Beruflich Dokumente
Kultur Dokumente
of
IEC 61508 and IEC 61511
Day 1
C. Timms
Tel: +44 (0) 1339 886618
c.timms@ifb.co.uk
Published 98-99
Safety Case
Regulations 1992:
Following Piper Alpha -
1988
© C & C Technical Support Services 2008 15 IEC 61508/61511 Training
Background:
Safety Case Regulations
The Offshore Installations (Safety Case)
Regulations (SCR), 1992
Prevention of Fire, Explosion and
Emergency Response (PFEER) on
Offshore Installations Regulations, 1995
The Offshore Installations and Wells
(Design and Construction etc.)
Regulations, 1996
4. Overall safety
requirements
Design/
Implementation
15%
RAISE
ACTIONS
Mechanical,
Instrument based
process design,
safeguards
procedural etc
Action
Responses &
Closeout
SIL Risk
Assessment
Process Development…...
Process Definition…………….
Process Design……………………...
Commissioning……………………………………………………….
Operation…………………………………………………………………………..
Eliminate Inventory
Minimise Pressure
Substitute Temperature
Moderate Energy release
Simplify Process equipment
Unwanted reaction
© C & C Technical Support Services 2008 35 IEC 61508/61511 Training
Hazard study 2
The purpose of Hazard study 2 is to identify significant
hazards and ensure that there are appropriate measures
to eliminate risk or reduce risks to tolerable levels
Key Aspects
Identification of significant hazardous events
Identification of causes or sequences that lead to
the hazardous event
Consequences
Quantification likelihood of Unmitigated Risks
Identify preventative measures to reduce
likelihood
Emergency measures to reduce consequences
Confirmation of relief and control philosophies
Team members
Process, Operations, HS&E, instruments etc.
Flow sheets and equipment details
Control block diagrams
Input from Hazard Study 1
Causes?
Consequences?
Can it be prevented?
Yes No
Internal fire √ √
Internal √ √
explosion
etc
Environmental √ √ 05/2
Pollution
Special items √ √
raised
Principles of HAZOP:
To identify Hazards or operability problems
through credible deviations from the design
intent.
The methodology is based on parameters and
“ guideword examination” of elements of a
plant or system
PHA/Haz 2 HAZOP
Preparation Phase
Plan--Collect Data--Choose recording method
Estimate time required- Arrange the schedule
Examination Phase
Divide system into elements--Examine element for deviations from design intent
Identify possible deviations, cause, consequences, protection needs
Agree actions -repeat for each element
Guideword Meaning
NO or NOT (or none) None of the design intent is achieved
MORE (more of, higher) Quantitative increase
LESS Quantitative decrease
Qualitative modification or additional
AS WELL AS (more than)
activity occurs
Only some of the design intent is
PART OF
achieved.
REVERSE Logical opposite of design intent
Complete substitution – another activity
OTHER THAN
takes place.
Elements
Material Transfer
FIC
B
A
Level
Study begins
Level Flow Control Temperature
Speed Pressure
Composition
Temperature Reaction
Key Aspects
Study is review of design and construction done after the
construction is substantially completed but before process
materials are introduced
Equipment and hardware as per design
Validation of completion of Previous Hazop Study actions
Emergency systems and procedures are in place
Operating Instruction are available and employee training is
adequate
Key Aspects
Study is done before process materials are introduced or
commencement of operations which ever is sooner
Validation of safety, health and environmental management
systems and procedures are in place
Validation of Emergency Systems are operational
Key Aspects
Done 3-6 months after plant operation
Validation that all documentation has been updated
Modifications made during commissioning and start up have not
altered
the risk profile
Validation of compliance to conditions of consent
Validation of employee occupational health monitoring
Broadly acceptable
region
(No need for detailed working to
demonstrate ALARP)
1 in 10 million per person/yr
Negligible risk
© C & C Technical Support Services 2008 61 IEC 61508/61511 Training
Reducing the Risk
Examples of risk reduction methods:
Design (probability of occurrence)
Mechanical strength (probability of occurrence)
Location (probability of occurrence and consequence)
Control (probability of occurrence)
Alarms (probability of occurrence)
Safety instrumented functions (probability of occurrence)
Other technology SRSs - Mechanical relief
(consequence)
Alarm Layer
Process
Increasing
risk
Consequences
of hazardous
event
(SIF)
Logic
Solver PCV
Start fire pump
Logic
PICA Fire Solver
PZA1 Activate area deluge
Inlet
XZV1
LICA
Some SIF’s mitigate
after the event
Outlet
consequences e.g.
Fire & Gas reduce LCV
escalation
PSV1
Flare
1oo2 voting
LICA
LZA2
LL
Oil out
XZV4 LCV
1oo2 voting
LICA
LZA2
LL
Oil out
XZV4 LCV
Instrumented
Initiator e.g. PZA1 Protective XZV1/2 – Inlet
System
Function 2
PZA1 Function 1
Final element
Function 2
Instrumented
Confirmed Protective XZV1/2 - Inlet
High Level System
Gas
LZA1 Function 3
Initiator 2 x x x
Initiator 3 x x x x
Initiator 4 x x x x
Initiator 5 x x x x
If a SIF fails:
There will be certain consequences which
could result in:
Harm
Damage to equipment and/or loss of production
OR gate
P1 + P2
F1 + F2
Flammable
gas
F1 = 0.1per year
LIC 100 HLA 01 The level of liquid in a tank is controlled and monitored as
shown in the diagram. The failure frequencies and probability of
failure for all the elements are given in the table below. Use a
fault tree analysis to determine how often the tank is going to
Overflow overflow.
XZV 200
W3 W2 W1
CA X1
a --- ---
X2
Starting point
for risk reduction
PA 1 a ---
CB FA PB X3
estimation
FB PA 2 1 a
CC PB X4
FA
FB PA 3 2 1
PB X5
Generalized arrangement
(in practical implementations
CD FA
FB PA 4 3 2
the arrangement is specific to X6
PB
the applications to be covered
by the risk graph) b 4 3
C = Consequence parameter --- = No safety requirements
Consequence (C) Average number of Fatalities CA Minor injury 1.The classification system
This can be calculated by determining the average has been developed to deal
numbers present when the area is occupied and CB Range 0.01 to 0.1 with injury and death to
multiplying by the vulnerability to the identified hazard. people.
The Vulnerability will be determined by the nature of 2.For the interpretation of CA,
CC Range >0.1 to 1.0 CB, CC and CD, the
the hazard being protected against. The following
factors are proposed consequences of the accident
V=0.01 Small release of flammable or toxic material CD Range > 1.0 to 10 and normal healing shall be
taken into account.
V=0.1 Large release of flammable or toxic material
V=0.5 As above but with a high chance of igniting or
highly toxic.
V=1 Rupture or explosion
Exposure probability in the hazardous zone (F) FA in the hazardous zone. 3. See comment 1 above.
This is calculated by determining the length of time the Occupancy less than 0.1
area is occupied during a normal working period.
NOTE - If the time in the hazardous area is different FB Frequent to permanent
depending on the shift being operated then the exposure in the hazardous
maximum should be selected. zone. Occupancy more
NOTE - It is only appropriate to use FA where it can be than 0.1
shown that the demand rate is random and not related
to when occupancy could be higher than normal. The
latter is the case with demands which occur at
equipment start-up
Possibility of avoiding the hazardous event (P) if the PA Adopted if all 4. PA should only be selected if all
protection system fails to operate. conditions in column the following are true:-
4 are satisfied • facilities are provided to alert the
operator that the protection has
failed
Adopted if all the • independent facilities are
conditions are not provided to shut down such that the
PB satisfied hazard can be avoided or which
enable all persons to escape to a
safe area
• the time between the operator
being alerted and a hazardous
event occurring exceeds 1 hour or
is definitely sufficient for the
necessary actions.
Demand rate of the unwanted occurrence (W) given no W1 Demand rate less 5. The purpose of the W factor
protection system. than 0.03 per year Is to estimate the frequency of the
To determine demand rate it is necessary to consider all hazard taking place without the
sources of failure that will lead to a demand on the W2 Demand rate addition of the SIS
protection system. In determining the demand rate, between 0.3 and 6. If the demand rate is very high
limited credit can be allowed for control system 0.03 per year (e.g., 10 per year) the
performance and intervention. The performance which
can be claimed if the control system is not to be
designed and maintained according to IEC61508, is W3 Demand rate
limited to below the performance ranges associated with between 3 and 0.3
SIL1. per year
W3 W2 W1
CA ---
a --- ---
X2
Starting point
for risk reduction
FB
PA a
1 ---
a ---
CB PB X3
estimation
FB PA 1
2 1a a
---
CC PB X4
FB PA
3
2 21 1a
PB X5
32
CD
Generalized arrangement
(in practical implementations FB PA 3
4 21
the arrangement is specific to X6
PB
the applications to be covered
by the risk graph) b
4 43 32
C = Consequence parameter --- = No safety requirements
CA ---
a --- ---
X2
Starting point
for risk reduction
FB
PA a
1 ---
a ---
CB PB X3
estimation
FB PA 1
2 1a a
---
CC PB X4
FB PA
3
2 21 1a
PB X5
32
CD
Generalized arrangement
(in practical implementations FB PA 3
4 21
the arrangement is specific to X6
PB
the applications to be covered
by the risk graph) b
4 43 32
C = Consequence parameter --- = No safety requirements
Required
integrity
Environmental Shutdown
integrity of systems
Function A
Function C
Control
etc systems
120 Bar
XZV1
Notes: PCV1
Classification:
Demand rate (W) :
Personnel consequence severity :
Personnel exposure :
Alternatives to avoid danger :
Personnel Safety SIL :
V101 HP
100Bar
LP
IA
4Bar
FZA
LL
FICA
L
Spec.
Break
Pump Notes:
1. Determine the consequences of The NGL unit is in a location not routinely
visited by an operator, but the pump has a
failure on demand of FZA for:
local stop/start.
a) Personnel safety
The NRV is not a tight shut off.
b) Production/equipment loss
The pump has a history of stalling 1 or 2
c) Environmental times a year.
2. Suggest improvements to the design. The plant has a large public exclusion zone
Classification:
Demand rate (W) :
Personnel consequence severity :
Personnel exposure :
Alternatives to avoid danger :
Personnel Safety SIL :
(LOPA)
LA
LIC
Closed drains
XZV1
10 Barg LICA
Long flow line
with tendency to
Outlet
surge @ 20 Barg
LCV
Intermediate Event
Frequency
Total Mitigated Event
Frequency
Tolerable Event
Frequency
Required SIS risk
reduction
Overpressure and
loss of containment
from First Stage Event Frequency
Separator
Protection &
Mitigation
Layers
Intermediate Event
Frequency
Total Mitigated Event
Frequency
Tolerable Event
Frequency
Required SIS risk
reduction
Overpressure and
loss of containment
from First Stage Event Frequency
Separator
Protection &
Mitigation
Layers
Intermediate Event
Frequency
Total Mitigated Event
Frequency
Tolerable Event
Frequency
Required SIS risk
reduction
100
90
80
70
60
% 50
40
30
20
10
0
SIL 0 SIL 1 SIL 2 SIL 3
Typical findings:
Large UK Natural Gas Processing Plant
Typical findings:
3rd Generation Platform – W. Africa