Beruflich Dokumente
Kultur Dokumente
3.
Anexure 2
Activity output to be measured
3
22.00 x (6.00 + 2.00) x 2.00 = 176 cum
Earth work in excavation in foundation Up to bed level :trenches not exceeding 1.5m with or 10
1 x 2 x x (5.00 x5.00) x 10.00=250.00 cum
sqm on plan in/c dressing bottom lift up Below bed level :to 1.5m in/c getting out the excavated
1 x 15.00 x 10.00 x 1.35 = 202.50 cum
soil &disposal of surplus excavated soil Cutoff Wall :as directed, with in a lead of 50m.
1 x2 x 15.00 x 1.50 x 0.457 =20.565 cum
Wing wall:2 x 2 x 5.00 x (3.80 + 2.50) x 1.50 =94.50 cum
------------------------Total = 567.565 cum
Filling in plinth with local sand under
floors in/c , watering, ramming,
Base:consolidating & and dressing complete.
1 x 15.00 x 10.00 x 0.20 = 30 cum
Cutoff Wall :1 x2 x 15.00 x 0.457 x 0.15=2.06 cum
Wing wall:2 x 2 x 5.00 x (3.80 + 2.50) x 0.25 =15.75 cum
------------------------Total = 47.81 cum
US=305 nos.
Time
5
Act. Description
No.
1
2
4.
Providing & laying cement concrete
1:4:8 (1 cement :4 river sand :8 brick
aggr. 40 mm nominal size) ex/c the
cost of centering & shuttering in:
Appron :
Upstream :- 1 x 14.10 x 1.00 x .20 =2.82 cum
Downstream:- 1 x 14.10 x 2.00 x .20 =5.64 cum
-------------------------Total = 8.46 cum
3
Base:1 x 15.00 x 10.00 x 0.20 = 30 cum
Cutoff Wall :1 x2 x 15.00 x 0.457 x 0.15=2.06 cum
Wing wall:2 x 2 x 5.00 x (3.80 + 2.50) x 0.25 =15.75 cum
------------------------Total = 47.81 cum
Wing wall :Area of High End :-6.00 x ( 3.60 + 0.50) = 12.30 Sqm
Area of Lower End :-4.00 x ( 2.30 + 0.50) = 5.60 Sqm
Quantity = 4 x 5.00 x (12.30 + 5.60) = 179.00 cum
Cutoff Wall :1 x2 x 14.10 x 0.457 x 1.15
= 14.82 cum
------------------------------------Total = 193.82 cum.
12 mm cement plaster 1:4 (1cement :4 Wing wall :river sand ) in/c neat
1 x 4 x 5.00 x (5.00 + 3.00) =
Cement punning.
---------------------------Total = 80.00 sqm
Time
Cement = 12 bags
Sand =1.38 cum. (i/c 15%
wastage
Sk = 14 nos
Us = 22 nos
9.
Act. Description
No.
1
2
8
Reinforced cement concrete work
1:1.5:3 (1cement :1.5 river sand :3
stone aggr. 20 mm nominal size) in/c
finishing &plastering the exposed
surface with cement mortar 1:3 (1
cement :3 river sand ) of thick ness
noty excceding 6mm to give a smooth
& even surface but ex/c the cost of
centering & shuttering in;
10
Time
5
Act. Description
No.
1
2
11
Cold twisted reinforcement for RCC
work in/c bending binding, placing in
position complete.
Time
5
Act. Description
No.
1
3
10 mm dia TMT bar :
Abutment and Pire :- 1 x 3 x 2 x 31 x 6.40 = 1190.40 m
Bottom slab and Top Slab :1 x 2 x 95 x 6.40 = 1216.00 m
Return wall (Vertical ):- 1 x 4 x 2 x10 x1.50 = 120 m
Railing :1 x2 x 2 x 4 x 14.10 = 225.60 m
--------------------------------------------Total = 2752.00 mtr
Add 5 % for over lapping = 137.60 mtr
-----------------------------------------------------Grand Total = 2889.60 mtr
@ 0.62 Kg / m = 1791.55 Kg
8 mm dia TMT bar :
Appron :1 x 25 x 14.00 = 350.00 m
1 x 114 x 2.90= 330.60 m
Railing post :2 x 10 x 6 x 0.85 = 102.00 m
Railing (Stirrup):- 2 x 10 x 7 x 0.65 = 91.00 m
Wheel guard (Stirrup):- 2 x 95 x 1.10 = 209.00 m
--------------------------------------------Total = 2526.40 mtr
Add 5 % for over lapping = 126.32 mtr
-----------------------------------------------------Grand Total = 2652.72 mtr
@ 0.62 Kg / m = 1644.68 Kg
Grand Total(Tor rod) = 13203.00 Kg
= 132.03 Quintal
Time
5
Act. Description
No.
1
2
12
Hiring charges for centering &
shuttering in/c propping comp. as per
direction of Er. In charge.
13
Wearing Course :
1 x 14.10 x 5.45 x 0.05 = 3.84 cum
-------------------------Total = 3.84 cum
3
Bottom slab I/C C.C 1 : 4 : 8 :1 x 2 x 14.10 x 0.95 = 26.79 Sqm
Abutment and Pier :
.
1 x 2 x (6.45 x 7.40)= 95.46 Sqm
1 x 4 x (6.00 x 6.45)= 154.80 Sqm
1 x 6 x (6.00 x 0.75)= 27.00 Sqm
Top Slab :1 x 2 x (14.10 x 0.675)= 19.00 Sqm
1 x 2 x (6.00 x 6.45 )= 77.40 Sqm
Railing post :
1x 2 x 10 x (0.90 x 1.00)= 18.00 Sqm
1 x 28 x (1.25 x 0.60) = 21.00 Sqm
Wheel Guard (inner):
1 x 2 x 14.1 x 0.225 = 6.35 Sqm
Return Wall :
1 x 4x (2 x 4.13) = 33.00 Sqm
-----------------------------------------Total = 478.80 Sqm
Cement= 31 bags
Stone Aggr. =3.42 cum..
Sand=1.89 cum(i/c 15%
wastage)
H/S =1 no.
S/k =1 no.
SSk = 3 nos.
US= 7 nos.
.
Time
5
Act. Description
Activity output to be measured
No.
1
2
3
14
Extra for Laying Concrete in or under Quantity = Vide Act. No 4
water or liquid and i/c cost of pumping
Base:or bailing out water and removing of
1 x 15.00 x 10.00 x 0.20 = 30 cum
shish etc complete
Cutoff Wall :1 x2 x 15.00 x 0.457 x 0.15=2.06 cum
Wing wall:2 x 2 x 5.00 x (3.80 + 2.50) x 0.25 =15.75 cum
------------------------Total = 47.81 cum
15
C.C Block for Downstream :1 x 105 x 0.40 x 0.40 x 0.40 = 6.72 cum
Cement= 30 bags
Brick Aggr. =6.03 cum..
Sand=3.46 cum(i/c 15%
wastage)
H/S =1 no.
S/k =1 no.
SSk = 5nos.
US=12 nos.
16
Time
5
Act. Description
Activity output to be measured
No.
1
2
3
9.
Labour of breaking departmental jhama a) 40 mm Size =Vide Act no. 4 = 42.88 Cum
bats or jhama brick ( in/c bigger lumps
2 brick size ) in to metal or chips and
stackingthe same properly as per b) 20 to 12.5 mm size jhama chips
directionof the Er. in charge withing
vide act. no 5 , 9 & 15
a lead of 50 mtrs.
= ( 7.53 + 7.34 + 6.03) cum
=20.90 cum
Prepared by
Samarendra Debbarma
Jr. Engineer, Gr-I
Dumburnagar R.D. Block.
Dhalai, Tripura.
Time
5
Name of work : Construction of R.C.C. Box culvert ( clear span 12.00 mtr , Height- 6.00 m ) at Rashyabari under East
Potachara ADC Village .
ANNEXURE 3
PART A, COLUMN 1
TO 8.
ITE
M
NO.
DESCRIPTION
1
1
2
First class Bricks
2.
4
5.
Jhama Bricks
Sand (Black )
Cement
Stone Chips (20 mm Size)
Centering & shuttering
Sand (Coarse)
Reinforcement (Rod)
Muli bamboo
Nails
Polythine
Black wire
Hiring charge of Diesel Pump
Coir rope
Barak Bamboo
Hiring Charge of Mixer Machine
Balli
6.
7.
8.
9
10
11
12
13
14
15
16
17
UNIT
REQUIR
EMENT
AS PER
ANNEXU
RE 2
3
NO
4
75,590
No
cum
Bags
cum
Sqm
Nos
Kg
Nos.
Kgs
Kg
Kg
Day
Kgs
No
Day
Nos
19,134
54.98
2007
155.00
478.80
179.53
13,203.0
500
75.00
35
50.00
60
70.00
80
25
150
COST OF
ONE UNIT
AS PER
RD
SCHEDUL
E
5
COST OF
WORK
AS PER R
D ISSUE
RATE
6
APPROVED COST
OF WORK AT
LOCATION
7
Rs (4.92 + 1.00 ) = Rs 5.92
8
Rs 4,47,492.00
Rs 1,13,273.00
Rs 35,682.00
Rs 6,02,100.00
Rs.6,00,625.00
Rs 41,177.00
Rs 1,19,567.00
Rs 6,42,194.00
Rs 3000.00
Rs 5250.00
Rs 3500.00
Rs 4000.00
Rs 21000.00
Rs 3150.00
Rs.6000.00
Rs.25,000.00
Rs.15,000.00
Rs 25,88,010.00
Total (A)=
Name of work : Construction of R.C.C. Box culvert ( clear span 12.00 mtr , Height- 6.00 m ) at Rashyabari under East
Potachara ADC Village .
ITE
M
NO.
1.
2.
3.
4.
DESCRIPTION
Highly skilled
Skilled
Semi skilled
Un- Skilled
UNIT
REQUI
REME
NT
AS PER
ANNEX
URE 2
No
No
No
No
281
128
558
1774
COST
OF ONE
UNIT AS
PER
RD
SCHEDU
LE
COST OF
WORK AS
PER R D
ISSUE
RATE
Rs 136.00
Rs 120.00
Rs.102.00
Rs 100.00
Total (B) =
APPROVED COST
OF WORK AT
LOCATION
Rs.38,216.00
Rs 15,360.00
Rs 56,916.00
Rs 1,77,400.00
Rs 2,87,892.00
Samarendra Debbarma
Jr. Engineer, Gr-I
Dumburnagar R.D. Block.
Dhalai, Tripura.