Intruduction
Objectives
After testing the proposed network design, the network designer collects the information gathered from the RFP and previous PPDIOO steps into a network proposal. The proposal typically contains the following sections: Executive Summary Network Requirements Current Network Environment Proposed Physical Design Proposed Logical Design Implementation Plan Cost Estimate
If the proposal is in response to an RFP, the proposal components and Table of Contents are assembled to strictly follow the format requested in the RFP. If there is no written RFP, or if the written RFP does not specify an outline or format, the designer can determine the layout and design of the proposal. In such cases, the proposal layout should be highly readable and aid the reader in locating information. Graphics enhance the readability of a proposal and convey information as well. Text should be legible, typically a serif typeface such as Times Roman, at 10-point to 12-point type. Page margins should be at least 0.5 inches, and page numbers should be included at the top or bottom of each page.
At this point in the stadium project, the NetworkingCompany account manager and the network designer develop a proposal to respond to the RFP of the StadiumCompany. Most source material for the proposal is already available, except for the implementation plan and the cost estimate. The designer edits and organizes the existing information prior to developing the implementation plan and the cost estimate. Executive Summary Network Requirements and Current Network Environment Physical and Logical Design
During the proposal assembly process, the network designer and account manager review all of the materials to ensure that they are complete. It is important that the StadiumCompany management and technical staff are able to easily find and understand the material contained in the proposal. A disorganized or incomplete proposal can cause the customer to choose another contractor to complete the project. The designer and account manager work together to complete the implementation planning and to create the cost proposal.
There are three installation methods that may be used for the implementation: New installation- commonly referred to as a green field installation Phased installation-install components into an existing, functioning network Complete replacement-commonly referred to as a fork-lift upgrade
The project duration is part of the contractual agreement. To meet the deadlines of the customer the network designer creates a project timeline. The availability of materials, the schedule of the contractor, and the schedule of the customer all affect the start date and the completion date. When creating a project timeline, the network designer must consider the possibility that the project might not begin on the proposed start date. The stadium RFP states that the project must be completed during the off-season for the two teams. This requirement gives the project a timeline of four months.
NetworkingCompany Resources
Given the required sets of tasks, the designer estimates what resources are needed to implement the network. To meet the 4-month deadline, the NetworkingCompany may have to increase the number of technicians assigned to the project. It may also be necessary to adjust the sequence of tasks to accommodate the delivery of specific pieces of equipment or the availability of TSP services.
Estimated Timeline
The network designer considers several factors when developing a project timeline: Equipment order and delivery Service installation, such as WAN links Customer schedule, including available maintenance and downtime windows Availability of appropriate technical personnel
One of the most important sections of the proposal to the stadium management is the cost estimate. To prepare the cost estimate, the network designer creates a Bill Of Material (BOM). A BOM is a document that details all of the required hardware and components necessary to implement the proposed upgrade. It consists of an itemized list of hardware, software, and other items that must be ordered and installed. The designer uses this list to obtain quotations and to create the equipment orders.
To create the BOM, the network designer looks at each section of the network to determine what pieces of networking equipment are required and what capabilities are needed in each device. There are 21 separate locations within the stadium where networking equipment is to be installed or upgraded: 16 wiring closets 4 WAN locations 1 new data center In addition, the wireless design shows 33 locations for AP installation.
The new applications, installation costs, and required training are added to the BOM with the identified hardware. The designer considers whether the network upgrade requires additional licenses to be purchased for existing software applications.
Summary