Beruflich Dokumente
Kultur Dokumente
Report 5
GEOMETRIC EVALUATION
July 2001
Transit New Zealand Heavy Vehicle Limits Project Page 2 of 38
ISBN 0-478-04710-X
Foreword
This report is one of a series of seven that cover the latest investigation of the feasibility of
changing the mass and dimensions of heavy vehicles on New Zealand’s roading system.
Transit New Zealand (Transit) has long recognised the importance of the roading network to
New Zealand’s economy, and the desire amongst the transport and export industry sectors for
increased productivity. To this end Transit has supported investigations since 1992 of the
potential benefits of raising weight limits.
Previous studies lead Transit to the conclusion that is was not feasible to upgrade the whole
road network to accommodate substantially longer heavier vehicles. Accordingly in 1998
Transit commenced the current study with the purpose of considering two new scenarios. We
are grateful to Transfund New Zealand for the provision of funding for the investigations.
These project reports represent the culmination of two years’ work by a group of consultants
both here and in Australia. These are listed below:
Transport Engineering Research NZ Ltd, Auckland
Infratech Systems and Services Pty Ltd, Brisbane
Roaduser International Pty Ltd, Melbourne
Saturn Corporate Resources Pty Ltd, Melbourne
Montgomery Watson NZ Ltd, Christchurch
ARRB Transport Research Limited, Melbourne
Commed Associates, Melbourne
Opus International Consultants Limited, Wellington
Pearsons Transport Resource Centre Pty Ltd, Melbourne
Transit is grateful to the members of the project steering group who have provided expert
guidance and comment on behalf of the following organisations:
Land Transport Safety Authority of New Zealand
Transfund New Zealand
Ministry of Transport
Road Transport Forum New Zealand
Bus and Coach Association New Zealand
Local Government New Zealand.
Robin Dunlop
Chief Executive
Transit New Zealand Heavy Vehicle Limits Project Page 4 of 38
Preface
What is the Transit New Zealand Heavy Vehicle Limits Project?
This report is one of seven issuing from Transit New Zealand’s Heavy Vehicle Limits Project
(HVLP) undertaken in 1999–2000. The full list of reports are:
1. Bridge Evaluation 5. Geometric Evaluation
2. Safety Evaluation 6. Environmental Evaluation(and)
3. Pavement Evaluation 7. Overview
4. Industry Economics
The Heavy Vehicles Limits Project arose out of Transit’s Heavy Transport Routes (HTR)
research project undertaken in 1992-96. As a result of the HTR project, Transit believed that it
was not feasible to upgrade the whole road network to accommodate substantially longer
vehicles. Transit therefore undertook preliminary studies on two scenarios, termed Scenario A
and Scenario B.
Scenario A examined the proposal that the existing vehicle fleet would be allowed to operate
at different weight limits than those presently permitted on the road network but there would
be no increase in vehicle dimensions.
Scenario B examined the proposal that increases in both vehicle weight and dimension limits
would be allowed on selected routes only.
These issues were considered in a preliminary study for Scenario A undertaken by Pearsons
Transport Resource Centre P/L. The work was divided into heavy vehicle weight
investigations and road user charges investigations. The findings were provided in a report
entitled Scoping Study for Scenario A.
Preliminary work on Scenario B for three specific routes by Opus International and Allan
Kennaird indicated that significant benefits would flow from network improvements giving
rise to higher weights and dimensions on these routes.
The Ministry of Transport undertook a separate investigation of road user charges.
As a result of the preliminary studies, the goal of the Heavy Vehicle Limits Project was to
evaluate the safety and economic effects of altering heavy vehicle weights on the entire road
network (Scenario A) and of increasing both heavy vehicle weights and dimensions for
selected routes only (Scenario B).
The general approach of the Project was to consider the effects of increasing allowable
weights on bridges, safety, pavements and industry economics. These issues were common to
both scenarios. In addition, an investigation was required of geometric issues for Scenario B
only. Separate contracts were let for evaluating the different areas. Also required were an
overview of the project with recommendations, and a separate summary with
recommendations.
In some cases, detailed data not published in the reports is available on diskette or CD ROM
upon request from Transit New Zealand. Details of the Scenario B network of routes are
included in Report 5, Geometric Evaluation. Readers not wishing to pursue the detail of the
project may be satisfied with Report 7, Overview alone.
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 5 of 38
Project Team
Acknowledgements
We would like to thank the following companies and individuals for their support and
assistance in carrying out the Geometrics Evaluation for the Heavy Vehicle Limits Project.
Contents
Project Team 5
Acknowledgements 5
List of Figures 7
List of Tables 8
Executive Summary 9
1. Introduction 11
2. Method 12
2.1 Outline of the Tasks...................................................................................................... 12
2.2 Developing the assumptions......................................................................................... 12
2.2.1 Road width, road edge, and curve widening 12
2.2.2 Preliminaries for the curve investigation 14
2.2.3 Alternative assumptions for the curve investigation 15
2.2.4 The effect of increased trailing infidelity 15
2.2.5 Preliminaries for the roundabout investigation 16
2.3 Method of analysis for the curve investigation .......................................................... 18
2.3.1 Models used to determine offtracking 19
2.3.2 Model validation 20
2.3.3 Costs of road widening in various terrain 22
2.3.4 Calculating the cost of modifying a curve 24
2.4 Method of analysis for the roundabout investigation................................................ 28
2.4.1 Details of the method for determining the cost of modifying a roundabout 28
2.4.2 Costs for the three representative roundabouts 29
3. Results and Discussion 34
3.1 The network of routes................................................................................................... 34
3.2 Results for the curve investigation .............................................................................. 35
3.3 Results for the roundabout investigation.................................................................... 36
4. References 38
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 7 of 38
List of Figures
List of Tables
Table 1. Estimated cost (in millions of dollars) for modifying curves and roundabouts on the
network of routes.............................................................................................................. 10
Table 2. Maximum offtracking observed for vehicles travelling in a straight line. ................ 16
Table 3: Major vehicle dimensions. ........................................................................................ 21
Table 4. Cost of widening road by 0.5 metres. ....................................................................... 23
Table 5. Cost of widening road by 1 metre. ............................................................................ 23
Table 6. Cost of widening road by 1.5 metres. ....................................................................... 24
Table 7. Cost of modifying the representative roundabout with 34 metre diameter central
island. ............................................................................................................................... 30
Table 8. Cost of modifying the representative roundabout with 21 metre diameter central
island. ............................................................................................................................... 30
Table 9. Cost of modifying the representative roundabout with 7.8 metre diameter central
island ................................................................................................................................ 30
Table 10. Roads selected for inclusion in the network of routes for the Scenario B vehicles.34
Table 11. Cost of modifying curves on the network of routes for B1233-62b and B1233-62f
for the original set of assumptions. .................................................................................. 35
Table 12. Cost of modifying curves on the network of routes for B1233-62b and B1233-62f
for Alternative assumption set 1....................................................................................... 35
Table 13. Cost of modifying curves on the network of routes for B1233-62b and B1233-62f
for Alternative assumption set 2....................................................................................... 35
Table 14. Costs for modifying roundabouts on the network of routes to accommodate B1233-
62b.................................................................................................................................... 36
Table 15. Costs for modifying roundabouts on the network of routes to accommodate B1233-
62f..................................................................................................................................... 36
Table 16. Costs of modifying the network of routes by Route Sector. ................................... 37
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 9 of 38
EXECUTIVE SUMMARY
This study investigates the amount of road width effectively occupied by vehicles longer than
20 metres and the cost of modifying a specific network of roads and roundabouts in New
Zealand to accommodate these vehicles should they be introduced. There are two reasons
why the longer vehicles may take up more road space than the current fleet; firstly, longer
vehicles are likely to have greater offtracking when cornering. Secondly, the trailing unit of a
combination vehicle travelling in a straight line may not exactly follow the path of the leading
unit due to minor steering adjustments, cross winds and cross slope of the road. This is
known as trailing infidelity. Unlike offtracking, trailing infidelity affects the amount of road
width a vehicle occupies on straights as well as in curves. The increase in trailing infidelity
on straights was predicted to be less than 50 millimetres so the effect of increased trailing
infidelity of longer vehicles was ignored in this study.
Specifically, the purpose of this investigation was to determine the cost of modifying roads
and roundabouts to accommodate each of two trial vehicles, which are longer and heavier
than vehicles currently permitted on New Zealand roads as a matter of course without a
special permit. The trial vehicles are both B-trains and are referred to as B1233-62f and
B1233-62b. B1233-62f has 18.8 metre overall axle spacing and B1233-62b has 22.0 metre
overall axle spacing. These two trial vehicles are 2.5 metres wide, the same width as vehicles
from the current fleet, and B1233-62b was also considered as part of the Heavy Vehicle
Limits Project Safety Evaluation.
The report is in two parts. First, the costs for modifying sections of road, excluding
roundabouts and intersections, are investigated. This is known as the geometric curve
investigation. Secondly, the costs for modifying roundabouts to accommodate the trial
vehicles are investigated. This is referred to as the roundabout investigation. In accordance
with the project brief, intersections along the specific routes not controlled by a roundabout
were not considered.
To determine the costs for modifying the network of routes, the following assumptions were
made:
• The current network of routes is satisfactory for existing vehicles. If a trial vehicle was
found to offtrack x metres more than a vehicle typical of the current fleet on a particular
curve then, to maintain the same clearances, that curve should be widened by 2x.
However, if 2x<0.25 metres, then it was assumed that widening would not be required.
• Also, if 2x ≥ 0.25 metres, then widening would still not be necessary as long as two trial
vehicles travelling in opposing directions could pass with 1 metre clearance between their
swept paths and 0.5 metres clearance to the edge of the road.
To test the sensitivity of the cost to these assumptions, four alternative sets of assumptions,
Alternatives 1 to 4 were considered.
Alternative 1 was that
• The current network of routes is satisfactory for existing vehicles. If a trial vehicle was
found to offtrack x metres more than a vehicle typical of the current fleet on a particular
curve then, to maintain the same clearances, that curve should be widened by 2x.
However, if 2x<0.15 metres, then it was assumed that widening would not be required.
• Also, if 2x ≥ 0.15 metres, then widening would still not be necessary as long as two trial
vehicles could pass with 2 metres clearance between their swept paths and 1 metre
clearance to the edge of the road.
Transit New Zealand Heavy Vehicle Limits Project Page 10 of 38
Table 1. Estimated cost for modifying curves and roundabouts on the network of routes.
Assumption set Cost for B1233-62b Cost for B1233-62f
Original Assumptions $43,600,000 $18,800,000
Alternative 1 $132,000,000 $44,700,000
Alternative 2 $214,000,000 $62,600,000
Alternative 3 $161,900,000 $113,500,000
Alternative 4 $292,100,000 $191,100,000
Cost for roundabouts $1,284,000 $1,173,000 .
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 11 of 38
1. INTRODUCTION
This investigation considered the modification of curves and roundabouts required for the
network of routes proposed by Transit New Zealand in the project brief to accommodate
vehicles that are longer and heavier than those currently permitted on New Zealand roads.
Two trial vehicles, longer and heavier than those allowed under current laws, were
investigated; a B-train with 22.0 metre overall axle spacing and a B-train with 18.8 metre
overall axle spacing. Two vehicles, typical of the current fleet, were used to provide a
benchmark against which the trial vehicles could be compared. The two benchmark vehicles
were a tractor semi-trailer with 13.1 metre overall axle spacing and a B-train with 16.0 metre
overall axle spacing. Details of these four vehicles are provided in Appendix A.
Transit New Zealand Heavy Vehicle Limits Project Page 12 of 38
2. METHOD
2.1 Outline of the Tasks
Seven tasks were specified in the project brief. These tasks culminated in finding the cost of
geometric modification of the network of routes. Briefly, the seven Tasks were
Task 1. To develop an analysis tool, describing the relationships between curve geometry
and offtracking for the two trial vehicles and two benchmark vehicles, typical of the
current fleet. Also, it was required to develop a tool to estimate the cost of widening
sections of road to accommodate the increase in offtracking.
Task 2. To finalise the network of routes.
Task 3. To compile an inventory of geometric information for each route.
(Task 7). To conduct a survey to confirm the assumptions regarding the cross sections of road
and adjacent country (including terrain slopes and soil types).
Task 4. To validate the method of modelling the vehicles by experiment using a B-train.
Task 5. To determine the cost of geometric modification of the network of routes.
Task 6. To write this report.
Assumption 1
While the current network of roads is generally satisfactory only for existing vehicles, in
practice it is unlikely that curve widening would be undertaken where the calculated required
widening is less than 0.25 metres (equivalent to 0.125 metres on each side of the road).
From Assumption 1, if a curve was found to require widening by an amount less than 0.25
metres then it was assumed that widening would not be carried out. However, if the
offtracking of a trial vehicle was found to be significantly greater than the offtracking of the
worst of the benchmark vehicles then Assumption 2 provided the foundation for the
specification of the required road width for such a curve.
Assumption 2
If a curve is such that the trial vehicle takes up significantly more road width than the
benchmark vehicles representing the existing fleet (Assumption 1 specifies 0.25 metres as
significant) then the amount of road width is unsatisfactory unless two trial vehicles,
travelling in opposite directions, can pass with 1 metre clearance between their swept paths
while each vehicle remains at least 0.5 metres from the edge of the road.
The 0.5 metres provided at the edge of the road was chosen to allow for two effects; firstly
driver variation, and secondly avoidance of excessive edgebreak problems for unkerbed roads.
The 1 metre clearance allowed between the swept paths of opposing vehicles was provided to
allow for driver variation. Note that if there were to be provision for cyclists, at least 1.5
metres clearance between the path of a truck and the edge of the road would be required.
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 15 of 38
Since a negligible proportion of the routes will have provision for cyclists, the cost of this
widening has been ignored.
If there was to be road widening to allow for increased trailing infidelity, straight roads as
well as curves may require modification as it is more difficult to maintain a smooth steering
input on a curve than on a straight road.
The preferred modification is to use mountable kerbs to accommodate heavy vehicles while
not interfering with the deflection of the roundabouts for other vehicles. Definition 1 relates
to Figure 3 and pertains to the specification of mountable curve kerbs on a roundabout. See
Figure 10 for details of how mountable kerbs might be used.
Definition 1
The inscribed circle diameter of the mountable kerb is the inscribed circle diameter measured
between mountable curve kerbs on opposite sides of a roundabout. Similarly, the inscribed
circle diameter of the non-mountable kerb is the inscribed circle diameter measured between
non-mountable curve kerbs on opposite sides of a roundabout. Also, note that not all
roundabouts have mountable kerbs.
Three existing roundabouts with central island diameters of 7.8 metres, 21 metres and 34
metres were used to represent a typical sample of all roundabouts on the network of routes.
To calculate how these roundabouts should be modified to accommodate each of the trial
vehicles Assumption 3 was made.
Assumption 3
The roundabouts that currently exist in the proposed network of routes are large enough to
accommodate the existing fleet but no larger. Therefore, any increase in the width of road
occupied by vehicles longer than those of the current fleet will require a corresponding
increase in the size of the roundabouts.
For a particular roundabout, to determine the amount of additional road width needed to
accommodate the trial vehicles, one of two assumptions was made. Either it was assumed
that the roundabout should allow the trial vehicle to navigate the roundabout without
interference from other traffic or it was assumed that one of the trial vehicles and a non-
articulated vehicle should be able to approach the roundabout side by side. The size of the
roundabout was used in Assumption 4 to determine which of these scenarios was considered.
Assumption 4
If the non-mountable central island diameter of the existing roundabout, D (in metres), was
such that
D<24
then it was assumed that the roundabout was designed to accommodate an articulated vehicle
only. If the non-mountable central island diameter of the existing roundabout, D (in metres),
was such that
D≥24
then it was assumed that the roundabout was designed to accommodate an articulated vehicle
and a non-articulated vehicle travelling side by side.
The following assumption was also made.
Assumption 5
For a right turn at a roundabout, the driver would approach the roundabout in the right-hand
lane. For a left turn the driver would approach the roundabout in the left lane and to travel
straight ahead the driver could use either lane.
Transit New Zealand Heavy Vehicle Limits Project Page 18 of 38
e2 Fn
M3
e1 Ft h2
mv2R-1
h1
mg
θ
Figure 4. Rear view of a vehicle cornering on a superelevated road.
ability of AutoSim to then generate accurate equations of motion has been well documented
by Sayers and Riley [1996] and Sayers [1989].
The B-train model, used to simulate B1233-44p, B1233-62f and B1233-62b, is a constant
velocity, 29 degree of freedom (DOF) model suitable for predicting the yaw and roll response
of a nine axle B-Train. The tractor sprung mass has 5 DOF, 2 translational and 3 rotational.
The first and second semi-trailers have 3 rotational DOF but no translational DOF. Two rigid
bodies each with 1 DOF are used to model each axle, one to account for vertical translation
and one for a rotation of the axle in the yaw plane due to the sprung mass rolling relative to
axle, (roll steer). The hitches are modelled as ball joints, the pitch and yaw stiffnesses are set
to zero and the roll stiffness is set high enough to provide adequate roll coupling between the
units (110 kNm – 340 kNm) [Sayers and Riley, 1996].
The vertical stiffness of the truck suspension is modelled with two springs per axle, the force
deflection characteristics of the springs are intended to capture the observed hysteretic
frictional behaviour of heavy truck suspensions. The describing equations for the spring are
those originally published by Fancher [1980]. Hydraulic dampers are modelled as linear
viscous dampers acting between the axles and sprung mass. The total roll stiffness of the
suspension derives from the vertical stiffness of the springs and any additional stiffness due to
linkages and from an anti-sway bar if fitted. The additional or auxiliary stiffness is modelled
as a torsion spring whose restoring moment is proportional to the roll of the sprung mass
relative to the axle.
The cornering force and aligning moment properties of the tyres are modelled using a table
lookup for a given slip angle and vertical load, longitudinal tyre dynamics are not included in
this model. Tyre damping rate is included as a linear viscous damper acting between the
ground and unsprung mass.
An implementation of the driver model of MacAdam [MacAdam, 1981] is used so that the
simulation can be run in closed loop mode, that is, the model can be steered to follow a
specified x-y path with minimal tracking error.
A complete listing of the model input data is given by Latto in Appendix C [Latto, 1999].
Physical Dimensions
Table 3 lists the vehicle dimensions, Overall Axle Spacing (OAS) and Overall Length (OAL).
A complete list of the vehicle dimensions and masses used in the simulations is given by
Latto [1999].
Test Procedure
Data from ten tests were recorded, four low speed tests and six high speed tests. The tests are
described below.
Transit New Zealand Heavy Vehicle Limits Project Page 22 of 38
The costs shown in Tables 4, 5, and 6 were used to determine the cost of modifying curves on
the network of routes. Estimated costs for widening a section of road by 0.5 metres, 1 metre
and 1.5 metres for various terrain types and zoning environments are given in Tables 4, 5, and
6.
Note that the figures in Tables 4-6 are only estimates and are not known precisely, although
the actual best guesses are listed in these Tables. Appendix C and Appendix M explain how
the costs presented in Tables 4-6 were calculated. Note that the taper cost is a lump sum and
allows for a 1 in 20 taper at the end of each curve. That is, 10 metres of taper on each end for
0.5 metre widening, 20 metres on each end for 1 metre widening and 30 metres on each end
for 1.5 metres widening.
f1
x2 R
f2
f4
x3 x4
w if x4<0.25 then
f3 x7=0 else x7=x4
x5
x7
if x5<0 then
x6=0 else x6=x5
q
x6 min(x6, x7)
Inspection of the algorithm shown in Figure 6 simply reveals the underlying assumptions
Assumption 1 and Assumption 2.
We will now show how Equations (1), (4), (5) and (6) were developed from the vehicle
simulation results.
Figure 7 shows the maximum road width occupied by B1233-62b and B1233-62f when
negotiating a curve of curvature R-1. The maximum was taken over simulations performed at
the advisory speed and half the advisory speed. Straight lines fitted to these data give
equations (1) and (6).
4.6
B1233-62b
4.4 B1233-62f
4.2
road width occupied (m)
3.8
3.6
3.4
3.2
2.8
2.6
0 0.005 0.01 0.015 0.02 0.025 0.03 0.035
-1
curvature (m )
Figure 7. Maximum curvature (R-1) versus maximum road width occupied for
B1233-62b and B1233-62f.
The road width occupied by the benchmark vehicles followed a similar trend
4
A123-39p
B1232-44p
road width occupied (m)
3.5
2.5
0 0.005 0.01 0.015 0.02 0.025 0.03 0.035
-1
curvature (m )
Figure 8. The road width occupied by the benchmark vehicles A123-39p and
B1232-44p when negotiating curves.
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 27 of 38
Note that we have defined curvature as R-1, where R is the radius of curvature of a curve. So,
a curve with R=100 metres has a curvature of 0.01 metres-1.
The difference between the maximum road width occupied by each of the trial vehicles and
the maximum of the two benchmark vehicles is shown in Figure 9.
0.7
B1233-62b
B1233-62f
0.6
0.5
difference in offtracking (m)
0.4
0.3
0.2
0.1
0
0 0.005 0.01 0.015 0.02 0.025 0.03 0.035
-1
curvature (m )
Figure 9. Difference between the maximum road width occupied by each of the
trial vehicles and the maximum of the two benchmark vehicles.
Straight lines were fitted to the data in Figure 9 (and doubled to account for two lanes) giving
equations (4) and (6) for B1233-62b and B1233-62f, respectively.
Typical curves and wheel paths used to determine the offtracking are given in Appendix D.
Remarks
• The kinks in Figure 7, Figure 8 and Figure 9 that occur at a curvature of 0.01 metres are
due to the imperfect nature of the driver model and have no physical significance.
• The lines that are fitted to the data in Figure 7 and Figure 8 are for 30<R<333. Therefore,
the lines fitted to the data in Figure 7 are not required to pass through (0,2.5) and the lines
fitted to the data in Figure 9 are not required to pass through the origin.
• Simulations were performed with fully loaded vehicles. The vehicle offtracking is a
combination of low speed effects (tracking inboard) and high-speed effects, which result
in less inboard offtracking or greater outboard offtracking. Since the high-speed effects
become more prevalent as the mass of the vehicle increases, the vehicles may offtrack
differently when unloaded.
• It was assumed, for the simulations, that a curve would be taken at a speed such that the
maximum lateral acceleration during the cornering manoeuvre was between 0.05g and
0.2g.
Transit New Zealand Heavy Vehicle Limits Project Page 28 of 38
2.4.1 Details of the method for determining the cost of modifying a roundabout
Consider the modification of a roundabout of arbitrary size. Consider the generalised
roundabout of Figure 10. The existing roundabout is shown with a solid line and the
modifications are shown with dashed lines. The proposed modifications are a reduction in the
size of the non-mountable part of the central island and an increase in the inscribed circle
diameter of the non-mountable kerb. Increasing the inscribed circle diameter of the non-
mountable kerb involves the removal of the part of each splitter island facing the roundabout,
moving the non-mountable curve kerb back and making the corresponding changes to the
entry curves and exit curves.
Table 7. Cost of modifying the representative roundabout with 34 metre diameter central island.
Reduce Inner Radius Move Outer Kerb Total
Vehicle B1233-62f B1233-62b B1233-62f B1233-62b B1233-62f B1233-62b
Change 0.2m 0.6m 0.6m 0.95m
Urban $12,345 $16,815 $91,605 $98,315 $103,950 $114,950
Industrial $12,345 $16,815 $91,605 $98,315 $103,950 $114,950
Rural $12,345 $16,815 $79,000 $85,540 $91,345 $102,355
Table 8. Cost of modifying the representative roundabout with 21 metre diameter central island.
Reduce Inner Radius Move Outer Kerb Total
Vehicle B1233-62f B1233-62b B1233-62f B1233-62b B1233-62f B1233-62b
Change 0.8m 1.0m 0.6m 1.05m
Urban $12,375 $16,500 $48,111 $52,584 $60,486 $69,084
Industrial $12,375 $16,500 $48,111 $52,584 $60,486 $69,084
Rural $12,375 $16,500 $45,105 $48,661 $57,480 $65,161
Table 9. Cost of modifying the representative roundabout with 7.8 metre diameter central island
Reduce Inner Radius Move Outer Kerb Total
Vehicle B1233-62f B1233-62b B1233-62f B1233-62b B1233-62f B1233-62b
1.4m 1.4m 0.6m 1.2m
Urban $6,170 $6,170 $48,150 $53,270 $54,320 $59,440
Industrial $6,170 $6,170 $48,150 $53,270 $54,320 $59,440
Rural $6,170 $6,170 $41,875 $48,045 $48,045 $52,940
Figure 11 shows a plot of central island diameter versus the cost of modifying a roundabout to
accommodate either B1233-62f or B1233-62b in a rural, industrial or urban zone. Drawings
of the three representative roundabouts used to generate Figure 11 are given in Appendix G.
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 31 of 38
120
100
80
cost (times $1,000)
20
0
10 15 20 25 30 35
central island diameter (m)
Curves were fitted to the data shown in Figure 11 to give equations for the estimated cost C of
modifying a roundabout as a function of the central island diameter. The cost of modifying a
roundabout of diameter D to accommodate B1233-62b is given by (7) for the case where the
roundabout is in a rural zone and (8) for the case when the roundabout is in an industrial or
urban zone
C = -0.0695D2 + 4.79D + 19.8 (7)
2
C = -0.0795D + 5.44D + 21.8 (8)
The cost of modifying a roundabout of diameter D to accommodate B1233-62f is given by (9)
for the case where the roundabout is in a rural zone and (10) for the case when the roundabout
is in an industrial or urban zone.
C = -0.0669D2 + 4.45D + 17.4 (9)
2
C = -0.0777D + 5.14D + 19.0 (10)
respectively. Recall that D is central island diameter in metres and C is the cost in thousands
of dollars.
The modifications required for roundabouts of arbitrary central island diameter were found by
interpolating between the modifications that were required for the three representative
roundabouts. The modifications that were required for the three representative roundabouts
are given below and an example of a plot of the swept path of a vehicle negotiating a
roundabout is shown in Appendix H.
Transit New Zealand Heavy Vehicle Limits Project Page 32 of 38
B1233-62f
B1233-62b
increase in inscribed circle dia.
1.5
1
5 10 15 20 25 30 35
D
Figure 12. Central island diameter versus required increase in inscribed circle
diameter for B1233-62f and B1233-62b.
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 33 of 38
3
B1233-62f
B1233-62b
2.5
reduction in D
1.5
0.5
0
5 10 15 20 25 30 35
D
Remarks
• A result of Assumption 3 is that all roundabouts apart from those where the trial vehicles
are only permitted to travel straight ahead are assumed to require modification to
accommodate the trial vehicles.
• Intersections along the specific routes not controlled by a roundabout were not considered
in accordance with the project brief.
Transit New Zealand Heavy Vehicle Limits Project Page 34 of 38
Table 10. Roads selected for inclusion in the network of routes for the Scenario B vehicles.
SOUTH ISLAND
Route Number Route Sector Location of Route Position Route Position
Number Port/Centre Node #1 Node #2
Note that Table 10 specifies the network of routes only roughly. Details of the exact roads
included in the network of routes may be found in Appendix L.
Table 11. Cost of modifying curves on the network of routes for B1233-62b and
B1233-62f for the original set of assumptions.
Cost for B1233-62b Cost for B1233-62f
Cost for N1= $3,500,000 $1,300,000
Cost for N2= $6,300,000 $4,000,000
Cost for N3= $300,000 $100,000
Cost for N4= $3,400,000 $1,600,000
Cost for S1= $8,100,000 $3,900,000
Cost for S2= $22,000,000 $7,900,000
total= $43,600,000 $18,800,000
Table 12. Cost of modifying curves on the network of routes for B1233-62b and
B1233-62f for Alternative assumption set 1.
Cost for B1233-62b Cost for B1233-62f
Cost for N1= $14,000,000 $3,900,000
Cost for N2= $23,100,000 $8,500,000
Cost for N3= $700,000 $300,000
Cost for N4= $18,200,000 $5,000,000
Cost for S1= $32,500,000 $8,900,000
Cost for S2= $43,500,000 $18,100,000
total= $132,000,000 $44,700,000
Table 13. Cost of modifying curves on the network of routes for B1233-62b and
B1233-62f for Alternative assumption set 2.
Cost for B1233-62b Cost for B1233-62f
Cost for N1= $38,800,000 $8,100,000
Cost for N2= $44,000,000 $12,400,000
Cost for N3= $5,100,000 $2,100,000
Cost for N4= $30,400,000 $7,000,000
Cost for S1= $46,400,000 $13,300,000
Cost for S2= $49,300,000 $19,700,000
total= $214,000,000 $62,600,000
The routes N1, N2, N3, N4, S1 and S2 are described in Table 10. Also note that RGDAS data
and RAMM data, which give detailed information about road width, curvature, terrain etc. for
roads in New Zealand were used for Tables 11, 12, and 13.
Remarks
• The costs for modifying curves on the network of routes presented in Table 11 are based
on Assumption 1 and Assumption 2.
• The removal of route S2 (State Highway 6) from the network of routes would
significantly reduce the costs.
Transit New Zealand Heavy Vehicle Limits Project Page 36 of 38
• Clearly, there are safety implications associated with the design of the assumptions for the
modification of curves on the network of routes. A recent Australian study suggested that
“a 1 metre increase in seal width (either as additional lane width or shoulder seal)
produced a 20 percent reduction in accident rates.” [McLean, 1996]. However, this was
an Australian study and dealt with widening of an entire section of road, not just the
curves. Milliken has made some attempt to estimate the safety implications of road
widening in [Milliken, 1999].
• The estimated costs of modifying curves on the network of routes were presented in
Tables 11, 12, and 13. The costs are sensitive to the assumptions that were used to
estimate widening because changing the widening assumptions alters the number of
curves that require modification. The number of curves that were estimated to require
modification were:
Assumption Set Vehicle Number of curves to be modified
Original B1233-62b 817
Original B1233-62f 376
Alternative 1 B1233-62b 2531
Alternative 1 B1233-62f 927
Alternative 2 B1233-62b 3784
Alternative 2 B1233-62f 1247 .
Table 14. Costs for modifying roundabouts on the network of routes to accommodate B1233-62b.
cost for N1= $175,000.00
cost for N2= $259,000.00
cost for N3= $205,000.00
cost for N4= $113,000.00
cost for S1= $364,000.00
cost for S2= $168,000.00
total cost= $1,284,000.00
Table 15. Costs for modifying roundabouts on the network of routes to accommodate B1233-62f.
cost for N1= $158,000.00
cost for N2= $236,000.00
cost for N3= $188,000.00
cost for N4= $103,000.00
cost for S1= $333,000.00
cost for S2= $154,000.00
total cost= $1,173,000.00
Details of the costs for each of the roundabouts on the network of routes that required
modification are given in Appendix J. Also note that it was not necessary to modify
roundabouts where only a ‘straight through’ manoeuvre was permitted. For the safety
evaluation project, 119 other alternative vehicles were simulated. Estimates of the costs of
modifying the network of routes to accommodate each of these alternative vehicles were
made. These results and the corresponding method are presented in Appendix K. The costs
for modifying curves and roundabouts on the network of routes are separated by route sector
in Table 16.
Report 5: Geometric Evaluation. Paul Milliken, TERNZ. Page 37 of 38
4. REFERENCES
[Austroads, 1993] Austroads, Guide to Traffic Engineering Practice Part 6 - Roundabouts,
Austroads, Sydney, 1993.
[Austroads, 1997] Austroads, Rural Road Design - Guide to the Geometric Design of Rural
Roads, Austroads, Sydney, 1997.
[Fancher, 1980] P. S. Fancher et al, Measurement and representation of the mechanical
properties of truck leaf springs., SAE: Warrendale. p. 14, 1980.
[Gillespie, 1992] T. D. Gillespie, Fundamentals of Vehicle Dynamics, Society of Automotive
Engineers, Warrendale, 1992.
[Latto, 1999] D. Latto, Road trial for Model Validation, TERNZ report for Transit New
Zealand, 1999.
[MacAdam, 1981] C. C. MacAdam, Application of an Optimal Preview Control for
Simulation of Closed-Loop Automobile Driving, IEEE Trans. on Systems, Man and
Cybernetics, SMC - 11(6), 1981.
[McLean, 1996] McLean, Review of accidents and Rural cross section elements including
roadsides, ARR 297, November 1996.
[Milliken, 1999] P. C. Milliken, Task 4 Summary Safety Report, TERNZ report for Transit
New Zealand, 1999.
[Prem et al., 1999] Prem, H., Ramsay, E., Fletcher, C., George, R., Gleeson, B., Estimation of
Lane Width Requirements for Heavy Vehicles on Straight Paths, preliminary report produced
at AARB, 1999.
[Sayers, 1989] M. W. Sayers, Automated Formulation of Efficient Vehicle Simulation Codes
by Symbolic Computation (AUTOSIM) in The Dynamics of Vehicles on Roads and Tracks,
Kingston, Ontario: Swets Zeitlinger, 1989.
[Sayers and Riley, 1996] M. W. Sayers and S. M. Riley, Modelling Assumptions for realistic
Multibody Simulations on the Yaw and Roll behaviour of Heavy Vehicles, SAE 960173, 1996.
[Sleath, 1999] L. Sleath, Email communication with Peter Baas, 30 June 1999.