Beruflich Dokumente
Kultur Dokumente
BUREAU OF MINES
David S. Brown, Acting Director
CONTENTS
Page Page
Abstract. .............. . . . 1 Preproductíon overburden removal . . .. ........ 24
Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 Bulldozers . . . " ...... . . . . . . .. . 24
Acknowledgments. . . .. . ... 2 Draglines . 25
Front.end loaders . 26
Section I.-Placer Mine Design
Rear-dump trucks. 27
Scrapers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Exploration . . . .. ............................ 3
Mine equipment... ..... . . 29
Panning ............. 4 Backhoes . . . .' ...... 29
Churn drillng. . . 4 Bulldozers .. . ., ...... 30
Bucket driling. . . .. . . .. . . . 4 Draglines . . . . . . . _ . . . . . . . . . . . . . . . . . . 31
Front.end loaders . . . . . . . . . . . . . . . . . . . . . . . . . . 32
Rotary driling. .. . .' ...... ........ ... 5
Rear.dump trucks ..... 33
Trenching. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Seismic surveys . . . . .. .. .. 5 Scrapers . . . . . 34
Mining........ 5
Backhoes (hydrau,lic excavators) . . 6
Processing equipment
Conveyors . . . . . . . . . . . . . .. . .....
35
35
Bulldozers. .. . " . ., . .... . 6
Draglines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Feed hoppers .. . . . . . . . . . . . . . _ . . . . . . . . . . . . . .
Jig concentrators . . _
36
37
Dredges. . . . . . . . . . . . . . 6
Front-end loaders. . .. . . .. . . . 7
Sluices . . . . .. ......
Spiral concentrators . . . .. . . .. .
38
39
Table concentrators ... . . . . . . . . . . . . . . . . . . . . .
Rear-dump trucks . 7 Trommels.. . .. .. 41
40
Scrapers .. . . .. ............................ 7
Vibrating screens 42
Processing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Supplemental . 43
Conveyors. . . . . . . . . . . . .... 8 Buíldings . 43
Feed hoppers . . . . . . .. 8 Employee housing ......................... 44
Jig concentrators. . . . . .. .. 8 Generators. . . . . . 45
Sluices. . .... . ...... ................... 8
Spiral concentrators ......................... 9
Pumps. .... 46
Table concentrator . 9 Settlng ponds. . 47
Trommels . 10
Vibrating screens 9 Operating costs .. .... .. .. . .. .. .. . 48
Overburden removal . . . . . . . . . . . . . . . . . . . . . . . . . 48
48
Sample mil design . 10 Bulldozers . . . . . . . . . . . . .. ................
Draglines .. . .' .... 49
Supplemental systems . . . . . . . . . . . . . . . . . . . . . . . .. 13
Buildings ............ ... .. . 13 Front-end loaders . . . . .. . .. 50
Camp facilties. . . .. . . .. . 13 Rear.dump trucks.. ............... .......
Scrapers. ................................
51
52
General services and lost time.. . 13
Pumps. . . .. .. .14
Generators . . . . . . . . . . . . . . . . . . . . 13
Settling ponds. 14
Mining .......
Backhoes . . . ., . ....
Bulldozers. .... .. . .' . .... . ..... 54
53
53
Draglines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
Environment. .... 14 Front.end loaders 56
Cost estimation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 15
Rear-dump trucks . .. . . . .. . . 57
Cost equations . . . . . . . . . . . . . . . . . 15
Cost date adjustments. 15
Site adjusment factors 16
Scrapers. . .. . .. ........... 58
Processing. ... .. ............... ....... 59
Conveyors . . . . . . . . . . . . . . . 59
Labor rates. .. . . . . . . .. ................. 17
Financial analysis ............................ 18
Feed hoppers.. . .,. 60
Bibliography . . . . . . . . . . . . . . . . . . .. ............ 18
Jig concentrators . . 61
Sluices. . 62
Spiral concentrators. . . . . . . . . . . . . . . . . . . . . 63
Secion 2.-Cost Estimation Table concentrators .. 64
Tailings removal. . . 65
Capital and operating cost categories . 19 Bulldozers .
Capital costs. . . .. . . .. . 20
Exploration. . . .. . .. . . .... 20
Draglines ...........................
65
66
Panning . .... .......................... 21
Churn drlIng. . . . . . .. .... 21
Front.end loaders. . . . . .
Rear-dump trucks . .
Scrapers .
........68 67
69
Bucket driling
Trenching 21
. . . 21 Trommels . .. .......................
Vibrating screens . . . . . . . . .
70
71
General reconnaissance. ............... 21 Supplemental . '" '" . . 72
Camp costs. . . .. . . ... ..... 21 Employee housing .... 72
Seismic sureying (refraction) 21
Rotar driling .. . . .. . 21
Helicopter rental . .... . ...... ...... 21
Generators. " .. .......................
Lost time and general services . . .
Pumps . . . . . . .
73
74
75
Development .......... 22 Bibliography .
Access roads 23
Clearing. 22 Appendix.-Example of cost estimate.
78
79
ii
ILLUSTRATIONS
Page
1. Sample flow sheet, sluice mil.. . .... . .. ................ . ., . . . 10
2. Sample flow sheet, jig inil . . . . . . . . .. ............ . 11
3. Sample flow sheet. table mil .... . . . . . . . . . . . . . . . . . . . . . . . 12
4. Exploration cost summary form ..... .......... . . . '" ....... . . . . . . . . . . . . .. 21
5. Capital cost summar form . . . . . . . . . . . . . . . . . . . . . . . . . . . .. .... . 76
6. Oprating cost summary form.. .. .... . . . . . . . . . . . . . . . . . . . . . . . . . 77
A.I. Sample flow sheet.. .... . .. .. ......... .. . . . . . . . . . . . . . . . .. .. . 80
A-2. Capital cost summary form completed for example estimation . . ..................... ... 87
A-3. Operating cost summar form completed for example estimation . . ....... 94
TABLES
-
1. Sample material balance, sluice mil . . . . . . . . . . . . . . . . . .. . . .. . 10
2. Sample material balance. jig mil. .... .............................. 10
3. Sample material balance, table mil. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . 10
4. Cost date indexes .. .... . . . . " . .., . . . . . . . . . . . 17
.
UNIT OF MEASURE ABBREVIA TJONS USED IN THIS REPORT
Bey
dJa
bank cubic yard
day per year
II LCy/h loose cubic yard per
hour
ft foot ¡.m micrometer
ft' square foot
ft'/yd3 square foot per min minute
cubic yard minl minute per hour
ft/h foot per hour
gpm gallon per minute 5t short ton
h hour stl short ton per hour
h1shift hour pel' shift tr oz troy ounce
hp horsepower tr ozlyd3 troy ounce per cubic
in inch yard
kW kilowatt wt% weight percent
kW/yd3 kilowatt per cubic ydl yard per hour
yard yd3 cubic yard
IblLCY pound per loose cubic yd3/d cubic yard per day
yard yd3/fP cubic yard per
lb/yd pound per yard square foot
Ib/yd3 pound per cubic yard yd3/h cubic yard per hour
LCY loose cubic yard yr year
LCY/a loose cubic yard per
year
COST ESTIMATION HANDBOOK FOR SMALL PLACER MINES
.
By Scott A. Stebbins'
II -
ABSTRACT
This Bureau of Mines publication presents a method for estimating capital and operating costs
associated with the exploration, mining, and processing of placer deposits. To ensure represent-
ative cost estimates, operational parameters for place ring equipment and bask principles of placer
mining techniques are detailed. _ _
i Mining engineer. Western Field Operations Center. BUfQU or Mines. Spokane. W A.
2
INTRODUCTION
In 1974, the Bureau of Mines began a systematic assess- mining techniques. If the reader is unfamiliar with this
ment of U.S. mineral supplies under its Minerals Avail. form of mining, section 1 should be thoroughly understood
ability Program (MAP). To aid in this program, a technique prior to estimating costs.
was developed to estimate capital and operating costs Section 2 contains cost equations that enable the user
associated with various mining methods. This technique, to estimate capital and operating costs of specific placer
developed under a Bureau contract by ST Engineers, techniques. Cost equations are designed to handle the wide
Inc., was completed in 1975, then updated in 1983. During variety of conditions commonly found in placer deposits.
the course of the update, it was noted that few provisions This allows the reader to tailor estimates to the
were made for estimating the costs of smalI-scale mining characteristics of a particular deposit, which ensures
and miling methods typicalIy associated with placer min. representative costs. Although based primarily on gold
ing. The popularity and widespread use of placer mining placer operations, cot equations ar valid for any other com-
methods indicated that a cost estimating system for placer modity found in deposits of unconsolidated materiaL. Equa.
mining would be of value to prosptors, miners, investors, tions are geard to operations handling between 20 and 500
and government evaluators. Ley /h of material (pay gravel plus overburden). Estimated
This report has been written to aid those involved with cost are representative of operations in the western United
placer mining in the estimation of costs to reover valuable States and Alaska, and are based on a cost date of January
minerals from placer depoits. It relies on the principle that 1985.
cost estimates wìl be representative only if calculated for The appendi provides an example of placer mine design
technically feasible mining operations. Because the design and cost estimation using the information contained in this
of such an operation can be diffcult, provisions have ben report.
made to assist the user in achieving this goal. This report is not intended to be an exhaustive discus.
Section 1 of the report describes the processes involved sion of placer mining. Many detailed texts have been writ.
in placering, and may be used to aid in designing a viable ten on this process, anyone of which wil assist the reader
. --
mine. Operational parameters for equipment commonly in method design. A number of these are listed in the
used in placer exploration, mining, and processing are bibliographies accompanying sections 1 and 2.
discussed, as well as basic principles of successful placer
ACKNOWLEDGMENTS
A special debt is owed to the late George D. Gale, of the ideas and fact it contains, are the product of his
metallurgist, Bureau of Mines. This handbook, and many ingenuity.
3
EXPLORATION
It can be safely stated that far more people seek placer Time, effort, and money spent on resource definition
deposits than actually mine them. Exploration for placer vary greatly from one deposit to the next. Some miners are
gold can be enjoyable work and has achieved a recreational satisfed with the degr of certnty obtainable with shovel,
status in the western United States. For the serious miner, pan, and physical labor. Others, wishing more security,
however, exploration is only the initial phas of a complete systematically trench or dril the deposit and process
mining operation. Consequently, it incus a cost that must samples using some sort of mechanical concentrator. Stil
be repaid by the recovery of valuable minerals. others, hoping for greater asurance, follow up driling or
. For the purposes of this report, exploration is divided trenching by bulk sampling using machinery intended for
into two phases. The firs phase involves locating the mining. These samples are then proessed in a scaled-down
deposit, and the seond consists of defining enough of a version of the proposed milL. The extent of effort spent on
resoure to either justify development or to eliminate the deposit definition is related to
deposit from further consideration. 1. Degree of certainty desired.
Costs for the first phase of exploration are diffcult to 2. Availabilty of capitaL.
attribute to anyone deposit. This type of exploration is 3. Experience of the operator.
typically regional in nature and deposit specifics are 4. Historical continuity of similar or local deposits.
rarely considered. For cost estimation purpses, expenses It is intuitively obvious that the degree of certainty of
assiated with a speific depoit are the main concern. Only success is related to the extnt of exploration undertaken,
costs directly related to the definition of that particular and it is desirable to delineate the deposit as extensively
deposit wil be calculated. Accordingly, this discussion deals as is practical prior to production. In many cases, however,
mainly with the deposit definition phase of exploration. lack of exploration capital and the need for cash.flow limit
4
the exploration phase, and mining commences on the waste during production. Skíled use of a gold pan d:ir~ng
limited information at hand. Goals of a thorough explora- the mining sequence can make or break the small mining
tion program include determination of operation.
1. Deposit volume.
2. Deposit and overburden geometry.
3. Deposit grade.
CHURN DRILLING
4. Distribution of valuable minerals within the
deposit. Methods of driling placer deposits are quite varied, but
5. Geological and physical characteristics of the the most common technique is churn drllng. Tyically, the
valuable minerals.
churn dril uses percussion to drive casing down through
6. Geological and physical characteristics of waste the material being sampled (in some instances, casing is
materiaL. not used). After a length of casing is driven, the contents
7. Location, geology, and physical nature of the are recovered (bailed), another length of casing is added,
bedrk. and the process is repeated. Depths are usually restrictd
8. Water availabilty. to less than 150 ft, and hole diameters range from 4 to 10 in.
9. Environmental concerns. One advantage of this method is that sample process-
Much of the information needed to estimate costs of ing keeps pace with drllng, allowing good control of dril.
developing and operating a placer mine is gathered during hole depth and instantaneous logging. A churn dril is
deposit exploration. Consequently, costs estimted aftr ex-
generally operated by two people; the drller operates the
ploration are much more precise than estiniates made prior dril, bails the sample. and keeps track of the depth of each
to exploration. run; the panner estimates the volume ofthe samples, pans
In section 2 of this report, two methods are presented them as they are recovered, and logs the hole.
for estimating exploration costs. With the first, a cost can Dríling rates average about 2 ft but can reach as
be calculated by simply estimating the total resourc of the much as 4 ft/ll"n clay, soil, sand, pebbles and soft bedrock.
deposit. This method is based on total exploration expen- The machine is suitable for driling through cemented
ditures for several active placer operations, but is not con-
gravels and permafrost, although productivity wil
sidered as precise as the seond method. diminish. Penetration is drastically reduced in ground con-
The second method requires that the evaluator design taining boulders and in competent or hard bedrock.
an exploration plan. This plan should include the typ and Samples recovered from churn dril casings are often
extent of each exploration method required, for example subject to volume changes caused by compaction or expan-
1. General reconnaissance, 5 days with a two-person sion of material within the casing. Sample volume changes
crew. can also be caused by compaction around the bit forCing
2. Seismic sureying, 10,000 linear ft. material out into the surounding formation, and by
3. Churn driling, 4,000 ft. material "run-in" due to high deposit water content. One
4. Trenching, 1,000 yd"
or more of these conditions may be encountered in anyone
5. Samples panned, 2,000. deposit, requiring the application of volume corrctions.
6. Camp facilties, four people for 20 days. This task is often diffcult and requires the experience of
To aid ìn developing this plan, some techniques com- a qualified driler or engineer.
monly employed for sampling and subsurace testing of
placer deposits are discussed in the following paragraphs.
These include panning, churn driling. bucket drillng,
rotary driling, trenching, and seismic sureying. BUCKET DRILLING
Bucket drllng, although not as popular as churn dril-
PANNING ing, has important applications in placer deposit evalua-
tion. Under ideal conditions, th tehnique is relatively fat
One of the most versatile and common sampling devices and provides large samples. In this systm, a standard
in placer mining is the gold pan. It is used as a recon- rotar drll is equippe with a special "bucket" bit con-
naissance tool, a sampling tool, and a concentrate refining sisting of a 30- to 48-in-diam cylinder, 3 to 4 ft long. The
tool. With a gold pan, the prospector has the abilty to, in bit is drven down through the deposit, using the rotational
effec, conduct his or her asay work on-site with immediate force of the dril, unti the cylinder is full. As the bit is
results. Although acuracy may be poor, the prospetor can withdrawn, a mechanism closes off the bottom of the bit
determine in the field if gold is present and in roughly what retaining the sample. The process is then repeated unti the
amounts. desired depth is reached.
The gold pan uses gravity separation to concentrate Bucket drils perform best in sands, soils, pebbles, and
heavy minerals. Pans come in a variety of sizes, ranging clays. Prgress is slow, and sometimes impoible, in ground
in diameter from 12 to 16 in. An experienced panner can containing boulders, cemented gravel layers, and bedrock.
concentrate approximately 0.5 yd" gravel daily. Because of The size of the bit tends to disprs drllng force over a large
this limited capacity, panning can be costly when large area, thereby reducing the effective penetration rate. For
volumes must be processed; however, low capital expense, this reason the bucket dril quickly becomes ineffcient in
ease of use, versatilty, and portabilty make the gold pan hard or compact materiaL. Problems are also encountered
invaluable. in saturate ground, where water often washes away a por.
Immediate feedback when exploring or mining is a tion of the sample as the bit is withdrawn.
prime advantage of the gold pan. This one feature is ex- Bucket driling extracts a much larger sample than
tremely important for eliminating areas of low potential other driling methods. Consequently, the infuence of the
during exploration, and for separating pay gravel from bit on compaction and expansion of material is reduced.
5
ROTARY DRILLING of the trench. The disadvantage of this method is the i.n-
abilty to determine the horizon of valuable mineral con-
This type of dril, commonly used for driling large- centration. With either method, large.volume samples are
diameter blastholes in surface mining, has found limited available at a low cost.
use in placer exploration. The only way to obtain a sample In sampling situations, backhoes can excavate from 20
with this machine is to analyze dril cuttings. Because the to 45 LCY /h. Sample control is typically good with little
method does not provide a core, it is diffcult to associate volume distortion or material dilution under properly con-
a volume with the recovered material, and it is hard to trolIed circumstances. Backhoes are relatively inexpensive,
estimate the depth horizon of the sample. easy to operate, versatile, and readily available. The
Rotary drils are useful in that they provide a fast, in- machine can dig a varety of formations, and digging depths
expensive way to determine the depth of bedrk. Holes pro- as much 30 ft below the machine platforms are possible.
vided by rotary drils range from 6 to 15 in. in diameter In saturated ground, keeping the trench open for sampling
and reach any depth required for placer mining. Virtually is normally a major problem.
any material can be driled, and penetration rates are far
superior to any other placer drillng method. Regardless of
the steps taken, however, it is diffcult to accurately SEISMIC SURVEYS
estimate deposit grade with samples obtained from rotary
drillng. In placer mining, bedrock depth plays a key role.
Although not always the case, gold tends to concentrate
near, on, or even in bedrock in a majority of placer deposits.
Consequently, it is imperative to understand the nature of
TRENCHING the bedrock and to design a mining method and selec equip-
ment based on its depth.
In fairly shallow, dr deposits, trenching with a backhoe One method of determining bedrock depth is seismic
is an extremely effecive sampling technique. The procedur refraction or reflection. In simple terms, the technique in-
involves digging a trench to bedrock, then obtaining volves bouncing sound energy off the relatively resistant
material from a channel taken down one side of the trench. bedrk to determine its depth. The method is much cheaper
This material is then measured and analyzed, providing a than driling a series of holes and, if bedrock proves to be
grade estimate. Another method relates an assay analysis too deep for practical mining, may prevent unnecessary
of aU the material ~xtracted by the backhoe to the volume driling.
MINING
Next, a method for excavation and and transportation equipment selection. Countless combinations of equipment
of material contained in the deposit is needed. Mining have been tried in attempts to effectively mine placer
methods are typically dictated by several basic factors. deposits. Equipment typically used in the western United
Deposit depth, size, and topography are of primary impor- States includes
tance. The geQlagic nature or the deposit and accompany. 1. Backhoes (hydraulic excavators).
ing overburden both play key roles. Types of equipment ob- 2. Bulldozers.
tainable locaUy, sources of power, and the availabilty of 3. Draglines.
water are all important factors. In some cases, operators 4. Dredges.
may simply feel more confdent using one method of extrac- 5. Front-end loaders.
tion as opposed to another, even if local conditions are 6. Rear-dump trucks.
unfavorable. 7. Scrapers.
In any event, the mining method should be designed Each type of equipment is suited to a particular task.
with one fundamental goal in mind: To extract pay gravel In sòme instances, only one piece of equipment may be
from the depoit and move it to the mil at the lowest p08si- used to remove overburden, excavate and haul pay gravel,
ble overall cost. Several basic concepts should be designed and place mil tailngs and oversize (i.e., bulldozers). More
into the mining method to keep costs low. These include often, several different types of equipment are uti1zed to
1. Haul only pay gravel to the mil. Eliminate hauling take advantage of their specific attributes. l
and processing unprofitable materiaL. When selecting placer mining equipment, the evaluator
2. Handle both overburden and pay gravel as few times must consider two important concepts. First, the volume
as possible. Do not pile overburden or tails on ground that of earth in place is less than the volume of the same earth
is scheduled for excavation. afer excavation. This point is crtical in cost estimation and
3. Locate the mil at a site that minimizes average pay must be remembered. Because placer gravel is relatively
gravel haul distance. In most instances, it is cheaper to light, placer mining equipment is typically limited by
pump water than to haul gravel. volume capacity, not weight capacity. For this reason, mine
4. Do not mine gravel that is not profitable even if it con- equipment capacities and associated cost equations in this
tains gold. Money is lost for every yard of gravel mined if report are based on volume after accounting for material
that gravel does not contain enough value to pay for the swell-in loose cubic yards. Resoure estimates are typically
cost of mining and processing. stated in bank cubic yards-the volume before accounting
As can be seen, common sense plays a large role in the for materi.al swell. This has a signifcant meaning to the
proper design of a placer mine. The same holds true for mine design of a placer mining system. To mine a 500,OOO.BCY
6
depoit, equipment wil have to move 570,000 LCY of gravel bedrock cleanup, overburden and pay gravel transportation,
if the material swelIs 14% (typical for gravel deposits). road construction, tailngs placement, and a variety of
Although the total weight of material moved is constant, minor functions. The bulldozer is the only device capable
equipment wil have to move a larger volume of gravel than of handling all tasks required for placer mining in a prac-
the in-place estimate indicates. As a result, the mining tical manner and must be considered if capital is scarce.
system should be designed around the total loo cubic yars Although bulldozers can handle all placer mining fUnc-
of gravel to be moved, not the total bank cubic yards. tions, they are not necessarily the most effcient machine
Second, mine equipment equations in seion 2 of this for anyone task. With its ripping capacity, the bulIdozer
report are based on the maximum amount of overburden, is capable of cleaning up bedrock; however, the backhoe is
pay gravel, and mil tails moved daily. Although average much more selective and effcient. The bulldozer can, and
volume handled might be less, equipment must be selected often is, used to transport gravel, but in most cases trucks,
to handle the maximum load. scrapers, and front-end loaders can each do the job cheaper
To aid in mine planning, and to obtain reasonable if haul distances are more than a few hundred feet. In ad.
capital and operating mine costs, the following information dition, bulldozers are not well suited to more large volumes
wil typically be required: of gravel or to dig to excessive depths. In both instances,
draglines exhibit superior petfomiance.
1. Total length and average width of haul and access A major advantage of the bulldozer is its ability to ex-
roads. cavate, transport, and load the mil all in one cycle,
2. Total surface area of deposit. eliminating the need for expensive rehandlìng. Dozer
3. Nature of ground cover. capacities for excavating and hauling range from 19 LCY!h
4. Topography of deposit area. for a 65-hp machine up to 497.5 LCYIh for a 700-hp dozer
5. Total loose cubic yard of overburden, and maximum (based on a 300.ft haul distance). Capacity is dependent
amount of overburden handled daily. upon ripping requirements, operator abílty, cutting
6. Total loose cubic yards of pay gravel, and maximum distance; haul distance, digging diffculty, and haul
amount of pay gravel handled daily. gradient.
7. Total cubic yards of mil tails handled daily. Dozers are best suited for situations where deposit and
8. Type of equipment desired. overburden thicknesses ar not excessive, few large obstruc-
9. Average haul distances and gradients for overburden, tions are present, and haul distances average less than
pay gravel, and tailngs. 500 f1.
\
The following is a discussion of the principal types of
equipment used in excavating and hauling overburden, ORAGLINES
placer gravel, and mil oversize and tails, and may be used
to aid in mine design and equipment selection. Draglines are well suited for excavating large quantities
of overburden, gravel, and waste. Although their material
transporting abilty is limited, draglines with booms up to
BACKHOES (HYDRAULIC EXCA V A TORS) 70 ft long are capable of acting as the sole piece of mining
equipment. As with the bulldozer, draglines can excavate
The backhoe is one of the most effcient types of equip. overburden and pay gravel, load the mil, and remove tail-
ment for bedrock cleanup. It is most often used for the ex- ings; however, draglines are relatively ineffcient at bedrock
traction of pay gravel, but can also be used for excavation cleanup, and do not handle diffcult digging as well as
of overburden. The machine has almost no capacity for backhoes or dozers.
transportation of material and for that reason is used in Depths of over 200 ft are obtainable with this type of
conjunction with either frnt-end loaders, trucks, or in some machine, and when used in conjunction with front-end
cases, bulldozers. Depending on bucket selection, the loaders or rear-dump trucks, large.capacity operations are
machine can handle a varety of ground conditions including possible. Draglines handle from 28 LCYIh for a 84-hp unit
clays, porly sorted gravels, tree rots, and vegetation. Dig- to 264 LCY /b for a 540-hp machine. Capacity is dependent
ging depths of over 30 ft are obtainable with certin upon bucket effciency, swing angle, and operator abilty.
backhoes, but production capabilty decreases rapidly as Draglines are ideal for overburden removal and for
maximum digging depth is approached. large, deep deposits where bedrock cleanup is not criticaL.
Backhoes typically used in the westrn United States They must, however, be matched with the right equipment
are capable of excavating frm 95 to 475 LCYIh. Sizes range (Le., portable mils or gravel transportation machinery).
from 105-hp machines with O.5-yd' buckets to 325.hp units
with 3.75-yd' buckets. Capacity is contingent upon digging
diffculty, operator abilty, swing angle, digging depth, and
obstructions. DREDGES
The backhoe is ideal for situations where bedrock
cleanup is critical, obstructions exist in the mining area, Cost estimation equations for dredging are not Ín-
and other means of transporting gravel are available. eluded in this report. Dredges, except for recreational units
and small machines used in active channels, are designed
for high~apacity excavation of specifc placer envionments.
BULLDOZERS The machines are best utilzed in large volume, relatively
flat-lying deposits that occur below water leveL. Because of
The bulldozer represents an extremely versatie tool in large capital investment requirements and a scai-ity of
placer deposit extraction, and is the most popular. It can ground suitable for large-scale dredging, they are Uncom-
be used for overburden removal, pay gravel excavation, mon in the western United States.
7
Operating costs for large-capacity dredges average ap- purposes: Material movement and mil feed. They have
proximately $0.70/yd'. Purchase and refurbishing costs are relatively low capital costs and require little maintenance
-
often more than $3 milion, and can run over $10 milion. compared to other placer equipment. Trucks do need fairly
In large.volume situations, dredges must be considered. good road surfaces and require careful matching with
Because suitable applications are rare, however, they have loading equipment to achieve acceptable effciency.
not been included in this report. Capacities for units at small placer operations range
from 3 to 47.5 yd3. Trucks are most productive over haul
distances of 1,000 to 10,000 ft and can travel faster than
FRONT-END LOADERS equivalent-sized scrapers or front-end loaders. Production
capacities range from 32.3 LCY ih for a 3-yd' truck to 444.8
This versatie machine is capable of many functions. In LCY ih for a 47.5-yd3 truck (based on a 2,500-ft haul
the western United States, its primary use is hauling distance). Capacity is contingent upon loader capacity, haul
previously excavated gravels, and the subsequent loading distance, and haul gradient.
of the mil. Although front-end loaders are not the most ef- Trucks are suited to operations where a fixed mil is
ficient hauling unit, their self-loading abilty provides many situated more than 0.5 mile from the minesite. They are
advantages. One is the elimination of the need to match equally effective hauling pay gravel, overburden, or mil
the excavation machine with the haul unit_ With a front- tailings and oversiz, but must be accompanied by a method
end loader, the excavator can operate at its own pace and of material loading.
simply stockpile materiaL. The loader then feeds from the
stokpile and transports gravel to the mil feed hopper. This
removes the problem of matching excavator output with SCRAPERS
truck cycles or mil feed rates.
The machine is also capable of removing and transport- These machines are noted for their high productivity
ing mil oversize and tailngs; however, front.end loaders when used tó transport overburden, pay gravel, and tail-
are not particularly adept at excavating consolidated ings. As with front-end loaders, scrapers are self-loading,
materiaL. If overburden or gravel are at all compacted, a although bulldozers or other scrapers often assist. They are
backhoe or bulldozer should be used for a primary capable of much higher speeds and greater capacity than
excavation. front-end loaders, and exhibit haulage characteristics
Front-end loaders are capable of hauling from 24 LCY/h similar to rear-dump trucks_ Scrapers, however, are more
for a 65-hp, 1.yd' ~achine to 348 LCY/h for a 690-hp, 12-yd' costly to purchase and maintain.
machine (based on a 500.ft haul distance). Capacity varies Scrapers are limited in their abilty to excavate con-
with haul length, haul gradient, operator abilty, bucket solidated or unsorted materiaL. A bulldozer equipped with
effciency, and type of loader. a ripper must precede them in overburden or gravel that
Front-end loaders are best utilzed as haul units over is not easily drftd. Ifboulders are present, they must either
distances ofless than 1,000 ft. Their verstilty makes them be blasted or removed by other means. The nature of the
useful for pay gravel and overburden transportation, mil scraper.dumping mechanism renders them unsuitable for
oversize and tailngs removal, and general site cleanup. direct mil feed. When used to haul pay gravel, scrapers will
typically unload near the mil, and bulldozers wil then be
used to feed materiaL.
REAR-DUMP TRUCKS Capacities range from 201 LCY/h for a 330-hp machine
to 420 LCY/h for a 550-hp machine (based on a 1,OOO-ft haul
Trcks represent the least expensive method of material distance). Capacity is contingent upon haul distance and
movement over long distances; however, since other gradient, and loading procedure.
machinery is required for loading, total gravel transport- In placer mining, scrapers are best utilzed for transpor-
tion expenses over short distances may be higher than for tation of unconsolidated overburden or mil tailngs over
front-end loaders or scrapers. Trucks generally serve two distances ranging from 500 to 5,000 ft.
PROCESSING
Oftn the most diffcult part of placer mining is achiev- combinations of natural phenomenon such as gràvity, tur-
ing the desired recovery of valuable minerals from mine- bulent fluid flow, and differences in mineral density. Con-
run graveL. The design of a successful mil is a specialized sequently, it would seem practical to utilize these conditions
science and often proves diffcult even for those actively in- to furher concentrate heavy minerals. This form of mineraI
volved in placer mining. Great care must be taken to en- recovery is referred to as gravity separation and is the basis
sur the recovery of a high percentage of contained valuable for most placer mils.
minerals. Obviously, the profitabilty of an operation is Gravity processes must consider both particle specific
directly related to the percentage of contained valuable gravity and size for effective separation. Differences in
minerals recovered by the milL. speific gravity alone wil not distinguish varous materials.
Although mil design can be diffcult, the basic premise It is the differences in weights in a common medium that
used in heavy mineral recovery is quite logicaL. In placer creates effcient separation. Consequently, a paricle of high
deposits, high-density minerals have been concentrated by speific gravity and small size may react the same as a large
8
particle with low specific gravity in a given fluid. If grav- feeder to smooth out material flow surges introduced by
ity separation is to be effective, size control must be im. loading devices with fixed bucket sizes (front-end loaders,
plemented to take advantage of differences in particle rear-dump trucks, ete.). Hoppers often contain a grzzly in
specific gravity. order to reject large oversize materiaL. The feeder, typically
Equipment used for gravity separation ranges from gold a vibrating tray located under the hopper, transfers gravel
pans to prebuilt self-contained placer plants. In general, the at an even rate to the circuit. Although the hopper-feeder
most widely employed devices in the western United States combination may appear to be a minor piece of equipment,
are a steady flow of material through the mil is very impor-
i. Jig concentrators. t:mt for effective gravity separation.
2. Sluices. Hopper capacity and feeder capacity are two separate
3. Spiral concentrators. items. Generally, hoppers are designed to hold enough
4. Table concentrators. material to provide a steady flow of gravel despite surges
5. Trommels. inherent in mining cycles. Feeders are set to provide the
6. Vibrating screens. appropriate flow rate to the milL. So even though a hopper
Of these devices, trommels and vibrating screens are may have a 100-yd3 capacity, the feeder might provide
used for particle size classification, and the remainder are material at 20 yd3/h.
form of gravity concentrators. In addition, fee hoppers and Feeders are not always used in placer mi1s. When they
conveyors are needed for surge capacity and material are not used, feed rate is regulated by the size of the open-
transporttion. These items, which are commonly neglected ing in the bottom ofthe hopper. The cost estimation curves
in plant costing, must be carefully selected to ensure prop- in this report calculate hopper-feeder costs based on feeder
er plant operation.
Although the complete design of a placer recovery plant
cannot be thoroughly covered in the space available here,
three sample flowsheets ilustrating basic placer mil design
are included at the end of this section on processing. Along
with a flow sheet detailng equipment type, size, and capa.
.
capacity, which typically equals miU capacity. Factors are
provided for situations where feeders are not used.
JIG CONCENTRATORS
city required for the mil, the following wil be needed to Jigs are gravity separation devices that use hìndered
obtain an accurate cost estimate using this report: settling to extract heavy minerals frm feed materiaL. They
typically consist of shallow, perforated trays through which
1. Maximum feed capacity of the mil. water pulsates in a vertical motion. In most instances, a
2. A material balance ilustrating feed, concentrate, and bed made up of sized shot, steel punchings, or other
tailngs rates. "ragging" material is placed over the perforations to pro-
3. The purse of each gravity separation device (rougher, mote directional currnts required for separation. Sluried
cleaner, scavenger, etc.). feed flowing over the bed is subjected to the vertical pulsa-
4. Method of removal and transportation of mil tails and tions of water, which tend to keep lighter partcles in
oversize. suspension while drawing down heavier consituents. These
The following discussion details equipment used in heavy minerals are either drawn through the bed and
discharged from spigots under the jig or, if too large to pass
gravity separation and may prove useful in mil design. through the perforations, are drawn off near the end of the
machine. Lighter paricles continue across and over the end
Sluice design can be quite complex but usually is a mat- yd3/h roughing down to 0.3 to 0-5 yd3fh cleaning per start.
ter of trial and error. Several basic principles typically Feed slurry density is typically less than 25% solids by
apply. Width is determined by the maximum and minimum weight, necessitating the use of larger pumps than needed
volume of water available, the size and quantity of over- for jigs or tables.
size feed that must be transported, and the slope. Length
depends principally on the character of the gold. Coarse gold
and granular gold settle quickly and are easily held in the
riffes, while fine gold and porous gold may be canied some TABLE CONCENTRATORS
distance by the current. Velocity of the water is controlled
primarly by the slope. In general, the sluice should be con- Concentrating tables (shaking tables) are one of the
structed ahd installed so that water flowing through the oldest methods of mechanical gravity concentration.
box will transport oversized material and prevent sand from Although capable of handling a variety of feed types and
packing the riffes. sizes, their optimum use is wet gravity cleaning of fine con-
If the sunace of the water flowing through the sluice centrates ranging from 15 ¡.m to 1/8 in. The unit co~sists
is smooth, the bottom of the sluice is probably packed with of a large, flat, smooth table, slightly tilted, with riffes at.
sand, allowing little gold to be saved. The desired condi- tached to the surace. A longitudinal reciprocating motion
tion occurs when waves form on the surace of the water is introduced to the deck by means of a vibrating mechanism
flowing through the sluice, and these waves, along with the or an eccentric head action.
wave.forming ridges of material on the bottom of the sluice, Although limited in capacity, tables have the advantage
migrate upstream. This indicates an eddying or boilng ac- of being easily adjustable by regulating the quantity of wash
water and altering the tilt angle of the deck. The results
tivity on the lee side of the ridges, which maximizes gold
recovery and tailngs transport. Consequently, the sluice
of these changes are immediately observable on the table.
attains maximum effciency when rime overloading is With the addition of splitters, effcient control of high-grade
concentrate recovery, middling recovery, and taílngs pro-
incipient.
Sluices are generally considered to be high-capacity
duction is possible.
units, with a 12.in-wide sluice oox capable of handling 15 Solids content for table feeds averages approximately
yd3/h if si.cient water is available. A 24-in-wide sluice can 25% by weight. Stroke length and speed are adjusted ac.
handle up to 40 yd3/h, and 48-in-wide sluices have reportedly cording to feed. Long strokes at slow speeds are used for
processed up to 200 yd3/h. Of course, a sluice will handle coarse feeds; fine material responds better to short strokes
at higher speeds. A reciprocating speed of 280 to 380
as much gravel ds the operator wants to push through it.
However, to ensure reasonable recovery, capacity is limited strokes/min wil handle most feeds. Table capacities range
by box width and slope, water availahìlty, and feed from 0.05 to 8 yd"Jh and depend on desired product as well
characteristics. as equipment size.
Feed slur densities are highly variable and range from
1 % to 35% solids by weight, averaging 10%. Water use can
be reduced significantly if the larger of the oversize is
eliminated from the feed. Sluices require no power to TROMMElS
operate unless a pump is needed to transport water or
slurry. One disadvantage of the sluice is the necessity to This machine is the most common size classification
halt operations in order to recover concentrates.
device used in gold placer mils and is well suited for this
task if properly designed. Trommels consist of a long
rotating cylinder that is typically divided into two sections.
In the first section, lengths of angle iron or similar
SPIRAL CONCENTRATORS material are fastened to the inside of the rotating drum.
These act as lifters to carr feed up the side of the rotating
Spirals are used infrequently in the western United cylinder. As material reaches the top of the rotation, it falls
States but may be applicable for certain types of feed. These the cylinder and.breaks upon impact.
back to the bottom of
gravity separation devices exhibit several desirable This action, along with water introduced under pressure,
features. They accept sized slurry directly, and require no serves to break up compacted soils and èìays, and liberate
energy to operate other than perhaps pumps for material valuable minerals.
feed. Pumps can be excluded if gravity feed is used. Selec- The second section consists of perforations in the
tivity is high because of adjustable splitters within the cylinder walls positioned along the length of the drum.
slurr flow. Spirals can be used to produce a bulk concen- Typically, perforation size wil graduate from 1/8 in, to 3/16
trate, scavenge valuable minerals from tailngs, or in some in, to 1/4 in as the feed progresses down the trommel.
instances, recover a finished concentrate. The abilty to pro- Sized fractions are drawn directly below the section of
duce a finished concentrate wil be limited to feeds that con- the trommel in which they are separated. They generally
tain a' higher concentration of desired product than typically flow to either a vibrating screen to be sized further or to
found in most gold placer feeds. a gravity separation device. Oversize material is discharged
To save space, two or three spiral starts are constructed out the end of the trommel as waste.
around a common vertical pipe. This arrangement takes lit- Trommels are particularly well adapted to placer feeds
tle floor space, allowing banks of multiple units to be set because of their abilty to handle a diversity of feed sizes
up for large~apacity requirements. In this situation, slurr and to break up material in the scrubber section. Capacity
distributors are required to sectìonalize feed for individual ranges from 10 to 500 yd"/h and is dependent on feed
spirals. characteristics, screen perforation sizes, and machine size.
Maximum fee rates vary according to feed particle den- Water requirements are contingent upon the amount of
sity, size, and shape. Rates generally range from 1.0 to 1.4 washing desired.
10
Vibrating screens are often used for secondary size (Specific gravity: Gold, 17.50: wasle. 2.81)
classification in circuits treating alluvial ores and, in some Feed Concentrate Tails
cases, may provide primary sizing. The machines consist Rate ..
Composition
.yd'/d. .
..Wl %.
120 0.1
100 0,08
119.9
99.92
of a deck, or decks, containing inclined screening surfaces Specific gravity . 2.81 2.82 2.81
that are vibrated in either a rectilnear or ellptical motion. Grade. . .... .lr OZ Au/yd'.. 0.040 42.24 0.005
Screening medium can be woven wire cloth, parallel bars, Gold distribution:
tr ozld 4.8 4.224 0.576
or punched sheet metal. %....................., 100 88 12
High capacity, ease of installation, and reasonable
operating costs have all contributed to the popularity of
vibrating screens. The practical minimum size limitation
for production screens is about 100 mesh, although Table 2.-Sample material balance, jig mil
325-mesh separations have ben achieved. Capacity is, of (Specific gravity: Gold. 17.50; wasle. 2.65)
course, dependent on many factors. These include type of Feed Concentrate Tails
material, amount of oversize, amount of undersize, moìsture
content, particle shape, screen opening size, and screen Rale . . . yd'/d.
Composition. , . . . WI %. .
700
100 0.1
0,0 699.9
99.99
medium. In general, from 0.40 to 0.75 tV of screen surface SpecifiC gravity. . . . . . . 2.ì5 2.71 2.65
area wil be needed for every cubic yard of feed handled per Grade.. .... .11 OJ; Au/yd'. 0.030 199.50 0.002
Gol diSlribulÌon:
hour. tr ozld ... ...... 21.0 19.95 1.05
"m............ ......... 100 95 5
SAMPLE MILL DESIGN
It is not possible to provide complete instruction on mil Táble 3.-Sample material balance, table mil
design within the constraints of this manuaL. Mils must
be planned with the intention of treating the size, shape, (Specific gravity: Gold. 17.50; waste. 2.73)
and grade characteriics of a speifc feed. Sample gold mil Fee Concentrate Tails
flow sheets shown in figures I, 2, and 3 are included to aid
the evaluator in cost estimation only. They are provided
Rate . . . yd'ld.
CompOSition . .. . Wl %.
250 0.2
100 0.08
249.8
99.92
to demonstrate that, in most instances, material wil have Speci/ic gravity. 2.73 2.75 2.73
Grade...... .Ir oz Au/yd'. 0.045 53.44 0.002
to be fed, washed, sized, and separated for proper recovery. Gold distribution:
Tables I, 2, and 3 provide sample material balances for Ir ozld 11.25 10.68 0.562
these mills. %...................... 100 9S 5
Mine-run gravel
(12 yd3/h)
Tails --
(4.49 yd3/h)
s+ . Water
Concentrates
(0.01 yd3/h)
p.n~ 1
Gold produc! Recycled water
Figure 1.-Sample "ow sheet. sluice mil.
11
Dragline
I
Mine-run gravel
(70 yd3/h)
Plus 4 in
(5 ydJ/h)
G+~ ~ (800 gpm)
Minus 4 in
si+. r- Waste
(15 yd3/h)
Minus 0.5 in
(30 yd3/h) Plus 0.5-in
nuggets
. Waste
(28 ydJ/h)
Minus 0.5-in
nuggets
Jig tray
Gold product
Waste
(1.5 yd3/h)
Concentrate
(0.01 yd3/h)
Dump
Tails
.
(15.25 yd3/h)
Waste
(0.49 yd3/h)
Concentrates
(0.01 yd3/h)
Oversize
Conveyor (14.75 yd3/h)
Minus 0.125 in
(0.5 yd3Jh)
Concentrates
(0.01 yd3/h)
Waste
Gold product (0.49 yd3/h)
Waste
(0.49 yd3h)
Recycled water
Dump
SUPPLEMENTAL SYSTEMS
Because of the relative low cost of placer mining and mil- To calculate the expense of camp facilties, it is
ing equipment and systems, the expenses associated with necessary to estimate the number of people staying at the
supplemental items represent a larger percentage of the mine. Guidelines for this estimate are provided with the
total cost than with other types of mining. For costing pur. cost equations in section 2 of this report. It must be
poses, any system, structure, or equipment not directly remembered that the number of people working at anyone
related to production but necessary for continued operation operation can be quite variable, and if the number of in-
is categorized as supplemental. These include tended or actual employees is available, this figure must
1. Buildings. be used.
2. Camp facilties.
3. General services and lost time.
4. Generators. GENERAL SERVICES AND LOST TIME
5. Pumps.
6. Settling ponds. Compared with other methods of mineral recovery,
Each item included in the supplemental section should placer mining is relatively ineffcient. Because oflimits in
be examined to determine if it is needed at a paricular workforc size, delays and tasks not directly related to min-
operation. To aid in this determination and to assist in cost ing have a noticeable effect on productivity. This
estimation of supplemental items, the following informa. ineffciency strongly infuences costs associated with placer
tion wil prove helpful: mining, and. must be taken into account.
1. Location and elevation of available water in reference In placer mining, most costs associated with ineffciency
to the milsite. can be attributed to three distinct areas:
2. Ecological sensitivity of the area. L Equipment downtime.
3. An estimate of the number and capacity of pumps 2. Site maintenance.
needed. 3. Concentrate refinement.
4. Maximum hourly capacity of mil. Specifc expenses can be further delineated.
5. Building requirements. 1. Equipment downtime.
6. An estimate of workforce size. A. Productivity lost by the entire crew because of
breakdown of key pieces of equipment.
B. Productivity lost by individual operators becaus
BUILDINGS of breakdown of single pieces of equipment.
C. Labor charges of outside maintenance personnel.
Many placer operators consider any building to be a lux- 2. Site maintenance.
ury; however, if weather is a factor or if operators desire A. Road maintenance.
to safely stre equipment, some buildings wil be needed. B. Stream diversion.
Tyically, a small placer mine wil have one structure that C. Drainage ditch construction and maintenance.
serves as a shop, a concentrate cleanup area, and a storage D. Site cleanup.
room. More elaborate operations, or those in areas of bad E. Reclamation grading and recontouring.
weather, wil cover the mil and often construct several F. Settlng pond maintenance.
small storage sheds. These buildings are usualIy temporar G. Mil relocation.
strctures of minimal dimensions constructed of wood or 3. Concentrate refinement.
metal. A. Concentrate panning.
The size of each building must be estimated for costing B. Mechanical separation.
pur. For the typical operation, the main strcture will C. Amalgamation.
be capable of housing the largest piece of mobile equipment Estimates indicate that in placer mining up to 37% of
at the mine with enough additional room for maintenance the total labor effort is spent on the above tasks. The lost
work. Shops oftn have concrte floors, and power and water time and general services cost cure must be used in all
facilties ate typically provided. Storage shed are usually placer mine cost estimates.
of minimum quality, have a wood floor if any at all, and
often contain power for lighting. Factors for all these
varables ar provided in the building co estimation cure. GENERATORS
In all but the most simple gravity separation miIs,
CAMP FACtLlTIES power will be needed to operate equipment. A minor amount
of power wil also be required for camp functions. Tyically,
The provision of facilties for workers is an important power is provided by one of three sources:
part of placer operations. In most situations, workers wil 1. Individual diesel engines driving each piece of
stay at the site during the mining season to take advan- equipment.
tage of good weather. The needs of these workers must be 2. Diesel generators.
met, and that typically involves providing living quartrs 3. Electrical power brought in through transmission
and food. In almost all cases, employee housing at placer lìnes.
mines consists of mobile homes or trailers with a minimum The third source generalIy requires excessive initial
amount of support equipment. Cooking is generally done capital expenditurs. Transmission lines are considered only
14
when the mil capacity is well over 200 yd'/h. existing A separate estimate must be made for each pump. Water
transmission lines are located near the site, or the mine requirements can either be calculated using parameters
life is expected to be 15 yr or more. Power source selection given in the processing portion of section 1, or roughly
should be based on lowest overall cost and minimum en- estimated using the following equation:
vironmental impact. For most small- to medium-sized
gravity separation mils in remote locations, diesel Water consumption (gpm) = 94.089(X)O'S46,
generators are selected to provide power.
Cost estimation cures in this report are based on diesel where X == maximum cubic yards of mil feed handled per
generators providing all power to miI equipment. Electric hour.
power çosts contained in individual processing equipment This equation provides the total gallons of water per
operating cost cures account for diesel generator operating minute consumed by the mil. Although not technically ac-
costs. curate, for the purposes of this report, head may be
estimated as the elevation difference between the pipe
PUMPS outlet at the mil or upper settling pond, and the pump
intake.
Water, used to wash gravel and to initiate slurrying of
the feed, i~ typically introduced as gravel enters the trom.
mel or screen. More water is added as needed throughout SETTLING PONDS
the circuit to dilute the slurr or assist in washing. To pro-
vide adequate washing, this water must be introduced With the current level of environmental awareness, it
under pressure which, in many cases, necessitates the use is almost assured that mil water wil have to be treated
of pumps. Pumps wil also be needed ifmil water is to be prior to discharge. Placer mines typicaIly recycle mil ef-
recycled through settling ponds. Under certain cir- fluent throûgh one or more settlng ponds to control en-
cumstances, one pump can handle all tasks required in a vironmental impact.
placer processing plant utilzing recycled water. It is To calculate the cost of settling pond construction USing
preferable to minimize the use of pumps by taking advan- this report, only the maximum mil feed rate is required.
tage of gravity. Cost curves provide the construction expense of unlined
Water use is dependent on several factors, including ponds sized to comply with most regulations. In some in-
1. Washing réquired to properly slurry feed. stances, the pond wil have to be lined with an impervious
2. Type of separation equipment used. materiaL. This is often required in ecologicaIly sensitive
3. Availabilty of water. areas, or in situations where underlying soils do not
4. Size and nature of valuable mineral constituents. properly fiter mill effuent, thereby increasing the turbidity
For costing purposes, the evaluator must estimate the of nearby streams. A factor is provided in the settling pond
volume of water pumped per minute and the pumping head. cost curve for impervious linings.
ENVIRONMENT
Enviromental costs are often decisive in placer mine a major stumbling block, beause some States restrict open
economic feasibilty. Costs assoiated with water quality burning. Next, a layer of overburden is removed to expose
control and aesthetics are inescapable and can represent the deposit. Finally, the valuable mineral-bearing gravel
a significant percentage of total mining expenses. Method can be excavated.
to minimize ecological disturbance are now considered an Currnt technology suggests that control of land dis-
integral function of the mining sequence and are treated turbance be incorporated into the mining sequence. Milil
as such in cost estimation. tailngs and oversize are typically dumped back into
Stream siltation from mil effuent and land disturbance worked-out areas. Soil cover and overburden are removed
from excavation are the main environmental problems fac- just prior to pay gravel excavation, then hauled to mined-
ing placer miners. Reduction of water quality is often the out areas to be graded and contoured over replaced tails.
biggest problem, and many tehniques have been devised Often the surface is revegetated. In most instances, the
to lessen the impact caused by mil operation. One methcd operator will have no choice but to implement ecological
involves limiting mil operation to short periods of time, control and reclamation procedures. Oprators are typically
thus allowing effuent to disperse before additional mil require to post a bond to cover the co of reclaiming mined
discharge is introduced. Ofen the mil is designed with the lands, and if the surface is left disturbed, these bonds wil
intent of using as little water as possible for valuable be forfeited.
mineral separation. The most common solution is mill water Regulations vary from State to State, and may appear
recirculation faciltated by the construction of settling diffcult and confusing at first; however, by contacting in.
ponds. These ponds are used to hold mil effuent until par- formation services at State capitals, operators wil be
ticulate matter has settled; water from the ponds is then directed to the agencies concerned. These agencies wil
reused in the mil circuit. detail regulations concernng placer operation and will also
Mining of alluvial deposits necessitates disturbance of point out which Federal agencies might be involved (U.S.
large areas ofland. TypicaIly all trees, brush, grasses, and Forest Service or U.S. Bureau of Land Management). In
ground cover wil be cleared. This task alone may present most insnces, contact will have to be made with both State
15
and Federal agencies. Typically, meeting environmental re- general services curve. An equation is also provided" for the
quirements for the State wil satisfy Federal regulations. construction of settling ponds, if water is to be recycled.
As stated earlier, environmental control is an integral Bond costs are not included since requirements are
part of mine and mil design, and costs are treated accord- highly varable. One other cost may arise that is not covered
ingly. Equations are provided for calculating the cost of mil in section 2. This is the expense of replanting, and usually
tails and oversize placement. Expenses associated with ranges from $100 to $200 per acre.
grading and contouring are contained in the lost time and
COST ESTIMATION
.
2. Mine equipment suppliers.
3. Published cost information services.
In all cases, cost figures quoted in the text and points
used in cost equation derivations are averages of all data
characteristics specific to a particular deposit. These fac.
tors determine the precision of the final cost, so they must
be selected and used carefully. Assistance in determining
the correct use of a factor, or in understanding the
parameters involved in a cost item, may be found in the
available. A bibliography of cost information publications preceding pages.
follows section 2. Many of these sources contain both cost To further improve cost estimates, labor rates are also
and capacity information and can be used to supplement adjustable. Rates can var greatly for small placer opera-
this manuaL. tions. For this reason, adjustments can be made to the fixed
Cost estimation methodology in this handbook is based rates used in this report for specific known rates at in-
on the Bureau's Cost Estimation System (CES), first dividual operations.
published in 1977 as "Capital and Operating Cost Estima-
tion System Handbook," by STRAAM Engineers, Inc. Pro-
cedures for cost estimation using this report closely follow COST DATE ADJUSTMENTS
that publication. The cost estimation portion of this report
is divided into operating and capital costs. Cost equations All cost equations were calculated in January 1985
are similar for both with the only difference appearing in dollars. Costs calculated for any particular cost item are
the units ofthe final answer. Capital cost are given in total broken down into specific categories and subcategories to
dollars expended and operating costs in dollar per year. faciltate adjustment to specific dates. These include
Using the appropriate curves, a separate cost is Labor.
calculated for each capital and operating cost item. Only 1. Mine labor.
costs directly associated with the operation under evalua. 2. Processing labor.
tion need be calculated. All other cost items should be ig- .3. Repair labor.
nored. Afr calculation, item costs should be entered on Equipment.
the respective capital and operating cost summary forms 1. Equipment and equipment pars.
(see figues 5 and 6 in section 2). 2. Fuel and lubrication.
Upon summation of individual expenses, a contingency 3. Electricity.
may be added to both capital and operating costs. It is dif- 4. Tires.
ficult to anticipate every condition that may arise at a par- Supplies.
ticular operation, and the purse of the contingency is to 1. Steel items.
account for unoresen expnditures. This figu is typically 2. Explosives.
bas on the degree of certainty of the evaluation in rela- 3. Timber.
tion to available information, and ranges from 10% to 20%. 4. Construction materials.
Cost per cubic yard of pay gravel processed is deter- 5. Industrial materials.
mined by dividing the sum of all annual operating costs by
the total amount of pay gravel processed per year. Summa. For placer mining, most general maintenance and non-
tion of individual capital expenditures produces the total overhaul repairs are accomplished by the equipment
capital cost. operator, so repair labor rates are assumed to be equal to
the individual curves is described in the follow.
Use of those of the operator. If information available to the
ing paragraphs. evaluator indicates that this is not the case, repair labor
16
portions of the total labor cost are stated to faciltate wil significantly alter the calculated cost. The following
adjustment. example ilustrates factor use.
Equipment operating costs are broken down into respec.
tive percentages contributed by parts, fuel and lubrication,
electricity, and tires. These percentages, listed immediately Example Adjustment Factor Application
following the cost equations, are used to calculate specific
costs for each subcategory so that they may he updated. Calculate the cost of extracting pay gravel in a hard dig-
Supply costs are broken down and handled in a similar ging situation and moving it 800 ft up an 8% gradient us-
manner. ing bulldozers. Assume a 200-LCY ih operation (January
Cost date indexes for the preceding subcategories are 1985 dollars), and use the operating cost and adjustment
provided in table 4. These and other cost indexes are up. factor equations provided in the operating costs-mining-
dated every 6 months and are available from the Bureau buIldozers portion of section 2.
of Mines, Western Field Operations Center, East 360 Third
Avenue, Spokane, WA 99202. To adjust a cost to a specific Operating costs per LCY
date, divide the index for that date by the index for January (from section 2):
1985, and multiply the resulting quotient by the cost Equipment operating cost 0.993(200)'°.430 $0.102
calculated for the respective subcategory. An example of Labor operating cost 14.01 (200)"°.945 .094
such an update follows. January 1985 total .. 196
..
1960.. .
1961 ...
Mining
labor"
52.61
2.64
Equip.
ment and
repair
parts
85.8
87.3
Fuel
and
lubrication
95.5
97.2
Elee-
tricity
100.1
100.7
Tires
113.1
109.9
Bits
and
sleel
97.1
97.2
Explo.
sives
94.5
97.0
Tim-
ber
92.1
87.4
Construe-
lion ma-
terial3
99
97
Indus-
trial
material
~95.3
.94.8
1962 .. . 2.70 87.5 96.1 101.9 94.7 95.8 97.0 89.0 96 94.8
1963 . 2.75 89.0 95.1 101. 96.9 95.7 100.4 91.2 98 94.7
196 ... 2.81 91.2 90.7 100.3 97.6 97.0 100.0 92.9 98 95.2
1965 .. 2.92 93.6 92.8 100.3 98.8 97.9 99.6 94.0 97 96.4
1966 .. 3.05 96.5 97.4 99.8 101.3 98.7 98.1 100.1 99 98.5
1967 3.19 100.0 100.0 100. 100.0 100.0 100.0 100.0 100 100.0
1968 3.35 105.7 98.1 100.9 102.7 101.9 102.3 117.4 127 102.5
1969 3.61 110.4 99.6 102.2 98.3 107.0 104.7 131.6 108 106.0
1970 ... 3.85 115.9 t01.0 106.6 105.4 115.1 106.7 113.7 109 110.0
1971 4.06 121.4 106.8 115.5 1 to.3 121.8 113.3 135.5 133 114.0
1972 .. 4.41 125.7 108.9 123.9 111.3 128. 115.2 159.4 151 117.9
1973 4.73 130.7 128.6 132.6 115.7 136.2 120.1 205.2 154 125.9
1974 5.21 152.3 223.4 172.3 141.6 178.6 150.0 207.1 167 153.8
1975 5.90 185.2 257.5 209.7 155.4 200.9 178.0 192.5 186.3 171.5
198 8.70 275.4 582.4 334.8 236.9 297.3 237.1 336.3 280.86 260.3
19805 .. 9.08 290.9 693.3 376.0 250.4 300.4 254.4 327.3 289.05 275.6
1981' 9.78 304.9 736.0 393.9 256.2 322.8 268.5 331.6 298.25 289.9
19815 10.07 324.0 818.4 429.9 269.6 338.7 292.8 330.1 312.11 306.0
1982' 10.58 337.0 802.9 454.0 271.6 34.1 293.2 310.6 324.74 311.7
19W 10.91 346.1 77.1 471.5 272.6 337.4 294.8 319.2 330.56 313.0
198' .. 11.10 348.6 727.1 482.6 285.4 333.2 300.4 324.2 342.01 314.0
19835 .. 11.31 352.7 694. 492.2 256.6 341.3 302.8 372.5 357.28 316.6
1984' 11.5a 35.3 669.7 492.0 258.0 354.1 301.3 353.2 355.52 319.2
19845 11.62' 358.2 674.6 525.5 256.3 357.2 312.4 343.3 357.90 324.0
1985" . 11.69 360.4 636.2 524.9 262.0 357.4 313.4 343.2 358.32 323.2
19855 .. 11.98 362.3 630.7 540.3 246.0 354.6 312.1 354.9 363.63 324.3
1 Unless otherwise noted, based on U.S. Bureau of Labor Statistics (BLS) "Producer Price Indexes," base year 1967 = 100.
Z Based on BLS "Employment and Earnings: Average Hourly Earnings, Mining."
3 Based on Engineering and News Record "Market Trends: Building Cost."
· January.
5 July.
S January (base cost year for this report).
.210
FINANCIAL ANALYSIS
The purose of this report is to provide an estimate of operating costs would be highly misleading. There is no
capital and operating costs for small placer mines. A distinc- quick and easy way to account for the wide variety of sitUa-
tion must be made between a cost estimate and an economic tions encountered in economic analysis. Each one of the
feasibilty analysis. Capital and operating costs are simply preceding items must be examined individually to provide
two separate variables in a complete economic analysis. To accurate economic feasibilty estimates, and a complete
determine the economic feasibility of an operation, the cash.flow analysis is the only way to ensure that proper
evaluator must consider each of the following: results are obtained. To accomplish this, all yearly income
1. Recoverable value of commodity. and expenses must be tabulated. Then the rate of return
2. Local, State, and Federal taxes. over time must be calculated from the resultant profits or
3. Capital depreciation. losses. The evaluator must consider all factors infuencing
4. Depletion allowances. income and include all expenses as well as account for the
5. Desired return on investment. value of money over time and choose an acceptable rate of
6. Costs and methods of project financing. return.
7. Inflation. In brief, the operator wil have to receive adequate
S. Escalation. revenues from commodities recovered to
9. Environmental intangibles. 1. Cover all operating expenses.
Economic feasibilty analysis is a subject in itself, and 2. Recover initial equipment expenditures.
wil not be covered here. The preceding list is included to 3. Provide for equipment replacement.
emphasize the fol1owing: A prospect is not economically 4. Cover all exploration and development costs.
feasible simply because the apparent commodity value ex- 5. Pay taxes.
ceeds the total capital and accrued operating costs calculated 6. Compensate for infation and cost escalation.
from this manuaL. 7. Supply å reasonable profit.
The cost asiated with the preceding list are real and
-
must be considered when determining the feasibilty of a Only when enough revenue is produced to cover all of
prospect. Any attempt to provide guidelines for determina- the above can an operation be considered economically
tion of feasibilty basd solely on estimates of capital and feasible.
EXPLORATION
/
t-
tailed exploration progam be designed if
-
10,000 100.00 r ,00,00
TOTFL ~E5OURCE, tx ci 1 e \prds
Exploration Cost Tabulations: As in the CES Hand- CES Exploration Cost Tabulations: Some oft.he more
book, costs are given in dollars per unit processed (cubic pertinent exploration cost items presented in the CES Hand-
yard, sample, foot driled, etcJ. The product ofthe unit cost book (ie 9142) are summarized in the following. A de.
and the total units processed constitutes the: total capital tailed description of these items can be found in that
cost for any particular method of exploration. Total explora- publication.
tion costs consist of the sum of these individual exploration
method expenses. A summary sheet for these calculations EXPLORATION-GENERAL RECONNAISSANC~
is shown in figure 4.
Average cost per worker.day. . $195
EXPLORATION-PANNING Cost range . $175-$210
Cost variables. Deposit access, terrain,
Average cost per sample ........ $2.10 and labor eftkiency.
Cost range $1.90-$2.60
Cost variables . . Labor effciency and EXPLORATION-CAMP COSTS
material being panned.
Average cost per worker.day $30
EXPLORATION-CHURN DRILUNG Cost range $19-$41
Cost variables . . . . . . . . . Deposit remoteness,
A verage cost per foot ..' $45 terrain, access, and
Cost range . $20-$70 climate.
Cost variables . Depth of hole, material
being driled, site access, EXPLORATION-SEISMIC SURVEYING (REFRACTION)
and local competition.
Average cost per linear foot. . $1.50
EXPLORATION-BUCKET DRILUNG Cost range. . . .'. _. ......... $1.00-$2.50
Cost variables Labor effciency, deposit
Average cost per foot . $9.20 access, and terrain.
Cost range . . . . . . . . . . . . .. ..... $5-$20
Cost variables . Depth of hole, material EXPLORATION-ROTARY DRILLING
being driled, and site
access. Average cost per foot ... . . . . . . . . $6.50
Cost range . $2.00-$11.50
EXPLORA TION- TRENCHING Cost variables . Depth of hole, material
being driled, and site
Average cost per cubic yard. $7.10 acceSs.
Cost range .. _ . . . . $2.25-$28.50
Cost variables . . _ . . . . . . .. ..... Labor effciency, material EXPLORATION-HELICOPTER RENTAL
being sampled, site
access, equipment owner- Average cost per hour $395
ship, sampling method, Cost range _ $305-$590
and total volume of work Cost variables . . Passenger capacity,
to be done. payload capacity, cruise
speed, and range.
Total
DEVELOPMENT-ACCESS ROADS
V
i-
CD
x = Average width of roadbed, in feet. a.
Il
"-
/" ..
c:
The following assumptions were made in estimating road
costs: ~ \0,000 ./
1. Side slope, 25%. 3. Moderate digging ..:t
o
u
2. Moderate ground cover. diffculty.
If
i-
Base Equation:
~
Access road capital cost . Yc = 765.65(X)O.9'l2
Fs == O.633el0.ll"ll"rC""t .I"peil.
Fe = 6_743.
DEVELOPMENT-CLEARING
c
"t
/
./
The following assumptions were made in estimating t- /'
clearing costs: cu..
F s = O.942el0.OOpercnl slope
ii.
FF = 1.750.
Total Cost: Clearing capital cost is determined by
(y c x F s x F B x F F)'
.g
x :: Maximum loose cubic yards of pay gravel, over. "
"-
burden, and tails moved hourly by dragline. ID
ID
o ..Eqil-\
..
'" ..
D
To obtain the overburden removal capital cost, the total cost tion. This product is subsequently entered in the ap-
per loose cubic yard must be multiplied by the total amount propriate row of the tabulation shown in figure 5 for final
of overburden handled by front-end loader prior to produc- capital cost calculation.
CAPITAL COSTS 27
.
overburden, and tails moved hourly by rear. o
dump trck.
!
The base equations assume the following: ... 0.100
a " ~iiil
1. Haul distance, 2,500 ft. 4. Average operator
1l
"-
2. Loader cycles to fill, 4. abilty.
3. Effciency, 50 minl. 5. Rollng resistance, 2%,
"~r.
nearly level gradient. §
~
Base Equations:
i
~
Equipment operating costs. Y E = 0.602(X)-.296
Labor operating cost. . ... Y L == 1 i.34(X)-.891 0.010
10 100 1,00
CJin. mii_ 100 able ',rOS par hor
Equipment operating costs consist of 28% pars, 58% fuel
and lubrication, and 14% tires. Labor operating costs con- Clrtn: roil ""ltQI casts - Riir-do tn.e
sist of 82% operator labor and 18% repair labor.
Ditace Factor: If averge haul distce is other than
2,500 ft. the factr obtained from the following equation
must be applied to total cost per loo cubic yard:
FD = O.093(distance)Ul1.
.
be multiplied by factors obtained from the following
equations:
~
burden, and tails moved hourly by scraper.
L
01
a.
The base curves assume the foIlowing: ~ 0_100
-i;ri-t
..
ci
1. Standard scrapers. 4. Average haul distance,
2. Rollng resistnce, 6%, 1,000 ft. -8
nearly level gradient. 5. Average operator .. '"
3. Effciency, 50 min/. abilty. g¡
u 'l.r
Base Equations: §..
If
w
Equipment operating cost. Y F. ;; 0.325(Xl-°.2IO &
Labor operating cost. . . . .. YI. ;; 12.0i(X)-O.930
MINE EQUIPMENT-BACKHOES
/
quid production. Cos do not include transporttion, saes ,
tax. or discounts. The equation is applied to the following
variable:
..
\.
/'
X = Maximum loose cubic yards of pay gravel moved E
hourly by backhoe.
'"
Õ
~
The following capacities were used to calculate the base ,.Ul 100,00
c
equation: r.
rf
105 hp .. 95 to 200 195 hp . .250 to 375 ~
LCY/h LCY/h ~
135 hp ..... .175 to 275 325 hp ......350 to 475
LCY/h LCY /h
Base Equati~n:
Equipment capital cost . Yc = 84.132.Oleio.oo~XIJ
MINE EQUIPMENT-BULLDOZERS
/ /
cost of purchasing the appropriate size and number of
crawler dozers needed to provide the maximum required
production. Costs do not include transportation, sales t~x.
or discounts. The equation is applied to the following
variable:
X == Maximum loose cubic yards of pay gravel,
overburden. and waste moved hourly by
Cd
el-
/ /
bulldozer.
-8
//
/ /
..
UJ 100,00
o
u
The following capacìties were used to calculate the base V
equation: æ
t-
o:
200 hp
65 hp. . .19.0 LCYIh . . . .126.0 LCY/h 15
80 hp. 31.5 LCYIh 335 hp . .263.5 LCYIh
105 hp " 56.5 LCYIh 460 hp 334.0 LCYIh
140 hp '" . . 82.0 LCY/h 700 hp 497.5 LCY/h
/
Capital Cost Equation: This equation furnishes the 1,00,00
cost of purchasing the appropriate size dragline needed to
provide the maximum required production. Costs do not in-
clude transportation, sales tax, or discounts. The equation
/' !
¡
is applied to the following variable:
/' ./
X= Maximum loose cubic yards of pay gravel,
overburden, and waste moved hourly by
II
L
/' I
dragline. o
C
II
/' i
I
The following capacities were usd to calculate the base ..UI 100,00 ¡
equation: au ,
..
84 hp. .28 LCY/h 190 hp. . 94 LCYIh ll
..
110 hp. .47 LCY/h 263 hp . 132 LCY ih ~
148 hp. .66 LCYIh 289 hp.. .188 LCy/h u
I
170 hp.. .75 LCYIh 540 hp . . .264 LCy/h i
//
,
of purchasing the appropriate size and number of wheel- !
type front-end loaders needed to supply the maximum reo i
I
/
quired production. Costs do not include transrtation, sales i i
/
front.end loader.
..Ul 100,00
i
i /1
ou "7
The base equation was calculated using the following
ël
capacities: ..
1.00-yd3 bucket, 3.50-yd3 bucket, 0:
200 hp . 129.50 LCY /h ua:
65 hp ." .24.00 LCY/h
1.50-yd3 bucket, 4.50.yd3 bucket,
80 hp. .34.50 LCY/h 270 hp . .171.00 LCY/h
1. 75-yd3 bucket, 6.50-yd3 bucket,
105 hp . 38.50 LCYih 375 hp .234.00 LCY/h
2.25-yd3 bucket, 12.00-yd3 bucket, 10'~D \00 1,000
125 hp. 56_25 LCY ih 690 hp .348.00 LCY/h
CAAC (TY. ma i m. I ""ss o. i c yords po r t-r
2.75-yd3 bucket,
155 hp . .66.00 LCY/h Hi"" equipmit copi tal costs - Frcit-end locrs
The above capacities are based on the following
assumptions: \.
1. Haul distance, 500 ft. 4. Wheel-type loader.
2. Rollng resistance, 2%, 5. Effciency, 50 minl.
nearly level gradient. 6. General purpose
3. Inconsistent bucket, heaped.
operation.
Base Equation:
Equipment capital cost. . Yç == 2,711.10(X)O.896
-
Equipment capital costs consist entirely of the equipment
purchase price.
y c x F D X F G X F u x FT'
Used Equipment Factor: This factor accounts for
reduced capital expenditure ofpurchasing equipment hav- Ths product is subsequently entered in the appropriate row
ing over 10,000 h of previous service life. of the tabulation shown in figue 5 for final capital cost
F u '" 0.386. calculation.
CAPITAL COSTS 33
7
/
variable:
~
l-
X =Maximum loose cubic yards of pay gravel, e
overburden, and waste moved hourly by e
'l
rear-dump truck.
I- 100.00
"'
o
u i
The following capacities were used to calculate the base
-i
equation: a:
l-
//
V
3.0-yd3 12.0-yd9 lL
//
truck. . .32.3 LCYIh truck . . 124.5 LCYIh !5
5.0-yd3 16.0-yd3
truck .. .53.4 LCYIh truck . .. . 163.9 LCY ih
6.0-yd3 22.8-yd9
truck. ...63.6 LCYIh truck . 223.5 LCY ih
8.0-yd3
truck . .83.5 LCY ih
34.0-yd"
truck . 326.3 LCYIh
Lo.~o 100 1.000
10.0-yd3 47.5-yd" OlPRC tTy. m: I RU I OOS8 o. i C !,ords per hcr
truck . .104.2 LCYIh truck..... 444.8 LCYIh
Mine Iilpml ~Ital costs - Rear-a. trucs
The above capacities are based on the foIlowing
assumptions:
'.
1. Diesel rear.dump 3. Haul distance, 2,500 ft.
trucks. 4. Rollng'resistance, 2%,
2. Loader cycles to fill, 4. nearly level gradient.
Base Equation:
Equipment capital cost. Y c = 472.09(X)1.139
II
F D = 0.06240(distance)O.364.
MINE EQUIPMENT-SCRAPERS
.
Capital Cost Equation: This equation furnishes the cast f .00.00
i
of purchasing the appropriate size and number of scrapers
//
/
I
needed to provide maximum required production. Costs do
not include transporttion, sales ta, or discunts. The equa. I
tion is applied to the following variable:
X=Maximum loose cubic yards of pay gravel, over. (D
/ i
7
~ I
burden, and waste moved hourly by scraper. o
i
no
The following capacities were used to calculate the base I
i
i- 100,00
equation: '"
o i
U
330 hp. _ . .201 LCY/h 550 hp .. 420 LCYIh
I
-l I
a:
450 hp _ . _ .323 LCY/h ,-
"- I
a: i
The above capacities are based on the following u
I
assumptions: !
PROCESSING EQUIPMENT-CONVEYORS
.
10
Equipment capital cost Yc = 4,728.36(X)O.287 a:C1TY:r ifirT cubic yards of ITle,.¡al rr..ad per hor-
The capital cost consists of 89% equipment purchase price, P rOC6"" í ng equ; pn t cc i to I ca t" -Ccivey""
8% installation labor, and 3% construction materials.
Length Factor: If the reuired conveyor length is other
than 40 ft, the façtor obtained from the following equation
must be applied to the calculated capital 'cost. This factor
is valid for conveyors 10 to 100 ft long:
F L = 0.304(length)O.330.
loa,QOO
Capital Cost Equation: This equation furnishes the I
cost of .purchasing and installng the appropriate size
vibrating feeder needed to meet maximum required produc-
I
tion. The cost includes assiated drive motors, springs, and
electrical hookup, plus the expense of a hopper. Equipment
transportation, sales tax, and discounts are not accounted
'"
for. The equation is applied to the foHowing variable: ~
o
X=Maximum cubic yards of material handled
/
~
/
hourly by feed hopper.
§ 10.00
LJ
The following capacities were used to calculate the bas
equation: ~ "7
. . . .. 16 yd3/h
/
12-in-wide unit &
'-
V~
24-in-wide unit " 211 yd3/h
36-in-wide unit . 522 yd3/h
/
CD
..
~
X=Maximum cubic yards of feed handled hourly by uõ V
jig concentrators.
The foIlowing capacities were used to calculate the base
... 10,000
'"
0
u
/ /
equation: ã!
Base Equation:
Equipment capital cost. ... _ y c = 6,403.82(X)O.5&5
PROCESSING EQUIPMENT-SLUICES
/1/
X=Maximum cubic yards of feed handled hourly
by sluice.
18-in-wide 36-in-wide ?i
i-
1/.
box . 20.75 yd"l box '...... 75.00 yd"lh
42-in-wide If
24-in.wide u
box ... 31.25 ydlh box. . 125.00 yd"l
30-in.wide
box 50.00 yd3/h
48-in-wide
box. ., _. .218.75 yd31h
/ / l/v
The above capacities are based on the following
assumptions:
V 10 100 1,000
1001
1. Steel plate 4. Length-to-width ratio, CRAtlT~. tlilT cubic ,"orei of fse lrsolad per her
construction. 4:1 Procsssing squipfll ixi tol cots - Sluice
2_ Angle-iron rimes. 5. Gravity feed.
3. Feed solids, 3,400
lb/yd3.
Base Equation:
'\
Equipment capital cost . . .. y c =' 113.51(X)O.567
..i
//
/
ull 10,00
10 starts 10 yd'ih 100 start .
The above capacities are based on the following
100 yd'/
/
assumptions:
1. Rougher service. 4. Slur density,
2. Solids per start, 10% solids. 1,00, 10 100 1.000
1.75 stlh. 5. Gravity feed. CAITY. ""inu cùic yan; of fee t.i-lEi per tir
3. Feed solids,
3,400 lb/yd". Proceeing eqipmt. cqlt.cl cot.s - Søircl ~ent.rolors
Base Equation:
Equipment capital cost. . Yc = 3,357.70(X)O.99
lê
number of tables needed to meet maximum required pro- _.- I:
duction. Cost includes associated drive motors, piping, and
-- f- _._-
-t-n- _d n_..
l;
electrical hookup. Equipment transportation, sales tax, and L-I ~~ r-~ V- i i
!
The above capacities are based on the following
i
assumptions. ,, )
Base Equation:
Equipme~t capital cost. .. Y(" = 20,598.06(Xlt)J¡~;1
~I
cost of
o
-LJ~I.
II -i
x = Maximum cubic yards of feed handled hourly "0
by trommels.
1. Trammels are sec- 2. Gravity feed. Processing eqipment capl tal costs - T~ommls
tioned for scrubbing 3. Feed density, 2,300
and sizing. lb/yd3.
Base Equation:
Equipment capital cost. . Yc = 7,176.2HX)o.559
1,000,000
Capital Cost Equation: This equation furnishes the i
cost of purchasing and installng the appropriate size and
L
number of vibrating screens needed to meet maximum re-
quired production. Cost includes installation and electrical j
hookup of both the screens and the associated drive motors.
:
Equipment transportation, sales tax, and discounts have w
not been taken into account. The equation is applied to the ~
o ¡
I
i
following variable: o
"0
!
x = Maximum cubic yards of feed handled hourly .. l00,OCO
ui
au /'
by vibrating screens.
..
0:
,/ /' :
7 ./
The following capacities were used to calculate the bas .. i
Q.
equation: a:
u
I
r
/
30.fl' screen 96.ft screen ./ r
surface .
56-ft' screen
47 yd"l surface. . . . . . 150 yd"/h
140.ft. screen
/' /' i
I
i
surface 87 yd'l surface. . 218 yd'/h
10'OOO 100 I.:XJO
I
60.ft' screen i
surface _, .. 93 yd3/h
CAACITY. maximu cubic ~crds or reed treated per ~u"
The abQve capacities are based on the following Procoseing equipmet cap; tal cots - Vibrating screes
assumptions:
1. An average of 0.624 ft" 2. Feed solids,
of screen is required for 3,120 Ibfyd'.
every cubic yard of 3. Gravity feed.
hourly capacity.
Base Equation:
Equipment capital cost. .. Yt: == 1,870.2OCXiii.6:1I
SUPPLEMENT AL-BUILOINGS
/
1 o:. DO
Capital Cost Equation: This equation provides the cos
of materials and construction for any buildings needed at
the site. These may include storage sheds, shops, or mil f-- -- /
buildings. Costs do not include sales tax, material transpor-
tation, or discounts. A separate cost must be calculated for
each building, and the equation is applied to the following
variable:
/
-i
1. Average quality tem- 3. Concrete perimeter a:
1-
porary structures. foundations with wood Q.
0:
2. Steel frame with floors. U
metal siding and 4. Electricity and
roofing. lighting provided.
Base Equation:
Capital cost. . . Y c = 34.09CX)O.90
I .oooo . i ,00 10,000
FLOO ARER. aqrs fasi
34% construction labor, 41% con-
The capital cost consists of
struction materials, and 25% equipment. Sulamalal coPi tal ccla - aui Idings
Yc )( Fe )( Fp x FF'
SUPPLEMENTAL-EMPLOYEE HOUSING
__.______ n_
L, i- -1-1-l'
- ,.- -- i.
ity single-wide trailers capable of meeting minimum
buílding code requirements. Costs do not include sales tax,
t--~~
~
------- .--- -
i
t
equipment transportation, or discounts. The equation is ap- " I
plied to the following variable: " ---_._- -~...~
i
C
lJ
x == Average loose cubic yards of overburden and i
pay gravel handled hourly. ti -
a ~OloOO
U
!
., i
The following capacities were used to calculate the base oJ
equation: I
&
l.l
25 LCY/h .. 3.1 workers 150 LCY!h . 6.6 workers
50 LCY/h. 4.2 workers 400 LCY/h . 9.9 workers
i I
- .
Base Equation:
Capital cost. . . . Yc == 7,002.51(X)O.418
. Workforce == O.822(Xt'.415
SUPPLEMENTAL-GENERATORS
Capital Cost Equation: This equation provides the cost 100.000 ,---- .-----T--- -ur
of purchasing and installing the appropriate size generator L----- l t-
required to meet maximum production. Cost includes in-
staIlation and connection through the fuse box. and allows ~- _ r- n
for mil, mine, camp, and ancilary function power consump-
L! i
i
i
tion. Costs do not include equipment transportation. sales, L
Base Equation:
Equipment capital cost.. Yc = 1,382.65(X)O.604
F p = i.365æjO.618,
SUPPLEMENT AL-PUMPS
¡ i)
i
i T
-I
i/
X
I
i
//
1 I
ponds, etcJ. If more than one pump is required, a separate i I i
,
cost must be calculated for each installation. Guidelines for i
!
'"
pump requirements are listed in section 1. In general, \.
o i : I I
however, at least one pump wil be required if water is o
, i
(
recycled through settling ponds. Costs of diesel-driven cen- "0 !
/
i I
and pipe instalIation labor are all considered. Costs of equip. u
ment transportation, sales tax, and discounts are not in. --
ci
/j)1 I
I-
cluded. The equation is applied to the following variable: 0.
a:
u
1ji i
Base Equation:
Equipment capital cost. . Y c = 63.909(X)O.6I!l
-
Used Equipment Factor: This factor accounts for
reduced capital expenditure ofpurchasing equipment hav.
ing over 10,000 h of previous service life:
Fu = 0.615.
Total Cost: Pump capital cost is determined by This product is subsequently entered in the appropriate row
of the tabulation shown in figure 5 for final capital cost
YcxFHxFu' calculation.
-
CAPITAL COSTS
SUPPLEMENTAL-SETTLING PONDS . 47
t-
II
o
/
If the water consumption rate is not known, one can be /
estimated from the foIlowing equation:
'-
~.J
,.
0- 100
/ /
/
X = 94. 089(y)O.546 , 0:
U
F L == 27.968(XrO.31..
OVERBURDEN REMOVAL-BULLDOZERS
.
Operating Cost Equations: These equations provide
the cost of excavating and relocating overburden using '2
\ .000
I
I
L
"' i
=r i- i
i
bulldozers. Costs are reported in dollars per loose cubic yard ":i i
Equipm~nt operating costs average 47% parts and 53% fuel Overburden remvQI oprotíng COBts SUI rdbzQrs
and lubrication. Labor operating costs average 86% oper.
ator labor and 14% repair labor.
Distance Fa~tor: If the average dozing distance is other
than 300 ft, the factor obtained from the following equa-
tion must be applied to total cost per loose cubic yard:
Fii = O.00581(distance)o.!l~
Digging Difficulty Factor: Parameters given in the Total Cost: Cost per loose cubic yard of overburden is
discussion on site adjustment factors in section 1 should be determined by
used to determine if a digging diffculty factor is required. (YE(U.) + YL(U1)))( FD x Fe)( FH x FR'
1fso, one of the following should be applied to total cost per
loose cubic yard: The total cost per loose cubic yard must then be multiplied
by the total yearly amount of overburden handled by
F If' easy digging. 0.830 F H' medium-hard bulldozer. This product is subsequently entered in the ap.
F H' medium digging . 1.250 propriate row of the tabulation shown in figure 6 for final
operating cost calculation.
digging 1.000 F H' hard digging. 1.670
OPERA TING COSTS 49
II
OVERBURDEN REMOV AL-DRAGLINES
~~
tI i
"-
variable: .
are reported in dollars per loose cubic yard of overburden d
..
Jl
handled. The equations are applied to the following U I
~U "- r-
x = Maximum loose cubic yards of pay gravel, over.
~ Ì"
'"
f' Ì' eq.""
~
0
0
-
burden, and tails moved hourly by dragline.
~
CD
a.
The base curves assume the following: ..
~ 0.100 I'
1. Bucket effciency, 3. Swing angle, 90° 2 '-
" Lcl,.
0.90. 4. Average operator Õ
2. Full hoist. abilty. "0
,.'-
iB
Base Equations: u
Ll
Equipment operating cost. . Y E= 1.984(X)-O.390 !..
Labor operating cost. Y L = 12.19(X)-o.888 If
w
&
Equipment operating costs consist of 67% parts and 33%
fuel and lubrication. Labor operating costs consist of 78%
operator labor and 22% repair labor.
0.010
10 100 1.000 I
The total cost per loose cubic yard must then be multiplied
by the total yearly amount of oioerburden handled by
dragline. This product is subsequently entered in the ap-
propriate row of the tabulation shown in figure 6 for final
operating cost calculation.
50 OPERA TING COSTS
F u= O.023(distance)Il.616.
fY E(U.XT.) + Y L(U1XT1)J x F D X F c.
The total cost per loose cubic yard must then be multiplied
by the total yearly amount of ouerburden handled by
dragline. This product is subsequently entered in the ap.
propriate row of the tabulation shown in figure 6 for final
operating cost calculation.
OPERATING COSTS
¡Yi;CUe+YLCU1)) x FD x Fa.
The total cost per loose cubic yard must then he multiplied
by the total yearly amount of overburden handled by truck.
This product is subseuently entered in the appropriate row
ofthe tabulation shown in figure 6 for final operating cost
calculation.
52 OPERA TING COSTS
OVERBURDEN REMOVAL-SCRAPERS
k"
X :; Maximum loose cubic yards of II
o
burden, and tails moved hourly by scraper. o
\.
æ
a.
The base curves assume the following: ~ 0.100
o l- ~Iiil
1 Standard scrapers. 4. Haul distance, 1,000 ft. o
2. Rolling resistance, 5. Average operator "
6%, nearly level abilty. I-
CI " I\ L-i
gradient. uo
3. Effciency, 50 minfh. Cl
~
l-
Base Equations: I
UJ
&
Equipment operating cost. . Yg=O.325(X)-O.2LO
Labor operating cost. . YI.,=12.01(X)-O.93o 0.010
10 100 I.COO
CRCITV. ma ¡mu Loose cuic yacds pec hoc
Equipment operating costs consist of 48% fuel and lubrica.
tion, 34% tires, and 18"'-l. parts. Labor operating costs con- Ovr-rd ~S' I op"ro t j ng COS ls - Scraprs
sist of 88% operator labor and 12% repair labor.
The total cost per loose cubic yard must then be multiplied
by the total yearly amount of overburden handled by
scraper. This product is subsequently entered in the ap-
propriate row of the tabulation shown in figure 6 for final
operating cost calculation.
OPERATING COSTS 53
MINING-BACKHOES
a. ""
1. Easy digging 4. Average operator "~ 0.100 -- -f--
diffculty. abilty. 'T
~
2. Swing angle, 60. to 5. No obstructions Õ "- '(~ '-
90 · . (boulders, tree roots, i:
3. Up to 50% of etc.).
maximum digging
...
ui
0
u
'" Ì\ ~ "- "
depth. (!
~
..
Base Equations: if
w
ii
0
95-200 LCY/h.
250-375 LCY/h:
MINING-BULLDOZERS
1.000
Operating Cost Equations: These equations provide
the cost of excavating and relocating pay gravel using
bulldozers. Costs are reported in dollars per loose cubic yard
tl~
"
:i
"'"
of pay gravel handled. The equations are applied to the u
following variable:
X=Maximum loose cubic yards of pay gravel, over.
~
æ
II
o ~ .. "-
"-
~ ::
o
burden, and tails moved hourly by bulldozer. ¡- r-
~
II
a.
The base equations asume the following: f! 0.100
II
1. No ripping. 4. Dozing distance, 300
" "- ..e,I-.l
2. Cutting distance, 50 ft.
ft. 5. Average operator
-0
..Ul
"
3. Effciency, 50 min/. ability. ou iax,
6. Nearly level gradient.
~
,.ci
Base Equations: a:
w
Equipment operating cost. .. YE""O.993(X)-O.430 !3
MINING-DRAGLINES
..
:i
dled_ The equations are applìed to the following variable: "
~
..
x .. Maximum loose cubic yards of pay gravel. over- CD
"-
burden. and tails moved hourly by dragline. .. "- .. Eqlpol
~
o
o
Swing Angle Factor: If the average swing angle is Mining operoting cols - Dragl ¡ne
other than 90°. the factor obtained from the following equa-
tion must be applied to total cost per loose cubic yard:
F s"" O.304( swi~~ angle)O.269.
I
Total Cost: Cost per loose cubic yard of pay gravel is
determined by
The total cost per loose cubic yard must then be multiplied
by the total yearly amount of pay grauel handled by
dragline. This product is subsequently entered in the ap-
propriate row of the tabulation shown in figure 6 for final
operating CQst calculation.
56 OPERA TING COSTS
1.000
Operating Cost Equations: These equations provide I
- t- i- Ì' i
~ --
8
burden, and tails moved hourly by front-end o
loaders. "-
It
'-
0.
~ 0.100
Ea1-it
The base equations assume the following: C i
The total cost per loose cubic yard must then be multiplied
by total yearly amount of pay gravel handled by front-end
loader. This product is subsequently entered in the ap-
propriate row of the tabulation shown in figure 6 for final
operating cost calculation.
OPERA TING COSTS 57
MINING-REAR-DUMP TRUCKS
F G=0.907eIO.o.91perc..t ¡:,'adi..t.l.
The total cost per loose cubic yard must then be multiplied
by the total yearly amount of pay gravel handled by rear-
dump truck. This product is subsequently entered in the
appropriate row ofthe tabulation shown in figure 6 for final
operating cost calculation.
58 OPERATING COSTS
MINING-SCRAPERS
10 100 1 ,00
Labor operating cost Y1.'" 12.0lCX)-Cl.9:¡ ~
0.010
Equipment operating costs consist of 48% fuel and lubrica-
tion, 34% tires, and 18% parts. Labor operating costs con- CRPRCITY. .. ì I' I ccss cu i c yards per hcr
sist of 88%. operator labor and 12% repair labor. Mining Qpsratlng costs - ScrQp9rs
(YE(U.)+ Yi.(UI))xFvxFa.
The total cost per loose cubic yard must then be multiplied
by the total yearly amount of pay gravel handled by scraper.
This product is subsequently entered in the appropriate row
of the tabulation shown in figure 6 for final operating cost
calculation.
OPERATING COSTS 59
PROCESSING-CONVEYORS
~
Equipment operating cost. . . Y E = O.218(X)-o.56\
Labor operating cost.. . Y L = 0.250(X)-O.702 ..
tI
oU
(!
Equipment operating costs average 72% parts, 24% elec- ~
tricity, and 4% lubrication. Labor operating costs consist ..
~ 0.00L10
entirely of repair labor. 100
~
CFC ¡TY. fIX i nu cub i c yard.. 0' fIter j c L irved per hour
Conveyor Length Factor: If conveyor length is other
than 40 ft, factors obtained from the following equations Processing oprating costs - Conveyors
must be applied to repective portions of th~ operating costs.
These factors are valid for conveyors 10 to 100 ft long:
Equipment factor. . . . . . . . . . Le = 0.209(length)o.43\
Labor factor. . ... . .. . L¡ = 0.245(1ength)Ü.390
(YE(L.XUe) + YL(LIXUI))'
PROCESSING-FEED HOPPERS
o
1l
..
CI -- i- f- -- ..
- r-
i- E~i~\
-L.lr
Equipment operating cost. .. y F. = 0.033(Xi-o.344
Labor operating cost.. YI. = O.017(Xro.295 au
UI
(!
Equipment operating costs consist of 88% parts, 6% elec.
!..
ii
tricity, and 6% lubrication. Labor operating costs consist
entirely of repair labor.
~ 0.00110 100 1 ~OOO
ir
PROCESSING-JIG CONCENTRATORS
t:
Operating Cost Equations: These equations provide
jig concentrators. Costs
the cost of gravity separation using 5 100.000
c
~- .,
~
are reported in dollars per cubic yard and include the .: , .
openiting cost of the jigs and associated drive motors. The "C - I
~
equations are applied to the following variable: ~ 10.00 "' .. --.
I
_.
o - ~- ,
x = Maximum cubic yards of feed handled hourly "C
\,
by jig concentrators. o "- n
:i
o 1.000
The base equations assume the following: D
~
o "
1. Cleaner service. 4. Slurry density, 40% \,
..
2. Hourly capacity, 0.617 solids. a. ;;"' ~
yd3/ftz. 5. Gravity feed. E 0.100
3. Feed solids, 3,400
lb/yd3.
II
o
~ "-
i~l
"C "\ ,
I-
¡g 0.010
Base Equations: u
Equipment operating cost. .. y = O.113(X)-o.328
l.
~
l-
ll
- - I
Supply operating cost. .. .. Y:;: O.002(XtO.I84 ir ~Ii..1,000.0
~ 0.0°'0.1 1.0 10.0 100.0 I
Labor operating cost.. . " Y L = 3.508(X)-i.26S
CRPClTV. rri lf cuic blcres of feed treeled per hi:l.r
Equipment operating costs consist of 40% parts, 34% elec-
tricity. and 26% lubrication. Supply operating costs consist Processing cpa~Ql¡ng oost$ - 1 ig cotrQtQ~5
entirely oflead shot for bedding materiaL. Labor operating
costs consist of 66% operator labor and 3~% repair labor.
Rougher-Coarse Factor: If jigs are' to be used for
rougher service or a coarse feed. higher productivity wil
be realized. To compensate for this situation, the following
factor must be applied to total operating cost:
F R = 0.344.
PROCESSING-SLUICES .
Operating Cost Equations: These equations provide "0
! 1.00
the cost of gravity separation using sluices. Costs are o
~
reported in dollars per cubic yard of feed and consist en- -~
tirely of the expense of periodic concentrate cleanup. The
equation is applied to the following variable:
tl"
~
-o
~ , ..
x :: Maximum cubic yards feed handled hourly tl~
by sluice. g, 0.100
o "'
The base equations assume the following: Ì'
1. Steel plnte 4. Length.to.width ratio,
~
~ ....
~,
"
construction. 4:1. 0-
Il
~
2. Angle iron rimes. 5. Gravity feed. C
3. Feed solids, 3,400 = 0.010
o .. ..i.,
"0
lb/yd'.
,.Ul
Base Equation: au
ci
z
Labor operating cost. . Yi, '" 0.337(Xi-o.6:1/ ..
PROCESSING-SPIRAL CONCENTRATORS
r
"" I
clude the operating cost of the spirals and s1 urr splitters ." r- i
'- =:
D -- ---" -
only. The equations are applied to the following variable: .!
'ö 0.100 - -
1-
x = Maximum cubic yards of feed handled hourly tl - - - tsfo r-- +- .
--
by spiral concentrators.
L
a
:i --+
.. ..i.. fo-
I)
Equipment operating co consist entirely of parts. Labor CFlTY. mai_ a.ic yards or fee treated per hor
operating costs consist entirely of operator labor, with the PMOsing ~rating cats - Spiral conentrolors
operator performing functions such as lining replacement.
Cleaner-Scavenger Factor: If spirals are to be used
for cleaning or scavenging, throughput is reduced. The
following factors must be applied to respective operating
costs:
Equipment factor C. = 2.429
Labor factor . . . . . . . . . . . . .. C1 = 1.796
PROCESSING-TABLE CONCENTRATORS
ì ~
" j
X == Maximum cubic yards of feed handled hourly n. i
' .
, .
g, 1.00
by table concentrators. ~ I i I i
" J "' i
.. r
The base equations assume the following;
1. Cleaner service. 3. Slurry density, 25%
2. Feed solids, 3,400 solids.
-9
u
ø
(l
II
i
I "'
~ i
,..~; ""
Ii
r I ¡
bulldozer.
F Ð = 0 .00581(distance)O.90.
PROCESSING-TAILINGS REMOVAL-DRAGLINES
~
.
"-
I'
t-
t'
I-
overburden, and tails moved hourly by
dragline.
.
\.
a.
~ 0.100
~, .. ecli-l
"~
the cost of removing and relocating tailngs using wheel- "0
L \.
type front-end loaders. Costs are reportd in dollars per ?
cubic yard of tailngs moved. The equations are applied to ~
the following variable:
~
..
X = Maximum loose cubic yards of pay gravel,
~ r- "-- -
overburden, and tails moved hourly by
front-end loader.
F 0= O.023(distance)O.616.
F G =O.877e1o.046Cpercent gradientll.
t- I L.Lr
2. Loader cycles to fil, 4. 5. Rolling resistance, 2%, In
oU
3. Effciency, 50 minlh. nearly level gradient.
l:
~
Base Equations: t-
li
Equipment operating cost. . Y r. = O.602(x)-a.296 &
Labor operating cost .. Yi. = 11.34(X)-O.891 0.010 100 1,000
10
CFITY. in i m. I 00_ cu i e IPrds po'" har
Equipment operating costs consist of 28% parts, 58% fuel
and lubrication, and 14% tires. Labor operating costs con- Pro....lng op.."iting costs' Tal' Ing r""vol - F!lor-ii trus
sist of 82% operator labor and 18% repair labor.
FI)=O.093(distance)O.:IJ i.
PROCESSING-TAILINGS REMOVAL-SCRAPERS
F G = O.776eIO.007(pe..eni gtadi"ntll.
PROCESSING- TROMMELS
iJ
Oprating Cost Equations: These equatíons provide 3 0.100
the cost of processing gravel using trommels. Costs are CI
.. i'
'"
reported in dollars per cubic yard of gravel handled. The ..~
~ ~ r-
"0
equations are applied to the following variable: '"
.!
¡.
x '" Maximum cubic yards of gravel procssd Õ
~ r- ..i.
¡-
hourly by trommels. tI
~
Ba Equations: -8
PROCESSING-VIBRATING SCREENS
II
Operating Cost Equations: These equations provide lJ
~ 0.100
the cost of processing gravel using vibrating screns. Costs I I I
~
are reported in dollars per cubic yard of gravel handled. The ~ I
equations are applied to the following variable: lJ
'"
i
~ i I I
x = Maximum cubic yards of gravel processed a
hourly by vibrating screen. u'-
o
:i
~¡ .. i",.
I
capacity. lb/yd3. o
o
lJ
I ""
4. Gravity feed.
.. 'LJ.r
Ul
Base Equations: ou
~
Equipment operating cost. .. Y E = O.104(X)-0,426 ..
Labor operating cost. .. Y L = 0.106(X)-o.57o ~a.oOlla 100 1,000
Ir
ir I
Equipment operating costs average 73% parts, 19% elec- CFACITY, mci", cuic yards of fse trsotsd per hour
tricity, and 8% lubrication. Labor operating costs consist Procsssing operating costs Vibrating screes
entirely of maintenance and repair labor.
Capacity Fac~or: If anticipated screen capacity is other
than 0.624 ft3/yd3 hourly feed capacity, the respective
operating costs must be multiplied by factors obtained from
the following equations:
Ce ;; 1.267(C)O.5i,
and
C¡ = 1.207(C)O.458,
SUPPLEMENTAL-EMPLOYEE HOUSING
Operating Cost Equation: This equation furnishes the 1.00 -- .-- _._ _n
o
for foo, supplies, water, heat, and electricity are all taken .g
into account. The equation is applied to the following o
variable: m
~
o
o
Ì' ..
x = Average loose cubic yards of overburden and ~
'"
c.
"" "'
pay gravel handled hourly. ~ 0.100
o Ì'
The base equation assumes the following: '-
"- "5ulj-
o
lJ
1. Shift, 10 h.
~-
m
ou
Base Equation: Cl
~
Supply operating cost. . Ys = 1.445(X)-O.58J l-
e!
ir
UJ
Cl
Supply operating costs average 95% industrial materials o
and 5% fueL. 0.010
10 100 I ,ODD
CFCITY. averc: 'ooe o. ic i,rd IX
Food Alowance Factor: If workers ar to pay for foo gravel plus overb..de. mined per hcr
and supplíes out of their own pockets, the cost calculated
Si I em to I op rat i ng CO ts - Eri i O'.. hc i ng
from the above equation must be multiplied by the follow.
ing factor:
F F :: 0.048:'
The total cost per loose cubic yard must then be multiplíed
by the total yearly amount of overburden and pay gralJel
handled. This product is subsequently entered in the ap.
propriate row of the tabulation shown in figure 6 for final
operating cost calculation.
OPERATING COSTS 73
SUPPLEMENT AL-GENERATORS
Operating Cost~ Operating costs of diesel generators account for the expense of electricity brought in through
are accounted for in the electrical portions of the other transmission lines if diesel generators are not used. This
equipment operating costs. By so doing, operating costs of is at best an approximation. However. costs assigned in this
the generators are tied directly to size and type of equip- manner are typically more representative than. costs
ment used. calculated by trying to estimate the total power consump-
The electrical portions of operating cost curves wil also tion of an operation.
74 OPERA TING COSTS
r:
for costs not directly related to production. Costs are tl~
reported in dollars per cubic yard. Items in this section 0
:J
include: u
i
i
L Equipment downtime.
~u o ..
i- ....
a. Productivity lost by the entire crew due to
breakdown of key pieces of equipment.
b. Productivity lost by individual operators due to
breakdown of single pieces of equipment.
'"
"0
~
~
'"
a.
.. 0.100
~ .. E~iønt
,
l_.
~
c. Labor charges of outside maintenance personneL.
~
d Wash plant relocation.
B
2. Site maintenance. ,:
In
a Road maintenance. B
b. Stream diversion. LI
~
c. Drainage ditch construction and maintenance. t-
ci
a:
d Site cleanup. w
e. Reclamation grading and recontouring. ~
f. Settling pond maintenance. 0.010
10 100 1,00
MILL CflTY. ""inu cùic yaeds of feed teeated pee hour
3. Concentrate refinement.
a Time spent recovering valuable minerals from mil S4lemlal apeealir- cosl" - Lost time c:d geral seevices
concentrates by panning, mechanical separation, or
amalgamation.
The equations. are applied t.o the following variable:
X = Maximum cubic yards of feed handled hourly
by mil.
Base Equations:
Equipment operating cost. . Y E = O.142(Xio.oo
Labor operating cost Y1: '" 2.673(Xi-O.524
YE + YL
SUPPLEMENTAL-PUMPS
/V
/
pump use. If more than one pump is used in the operation. i
a separate cost must be calculated for each. The equations a /' E(l'..t
are applied to the following variable: í:
..
V
"
x = Maximum gallons of water required per
~ 1,,00
II
..
/
minute. C
/..
/'
,/
The base equations assume the following:
1. Total head, 25 ft. 3. Abrasion-resistant
-8
..In
o
U
~
2. Diesei.powered pumps. steel construction. ~ 0.10 ~~
4. Total engine-pump ef. .. ./
ficiency, 60%. ~
~
-g
'"
Base Equations:
Equipment operating cost. . Y E = 0.007(X)O.7!
Labor operating cost .... . Y!. = 0.OO4(X)O.867 0.0110 100 1.000 10,000
F' CACITY, fI i nu gal Ions pei- m; i-ts
Equipment operating costs average 59% fuel and lubrica.
tion, and 41% parts. Labor operating costs consist of 82% Sup I emlal opi-at ing costs - Pus
operator labor and 18% maintenance and repair labor.
(Operator labor includes pipeline work.)
and
Hi = 0.054(H)o.893
The total cost per hour must then be multiplied by the an-
ticipated hour per year of pump use. This product is subse-
quently entered in the appropriate row of the tabulation
shown in figue 6 for final operating cost calculation.
76
Item Cost
Exploration:
Method 1 cost ....... .......... ....... $
Method 2 cost . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , . . . . . . . . . . . . . .
Development:
Access roads ... . . . .. . .
Clearing. . . . .. " . ..
Preprouction overburden removal:
Bulldozers. . . . . . . . . . . . . . . . . . . . . . . . . . . _ . . . .. ............
Draglines. " ..... . .. .. . . . . ., ..........,..........
Front-end loaders ........... " ...........
Rear-dump trucks .,. " .. . .. .
Scrapers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. ..... ...... .
Mine equ ipment:
Backhoes .... . . .. ....... ..... ...................
Blolldozers " . .. . " .
Dragllnes. . . . . . . . . . .. . .. ... .., ,., ., .. .
Front-end loaders ......... ............. .. " ...... . "
Rear-dump trucks .,................................. .........
Scrapers.. ,.,.. .............. .... ......................
Processing equipment:
Conveyors.. ...... " . . . . . . . .... .. ... .. . . . .. .. . .
Feed hoppers. , . . . . . , . . . . . . . . . . . . . .. ..... ..... ......
Jig concentrators. . . . . , . . . . . . . . . . . . . . . . . . . . . , . . . . . . . . . . . . . . . . . .
Sluices .. .. .. ..... .... . ... ...........................
Spiral concentrators . . .. . .., ., .. .. " .. . .,
Table concentrators. .. .. . ., .... . . .. " .... .. .
¡rammels . . . . . . . . . . . . . . . . . . . . . . . . .. ...................,... .
Vibrating screens, . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . _ . .. .......
Supplemental:
Buildings, .,... , . . . . . .. ..... ..... .....,.,.,.."..
Camp. . .. . .. .... .....,
Generators .. . ......... . .... ........ ...... .....
Pumps. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Settling ponds .. . . .. ................ .....
Subtotal .. . ., . . .. " .. . ... ,. .,. . ....
Contingency (10%) .. .. ..... .... .. .. .., ..... '" .
Total...... ..... .... .......... ............. .. " .. .
Cost per cubic yard pay gravel = total annual cost divided by pay gravel mined per year.
Final cost per cubic yard pay gravel.. .,. . ., . 0
BIBLIOGRAPHY
Caterpilar Tractor Co. Peoria, IL. Caterpilar Performce Hand. Richardson Engineering Services, Inc. (San Marcos, CA). Procss
bok. 15th ed., 1984, 600 pp. Plant Construction Estimating Standards. Periodically updated.
Dataquest Inc. Cos Reference Guide for Construction Equipment. Schumacher, a.L. Mining Cost Service. Western Mine Eng.,
Equipment Guide Book Co., Palo Alto, Ca. Periodically upated. Spokane, W A, periodically updte.
Gofrey, R.S. Means Building Construction Cost Data, 1985. Terex Corp. (Hudson, OR). Prduction and Cost Estimating of
Robert Snow Means Co.Inc., Kingston, MA. 43d ed., 1984,455 pp. Material Movement With Earhmoving Equipment. 1981, 78 pp.
Marshall and Swift (Los Angeles, CAl. Marshall Valuation Serv-
ice. Periodically updated.
79
Parameters
General: Mining:
150 operating dJa. Excavation by 1 backhoe.
10 h/shift. Hauled by 2 front-end loaders.
ioO-LCYIh pay gravel capacity. ioO-LCYIh production capacity.
2.5-LCY stripping ratio. Medium-hard digging.
150,000 LCY/a pay gravel mined. length.
800.ft average haul
375,000 LCY/a overburden removed. +6% average haul gradient.
Workers live on site.
Exploration: Mine equipment:
20 worker.days reconnaissance. 1 new backhoe.
1,400 ft chur driling. 1 used bulldozer.
2,000 yd' trenching 2 new front-end loaders.
1,200 samples panned. 1 used scraper.
8 h helicopter time.
180 worker.days camp requirements.
.
Trommel, 100 LCYIh.
Forested. Rougher jig, 20 yd3/h.
22 ft wide. II Cleaner jigs, 2 at 5 yd3/h.
Ungraveled. Final jig, 0.2 yd"/.
6 acres cleared. Scavenger sluice, 50 yd3/h.
Forested. Scavenger sluice, 20 yd3/h.
10% side slope. Conveyor, 70 yd3/h, 40 ft.
Overburden removal: Tailngs placement:
Excavated and hauled by 1 scraper. Transportd using 1 bulldozer.
250-LCY/h production capacity. 100-LCY/h production capacity.
330,000 LCY prior to production. 400.ft average haul length.
3,000-ft average haul distance. -8% average gradient.
+8% average haul gradient.
Mine-run gravel
(100 yd3/h)
Ovenize
(25 yd3/h)
Waste
Waste (20 yd3/h)
Waste Sluice
Concentrate
(0.01 yd3/h)
Concentrate
(0.1 yd3/h)
Concentrate
(0.03 yd3/h)
Dump
Gold product
CAPITAL COSTS
Overburden removal capital cost = (($0.100 x 1.060) + ($0.073 x 1.019)) x 1.975 x 1.130 x
30,000 ...........................,............... ... ..... $12,077
Equipment price.. " . .. " . . .. . " . " . " . .. .. . " " .. . $2,458 x 0.62 x 1..005 ;: $1,532
Installation labor. . . . . . . . . . . . . , . . . . . . .$2,458 x 0.12 x I.025 302
Construction materials... .... . $2,458 x 0.26 x 1.015 649
Item Cost
Exploration:
Method 1 cost. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. $
Method 2 cost. . . . . . . . . . . . . .. ... ............................... 94,485
Development:
Access roads . . .. ... ...... . ...... . . . . 88,180
Clearing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. .... .. . .. . 9,725
Preproduction overburden removal:
Bulldozers .. . .. .. .... . . . . . . . . . . . . . . . . . . , .
Draglines. .. .. .." . .. . .. . .. . . .. ............
Front-end loaders . . . . .. ... . .. .. .... . ......... .
Rear-dump trucks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , . . . . . . . . . . . . . . . .
Scrapers ....................................................... 12,077
Mine equipment:
Backhoes. . . . ... ... .... ... ., .. .. .. . ... . .. ,. 266,792
Bulldozers . . . . . . . . .. ...................... .. .. . .., . .. .. 69,022
Draglines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , , . . . .
Front-end loaders. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , . . . 272,207
Rear-dump trucks. .. .. . .. .. .. .. .. .. ..... . ......
Scrapers ............................ .. .. .. .. . ... .. . 200,817
Processing equipment:
Conveyors . . . . . . . . . . . . . . . . . , . . . . , . . . . . . . . . . . . . . . . .. ........ .. 16,115
Feed hoppers. .. ............................................., 4,022
Jig concentrators. .. .. .. . .. .. . .................... 56,601
Sluices. .. .. .. .. .. .. . ..... .. .. . .. ., . . . . 1,700
Spiral concentrators.. .. .. . ... ... ......... . .. ..
Table concentrators. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Trommels ...................................................... 95,221
Vibrating screens. .. .. .. .. .. .. .. .. .. ...................
Supplemental:
Buildings . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , , . . . . . . . . . . . . . . . . . . . . .. . 41,994
Camp.......... ................ .........,... .... ............ ... 51,476
Generators ... . . .. .. . .. .. .. .. ... . . . . . . . . . . . . . . . . . . . . 22,530
Pumps. .. . . . , . . .. .. . .. .. .. .. . . . .. . .. .. . 10,308
Settling ponds .................................................. 3,360
Subtotal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,316,632
Contingency (10%) .... . . . . . . . .. ..... . . .
Total... .. .. .. .... ..... .................
131,663
1,448,295
OPERATING COSTS
Overburden removal cost. . . . . . . .. . . . . . . . . . . . .((0.100 x 1.060) + (0.073 x 1.019)) x 1.975 x 1.130 = $0.403/LCY
Annual scrape~ operating cost = $O.403JLCY x 375,000 LCY/a $151,125
Annual feed hopper operating cost = $O.Oll/LCY x 150,000 LCY/a . . .". $1.650
90
Annual cleaner jig operating cost = $O.5351yd3 x 15,000 yd3/a. 'l .... $8,025
91
.
Supplies. . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . Ys = 0.002(0.2)-0.184 $0.003/yd'
Industrial materials. . . . $0.003 x 1.00 x 1.003 $0.003
Labor . . . . .. ... ... .... ... ... . .' YL = 3.508(0.2)-1.268 $26.999/yd3
Labor . . . . .$26.999 x 1.00 x 1.025 $27.674
Final jig operating cost = (0.193 + 0.003 + 27.674) = $27.870/yda
Annual final jig operating cost = $27.870/yd3 x 300 yd3/a .
Tailngs removal cost = ((0.137 x 1.36) + (0.185 x 1.036)) x 1.307 x 0.923 = $0.419ILCY
Annual bulldozer operating cos = $O.4;t9/LCY x 150,000 LCY/a . . . . . . . . . . . . . . . . . . . . . . . . $62,850
Annual lost time and general service cost = $0.389/LCY X 675,000 LCY/a . $262,575
Overburden removal:
Bulldozers .. . , " _. ..... $
Draglines .. .. . " .. .
Front-end loaders. .. ....... . . . . . .. ........
Rear-dump trucks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 151,125
Scrapers .............. ......... ..............................
Mining:
Backhoes .. .... ... . . .. . .. . . . ... . . . .. . .. .. 73,650
Bulldozers.. .... .. ..... ... . . . . . . . . . . .. . . .. ..
Draglines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Front-end loaders. . . . . .. ......... ... ..... '.' .................. 124,650
Rear-dump trucks. .. .. .. ., .. . . . .
Scrapers . .. . .. .... .... .. . .. ... . . . .. . .. ... . ..
Processing:
Conveyors. . . . . . . . . . . . . . . . . . . . . " .............................. 3,465
Feed hoppers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,650
Jig concentrators. " .. .. . . . ... . .. .., . " 17,676
Sluices .. . ..... . ..... . . .. ... .. '" . .. .. ... . . . 4,110
Spiral concentrators. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Table concentrators. . . .. ......... ..............................
Tailngs removal:
Bulldozers . .. . .., . . . . . '. .,. ......... . 62,850
Draglines .. . " ., . " .. ..... " . ..
Front-end loaders . . . . . . . . . . , . . . , . . . . . . . . . . , . . . . . . . . . . . .. ......
Rear-dump trucks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Scrapers. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , . . . . . . . . . . . . .
Trammels ..... ........ . ...... . . .. '" ..................... 7,950
Vibrating screens .. .... .. .... .. ...... . .. ., .... . " ..
Supplemental:
Employee housing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24,675
Lost time and general services. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 262,575
Pumps .. . . . . . . . . . . . . .. ... .... 11,319
Subtotal .. . . .. . '" ... ..... . 745,695
Contingency (10%) ..... ..... . ....................... .......... 74,570
Total......,....... .......................................... 820,265
-
Cost per cubic yard pay gravel == total annual cast divided by pay gravel mined per year.
Final cost per cubic yard pay gravel " ... ~ . . . . . . . . . . . . . . . . . . . . . . . . . $5.47