No Activity Owner-Primary
1 Communication to MTT users Informing "System Down Time" Syed Suboor
2 Appoval from Sponsor "Go & No-Go" Srini Sandaka
3 DB backup Lakshmi Alekya
4 Preparation of Production Tables Harshada
5 Locking of Users"Except Production Deplyment Users" Harshada
6 Production Deployment FE Lakshmi Alekya
7 Production Deployment BE&DB Priyanka Ashok
8 Code Deployment Confirmation Suresh
9 Sanity Checks Karthika P
10 Unlock All users Priyanka Ashok
11 Communication to MTT users Informing "System Up-Time" Syed Suboor
Owner-Secondary Start Date & Time End Date & Time
Bhaskar Konda 29/12/23 18:00 IST 29/12/23 18:00 IST
29/12/23 19:00 IST
29/12/23 21:00 IST 29/12/23 21:30 IST
29/12/2023 21:30 IS29/12/2023 22:00 IST
Harshada & Suresh 29/12/23 21:00 IST 30/12/23 01:00 IST
Siva Naga Lakshmi Priyanka & 29/12/23 22:00 IST 29/12/23 23:00 IST
Harshada 29/12/23 22:00 IST 29/12/23 23:00 IST
Suresh,Harshada, Lakshmi Ale 29/12/23 23:30 IST 30/12/23 00:00 IST
Pavan Kumar T 29/12/23 22:00 IST 30/12/23 00:45 IST
Harshada& Suresh 30/12/23 00:45 IST 30/12/23 00:50 IST
Bhaskar Konda 30/12/23 00:55 IST 30/12/23 01:00 IST
Comments
"Planned email About application Down time"

023 22:00 IST

Planned Email About Application Up-Time