DEPARTMENT OF INTERDISCIPLINARY STUDIES IS 6230-PROJECT MANAGEMENT

TWO STORY SHOPPING COMPLEX CONSTRUCTION PROJECT Assignment 01

NAME REG No DATE

: JAYAWEERA J.G.B.P.S : RU/E/2007/210 : 09-09-2011

1.0

Project Scope

This project is designed to construct a two story building in Nuwaraeliya town. The contractor will focus on finishing the project on time and satisfying all the customer needs with the estimated cost. 1.1 Objectives

This project will construct a two story building at Nuwaraeliya town. Project duration Project start date Project end date Estimated cost 1.2 Deliverables : 300 days : 01 Nov 2011 : 31 Aug 2012 : LKR 3,500,000

Construction of two story building has several stages for one year period. Mainly focus on five main stages. The expected outputs of the each phase are as follows.

Stage 1)Preliminary and general

Duration 35

Task Site investigation (Bore hole investigation, soil testing and submit laboratory test report)

Preparation of drawings and approval 2)Construction 60 Mobilization of machines and equipments

Site clearing Excavation of foundation Construction of foundation 3)Construction of ground floor 70 Construction of wall Supplying and fixing doors and windows and interior partition etc... Providing utility facilities,

electricity, telephone and water etc... Formwork for slab, Placing of concrete slab (late start constraint has to be applied) 4) Construction of first floor 85 Construction of wall

Supplying and fixing doors and windows and interior partition etc... Providing utility facilities, electricity, telephone and water etc... Construction of roof, ceiling etc... 5) finishing work 25 Painting of wall, doors and windows Fixing of electrical fittings, water pipes, telephone connections etc...

1.3

Milestones

1.4 1.5

Complete the budget documents Approval of loan Preliminary and general work Construction work Construction of ground floor Construction of first floor Finishing/ Landscaping work Technical requirements Limits and exclusions

Mon 11/06/11 Mon 11/13/11 Mon 12/19/11 Mon 03/12/12 Mon 06/18/12 Mon 10/15/12 Mon 11/19/12

1.6

Customer Review

Customer is a businessman in Nuwaraeliya area. He is planning to construct his own house near a land own to customer. Customer needs us to carryout the whole process. He is willing to finish the work of the house within one year. The total estimated cost is 3.5 million rupees. He will pay 35% of the total cost at the initial stage. Rest of the cost will pay after 6 months from the stating date. 2.0 Project Priorities Time Constrain Enhance Accept X X Cost X Performance

3.0

Work Breakdown Structure

Construction of the two story building project activities will breakdown in to smaller function in order to reduce the complexity. The building construction is supervised and done by the customer of the project with help of contractor. Necessary assistance will give to contractor according to customer requirements.

4.0

Integrating the WBS with the Organization

The organization is a small scale organization with four main departments such as planning,

5.0 ID 1 2 3 submit 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

Coding the WBS for the Information System Task name 1.0 Construction of two story building 1.1 Preliminary and general 1.1.1 Site investigation (Bore hole investigation, soil testing and laboratory test report)" Preparation of drawings and approval

1.1.2 1.2

Construction 1.2.1 1.2.2 1.2.3 1.2.4 Mobilization of machines and equipments Site clearing Excavation of foundation Construction of foundation

1.3

Construction of ground floor 1.3.1 1.3.2 1.3.3 1.3.4 Construction of wall Supplying and fixing doors and windows and interior partition Providing utility facilities, electricity, telephone and water etc... Formwork for slab, Placing of concrete slab

1.4

Construction of first floor 1.4.1 1.4.2 1.4.3 1.4.4 Construction of wall Supplying and fixing doors and windows and interior partition Providing utility facilities, electricity, telephone and water etc... Construction of roof, ceiling etc...

1.5

Finishing work 1.5.1 1.5.2 Painting of wall, doors and windows Fixing of electrical fittings, water pipes, telephone connections