Beruflich Dokumente
Kultur Dokumente
Presentation by:
Contents
EWPL Project and its Challenges Special Crossings Crossing Methodologies Microtunnel HDD Float and Sink Cofferdam
Construction methods viz. Micro tunnelling, HDD, Float and Sink, Cofferdam and other construction adopted World record crossing of over 2 400 m long Gauthami Godavari 2,400 river executed by using Microtunneling World record HDD crossings of 48 diameter pipeline; 1,724 m long Vashista Godavari river and 1 500 m long Narmada river 1,500
Trunkline Crossings
Record number of Crossings viz. Road (NH, SH, MDR, Others), Railway, Canal, River, Streams, 3rd Party Pipelines, etc. encountered by Trunkline. In all 1770 crossings were encountered, which is approx. 1.3 Crossings per km of pipeline length Total HDD Crossings in EWPL is over 8,200 m
River Crossings
Crossings are the most difficult part of pipeline project execution. It involves extensive surveys investigation design evaluation of surveys, investigation, design, construction methodology including identification of technology limitations, careful planning and establishment of additional infrastructure. Resource mobilization of specialized equipment and manpower is a challenging task as additional specialized equipment to tackle contingency measures also to be mobilised. g y Crossing location normally selected during overall pipeline route selection Selection is done such that the crossing length is minimum, river does not meander, meander riverbed with minimum rock gentle banks on both sides rock, sides, adequate space available beyond the banks for construction infrastructure .
Presentation Coverage
This presentation covers : World Record Microtunnel Crossing across Gauthami Godavari World Record HDD Crossing across Vashista Godavari Tapi River Crossing adopting Float & Sink Technique Terna River Crossing adopting Cofferdam Technique
Crossing Location
HDD
Infrastructure Established
Access Roads to Shaft locations Temporary Pipe Bridge across an irrigation canal on East side Hard Stand provided around Shaft Temporary pipe factory for shaft segments and jacking pipes p ypp y g j gpp
Pipe F t Pi Factory
Shaft Locations
West Shaft
Center Shaft
East Shaft
Shallow Sh ll Shaft
1304 m
1135 m
80 m
- 11.1 m dia, 8.5 m deep (Launch) 11.1 m dia, 9 m deep (Launch) 8.8 m dia, 26.7 m deep (Receipt) 8.8 m dia, 7 m deep (Receipt)
Shaft Rings
Soft Eye
Soft Eye
Base Slab
Grout
Shaft Installation
Site Preparation
Shaft Sinking
Shaft Sinking
Tunneling Operations g p
Tunnelling operations planned from both east and west banks simultaneously, so that the activity completed before onset of monsoon. Two TBMs mobilised to site. Tunnel driven through silty fine sand, clayey sand, clayey silt and fine to medium sand with traces/pockets of clay or gravel m um n w /p f y g Dual mode TBM (EPB 2400 AH) mobilised, which operated on EPB (Earth Pressure Balance) for clayey silt and Slurry mode for sand and g gravel TBM cutting head turns during tunnel pipe jacking operation and the cutting tools at the face cut the soil. Soil is pressed through the opening in the cutter head into excavation chamber. p g In EPB mode, soil is transported via screw conveyor out of the excavation chamber to a belt conveyor and into a muck car. Muck car p pulled over the rails installed within the tunnel pipes by a hydraulic pp winch.
Tunneling Operations g p
In Slurry mode, the material is transported via screw conveyor out of the excavation chamber to a slurry box. Soil is mixed with water and then pumped through a slurry line to surface via pumps. Pump transfers the material to a desander where the water from material is separated. Jacking is done with the help of 4 no. hydraulic cylinders, 4 m stroke length, located within the launching shaft. Jacking arrangement connected with hydraulic hose to the control container located y above ground near the shaft Lubrication system comprising of mixture of water and bentonite is used to reduce skin friction between tunnel pipe and surrounding soil
Tunneling Operations u g p
Intermediate jacking station (IJS) is used to give additional thrust to push the pipes. Control of pipeline alignment is monitored through UNS, capable pp g g , p of detecting deviations from planned alignment and level occurring during jacking operation. Once deviations are detected, the same is corrected through the steering cylinders at the head of TBM. Rubber sealant is used between tunnel segments for water g tightness
Jacking Pipe
Anchor Steel Collar Rubber Seal
Hydrophilic Seal
Sealing
TUNNELLING OPERATIONS
Commencement of Tunnelling
Gantry Set-up
Jacks in Operation
Jacking Pipe Aligning
Tunneling Operation u g p
West Shaft
Center Shaft
East Shaft
Shallow Sh ll Shaft
1304 m
1135 m
80 m
IJS No.1
IJS No.2
Main Jacks
Lubrication System
Lubrication Compr. Air
Bentonite Lubrication
Pipe Lift-off
Rail/wheel Misalignment
Rail Misalignment
Project Milestones
Infrastructure works commenced in May, 2006 Site development and pipe factory works commenced in June, 06 Shaft construction started in Nov 06 and completed in April 07 East, West, East West Central and Shallow Shafts took 26 23 72 and 14 days 26, 23, respectively to complete Tunneling commenced in January 07 and completed in May 07 Tunnel from East to Central Shaft (280 pipes), West to Central Shaft (324 pipes) and East to Shallow Shaft (12 pipes) took 84, 83, and 16 days respectively i l Fabrication of 2400 m long product pipe took 4 months between Feb and May 07 Product pipe pushing took 6 days to complete in July 07
Project Statistics
Approx. 20,000 m3 of soil removed during tunneling Tunnelling activity took days to complete Total concrete used is 5,700 m3 and steel used 820 t. Number of RCC Tunnel pipes used is 616. Annular space filled with grout (mix of fly ash, cement and bentonite); 3,500 t of fly ash, 1,000t of cement and 400 t of ) y bentonite; Total grout used 8,600 m3. Grout filling done from East to Central Shaft and Shallow to Central Shaft in C t l Sh ft i 12 d s and 22 d s respectively days d days s ti l
Background
Past history in executing large dia HDD were limited at the project development stage. 48 48 Size & over 1700 m length made this crossing biggest HDD attempted ever before. Any failure would seriously affect the project completion schedule, thus a fail-safe methodology was required required. HDD Contractors willing to stretch the limit of technology, but were unwilling to take high risks involved. Despite approaching renowned HDD Contractors worldwide, firm proposals could not be secured. g p p p To encourage HDD Contractors participation, innovative concepts of Cost Plus and Risk Sharing were required. Infrastructure related works got done separately Renowned HDD specialists engaged to finalise methodology and equipment selection.
Constraints
River flood-prone during monsoon (July October) and HDD works were to be performed between November and June. High embankment (> 5m) on either banks (Flood Bunds) restricted the working space availability. Entry/exit points were to be located within the river, so that drilled length is minimum and the construction methodology feasible feasible. Any delay in construction, may result in work abandonment due to river flooding Space available between exit point and the flood bund not enough for accommodating the product pipe string p p q g g Flood Bunds were not permitted to be cut open, hence requiring huge temporary ramps to be constructed on either sides Pulling the pipe over the ramp required additional equipment provision
Crossing Location
Crossing located at KP 64.7 on EWPL Trunkline in Andhra Pradesh State Length of the crossing more than 1700 m m. Product pipe : 48 dia, 25.4 mm thk, X-70, & FOC 8 dia
Flood Bund
Flood Bund
Pipe Side
Rig Side
Design
Site investigation done, soil analysis and scour potential estimated, pipe profile worked out to be below the scour profile. M i Maximum cover of 36 m b l f below th river b d the i bed Due to stiffness of 48, 25.4 mm thk pipe, profile with a radius of 2000 m for both entry and exit curves required. Pipe profile passed through successive layers of 200 m of silty sand at entry curve, a second section of 1100 m of clay layer on the central horizontal section, and in a final section of 424 m of silty sand at the exit curve Entry & Exit angle - 6 Deg silty Soil conditions favorable for HDD, but the interface between the siltysand and clay layers were critical
Methodology
Methodology developed duly taking into account the field constraints and the risks involved Two rigs envisaged to provide assistance when needed envisaged, Para Track system considered of tracking the pilot hole Floatation trench considered to reduce the pipe weight and to reduce the pull-back forces pull back Ramps on either sides of flood bund on pipeside considered to enable pipe cross-over during pull-back operation Buoyancy system considered to reduce downhole pipe weight, and also y y y pp g not to exert loading during pull-back on ramp Multiple contingency arrangements viz. RCC Anchors, Air Hammer and winches provided for Round the clock working considered due to the type of soil present HDD Specialists mobilised to provide round the clock support and technical assistance
Pipe Profile p
Scour Profile
Infrastructural Works
Approach roads from nearest main road to Rig Side and Pipe Side
Anchor foundation for 400T/250T Rig Lagoons for mud preparation & water storage Hard stand around Rig site & Pipe site area Ramp on Flood bunds for Vehicular movement and string preparation/Pulling Floatation Trench for Pipe string Anchors for contingency
Equipment Deployment
Drilling Spread comprising of 2 no. rigs viz. 400 T with a torque capacity of 120 kNm on the rig side, and a 250 T rig with a torque capacity of 90 kNm on the pipe side. Downhole tools consisting of 2000 m 5 drill pipes Gr S 135 and 2000 m 5 Gr S 135 drill pipes; 10 no. fly cutters and 9 no. barrel reamers of various sizes Mud equipment included 2 no. mud mixing tank, 2 no. recycling unit, 3 no. high pressure pumps (for 2.5 m3/minute), 13 no. transfer pumps and 2 no. mud return pumps (150 m3/minute) for running the mud system in between mixing, recycling and pumping equipment. Air Hammer Taurus combined with 2 no. 30 t winches to provide assistance to 400 T rig at the tail of the product pipe during pull back operation 600 T THR Bentonite and 50 t additives mobilised with mud engineers Side boom 90 t 5 no 70 t 2 no no., no.
HDD O Operations i
Mobilization started in September 2006, and the first drilling spread (250 tons) reached the site two months later for starting the first pilot hole Drilling spreads, including one 400 T and 250 T rigs, set up at entry and exit points, located inside the floodable zone of the river Product pipe string, 1724 m long, positioned at the exit side, over 5 m high flood bund by building two ramps . To reduce the pulling loads, entire pipe string beyond flood bund made to float within a trench filled with water. Custom built heavy duty rollers (80 T) used for accommodating the pipe string between the trench and exit point, thru the ramp.
HDD Operations
Work performed on 24 hrs basis due to the nature of soil present 1st Pilot hole completed in 23 days including pull back of casing pipe. 2nd Pilot hole completed in 16 days Both the pilot holes with 250 t rig and days. 5 drill pipe. For both pilot holes, entry casings 200 meter, 12 diameter, inserted in the first sand layer at entry side in order to maintain the drill string in position while pushing on the long drill string. Hole opening completed in 52 days with both 400 t and 250 t rig working in tandem and using 5 drill pipe pipe. Hole opening operation done in five successive reaming passes with buoyant fly cutters upto a final size of 68.
32 Fly 44 Fly 54 Fly 60 Fly 66 Fly + + + + + 28 Barrel 40 Barrel 50 Barrel 56 Barrel 62 Barrel 1st stage 2nd stage 3rd stage 4th stage 5th stage
HDD Operations
During 1st pull back operations, a twist off of the pulling assembly occurred between swivel joint and pull head, while pulling thru gravel interface at exit curve. 48 pipe already pulled approx. 500 m inside the reamed hole was removed with assistance of Taurus Air Hammer and side booms After reconditioning the product pipe and the reamed hole 2nd pull pipe, hole, back attempt performed two weeks later successfully in 72 hrs, and experiencing a maximum pull force of 320 t. HDPE Pipes inserted taken out with difficulty due to damage caused difficulty, by air-hammer oprations.
Contingency Arrangement g y g
World Record
Notwithstanding several setback faced during construction including delayed arrival of rigs, bentonite blow-out, failure during 1st pull back attempt, damage to HDPE Pipes during pull back, the entire operation could be completed and World Record thus made due to determination of Team EWPL Critical and timely decisions helped in accelerating the work execution and creating History.
Surat
LOCATION
Located at KP 1322 on Trunkline Route, south of Surat City in Gujarat Location isolated from tidal influence due to barrage present
downstream Perennial River with average water level of 3 5 m; 3.5 Bed width : 532 m; Bank width : 585 m ; North Bank 19m; South B k +18 m; Ri N h B k + 19 h Bank 18 River B d -3.1 m; HFL +19.85 m; Bed 3 1 19 85 Max Vel : 4.3 m/sec Soil investigation (d l (deep b bore h l ) and h d l holes) d hydrological d l data collected ll d Soil found to be suitable for HDD
EXECUTION
HDD work awarded, equipment mobilised and installation procedure finalised in time to commence the work. RoU issues arose at the work site, thus necessitating re-routing resulting in change in crossing location. Soil investigation redone and presence of gravel and boulders detected. HDD option ruled out due to this soil strata and alternate installation strata, methodologies became necessary g Micro-tunnelling not found feasible within the time available for implementation Trench excavation by open-cut the trench and pipeline installation by float & sink technique was only feasible option.
4
EXECUTION
Trenching in underwater with water based equipment, excavation in steep banks and State Highway crossing near the north bank posed difficulties in working out an installation methodology Also no Contractor was willing to undertake the works with a single point responsibility. Specialists engaged separately to detail the installation methodology , identify and select the equipments, and make a plan for implementation. Separate Agencies engaged for underwater trenching/backfilling & excavation on bank pipeline installation
Equipment q p
Crossing location being far from coastal area, equipment to work within the waterbody were not readily available. Pontoons were identified and mobilised to site by road trailors, so that a floating working platform could be established, over which land based dredger/excavators or dredging equipment could mounted for carrying out trench excavation works works. Custom designed, Pi-Derrick supporting structure fabricated at site, to assist in holding the swan neck during pulling operation. g gp g p
Design g
Pipeline designed in compliance with ASME B31.8 and applicable statutory p g mp E . pp y regulations. Pipe wall thickness selected for design and checked for installation conditions involving pulling of pipeline Anti-buoyancy measures viz. continuous concrete coating of 130 mm provided on the pipe Elastic bending radius of 2000 m adopted Pipeline designed t h Pi li d i d to have a minimum cover of 2 5 m f i i f 2.5 from th riverbed. the i b d
Sinking
During the pulling operation water was filled into the pipe string at two stages i.e. at 40% and 60% of pulling to partly submerge the pulled string to ensure stability against river currents and wind Once the swan neck bend reached the south bank, swan neck for the north bank welded to the end of the string and pulling continued till the time the bends reached the designated location location. Once the location reached, pulling mechanism released the floatation tanks, facilitating sinking of the pulled string to the bottom of the river bed
12
Trenching Operations
Excavation in River
Pulling Operations
String Floatation
Back filling
Sand and spoil dredged earlier were again dredged and pumped back in to the trench over the pipe for cover, using pontoon mounted excavator and sand boat dredgers. Wherever the cover found to be less, grout bags with sand and cement in 1:10 ratio placed over the backfill; transportation by barge and placement by excavator excavator. Positioning done with GPS and monitoring done with bathymetric y survey. In addition, smaller grout bags with sand cement mix were also spread over the large grout bags in post-monsoon season.
15
Summary
Despite the set-back in the intiial plan, alternative installation methodology worked out, specialist agencies engaged, equipment mobilised to undertake and complete the pipeline installation in a short time span available before onset of monsoon monsoon. Trenching took over 4 months and fabrication of strings and other paraphernal a paraphernalia took over 2 months, where as the actual pulling o er pull ng completed in 3 days time. Entire activities including bank stabilisation done prior to onset of monsoon and in time for pre-commissioning of adjoining pipeline sections
16
19
PROJECT PLANNING
Soil required for cofferdam construction was approx. 350,000 cu m (Approx. 40,000 dumper truckloads) Dewatering the cofferdam required approx. 10,000 cu m / hr pumping capacity To ensure stability, cofferdam size minimized and 4 no. of cofferdam constructed which eased the pipeline construction In order to avoid increase in water level during monsoon and consequent difficulty in constructing cofferdam, works were planned to be completed within 16 weeks time.
20
PROJECT PLANNING
Resources identified and mobilised to complete the works within 16 weeks. k Major resources required were dumpers, dewatering pumps, excavators and rock b d k breakers. k To minimise the time for transportation of soil, land in the vicinity of crossing l i leased and soil excavated f construction of cofferdam. Thi d d il d for i f ff d This methodology substantially saved the efforts and in turn time. Two d ff different agencies engaged viz. d
Cofferdam construction and dismantling Dewatering, t D t i trenching, stringing, pipeline i t ll ti and b kfilli hi t i i i li installation d backfilling
21
COFFERDAM CONSTRUCTION
Width of Cofferdam at the base kept considering the eventuality of encountering water level increasing upto 9 m. Layered polythene sheets used to minimize seepage of water through cofferdam Dewatering pumps to maintain discharge capacity of 10,000 m3/hr deployed. Once dewatered, equipment mobilised to cofferdam for trenching and rockbreaking. Dewatering pumps kept in operation continuously to take out seepage water Pre-tested pipes strung and welded in trench and equipment movement within cofferdam minimised. Due to difficulty in handling heavy concrete coated pipes, option of geotextiles bag filled with crushed stone (2.2 T/m) adopted for anti-buoyancy measure.
22
Coffer Dam #3
S u b m e r g e n c e
Dewater
Pipeline Buried
Terna River
S u b m e r g e n c e
Difficulties Encountered
Difficulties faced including partial collapse of cofferdam, water seepage, increased water level due to early onset of monsoon, etc. Despite all the difficulties, the work could be carried out and completed within the targeted time schedule of 4 months from December 07 to April 08.
24
Acknowledgement
Thanks to Reliance Management for this Presentation and h k l f h P d Reliance Construction Groups for providing valuable inputs in preparing pr p rin this pr s nt ti n presentation
Thank You