Points for 5MVA, 25KVA, 63KVA, 100 KVA & 315 KVA Transformer 1 2 3 4 5 5 MVA Transformer Max.

Hot spot Temp mentioned as 110.4C, whereas requirement is 100C. Point no 4 of GTP Core material mentioned as CRGO M4. Our requirement is CRGO H1-B Impulse flash over voltage is mentioned as not applicable for HV & LV windings, whereas our requirement is 175 & 75 KV for HV & LV windings respectively. Point no 27 (iii) of GTP Material of bushing mentioned as Brass & Copper for HV & LV respectively, whereas our requirement is Tinned Copper Fixed losses mentioned as 5.5KW, whereas in type test report it is 6.5 KW. Load loss mentioned as 33KW whereas in type test report it is 34KW

100 KVA Transformer 1. 2. 3. 4. Lighting impulse voltage mentioned as 95KVp, type testing is at 75KVp Details of conservator not mentioned in GTP Current density & area of cross section of HV & LV windings not mentioned Temp. Rise test report not submitted.

315 KVA Transformer 1. 2. 3. 4. No load losses @50% loading mentioned as 1100W in GTP, whereas type testing report says , it is 1140 W Details of conservator not mentioned in GTP Current density & area of cross section of HV & LV windings not mentioned Temp. Rise test report not submitted.

25 KVA Transformer 1. 2. 3. 4. Induced overvoltage withstand, for LV windings is mentioned as 866KV instead og 866V. Weight of transformer in type Current density & area of cross section of HV & LV windings not mentioned Temp. Rise test report not submitted. 63 KVA Transformer 1. 2. 3. 4. 5. 6. Induced overvoltage withstand, for LV windings is mentioned as 866KV instead og 866V. Lighting impulse voltage mentioned as 95KVp, type testing is at 75KVp Weight of transformer in drawing is 510 kg, in GTP its is 615 kg Current density & area of cross section of HV & LV windings not mentioned Details of conservator not mentioned in GTP Temp. Rise test report not submitted. List of type test For Power transformers: 1. Short circuit test. 2. Lightning impulse voltage withstand test. 3. Loss of measurement test. 4. Temperature rise test.

List of type test


For Power transformers (IS: 2026):
1. 2. 3. 4. Short circuit test. Lightning impulse voltage withstand test. Loss of measurement test. Temperature rise test.

For Distribution transformers:


1. Short circuit withstand test (IS-1180) 2. Impulse voltage withstand test 3. Temperature rise test. 4. Magnetic balance test. 5. Unbalance current test. 6. Noise level test. 7. Measurement of zero phase sequence impendence 8. Measurement of harmonics of no-load current. 9. Air pressure test. 10. Vacuum Test. http://www.scribd.com/doc/6673219/Surge-Arrest-Test-Procedures http://www.scribd.com/doc/6655379/IS-1554-PART-1-1988 http://www.scribd.com/doc/47819699/278 (barbed wire) Type test for DO Fuses (http://www.scribd.com/doc/7191534/11kv-Do-Fuses ) 1. Dielectric test (rated impulse withstand & rated one minute power frequency withstand test voltages) 2. Temperature rise test 3. Pull out test for embedded components of the fuse base 4. Beam strength of porcelain base

LIST OF TYPE TESTS (as per our tender & BEE specifications)

For Distribution transformers (of star rating):


1. Short circuit withstand test (IS-1180) 2. Impulse voltage withstand test 3. Temperature rise test. 4. Magnetic balance test. 5. Unbalance current test. 6. Noise level test. 7. Measurement of zero phase sequence impendence 8. Measurement of harmonics of no-load current. 9. Air pressure test. 10. Vacuum Test

MEETING ON 26.12.2011 [KEC International]

1. CMD(WZ) has desired that KEC should open a account with a OD of one crores at Indore for smooth working of project so that the project is not impeded by delay in payment to labour contractors. 2. By end of Dec 2011 the firm has committed that material worth 9.0 Crs will reach to site stores and by end of Jan2012 firm will put 30% (70.0 Crs) of material into their site stores. 3. It was surprise to note that M/s KEC has a new Manager, which is third change in the management to execute the project. It is expected that firm will keep consistency of manpower to execute the project in better way. 4. M/s KEC committed following delivery of progress,:i. By end of Jan.2012.1 No of 33/11 kv sub-station. ii. By end of 10th Feb20122 No(cumulative) of 33/11 kv substations. iii. By end of March 2012 ..5 No (cumulative) of 33/11 kv substations. 5. CMD(WZ) has very clearly stated that the ratio of HV works with 11kv works will not be less than 1:10 i.e against one 33/11 kv sub-station, work of 10 no 11kv feeders should be completed. Firm has given commitment for completion of 10 No. 11kv feeders in month of Jan. 2012.

6. CMD(WZ) has strictly instructed to adhere on safety precautions while working in field and ensure that no accident of any manner should occur during execution. 7. M/s KEC has submitted plan for execution up to March 2012. To achieve the targets as per plan, KEC has to be very aggressive in their approach. 8. As you are aware that the main aim of the project is to reduce AT&C Loss in LT Network. To achieve this errection of LT AB Cable in theft prone area is important but no inspection call for LT AB Cable is raised till date. You are required to procure this material on priority. 9. Inventory of steel items at you store is inadequate, therefore a proper planning is required for smooth flow of work. 10.Next meeting is scheduled on 09.01.2012.

GET

1. GET will submit BOQ of 10 no of Towns before 15th Jan 2012 and remaining 4 no of Towns by end of Jan 2012. 2. M/s GET has committed that by end of Jan2012 50% of material will reach to their site stores. 3. Quantity of energy will increase therefore a BOQ of all 14 towns shall be prepared so that variation in quantity can be derived. 4. GET assured that by end of FEB 2012 ring fencing of all towns will be completed. 5. First bill will be submitted before 15th April 2012 for at least 3 to 4 towns.

KEI Industries Ltd

1. M/S KEI committed that it will submit BOQ of 4no towns before 5 th Jan, 6no before 15th Jan and all 14 no before end of Jan 2012. 2. 50% of material will reach to site stores before end of Jan2012. 3. Complete ring fencing will be complete by end of FEB 2012. 4. Errection will start by 10th of Jan2012.in four towns. 5. Ring fencing will be completed in 9 no of towns by FEB 2012 first week.