Minnesota Vikings

Activity Name

Summary and Milestones


Football Seasons Milestones

2011 2012 2013 2014 2015 A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N


2011 Legislative Approval 11/30/11*, 2012 Start Construction 11/28/12, 2013 2014 Substantial Completion 2015 8/27/15

Off-Site Roadway Improvements - MnDOT


Environmental Impact Studies/Approvals Roads / Infrastructure Improvements

Environmental Assessment / Approvals Project Layouts & Ph 1 Permits DB Procurement Design & Ph 2 Permits Construction

New Vikings Stadium

Planning and Development

Site Acquisition Environmental Impact Studies/Approvals Remediation Plan / MPCA Approvals Financing / Bond Sale

Site Acquisition EAW / Scoping Stadium Site Draft EIS Bldg 502 Sale Final EIS Remainder

Stadium Design

Authorization / Docs

Select Design & Construction Team Preliminary Design Construction Documents

Select Team Conceptual Schematics Design Development Construction Documents

Site Preparation
Site Utilities

Environmental Remediation Site Preparation

Investigation Stadium Footprint Initial Demo

Bldg 502

Remainder

Demo Clear Approvals Design Construction

Stadium Construction
Foundations Structure

Site Prep and Excavation

Roof Structure

Enclosure Interior Rough-In

Equipment Drywall and Finishes Site Improvements Street Improvements / Parking Furniture, Fixtures, and Equipment
Milestone Design

Systems Start-Up / Project Cose-Out


Actual Work Approvals Pre-Season Regular Season Post-Season

Development

Construction

Preliminary Schedule

Project ID: 08150003-12-2011-3... Layout: Arden Hills Summary TASK filter: Vikings Arden Hills Site.

Start Date 1/1/11 Finish Date 12/30/15 Data Date 1/1/11

Page 1 of 1 Run Date 10/19/11 10:15