The New Construction Act

2011

LOCAL DEMOCRACY, ECONOMIC DEVELOPMENT AND CONSTRUCTION ACT 2009 THE NEW CONSTRUCTION ACT A GUIDE TO THE CHANGES

FC Construction

The New Construction Act


2011

Today: Reviewthechanges Consider what they mean for Mansell anditsbusiness

AmyMorley Partner FreethCartwrightLLP

The New Construction Act


2011

Somecontext...
Housing Grants, Construction and Regeneration1996(theOldAct). Amended by Local Democracy, Economic Development and Construction Act 2009 (the NewAct). NewSchemeforConstructionContracts. No opting out for qualifying construction contracts.

The New Construction Act


2011

When:
Appliestoallcontractsenteredintoafterthe effectivedate. 01October2011(EnglandandWales) 01November2011(Scotland)

Contracts that are entered into before the effectivedatewillcontinuetooperateunder theOldAct.

The New Construction Act


2011

Summaryofchanges: Adjudication: Oralcontracts; Costs; SlipRule. PaymentNotices: Section 111 Withholding Notices are replaced; PaywhenCertifiedunenforceable; NewPaymentNoticeregime; Introduction of Notified Sum for payment.

The New Construction Act


2011

Section110APaymentNotice Payment Notice required in respect of any payment. Contract must nominate who will serve the Notice:
Payer; SpecifiedPerson; Payee.

Noticemustbeservedwithin5daysofthedue date.

The New Construction Act


2011

Section110APaymentNotice Mustsetoutthesumdue. Must set out the basis on which it is calculated. Whatdoescalculatedmean. Notice required even if the amount is 0. The amount identified in the Notice becomestheNotifiedSum tobepaid.

The New Construction Act


2011

NopaymentNoticeserved? The New Act provides for a party receiving paymenttoserveaDefault Notice. WhataretherequirementsofaPayeeNotice indefault? Mustidentifythesumdue. Setoutthebasisonwhichitiscalculated. Incentivetoserveearlyduetopostponement ofthefinaldateforpayment.

The New Construction Act


2011

PayeeNoticeindefault Ifthepayeeisrequiredtoserveanapplication thenaseparatePayeeNoticeindefaultisnot required. Silentbutdeadly... The amount identified as due in the application becomes the Notified Sum for payment. Unless: APayLessNoticeisserved

The New Construction Act


2011

PayLessNotice NotifiedSummustbepaidcomewhatmay. UnlessaPayLessNoticeserved. Noticemustsetoutthesumdueandthebasis onwhichitiscalculated. Thisbecomesthenotifiedsumtobepaid. AbatementandSetoffbothcovered. ItisnotaWithholdingNotice. Nogroundsforwithholdingtobeprovided?

The New Construction Act


2011

The New Construction Act


2011

The New Construction Act


2011

The New Construction Act


2011

Suspension[Section112] Anyorallcontractualobligations Reasonable cost and expenses incurred as a consequence ExtensionofTimetocoverremobilisation

The New Construction Act


2011

Paywhencertified No longer possible to link performance and the issue of certificates on one contract to paymentunderanother. RetentionandSubcontractors.

The New Construction Act


2011

Insolvency Theoneexceptiontopaywhenpaid The right to withhold payment only if the contractexpresslystatesthisright. Still required to comply with Notice provisions. So must serve a Pay Less Notice if the insolvency is after the Due Date but before thelastdaytoserveaPayLessNotice.

The New Construction Act


2011

Adjudication Contractsnolongerinwriting. Section107oftheOldActnolongerapplies. All the case law on what was and wasnt a contract evidenced in writing no longer applies. Moreadjudication? Increased challenges and uncertainty in dealing with oral/part oral contracts in adjudication.

The New Construction Act


2011

Adjudication The Agreement to refer disputes to adjudicationmustbeinwriting. IfnotthentheSchemewillapply. Adjudication Agreement must include a slip rule. IfnoslipruleisincludedthentheSchemewill apply.

The New Construction Act


2011

AdjudicationCosts TheOldActsilentoncosts. NewActsaystheAdjudicatormustbeableto decidewhowillpayhisfees. Only exception is if an agreement is made in writingafter thegivingofaNoticeofIntention toRefertoAdjudication. Parties still able to allocate who should pay partycosts e.g.consultantorlawyertime. So called Tolent clauses only enforceable if they refer generically to Referring Party or RespondingParty.

The New Construction Act


2011

NoticeProvisionsandcalculatingtimeperiods Expresscontractualprovisionsonservice:
How? Where? When?

Expect any tribunal will uphold express provisionsinthecontract. Ifthecontractissilent:


TheOldActapplies

The New Construction Act


2011

Reminder of the Old Act provisions on Service Method:


Byanyeffectivemeans Timerunsfromreceipt Considerhowyouevidencereceipt Recordeddeliveryandfax Email
Outofofficereplies Deliveryfailures

The New Construction Act


2011

Calculatingtimeperiods TheOldActprovisions: When a period of days is specified then time begins to run immediately after the point in action e.g. if Notice of Suspension is to be
given(7daysisrequired)theniftheNoticewasreceivedon Monday the 7 days starts on Tuesday and suspension can takeplaceonthefollowingTuesday.

BanksHolidaysarenotcounted.

The New Construction Act


2011

Materialsavailable: TheNewConstructionAct FCGuidetotheChanges. LegalSurgerydayinyourBusinessUnit. Mansells Subcontract Conditions (amended to provided for SubcontractorserviceofthePaymentNotice) Mansell NEC Subcontract amendments with update to provide for the New Construction Act and Subcontractor service of the PaymentNotice. JCT Design & Build Subcontract 2011 version with bespoke amendments to provide for Subcontractor service of the PaymentNotice. JCT Standard Building Subcontract 2011 version with bespoke amendments to provide for Subcontractor service of the PaymentNotice. Track changed copy of the Old and New legislation to identify thechangesmade.

The New Construction Act


2011

Thankyouforyourtime