Sie sind auf Seite 1von 5

Ten Ways to Minimize Stagnation in Domestic Water Systems

by Matthew R. Freije Posted: May 1, 2006 Piping with low or infrequent flows can be a breeding ground for Legionella bacteria, but the following measures will help to prevent these dead legs in water system designs.

Figure 1. Piping left after hot water tanks were removed.

Minimizing dead legs in domestic water plumbing is perhaps the most widely recommended Legionella preventive measure, yet the advice is usually given without even defining dead legs, let alone substantiating the cost versus benefits of removing them. Moreover, dead legscommonly thought of as piping with low or infrequent floware only one of many causes of stagnation in domestic water systems. Hospitals, nursing homes, hotels, office buildings and other large facilities should have an expert evaluate the building water systems and provide specific recommendations for minimizing stagnation. For now, though, implementing the following measures will provide a good start:
Figure 2. Both regulator lines (A and B) should be kept open, or flushed before use. The domestic water system is exposed to stagnant water in the bypass line (C) because of the dead segments between valve D and the tees at E and F. Also, the line c annot be flushed to waste without adding a drain and another valve.

1. Remove dead-legs. Although Legionella bacteria in dead legs can contaminate an entire domestic water system, the presence of dead legs does not necessarily mean there will be a Legionella problem, nor will removing them necessarily solve one. Before removing a dead leg, consider the benefits versus the cost. Some dead legs present a greater risk than do others. Some are expensive to correct; others are not. The following rules are good practice: a. Remove accessible dead legs. In equipment rooms and other areas where dead legs are accessible, the cost of removal will typically be minimal, so remove them. For example, if water heaters are abandoned, remove all the piping associated with the installation to the point of flow, rather than simply capping the lines (see Figure 1).

b. Establish a policy of removing dead legs during plumbing renovations. This should be added to any project specifications. c. If a dead leg cannot be removed without tearing out a wall, then leave it in the wall but cut and cap it where it tees into the main. For example, if a sink is removed, cut and cap the water lines serving the sink where they tee into the main, rather than at the wall. d. If a dead leg is not accessible, and it cannot be cut at the main, then try other methods of controlling Legionella bacteria before going to the expense of

tearing out walls to remove dead legs. The cost of removing dead legs that are behind walls may not be justified without knowing if you have a Legionella problem, and that removal of the dead legs will solve the problem. (It probably wont.) If water tests indicate that Legionella bacteria are under control in your facility, then the expense of removing inaccessible dead legs is probably not warranted. If Legionella bacteria is not under control, then continuous disinfection (e.g., copper-silver ionization or chlorine dioxide) will likely be more practical and effective than tearing out walls and removing dead legs (see e.). Building operators that do not periodically test domestic water for Legionella will need to be more aggressive in correcting dead legs. e. If a continuous disinfection system is installed and operating properly, yet test results indicate that Legionella bacteria are still not under control, then dead legs and other stagnant water conditions may have to be corrected unless another method (e.g., point-of-use submicron filters) can be implemented. This scenario is not uncommon. Removal of stagnant water piping is often necessary to make a disinfection system effective. A disinfectant cannot kill pathogens in water when there is no contact with the pathogens, such as in a dead leg. f. Choose flushing over removal only as a last resort. In some situations, facility operators choose to periodically flush dead legs rather than removing them. For example, rather than removing dead piping that used to supply an abandoned shower, a hospital will attach hose connections and set a maintenance policy of flushing the piping every two weeks. Relying on the maintenance staff to flush the lines is a risk. Also, Legionella bacteria will, theoretically, build up in the lines between flushes, posing a health risk. And facilities operators will not know how often to flush the lines unless they gather a significant amount of data. 2. Do not use showers for storage unless the unused piping is removed. 3. Keep backup lines open, or flush them before use. For water lines that split into two branches and then come back into one (e.g., to have a backup), both branches should ideally be kept open at all times (see Figure 2). If one branch is valved off, it should be flushed thoroughly to the drain before each use, so that none of the potentially contaminated water is distributed to the building. This may require adding a valve and drain at the downstream end of each branch. 4. Design bypass lines to minimize the domestic water systems exposure to stagnant water, and flush before each use. (See Figures 2 and 3.) 5. Use all pumps regularly, preferably everyday. If two pumps are installed on the domestic hot water return line, but only one is operating at a given time, they should ideally be rotated so that neither is offline for more than 24 hours (see Figure 4). The same principle applies to cold water

Figure 3. Design A exposes the domestic water system to stagnant water between the tees and the bypass valves, but design B does not. Also, design B allows the bypass to be flushed to waste by opening the upstream valve, c losing the downstream valve, and opening the drain. Flushing the bypass before use is

6. Flush vacant buildings, floors and rooms regularly. If a building or wing is completely out of use, requiring no water, the water system serving it should ideally be valved off and drained. On vacant floors with undrained systems, an employee in generally good health should periodicallyat least twice a week, but preferably dailyrun water at all outlets at full flow for 30 seconds and flush all toilets. This applies also to infrequently used sinks, showers or toilets in rooms that have been converted from patient to office or storage use (occupants of these rooms should be encouraged to operate the fixtures daily). Prior to assigning a hospital patient or hotel guest to a room that has been vacant for three or more days, an employee in generally good health should run the cold and hot water at each faucet and shower at full flow for at least two minutes and flush the toilets. For new hospital construction, consider electronic mixing valves for faucets and showers, which were recently introduced by Armstrong International Inc. After approximately 12 hours of inactivity, these valves will automatically run the hot and cold water for a few seconds at a safe temperature. 7. Use backup water supplies regularly, or flush them before each use. Most hospitals have a backup water supply from the city main to the building that may go several months or years without use. These lines can build up foul water that will be distributed throughout the facility when the line is used. If backup supply lines are not kept open, they should be flushed before each use, which may require adding a valve and drain at the downstream end, just before the building.

c ritical, espec ially sinc e bypass lines may go years without use, harboring foul water that c an c ontaminate an entire domestic water system.

(see Figure 4). The same principle applies to cold water booster pumps, alternating the lead pump accordingly. Stagnant water in idle pumps and the piping associated with them can provide a habitat for Legionella and other bacteria that can enter the system when the pumps are turned on.

8. Store water for no longer than 24 hours. If hot water storage tanks are used, or if tank-type water heaters are used in lieu of instantaneous heaters, then design and operate the system so that water remains in the tanks for no longer than 24 hours. The same is true for cold water storage tanks, unless they are treated. 9. Use water heaters daily. Even semi-instantaneous water heaters hold enough water (about 20 gallons) to pose a problem (see Figure 5). If removing backup water heaters is not a reasonable option, then they should be used regularly, preferably daily. If they are not used, they should be drained and isolated from the rest of the system, and disinfected before use. 10. Eliminate or isolate crossover piping. Pipes connecting buildings or systems, often used as a backup supply of hot or cold water, may harbor stagnant water that makes control

Figure 4. Unless one of these hot water recirculation pumps and its associated piping is removed, both should be operated all the time, or rotated regularly.

or cold water, may harbor stagnant water that makes control of Legionella bacteria difficult. If the crossover piping cannot be eliminated, it should be isolated from the rest of the system, and flushed before use. Priortize remedial measures based on a building assessment. Deserving higher priority are measures that either reduce a significant risk, or are relatively inexpensive and should thus be implemented out of good sense. Classify measures as lower priority if the risk reduction benefit is questionable and the cost of implementation is relatively high.

Figure 5. The heater on the right serves the lower floors of the building, the heater on the left serves the upper floors, and the one in the middle is a backup. This arrangement presents two problems. First, even if the middle tank is valved off, its piping leaves dead legs that expose the two operating tanks to stagnant water. The dead legs are short, but c ould still provide a habitat for bacteria. Second, stagnant water in the dead piping that is isolated with the middle heater, as well as in the heater itself (if it isnt drained), will enter and possibly c ontaminate the domestic water system when the heater is put into service. If the middle tank is not removed, it should be used full time in conjunc tion with one of the other two, or else flushed and disinfected prior to each use.

Matthew R. Freije mf@hcinfo.com Matt Freije is president of HC Information Resources Inc., Fallbrook, CA (www.hcinfo.com). He is the author of the book Legionellae Control in Health Care Facilities: A Guide for Minimizing Risk and three new Legionella management plans for hospitals, hotels and nursing homes. He is also the editor of Legionella Enews, an

international newsletter that covers outbreaks and new technology. Freije conducts Legionella building assessments, serves as an expert in litigation related to Legionnaires disease, recommends domestic water disinfection strategies and teaches seminars. He can be reached at (760) 451-1050, or mf@hcinfo.com.

Das könnte Ihnen auch gefallen