Sie sind auf Seite 1von 19

Aker Construction Trade& Industrial INC.

GAZA-TURKISH PALESTINE FRIENDSHIP HOSPITAL

MONTHLY PROGRESS REPORT


Month: End of September 2011

CONSTRUCTION PROGRESS REPORT ( Sep. 2011)

1.

Name of Project Contract No.

: GAZA-TURKISH PALESTINE FRIENDSHIP HOSPITAL : AKER-GZ/2011 : Turkish Development and Cooperation Agency TIKA : Islamic University Gaza " Engineering Office " : Aker Construction Trade& Industrial INC.

2.

Client Consultant Contractor

3.

Site handing over date 05/ 05 / 2011

Actual Start
14 / 06 / 2011

Scheduled Finish 31 /05 / 2013

4.

Subcontractors working at site during reporting period :


Subcontractor : Saqqa

& Khoudary Co. Ltd.

5.

Manpower (Monthly average )

Project manager Administrative Manager Engineers Safety officer Accountant Forman Surveyor Assistant surveyor Skilled labor Unskilled labor Driver Office Boy Guard man Total on site

24 24 401 38 24 288 53 54 1859 1006 72 48 72 3963

6.

Occurrences /hindrances unexpected and unforeseen

None

7.

Financial Matter Total Amount : $34,000,000

8.

Material at site : Material Steel Bars Waterproof membrane Timber formwork

Qty for this month

Total

388.16 Tons 4500 m2 208.55 m3

952.81 tons 17000 m2 351.22 m3

9.

Equipment on site : Equipment


No. 2 2 1 3 1 1 3 1 2 20 295 2 2 2 10 1

No. of working day 22 24 24 24 0 24 20 14 6 18 24 24 24 3

Compressor Water pump Generator Cutting Machine Welding machine Mobile Crane Vibrator Loader Compactor Concrete pump Concrete mixer Total station Level Petroleum tank Water tank Back-hoe excavator

10. Work Performed during report period: Complete the placing concrete for mat foundation at block A-A',B-B', Qty = 838 m3. Complete the placing concrete for mat foundation at block F-G, Qty= 1187 m3. Complete the placing concrete for R.C walls and columns at block C, Qty= 286 m3. Placing concrete for parts of R.W and R.W foundation, Qty= 401 m3. Placing concrete for part of R.C walls and columns at block E Qty=161 m3. Complete the rebar and formwork installation for remaining part of R.C walls at block E. Complete the Placing concrete for caps foundation at Block A-B,F-G,C-E, Qty= 47 m3. Continue the rebar and formwork installation for external Retaining Wall. Continue the rebar and formwork installation for R.C walls and columns at Block D, A-B,F-G. Backfilling work on the foundation at Block C. Placing concrete for up stand beams at block C, Qty = 5.5.

11. Concrete delivered to site during report period:

Description Lean Concrete (B150) Protection concrete (B250) External R.W (B250) Structural Elements (B250)

This month 13 401 2510.5 2925.5

Previous 892.5 534 513 1192 3131.5

Total (m3) 905.50 534 914 3716.5 6072

11. Progress of work item of work executed Actual completion Planned ahead or behind schedule Ahead Ahead Ahead

Site handing over site mobilization Excavation work External Retaining wall R.C RF Concrete Structural works C-D-E Blocks 10 cm Gravel & Sand Plain concrete under foundation Water Proofing works Protection Concrete Foundation works Columns & RC walls -9.0 to -4.5m 30cm Backfilling on the foundation Plain concrete (At -9.0m ) -4.5m Slab& Beams Water proofing works for RC.Walls A-A',B-B' Blocks 10 cm Gravel & Sand Plain concrete under foundation water Proofing works Protection Concrete Foundation works Columns & RC walls -9.0 to -4.5m 30-40 cm Backfilling on the foundation Plain concrete (At -9.0m ) -4.50m Beams & Slab Waterproofing works for RC.Wall F-G Block 10 cm sand & Gravel Plain concrete under foundation water Proofing works Protection concrete Foundation works Columns & RC walls -9.0 to -4.5m 30-40 cm Backfilling on the foundation

100% 100 % 65%

100% 100% 62%

100% 100% 100% 100% 100% 85% 35% 0.0% 0.0% 0.0% 100% 100% 100% 100% 100% 35% 0.0% 0.0% 0.0% 0.0% 100% 100% 100% 100% 100% 20% 0.0%

100% 100% 100% 100% 100% 84% 15% 0.0% 0.0% 0.0% 100% 100% 100% 100% 100% 28% 0.0% 0.0% 0.0% 0.0% 100% 100% 100% 100% 86% 18% 0.0%

Ahead Ahead Ahead Ahead Ahead Ahead Ahead Ahead Ahead Ahead Ahead Ahead Ahead

Ahead Ahead Ahead Ahead Ahead Ahead Ahead

12. Work plan for Next month:


Block C-D-E Complete the placing concrete for remaining part of RC. Wall at block E,D. Complete the backfilling above foundation at block C-E-D. Complete the placing lean concrete basement floor at block C-D-E. Begin the formwork and rebar installation for 2nd basement slab and beams at block C-D-E . Placing concrete for 2nd basement slab and beams at block C. Block A-A'-B Complete the placing concrete for R.C walls and columns at block A-A',B. Begin the backfilling work above foundation at Block A-A',B. Block F-G Continue the formwork and rebar installation for R.C walls and columns at block F-G. Complete the placing concrete for RC walls and columns at block F. Complete placing concrete for separated columns at block G. External Retaining Wall: Continue the formwork and rebar installation for external R.W. Placing concrete for new parts of R.W and R.W foundations.

13. Schedule:

14. Photos of the construction progress:

Photo # 1 Rebar installation for R.C walls at block C.

Photo # 2 Rebar installation for columns at Block C

Photo # 3 Formwork of columns at block C

Photo # 4 Formwork of columns at block E

Photo # 5 Placing concrete for columns at block C

Photo # 6 Placing concrete for RC walls at Block C 9

Photo # 7 Placing Concrete for walls at block E

Photo # 8 Walls At Block C

10

Photo # 9-a Backfilling Work at block C

Photo # 9-b Backfilling at block C

11

Photo # 10

30 cm sand above foundation at block C

Photo # 11 Block C-D-E

12

Photo # 12 Placing concrete for mat foundation at block B

Photo# 13 Placing concrete for mat foundation A-B'

13

Photo # 14 Formwork for caps foundation at block A

Photo # 15 Rebar installation for columns at block A

14

Photo # 16 Formwork for walls and columns at block B

Photo # 17 Rebar installation at block B

15

Photo # 18 Block A-A'-B

Photo # 19 Rebar installation for mat foundation at block G

16

Photo # 20 Placing concrete for mat foundation at block F

Photo # 21-a Placing concrete for mat foundation at block G

17

Photo # 21-b Placing concrete for mat foundation block G

Photo # 22 Block F-G

18

Report #:

1 01/09/2011 30/09/2011

Reporting Period:

Date of submission:

5/10/2011

Approved by:

PM/ Mr. Mahmut CELEPLI

Prepared by:

Eng. Hazem Abu Shaaban