific dates for delivery. All documentation shall be supplied in English language. Following the minimum set of TECHNICAL DOCUMENTATION that shall be supplied with the system:

6.2

Engineering Design Documentation (Not Applicable) Engineering Design documentation shall contain all relevant information pertaining to the design and operation of the delivered equipment and systems. The documentation is intended to provide COMPANY/CONTRACTOR with an indepth understanding of the operational and design parameters of the system and enable planning of future expansions. Engineering Design Documentation shall include, but not limited to: System Block Diagrams Equipment functional descriptions System functional descriptions

6.3

Construction Drawings and Documentation Construction Drawings and Documentation shall include, but not limited to: Cabinet/Rack Layout (Not Applicable) Equipments Location Plans (Not Applicable) Wiring Diagrams (Not Applicable) Cabinet interconnection drawings (Not Applicable) Termination drawings (Not Applicable) Grounding system drawings (Not Applicable) Power system diagrams (Not Applicable) Installation manuals FOC Data Sheet

6.4

Test and Commissioning Procedures Detailed Test and Commissioning procedures shall be submitted to COMPANY/CONTRACTOR for approval prior to the start of any test and commissioning activities. Test and Commissioning procedures shall provide details for all tests and adjustments to be carried out with descriptions of the methods to be employed. Test and Commissioning Procedures shall include, but not limited to: Factory Acceptance Test Site Acceptance Test Pre-Commissioning Commissioning

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 23 / 38

e & p division
6.5 As-Built Drawings

03

On acceptance of the system by COMPANY, all construction drawings shall be updated to As-Built status to reflect the equipment and system configurations as actually installed. All drawings shall comply with COMPANY drawing standards and drawing format. Both hard and soft copies of As-Built drawings shall be submitted to COMPANY. 6.6 System Documentation Equipment service manuals shall permit the maintenance and repair of the equipment by trained and qualified technicians. The manuals shall contain circuit diagrams, part lists, test and alignment procedures and measurement parameters required to ensure that the equipment may operate within the intended design of type approval specifications. Equipment and system documentation shall include, but not limited to: User manuals System operation manuals Maintenance procedures Equipment technical and service manuals

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 24 / 38

e & p division 7 INSTALLATION

03

Cable shall be installed in accordance with the cable manufacturers specifications and the industry standards, observing cable tensile strength and bending radius limitations. CONTRACTOR shall provide a Cable Drum Schedule. For FOC Type 1 and Type 2, typically the cable drum will be supported on a mobile dispensed which then will travel parallel to the trench. The cables will be manually spooled off the drum and laid directly into the trench. The cable will not be pulled off the drum as the cable will be rotated manually so that the cable is always in a slack condition between the drum and the trench The cables shall be installed as far as practically possible in long continuous lengths without intermediate splices. Where necessary, cables shall be joined as per referenced technical specification. If damage is found during the post-installation test, the cable shall be replaced immediately where applicable. For FOC Type 3, CONTRACTOR/SUBCONTRACTOR shall provide the appropriate installation manual for approval. In case of cable damage and where replacement is not applicable, the CONTRACTOR shall provide a 100 m of new FOC between the double splice boxes. After the splicing, the splicing box shall be tested with an air compressor to evaluate the sealing.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 25 / 38

e & p division 8
8.1

03

BEDDING PADDING AND BACKFILLING OF TRENCH


Trench Bed Preparation In rocky and/or gravel areas or other areas where the material in the bottom of trench has potential to damage the cables, CONTRACTOR shall provide the trench bedding as per the relevant 00250600BLDQ82101 Trench Dimension for Pipeline/Flowline Typical Drawing. The trench bedding material shall be selected desert sand or fine graded material with a maximum particle size of 5 mm. The bedding material shall be free of salt, organic material and hard bodies. Under no circumstances shall the material used for bedding be contaminated by petroleum products, solvents, concentrated acids or alkalis, or corrosive chemical compounds. CONTRACTOR shall place the bedding material along the trench bottom with a minimum thickness of 150 mm throughout its length and shall uniformly grade it to give continuous to cables when lowered into place. The finished surface of the trench bed, shall be at a level necessary to achieve the minimum cables depth of cover.

8.2

Padding and Backfilling The CONTRACTOR shall not commence the padding and backfilling operations until COMPANY has inspected and approved the lowered-in cables. Before any section of trench is padded and backfilled, the CONTRACTOR shall survey and record "as-built" measurements which shall include the location and record of the cables joint number. Padding material shall consist of selected desert sand or fine grain soil meeting the requirements of Paragraph 8.1 of this Specification. The depth of the padding shall be such as to give the cables in place, the specified clearance from the hard backfill material. The padding material shall be carefully placed around the cables in layers uniformly graded. Backfilling of the trench will be performed as soon as possible after the padding. The CONTRACTOR shall plan the backfilling operation so that it can follow as closely as possible the lowering-in, in order to prevent exposing the cables to trench cave-ins and to adverse weather condition. Should it be impossible, for any valid reason, to complete the backfilling operations after lowering-in, CONTRACTOR shall carry out partial backfilling to protect the cables into the trench. Backfilling of the trench shall be completed within 24 hours from partial backfilling. The material used for backfilling will be trench excavated material, free from
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 26 / 38

e & p division

03

construction debris, organic material or aggressive soil and shall not contain rock pebbles and heart clods greater that 1.000 cubic centimetres and 100 mm in any dimensions. The backfilling material shall be placed in such a manner that penetration of pebbles or clods into the padding layer shall be avoided. After backfilling the trench, CONTRACTOR shall form a berm over the cables trench with suitable material to avoid displacement of trench backfill material during the sand storm and similar event. The berm shall not be placed at crossings of roads ditches and the bed of oueds. Gaps on the trench berm shall be left at appropriate locations. The spoil material resulting from the excavation of the pipeline trench shall be disposed off along the Right Of Way in an acceptable manner. Backfilling shall be interrupted at the points where the cables sections are to be spliced. At these points the dimensions of the trench shall be sufficient wide to carry out the splicing in safe condition.

8.3

Installation of Warning Tape Warning tape shall be installed by CONTRACTOR in the trenches 150 mm minimum (between padding and backfilling) over the top of cables, all along the trench. The tape shall be provided by CONTRACTOR. The inscription shall be in English and Arabic languages Warning Fibre Optic Cable.

8.4

Line Markers The cables marker posts shall be located at 1km interval along the cables route unless otherwise specified on Construction Drawings, at crossing with existing pipeline, cables, roads, turning points and at splicing /joint locations required to signal the cables or as shown on the Construction Drawings. Cables markers to be installed shall be able to be read in either direction of the cables route and the kilometre post numbers shall indicate the actual as-built kilometre post from the origin of cables to the terminal.

8.5

Manhole for Joint Splice Closure Joint splice closure shall be installed in dedicated prefabricated concrete manhole. Manhole shall be supplied by CONTRACTOR with internal dimensions 1m x 1m x 1m and 70mm wall thickness (dimensions to be confirmed during engineering design). CONTRACTOR shall provide two types of passive markers to identify the location of each manhole: Buried passive markers Surface passive markers (Line Markers) Manhole shall be supplied with at least n1 hole in one side and n1 hole in the opposite side for cable entry/exit. After cable installation holes shall be sealed by
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 27 / 38

e & p division

03

CONTRACTOR to prevent water and debris ingress. Manhole shall be supplied with a removable cover for future inspection. Inside Manhole the Joint splice closure shall be installed in one side with at least 10 m of coiled spare cable. The spare cable coiled inside the manhole shall be installed to respect the bending radius as per Vendor recommendations. Manhole shall be cleaned from debris, stones, dust, etc before covering and inspected by COMPANY.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 28 / 38

e & p division 9
9.1

03

SPECIAL TOOLS AND TEST EQUIPMENT


Special tools SUBCONTRACTOR shall supply as part of the CONTRACT, all special, system specific tools required to operate and maintain the equipments and the system. These tools shall be different and separate from those tools used by CONTRACTOR to perform his installation and commissioning works. Tools shall be delivered in a new and unused condition directly to COMPANY and shall not be used for installation and commissioning activities.

9.2

Test Equipment SUBCONTRACTOR shall supply test equipments for the normal operation and maintenance of the system. These test equipment shall be different and separate from the test equipment used by CONTRACTOR to perform his installation and commissioning works. Test equipment shall be delivered in a new and unused condition directly to COMPANY and shall not be used for installation and commissioning activities. All test equipment shall have a valid calibration labels and certification traceable to known international standards.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 29 / 38

e & p division

03

10 TEST AND COMMISSIONING


10.1 General All components of the system shall be carefully tested in the manufacturer's workshop and at site before commissioning.

10.2 Factory Acceptance Test (FAT) All materials shall be tested at SUBCONTRACTOR factory site or at a location defined by CONTRACTOR and approved by COMPANY, prior to clearance for shipping and shall include test certifications. Factory Acceptance Test will be to demonstrate adherence of the equipment and materials to the design standards and functional compliance with the specification. The FAT also includes a testing of all interfaces to other systems. Prior to the FAT activities, FAT procedures will be supplied by VENDOR for CONTRACTOR and COMPANY approval. COMPANY personnel may, at COMPANY discretion, attend the FAT. In this case, CONTRACTOR will ensure that all tests shall be carried out in presence of COMPANY personnel. If COMPANY declines to attend the FAT, the tests shall be carried out and the result submitted to COMPANY for approval. All FAT tests shall be documented with the result obtained and their success or failure. Test results shall be submitted to COMPANY prior to clearance of the FAT and authorization to shipping. Test results shall include a list of test equipment used with last calibration date and the acceptable period between calibrations. Each particular cable length shall be factory acceptance tested and shall be delivered together with the respective test reports. Attenuation tests of each fibre at 1310 +30/-15 nm and at 1550 +30/-70 nm with OTDR according to IEC 60793-1 (Parts 1-40 to 1-49) Dispersion tests of each fibre at 1310 and 1550 nm according to IEC 60793-1 (Parts 1-40 to 1-49) shall be performed. Zero dispersion slope shall be performed. These measurements shall be performed on each fibre prior to cable manufacturing and on the fabricated cable. Tension and temperature test of the FOC, as a homologation test, and determination of resulting attenuation and variation in attenuation according to IEC 60793-1 (Parts 1-40 to 1-49) shall be performed. Please refer also to IDS for Fibre Optic Cable document no. 00250600BCGB49840 IDS for Fibre Optical Cable These types of tests shall be performed by F.O.C. SUBCONTRACTOR.

10.3 Cable Testing COMPANY required inspection and witnessed tests shall be as indicated on the document 00250600BCGB49840 IDS for Fibre Optical Cable

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 30 / 38

e & p division

03

10.4 Shop Inspection Testing SUBCONTRACTOR shall be responsible for all testing of materials and equipment prior to delivery. No equipment or materials shall be delivered until all applicable tests have been completed and all defects rectified and re-tested successfully. Documentary evidence shall be available for COMPANY/CONTRACTOR review upon request. The COMPANY/CONTRACTOR reserve the right to witness testing or to request additional testing according to their requirements. The certificate of works test and inspection shall not be accepted until all items on the Test and Inspection Schedule are completed and signed off by SUBCONTRACTOR QA/QC personnel and COMPANY/CONTRACTOR has witnessed tests according to their requirements. Dimensional Tests SUBCONTRACTOR shall carry out tests on incoming goods, to verify the integrity of the materials manufactured. Tube dimension: (with tolerances 10%) Sheath thickness (with tolerances 10%) Outer diameter (with tolerances 10%) inner diameter measurement outer diameter measurement nominal measurement average measurement minimum measurement nominal measurement

Dimensions shall also be tested random (one for each cable length) during the manufacturing process.

10.5 Site Acceptance Test After cable installation activities at site, a Site Acceptance Test (SAT) will be carried out in order to verify the full operational functionality of the system and witnessed by COMPANY personnel who shall certify the acceptance of the system. The SAT will be conducted at first on stand-alone system equipment and then on networked equipment, where applicable. Prior to the SAT activities, SAT procedures will be supplied by SUBCONTRACTOR for CONTRACTOR/COMPANY approval. All SAT tests shall be documented with the result obtained and their success or failure. Test results shall be submitted to COMPANY prior to clearance of the SAT Test results shall include a list of test equipment used with last calibration date and the acceptable period between calibrations. A site acceptance test shall be performed by CONTRACTOR to verify the full operational functionality of the Fiber Optical cables and witnessed by COMPANY personnel who shall certify the acceptance of the cables. The Optical Time Domain Reflectometer shall be used to verify the integrity of the Fiber Optical Cable after installation that shall be carried out without any damage The SAT shall be conducted on cables, but not connected to any existing network equipment. If network connection is necessary to verify functionality, it shall be arranged with COMPANY for limited test access to be provided.
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 31 / 38

e & p division

03

On satisfactory handover, CONTRACTOR shall connect the installed system to the systems for overall voice and data system connection and testing. Prior to the SAT, CONTRACTOR shall submit a test procedure to COMPANY for approval.

10.6 Certificate of Acceptance At the satisfactory conclusion of the FAT, a factory Certificate of Acceptance shall be provided by the SUBCONTRACTOR for signature by the CONTRACTOR/COMPANY. At the satisfactory conclusion of the SAT, a final Certificate of Acceptance shall be provided by the SUBCONTRACTOR. Certificate shall be all test records, receipt for documentation and spare parts plus any other pertinent records regarding the SUBCONTRACTOR delivery. The document becomes a Certificate of Final Site acceptance, which COMPANY shall review and approve.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 32 / 38

e & p division 11 ATTACHMENTS

03

11.1 Optical Requirements Fiber Optic Cable Data Sheet Type 1, and Type 2 and Type 3 FIBRE OPTIC CABLE DATA SHEET Type

1, and Type 2 and Type


Required Guaranteed (*)

3
No.
1 1.1 1.1.1 1.2 1.2.1 1.2.2 1.2.3 1.2.4 1.2.5 1.2.6 1.2.7 1.2.8 1.2.9 1.3 Attenuation 1,2 1.3.1 at 1310 nm at 1550 nm Max average value between 1285 and 1330 nm Local Attenuation (point of attenuation) at 1310 nm at 1550 nm Dispersion value at 1550 nm between 1285 and 1130 nm Zero dispersion wavelength, 0 Zero dispersion slope 1.3.4 1.3.5 Cable cut-off wavelength Macro bending 4 loss at 1550 nm Mode field diameter Cladding diameter Coating diameter Cladding non-circularity Core/Cladding concentricity error Cladding/Coating concentricity error Core refractive index Index profile Structure material Cladding material Primary coating material Doped silica glass Silica Glass Dual Layer UV Cured acrylate Optical Characteristics dB/km 0.36 dB/km dB/km dB/km dB/km
Ps/nmkm Ps/nmkm

sheet 1/3

Description

Unit
Standards

Notes

Optic fibers Type Product specification at 1310 nm at 1550 nm

1, and Type 2 and Type 3


ITU-T G.652D

Construction Requirements m m m m % m m 125.0 1.0 245 10 5.0 0.6 12.5

0.25 0.45 0.10 0.10

1.3.2

1.3.3

nm
Ps/nm2 km

1300 0 1324 0.092 1260 0.05

nm dB

Note: 1 : Temperature : +20C 3C 2 : : 1310 nm = 1310 +30/-15 nm , 1550 nm = 1550 +30/-70nm 3 : Polarization Mode Dispersion 4 : Bend test : 100 turns on a 60 mm diameter mandrel

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 33 / 38

e & p division

03

11.2 Construction Requirements for Fiber Optic Cable Type 1 FIBRE OPTIC CABLE DATA SHEET TYPE No.
2 2.1 2.1.1 2.1.2 2.1.3 2.1.4 Product specification Number of fibres Lifetime Cable length (per drum) Temperature 2.1.5 2.1.6 2.1.7 2.1.8 2.1.9 2.1.10 2.1.11 2.1.12 Central Strength Member (CSM) Loose tube Cable core Core filling: dry core or flooded Wrapping 1st Inner Sheath (6,7) Aluminum Tape HDPE Nylon (PA) 2.1.14 2.1.15 2.1.16 2.1.17 2.2 2.2.1 2.2.2 2.2.4 2.2.5 2.2.6 2.2.7 2.2.8 Minimum Bending Radius during installation Minimum Bending Radius without force Maximum crush resistance (Short term) Maximum crush resistance (long term) Tensile Strength (Short Term) Tensile Strength (Long Term) Water Penetration N/10cm N/10cm N N Armoring Outer Sheath Weight per drum Outer Diameter mm Kg mm Additional Construction Requirements 20 x Cable Diameter 15 x Cable Diameter 4000 1000 3200 (fibre strain <0.33%) 1400 (zero fibre strain) 3m cable/ 1m water
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

1
Guaranteed (*)

sheet 2/3

Description

Unit

Required

Notes

24 Cores Fiber Optic Cable Type General IEC 60794-3 No. yrs km operational laying storage C C C mm mm 24 25 4 ( 0,1) -5 to +60 -10 to +40 -30 to +70

According to cable drums schedule


According to (IEC 60794-1-2-F1)

2.0 - 2.6 (FRP) 2.0 - 2.5 (PBT 6 or 8 fiber for each loose tube) Four or three loose tube and filler stranded around CSM Swellable tape or Compund Included 1.0 (PVC) 0.15 + 0.04 1.0 0.5 Corrugated Steel Tape 2,5 (FR PVC)

mm mm mm mm

According to (IEC 60794-1-2-E11) According to (IEC 60794-1-2-E11) According to

(IEC 60794-1-2 E3)


According to

(IEC 60794-1-2 E3)


According to

(IEC 60794-1-2-E1)
According to

(IEC 60794-1-2-E1)
According to

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042 column x 24 h (no leakage) 20Nm, R=200 mm, 3 spots IEC 60304

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 34 / 38

e & p division

03 (IEC 60794-1-2-F5)
According to

2.2.9 2.2.10

Impact Fiber Coloring

(IEC 60794-1-2-E4)

Note: 5 : Filling compound in tubes and cable core must not impair the colour of the secondary coating, must be easy removable from primary and secondary coating, must be non-toxic, scentless and harmless to human skin 6 : According to IEC 60811-4-1 7 : According to IEC 60189-1

(*) To Be filled by Supplier

11.3 Construction Requirements for Fiber Optic Cable Type 2 FIBRE OPTIC CABLE DATA SHEET TYPE No.
3 3.1 3.1.1 3.1.2 3.1.3 3.1.4 Product specification Number of fibres Lifetime Cable length (per drum) Temperature 3.1.5 3.1.6 3.1.7 3.1.8 3.1.9 3.1.10 3.1.11 3.1.12 3.1.13 3.1.14 3.1.15 3.1.16 3.1.17 3.2 Central Strength Member (CSM) Loose tube Cable core Flooding Compound Wrapping Strain Bearing Element Inner Sheath (6,7) Inner Sheath Tape Armoring Outer Sheath Weight per drum Outer Diameter mm Kg mm Additional Construction Requirements
This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

2
Guaranteed (*)

sheet 3/3

Description

Unit

Required

Notes

4 24 cores Fiber Optic Cable Type General IEC 60794-3 No. yrs km operational laying storage C C C mm mm 24 4 25 4 ( 0,1) -5 to +60 -10 to +40 -30 to +70

According to cable drums schedule


According to (IEC 60794-1-2-F1)

2.0 - 2.6(FRP) 2.0 - 2.5 (PBT 4 6 or 8 fiber in one for each loose tube) Four or three loose tube and filler stranded around CSM Water proof Gel Included Reinforcement Yarns

mm

1,5 (PE ) Water Swellable tape Corrugated Steel Tape 2,5 (FR PVC)

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 35 / 38

e & p division
3.2.1 3.2.2 3.2.4 3.2.5 3.2.6 3.2.7 3.2.8 3.2.9

03

Minimum Bending Radius during installation Minimum Bending Radius without force Maximum crush resistance Tensile Strength (Installation) Tensile Strength (Operation) Water Penetration Impact Fiber Coloring N/10cm N N

20 x Cable Diameter 15 x Cable Diameter 3000 3000 (fibre strain less than 0.1%) 2500 (zero fibre strain) 3m cable/ 1m water column x 24 h (no leakage) 20Nm, R=200 mm, 3 spots IEC 60304

According to (IEC 60794-1-2-E11) According to (IEC 60794-1-2-E11)

According to

(IEC 60794-1-2-E1)
According to

(IEC 60794-1-2-E1)
According to

(IEC 60794-1-2-F5)
According to

(IEC 60794-1-2-E4)

Note: 5 : Filling compound in tubes and cable core must not impair the colour of the secondary coating, must be easy removable from primary and secondary coating, must be non-toxic, scentless and harmless to human skin 6 : According to IEC 60811-4-1 7 : According to IEC 60189-1

(*) To Be filled by Supplier

11.4 Construction Requirements for Fiber Optic Cable Type 3 FIBRE OPTIC CABLE DATA SHEET TYPE No.
3 3.1 3.1.1 3.1.2 3.1.3 3.1.4 Product specification Number of fibres Lifetime Cable length (per drum) Temperature 3.1.5 3.1.6 3.1.7 3.1.8 3.1.9 3.1.10 3.1.11 3.2 3.2.1 Minimum Bending Radius during Loose tube quantity Flooding Compound (1) Protection Jacket Armoring Weight per drum Outer Diameter Kg mm Additional Construction Requirements 40 x Cable Diameter operational laying storage No. yrs km C C C n -50 to +80 -50 to +80 -50 to +80 1 to 4 Water proof Gel Aluminium Galvanized Steel Wire

3
Guaranteed (*)

sheet 3/3

Description

Unit

Required

Notes

24 cores Fiber Optic Cable Type General IEC 60794-4 24 25

According to cable drums schedule

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 36 / 38

e & p division
installation 3.2.2 3.2.3 3.2.4 3.2.5 3.2.6 3.2.7

03

Minimum Bending Radius without force Tensile Strength (Installation) Tensile Strength (Operation) Electrical Resistance (at 20C) Short Circuit Rating from 40C Short Circuit Current for 0.3 s kN kN Ohm kA2s kA

20 x Cable Diameter > 50 > 40 < 0.8 > 40 > 11

Note: 1 : Filling compound in tubes and cable core must not impair the colour of the secondary coating, must be easy removable from primary and secondary coating, must be non-toxic, scentless and harmless to human skin

11.5 Joint Splice Enclosure for Fiber Optic Cable FOC ACCESSORIES DATA SHEET

Joint Splice Enclosure


No.
1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 1.13 1.14 Water ingress protection Pressure rating Splice organizer tray for 24 cores (4 trays as minimum) Storage temperature Compression resist deforming Pressure Testing Valve Splice closure Installation Kit inside manhole Earthing derive device Splice Protection Sleeves Inlet/Outlet Ports Cable blocking type heat shrink Splice numbering Service life set set Nr nr set set years IP bar splices C kg

Description

Unit

Required
67 1 24 for 24 cores FOC, 4 for 4 cores FOC 40 to +70 182 On closure Body Dome Type 1 1 24 4 round 1 oval 1 1 25

Guaranteed

Notes

Splicing Enclosures

Joint splice enclosures for FOC type 3 shall be adequate to OPGW installation.

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 37 / 38

e & p division

03

12 ESTIMATED QUANTITIES OF FIBER OPTIC CABLE AND SPLICE CLOSURE


The table below indicating F.O.C. and Joint splice quantities shall be filled by EPC CONTRACTOR during engineering design and supplied by SUBCONTRACTOR

F.O.C. Type 1

(*) Estimated Length (Km)

(**)Joint Splice Closure (n)

FROM

TO

10% Spare Spare quantities at terminal points

Total ___Km Total ___Km Total ___ Km

Total n ____ Total n____

TOTAL
____ Km
(F.O.C)

TOTAL
N ____
(Joint Splice Closure)

F.O.C. Type 2

(*) Estimated Length (Km)

(**)Joint Splice Closure (n)

FROM

TO

10% Spare Spare quantities at terminal points

Total ___Km Total ___Km Total ___ Km

Total n ____ Total n____

TOTAL
____ Km
(F.O.C)

TOTAL
N ____
(Joint Splice Closure)

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.

Logo and business name of Document owner

Company Document Identification


00250600BCST49042

Owner Document Identification


022026-2506-HAE-49042

Revision Index Validity Status CD-FE Rev.

Sheet of Sheets 38 / 38

e & p division

03

F.O.C. Type 3

(*) Estimated Length (Km)

(**)Joint Splice Closure (n)

FROM

TO

10% Spare Spare quantities at terminal points

Total ___Km Total ___Km Total ___ Km

Total n ____ Total n____

TOTAL
____ Km
(F.O.C)

TOTAL
N ____
(Joint Splice Closure)

This document is property of Eni S.p.A. Exploration & Production Division. It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.