ID 1 2 Activities
Security
Time Scale
62 days
Start
Mon 14/02/11 Mon 14/02/11
Finish
Mon 16/05/11 Mon 28/02/11
06 Dec '10
10 Jan '11
14 Feb '11
21 Mar '11
25 Apr '11
30 May '11
04 Jul '11
3 4 5 6 7 8
Submission of updated security plan 11 days to reflect requirements of the delivery proposals for the Mandatory Work Activity Independent CESG penetration test 4 days Review and implementation of new policies and procedures required (ISO27001 Standard) FIPS 140-2 Encryption software introduced Submission of final security plan 5 days
Nettitude Regional Compliance Manager Regional Compliance Manager Regional Compliance Manager 6 DWP
Nettitude Regional Compliance Manager Regional Compliance Manager Regional Compliance Manager DWP Regional Compliance Manager
4 days 1 day
9 10
Approval for access to PRaP 1 day information / Final security plan sign off Implementation of new policies and 5 days procedures required from penetration test and final security plan sign off Case Management System and 62 days
Thu 28/04/11
Fri 06/05/11
Installation
Initial commencement of the 1 day development of Case Management System (CMS) including Customer Relationship Management (CRM) Process map and formal procedures 15 days developed BETA walk through testing of CMS 5 days Additional systems licences for BEST Pre go live role play week and final sign off 1 day 2 days 25 days 1 day
11 12 13 14 15 16 17 18
Mon 04/04/11 Mon 09/05/11 Tue 12/04/11 Thu 12/05/11 Wed 06/04/11 Wed 27/04/11
Fri 22/04/11 Fri 13/05/11 Tue 12/04/11 Fri 13/05/11 Mon 16/05/11 Wed 27/04/11 10 12 13
Data Information Manager Data Information Manager Cognisoft Implementation Manager Human Resource Manager,Regional Compliance Manager Operations Director
Human Resource Manager,Regional Compliance Man Operations Director Operations Director Operations Director
11 days
Wed 13/04/11
Fri 29/04/11
39
Operations Director
5 days
Mon 09/05/11
Fri 13/05/11
39
Operations Director
19 20 21
22
5 days
Thu 28/04/11
Fri 06/05/11
23 24 25 26 27 28
Premises
1 day
Health and Safety vetting of each 4 days centre, including subcontractor sites
DCO
Staff Training
Training needs analysis of BEST Creation of training packages and resources Job matching from current post to new posts
Mon 16/05/11 Fri 22/04/11 Fri 06/05/11 Fri 29/04/11 26 Human Resource Manager Human Resource Manager
Human Resource Manager Human Resource Manager Start Activity Finish Activity Page 1 Activity Progress
Finish
Fri 06/05/11 Tue 10/05/11 Fri 13/05/11 Mon 16/05/11 Fri 13/05/11 Fri 06/05/11 Tue 10/05/11 Fri 13/05/11 Mon 16/05/11 Fri 01/04/11 Thu 28/04/11 Fri 06/05/11
06 Dec '10
10 Jan '11
14 Feb '11
21 Mar '11
Workshops for placement providers 2 days partners and BEST staff Webyeti IT training for case 2 days management system for BEST Pre go live role play week 4 days
04 Jul '11
Regional Compliance Manager,Human Resource Man Business Development Manager Business Development Manager Business Development Manager Business Development Manager DWP DWP DWP,Managing Director 06/05 16/05 06/05 06/05 13/05 16/05
Marketing
Website updates Develop marketing Literature Local stakeholder events JCP awareness campaign
Business Development Manager Business Development Manager Business Development Manager Business Development Manager
Contract Award
Preferred bidder notified Confirmation of Contract Award Signed Contract with DWP and BEST Milestones / Critical Path
Final sign off of Health and Safety at 0 days all premises including sub contractors Sign off of security plan by DWP 0 days Full availability of IT system CMS and CRM Signed Contracts with supply chain Go Live role play for all staff The BEST MWA goes Live 0 days 0 days 0 days 0 days
Fri 06/05/11
Fri 06/05/11
Mon 16/05/11 Fri 06/05/11 Fri 06/05/11 Fri 13/05/11 Mon 16/05/11
Mon 16/05/11 Fri 06/05/11 Fri 06/05/11 Fri 13/05/11 Mon 16/05/11
Activity Progress
15