Gary DeShazo Director, Regional Transmission North California ISO September 17, 2010
FERC technical conference was held on August 24, 2010 Still an ongoing process
Slide 3
Slide 4
Jan 10 June 10
No of Interconnection Request
50 45 40 35 30 25 20 15 10 5 0 2008 2009 2010
Generator Type
Slide 5
LGIP The ISO continue to see large number of renewables in the Queue
Transition Cluster
More than 50 projects, total capacity exceeds 10,000 MW From the total amount, approx 8,000 MW are renewable (6,000 MW of solar and 2,000 MW of wind) Complete technical studies as part of Phase II, LGIA in progress
Cluster 1
More than 6,000 MW of new applications, less than 100 MW of nonrenewable Phase I technical studies have been completed Phase II studies will be performed in 2011
LGIP The ISO continue to see large number of renewables in the Queue
Cluster 2
Approx 9,700 MW of new applications. Out of this amount, approx 7900 MW are renewables Phase I study is ongoing
Cluster 3
Cluster 3 window closed, applications are being reviewed Mostly renewable (similar to clusters 1-2), total number of applications and capacity are being finalized. Cluster 3 Phase I studies will be conducted in 2011
10000
8000
6000
4000
2000
0 TC Cluster 1 Cluster 2