You are requessted to quote yor most compettive rates for above mentioned work in the enclosed BOQ and send
the offer back to the "Office of the JGM/Civil-IV, Tulsibagh, Srinagar, J&K, at 15.300 hours on ____/___/ 2008.
B.O.Q Rate (in Ref. D.S.R-
Item no. Description of Work Unit Amount
Quantity Rs.) 2007
1 2 3 4 5 6 7
SCHEDULE- 'A' ( CIVIL WORK )
Sub Head : 1- Earh Work
2.13.1.1,
2.1 Pipes, cables etc. not exceeding 80mm dia Rm 42.000 100.20 4,208.40
Page-65
Page 1 of 6
Sub Head : 5- Reinforced Cement Concrete Work
Providing and laying in position machine
batched, machine mixed and machine
vibrated design mix cement concrete of
specified grade for reinforced cement
concrete work including pumping of concrete
to site of laying but excluding the cost of
centering, shuttering, finishing and
5.33,
4 reinforcement including admixtures in Cum 6.000 4147.40 24,884.40
Page-93
recommended proportions (as per IS 9103)
to accelerate, retard setting of concrete,
improve workability without impairing
strength and durability as per the direction of
Engineer-in-charge. M-25 grade reinforced
cement concrete by using 410kg. of cement
per cum of concrete.
Page 2 of 6
SCHEDULE- 'C' ( STEEL )
Sub Head : 5- Reinforced Cement Concrete Work
Reinforcement for R.C.C. work including
12 straightening, cutting, bending, placing, in
position and binding all complete.
5.22.6,
12.1 Thermo mechanically treated bars. Kg 480 42.70 20,496.00
Page - 92
Sub Head : 10 - Steel Work
Steel work welded in built up
sections/framed work including cutting
13 hoisting, fixing in position and applying a
priming coat of approved steel primer using
structural steel etc.as required.
In gratings, frames, guard bar, ladders, 10.25.2,
13.1 Kg 2400.000 51.20 122,880.00
railings, brackets, gates & similar works. Page - 166
SUB-TOTAL FOR SCHEDULE -C 143,376.00 52