Sie sind auf Seite 1von 105

TURKISH ELECTRICITY TRANSMISSION CORPORATION

RESEARCH PLANNING AND COORDINATION DEPARTMENT

TURKISH ELECTRICAL ENERGY


10-YEAR GENERATION CAPACITY PROJECTION
(2009 2018)

JUNE 2009

CONTENTS

I.

INTRODUCTION..............................................................................................................................2

II.

DEMAND ..........................................................................................................................................4
II.1. PEAK LOAD AND ELECTRICITY CONSUMPTION OF TURKISH ELECTRICITY SYSTEM BETWEEN 1999-2008 ........ 4
II.2. ANALYSIS OF DAILY ELECTRICITY CONSUMPTION FOR THE YEAR 2008 ............................................................ 5
30 SEPTEMBER 2 OCTOBER AND 8 11 DECEMBER WERE RELIGIOUS HOLIDAY IN 2008. ........................................ 8
II.3. LOAD DURATION CURVES FOR YEARS 2007 AND 2008....................................................................................... 9
II.4. DEMAND FORECASTS .......................................................................................................................................... 9

III.

ANNUAL GENERATION PROGRAMS AND REALIZATION FOR YEARS 2007-2008 .........14

III.1. YEAR 2007 ...................................................................................................................................................... 14


III.2. YEAR 2008 ...................................................................................................................................................... 15

IV.

TRANSMISSION AND DISTRIBUTION SYSTEM .....................................................................17

IV.1. TRANSMISSION SYSTEM ................................................................................................................................... 17


IV.2. DISTRIBUTION SYSTEM .................................................................................................................................... 18
IV.3. SYSTEM LOSSES .............................................................................................................................................. 19

V.

ASSUMPTIONS USED FOR THE GENERATION CAPACITY PROJECTION.........................20


V.1. DEMAND............................................................................................................................................................ 20
V.2. EXISTING GENERATING SYSTEM ....................................................................................................................... 20
V.3. CAPACITIES UNDER CONSTRUCTION, CAPACITIES GRANTED BY LICENCE BY THE END OF 2008 AND EXPECTED
TO BE IN SERVICE ON PLANNED DATES ...................................................................................................................... 21

VI.

RESULTS ........................................................................................................................................41

VI.I. CASE I A (HIGH DEMAND SCENARIO 1) ...................................................................................................... 41


VI.2. CASE I B (HIGH DEMAND SCENARIO 2)...................................................................................................... 50
VI.3. CASE II A (LOW DEMAND SCENARIO 1) ..................................................................................................... 60
VI.4. CASE II B (LOW DEMAND SCENARIO 2) ..................................................................................................... 69

VII.

COMPARISON OF RESULTS .......................................................................................................78

VIII.

CONCLUSION AND RECOMMENDATIONS.............................................................................80

IX.

ANNEXES .......................................................................................................................................82

ANNEX 1 : EXISTING SYSTEM (AS END OF YEAR 2008) .................................................................................. 83


ANNEX 2 : POWER PLANTS CONNECTED TO AND DISCONNECTED FROM THE POWER SYSTEM IN
2008.......................................................................................................................................................................... 96
ANNEX 3 : POWER PLANTS EXPECTED TO BE IN SERVICE BETWEEN 2009-2016 UNDER
CONSTRUCTION AND GRANTED BY LICENCE .............................................................................................. 98
ANNEX 3 (CONT.) : POWER PLANTS EXPECTED TO BE IN SERVICE BETWEEN 2009-2016 UNDER
CONSTRUCTION AND GRANTED BY LICENCE ............................................................................................ 101

X.

Abbrivations...................................................................................................................................104

I.

INTRODUCTION

This report has been prepared by Turkish Electricity Transmission Corporation (TEA)
according to the authorization on preparing 10-Year Generation Capacity Projection and
submitting for approval of Energy Market Regulatory Authority (EPDK) within the framework of
the Electricity Market Law (EPK) No: 4628 and the Grid Code to guide the market participants by
using demand projections estimated by Ministry of Energy and Natural Resources (ETKB).
Electricity demand forecasts to be used for Generation Capacity Projection should be
estimated by distribution companies. But, since the demand projections have not been completed
yet by distribution companies, according to the temporary article of the Grid Code, High Demand
and Low Demand series which have been revised by taking into consideration recent economic
crisis by Ministry of Energy and Natural Resources (ETKB) are used in this study.
The study period for the Generation Capacity Projection is 10 years and it covers the
period from 2009 to 2018. Supply-Demand Balance in terms of capacity and energy based on two
demand series is calculated by considering existing power plants, projects which are currently
under construction and new projects granted by licence foresighted to be in operation between
years 2009 and 2013 which are prepared as two different scenarios (Scenario 1 and Scenario 2)
according to the Progress Report of January 2009 by Energy Market Regulatory Authority
(EPDK). Related data to the project (average) and firm generation values for the next 10 years are
obtained from Electricity Generation Corporation (EA), Turkish Electricity Trade and
Contracting Corporation (TETA) and General Directorate of State Hydraulic Works (DS) for
existing and under construction power plants. Data for new projects granted by licence by end of
December 2008 have been obtained from EPDK and these data have been updated according to
the Progress Report of January 2009 published by EPDK. While calculating generation
capacities, average generating values of hydro power plants under normal hydro conditions and
firm generating values of hydro power plants under dry hydro conditions are considered
separately and Supply-Demand Balances together with energy reserves are calculated for both
demand series (High Demand and Low Demand) and for both scenarios prepared by EPDK and
related to the new projects foresighted to be in operation in this period (Scenario 1 and Scenario
2), and then results are submitted in this report as Result I-A, Result I-B and Result II-A, Result
II-B.
In the report, it is analyzed how to meet both demand series according to:

Existing plants,
Existing plants - under construction state owned plants
Existing plants - under construction state owned plants - licenced private sector plants as of
December 2008 and expected to be commissioned on planned dates and prepared as two
different scenarios in accordance with the Progress Reports of January 2009.
as end of 2008 for Turkish Electricity System.

New additional capacities are not considered in this study, because the Generation
Expansion Planning Study has not been updated yet.
In this capacity projection study covering the period 2009-2018, it is analyzed how to meet
the demand safely, i.e. with a suitable reserve, by taking into account existing plants, under
construction plants and licenced projects which are expected to be in service on planned date. In
the study, generating amounts of these power plants are considered as Average and Firm
2

generating capacities. The year in which the electricity shortage may occure is being determined
by this study, thus it is aimed to indicate the time of new additional capacity need to investors. .
In this study, the covering of demand according to average and firm generating amounts is
calculated by taking into account maintenance, planned outages, forced outages, hydro conditions
and rehabilitation schedule of power plants in the existing system. While calculating generating
capacity amount it is also assumed that there will be no deficit on fuel supply.
Assumptions for this Capacity Projection Report are the most important data. and
This section should be carefully examined and results should be evaluated by considering
these assumptions.

II.

DEMAND

In this section, electricity consumption development for the last decade (1999-2008), peak
load development in the same period, typical daily load curves for the year 2008, comparison of
actual consumption values with forecasts and demand projections of peak loads and electricity
consumptions carried out by Ministry of Energy and Natural Resources (ETKB) for the next 10
years (2009-2018) are submitted.
Electricity Market Law No: 4628 and the Turkish Electricity Grid Code require
Distribution Companies to prepare demand forecast for their region covering 10-year ahead.
Since Distribution Companies have not prepared the demand projections yet, the demand series
updated by taking into consideration the effects of the economic crisis starting in the year 2008 to
the electrical energy demand by ETKB are being used in this study as done before.
II.1. Peak Load and Electricity Consumption of Turkish Electricity System Between 19992008
Gross electricity consumption (equal to gross generation + import export) has reached to
190 TWh by annual increase of 8.8% for the year 2007, and to 198.1 TWh by annual increase of
4.2% for the year 2008. Net consumption (internal consumption, grid losses and power theft
included) is 155.1 TWh for the year 2007 and 161.9 TWh for 2008.
Table 1 and Figure 1 show instantaneous peak load and electricity consumption of Turkish
Power System by years. The peak load and the minimum load are 29249 MW and 11100 MW for
the year 2007 respectively. The peak load is 30517 MW and the minimum load is 10409 MW for
the year 2008.
Table 1 : Peak Load and Electricity Consumption of Turkish Electricity System Between
19992008

PEAK LOAD
(MW)

INCREASE
(%)

ELECTRICITY
CONSUMPTION
(GWh)

INCREASE
(%)

1999

18938

6,4

118485

3,9

2000

19390

2,4

128276

8,3

2001

19612

1,1

126871

-1,1

2002

21006

7,1

132553

4,5

2003
2004
2005
2006
2007
2008

21729
23485
25174
27594
29249
30517

3,4
8,1
7,2
9,6
6,0
4,3

141151
150018
160794
174637
190000
198085

6,5
6,3
7,2
8,6
8,8
4,2

Figure 1 : Peak Load and Electricity Consumption of Turkish Electricity System Between
19992018
65000

400000

60000
350000

55000
50000

300000

45000

MW

35000
200000
30000
25000

GWh

250000

40000

150000

20000
100000

15000
10000

50000

5000
0

0
1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

TKETM (GWh)

SENARYO 1 ENERJ TALEB

SENARYO 2 ENERJ TALEB

PUANT YK (MW)

SENARYO 1 PUANT TALEP

SENARYO 2 PUANT TALEP

2018

II.2. Analysis of Daily Electricity Consumption for the Year 2008


Daily load curves of the maximum and minimum electricity consumption days in 2008,
are on Figure 2 and Figure 3, daily load curves for third Wednesday of each month are on Figure
4. The peak load is 30517 MW on the maximum consumption day in 2008.
Figure 2 : Loading order of power plants regarding type of primary energy resources on
the maximum consumption day of the year 2008 (July 23, 2008)

Figure 3 : Loading order of power plants regarding type of primary energy resources on
the minimum consumption day of the year 2008 (October 1, 2008)

Figure 4 : Daily Load Curves of Third Wednesday of Each Month in 2008

30 September 2 October and 8 11 December were Religious Holiday in 2008.

II.3. Load Duration Curves for Years 2007 and 2008


Figure 5 : Load Duration Curve for the year 2007

MW

2007 YILI TERTPLENM YK ERS


31000
30000
29000
28000
27000
26000
25000
24000
23000
22000
21000
20000
19000
18000
17000
16000
15000
14000
13000
12000
11000
10000
9000
8000
7000
6000
5000
4000
3000
2000
1000
0
1

SAAT

Figure 6 : Load Duration Curve for the year 2008

II.4. Demand Forecasts


In this Generation Capacity Projection study, the demand series which are updated
according to the economic crisis affect by Ministry of Energy and Natural Resources (ETKB) are
used. While determining the demand series, it is excepted that in the year of 2009 a recession of
2% in the electrical energy demand will occure, in the years of 2010 and 2011 the increase of
electrical energy demand will be low because of the effect of the economic crisis and in the
following years the annual rates of the demand increase calculated by using of MAED Model on
May 2008 are used for both the demand series.
Comparison of former demand forecasts carried out by ETKB with actual values is
submitted on Table 2 and Table 3 1.

The Study Report on Long-Term Electricity Demand of Turkey, ETKB-APKK, 2004


9

Table 2 : Comparison of Former Demand Forecasts with Realized Values


TWh
Electricity
Consumption

1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008

24.6
26.3
28.3
29.6
33.3
36.4
40.5
44.9
48.4
52.6
56.8
60.5
67.2
73.4
77.8
85.5
94.8
105.5
114.0
118.5
128.3
126.9
132.6
141.2
150.0
160.8
174.6
190.0
198.0

Policies
1985

35.9
40.5
45.2
50.5
56.4
62.0
68.0
74.6
81.8
89.6
98.3
106.9
116.3
126.5
137.5
149.6

1987

51.6
57.9
65.0
71.7
79.0
87.2
96.1
105.9
115.6
126.8
138.9
152.3
166.8
177.0
189.3
202.5
216.5
231.5
247.6
264.8
283.1

1988/1

57.9
64.9
71.9
79.2
87.3
96.1
105.9
115.6
126.8
138.9
152.3
166.8
177.0
189.3
202.5
216.5
231.5
247.6
264.8
283.1

1988/2

55.5
61.8
68.2
75.3
83.1
91.8
101.2
110.6
120.6
131.6
143.5
156.5
165.3
178.1
191.9
206.7
222.7
239.9
258.5
278.5

5th Energy
Congress
1990

52.6
56.5
68.2
75.3
83.1
91.8
101.2
110.6
120.6
131.6
143.5
156.5
168.0
180.2
193.4
207.5
222.7
239.9
258.5
278.5

PROJECTIONS
1990/2

52.6
56.8
68.2
75.3
83.1
91.8
93.0
100.8
109.3
118.5
128.4
139.3
150.8
163.2
176.7
191.3
207.1
224.2
242.7
262.7

1993

71.7
80.4
88.4
96.8
106.0
116.1
127.2
139.3
150.7
163.2
176.7
191.3
207.1
224.2
242.7
262.7

6th Energy
Congress
1994

81.0
87.2
94.6
102.5
111.1
120.3
130.4
140.9
151.7
163.4
176.0
189.6
203.7
218.8
235.1

1996

2000

105.3
113.8
123.7
134.3
146.2
158.0
170.8
184.6
199.6
215.2
231.8
249.7

118.5
126.8
138.8
151.4
165.2
180.2
196.6
213.2
231.1
250.6

2002/1

128.3
127.3
133.4
151.5
172.1
195.5
211.0
227.8
245.9

2002/2

128.3
126.9
132.3
142.5
158.2
175.7
190.7
207.1
224.8

2004

160.5
176.4
190.7
206.4

Table 3 : Deviation Ratio of Demand Forecasts from Realization (%)


Policies
1985

1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008

-1.4
0.0
0.7
4.3
7.2
9.2
12.4
11.0
11.4
15.2
15.0
12.8
10.2
11.0
16.0
16.6

1987

6.6
10.1
14.4
18.5
17.6
18.8
23.5
23.9
21.9
20.2
21.8
28.5
30.0
39.5
42.8
43.5
44.3
44.0
41.8
39.4
43.0

1988/1

10.1
14.3
18.8
17.9
18.9
23.5
23.9
21.9
20.2
21.8
28.5
30.0
39.5
42.8
43.5
44.3
44.0
41.8
39.4
43.0

1988/2

5.5
8.8
12.7
12.1
13.2
18.0
18.4
16.7
14.3
15.4
21.1
22.0
30.3
34.4
36.0
37.8
38.5
37.4
36.1
40.7

5th Energy
Congress
1990

0.0
-0.5
12.7
12.1
13.2
18.0
18.4
16.7
14.3
15.4
21.1
22.0
32.4
35.9
37.0
38.3
38.5
37.4
36.1
40.7

PROJECTIONS
1990/2

0.0
0.0
12.7
12.1
13.2
18.0
8.8
6.3
3.6
3.9
8.4
8.6
18.8
23.1
25.2
27.5
28.8
28.4
27.7
32.7

11

1993

-2.3
3.3
3.4
2.1
0.5
1.8
7.3
8.6
18.8
23.1
25.2
27.5
28.8
28.4
24.7
32.7

6th Energy
Congress
1994

4.1
2.0
-0.2
-2.8
-2.5
1.5
1.6
11.0
14.4
15.8
17.3
17.9
16.7
15.2
18.7

1996

-0.2
-0.2
4.4
4.7
15.2
19.2
21.0
23.1
24.1
23.3
22.0
26.1

2000

0.0
-1.2
9.4
14.2
17.0
20.1
22.3
22.1
21.6
26.6

2002/1

0.0
0.3
0.6
7.3
14.7
21.6
20.8
19.9
24.2

2002/2

0.0
0.0
-0.2
1.0
5.5
9.3
9.2
9.0
13.5

2004

-0.2
1.0
0.4
4.2

Demand projection series (High Demand and Low Demand) together with annual increase
rates are given in Table 4, Figure 7 and Table 5, Figure 8 respectively.
Demand series for total Turkish Electricity System are on Table 4 and Table 5 and they are
gross values. Transmission and Distribution losses, internal consumptions of plants and power
theft are included in this gross demand. Further, embedded generation (connected to the
distribution system) and the generation of plants which are not subject to Load Dispatching
instructions are included too.
Table 4 : Demand Forecast (High Demand)

Year
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018

PEAK LOAD
ELECTRICITY DEMAND
Increase
Increase
MW
GWh
(%)
(%)
29900
194000
31246
4,5
202730
4,5
33276
6,5
215907
6,5
35772
7,5
232101
7,5
38455
7,5
249508
7,5
41339
7,5
268221
7,5
44440
7,5
288338
7,5
47728
7,4
309675
7,4
51260
7,4
332591
7,4
55053
7,4
357202
7,4

Figure 7 : Demand Forecast (High Demand)

12

Table 5 : Demand Forecast (Low Demand)


PEAK LOAD
Year
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018

MW
29900
31246
32964
35173
37529
40044
42727
45546
48553
51757

Increase
(%)
4,5
5,5
6,7
6,7
6,7
6,7
6,6
6,6
6,6

Figure 8 : Demand Forecast (Low Demand)

13

ELECTRICITY
DEMAND
Increase
GWh
(%)
194000
202730
4,5
213880
5,5
228210
6,7
243500
6,7
259815
6,7
277222
6,7
295519
6,6
315023
6,6
335815
6,6

III. ANNUAL GENERATION PROGRAMS AND REALIZATION FOR


YEARS 2007-2008
III.1. Year 2007
Total electricity generation of Turkey has been estimated to be around 187.7 TWh in the
year 2007 and so the consumption has been estimated around 185.2 TWh. The realization of the
consumption is 190 TWh by the increase of 8.8% according to the previous year. (Table 6). By
the end of the year 2007 total installed capacity is 40835.7 MW. The breakdown of total installed
capacity by utilities is on Table 7.
Table 6 : Annual Generation Program and Realization for 2007 (GWh)
UTILITIES

70766

2007
Revised
Annual
Program
75700

15485
101

19098
138

73839
216
18488
797

4141

4480

4268

14674

14455

14256

46013
16124
20430
116968
187733

44946
17927
16324
117368
193068

44970
19399
15325
117719
191558

540

743

864

188273

193811

192422

3093

2873

2422

185180

190938

190000

2007
Annual
Program

EA
ADA
AFFILIATED PARTNERSHIP OF EA
MOBILE PLANTS
POWER PLANTS UNDER TRANSFER
OF OPERATIONAL RIGHT CONTRACT
POWER PLANTS UNDER BUILTOPERATE-TRANSFER CONTRACT
POWER PLANTS UNDER BUILTOPERATE CONTRACT
GENERATION COMPANIES
AUTOPRODUCERS
NON-EA GENERATION
TOTAL GENERATION OF TURKEY
IMPORT
TURKEYS GENERATION + IMPORT
EXPORT
TOTAL CONSUMPTION OF TURKEY

14

2007
Realization

Table 7 : Breakdown of Installed Capacity (2007)


INSTALLED
CAPACITY

UTILITIES

MW

EA
AFFILIATED PARTNERSHIP OF EA
ADA
POWER PLANTS UNDER TRANSFER OF
OPERATIONAL RIGHT CONTRACT
MOBILE PLANTS
POWER PLANTS UNDER BUILT-OPERATE
CONTRACT
POWER PLANTS UNDER BUILT-OPERATETRANSFER CONTRACT

GENERATION COMPANIES

AUTOPRODUCERS

TOTAL INSTALLED CAPACITY

THERMAL
HYDRO
THERMAL
THERMAL
HYDRO
THERMAL
HYDRO
THERMAL

8.690,9
11.350,3
3.834,0
30,0
111,3
620,0
30,1
262,7

THERMAL

6.101,8

THERMAL
WIND
HYDRO
THERMAL
WIND
HYDRO
THERMAL
WIND
HYDRO
THERMAL
WIND
HYDRO

1.449,6
17,4
982,0
3130,3
127,7
363,0
3.175,2
1,2
558,2
27.294,5
146,3
13.394,9

TOTAL
INSTALLED
CAPACITY
MW

20.041,2
3.834,0
141,3
650,1
262,7
6.101,8
2.449,0

3.621,0

3.734,6

40.835,7

III.2. Year 2008


In the year 2008, while the forecasted total electricity generation amount was 205.4 TWh,
the realization was 198.4 TWh by the increase of 3.5% from the previous year and the
consumption was 198.1 TWh by the increase of 4.2% while it was forecasted as 204.0 TWh.
(Table 8). By end of the year 2008, the total installed capacity is 41817.2 MW and the breakdown
of this total installed capacity to the utilities is on Table 9.
The power plants connected to the system and the decommissioning power plants in 2008
are listed in Annex-2.

15

Table 8 : Annual Generation Program and Realization for 2008 (GWh)

UTILITIES
EA
ADUA
AFFILIATED PARTNERSHIP OF EA
MOBILE PLANTS
POWER PLANTS UNDER TRANSFER OF
OPERATIONAL RIGHT CONTRACT
POWER PLANTS UNDER BUILTOPERATE-TRANSFER CONTRACT
POWER PLANTS UNDER BUILT-OPERATE
CONTRACT
GENERATION COMPANIES
AUTOPRODUCERS
NON-EA GENERATION
TOTAL TURKEYS GENERATION
IMPORT
TURKEYS GENERATION + IMPORT
EXPORT
TOTAL TURKEYS CONSUMPTION

2008
Annual
Program
74731
482
20472
1800

2008 Yl
Realization
74919
320
22798
330

4203

4315

13758

13171

47219
25600
17118
130352
205383
600
205983
1983
204000

43342
23499
15724
123499
198418
789
199207
1122
198085

Table 9 : Breakdown of Installed Capacity (2008)


INSTALLED
TOTAL
CAPACITY INSTALLED
(MW)
CAPACITY

UTILITIES
EA
AFFILIATED PARTNERSHIP OF EA
POWER PLANTS UNDER TRANSFER OF OPERATIONAL RIGHT
CONTRACT
MOBILE PLANTS
POWER PLANTS UNDER BUILT-OPERATE CONTRACT
POWER PLANTS UNDER BUILT-OPERATE-TRANSFER
CONTRACT
GENERATION COMPANIES

AUTOPRODUCERS

TOTAL INSTALLED CAPACITY

16

THERMAL
HYDRO
THERMAL
THERMAL
HYDRO
THERMAL
THERMAL
THERMAL
WIND
HYDRO
THERMAL
WIND
HYDRO
THERMAL
WIND
HYDRO
THERMAL
WIND
HYDRO

8.690,9
11.455,9
3.834,0
620,0
30,1
262,7
6.101,8
1.449,6
17,4
982,0
3.687,3
345,1
807,2
2.978,5
1,2
553,5
27.624,9
363,7
13.828,7

20.146,8
3.834,0
650,1
262,7
6.101,8
2.449,0

4.839,6

3.533,2

41.817,2

IV.

TRANSMISSION AND DISTRIBUTION SYSTEM

IV.1. Transmission System


Transmission system is the group of facilities starting from generation units to distribution
network and transmitting energy at the level of 36 kV Voltage Level. Components of transmission
system are:
Transmission lines and cables
Transmission Substations and Switching Centers (switchyards not containing step down
substations and transformers)
Turkish electricity transmission system, which is composed of 380 kV EHV lines and 154
kV HV lines, 380/154 kV Autotransformers and 154/MV step down substations, has been
equipped with the sufficient amount of serial and shunt capacitors due to their technical and
economic advantages. The transmission system has standard voltage level of 380 kV and 154 kV.
Interconnection lines connecting Turkish system to Georgia and to Armenia are at the level of 220
kV appropriate to other countries system.
Turkish generation and transmission system is being managed via 9 regional dispatching
centers (Adapazar, aramba, Keban, zmir, Glba, kitelli, Erzurum, ukurova and Kepez)
coordinated by the National Dispatching Center in Ankara (Glba). Operating of the power
system is being carried out by SCADA 2 and Energy Management System EMS 3 software.
SCADA system includes 380 kV lines and power plants greater than 50 MW. System operator
can manage every kind of system studies necessary for more quality, daily operating programs
and system frequency control.
The existing situation of the transmission system is summarized on Table 10 and Table 11.
Table 10 : Number of Transmission Substations and Capacities by primary voltage level
(Values for 2008)
380 kV
AMOUNT
174

154 kV

66 kV and lower

CAPACITY
CAPACITY
AMOUNT
(MVA)
(MVA)
33220
1010
55584

AMOUNT
57

CAPACITY
(MVA)
672

TOTAL
AMOUNT
1241

CAPACITY
(MVA)
89476

Table 11 : Length of Transmission Lines (km) ( Values for 2008)


380 kV

220 kV

154 kV

66 kV

TOTAL

14420.2

84.5

31653.9

508.5

46667.1

154 kV underground capacity cable length is 162.9 km


380 kV underground capacity cable length is 12.8 km
Transmission system is the main backbone of the electric system. Transmission System
investments are expensive and have long construction period.
2
3

Supervisory Control And Data Acquisition


Energy Management System
17

IV.2. Distribution System


The total length of Turkis electricity distribution system is 940922 km as end of the year
2008. The breakdown of distribution line lengths by voltage level is summarized on Table 12.
Table 12 : Length of Distribution Lines (km)
33 kV

15,8 kV

10,5 kV

6,3 kV

Other

0,4 kV

TOTAL

339691

30848

5573

7792

101

556918

940922

Resource : TEDA

The current situation of Turkish Electricity Distribution System is as end of the year 2008
outlined on Table 13.
Table 13 : Number of Distribution Substations and Capacities by primary voltage level
Secondary Voltage
Level
33 kV
15,8 kV
10,5 kV
6,3 kV
OTHER

Secondary Voltage
Level

15,8 kV

10,5 kV

6,3 kV

0,4 kV

TOTAL

AMOUNT

491

219

445

56

267.572

268782

CAPACITY (MVA)

4.090

3.528

3.344

268

71.663

82893

AMOUNT

31.233

31241

CAPACITY (MVA)

15

9.202

9220

AMOUNT

8.227

8228

CAPACITY (MVA)

7.019

7023

AMOUNT

8.100

8105

CAPACITY (MVA)

141

3.611

3752

AMOUNT

1.920

1930

CAPACITY (MVA)
TOTAL

OTHER

59

365

424

AMOUNT

491

219

451

74

317052

318286

CAPACITY (MVA)

4090

3528

3363

471

91859

103312

Resource : TEDA

18

IV.3. System Losses


Transmission system has been designed appropriate to European standards by considering
population density, location of supply resources and geografical conditions and the line losses
around 3% which is at the level of international performances. (Table 14)
Table 14 : Transmission Losses

YEAR

GWh

2001

2.8

3374.4

2002

2.7

3440.7

2003

2.4

3330.7

2004

2.4

3422.8

2005

2.4

3695.3

2006

2.7

4543.8

2007

2.5

4523.0

2008

2.3

4388.4

Resource : Turkish Electricity Generation-Transmission Statistics, TEA-APK

19

V.

ASSUMPTIONS USED FOR THE GENERATION CAPACITY


PROJECTION

V.1. Demand
In the Generation Capacity Projection study covering the period between years 2009 and
2018, the demand series which are updated according to the economic crisis started in the year
2008 by Ministry of Energy and Natural Resources (ETKB) are used. While determining the
demand series, it is excepted that in the year of 2009 a recession of 2% in the electrical energy
demand will occure, in the years of 2010 and 2011 the increase of electrical energy demand will
be low because of the current economic crisis effect. For the following years, the annual growth
rates of demand are being considered as two different scenerios, which are High Demand Series
and Low Demand Series. Both demand series are calculated by using MAED model. By assuming
no change on annual load curve characteristic for the study period, annual peak load values are
obtained by using annual demand growth rates.
V.2. Existing Generating System

Power plants connected to Turkish Power System and in operation as the end of the year
2008 are considered as existing system.
Maximum generating capacity called as Project Generation and reliable generating capacity
called as Firm Generation for EA thermal power plants are obtained from EA.
Nominal generating capacity called as Project Generation and reliable generating capacity
called as Firm Generation for EA hydro power plants are obtained from EA.
Project Generation and Firm Generation amounts of thermal power plants owned by
affiliated partnerships are obtained from EA for the period from 2009 to 2018.
Project Generation and Firm Generation amounts of Autoproducer and Generation
Company power plants are obtained from their licences and these generation amounts are
accepted as to remain at the same level for the next 10-year period. Generating capacity
amounts indicated on their licences are obtained from EPDK.
Generating capacity amounts of power plants under BO contract for the future ten-year
period are the energy sale amounts indicated on their contracts and obtained from TETA.
Generating capacity amounts of power plants under BOT and TOR contract for the future
10-year period are the energy sale amounts indicated on their contracts and obtained from
TETA. In spide of the agreements of some power plants under BOT contract expiring with
TETA in the period of the projection, it is assumed that these power plants will continue to
produce electricity in a different structure. The generation amount is taken as the same in
the period of the projection after expiring of their contracts.
The installed capacities of Autoproducer and Generation Company power plants (except for
decomissioning) whose licences have been cancelled are kept in total installed capacity and
their generation capacities are taken as zero.
The contracted generation amounts of Mobile Plants are used as Generating Capacity
Amount for mobile plants and these amounts are used till the end of their contracts with
EA. Due to expiration of mobile power plant contracts with EA, the corresponding
generation amounts by year will be decreased from the total generation capacity and only
the mobile power plants going on their contracts are put in the lists. After finishing their
contracts, the power plants will be able to produce by taking Generation Company licence.
The power plants with the licence of Generation Company till the end of 2008 are taken into
consideration in the study. But the plants not only expiring their contracts and but also not
taking the new generation licence are not taken into consideration.
20

Firm and Project generation capacity amounts of natural gas fired power plants are given by
related ownerships by assuming that there will be no constraint on natural gas supply during
the study period 2008-2017.
By taking into consideration of rehabilitation investments and maintenance-repair program
for state owned power plants, the generation amounts of the plants are given by EA.
2 x 150 MW units of Ambarl fuel oil fired power plant which is currently being extended
to be decommissioned in 2010 and new one to be commissioned as a natural gas fired power
plants with 840 MW (540 MW + 300 MW) total installed capacity in 2013 are taken into
consideration.

V.3. Capacities Under Construction, Capacities Granted by Licence by the end of 2008 and
expected to be in service on planned dates

On line dates and Project (in average hydro conditions) and Firm (in dry hydro conditions)
generation amounts of hydro power plants having total installed capacity of 2835.7 MW
which are constructed by DS and expected to be in service between the years of 2009 and
2016 are obtained from DS. Annual generation amounts of the projects whose
commissioning dates are given project by project in detail taken into consideration in the
balance tables by calculating as of their commissioning dates.
Installed capacity, project generation and firm generation data for power plants granted by
licence as the end of December 2008, under construction and expected to be in service on
proposed time are obtained according to two seperate scenarios (Scenario 1 and Scenario 2)
from January-2009 Progress Report by EPDK. The scenarios are prepared, by considering
assumptions below, by EPDK.
In this context, it is assumed that for the Scenario 1 the comissioning dates of both the
projects whose progressive rates are less and equal than 10% and the projects whose
progressive rates are not given are excepted uncertain. In addition the projects progressive
rate being more than 70% is assumed to be commissioned in 2009. Furthermore it is
assumed that the projects whose progressive rates are between 35% and 70% and which
have the capacity of

less than 100 MW will be comissioned in 2010


between 100 MW and 1000 MW will be comissioned in 2011 and
more than 1000 MW will be comissioned in 2012.

Besides the projects whose progressive rates are between 10% and 35% are assumed to be
comissioned 1 year forward of the year expected to be in service before.
Although the same methodology of the Scenario 1 is used for the Scenario 2, 15%, 40% and
80% are used instead of 10%, 35% and 70% respectively for the progressive rates.

Since EPDK did not give the commissioning date of private sector projects granted by
licence in monthly/yearly detail and project by project, these projects are assumed to start
operation from the beginning of the second part of commissioning year and then the
generations are taken into consideration in the balance tables according to this situation.
It is assumed that power plants under construction (2835.7 MW) by DS, Ambarl thermal
power plant being rehabilitated (840 MW) by EA and power plants granted by licence as
end of December 2008 and expected to be in service on proposed time (total installed
capacity, 11188.8 MW for Scenario 1 and 9047.1 MW Scenario 2) by EPDK will be in
service on proposed date within the period 2009-2016.
21

No import and export are being considered.


New additional capacities are not added to the system in this report, because the Generation
Expansion Planning Study hasnt been updated according to the variety (decreasing) of the
electricity energy demand being related to the economic crisis.
The year on which the shortage may occure is being determined by this study. By observing
this study results, investors might be able to decide new generation investment time.
Construction period of power plants should also be taken into consideration for new
investments.
Power plants in operation as end of the year 2008 are listed on ANNEX-1, power plants
which have been commissioned and decommissioned in 2008 are on ANNEX-2 and power
plants currently under construction and granted by licence and expected to be in service on
proposed time are listed as breakdown of the installed capacities by primary resources for
Scenario 1 and Scenario 2 on Table 15 and on Table 18 respectively and also as breakdown
of the project and firm generation capacity by primary resources for Scenario 1 and
Scenario 2 on Table 16 and 17 respectively and on Table 19 and 20 respectively.

22

Table 15 : Breakdown of Installed Capacity of Private Sector Power Plants under


construction and State-owned Power Plants under construction by Primary Resources.
Private Sector Power Plants

(Scenario 1)
Installed Capacity (MW)

RESOURCES

2009

Biogas

2010

2011

2012

2013

2014

2015

2016

TOTAL

2,6

Waste Gas (LFG)

2,6
11,4

7,8

19,2

410,3

1215,8

145,6

805,9

1911,9

Other Coal

187,1

Natural Gas

91,9

Fuel Oil

67,0

67,0

Lignite

1,7

1,7

Geothermal

3026,6
2955,3

54,9

54,9

Hydro

562,0

1024,7

1007,5

Wind

205,8

173,3

269,5

1173,0

1354,9

2501,1

TOTAL

1213,3

1818,7

4412,9
648,6

4946,4

1213,3

0,0

0,0

0,0

11188,8

State-owned Power Plants


Installed Capacity (MW)
RESOURCES

2009

2010

2011

2012

Thermal

2013

2014

2015

2016

840,0

Hydro

495,3

470,4

670,0

TOTAL

495,3

470,4

670,0

0,0

840,0

TOTAL
840,0

0,0

1200,0

2835,7

0,0 1200,0

3675,7

GRAND TOTAL
Installed Capacity (MW)
RESOURCES
Thermal
Hydro
Wind+Renewable
TOTAL

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

347,7

145,6

1216,3

3127,7

2053,3

0,0

0,0

0,0

6890,6

1057,3

1495,1

1677,5

1818,7

0,0

0,0

0,0 1200,0

7248,6

263,3

184,7

277,3

0,0

0,0

0,0

0,0

0,0

725,2

1668,3

1825,3

3171,1

4946,4

2053,3

0,0

0,0 1200,0

14864,5

NOTE: 2 x 150 MW units of Ambarl fuel oil fired power plant which is currently being
extended to be decommissioned in 2010 and new one to be commissioned as a natural gas
fired power plant with 840 MW (540 MW + 300 MW) total installed capacity in 2013 are
taken into consideration.

23

Table 16 : Breakdown of Project Generation of Private Sector Power Plants under


construction and State-owned Power Plants under construction by Primary Resources.
Private SectorPower Plants

(Scenario 1)
Project Generation (GWh)

RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

Biogas

9,9

9,9

0,0

0,0

0,0

0,0

0,0

0,0

19,8

Waste Gas (LFG)

0,0

43,8

73,8

30,0

0,0

0,0

0,0

0,0

147,5

Other Coal

595,2

595,2

1458,0

5778,0

8327,8 4007,8

0,0

0,0

20762,0

Natural Gas

352,1

932,0

3700,8 10795,2

7674,4

0,0

0,0

0,0

23454,5

Fuel Oil

195,1

195,1

0,0

0,0

0,0

0,0

0,0

0,0

390,2

4,2

4,2

0,0

0,0

0,0

0,0

0,0

0,0

8,4

187,7

187,7

0,0

0,0

0,0

0,0

0,0

0,0

375,5

1112,9 3084,1

3793,4

4775,6

2953,4

0,0

0,0

0,0

15719,4

810,0

486,6

0,0

0,0

0,0

0,0

2421,1

9836,0 21865,4 18955,6 4007,8

0,0

0,0

63298,5

Lignite
Geothermal
Hydro
Wind
TOTAL

400,5

724,0

2857,6 5776,0

State-owned Power Plants


Project Generation (GWh)
RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

0,0

0,0

0,0

5880,0

0,0

0,0

0,0

5880,0

Hydro

516,8 1964,4

1104,5

1500,3

0,0

0,0

0,0 3833,0

8919,0

TOTAL

516,8 1964,4

1104,5

1500,3

5880,0

0,0

0,0 3833,0

14799,0

Thermal

0,0

GRAND TOTAL
Project Generation (GWh)
RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

Thermal

1146,6 1726,5

5158,8 16573,2 21882,2 4007,8

0,0

0,0

50495,2

Hydro

1629,7 5048,5

4897,9

6275,9

2953,4

0,0

0,0 3833,0

24638,3

883,8

516,6

0,0

0,0

0,0

Wind+Renewable
TOTAL

598,2

965,4

3374,4 7740,4 10940,5 23365,7 24835,6 4007,8

24

0,0

2963,9

0,0 3833,0

78097,4

Tablo 17: Breakdown of Firm Generation of Private Sector Power Plants under
construction and State-owned Power Plants under construction by Primary Resources.
Private SectorPower Plants

(Scenario 1)
Firm Generation (GWh)

RESOURCES

2009
9,9

Biogas

2010
9,9

2011

2012

0,0

0,0

2013
0,0

2014
0,0

2015

2016

0,0

0,0

TOTAL

19,8

0,0

43,8

73,8

30,0

0,0

0,0

0,0

0,0

147,5

Other Coal

595,2

595,2

1458,0

5778,0

8327,8

4007,8

0,0

0,0

20762,0

Natural Gas

352,1

932,0

3700,8

10795,2

7674,4

0,0

0,0

0,0

23454,5

Fuel Oil

195,1

195,1

0,0

0,0

0,0

0,0

0,0

0,0

390,2

4,2

4,2

0,0

0,0

0,0

0,0

0,0

0,0

8,4

Waste Gas (LFG)

Lignite
Geothermal

187,7

187,7

0,0

0,0

0,0

0,0

0,0

0,0

375,5

Hydro

523,0

1449,5

1782,9

2244,5

1388,1

0,0

0,0

0,0

7388,1

Wind
TOTAL

340,5

615,4

688,5

413,6

0,0

0,0

0,0

0,0

2057,9

2207,7

4032,9

7703,9

19261,3

17390,3

4007,8

0,0

0,0

54604,1

State-owned Power Plants


Firm Generation (GWh)
RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

0,0

0,0

0,0

0,0

5606,4

0,0

0,0

0,0

5606,4

Hydro

371,9

1347,4

617,2

858,5

0,0

0,0

0,0

2459,0

5654,0

TOTAL

371,9

1347,4

617,2

858,5

5606,4

0,0

0,0

2459,0

11260,4

Thermal

GRAND TOTAL
Firm Generation (GWh)
RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

1146,6

1726,5

5158,8

16573,2

21608,6

4007,8

0,0

0,0

50221,6

Hydro

894,9

2796,9

2400,1

3103,0

1388,1

0,0

0,0

2459,0

13042,1

Wind+Renewable

538,1

856,8

762,3

443,6

0,0

0,0

0,0

0,0

2600,8

2579,6

5380,3

8321,1

20119,8

22996,7

4007,8

0,0

2459,0

65864,5

Thermal

TOTAL

25

Tablo 18: Breakdown of Installed Capacity of Private Sector Power Plants under
construction and State-owned Power Plants under construction by Primary Resources.
Private SectorPower Plants

(Scenario 2)
Installed Capacity (MW)

RESOURCES

2009

11,4

Waste Gas (LFG)


Natural Gas
Fuel Oil
Lignite
Geothermal
Hydro
Wind
TOTAL

2011

2012

2013

2014

2015

2016

2,6

Biogas
Other Coal

2010

187,1
91,9
67,0
1,7
47,4
412,5
172,8
983,0

78,6

7,8
410,3
872,9

7,5
893,3 956,2
183,8 202,0
1174,6 2449,3

607,9

1213,3
1025,0

1594,0
2201,9

2238,3

0,0

0,0

0,0

TOTAL

2,6
19,2
2418,7
2068,4
67,0
1,7
54,9
3856,1
558,6
9047,1

State-owned Power Plants


Installed Capacity (MW)
RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

840,0

840,0

Thermal
Hydro

495,3

470,4

670,0

TOTAL

495,3

470,4

670,0

0,0

840,0

TOTAL

0,0

1200,0

2835,7

0,0 1200,0

3675,7

GENEL TOPLAM
Installed Capacity (MW)
RESOURCES

2009

Hydro

347,7
907,8

Wind+Renewable

222,8

Thermal

TOTAL

1478,3

2010

2011

2012

2013

607,9
1594,0

3078,3
0,0

0,0
0,0

0,0
0,0
0,0 1200,0

209,8

0,0

0,0

0,0

0,0

0,0

635,2

1645,0 3119,3

2201,9

3078,3

0,0

0,0 1200,0

12722,8

78,6 1283,3
1363,7 1626,2
202,7

2014

2015

2016

TOTAL

5395,8
6691,8

NOTE: 2 x 150 MW units of Ambarl fuel oil fired power plant which is currently being
extended to be decommissioned in 2010 and new one to be commissioned as a natural gas
fired power plants with 840 MW (540 MW + 300 MW) total installed capacity in 2013 are
taken into consideration.

26

Tablo 19: Breakdown of Project Generation of Private Sector Power Plants under
construction and State-owned Power Plants under construction by Primary Resources.
Private SectorPower Plants

(Scenario 2)
Project Generation (GWh)

RESOURCES

2009
9,9

Biogas

2010
9,9

2011
0,0

2012
0,0

2013

2014

0,0

2015

2016

0,0

0,0

0,0

TOTAL

19,8

0,0

43,8

73,8

30,0

0,0

0,0

0,0

0,0

147,5

Other Coal

595,2

595,2

1458,0

3618,0

6167,8

4007,8

0,0

0,0

16442,0

Natural Gas

352,1

672,0

3700,8

3380,8

4200,0

4200,0

0,0

0,0

16505,7

Fuel Oil

195,1

195,1

0,0

0,0

0,0

0,0

0,0

0,0

390,2

4,2

4,2

0,0

0,0

0,0

0,0

0,0

0,0

8,4

Geothermal

156,2

187,7

31,5

0,0

0,0

0,0

0,0

0,0

375,5

Hydro

825,0

2579,1

3527,9

4338,1

2564,3

0,0

0,0

0,0

13834,5

713,3

360,2

0,0

0,0

0,0

0,0

2066,3

9505,3 11727,1

12932,1

8207,8

0,0

0,0

49790,0

Waste Gas (LFG)

Lignite

Wind
TOTAL

319,9

673,0

2457,6

4960,1

State-owned Power Plants


Project Generation (GWh)
RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

0,0

0,0

0,0

0,0

5880,0

0,0

0,0

0,0

5880,0

Hydro

516,8

1964,4

1104,5

1500,3

0,0

0,0

0,0

3833,0

8919,0

TOTAL

516,8

1964,4

1104,5

1500,3

5880,0

0,0

0,0

3833,0

14799,0

Thermal

GRAND TOTAL
Project Generation (GWh)

2009

2010

2011

2012

2013

2014

Thermal

1146,6

1466,5

5158,8

6998,8

16247,8

8207,8

0,0

0,0

39226,4

Hydro

1341,8

4543,5

4632,4

5838,4

2564,3

0,0

0,0

3833,0

22753,5

486,0

914,4

818,6

390,2

0,0

0,0

0,0

0,0

2609,1

6924,5 10609,8 13227,4

18812,1

8207,8

0,0

3833,0

64589,0

RESOURCES

Wind+Renewable
TOTAL

2974,4

27

2015

2016

TOPLAM

Tablo 20: Breakdown of Firm Generation of Private Sector Power Plants under
construction and State-owned Power Plants under construction by Primary Resources.
Private SectorPower Plants

(Scenario 2)
Firm Generation (GWh)

RESOURCES
Biogas
Waste Gas (LFG)
Other Coal
Natural Gas
Fuel Oil
Lignite
Geothermal
Hydro
Wind

9,9
9,9
0,0
0,0
43,8
73,8
595,2
595,2 1458,0
352,1
672,0 3700,8
195,1
195,1
0,0
4,2
4,2
0,0
156,2
187,7
31,5
387,8 1212,2 1658,1
271,9
572,0
606,3
1972,4 3492,2 7528,5

0,0
0,0
0,0
30,0
0,0
0,0
3618,0
6167,8 4007,8
3380,8
4200,0 4200,0
0,0
0,0
0,0
0,0
0,0
0,0
0,0
0,0
0,0
2038,9
1205,2
0,0
306,1
0,0
0,0
9373,9 11573,0 8207,8

0,0
0,0
0,0
0,0
0,0
0,0
0,0
0,0
0,0
0,0

TOTAL
0,0
147,5
0,0
16442,0
0,0
16505,7
0,0
390,2
0,0
8,4
0,0
375,5
0,0
6502,2
0,0
1756,4
0,0
0,0
42147,8

TOTAL
State-owned Power Plants
Firm Generation (GWh)
RESOURCES

2009

2010

2011

2012

2013

2014

2015

2016

TOTAL

0,0

0,0

0,0

5606,4

0,0

0,0

0,0

5606,4

Hydro

371,9 1347,4

617,2

858,5

0,0

0,0

0,0 2459,0

5654,0

TOTAL

371,9 1347,4

617,2

858,5

5606,4

0,0

0,0 2459,0

11260,4

Thermal

0,0

GRAND TOTAL
Firm Generation (GWh)
RESOURCES
Thermal
Hydro
Wind+Renewable
TOTAL

2009

2010

2011

1146,6 1466,5 5158,8


759,7 2559,6 2275,3
438,0

813,5

711,6

2012

2013

2014

6998,8 15974,2 8207,8


2897,4
1205,2
0,0
336,1

0,0

0,0

2344,3 4839,6 8145,7 10232,4 17179,4 8207,8

2015

2016

0,0
0,0
0,0 2459,0

TOPLAM

38952,8
12156,2

0,0

2299,2

0,0 2459,0

53408,2

0,0

The installed capacities and generation data of DS power plants which are currently under construction ,
Ambarl natural gas fired power plant extended by EA and power plants granted by licence as end of
December 2008 started the construction but not in operation yet according to January 2009 Progress
Report of EPDK for both scenarios are listed on ANNEX-3.
The breakdown of total installed capacity which consists existing capacity as end of the year 2008 and new
additional capacities which are under construction and granted by licence and expected to be in service on
proposed date according to Scenario 1 by primary resources and by utilities are listed on Table 21 and
Figure 9 and also according to Scenario 2 are on Table 24 and Figure 10.

28

Table 21 : Breakdown of Installed Capacity by Utilities and by Primary Resources


(Scenario 1)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(MW)
2009

EA and AFFILIATED
PARTNERSHIP POWER
PLANTS

POWER PLANTS
UNDER BO CONTRACT

2014

2015

2016

2017

2018

FUEL OIL

380

380

380

380

380

380

DIESEL

181

181

181

181

181

181

181

181

181

181

HARD COAL

300

300

300

300

300

300

300

300

300

300

LIGNITE

7461 7461

7461

7461

7461

7461

7461

7461

7461

7461

NATURAL GAS

3903 3903

3903

3903

4743

4743

4743

4743

4743

4743

HYDRO

11951

12422

13092

13092

13092

13092

13092

14292

14292

14292

TOTAL

24476

24647

25317

25317

26157

26157

26157

27357

27357

27357

620

620

620

620

620

620

620

620

620

30

30

30

30

30

30

30

30

650

650

650

650

650

650

650

650

NATURAL GAS

4782 4782

4782

4782

4782

4782

4782

4782

4782

4782

IMPORTED COAL

1320 1320

1320

1320

1320

1320

1320

1320

1320

1320

TOTAL

6102 6102

6102

6102

6102

6102

6102

6102

6102

6102

NATURAL GAS

1450 1450

1450

1450

1450

1450

1450

1450

1450

1450

982

982

982

982

982

982

982

982

17

17

17

17

17

17

17

17

2449

2449

2449

2449

2449

2449

2449

2449

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

799

799

799

799

799

799

799

799

799

10

10

10

10

10

10

10

10

LIGNITE

620

30 30

HYDRO
TOTAL

FUEL OIL

650

982

982

2449 2449
263
0

TOTAL

263

DIESEL

650

17 17

DIESEL
FUEL OIL

799

10 10

IMPORTED COAL

196

196

196

196

196

196

196

196

196

196

HARD COAL

255

255

255

255

255

255

255

255

255

255

LIGNITE

178

178

178

178

178

178

178

178

178

178

52

52

52

52

52

52

52

52

1388

1388

1388

1388

1388

1388

1388

1388

LPG
NATURAL GAS

52 52
1388 1388

BOGAS

13 13

13

13

13

13

13

13

13

13

NAPHTA

71 71

71

71

71

71

71

71

71

71

OTHER

22 22

22

22

22

22

22

22

22

22

554

554

554

554

554

554

554

554

554

3538

3538

3538

3538

3538

3538

3538

3538

358

358

358

358

358

358

358

358

15

15

15

15

15

15

15

15

HYDRO
WIND
TOTAL
FUEL OIL
DIESEL

GENERATION
COMPANIES GRANTED
BY LICENCE

2013

380

TOTAL

AUTOPRODUCERS

2012

380

HYDRO
POWER PLANTS
UNDER BOT CONTRACT WIND

MOBILE PLANTS

2011

380

GEOTHERMAL

POWER PLANTS
UNDER TOR
CONTRACT

2010

680

554
1

3538 3538
358

358

15 15

LIGNITE

H.COAL+ASPHALTIT

322

732

1948

3162

3162

3162

3162

3162

3162

4123

6034

6034

6034

6034

6034

6034

6034

107

107

107

107

107

107

107

107

85

85

85

85

85

85

85

85

3401

5220

5220

5220

5220

5220

5220

5220

47

47

47

47

47

47

47

47

994

994

994

994

994

994

994

994

9863

14810

16023

16023

16023

16023

16023

16023

48182

53128

55182

55182

55182

56382

56382

56382

IMPORT COAL
NATURAL GAS
NAPHTA
GEOTHERMAL
HYDRO
BOGAS+WASTE
WIND
TOTAL

GRAND TOTAL

322

3171 3317
107

107

85 85
1369 2394
28 39
551

724

6007 7362
43485

45011

29

Table 21 (Cont.) : Breakdown of Total Installed Capacity by Primary Resources


(Scenario 1)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(MW)
YEAR
LIGNITE
HARD COAL+ASPHALTIT
IMPORTED COAL
NATURAL GAS
GEOTHERMAL
FUEL OIL
DIESEL
OTHER
THERMAL TOTAL
BOGAS+WASTE
HYDRO
WIND
TOTAL

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

8260
8260
8260
8260
8260
8260
8260
8260
8260
8260
555
555
555
555
555
555
555
555
555
555
1838
1838
2248
3464
4678
4678
4678
4678
4678
4678
14693 14839 15645 17556 18396 18396 18396 18396 18396 18396
85
85
85
85
85
85
85
85
85
85
2100
1800
1800
1800
1800
1800
1800
1800
1800
1800
206
206
206
206
206
206
206
206
206
206
251
251
251
251
251
251
251
251
251
251
27989 27835 29051 32179 34232 34232 34232 34232 34232 34232
41
52
60
60
60
60
60
60
60
60
14886 16381 18058 19877 19877 19877 19877 21077 21077 21077
570

743

1012

1012

1012

1012

1012

1012

1012

1012

43485 45011 48182 53128 55182 55182 55182 56382 56382 56382

Figure 9 : Breakdown of Total Installed Capacity by Utilities (Scenario 1)

Project and firm generation capacities of existing power plants as end of the year 2008, under
construction state-owned power plants and under construction private sector power plants granted
by licence and expected to be in service on proposed date by utilities and by primary resources are
indicated according to Scenario 1 on Table 22 and on Table 23 respectively and according to
Scenario 2 on Table 25 and Table 26 respectively.

30

Table 22 : Breakdown of Project Generation Capacity by Utilities and by Primary


Resources (Scenario 1)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
2009

FUEL OIL
DIESEL
EA and
HARD COAL
AFFILIATED
LIGNITE
PARTNERSHIP
NATURAL GAS
POWER PLANTS
HYDRO
TOTAL
POWER PLANTS LIGNITE
UNDER TOR
HYDRO
CONTRACT
TOTAL
POWER PLANTS NATURAL GAS
UNDER BO
IMPORTED COAL
CONTRACT
TOTAL
NATURAL GAS
POWER PLANTS
HYDRO
UNDER BOT
WIND
CONTRACT
TOTAL
FUEL OIL
MOBILE PLANTS
TOTAL
FUEL OIL
DIESEL
IMPORTED COAL
HARD COAL
LIGNITE
LPG
AUTOPRODUCERS NATURAL GAS
BOGAS
NAPHTA
OTHER
HYDRO
WIND
TOTAL
FUEL OIL
DIESEL
LIGNITE
H.COAL+ASPHALTIT
IMPORT COAL
GENERATION
COMPANIES
NAPHTA
GRANTED BY
NATURAL GAS
LICENCE
GEOTHERMAL
HYDRO
BOGAS+WASTE
WIND
TOTAL
GRAND TOTAL

2010

2011

2012

2013

2014

2015

2016

2017

2018

4760

4760

4760

4760

4760

4760

4760

4760

4760

4760

1260

1260

1260

1260

1260

1260

1260

1260

1260

1260

1950

1950

1950

1950

1950

1950

1950

1950

1950

1950

48497

48497

48497

48497

48497

48497

48497

48497

48497

48497

27320

27320

27320

27320

33200

33200

33200

33200

33200

33200

40165

42129

43234

44734

44734

44734

44734

48567

48567

48567

123952

125916

127021

128521

134401

134401

134401

138234

138234

138234

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

37787

38885

38653

38133

37947

37683

37485

38175

37973

33247

9135

9092

9309

9065

9025

8526

8775

9466

9031

9078

46922

47978

47962

47198

46972

46208

46260

47641

47005

42325

11245

10777

9974

11012

10777

9974

10834

10777

10146

11002

3479

3576

3527

3477

3428

3379

3340

3385

3385

3385

50

49

49

49

49

49

49

49

49

49

14774

14402

13551

14538

14254

13403

14223

14211

13580

14436

1752

1752

5066

5066

5066

5066

5066

5066

5066

5066

5066

5066

73

73

73

73

73

73

73

73

73

73

1470

1470

1470

1470

1470

1470

1470

1470

1470

1470

1072

1072

1072

1072

1072

1072

1072

1072

1072

1072

436

436

436

436

436

436

436

436

436

436

401

401

401

401

401

401

401

401

401

401

9749

9749

9749

9749

9749

9749

9749

9749

9749

9749

72

72

72

72

72

72

72

72

72

72

546

546

546

546

546

546

546

546

546

546

145

145

145

145

145

145

145

145

145

145

1688

1688

1688

1688

1688

1688

1688

1688

1688

1688

20720

20720

20720

20720

20720

20720

20720

20720

20720

20720

2270

2465

2465

2465

2465

2465

2465

2465

2465

2465

75

75

75

75

75

75

75

75

75

75

1543

2138

3596

9374

17702

21710

21710

21710

21710

21710

571

571

571

571

571

571

571

571

571

571

24223

25155

28856

39651

47326

47326

47326

47326

47326

47326

399

587

587

587

587

587

587

587

587

587

4330

7414

11207

15983

18936

18936

18936

18936

18936

18936

199

253

327

357

357

357

357

357

357

357

1591

2315

3125

3612

3612

3612

3612

3612

3612

3612

35206

40982

50818

72683

91639

95647

95647

95647

95647

95647

246949

253501

263617

287254

311628

313931

314754

319998

318779

315004

31

Table 22 (Cont.) : Breakdown of Total Project Generation Capacity by Primary Resources


(Scenario 1)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
2010

2011

2012

2013

2014

2015

2016

2017

2018

52560
LIGNITE
3022
H.COAL+ASPHALTIT
12148
IMPORTED COAL
110325
NATURAL GAS
399
GEOTHERMAL
13848
FUEL OIL
1408
DIESEL
1663
OTHER
195372
THERMAL TOTAL
271
BOGAS+WASTE
49662
HYDRO
1643
WIND

52445
3022
12701
111887
587
12291
1408
1663
196003
325
54807

52486
3022
14376
114553
587
12291
1408
1663
200385
399
59657

52534
3022
19910
125866
587
12291
1408
1663
217280
429
65882

52583
3022
28197
138999
587
12291
1408
1663
238750
429
68787

52493
3022
31706
137933
587
12291
1408
1663
241102
429
68738

52445
3022
31955
138593
587
12291
1408
1663
241964
429
68699

52486
3022
32646
139227
587
12291
1408
1663
243330
429
72577

52534
3022
32211
138394
587
12291
1408
1663
242110
429
72577

52583
3022
32258
134525
587
12291
1408
1663
238335
429
72577

2366

3176

3663

3663

3663

3663

3663

3663

3663

246949

253501

263617

287254

311628

313931

314754

319998

318779

315004

YEAR

TOTAL

2009

32

Table 23 : Breakdown of Firm Generation Capacity by Utilities and by Primary Resources


(Scenario 1)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
2009

FUEL OIL
DIESEL
EA and
HARD COAL
AFFILIATED
LIGNITE
PARTNERSHIP
NATURAL GAS
POWER PLANTS
HYDRO
TOTAL
LIGNITE
POWER PLANTS
UNDER TOR
HYDRO
CONTRACT
TOTAL
NATURAL GAS
POWER PLANTS
UNDER BO
IMPORTED COAL
CONTRACT
TOTAL
NATURAL GAS
POWER PLANTS
HYDRO
UNDER BOT
WIND
CONTRACT
TOTAL
FUEL OIL
MOBILE PLANTS
TOTAL
FUEL OIL
DIESEL
IMPORTED COAL
HARD COAL
LIGNITE
LPG
AUTOPRODUCERS NATURAL GAS
BOGAS
NAPHTA
OTHER
HYDRO
WIND
TOTAL
FUEL OIL
DIESEL
LIGNITE
H.COAL+ASPHALTIT
IMPORT COAL
GENERATION
COMPANIES
NAPHTA
GRANTED BY
NATURAL GAS
LICENCE
GEOTHERMAL
HYDRO
BOGAS+WASTE
WIND
TOTAL
GRAND TOTAL

2010

2011

2012

2013

2014

2015

2016

2017

2018

2625

2638

2638

2638

2638

2638

2638

2638

2638

2638

1071

1051

1051

1051

1051

1051

1051

1051

1051

1051

1967

1537

1221

1537

1840

1840

1840

1840

1840

1840

37041

36435

35972

38160

44062

44062

44062

44062

44062

44574

22659

23967

25919

24614

31526

30223

31526

31005

31526

31005

24531

25879

26496

27354

27354

27354

27354

29813

29813

29813

89896

91508

93297

95354

108470

107167

108470

110408

110929

110920

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

37787

38885

38653

38133

37947

37683

37485

38175

37973

33247

9135

9092

9309

9065

9025

8526

8775

9466

9031

9078

46922

47978

47962

47198

46972

46208

46260

47641

47005

42325

11245

10777

9974

11012

10777

9974

10834

10777

10146

11002

3479

3576

3527

3477

3428

3379

3340

3385

3385

3385

50

49

49

49

49

49

49

49

49

49

14774

14402

13551

14538

14254

13403

14223

14211

13580

14436

1000

1000

5066

5066

5066

5066

5066

5066

5066

5066

5066

5066
72,7

72,7

72,7

72,7

72,7

72,7

72,7

72,7

72,7

72,7

1470

1470

1470

1470

1470

1470

1470

1470

1470

1470

1072

1072

1072

1072

1072

1072

1072

1072

1072

1072

436

436

436

436

436

436

436

436

436

436

401

401

401

401

401

401

401

401

401

401

9749

9749

9749

9749

9749

9749

9749

9749

9749

9749

72

72

72

72

72

72

72

72

72

72

546

546

546

546

546

546

546

546

546

546

145

145

145

145

145

145

145

145

145

145

1223

1223

1223

1223

1223

1223

1223

1223

1223

1223

20255

20255

20255

20255

20255

20255

20255

20255

20255

20255

2270

2465

2465

2465

2465

2465

2465

2465

2465

2465

75

75

75

75

75

75

75

75

75

75

1543

2138

3596

9374

17702

21710

21710

21710

21710

21710

571

571

571

571

571

571

571

571

571

571

24223

25155

28856

39651

47326

47326

47326

47326

47326

47326

391

579

579

579

579

579

579

579

579

579

2381

3808

5591

7835

9223

9223

9223

9223

9223

9223

185

239

313

343

343

343

343

343

343

343

1400

2015

2703

3117

3117

3117

3117

3117

3117

3117

33044
209514

37054

44757

64019

81409

85417

85417

85417

85417

85417

214700

223368

244957

275002

276003

278128

281477

280779

276995

33

Table 23 (Cont.) : Breakdown of Total Firm Generation Capacity by Primary Resources


(Scenario 1)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

LIGNITE
HARD COAL+ASPHALTIT
IMPORTED COAL
NATURAL GAS
GEOTHERMAL
FUEL OIL
DIESEL
OTHER
THERMAL TOTAL
BOGAS+WASTE
HYDRO

41105
3039
12148
105664
391
10961
1219
1663
176190
257
31615

40384
2609
12701
108534
579
10169
1199
1663
177837
311
34486

39961
2293
14376
113152
579
10169
1199
1663
183392
385
36837

42198
2609
19910
123159
579
10169
1199
1663
201485
415
39890

48148
2912
28197
137324
579
10169
1199
1663
230190
415
41229

48058
2912
31706
134956
579
10169
1199
1663
231240
415
41180

48010
2912
31955
136919
579
10169
1199
1663
233405
415
41141

48051
2912
32646
137032
579
10169
1199
1663
234250
415
43645

48100
2912
32211
136720
579
10169
1199
1663
233551
415
43645

48660
2912
32258
132329
579
10169
1199
1663
229768
415
43645

WIND
TOTAL

1452

2066

2755

3168

3168

3168

3168

3168

3168

3168

209514

214700

223368

244957

275002

276003

278128

281477

280779

276995

34

Table 24: Breakdown of Installed Capacity by Utilities and by Primary Resources


(Scenario 2)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(MW)
2009

EA and
AFFILIATED
PARTNERSHIP
POWER PLANTS

POWER PLANTS
UNDER TOR
CONTRACT
POWER PLANTS
UNDER BO
CONTRACT
POWER PLANTS
UNDER BOT
CONTRACT

FUEL OIL
DIESEL
HARD COAL
LIGNITE
NATURAL GAS
HYDRO
TOTAL
LIGNITE
HYDRO
TOTAL
NATURAL GAS
IMPORTED COAL
TOTAL
NATURAL GAS
HYDRO
WIND

TOTAL
FUEL OIL
MOBILE PLANTS
TOTAL
FUEL OIL
DIESEL
IMPORTED COAL
HARD COAL
LIGNITE
LPG
AUTOPRODUCERS NATURAL GAS
BOGAS
NAPHTA
OTHER
HYDRO
WIND

2010

2011

2012

2013

2014

2015

2016

2017

2018

680

380

380

380

380

380

380

380

380

380

181

181

181

181

181

181

181

181

181

181

300

300

300

300

300

300

300

300

300

300

7461

7461

7461

7461

7461

7461

7461

7461

7461

7461

3903

3903

3903

3903

4743

4743

4743

4743

4743

4743

11951

12422

13092

13092

13092

13092

13092

14292

14292

14292

24476

24647

25317

25317

26157

26157

26157

27357

27357

27357

620

620

620

620

620

620

620

620

620

620

30

30

30

30

30

30

30

30

30

30

650

650

650

650

650

650

650

650

650

650

4782

4782

4782

4782

4782

4782

4782

4782

4782

4782

1320

1320

1320

1320

1320

1320

1320

1320

1320

1320

6102

6102

6102

6102

6102

6102

6102

6102

6102

6102

1450

1450

1450

1450

1450

1450

1450

1450

1450

1450

982

982

982

982

982

982

982

982

982

982

17

17

17

17

17

17

17

17

17

17

2449

2449

2449

2449

2449

2449

2449

2449

2449

2449

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

263

799

799

799

799

799

799

799

799

799

799

10

10

10

10

10

10

10

10

10

10

196

196

196

196

196

196

196

196

196

196

255

255

255

255

255

255

255

255

255

255

178

178

178

178

178

178

178

178

178

178

52

52

52

52

52

52

52

52

52

52

1388

1388

1388

1388

1388

1388

1388

1388

1388

1388

13

13

13

13

13

13

13

13

13

13

71

71

71

71

71

71

71

71

71

71

22

22

22

22

22

22

22

22

22

22

554

554

554

554

554

554

554

554

554

554

TOTAL
FUEL OIL
DIESEL
LIGNITE
H.COAL+ASPHALTIT
IMPORT COAL
NATURAL GAS
NAPHTA
GEOTHERMAL
HYDRO
BOGAS+WASTE
WIND

3538

3538

3538

3538

3538

3538

3538

3538

3538

3538

358

358

358

358

358

358

358

358

358

358

15

15

15

15

15

15

15

15

15

15

322

322

732

1340

2554

2554

2554

2554

2554

2554

3171

3250

4123

4123

5148

5148

5148

5148

5148

5148

107

107

107

107

107

107

107

107

107

107

77

85

85

85

85

85

85

85

85

85

1220

2113

3069

4663

4663

4663

4663

4663

4663

4663

28

39

47

47

47

47

47

47

47

47

518

702

904

904

904

904

904

904

904

904

TOTAL

5817

6992

9441

11643

13881

13881

13881

13881

13881

13881

GRAND TOTAL

43295

44640

47760

49962

53040

53040

53040

54240

54240

54240

GENERATION
COMPANIES
GRANTED BY
LICENCE

35

Table 24 (Cont.) : Breakdown of Total Installed Capacity by Primary Resources


(Scenario 2)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(MW)
YEAR
LIGNITE
HARD COAL+ASPHALTIT
IMPORTED COAL
NATURAL GAS

2009
8260

2010
8260

2011
8260

2012
8260

2013
8260

2014
8260

2015
8260

2016
8260

2017
8260

2018
8260

555

555

555

555

555

555

555

555

555

555

1838

1838

2248

2856

4070

4070

4070

4070

4070

4070

14693

14772

15645

15645

17510

17510

17510

17510

17510

17510

77

85

85

85

85

85

85

85

85

85

2100

1800

1800

1800

1800

1800

1800

1800

1800

1800

DIESEL

206

206

206

206

206

206

206

206

206

206

OTHER

251

251

251

251

251

251

251

251

251

251

27982

27768

29051

29659

32737

32737

32737

32737

32737

32737

GEOTHERMAL
FUEL OIL

THERMAL TOTAL
BOGAS+WASTE
HYDRO
WIND
TOTAL

41

52

60

60

60

60

60

60

60

60

14736

16100

17726

19320

19320

19320

19320

20520

20520

20520

537

720

922

922

922

922

922

922

922

922

43295

44640

47760

49962

53040

53040

53040

54240

54240

54240

Figure 10: Breakdown of Total Installed Capacity by Utilities (Scenario 2)

36

Table 25: Breakdown of Project Generation Capacity by Utilities and by Primary Resources
(Scenario 2)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
2009

EA and
AFFILIATED
PARTNERSHIP
POWER PLANTS

POWER PLANTS
UNDER TOR
CONTRACT
POWER PLANTS
UNDER BO
CONTRACT
POWER PLANTS
UNDER BOT
CONTRACT
MOBILE PLANTS

FUEL OIL
DIESEL
HARD COAL
LIGNITE
NATURAL GAS
HYDRO
TOTAL
LIGNITE
HYDRO
TOTAL
NATURAL GAS
IMPORTED COAL
TOTAL
NATURAL GAS
HYDRO
WIND
TOTAL
FUEL OIL
TOTAL

FUEL OIL
DIESEL
IMPORTED COAL
HARD COAL
LIGNITE
LPG
AUTOPRODUCERS NATURAL GAS
BOGAS
NAPHTA
OTHER
HYDRO
WIND

GENERATION
COMPANIES
GRANTED BY
LICENCE

TOTAL
FUEL OIL
DIESEL
LIGNITE
H.COAL+ASPHALTIT
IMPORT COAL
NAPHTA
NATURAL GAS
GEOTHERMAL
HYDRO
BOGAS+WASTE
WIND
TOTAL

GRAND TOTAL

2010

2011

2012

2013

2014

2015

2016

2017

2018

4760

4760

4760

4760

4760

4760

4760

4760

4760

4760

1260

1260

1260

1260

1260

1260

1260

1260

1260

1260

1950

1950

1950

1950

1950

1950

1950

1950

1950

1950

48497

48497

48497

48497

48497

48497

48497

48497

48497

48497

27320

27320

27320

27320

33200

33200

33200

33200

33200

33200

40165

42129

43234

44734

44734

44734

44734

48567

48567

48567

123952

125916

127021

128521

134401

134401

134401

138234

138234

138234

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

37787

38885

38653

38133

37947

37683

37485

38175

37973

33247

9135

9092

9309

9065

9025

8526

8775

9466

9031

9078

46922

47978

47962

47198

46972

46208

46260

47641

47005

42325

11245

10777

9974

11012

10777

9974

10834

10777

10146

11002

3479

3576

3527

3477

3428

3379

3340

3385

3385

3385

50

49

49

49

49

49

49

49

49

49

14774

14402

13551

14538

14254

13403

14223

14211

13580

14436

1752

1752

5066

5066

5066

5066

5066

5066

5066

5066

5066

5066

73

73

73

73

73

73

73

73

73

73

1470

1470

1470

1470

1470

1470

1470

1470

1470

1470

1072

1072

1072

1072

1072

1072

1072

1072

1072

1072

436

436

436

436

436

436

436

436

436

436

401

401

401

401

401

401

401

401

401

401

9749

9749

9749

9749

9749

9749

9749

9749

9749

9749

72

72

72

72

72

72

72

72

72

72

546

546

546

546

546

546

546

546

546

546

145

145

145

145

145

145

145

145

145

145

1688

1688

1688

1688

1688

1688

1688

1688

1688

1688

20720

20720

20720

20720

20720

20720

20720

20720

20720

20720

2270

2465

2465

2465

2465

2465

2465

2465

2465

2465

75

75

75

75

75

75

75

75

75

75

1543

2138

3596

7214

13382

17390

17390

17390

17390

17390

571

571

571

571

571

571

571

571

571

571

24223

24895

28596

31977

36177

40377

40377

40377

40377

40377

367

555

587

587

587

587

587

587

587

587

4042

6621

10149

14487

17051

17051

17051

17051

17051

17051

199

253

327

357

357

357

357

357

357

357

1510

2183

2897

3257

3257

3257

3257

3257

3257

3257

34806

39766

49271

60998

73930

82138

82138

82138

82138

82138

246549

252285

262070

275569

293919

300422

301246

306489

305270

301495

37

Table 25 (Cont.): Breakdown of Total Project Generation Capacity by Primary


Resources (Scenario 2)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

52560

52445

52486

52534

52583

52493

52445

52486

52534

52583

3022

3022

3022

3022

3022

3022

3022

3022

3022

3022

12148

12701

14376

17750

23877

27386

27635

28326

27891

27938

NATURAL GAS

110325

111627

114293

118191

127850

130984

131645

132278

131445

127576

GEOTHERMAL

367

555

587

587

587

587

587

587

587

587

13848

12291

12291

12291

12291

12291

12291

12291

12291

12291

DIESEL

1408

1408

1408

1408

1408

1408

1408

1408

1408

1408

OTHER

1663

1663

1663

1663

1663

1663

1663

1663

1663

1663

195341

195711

200125

207446

223281

229833

230695

232061

230842

227067

YEAR
LIGNITE
H.COAL+ASPHALTIT
IMPORTED COAL

FUEL OIL

THERMAL TOTAL
BOGAS+WASTE
HYDRO
WIND
TOTAL

271

325

399

429

429

429

429

429

429

429

49374

54015

58598

64387

66902

66853

66814

70692

70692

70692

1563

2235

2948

3308

3308

3308

3308

3308

3308

3308

246549

252285

262070

275569

293919

300422

301246

306489

305270

301495

38

Table 26: Breakdown of Firm Generation Capacity by Utilities and Primary Resources
(Scenario 2)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
2009

FUEL OIL
DIESEL
EA and
HARD COAL
AFFILIATED
LIGNITE
PARTNERSHIP
POWER PLANTS NATURAL GAS
HYDRO
TOTAL
POWER PLANTS LIGNITE
UNDER TOR
HYDRO
CONTRACT
TOTAL
POWER PLANTS NATURAL GAS
UNDER BO
IMPORTED COAL
CONTRACT
TOTAL
NATURAL GAS
POWER PLANTS
HYDRO
UNDER BOT
WIND
CONTRACT
TOTAL
FUEL OIL
MOBILE PLANTS
TOTAL
FUEL OIL
DIESEL
IMPORTED COAL
HARD COAL
LIGNITE
LPG
AUTOPRODUCERS NATURAL GAS
BOGAS
NAPHTA
OTHER
HYDRO
WIND
TOTAL
FUEL OIL
DIESEL
LIGNITE
H.COAL+ASPHALTIT
IMPORT COAL
GENERATION
NAPHTA
COMPANIES
GRANTED BY
NATURAL GAS
LICENCE
GEOTHERMAL
HYDRO
BOGAS+WASTE
WIND
TOTAL
GRAND TOTAL

2010

2011

2012

2013

2014

2015

2016

2017

2018

2625

2638

2638

2638

2638

2638

2638

2638

2638

2638

1071

1051

1051

1051

1051

1051

1051

1051

1051

1051

1967

1537

1221

1537

1840

1840

1840

1840

1840

1840

37041

36435

35972

38160

44062

44062

44062

44062

44062

44574

22659

23967

25919

24614

31526

30223

31526

31005

31526

31005

24531

25879

26496

27354

27354

27354

27354

29813

29813

29813

89896

91508

93297

95354

108470

107167

108470

110408

110929

110920

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

3624

3504

3546

3594

3642

3553

3504

3546

3594

3642

37787

38885

38653

38133

37947

37683

37485

38175

37973

33247

9135

9092

9309

9065

9025

8526

8775

9466

9031

9078

46922

47978

47962

47198

46972

46208

46260

47641

47005

42325

11245

10777

9974

11012

10777

9974

10834

10777

10146

11002

3479

3576

3527

3477

3428

3379

3340

3385

3385

3385

50

49

49

49

49

49

49

49

49

49

14774

14402

13551

14538

14254

13403

14223

14211

13580

14436

1000

1000

5066

5066

5066

5066

5066

5066

5066

5066

5066

5066

72,7

72,7

72,7

72,7

72,7

72,7

72,7

72,7

72,7

72,7

1470

1470

1470

1470

1470

1470

1470

1470

1470

1470

1072

1072

1072

1072

1072

1072

1072

1072

1072

1072

436

436

436

436

436

436

436

436

436

436

401

401

401

401

401

401

401

401

401

401

9749

9749

9749

9749

9749

9749

9749

9749

9749

9749

72

72

72

72

72

72

72

72

72

72

546

546

546

546

546

546

546

546

546

546

145

145

145

145

145

145

145

145

145

145

1223

1223

1223

1223

1223

1223

1223

1223

1223

1223

20255

20255

20255

20255

20255

20255

20255

20255

20255

20255

2270

2465

2465

2465

2465

2465

2465

2465

2465

2465

75

75

75

75

75

75

75

75

75

75

1543

2138

3596

7214

13382

17390

17390

17390

17390

17390

571

571

571

571

571

571

571

571

571

571

24223

24895

28596

31977

36177

40377

40377

40377

40377

40377

359

547

579

579

579

579

579

579

579

579

2246

3435

5093

7132

8337

8337

8337

8337

8337

8337

185

239

313

343

343

343

343

343

343

343

1331

1903

2509

2815

2815

2815

2815

2815

2815

2815

32809

36277

43806

53180

64753

72961

72961

72961

72961

72961

209278

213924

222416

234119

258346

263547

265672

269021

268323

264539

39

Table 26 (Cont.) : Breakdown of Firm Generation Capacity by Utilities and Primary


Resources
(Scenario 2)
(Including Existing, State-owned underconstruction and Private Sector under construction
granted by licence and expected to be in service on proposed time Power Plants)
(GWh)
2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

41105

40384

39961

42198

48148

48058

48010

48051

48100

48660

3039

2609

2293

2609

2912

2912

2912

2912

2912

2912

12148

12701

14376

17750

23877

27386

27635

28326

27891

27938

NATURAL GAS

105664

108274

112892

115485

126176

128007

129970

130083

129771

125380

GEOTHERMAL

359

547

579

579

579

579

579

579

579

579

10961

10169

10169

10169

10169

10169

10169

10169

10169

10169

DIESEL

1219

1199

1199

1199

1199

1199

1199

1199

1199

1199

OTHER

1663

1663

1663

1663

1663

1663

1663

1663

1663

1663

176158

177545

183132

191651

214722

219972

222136

222981

222283

218499

257

311

385

415

415

415

415

415

415

415

31479

34114

36340

39187

40343

40294

40255

42759

42759

42759

1383

1954

2560

2867

2867

2867

2867

2867

2867

2867

209278

213924

222416

234119

258346

263547

265672

269021

268323

264539

YEAR
LIGNITE
HARD COAL+ASPHALTIT
IMPORTED COAL

FUEL OIL

THERMAL TOTAL
BOGAS+WASTE
HYDRO
WIND
TOTAL

40

VI.

RESULTS

VI.I. Case I A (High Demand Scenario 1)


In this section the power plants which are

Existing as end of the year 2008,

State owned under construction and

Private sector owned under construction granted by licence and expected to be in service on
proposed date based on January 2009 Progress Report of EPDK and prepared according to
Scenario 1 by EPDK,

considered with High Demand Series. By taking into consideration the effects of the economic crisis,
Demand Series have been revized by ETKB and the generation demand is expected to reach 202.7 TWh in
2010 and 357.2 TWh in 2018. The supply and demand situation according to these data is calculated:
According to above situation, peak demand can be covered in the all study period. When the generation
capacity is considered, the energy demand can not be covered in 2015 according to firm generation
capacity and in 2017 according to project generation capacity.
The development of the existing capacity, the state-owned capacity under construction and the private
sector owned capacity under construction granted by licence and expected to be in service on the proposed
time, covering the increasing demand by years is indicated on Table 27.
Beside this, not only the development of total installed capacity consisting of the existing, the state owned
under construction and the private sector owned under construction granted by licence and expected to be
in service on proposed date but also the development of the capacity reserves after covering the peak load
with the power plants which are;

only existing capacity,

existing capacity + state owned capacity under construction and

existing capacity + state owned capacity under construction + private sector owned under
construction capacity granted by licence and expected to be in service on proposed date

are submitted on Table 27 and the year is determined in which new generation facilities will be needed.
When the existing power plants are considered solely, capacity reserve starts from 39.9% in 2009 and
continuously decreases and the peak demand exceeds the total installed capacity in 2015 by reaching to
6.6%. According to the increase of peak demand the capacity reserve reaches to 24.6% in year 2018
with the existing capacity as end of the year 2008.
When the sum of existing capacity and state-owned capacity under construction are considered, the
capacity reserve is 41.5% in 2009, drops to 1% in 2015 and reaches to 17.9% in 2018.
When existing capacity, state owned capacity under construction and private sector owned under
construction capacity granted by licence and expected to be in service on proposed date are examined
together, capacity reserve is 45.4% in 2009 and decreases to 2.4% in 2018.
In spide of no shortage in the capacity reserve up to 2018, new additional capacity will be necessary to be
commissioned to the system starting from 2015, by considering the necessity of a certain amount of the
reserve in the system, in order not to face energy shortage in the system.

41

Table 27 :Installed Capacity and Peak Demand Balance


(Case I A) High DemandScenario1
(MW)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

27557 27257 27257 27257 27257 27257 27257 27257 27257 27257
13829 13829 13829 13829 13829 13829 13829 13829 13829 13829
432
432
432
432
432
432
432
432
432
432

GRAND TOTAL

41817 41517 41517 41517 41517 41517 41517 41517 41517 41517

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


PEAK LOAD DEMAND
RESERVE %

29900 31246 33276 35772 38455 41339 44440 47728 51260 55053
39,9

32,9

24,8

16,1

8,0

0,4

-6,6

-13,0

-19,0

-24,6

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

0
495
0

0
966
0

0
1636
0

0
1636
0

840
1636
0

840
1636
0

840
1636
0

840
2836
0

840
2836
0

840
2836
0

GRAND TOTAL

495

966

1636

1636

2476

2476

2476

3676

3676

3676

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

27557 27257 27257 27257 28097 28097 28097 28097 28097 28097
14324 14794 15464 15464 15464 15464 15464 16664 16664 16664
432
432
432
432
432
432
432
432
432
432

GRAND TOTAL

42312 42483 43153 43153 43993 43993 43993 45193 45193 45193

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

29900 31246 33276 35772 38455 41339 44440 47728 51260 55053
41,5

36,0

29,7

20,6

14,4

6,4

-1,0

-5,3

-11,8

-17,9

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

348

493

1710

4837

6051

6051

6051

6051

6051

6051

562
263

1587
448

2594
725

4413
725

4413
725

4413
725

4413
725

4413
725

4413
725

4413
725

1173

2528

5029

9976 11189 11189 11189 11189 11189 11189

STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION


LICENCED POWER PLANTS
348
493
1710
4837
6891
6891
6891
THERMAL TOTAL
1057
2552
4230
6049
6049
6049
6049
HYDRO TOTAL
263
448
725
725
725
725
725
WIND + RENEWABLE TOTAL
GRAND TOTAL

1668

3494

6891
7249
725

6891
7249
725

6891
7249
725

6665 11611 13665 13665 13665 14865 14865 14865

EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS
27905 27750 28966 32094 34147 34147 34147 34147 34147 34147
THERMAL TOTAL
14886 16381 18058 19877 19877 19877 19877 21077 21077 21077
HYDRO TOTAL
695
880
1157
1157
1157
1157
1157
1157
1157
1157
WIND + RENEWABLE TOTAL
GRAND TOTAL

43485 45011 48182 53128 55182 55182 55182 56382 56382 56382

COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR
UNDER CONSTRUCTION LICENCED POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

29900 31246 33276 35772 38455 41339 44440 47728 51260 55053
45,4

44,1

44,8

42

48,5

43,5

33,5

24,2

18,1

10,0

2,4

The annual development of total installed capacity composed of existing capacity, state owned capacity
under construction and private sector owned capacity under construction granted by licence and expected
to be in service on proposed time is on Figure 11.

Figure 11 : Development of Installed Capacity Composed of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Time and Peak
Demand
(Case I - A) High Demand-Scenario 1
60000

50000

MW

40000

30000

20000

10000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

PEAK DEMAND

The development of total project generation composed of existing, state owned under construction and
private sector owned under construction granted by licence and expected to be in service on proposed time
together with energy reserve after covering the demand with these power plants are submitted on Table 28
for each composition.
When the existing power plants are considered solely, energy reserve starts from 25.6% in 2009 and
decreases continuously by year, the energy demand exceeds the project generation capacity in 2013 and the
energy reserve drops to 33.7% in 2018.
When the total project generation of existing power plants and state owned power plants under
construction are considered, the energy reserve is 25.8% in 2009, vanishes in 2013 and drops to negative
value of -6.6% in 2014 and reaches to 29.5% in 2018.
If the project generations of existing power plants, state owned power plants under construction and private
sector owned power plants under construction granted by licence and expected to be in service on proposed
date are examined together, 27.3% of energy reserve is calculated in 2009, by decreasing the reserve
becomes negative value of 4.2% in 2017 and drops to 11.8% in 2018.

43

Table 28 : Project Generation Capacity and Energy Demand Balance 2009-2018


(Case I-A) High Demand Scenario 1
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

193827 192543 191767 192089 191676 190020 190882 192248 191029 187254
48032 48129 48080 48030 47981 47932 47893 47938 47938 47938
1715
1714
1714
1714
1714
1714
1714
1714
1714
1714

GRAND TOTAL

243574 242387 241561 241833 241371 239666 240490 241900 240681 236906

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (HIGH DEMAND) 194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
RESERVE %

25,6

19,6

11,9

4,2

-3,3

-10,6

-16,6

-21,9

-27,6

-33,7

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

0
517
0

0
2481
0

0
3586
0

0
5086
0

5880
5086
0

5880
5086
0

5880
5086
0

5880
8919
0

5880
8919
0

5880
8919
0

GRAND TOTAL

517

2481

3586

5086

10966

10966

10966

14799

14799

14799

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

193827 192543 191767 192089 197556 195900 196762 198128 196909 193134
48549 50610 51666 53116 53067 53018 52979 56857 56857 56857
1715
1714
1714
1714
1714
1714
1714
1714
1714
1714

GRAND TOTAL

244091 244868 245147 246919 252337 250632 251456 256699 255480 251705

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (HIGH DEMAND) 194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
RESERVE %

25,8

20,8

13,5

6,4

1,1

-6,6

-12,8

-17,1

-23,2

-29,5

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

1147

2873

8032

24605

40607

44615

44615

44615

44615

44615

1113
598

4197
1564

7990
2447

12766
2964

15719
2964

15719
2964

15719
2964

15719
2964

15719
2964

15719
2964

GRAND TOTAL

2858

8634

18470

40335

59291

63298

63298

63298

63298

63298

STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED


POWER PLANTS
1147
2873
8032 24605 46487 50495 50495 50495
THERMAL TOTAL
1630
6678 11576 17852 20805 20805 20805 24638
HYDRO TOTAL
598
1564
2447
2964
2964
2964
2964
2964
WIND + RENEWABLE TOTAL

50495
24638
2964

50495
24638
2964

78097

78097

GRAND TOTAL

3375

11115

22056

45421

70257

74264

74264

78097

EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
194974 195416 199799 216694 238163 240515 241378 242743 241524 237749
THERMAL TOTAL
49662 54807 59657 65882 68787 68738 68699 72577 72577 72577
HYDRO TOTAL
2313
3278
4161
4678
4678
4678
4678
4678
4678
4678
WIND + RENEWABLE TOTAL
GRAND TOTAL

246949 253501 263617 287254 311628 313931 314754 319998 318779 315004

COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (HIGH DEMAND) 194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
RESERVE %

27,3

25,0

22,1

44

23,8

24,9

17,0

9,2

3,3

-4,2

-11,8

The annual development of the project generations of existing power plants, state owned power plants
under construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date is on Figure 12 and the firm generation of the same capacity
composition is on Figure 13. The demand can not be covered with the total project generation in 2017 and
with the total firm generation in 2015 with the capacities of existing power plants, state owned power
plants under construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date.

Figure 12 : Development of Project Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants under
construction Granted by Licence and Expected to be in Service on Proposed Time and
Energy Demand (Case I - A)
450000
The year in which energy shortage is
expected according to generation capacity
total of existing, under construction and
granted by licence capacities

400000

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

ENERGY DEMAND

The development of total firm generation capacities of existing, state owned under
construction and private sector owned under construction granted by licence and expected to be in
service on proposed time is submitted together with energy reserve after covering the demand
with these power plants on Table 29.
When the existing power plants are considered solely, firm energy reserve starts from 6.7% in 2009 and
decreases by year, the energy demand exceeds the firm generation capacity and the energy reserve drops to
negative value of 4.1% in 2011. The energy reserve drops persistently to the level of 40.9% in 2018.
When the total firm generation capacities of existing power plants and state owned power plants
under construction is considered, energy reserve is 6.9% in 2009, drops to negative value of 3% in 2011
and reaches to 37.7% in 2018.
If the total firm generation capacities of existing power plants, state owned power plants under
construction and private sector owned under construction power plants granted by licence and expected to
be in service on proposed date is examined, 8% of energy reserve is calculated in 2009, by decreasing the
energy reserve becomes negative value of 3.5% in 2015 and drops to 22.5% in 2018. New additional
capacity will be necessary to be commissioned in the system starting from 2015 in the case of considering
of the covering of the demand with the firm energy generation according to the case.

45

Table 29 : Firm Generation Capacity and Energy Demand Balance 2009-2018


(Case I - A) High Demand Scenario 1
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 183398 180440 182605 183450 182751 178968
30720

30794

30745

30695

30646

30597

30558

30603

30603

30603

1562

1561

1561

1561

1561

1561

1561

1561

1561

1561

206934 206740 207087 208557 215605 212598 214723 215613 214915 211131

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
6,7

2,0

-4,1

-10,1

-13,6

-20,7

-25,5

-30,4

-35,4

-40,9

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


0

5606

5606

5606

5606

5606

5606

372

1720

2337

3195

3195

3195

3195

5654

5654

5654

372
1720
2337
3195
8801
GRAND TOTAL
EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS

8801

8801

11260

11260

11260

THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 189005 186047 188211 189056 188358 184574
31092 32514 33082 33890 33841 33792 33753 36257 36257 36257
1562
1561
1561
1561
1561
1561
1561
1561
1561
1561
207306 208459 209424 211752 224406 221399 223524 226873 226175 222391

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
6,9

2,8

-3,0

-8,8

-10,1

-17,5

-22,5

-26,7

-32,0

-37,7

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


1147

2873

8032

24605

40607

44615

44615

44615

44615

44615

HYDRO TOTAL

523

1973

3756

6000

7388

7388

7388

7388

7388

7388

WIND + RENEWABLE TOTAL

538

1395

2157

2601

2601

2601

2601

2601

2601

2601

2208
6241 13945 33206 50596 54604 54604 54604
GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS

54604

54604

THERMAL TOTAL

1147

2873

8032

24605

46214

50222

50222

50222

50222

50222

HYDRO TOTAL

895

3692

6092

9195

10583

10583

10583

13042

13042

13042

WIND + RENEWABLE TOTAL

538

1395

2157

2601

2601

2601

2601

2601

2601

2601

THERMAL TOTAL

2580
7960 16281 36400 59397 63405 63405 65864 65864 65864
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

175799 177258 182813 200907 229612 230662 232826 233671 232973 229189
31615

34486

36837

39890

41229

41180

41141

43645

43645

43645

2100

2956

3718

4161

4161

4161

4161

4161

4161

4161

209514 214700 223368 244957 275002 276003 278128 281477 280779 276995
GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
8,0

5,9

3,5

46

5,5

10,2

2,9

-3,5

-9,1

-15,6

-22,5

Figure 13 : Development of Firm Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Date and
Energy Demand (Case I - A)
400000

The yearinwhichenergyshortageisexpected
accordingtogenerationcapacitytotalof
existing,underconstructionandgrantedby
licencecapacities

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

ENERGY DEMAND

Between the years of 2009 and 2018 with the addition of 3676 MW state owned capacity under
construction and 11189 MW private sector owned capacity under construction granted by licence and
expected to be in service on proposed date to the existing system, the total installed capacity will reach to
56382 MW in the year 2018.

In conclusion, the power plants of existing system, 3676 MW state owned under
construction and 11189 MW private sector owned under construction granted by licence
and expected to be in service on proposed date according to Scenario 1 will not cover High
Energy Demand according to Project Generation and Firm Generation starting from the
years 2017 and 2015 respectively.

47

Figure 14 : Development of Total Installed Capacity and Peak Demand


(Case I - A) High Demand Scenario 1
60000

50000

MW

40000

30000

20000

10000

0
2009

2010

2011

THERMAL

2012

2013

HYDRO

2014

WIND+REN.

2015

2016

2017

2018

PEAK DEMAND

Table 30 : Development of Total Installed Capacity (Case I - A) High Demand Scenario 1

2009
2010
2011
2012
2013
2014
2015
2016
2017
2018

THERMAL
MW
%
27905
64
27750
62
28966
60
32094
60
34147
62
34147
62
34147
62
34147
61
34147
61
34147
61

HYDRO
MW
14886
16381
18058
19877
19877
19877
19877
21077
21077
21077

48

%
34
36
37
37
36
36
36
37
37
37

WIND+RENEWABLES
MW
%
695
2
880
2
1157
2
1157
2
1157
2
1157
2
1157
2
1157
2
1157
2
1157
2

TOTAL
MW
43485
45011
48182
53128
55182
55182
55182
56382
56382
56382

Figure 15 : Capacity Reserve, Project Generation Reserve and Firm Generation Reserve
(Case I - A) High Demand Scenario 1
100,0
90,0
80,0
70,0
60,0

(%)

50,0
40,0
30,0
20,0
10,0
0,0
-10,0
-20,0
-30,0

2009

2010

2011

2012

2013

2014

2015

2016

2017

CAPACITY RESERVE

45,4

44,1

44,8

48,5

43,5

33,5

24,2

18,1

10,0

2018
2,4

PROJECT GENERATION RESRVE

27,3

25,1

22,1

23,8

24,9

17,1

9,2

3,3

-4,1

-11,8

FIRM GENERATION RESRVE

8,0

5,9

3,5

5,5

10,2

2,9

-3,5

-9,1

-15,6

-22,4

As can be seen from the Figure 15, starting from the year 2015 the new additional capacity
is necessary to be comissioned in the system in order not to face energy shortage in the system
according to the case.
Figure 16 : Development of Project Generation, Firm Generation and Energy Demand
(Case I - A) High Demand Scenario 1
550000

450000

GWh

350000

250000

150000

50000

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

-50000
PROJECT GENERATION CAPACITY

FIRM GENERATION CAPACITY

49

DEMAND

VI.2. Case I B (High Demand Scenario 2)


In this section the power plants which are

Existing as end of the year 2008,

State-owned under construction and

Private sector under construction granted by licence and expected to be in service on proposed date
based on January 2009 Progress Report of EPDK and prepared according to Scenario 2 by
EPDK,

considered with High Demand Series. By taking into consideration the effects of the economic crisis,
Demand Series have been revized by ETKB and the generation demand is expected to reach 202.7 TWh in
2010 and 357.2 TWh in 2018. The supply and demand situation according to these data is calculated.
According to above situation, peak demand can be covered in the all study period. When the generation
capacity is considered, the energy demand can not be covered in 2014 according to firm generation
capacity and in 2016 according to project generation capacity.
The development of the existing capacity, the state owned capacity under construction and the private
sector owned capacity under construction granted by licence and expected to be in service on the proposed
time covering the increasing demand by years is indicated on Table 31.
Beside this, not only the development of total installed capacity consisting of the existing, the state owned
under construction and the private sector owned under construction granted by licence and expected to be
in service on proposed date but also the development of the capacity reserves after covering the peak load
with the power plants which are;

only existing capacity,

existing capacity + state owned capacity under construction and

existing capacity + state owned capacity under construction + private sector owned under
construction capacity granted by licence and expected to be in service on proposed date

are submitted on Table 31 and the year is determined in which new generation facilities will be needed.
When the existing power plants are considered solely, capacity reserve starts from 39.9% in 2009 and
continuously decreases and the peak demand exceeds the total installed capacity in 2015 by reaching to
6.6%. According to the increase of peak demand the capacity reserve reaches to 24.6% in year 2018
with the existing capacity as end of the year 2008.
When the sum of existing capacity and state-owned capacity under construction are considered, the
capacity reserve is 41.5% in 2009, drops to 1% in 2015 and reaches to 17.9% in 2018.
When existing capacity, state owned capacity under construction and private sector owned under
construction capacity granted by licence and expected to be in service on proposed date are examined
together, capacity reserve is 44.8% in 2009, decreases to 5.8% in 2017 and -1.5% in 2018.
In spide of no shortage in the capacity reserve up to 2017, new additional capacity will be necessary to be
commissioned in the system starting from 2014, by considering the necessity of a certain amount of the
reserve in the system, in order not to come into existence of energy shortage in the system.

50

Table 31 :Installed Capacity and Peak Demand Balance


(Case I B) High DemandScenario2
(MW)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

THERMAL TOTAL

27557

27257

27257

27257

27257

27257

27257

27257

27257

27257

HYDRO TOTAL

13829

13829

13829

13829

13829

13829

13829

13829

13829

13829

EXISTING POWER PLANTS

WIND + RENEWABLE TOTAL


GRAND TOTAL

432

432

432

432

432

432

432

432

432

432

41817

41517

41517

41517

41517

41517

41517

41517

41517

41517

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


PEAK LOAD DEMAND
RESERVE %

29900

31246

33276

35772

38455

41339

44440

47728

51260

55053

39,9

32,9

24,8

16,1

8,0

0,4

-6,6

-13,0

-19,0

-24,6

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

840

840

840

840

840

840

495

966

1636

1636

1636

1636

1636

2836

2836

2836

495

966

1636

1636

2476

2476

2476

3676

3676

3676

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL

27557

27257

27257

27257

28097

28097

28097

28097

28097

28097

HYDRO TOTAL

14324

14794

15464

15464

15464

15464

15464

16664

16664

16664

WIND + RENEWABLE TOTAL


GRAND TOTAL

432

432

432

432

432

432

432

432

432

432

42312

42483

43153

43153

43993

43993

43993

45193

45193

45193

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

29900

31246

33276

35772

38455

41339

44440

47728

51260

55053

41,5

36,0

29,7

20,6

14,4

6,4

-1,0

-5,3

-11,8

-17,9

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


348

426

1710

2318

4556

4556

4556

4556

4556

4556

HYDRO TOTAL

413

1306

2262

3856

3856

3856

3856

3856

3856

3856

WIND + RENEWABLE TOTAL

223

426

635

635

635

635

635

635

635

635

983
2158
4607
6809
9047
9047
9047
9047
GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS

9047

9047

THERMAL TOTAL

THERMAL TOTAL

348

426

1710

2318

5396

5396

5396

5396

5396

5396

HYDRO TOTAL

908

2272

3898

5492

5492

5492

5492

6692

6692

6692

WIND + RENEWABLE TOTAL

223

426

635

635

635

635

635

635

635

635

1478
3123
6243
8445 11523 11523 11523 12723 12723 12723
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS
THERMAL TOTAL

27905

27683

28966

29574

32653

32653

32653

32653

32653

32653

HYDRO TOTAL

14736

16100

17726

19320

19320

19320

19320

20520

20520

20520

655

857

1067

1067

1067

1067

1067

1067

1067

1067

43295

44640

47760

49962

53040

53040

53040

54240

54240

54240

29900

31246

33276

35772

38455

41339

44440

47728

51260

55053

44,8

42,9

43,5

39,7

37,9

28,3

19,4

13,6

5,8

-1,5

WIND + RENEWABLE TOTAL

GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR
UNDER CONSTRUCTION LICENCED POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

51

The annual development of total installed capacity composed of existing capacity, state
owned capacity under construction and private sector owned capacity under construction granted
by licence and expected to be in service on proposed time is on Figure 17. On the figure, when the
installed capacity development is compared with peak demand, the peak demand can not be
covered with the total installed capacity which are composed of the existing, under construction
and granted by licence and expected to be in service on proposed time starting from the year
2018.
Figure 17 : Development of Installed Capacity Composed of Existing Power Plants + State
owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Time and Peak
Demand
(Case I - B) High Demand-Scenario 2
60000

The year in which peak demand can not be covered by sum of


existing, under construction and granted by licence capacities

50000

MW

40000

30000

20000

10000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

PEAK DEMAND

The development of total project generation capacities of existing, state owned under construction and
private sector owned under construction granted by licence and expected to be in service on proposed time
together with energy reserve after covering the demand with these power plants are submitted on Table 32
for each composition.
When the existing power plants are considered solely, energy reserve starts from 25.6% in 2009 and
decreases continuously by year, the energy demand exceeds the project generation capacity in 2013 and the
energy reserve drops to 33.7% in 2018.
When the total project generation of existing power plants and state owned power plants under
construction are considered, the energy reserve is 25.8% in 2009, vanishes in 2013 and drops to negative
value of -6.6% in 2014 and reaches to 29.5% in 2018.

If the project generations of existing power plants, state owned power plants under
construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date are examined together, 27.1% of energy reserve is
calculated in 2009, by decreasing the reserve becomes negative value of 1% in 2016 and drops to
15.6% in 2018.

52

Table 32 : Project Generation Capacity and Energy Demand Balance 2009-2018


(Case I-B) High Demand Scenario 2
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

193827 192543 191767 192089 191676 190020 190882 192248 191029 187254
48032 48129 48080 48030 47981 47932 47893 47938 47938 47938
1715
1714
1714
1714
1714
1714
1714
1714
1714
1714

GRAND TOTAL

243574 242387 241561 241833 241371 239666 240490 241900 240681 236906

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
11,9

4,2

-3,3

-10,6

-16,6

-21,9

-27,6

-33,7

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


0
0
0
THERMAL TOTAL
517
2481
3586
HYDRO TOTAL
0
0
0
WIND + RENEWABLE TOTAL

0
5086
0

5880
5086
0

5880
5086
0

5880
5086
0

5880
8919
0

5880
8919
0

5880
8919
0

5086

10966

10966

10966

14799

14799

14799

GRAND TOTAL

25,6

517

19,6

2481

3586

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

193827 192543 191767 192089 197556 195900 196762 198128 196909 193134
48549 50610 51666 53116 53067 53018 52979 56857 56857 56857
1715
1714
1714
1714
1714
1714
1714
1714
1714
1714

GRAND TOTAL

244091 244868 245147 246919 252337 250632 251456 256699 255480 251705

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
25,8

20,8

13,5

6,4

1,1

-6,6

-12,8

-17,1

-23,2

-29,5

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

1147
825
486

2613
3404
1401

7772
6932
2219

14771
11270
2609

25139
13835
2609

33346
13835
2609

33346
13835
2609

33346
13835
2609

33346
13835
2609

33346
13835
2609

GRAND TOTAL

2458

7418

16923

28650

41582

49790

49790

49790

49790

49790

STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED


POWER PLANTS
1147
2613
7772 14771 31019 39226 39226 39226
THERMAL TOTAL
1342
5885
10518
16356 18921 18921 18921 22754
HYDRO TOTAL
486
1401
2219
2609
2609
2609
2609
2609
WIND + RENEWABLE TOTAL

39226
22754
2609

39226
22754
2609

64589

64589

GRAND TOTAL

2975

9899

20509

33736

52548

60756

60756

64589

EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
194974 195156 199539 206859 222694 229246 230109 231474 230255 226480
THERMAL TOTAL
49374 54015 58598 64387 66902 66853 66814 70692 70692 70692
HYDRO TOTAL
2201
3115
3933
4323
4323
4323
4323
4323
4323
4323
WIND + RENEWABLE TOTAL
GRAND TOTAL

246549 252285 262070 275569 293919 300422 301246 306489 305270 301495

COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (HIGH DEMAND) 194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
RESERVE %

27,1

24,4

21,4

53

18,7

17,8

12,0

4,5

-1,0

-8,2

-15,6

The annual development of the project generation capacities of existing power plants, state owned power
plants under construction and private sector owned power plants under construction granted by licence
and expected to be in service on proposed date is on Figure 18 and the firm generation of the same capacity
composition is on Figure 19. The demand can not be covered with the total project generation in 2016 and
with the total firm generation in 2014 with the capacities of existing power plants, state owned power
plants under construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date .

Figure 18 : Development of Project Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Time and
Energy Demand
(Case I - B) High Demand Scenario 2
400000
The year in which energy
demand can not be covered
by the project generation
capacity total

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

ENERGY DEMAND

The development of total firm generation capacities of existing, state owned under
construction and private sector owned under construction granted by licence and expected to be in
service on proposed time is submitted together with energy reserve after covering the demand
with these power plants on Table 33.
When the existing power plants are considered solely, firm energy reserve starts from 6.7% in 2009 and
decreases by year, the energy demand exceeds the firm generation capacity and the energy reserve drops to
negative value of 4.1% in 2011. The energy reserve drops persistently to the level of 40.9% in 2018.
When the total firm generation of existing power plants and state owned power plants under
construction is considered, energy reserve is 6.9% in 2009, drops to negative value of 3% in 2011 and
reaches to 37.7% in 2018.
If the total firm generation of existing power plants, state owned power plants under construction and
private sector owned under construction power plants granted by licence and expected to be in service on
proposed date is examined, 7.9% of energy reserve is calculated in 2009, by decreasing the energy reserve
becomes negative value of 1.7% in 2014 and drops to 25.9% in 2018.
New additional capacity will be necessary to be commissioned in the system starting from 2014 in the case
of considering of the covering of the demand with the firm energy generation according to the case.
54

Between the years of 2009 and 2018 with the addition of 3676 MW state-owned capacity under
construction and 9047 MW private sector capacity under construction granted by licence and expected to
be in service on proposed date to the existing system, the total installed capacity will reach to 54240 MW
in the year 2018.

In conclusion, the power plants of existing system, 3676 MW state owned under
construction and 9047 MW private sector owned under construction granted by licence and
expected to be in service on proposed date according to Scenario 2 will not cover High
Energy Demand according to Project Generation and Firm Generation starting from the
years 2016 and 2014 respectively.

55

Table 33 : Firm Generation Capacity and Energy Demand Balance 2009-2018 (Case I - B)
High Demand Scenario 2
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 183398 180440 182605 183450 182751 178968
30720

30794

30745

30695

30646

30597

30558

30603

30603

30603

1562

1561

1561

1561

1561

1561

1561

1561

1561

1561

206934 206740 207087 208557 215605 212598 214723 215613 214915 211131

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
6,7

2,0

-4,1

-10,1

-13,6

-20,7

-25,5

-30,4

-35,4 -40,9

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


0

5606

5606

5606

5606

5606

5606

372

1720

2337

3195

3195

3195

3195

5654

5654

5654

372
1720
2337
3195
8801
GRAND TOTAL
EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS

8801

8801

11260

11260

11260

THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 189005 186047 188211 189056 188358 184574
31092 32514 33082 33890 33841 33792 33753 36257 36257 36257
1562
1561
1561
1561
1561
1561
1561
1561
1561
1561
207306 208459 209424 211752 224406 221399 223524 226873 226175 222391

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
6,9

2,8

-3,0

-8,8

-10,1

-17,5

-22,5

-26,7

-32,0

-37,7

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


1147

2613

7772

14771

25139

33346

33346

33346

33346

33346

HYDRO TOTAL

388

1600

3258

5297

6502

6502

6502

6502

6502

6502

WIND + RENEWABLE TOTAL

438

1252

1963

2299

2299

2299

2299

2299

2299

2299

1972
5465 12993 22367 33940 42148 42148 42148
GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS

42148

42148

THERMAL TOTAL

1147

2613

7772

14771

30745

38953

38953

38953

38953

38953

HYDRO TOTAL

760

3320

5595

8492

9697

9697

9697

12156

12156

12156

WIND + RENEWABLE TOTAL

438

1252

1963

2299

2299

2299

2299

2299

2299

2299

THERMAL TOTAL

2344
7184 15330 25561 42741 50949 50949 53408 53408 53408
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

175799 176998 182553 191072 214143 219393 221558 222402 221704 217921
31479

34114

36340

39187

40343

40294

40255

42759

42759

42759

2000

2812

3524

3860

3860

3860

3860

3860

3860

3860

209278 213924 222416 234119 258346 263547 265672 269021 268323 264539
GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 215907 232101 249508 268221 288338 309675 332591 357202
7,9

5,5

3,0

56

0,9

3,5

-1,7

-7,9

-13,1

-19,3

-25,9

Figure 19 : Development of Firm Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Date and
Energy Demand
(Case I - B) High Demand Scenario 2
400000
Theyearinwhichenergydemand cannotbecoveredby
thetotalprojectgenerationcapacitiesofexisting,under
constructiionandgrantedbylicence.

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010
EXISTING

2011

2012

2013

2014

UNDER CONSTRUCTION

2015

2016

GRANTED BY LICENCE

2017

2018

ENERGY DEMAND

In accordance with Case 1 B the breakdown of the total installed capacity to thermal, hydro and wind
resources by year is shown on Table 34 and Figure 20.

Table 34 : Development of Total Installed Capacity (Case I - B) High Demand Scenario 2

2009
2010
2011
2012
2013
2014
2015
2016
2017
2018

THERMAL
MW
%
27905
64
27683
62
28966
61
29574
59
32653
62
32653
62
32653
62
32653
60
32653
60
32653
60

HYDRO
MW
14736
16100
17726
19320
19320
19320
19320
20520
20520
20520

57

%
34
36
37
39
36
36
36
38
38
38

WIND+RENEWABLES
MW
%
655
2
857
2
1067
2
1067
2
1067
2
1067
2
1067
2
1067
2
1067
2
1067
2

TOTAL
MW
43295
44640
47760
49962
53040
53040
53040
54240
54240
54240

Figure 20 : Development of Total Installed Capacity and Peak Demand


(Case I - B) High Demand Scenario 2
80000

70000

60000

MW

50000

40000

30000

20000

10000

0
2009

2010

2011

2012

THERMAL

2013

HYDRO

2014

2015

2016

WIND+REN.

2017

2018

PEAK DEMAND

Figure 21 : Capacity Reserve, Project Generation Reserve and Firm Generation Reserve
(Case I - B) High Demand Scenario 2
100,0
90,0
80,0
70,0
60,0

(%)

50,0
40,0
30,0
20,0
10,0
0,0
-10,0
-20,0
-30,0

2009

2010

2011

2012

2013

2014

2015

2016

2017

CAPACITY RESERVE

44,8

42,9

43,5

39,7

37,9

28,3

19,4

13,7

5,8

2018
-1,5

PROJECT GENERATION RESRVE

27,1

24,5

21,4

18,7

17,8

12,0

4,5

-1,0

-8,2

-15,6

FIRM GENERATION RESRVE

7,9

5,5

3,0

0,9

3,6

-1,7

-7,9

-13,1

-19,3

-25,9

As can be seen from the Figure 21, starting from the year 2014 the new additional capacity
is necessary to be comissioned to the system in order not to face energy shortage according to the
case.
58

Figure 22 : Development of Project Generation, Firm Generation and Energy Demand


(Case I - B) High Demand Scenario 2
400000

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010

2011

2012

2013

PROJECT GENERATION CAPACITY

2014

2015

FIRM GENERATION CAPACITY

59

2016

2017
DEMAND

2018

VI.3. Case II A (Low Demand Scenario 1)


In this section the power plants which are

Existing as end of the year 2008,

State owned under construction and

Private sector owned under construction granted by licence and expected to be in service on
proposed date based on January 2009 Progress Raport of EPDK and prepared according to
Scenario 1 by EPDK,

and besides, Low Demand, by taking into consideration the effects of the economical crisis, is revized by
ETKB and therefore, the generation demand to reach 202.7 TWh in 2010 and 335.8 TWh in 2018 and so
the results about supply and demand situation and how to cover demand are given. According to above
situation, peak demand can be covered in the all period. When the generation capacity is considered, the
energy demand can not be covered in 2016 according to firm generation capacity and in 2018 according to
project generation capacity.
The development of the existing capacity, the state owned capacity under construction and the private
sector owned capacity under construction granted by licence and expected to be in service on the proposed
time, meeting the increasing demand by years is indicated on Table 35.
Beside this, not only the development of total installed capacity consisting of the existing, the state-owned
under construction and the private sector under construction granted by licence and expected to be in
service on proposed date but also the development of the capacity reserves after covering the peak load
with the power plants which are;

only existing capacity,

existing capacity + state owned capacity under construction and

existing capacity + state owned capacity under construction + private sector owned under
construction capacity granted by licence and expected to be in service on proposed date

are submitted on Table 35. Therefore the years in which new generation facilities are necessary will be
able to be determined.
When the existing power plants are considered solely, capacity reserve starts from 39.9% in 2009 and
continuously decreases and the peak demand exceeds the total installed capacity in 2015 by reaching to
2.8%. According to the increase of peak demand the capacity reserve reaches to 19.8% in year 2018
with the existing capacity as end of the year 2008.
When the sum of existing capacity and state owned capacity under construction are considered, the
capacity reserve is 41.5% in 2009 and 3% in 2015, drops to negative value -0.8% in 2016 and reaches to
17.9% in 2018.
When existing capacity, state owned capacity under construction and private sector owned under
construction capacity granted by licence and expected to be in service on proposed date are examined
together, capacity reserve is 45.4% in 2009 and decreases to 8.9% in 2018.
In spide of no shortage in the capacity reserve up to 2018, new additional capacity will be necessary to be
commissioned in the system starting from 2015, by considering the necessity of a certain amount of the
reserve in the system, in order not to come into existence of energy shortage in the system.

60

Table 35 :Installed Capacity and Peak Demand Balance (Case II A) Low DemandScenario1
(MW)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

THERMAL TOTAL

27557

27257

27257

27257

27257

27257

27257

27257

27257

27257

HYDRO TOTAL

13829

13829

13829

13829

13829

13829

13829

13829

13829

13829

432

432

432

432

432

432

432

432

432

432

41817

41517

41517

41517

41517

41517

41517

41517

41517

41517

EXISTING POWER PLANTS

WIND + RENEWABLE TOTAL


GRAND TOTAL

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


PEAK LOAD DEMAND
RESERVE %

29900

31246

32964

35173

37529

40044

42727

45546

48553

51757

39,9

32,9

25,9

18,0

10,6

3,7

-2,8

-8,8

-14,5

-19,8

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


0

840

840

840

840

840

840

495

966

1636

1636

1636

1636

1636

2836

2836

2836

495
966
1636
1636
2476
GRAND TOTAL
EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS

2476

2476

3676

3676

3676

THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

THERMAL TOTAL

27557

27257

27257

27257

28097

28097

28097

28097

28097

28097

HYDRO TOTAL

14324

14794

15464

15464

15464

15464

15464

16664

16664

16664

432

432

432

432

432

432

432

432

432

432

42312

42483

43153

43153

43993

43993

43993

45193

45193

45193

WIND + RENEWABLE TOTAL


GRAND TOTAL

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

29900

31246

32964

35173

37529

40044

42727

45546

48553

51757

41,5

36,0

30,9

22,7

17,2

9,9

3,0

-0,8

-6,9

-12,7

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


THERMAL TOTAL

348

493

1710

4837

6051

6051

6051

6051

6051

6051

HYDRO TOTAL

562

1587

2594

4413

4413

4413

4413

4413

4413

4413

WIND + RENEWABLE TOTAL


GRAND TOTAL

263

448

725

725

725

725

725

725

725

725

1173

2528

5029

9976

11189

11189

11189

11189

11189

11189

STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION


LICENCED POWER PLANTS
THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

348

493

1710

4837

6891

6891

6891

6891

6891

6891

1057

2552

4230

6049

6049

6049

6049

7249

7249

7249

263

448

725

725

725

725

725

725

725

725

1668
3494
6665 11611 13665 13665 13665 14865 14865 14865
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS
THERMAL TOTAL

27905

27750

28966

32094

34147

34147

34147

34147

34147

34147

HYDRO TOTAL

14886

16381

18058

19877

19877

19877

19877

21077

21077

21077

695

880

1157

1157

1157

1157

1157

1157

1157

1157

WIND + RENEWABLE TOTAL

43485 45011 48182 53128 55182 55182 55182 56382 56382 56382
GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR
UNDER CONSTRUCTION LICENCED POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

29900

31246

32964

35173

37529

40044

42727

45546

48553

51757

45,4

44,1

46,2

51,0

47,0

37,8

29,1

23,8

16,1

8,9

61

The annual development of total installed capacity composed of existing capacity, state-owned
capacity under construction and private sector capacity under construction granted by licence and
expected to be in service on proposed time is on Figure 23.
Figure 23 : Development of Installed Capacity Composed of Existing Power Plants + State
owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Time + New
Additional Capacity and Peak Demand
(Case II - A) Low Demand-Scenario 1
60000

50000

MW

40000

30000

20000

10000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

PEAK DEMAND

The development of total project generation composed of existing, state owned under construction and
private sector owned under construction granted by licence and expected to be in service on proposed time
together with energy reserve after covering the demand with these power plants are submitted on Table 36
for each composition.
When the existing power plants are considered solely, energy reserve starts from 25.6% in 2009 and
decreases continuously by year, the energy demand exceeds the project generation capacity in 2013 and the
energy reserve drops to 29.5% in 2018.
When the total project generation of existing power plants and state owned power plants under
construction are considered, the energy reserve is 25.8% in 2009, vanishes in 2014 and drops to negative
value of -3.5% in 2014 and reaches to 25% in 2018.
If the project generations of existing power plants, state owned power plants under construction and private
sector power owned plants under construction granted by licence and expected to be in service on proposed
date are examined together, 27.3% of energy reserve is calculated in 2009, by decreasing the reserve
becomes negative value of 6.2% in 2018.

62

Table 36 : Project Generation Capacity and Energy Demand Balance 2009-2018 (Case II-A)
Low Demand Scenario 1
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

193827 192543 191767 192089 191676 190020 190882 192248 191029 187254
48032

48129

48080

48030

47981

47932

47893

47938

47938

47938

1715

1714

1714

1714

1714

1714

1714

1714

1714

1714

243574 242387 241561 241833 241371 239666 240490 241900 240681 236906

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
25,6

19,6

12,9

6,0

-0,9

-7,8

-13,3

-18,1

-23,6

-29,5

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

5880

5880

5880

5880

5880

5880

517

2481

3586

5086

5086

5086

5086

8919

8919

8919

517

2481

3586

5086

10966

10966

10966

14799

14799

14799

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

193827 192543 191767 192089 197556 195900 196762 198128 196909 193134
48549

50610

51666

53116

53067

53018

52979

56857

56857

56857

1715

1714

1714

1714

1714

1714

1714

1714

1714

1714

244091 244868 245147 246919 252337 250632 251456 256699 255480 251705

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
25,8

20,8

14,6

8,2

3,6

-3,5

-9,3

-13,1

-18,9

-25,0

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


THERMAL TOTAL

1147

2873

8032

24605

40607

44615

44615

44615

44615

44615

HYDRO TOTAL

1113

4197

7990

12766

15719

15719

15719

15719

15719

15719

598

1564

2447

2964

2964

2964

2964

2964

2964

2964

2858

8634

18470

40335

59291

63298

63298

63298

63298

63298

THERMAL TOTAL

1147

2873

8032

24605

46487

50495

50495

50495

50495

50495

HYDRO TOTAL

1630

6678

11576

17852

20805

20805

20805

24638

24638

24638

WIND + RENEWABLE TOTAL

GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS

WIND + RENEWABLE TOTAL

598

1564

2447

2964

2964

2964

2964

2964

2964

2964

3375

11115

22056

45421

70257

74264

74264

78097

78097

78097

GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

194974 195416 199799 216694 238163 240515 241378 242743 241524 237749
49662

54807

59657

65882

68787

68738

68699

72577

72577

72577

2313

3278

4161

4678

4678

4678

4678

4678

4678

4678

246949 253501 263617 287254 311628 313931 314754 319998 318779 315004
GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
27,3

25,0

23,3

63

25,9

28,0

20,8

13,5

8,3

1,2

-6,2

The annual development of the project generations of existing power plants, state owned power plants
under construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date according to Scenario 1 is on Figure 24 and the firm generation
of the same capacity composition is on Figure 25. The demand can not be covered with the total project
generation in 2018 and with the total firm generation in 2016 with the capacities of existing power plants,
state-owned power plants under construction and private sector power plants under construction granted by
licence and expected to be in service on proposed date .

Figure 24 : Development of Project Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Time and
Energy Demand (Case II - A)
Low Demand Scenario 1
500000
450000
400000
350000

GWh

300000

250000
200000
150000
100000
50000
0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

2016

GRANTED BY LICENCE

2017

2018

ENERGY DEMAND

The development of total firm generation composed of existing, state owned under
construction and private sector owned under construction granted by licence and expected to be in
service on proposed time is submitted together with energy reserve after covering the demand
with these power plants on Table 37.
When the existing power plants are considered solely, firm energy reserve starts from 6.7% in 2009 and
decreases by year, the energy demand exceeds the firm generation capacity and the energy reserve drops to
negative value of 3.2% in 2011. The energy reserve drops persistently to the level of 37.1% in 2018.
When the total firm generation of existing power plants and state owned power plants under
construction is considered, energy reserve is 6.9% in 2009, drops to negative value of 2.1% in 2011 and
reaches to 33.8% in 2018.
If the total firm generation of existing power plants, state owned power plants under construction and
private sector owned under construction power plants granted by licence and expected to be in service on
proposed date is examined, 8% of energy reserve is calculated in 2009, by decreasing the energy reserve
becomes negative value of 4.8% in 2016 and drops to 17.5% in 2018.
Although the shortage of the energy begins in 2016, because of not enough energy reserve to cover the
energy demand in 2015 according to the firm energy generations, new additional capacity will be
necessary to be comissioned in the system starting from the year 2015.
64

Table 37 : Firm Generation Capacity and Energy Demand Balance 2006-2015 (Case II - A)
Low Demand Scenario 1
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 183398 180440 182605 183450 182751 178968
30720

30794

30745

30695

30646

30597

30558

30603

30603

30603

1562

1561

1561

1561

1561

1561

1561

1561

1561

1561

206934 206740 207087 208557 215605 212598 214723 215613 214915 211131

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
6,7

2,0

-3,2

-8,6

-11,5

-18,2

-22,5

-27,0

-31,8

-37,1

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

5606

5606

5606

5606

5606

5606

372

1720

2337

3195

3195

3195

3195

5654

5654

5654

372

1720

2337

3195

8801

8801

8801

11260

11260

11260

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 189005 186047 188211 189056 188358 184574
31092

32514

33082

33890

33841

33792

33753

36257

36257

36257

1562

1561

1561

1561

1561

1561

1561

1561

1561

1561

207306 208459 209424 211752 224406 221399 223524 226873 226175 222391

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
6,9

2,8

-2,1

-7,2

-7,8

-14,8

-19,4

-23,2

-28,2

-33,8

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL

1147

2873

8032

24605

40607

44615

44615

44615

44615

44615

523

1973

3756

6000

7388

7388

7388

7388

7388

7388

538

1395

2157

2601

2601

2601

2601

2601

2601

2601

2208

6241

13945

33206

50596

54604

54604

54604

54604

54604

1147

2873

8032

24605

46214

50222

50222

50222

50222

50222

HYDRO TOTAL

895

3692

6092

9195

10583

10583

10583

13042

13042

13042

WIND + RENEWABLE TOTAL

538

1395

2157

2601

2601

2601

2601

2601

2601

2601

WIND + RENEWABLE TOTAL

GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS
THERMAL TOTAL

2580
7960 16281 36400 59397 63405 63405 65864 65864 65864
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

175799 177258 182813 200907 229612 230662 232826 233671 232973 229189
31615

34486

36837

39890

41229

41180

41141

43645

43645

43645

2100

2956

3718

4161

4161

4161

4161

4161

4161

4161

209514 214700 223368 244957 275002 276003 278128 281477 280779 276995
GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (HIGH DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
8,0

5,9

4,4

65

7,3

12,9

6,2

0,3

-4,8

-10,9

-17,5

Figure 25 : Development of Firm Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Date and
Energy Demand (Case II - A)
Low Demand Scenario 1
450000

400000

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015
LSANS ALMI

2016

2017

2018

ENERGY DEMAND

Between the years of 2009 and 2018 with the addition of 3676 MW state owned capacity under
construction and 11189 MW private sector owned capacity under construction granted by licence and
expected to be in service on proposed date to the existing system, the total installed capacity will reach to
56382 MW in the year 2018.

In conclusion, the power plants of existing system, 3676 MW state owned under
construction and 11189 MW private sector owned under construction granted by licence
and expected to be in service on proposed date according to Scenario 1 will not cover Low
Energy Demand according to Project Generation and Firm Generation starting from the
years 2018 and 2016 respectively.

66

Figure 26 : Development of Total Installed Capacity and Peak Demand (Case II - A)


Low Demand Scenario 1
60000

50000

MW

40000

30000

20000

10000

0
2009

2010

2011

THERMAL

2012

2013

HYDRO

2014

2015

WIND+REN.

2016

2017

2018

PEAK DEMAND

Table 38 : Development of Total Installed Capacity (Case II - A) Low Demand Scenario 1

2009
2010
2011
2012
2013
2014
2015
2016
2017
2018

THERMAL
MW
%
27905
64
27750
62
28966
60
32094
60
34147
62
34147
62
34147
62
34147
61
34147
61
34147
61

HYDRO
MW
14886
16381
18058
19877
19877
19877
19877
21077
21077
21077

67

%
34
36
37
37
36
36
36
37
37
37

WIND+RENEWABLES
MW
%
695
2
880
2
1157
2
1157
2
1157
2
1157
2
1157
2
1157
2
1157
2
1157
2

TOTAL
MW
43485
45011
48182
53128
55182
55182
55182
56382
56382
56382

Figure 27 : Capacity Reserve, Project Generation Reserve and Firm Generation Reserve
(Case II - A) Low Demand Scenario 1
70,0

60,0

50,0

40,0

30,0

(%)

20,0

10,0

0,0

-10,0

-20,0

-30,0

2009

2010

2011

2012

2013

2014

2015

2016

2017

CAPACITY RESERVE

45,4

44,1

46,2

51,1

47,0

37,8

29,2

23,8

16,1

2018
8,9

PROJECT GENERATION RESERVE

27,3

25,1

23,3

25,9

28,0

20,8

13,5

8,3

1,2

-6,2

FIRM GENERATION RESERVE

8,0

5,9

4,4

7,3

12,9

6,2

0,3

-4,7

-10,9

-17,5

As can be seen from the Figure 27, starting from the year 2015 the new additional capacity
is necessary to be comissioned in the system not to come into existence of energy shortage in the
system according to the case.
Figure 28: Development of Project Generation, Firm Generation and Energy Demand
(Case II - A) Low Demand Scenario 1
500000

450000

400000

GWh

350000

300000

250000

200000

150000

100000

50000

0
2009

2010

2011

PROJECT

2012

2013

2014

FIRM

68

2015

2016

DEMAND

2017

2018

VI.4. Case II B (Low Demand Scenario 2)


In this section the power plants which are

Existing as end of the year 2008,

State owned under construction and

Private sector owned under construction granted by licence and expected to be in service on
proposed date based on January 2009 Progress Raport of EPDK and prepared according to
Scenario 2 by EPDK,

and besides, Low Demand, by taking into consideration the effects of the economical crisis, is revized by
ETKB and therefore, the generation demand to reach 202.7 TWh in 2010 and 335.8 TWh in 2018 and so
the results about supply and demand situation and how to cover demand are given. According to above
situation, peak demand can be covered in the all period. When the generation capacity is considered, the
energy demand can not be covered in 2015 according to firm generation capacity and in 2017 according to
project generation capacity.
The development of the existing capacity, the state owned capacity under construction and the private
sector owned capacity under construction granted by licence and expected to be in service on the proposed
time, meeting the increasing demand by years is indicated on Table 39.
Beside this, not only the development of total installed capacity consisting of the existing, the state-owned
under construction and the private sector under construction granted by licence and expected to be in
service on proposed date but also the development of the capacity reserves after covering the peak load
with the power plants which are;

only existing capacity,

existing capacity + state owned capacity under construction and

existing capacity + state owned capacity under construction + private sector owned under
construction capacity granted by licence and expected to be in service on proposed date

are submitted on Table 39. Therefore the years in which new generation facilities are necessary will be
able to be determined.
When the existing power plants are considered solely, capacity reserve starts from 39.9% in 2009 and
continuously decreases and the peak demand exceeds the total installed capacity in 2015 by reaching to
2.8%. According to the increase of peak demand the capacity reserve reaches to 19.8% in year 2018
with the existing capacity as end of the year 2008.
When the sum of existing capacity and state owned capacity under construction are considered, the
capacity reserve is 41.5% in 2009, decreases to 3% in 2015, drops to the negative value of 0.8% in 2016
and reaches to 12.7% in 2018.
When existing capacity, state owned capacity under construction and private sector owned under
construction capacity granted by licence and expected to be in service on proposed date are examined
together, capacity reserve is 44.8% in 2009 and decreases to 4.8% in 2018.
In spide of no shortage in the capacity reserve up to 2018, new additional capacity will be necessary to be
commissioned in the system starting from 2014, by considering the necessity of a certain amount of the
reserve in the system, in order not to come into existence of energy shortage in the system.

69

Table 39 :Installed Capacity and Peak Demand Balance (Case II B) Low DemandScenario2
(MW)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

THERMAL TOTAL

27557

27257

27257

27257

27257

27257

27257

27257

27257

27257

HYDRO TOTAL

13829

13829

13829

13829

13829

13829

13829

13829

13829

13829

432

432

432

432

432

432

432

432

432

432

41817

41517

41517

41517

41517

41517

41517

41517

41517

41517

EXISTING POWER PLANTS

WIND + RENEWABLE TOTAL


GRAND TOTAL

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


PEAK LOAD DEMAND
RESERVE %

29900

31246

32964

35173

37529

40044

42727

45546

48553

51757

39,9

32,9

25,9

18,0

10,6

3,7

-2,8

-8,8

-14,5

-19,8

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

840

840

840

840

840

840

495

966

1636

1636

1636

1636

1636

2836

2836

2836

495

966

1636

1636

2476

2476

2476

3676

3676

3676

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL

27557

27257

27257

27257

28097

28097

28097

28097

28097

28097

HYDRO TOTAL

14324

14794

15464

15464

15464

15464

15464

16664

16664

16664

432

432

432

432

432

432

432

432

432

432

42312

42483

43153

43153

43993

43993

43993

45193

45193

45193

WIND + RENEWABLE TOTAL


GRAND TOTAL

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

29900

31246

32964

35173

37529

40044

42727

45546

48553

51757

41,5

36,0

30,9

22,7

17,2

9,9

3,0

-0,8

-6,9

-12,7

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


THERMAL TOTAL

348

426

1710

2318

4556

4556

4556

4556

4556

4556

HYDRO TOTAL

413

1306

2262

3856

3856

3856

3856

3856

3856

3856

WIND + RENEWABLE TOTAL

223

426

635

635

635

635

635

635

635

635

983
2158
4607
6809
9047
9047
9047
GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION
LICENCED POWER PLANTS

9047

9047

9047

THERMAL TOTAL

348

426

1710

2318

5396

5396

5396

5396

5396

5396

HYDRO TOTAL

908

2272

3898

5492

5492

5492

5492

6692

6692

6692

WIND + RENEWABLE TOTAL

223

426

635

635

635

635

635

635

635

635

1478
3123
6243
8445 11523 11523 11523 12723 12723 12723
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS
THERMAL TOTAL

27905

27683

28966

29574

32653

32653

32653

32653

32653

32653

HYDRO TOTAL

14736

16100

17726

19320

19320

19320

19320

20520

20520

20520

655

857

1067

1067

1067

1067

1067

1067

1067

1067

WIND + RENEWABLE TOTAL

43295 44640 47760 49962 53040 53040 53040 54240 54240 54240
GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR
UNDER CONSTRUCTION LICENCED POWER PLANTS
PEAK LOAD DEMAND
RESERVE %

29900

31246

32964

35173

37529

40044

42727

45546

48553

51757

44,8

42,9

44,9

42,0

41,3

32,5

24,1

19,1

11,7

4,8

70

The annual development of total installed capacity composed of existing capacity, state owned
capacity under construction and private sector owned capacity under construction granted by licence and
expected to be in service on proposed time is given on Figure 29.

Figure 29 : Development of Installed Capacity Composed of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Time and Peak
Demand
(Case II - B) Low Demand-Scenario 2
60000

50000

MW

40000

30000

20000

10000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

PEAK DEMAND

The development of total project generation composed of existing, state owned under construction and
private sector owned under construction granted by licence and expected to be in service on proposed time
together with energy reserve after covering the demand with these power plants are submitted on Table 40
for each composition.
When the existing power plants are considered solely, energy reserve starts from 25.6% in 2009 and
decreases continuously by year, the energy demand exceeds the project generation capacity in 2013 and the
energy reserve drops to 29.5% in 2018.
When the total project generation of existing power plants and state owned power plants under
construction are considered, the energy reserve is 25.8% in 2009 and drops to negative value of -3.6% in
2014 and reaches to 25% in 2018.

If the project generations of existing power plants, state owned power plants under
construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date are examined together, 27.1% of energy reserve is
calculated in 2009, by decreasing the reserve becomes negative value of 3.1% in 2017 and drops
to 10.2% in 2018.

71

Table 40 : Project Generation Capacity and Energy Demand Balance 2009-2018 (Case II-B)
Low Demand Scenario 2
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

193827 192543 191767 192089 191676 190020 190882 192248 191029 187254
48032

48129

48080

48030

47981

47932

47893

47938

47938

47938

1715

1714

1714

1714

1714

1714

1714

1714

1714

1714

243574 242387 241561 241833 241371 239666 240490 241900 240681 236906

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
25,6

19,6

12,9

6,0

-0,9

-7,8

-13,3

-18,1

-23,6

-29,5

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

5880

5880

5880

5880

5880

5880

517

2481

3586

5086

5086

5086

5086

8919

8919

8919

517

2481

3586

5086

10966

10966

10966

14799

14799

14799

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

193827 192543 191767 192089 197556 195900 196762 198128 196909 193134
48549

50610

51666

53116

53067

53018

52979

56857

56857

56857

1715

1714

1714

1714

1714

1714

1714

1714

1714

1714

244091 244868 245147 246919 252337 250632 251456 256699 255480 251705

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
25,8

20,8

14,6

8,2

3,6

-3,5

-9,3

-13,1

-18,9

-25,0

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


1147

2613

7772

14771

25139

33346

33346

33346

33346

33346

HYDRO TOTAL

825

3404

6932

11270

13835

13835

13835

13835

13835

13835

WIND + RENEWABLE TOTAL

486

1401

2219

2609

2609

2609

2609

2609

2609

2609

2458
7418 16923 28650 41582 49790 49790 49790
GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS

49790

49790

THERMAL TOTAL

THERMAL TOTAL

1147

2613

7772

14771

31019

39226

39226

39226

39226

39226

HYDRO TOTAL

1342

5885

10518

16356

18921

18921

18921

22754

22754

22754

486

1401

2219

2609

2609

2609

2609

2609

2609

2609

WIND + RENEWABLE TOTAL

2975
9899 20509 33736 52548 60756 60756 64589 64589 64589
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

194974 195156 199539 206859 222694 229246 230109 231474 230255 226480
49374

54015

58598

64387

66902

66853

66814

70692

70692

70692

2201

3115

3933

4323

4323

4323

4323

4323

4323

4323

246549 252285 262070 275569 293919 300422 301246 306489 305270 301495

GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
27,1

24,4

22,5

72

20,8

20,7

15,6

8,7

3,7

-3,1

-10,2

The annual development of the project generations of existing power plants, state owned power plants
under construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date is on Figure 30 and the firm generation of the same capacity
composition is on Figure 31. The demand can not be covered with the total project generation in 2017 and
with the total firm generation in 2015 with the capacities of existing power plants, state owned power
plants under construction and private sector owned power plants under construction granted by licence and
expected to be in service on proposed date.

Figure 30 : Development of Project Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Time and
Energy Demand (Case II - B)
Low Demand Scenario 2
400000

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010
EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

ENERGY DEMAND

The development of total firm generation composed of existing, state owned under
construction and private sector owned under construction granted by licence and expected to be in
service on proposed time is submitted together with energy reserve after covering the demand
with these power plants on Table 41.
When the existing power plants are considered solely, firm energy reserve starts from 6.7% in 2009 and
decreases by year, the energy demand exceeds the firm generation capacity and the energy reserve drops to
negative value of 3.2% in 2011. The energy reserve drops persistently to the level of 37.1% in 2018.
When the total firm generation of existing power plants and state owned power plants under
construction is considered, energy reserve is 6.9% in 2009, drops to negative value of 2.1% in 2011 and
reaches to 33.8% in 2018.
If the total firm generation of existing power plants, state owned power plants under construction and
private sector owned under construction power plants granted by licence and expected to be in service on
proposed date is examined, 7.9% of energy reserve is calculated in 2009, by decreasing the energy reserve
becomes negative value of 4.2% in 2015 and drops to 21.2% in 2018.

In conclusion, the power plants of existing system, 3676 MW state owned under
construction and 9047 MW private sector owned under construction granted by licence and
expected to be in service on proposed date according to Scenario 2 will not cover Low
Energy Demand according to Project Generation and Firm Generation starting from the
years 2017 and 2015 respectively.
73

Table 41 : Firm Generation Capacity and Energy Demand Balance 2009-2018 (Case II - B)
Low Demand Scenario 2
(GWh)
YEAR

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

EXISTING POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 183398 180440 182605 183450 182751 178968
30720

30794

30745

30695

30646

30597

30558

30603

30603

30603

1562

1561

1561

1561

1561

1561

1561

1561

1561

1561

206934 206740 207087 208557 215605 212598 214723 215613 214915 211131

COVERING OF PEAK DEMAND WITH EXISTING POWER PLANTS


ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
6,7

2,0

-3,2

-8,6

-11,5

-18,2

-22,5

-27,0

-31,8

-37,1

STATE-OWNED POWER PLANTS UNDER CONSTRUCTION


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

5606

5606

5606

5606

5606

5606

372

1720

2337

3195

3195

3195

3195

5654

5654

5654

372

1720

2337

3195

8801

8801

8801

11260

11260

11260

EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS


THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL
GRAND TOTAL

174653 174385 174781 176302 189005 186047 188211 189056 188358 184574
31092

32514

33082

33890

33841

33792

33753

36257

36257

36257

1562

1561

1561

1561

1561

1561

1561

1561

1561

1561

207306 208459 209424 211752 224406 221399 223524 226873 226175 222391

COVERING OF PEAK DEMAND WITH EXISTING AND STATE-OWNED UNDER CONSTRUCTION POWER PLANTS
ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
6,9

2,8

-2,1

-7,2

-7,8

-14,8

-19,4

-23,2

-28,2

-33,8

PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER PLANTS


1147

2613

7772

14771

25139

33346

33346

33346

33346

33346

HYDRO TOTAL

388

1600

3258

5297

6502

6502

6502

6502

6502

6502

WIND + RENEWABLE TOTAL

438

1252

1963

2299

2299

2299

2299

2299

2299

2299

1972
5465 12993 22367 33940 42148 42148 42148
GRAND TOTAL
STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED
POWER PLANTS

42148

42148

THERMAL TOTAL

1147

2613

7772

14771

30745

38953

38953

38953

38953

38953

HYDRO TOTAL

760

3320

5595

8492

9697

9697

9697

12156

12156

12156

WIND + RENEWABLE TOTAL

438

1252

1963

2299

2299

2299

2299

2299

2299

2299

THERMAL TOTAL

2344
7184 15330 25561 42741 50949 50949 53408 53408 53408
GRAND TOTAL
EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER CONSTRUCTION LICENCED POWER
PLANTS
THERMAL TOTAL
HYDRO TOTAL
WIND + RENEWABLE TOTAL

175799 176998 182553 191072 214143 219393 221558 222402 221704 217921
31479

34114

36340

39187

40343

40294

40255

42759

42759

42759

2000

2812

3524

3860

3860

3860

3860

3860

3860

3860

209278 213924 222416 234119 258346 263547 265672 269021 268323 264539
GRAND TOTAL
COVERING OF PEAK DEMAND WITH EXISTING, STATE-OWNED UNDER CONSTRUCTION AND PRIVATE SECTOR UNDER
CONSTRUCTION LICENCED POWER PLANTS
ENERGY DEMAND (LOW DEMAND)
RESERVE %

194000 202730 213880 228210 243500 259815 277222 295519 315023 335815
7,9

5,5

4,0

74

2,6

6,1

1,4

-4,2

-9,0

-14,8

-21,2

Figure 31 : Development of Firm Generation Capacity of Existing Power Plants + State


owned Power Plants Under Construction + Private Sector owned Power Plants Under
Construction Granted by Licence and Expected to be in Service on Proposed Date and
Energy Demand (Case II - B)
Low Demand Scenario 2
400000

350000

300000

GWh

250000

200000

150000

100000

50000

0
2009

2010

EXISTING

2011

2012

2013

UNDER CONSTRUCTION

2014

2015

GRANTED BY LICENCE

2016

2017

2018

ENERGY DEMAND

In accordance with Case II B, breakdown of the total installed capacity to thermal,


hydro and wind resources by year is given on Table 42 and Figure 32.
Table 42 : Development of Total Installed Capacity (Case II - B) Low Demand Scenario 2

2009
2010
2011
2012
2013
2014
2015
2016
2017
2018

THERMAL
MW
%
27905
64
27683
62
28966
61
29574
59
32653
62
32653
62
32653
62
32653
60
32653
60
32653
60

HYDRO
MW
14736
16100
17726
19320
19320
19320
19320
20520
20520
20520

75

%
34
36
37
39
36
36
36
38
38
38

WIND+RENEWABLES
MW
%
655
2
857
2
1067
2
1067
2
1067
2
1067
2
1067
2
1067
2
1067
2
1067
2

TOTAL
MW
43295
44640
47760
49962
53040
53040
53040
54240
54240
54240

Figure 32 : Development of Total Installed Capacity and Peak Demand (Case II - B)


Low Demand Scenario 2
60000

50000

MW

40000

30000

20000

10000

0
2009

2010

2011

2012

THERMAL

2013

2014

HYDRO

2015

WIND+REN.

2016

2017

2018

PEAK DEMAND

Figure 33 : Capacity Reserve, Project Generation Reserve and Firm Generation Reserve
(Case II - B) Low Demand Scenario 2
75,0

65,0

55,0

45,0

35,0

(%)

25,0

15,0

5,0

-5,0

-15,0

-25,0

2009

2010

2011

2012

2013

2014

2015

2016

2017

CAPACITY RESERVE

44,8

42,9

44,9

42,1

41,3

32,5

24,1

19,1

11,7

2018
4,8

PROJECT GENERATION RESERVE

27,1

24,5

22,5

20,8

20,7

15,6

8,7

3,7

-3,1

-10,2

FIRM GENERATION RESERVE

7,9

5,5

4,0

2,6

6,1

1,4

-4,2

-9,0

-14,8

-21,2

As can be seen from the Figure 33, starting from the year 2015 the new additional capacity
is necessary to be comissioned in the system not to come into existence of energy shortage in the
system according to the case.

76

Figure 34: Development of Project Generation, Firm Generation and Energy Demand
(Case II - B) Low Demand Scenario 2
500000

450000

400000

GWh

350000

300000

250000

200000

150000

100000

50000

0
2009

2010

2011

PROJECT

2012

2013

2014

FIRM

2015

DEMAND

77

2016

2017

2018

VII. COMPARISON OF RESULTS


By taking into consideration of the capacities granted by licence by EPDK and expected to be in
comissioning in the period of the Capacity Projection, two different Scenarios, Scenario 1 and
Scenario 2, have been formed. As has been explained before it is expected that 11188.8 MW and
9047.1 MW additional capacities will be added to the system in the study period according to
Scenario 1 and Scenario 2 respectively. High and Low Demand series determined by ETKB have
been used for both two scenarios and so Suppy-Demand Balances are calculated according to the
Project and Firm Generation Capacities.
The capacities of the private sector owned under construction granted by licence and expected to
be in comissioning in the study period have accumulated for both two scenarios in the period of
the years of 2009 and 2013. Therefore as can be seen from Table 43, Table 44 and Figure 35,
reserve rates increase up to 2013 and then while demand increases reserve rates decrease sharply
because of no new additional capacity.
In the Chapter II the demand forecastes are explained detailed as High Demand series and Low
Demand series. The expected yearly average demand rates are about 7.5% and 6.5% for High
Demand and Low Demand respectively forward.
Rate of energy reserve is very important for reliability of system. In case if not only the demand
rates but also the capacities existing, under construction and granted by licence and expected to be
in comissioning in the period of study are realised as expected, the shortages of energy are
supposed in accordance with;

Scenario 1 for the project generation capacity and both high and low demand series in
2017 and 2018 respectively,
Scenario 1 for the firm generation capacity and both high and low demand series in 2015
and 2016 respectively,
Scenario 2 for the firm generation capacity and both high and low demand series in 2016
and 2017 respectively,
Scenario 2 for the firm generation capacity and both high and low demand series in 2014
and 2015 respectively.

In accordance with not only the results of Scenario 2 which is formed by expecting much less
capacities to be comissioned in the system in the period of study and but also realization of the
demand as expected, it is supposed that the electricity demand will not be able to be covered in
2014. Therefore necessary measures should be realized by taking into consideration of
construction duration of investment facilities that will be comissioned in the system after 2014 in
order to be completed their licence procedures and to be started their investments as starting from
2010. If there is any delay in comissioning of the new additional capacity composed of under
construction and granted by licence and expected to be comissioned in the study period, the rates
of energy shortage will increase by year as can be seen from the table and figure below.

78

Table 43: Reserve Rates for both two Scenarios in accordance with Project Generation
Capacity (%)
SCENARIO 1

2009

SCENARIO
1
HIGH DEMAND
LOW DEMAND

SCENARIO 2

2010

LOW DEMAND

2012

2013

2014

2015

2016

2017

%
2018

27,3

25,1

22,1

23,8

24,9

17,1

9,2

3,3

-4,1

-11,8

27,3

25,1

23,3

25,9

28,0

20,8

13,5

8,3

1,2

-6,2

2009

SCENARIO
2
HIGH DEMAND

2011

2010

2011

2012

2013

2014

2015

2016

2017

%
2018

27,1

24,5

21,4

18,7

17,8

12,0

4,5

-1,0

-8,2

-15,6

27,1

24,5

22,5

20,8

20,7

15,6

8,7

3,7

-3,1

-10,2

Table 44: Reserve Rates for both two Scenarios in accordance with Firm Generation
Capacity (%)
%

SCENARIO 1

2009

SCENARIO
1
HIGH DEMAND
LOW DEMAND

2010

2011

2012

2013

2014

2015

2016

2017

2018

8,0

5,9

3,5

5,5

10,2

2,9

-3,5

-9,1

-15,6

-22,4

8,0

5,9

4,4

7,3

12,9

6,2

0,3

-4,7

-10,9

-17,5
%

SCENARIO 2

2009

SCENARIO
2
HIGH DEMAND
LOW DEMAND

2010

2011

2012

2013

2014

2015

2016

2017

2018

7,9

5,5

3,0

0,9

3,6

-1,7

-7,9

-13,1

-19,3

-25,9

7,9

5,5

4,0

2,6

6,1

1,4

-4,2

-9,0

-14,8

-21,2

Figure 35: Reserve Rates for both two Scenarios in accordance with Project and Firm
Generation Capacities (%)
SCENERIO 1

SCENERIO 2

30,0

25,0

20,0
15,0

10,0

5,0

0,0
2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2009

2010

2011

2012

2013

2014

2015

2016

-5,0

-10,0

-15,0

-20,0

PROJECT HIGH DEMAND


FIRM HIGH DEMAND

-25,0

PROJECT LOW DEMAND


FIRM LOW DEMAND

-30,0

79

PROJECT HIGH DEMAND


FIRM HIGH DEMAND

PROJECT LOW DEMAND


FIRM LOW DEMAND

2017

2018

VIII. CONCLUSION AND RECOMMENDATIONS


In case if Base Energy Demand prepared by ETKB is realized;

with addition of 14865 MW new installed capacity composed of 3676 MW state owned
under construction and 11189 MW private sector owned under construction granted by
licence (Scenario 1) and proposed to be in comissioning up to 2013 by EPDK to the
existing power system as end of the year 2008, it is calculated that the expected electricity
demands according to project generation capacity and firm generation capacity will not be
covered as from the years of 2017 and 2015 respectively.
with addition of 12723 MW new installed capacity composed of 3676 MW state owned
under construction and 9047 MW private sector owned under construction granted by
licence (Scenario 2) and proposed to be in comissioning up to 2013 by EPDK to the
existing power system as end of the year 2008, it is calculated that the expected electricity
demands according to project generation capacity and firm generation capacity will not be
covered as from the years of 2016 and 2014 respectively.

As mentioned in the Assumptions Section of this report before, balance tables and years of
demand not covered have been calculated in accordance with the following assumptions :

all of the power plants, connected to the system, which are existing, state owned under
construction and private sector owned under construction granted by licence will generate
electricity as much as the amount of their project and firm generation capacities,
there will be no constraint on fuel supply,
related to hydro conditions, hydro power plants will generate the amount of electricity as
expected and
power plants which are granted by licence and under construction will be in service on
proposed date.

Although contracts of some BOT Projects with TETA will expire in the period of the projection,
after expired contract it is supposed that these plants will continue to produce electicity as much
as produced before according to the new statue. So the balance tables has been prepared
according to this assumption.
But different realization of any assumption from the Assumptions mentioned in The Capacity
Projection Study will affect the results calculated in the report and so the years of demand not
covered will be able to change.
The capacities in the scope of the BOT, TOR and BO models guaranteed for purchasing of their
electricity (take-or-pay contract) have been used almost fully productive, but it is seen clearly
from this study that some part of the state owned capacity couldnt have been used because of the
demand quantity and the load characteristics.
In case if ;
demand does not realize as estimated
water flow accumulated in hydro plants does not realize as estimated before,
some constrains are faced with in the supply and quality of fuel,
long term outages occur at power plants,
state owned and private sector owned plants which are under construction, are not become
in service on foreseen dates,
80

it is essentially necessary that capacity and energy reserves by primary energy resources should be
kept on certain amounts for reliable operation of the electricity system. Therefore, in order to
operate generation system with reserves before the overlap of demand with supply, necessary
measures should be adopted by taking into consideration of construction duration of investment
facilities in order to be completed their licence procedures and to be started their investments as
starting from 2010.
When the majority of new additional capacity comes from thermal resources, the total additional
capacity is lower but in case of hydro and wind intensity in the new additional capacity, the
amount of total new additional capacity is relatively higher. While a decision and a policy are
determined about the additional capacity to connect to the system, this situation should be
considered. Especially, this situation should be considered more sensitively for investments and
security of supply in electricity systems in which high demand increases are expected. In the case
of covering whole of required new capacity to be constructed in order to meet peak demand, from
thermal plants, the additional capacity will be about half of the same capacity that is totally
covered by hydro and renewable plants.
Moreover, not only in the market structure that investment decisions from the point of view of
resource types and commissioning years of power plants are given by investors and but also
especially in the electricity system that electricity demand is expected to increase with a high rate
as gradually after wearing to an end of effects of the economic crisis, how the necessary
investments break primary resources down is extremely important. In other words, it is very
important that how much suitable diversification policies of necessary generation in point of
primary resources are, should be investigated in order to meet the country demand with a reliable
reserve and for security of supply.
In addition in the market that demand is expected to increase with a high rate as gradually, it is
extremely important that required measures should be taken in order to have plants both granted
by licence and applied for licence been in operation on proposed date for security of supply.
Especially since the end of 1990s increasing of the private sectors installed capacities, huge
amount of these capacities being thermal and also guaranteed with take or pay contracts have
caused the state owned power plants to be operated limited related to low demand. In actual
conditions, when generation capacity is higher than demand, extra capacities arent used.
Moreover when all of the power plants are in equal conditions, operation order of the power
plants starts from the plants with the cheapest generation cost to the most expensive one. However
since the specific capacity has privileged rights or generation priority, electricity is generated
from this capacity first without taking into consideration the generation cost. Therefore not only
total electricity demand but also load profile showing levels of electricity consumption should be
kept in mind while generation priority or privileged rights are given to the plants. At least, total
amount of the capacity to which the priority is given should be paid attention to be less than level
of the base load of the electricity system.

81

IX.

ANNEXES

82

ANNEX 1 : EXISTING SYSTEM (As end of year 2008)


EA THERMAL POWER PLANTS
Installed
Capacity
MW

HARD
COAL
NATURAL
GAS

LIGNITE

EA

DIESEL

FUEL OIL

NAME OF THE PLANT

AMBARLI

Project
Generation
GWh

Firm
Generation
(for 2008)
GWh

630,0

4410

2425

HOPA

50,0

350

200

TOTAL

680,0

4760

2625

ALAA-EVRM

180,0

1260

1071

1,0

TOTAL

181,0

1260

1071

ATALAZI-B

300,0

1950

1967

TOTAL

300,0

1950

1967

AN 1-2

320,0

2080

2110

HAKKAR UKURCA

ELBSTAN A

1355,0

8808

4306

ELBSTAN B 1-4

1440,0

9360

8797

KANGAL

457,0

2971

1975

ORHANEL

210,0

1365

1167

SEYTMER

600,0

3900

3745

TUNBLEK

365,0

2373

1624

TOTAL

4747,0

30856

23724

AMBARLI-D.GAZ

1350,9

9456

8046

BURSA D.GAZ

1432,0

10024

8581

TOTAL

2782,9

19480

16627

8690,9

58305,8

46014,0

Project
Generation
GWh

Firm
Generation
(for 2008)
GWh
3390

EA THERMAL TOTAL

EA AFFILIATED PARTNERSHIPS POWER PLANTS


Installed
Capacity
MW

LIGNITE

KEMERKY

NATURAL
GAS

EA AFFILIATED PARTNERSHIPS

NAME OF THE PLANT

630,0

4095

SOMA A

44,0

286

235

SOMA B

990,0

6435

4859

YATAAN

630,0

4095

3542

YENKY

420,0

2730

1291

TOTAL

2714,0

17641

13317

HAMTABAT

1120,0

7840

6031

TOTAL

1120,0

7840

6031

3834,0

25481

19348

EA AFFILIATED PARTNERSHIPS TOTAL

83

EA HYDRO POWER PLANTS


Installed
Capacity
MW

NAME OF THE PLANT

62,0

150

10

ALMUS

27,0

100

30

ALTINKAYA

702,6

1632

740

ASLANTA

138,0

569

320

ATATRK

2405,0

8100

5230

BATMAN

198,0

483

200

BERKE

510,0

1669

790

BORKA

300,6

1039

600

ATALAN

168,9

596

330

AMLIGZE

32,0

102

68

DEMRKPR

69,0

80

32
150

56,4

257

110,0

298

220

74,5

314

200

GEZENDE

159,4

528

130

GKEKAYA

278,4

400

240

HASAN UURLU

500,0

1217

820

HRFANLI

128,0

300

140

KAPULUKAYA

54,0

190

120

KARACAREN-1

32,0

142

60

KARACAREN II

46,4

206

90

1800,0

7500

5310

DCLE
DOANKENT

HYDRO

Firm
Generation
(for 2008)
GWh

ADIGZEL

DERBENT

EA

Project
Generation
GWh

KARAKAYA
KARKAMI

189,0

652

320

KEBAN

1330,0

6600

4120

KEMER

48,0

80

45

KESKKPR

76,0

250

80

120,0

332

277
300

KILIKAYA
KKLCE

90,0

588

KRALKIZI

94,5

146

90

KRTN

85,0

198

140

MANAVGAT

48,0

220

110

MENZELET

124,0

515

360

MURATLI

115,0

444

253

ZLCE

170,0

413

290

SARIYAR

160,0

300

180

SUAT UURLU

69,0

350

250

TORTUM

26,2

100

85

YENCE

37,9

122

50

TORUL

105,6

322

130

60,0

350

212

SEYHAN I
SEYHAN II

7,5

33

283,5

725

500

KADINCIK I

70,0

315

180

KADINCIK II

56,0

307

165

YRER

6,0

20

KEPEZ I-II

32,4

170

55

ANLI URFA

51,8

124

85

DERLER

148,3

100

40

11455,9

39648

24158

23980,8

123435

89520

SIR

EA HYDRO TOTAL
EA AND AFFILIATED PARTNERSHIPS
TOTAL

84

TRANSFER OF OPERATIONAL RIGHT POWER PLANTS

Installed
Capacity
MW

TOR

NAME OF THE PLANT

AYIRHAN PARK HOLD.

Firm
Project
Generation
Generation
(for 2008)
GWh
GWh

620,0

3624

3624

30,1

TOTAL

650,1

3624

3624

TOR TOTAL

650,1

3624

3624

HAZAR 1-2

BUILT - OPERATE POWER PLANTS

Installed
Capacity
MW

NATURAL GAS
IMPORT
COAL

BO

NAME OF THE PLANT

ANKARA
GEBZE D.GAZ
ADAPAZARI

Firm
Project
Generation
Generation
(for 2008)
GWh
GWh

798,0

5884

5884

1595,4

12822

12822

797,7

6398

6398

1590,7

12683

12683

TOPLAM

4781,8

37787

37787

SKENDERUN

1320,0

9135

9135

TOTAL

1320,0

9135

9135

BO TOTAL

6101,8

46922

46922

ZMR

85

BUILT OPERATE TRANSFER POWER PLANTS

Installed
Capacity
MW

BOT THERMAL

NAME OF THE PLANT

TRAKYA ELEKTRK ENRON

498,7

3772

3772

ESENYURT (DOA)

188,5

1381

1381

OVA ELEK.

258,4

2215

2215

UNMAR

504,0

3877

3877

1449,6

11245

11245

672,0

2258

2258

4,2

21

21

AKSU (AYKY)

16,0

35

35

BERDAN (ALARKO)

10,0

44

44

AL (LMAK) (Denizli)

2,5

11

11

84,0

361

361

3,0

16

16

16,5

88

88

TOTAL
BRECK
AHKY I-II

AMLICA (AYEN ENERJ)

BOT

BOT HYDRO

DNAR-II (METAK)
FETHYE
GAZLER (Idr)

11,2

51

51

GRLEVK-II / MERCAN

11,0

39

39

GNEN

10,6

48

48

9,6

42

42

HASANLAR (ALARKO)
KISIK (AYEN ENERJ)

9,6

34

34

SUATI (ERE EN.)

7,0

26

26
12

STCLER

2,3

12

12,5

58

58

YAMULA

100,0

336

336

TOTAL

982,0

3480

3480

7,2

19

19

10,2

31

31

TOHMA MEDK (ALARKO)

BOT WIND

Firm
Project
Generation
Generation
(for 2008)
GWh
GWh

ARES (ALAATI)
BORES (BOZCAADA)
TOTAL

BOT TOTAL

17,4

49,9

49,9

2449,0

14775

14775

MOBILE POWER PLANTS

Installed
Capacity
MW

FUEL OIL

MOBILE

NAME OF THE PLANT

Firm
Project
Generation
Generation
(for 2008)
GWh
GWh

SAMSUN 1

131,3

876

500

SAMSUN 2

131,3

876

500

MOBILE TOTAL

262,6

1752

1000

86

Installed
Capacity
MW

NAME OF THE PLANT

AKSEN (Gaziantep)

21,1

AKDENZ SEKA (Silifke)

20,0

MLDA KAIT (AKSU SEKA)


AK TEKSTL-1(Gaziantep)
ALAA PETKM
ANADOLU EFES BRA I
ALBAYRAK TURZM (BALIKESR
SEKA)

FUEL OIL

20
87

87

170,0

1357

1357

3,8

32

32

9,3

56
70

GAP N.(CAY SEKA-AFYON)

8,0

60

60

75,0

450

450

GL ENERJ (Gaziantep)

25,0

193

193

HABA (Bilecik)

18,0

144

144

HABA (zmir)

36,0

288

288

5,1

39

39

HALKALI KAIT
ISPARTA MENSUCAT

10,7

85

85

KIRKA BORAKS (Krka)

8,2

32

32

POLNAS (Manisa)
SAMUR A.. (Esenboa)

3,4

27

27

26,2

106

106
52

7,4

52

10,0

75

75

7,4

60

60

ET ALMNYUM (S.EHR)

11,9

35

35

SUPER FLM

25,3

203

203

TPRA ZMR (ALAA RAF.)

44,0

306

306

TPRA (Orta Anadolu-Krkkale)

24,0

168

168

TPRA (zmit-Yarmca)

84,1

545

545

TPRA (Batman)

10,3

72

72

8,0

37

37

TRE-KUTSAN (Tire)
DERLER (zole)
TOTAL
DIESEL

20

8,0
13,0

56

ORS (Polatl)

TPRA (Batman)
DERLER
TOTAL

IMPORT
COAL

168

70

MOPAK (Dalaman)

HARD COAL

168

10,0

MED UNON A.. (EBSO)

96,0

300

300

799,2

5067

5067

10,3

72

72

0,1

10,4

73

73

190,0

1425

1425

6,0

45

45

196,0

1470

1470

220,4

772

772

35,0

300

300

255,4

1072

1072

3,4

24

24

10,7

78

78

PETLAS

6,0

40

40

MARMARA KAIT (Bilorsa)

2,0

155,5

285

285

177,6

436

436

OLAKOLU-2
KAHRAMANMARA KAIT
TOTAL
SDEMR
KARDEMR
TOTAL
ALKM (ALKAL KMYA) (Dazkr)
ET MADEN (BANDIRMA BORAKS)

LIGNITE

Firm
Generation
GWh

OYKA KA. (CAYCUMA SEKA)


ERDEMR

AUTOPRODUCERS

Project
Generation
GWh

DERLER
TOTAL

87

Installed
Capacity
MW

LPG

NAME OF THE PLANT

10,4

82

82

EGE BRLEK ENERJ

12,8

107

107

GOODYEAR (Adapazar)

9,6

79

79

GOODYEAR (zmit)

4,2

35

35

MOPAK KAIT (Iklar)

TOTAL

NAPTHA

MENDERES TEKS. (AKA ENERJ)

4,6

33

33

10,0

65

65

51,6

402

402
140

18,7

140

ALKM KAIT

5,2

41

41

DENTA (Denizli)

5,0

38

38

DESA (Iklar)

10,6

70

70

MENSA MENSUCAT

10,4

85

85

TOROS (Ceyhan)

4,7

38

38

TOROS (Mersin)

12,1

96

96

SKTA Aydn)

4,5

38

38

71,2

546

546

ACIBADEM Bursa

1,3

11

11

ACIBADEM Kadky 1

0,5

TOTAL

ACIBADEM Kadky 2

0,6

AKATEKS orlu

1,8

14

14

AKBALAR

8,7

73

73

AKIN ENERJ (B.Kartran)

4,9

37

37

AKMAYA (LLEBURGAZ)

6,9

48

48

ALTINYILDIZ (Yenibosna)

4,7

40

40

ALTINMARKA

3,6

29

29

AMYLUM NASTA (Adana)


ARELK (ayrova)
ARELK (Eskiehir)

14,3

80

80

6,5

49

49

6,3

48

48

12,7

101

101

ATA N. ANTALYA

5,4

37

37

ATATEKS TEKSTL

5,6

45

45

ATLAS HALICILIK (orlu)

1,0

AYDIN RME

7,5

60

60

AYKA TEKSTL

5,5

41

41

ARENKO (Denizli)
NATURAL GAS

Firm
Generation
GWh

ET BOR (EMET)

ORTA ANADOLU MENSUCAT

AUTOPRODUCERS

Project
Generation
GWh

BAHARYE HALI

1,0

BAHIVAN GIDA (LLEBURGAZ)

1,2

BAYDEMRLER (Beylikdz)

9,3

77

77

BEY ENERJ (B.Kartran)

5,0

36

36

BL ENERJ (Ankara)

36,6

255

255

CAN TEKSTL (orlu)

5,2

40

40

ECZACIBAI BAXTER

1,0

COGNS (Tuzla)*

1,0

IRAAN SARAYI

1,3

11

11

123,4

1047

1047

14,0

113

113

1,0

OLAKOLU-1
DENZL MENTO
DOU (B.Kartran)

88

Installed
Capacity
MW

NAME OF THE PLANT

4,9

38

38

EKOTEN TEKSTL

1,9

15

15

ELSE TEKSTL

3,2

25

25

ERAK GYM

1,4

12

12

EROLU GYM

1,2

ESKEHR ENDSTR ENERJ(OSB)

59,0

452

452

ERDEMR

80,0

480

480

EVYAP

5,1

30

30

FLOKSER Tekstil (Poliser)

2,1

17

17

FLOKSER Tekstil (Setser)

2,1

17

17

FOUR SEASONS OTEL

1,2

FRTOLAY GIDA

0,6

GLLE ENTEGRE (orlu)

6,3

47

47

HABA (Aliaa)

NATURAL GAS

Firm
Generation
GWh

EDP PLK (B.Kartran)

GRANSER GRANT

AUTOPRODUCERS

Project
Generation
GWh

5,5

42

42

224,5

1796

1796

HAYAT KAIT SAN.

7,5

56

56

HAYAT KMYA (zmit)

5,2

32

32

HAYAT TEMZLK

15,0

94

94

GSA (Yarmca)

11,0

76

76

9,2

63

63

SKO (negl)
KALESERAMK
(an.seramik+Kalebodur)
KARTONSAN (zmit)

21,6

157

157

24,0

192

192

KASTAMONU ENTEGRE

7,5

48

48

KIVAN TEKSTL

3,9

33

33

KL-SAN

3,2

25

25

KOMBASSAN AMBALAJ (Konya)

5,5

40

40

KOMBASSAN AMBALAJ (Tekirda)

5,5

38

38

KORUMA KLOR

9,6

77

77

KKALIK TEKSTL

8,0

64

64
434

MANSA O.S.B.

84,8

434

MAKS ENERJ (HAMOLU)

7,7

62

62

MARMARA PAMUK

8,7

71

71

MB EKER NASTA SAN.(AKSARAY)

8,8

60

60

MELKE TEKSTL (GAZANTEP)

1,6

11

11

MSS APRE TEKS. (ADANA)

2,0

14

14

MERCEDES BENZ

8,3

68

68

MODERN ENERJ

96,8

680

680

NUH ENERJ 2 (Nuh imento)

514

73,0

514

NUR YILDIZ (GEM-TA)

1,4

ZAKIM ENERJ (Grsu)

7,0

60

60

PAKGIDA (Dzce-Kseky)

6,9

55

55

PAKGIDA (Kemalpaa)

5,7

43

43

PAKMAYA (zmit)
POLAT TURZM (POLAT
RENAISSANCE)

6,9

55

55

1,6

11

11

89

Installed
Capacity
MW

NAME OF THE PLANT

NATURAL GAS

Firm
Generation
GWh

SARKUYSAN (Tuzla)

7,7

60

60

SMKO (Kartal)

2,1

14

14

STANDARD PROFL

6,7

49

49

SPERBOY BOYA

1,0

SNMEZ FLAMENT

4,1

29

29
180

AHNLER ENERJ (B.Kartran)

AUTOPRODUCERS

Project
Generation
GWh

26,0

180

IK MAKAS

1,6

13

13

SWISS OTEL ( stanbul)

1,6

11

11

TAV Esenboa

3,9

33

33

TANRIVERD

4,7

39

39

TEKBOY TEKSTL

2,2

16

16

TERMAL SERAMK (St)

4,6

34

34

TEZCAN GALVANZ GR I-II

3,7

29

29

TRAKYA PLK (erkezky)

4,2

29

29

TBA

1,4

YILDIZ ENTEGRE

6,2

40

40

YILFERT (TGSA GEMLK GB.)

8,0

50

50

TP MERSERZE (B.Kartran)

5,7

46

46

YALOVA ELYAF

12,3

YILDIZ SUNTA (Kseky)

27,8

180

180

YONGAPAN (Kastamonu)

9,7

61

61

YURTBAY (Eskiehir)

7,8

62

62

ZEYNEP GYM

1,2

78,9

275

275

1387,8

9747,3

9747,3

DERLER
TOTAL

90

Installed
Capacity
MW

BIO GAS

NAME OF THE PLANT

3,2

22

22

ZAYDA (zmit p)

5,2

37

37

KEMERBURGAZ

4,0

ADANA ATIK

0,8

OTHERS

13,2

72

72

BANDIRMA AST(ET MADEN)

11,5

88

88

BANDIRMA BAFA

10,0

57

57

21,5

145

145

1,2

1,2

OYMAPINAR (ET ALMNYUM)

540,0

1620

1170

TOPLAM

TOTAL

WIND

SUNJT
TOTAL

RUN OF RIVER

AUTOPRODUCERS

Firm
Generation
GWh

BELKA (Ankara)

TOTAL

HYDRO
(DAM)

Project
Generation
GWh

540,0

1620

1170

BACI SU RNLER

0,3

1,7

1,7

KAREL (PAMUKOVA)

9,3

55,0

40,0

MOLU

3,4

10,6

10,6

YELLLER (Krehir)

0,5

1,0

1,0

13,5

68

53

553,5

1688

1223

3.538,5

20.720,4

20.254,9

TOTAL
HYDRO TOTAL
AUTOPRODUCERS TOTAL

91

PRIVATE GENERATION COMPANY POWER PLANTS


Installed
Capacity
MW

NATURAL GAS

PRIVATE GENERATION COMPANIES

NAPTHA

NAME OF THE PLANT

Project
Generation
GWh

Firm
Generation
GWh

AK ENERJ (Yalova) zole

21,0

173

173

AK ENERJ (Deba Denizli)


ATAER ENERJ (EBSO)

15,6
70,2

398

398

TOPLAM
AK ENERJ (Yalova Akal)
AK ENERJ (zmir-Batim)
AK ENERJ (Bozyk)
AK ENERJ (erkezky)
AK ENERJ (Yalova)
AK ENERJ (Kemalpaa)
AK ENERJ (Uak OSB)
AKSA ENERJ (ANTALYA)
AKSA ENERJ (MANSA)
ALARKO ALTEK
ALAA akmaktepe Enerji
ANTALYA ENERJ
AYEN OSTM
BERK ENERJ (KURTKY))
BS ENERJ (Bursa San.)
BOSEN (Bursa San.)
BOZ ENERJ
BURGAZ ELEKTRK
CAM ELEKTRK (Mersin)
CAM ELEKTRK (B.Kartran)
CAN ENERJ
EB ENERJ
ELK ENERJ (Uzuniftlik)
ERKEZKY ENERJ
ENERJ-SA (Adana)
ENERJ-SA (Mersin)
ENERJ-SA (anakkale)
ENERJ-SA (KENTSA)Kseky
ENTEK (Kseky-ztek)
ENTEK (KO niversite)
ENTEK Demirta
KAREN I-II KPA ELEKTRK
KAREGE ARGES
METEM ENERJ (Hacramat)
METEM ENERJ (Peliklik)
NOREN ENERJ
NUH ENERJ 1 (Nuh imento)
SAYENERJ (Kayseri OSB)
SNMEZ ELEKTRK
T ENERJ TURCAS
ZORLU ENERJ (Bursa)
ZORLU ENERJ (B. Kartran)
ZORLU ENERJ (Sincan)
ZORLU ENERJ (Kayseri)
ZORLU ENERJ (Pnarba/Kayseri)
ZORLU ENERJ (Yalova)
TOTAL

92

106,8
10,4
45,0
126,6
98,0
38,5
127,2
15,2
183,8
52,4
82,0
34,8
52,4
41,0
14,8
410,0
142,8
8,7
6,9
126,1
32,9
56,3
64,4
2,4
49,2
130,2
64,5
64,1
120,0
144,8
2,3
145,9
24,3
43,6
7,8
11,7
8,7
38,0
5,9
26,2
1,6
90,0
65,8
50,3
188,5
7,2
15,9

571
85
370
817
805
317
1044

571
85
370
817
805
317
1044

1290
370
567
278
367
348
104
3383
1071
60
55
1008
270
327
505
19
403
850
520
520
930
1251
19
1259
180
348
58
89
70
326
47
202
13
752
525
429
1439
59
122

1290
370
567
278
367
348
104
3383
1071
60
55
1008
270
327
505
19
403
850
520
520
930
1251
19
1259
180
348
58
89
70
326
47
202
13
752
525
429
1439
59
122

3079,1

23871

23871

PRIVATE GENERATION COMPANY POWER PLANTS


Installed
Capacity
MW

NAME OF THE PLANT


AKSA

1,4

10

10

150

140

EKOLOJK ENERJ (Kemerburgaz)

1,0

ORTADOU ENERJ (ODA YER)

2,8

22

19

TOTAL

25,0

189,5

176

AKSA ENERJ (Hakkari)

24,0

175

175

KIZILTEPE

34,1

250

250

WASTE
IMPORT
COAL

FUEL OIL

KARKEY (SLOP)

DIESEL

Firm
Generation
GWh

19,8

ITC-KA ENERJ MAMAK

PRIVATE GENERATION COMPANIES

Project
Generation
GWh

171,9

1200

1200

PS3-A -1

11,4

80

80

PS3-A -2 (DL)

24,4

180

180

SRT

25,6

190

190

TOTAL

291,4

2075

2075

DA ELK

135,0

948

948

TOTAL

135,0

948

948

VAN ENGL GAZ (ZORLU ENERJ)

15,0

75

75

TOTAL

15,0

75,0

75

3652,3

27729

27716

THERMAL TOTAL

93

Installed
Capacity
MW

NAME OF THE PLANT


BEREKET (DENZL)
BEREKET ( DALAMAN)

3,7

12

12

37,5

179

179

9,5

41

25

BEREKET (GKYAR)

11,6

43

23

39,9

163

140

101,9

408

263

DAREN HES (SEYRANTEPE)

49,7

182

161

ALP ELEKTRK (TINAZTEPE)

7,7

29

17

CANSU ELEKTRK (ARTVN)

9,2

47

31

ALDERE ELEKTRK (DALAMAN)

8,7

35

25

AKKY ENERJ (AKKY I HES)

DERMENST HES (KAHRAMANMARA)

25,7

69

40

HAMZALI HES (TURKON MNG)

16,7

117

66

8,7

18

11

22,4

79

45

H.G.M. ENERJ (KEKLCEK)


HDRO KONTROL (YUKARI MANAHOZ)
-EN ELEKTRK (ALKILA)

HYDRO

Firm
Generation
GWh

BEREKET (FESLEK)
BEREKET (MENTA)

PRIVATE GENERATION COMPANIES

Project
Generation
GWh

7,7

18

11

KALEN ENERJ (KALEN II)

15,7

50

28

MARA ENERJ (FIRNIS)

7,2

36

23

SARMAIK I HES (FETA FETHYE)

21,0

96

54

SARMAIK II HES (FETA FETHYE)

21,6

108

61

YEL ENERJ (TAYFUN HES)

0,8

MURGUL BAKIR

4,6

TEMSA ELEKTRK (GZEDE)

2,4

10

EKN ENERJ (BAARAN HES)

0,6

ENERJ-SA (BRKAPILI)

48,5

171

17

ENERJ-SA (AKSU- AHMALLAR)

14,0

45

ENERJ-SA (SUGZ-KIZILDZ)

15,4

55

EEN-II (GLTA)

43,4

170

ELTA (DODURGA)

4,1

12

12

14,2

44

20

SKUR (SLEYMANLI HES)

4,6

18

KURTEKS Karasu Andrn HES

2,4

19

19
30

TA YUKARI MERCAN

MOLU ENERJ (BAHELK HES)

4,2

30

ZGR ELEK. K.MARA Tahta HES

12,5

54

54

PAMUK (Toroslar)

23,3

112

28

SU ENERJ (AYGREN HES)

4,6

19

TEKTU-KARGILIK

23,9

83

19

TEKTU-KALEALTI HES

15,0

52

11

TEKTU-KEBANDERES

5,0

32

20

13,3

90

54
10

YAPISAN HACILAR
YPM ALTINTEPE HES

4,0

18

YPM BEYPINAR HES

3,6

18

YPM KONAK HES

4,0

19

10

BEYKY

16,8

87

87

KUZGUN

20,9

36

TERCAN

15,0

51

28

ATAKY

5,5

15,4

30

20

KZDERE

18,6

110

100

MERCAN

20,4

78

48

807,1

3217

1858

ILDIR

HYDRO TOTAL

94

PRIVATE GENERATION COMPANY POWER PLANTS


Installed
Capacity
MW

WIND

Project
Generation
GWh

Firm
Generation
GWh

ALZE ENERJ (Delta Plastik)

1,5

ANEMON ENERJ (NTEPE)

30,4

92

83

BARES (BANDIRMA)

30,0

105

95

DOAL ENERJ (BURGAZ)

14,9

48

43

DENZL ELK. (Karakurt-Akhisar)

10,8

28

24

0,9

MARE MANASTIR

39,2

129

129

BAK ELEKTRK AMLI RZGAR

21,0

104

92

8,1

24

19

ERTRK ELEKTRK (ATALCA)

60,0

210

180

NNORES ELEKTRK (YUNTDA)

42,5

161

145

ERTRK ELK. (TEPE)

DATA RES

LODOS RES (TAOLUK)

24,0

85

69

SAYALAR RZGAR (DOAL ENERJ)

30,6

97

88

SEBENOBA (DENZ ELEKTRK-SAMANDA)

31,2

100

86

345,1

1191

1059

TOTAL
MENDERES JEOTERMAL
GEOTH.

PRIVATE GENERATION COMPANIES

NAME OF THE PLANT

ZORLU ENERJ DENZL JEOTERMAL


SARAYKY JEOTERMAL (DENZL)
TOTAL

PRIVATE GENERATION COMPANY TOTAL

95

8,0

56

56

15,0

105

105

6,9

50

42

29,9

211

203

4834,4

32347

30835

ANNEX 2 : POWER PLANTS CONNECTED TO AND DISCONNECTED FROM THE


POWER SYSTEM IN 2008
CONNECTED
INSTALLED
CAPACITY (MW)

NAME OF PLANT
MB EKER NASTA SAN. A.. (Sultanhan)
AKSA ENERJ (Antalya)
AKSA ENERJ (Manisa)
ANTALYA ENERJ (lave)
ATA NAAT SAN. A.S.B.(ANTALYA)
BAHIVAN GIDA (LLEBURGAZ)
CAN ENERJ (orlu-TEKRDA) (lave)
FOUR SEASONS OTEL (ATK PASHA TUR.A.)
FRTOLAY GIDA SAN.VE TC.A.(lave)
ITC-KA Enerji retim A..(Mamak)(lave)
KARKEY(SLOP-5) (154 kV) (lave)
MELKE TEKSTL (GAZANTEP)
MSS APRE TEKSTL BOYA EN. SAN.
MODERN ENERJ (LLEBURGAZ)
ORTADOU ENERJ (ODA YER) (Eyp/ST.)
POLAT TURZ. (POLAT RENAISSANCE ST.OT.)
SARAYKY JEOTERMAL (Denizli)
YILDIZ SUNTA (Uzuniftlik-Kseky)(Dzeltme)
SNMEZ Elektrik (lave)
AKKY ENERJ (AKKY I HES)
ALP ELEKTRK (TINAZTEPE) ANTALYA
CANSU ELEKTRK (Murgul/ARTVN)
ALDERE ELK.(ALDERE HES)Dalaman-MULA
DAREN HES ELKT. (SEYRANTEPE BARAJI VE HES)
DERMENST EN. (KAHRAMANMARA)
GZEDE HES (TEMSA ELEKTRK) BURSA
H.G.M. ENERJ (KEKLCEK HES) (Yeilyurt)
HAMZALI HES (TURKON MNG ELEKTRK)
HDRO KNT.(YUKARI MANAHOZ REG.VE HES)
-EN ELK.(ALKILA REGLATR VE HES)
KALEN ENERJ (KALEN II REGLAT. VE HES)
MARA ENERJ (FIRNIS REGLATR VE HES)
SARMAIK I HES (FETA FETHYE ENERJ)
SARMAIK II HES (FETA FETHYE ENERJ)
TORUL
YEL ENERJ ELEKTRK (TAYFUN HES)
ZORLU ENERJ (MERCAN) (Dzeltme)
BAK ELEKTRK AMLI RZGAR
DATA RES (Data)
ERTRK ELEKTRK atalca RES
NNORES ELK YUNTDA RZG. (Aliaa)
LODOS RES (Taoluk)(G.O.P./STANBUL)
SAYALAR RZGAR (Doal Enerji)
SEBENOBA (DENZ ELK.) (Samanda-HATAY)
TOTAL

96

GENERATION
(MWh)

8,800
183,800
52,380
17,460
5,400
1,165
52,380
1,165
0,060
14,130
14,780
1,584
2,000
13,400
2,830
1,600
6,850
22,630
8,730
101,940
7,689
9,180
8,740
49,700
25,700
2,400
8,674
16,700
22,400
7,660
15,650
7,220
21,040
21,580
105,600
0,820
1,275
21,000
8,100
60,000
42,500
24,000
30,600
31,200

0
133.736
79.183
256.120
10
0
274.260
0
0
95.832
16.362
0
5.324
508.942
0
490
14.099
136.018
61
21.608
9.245
12.518
11.153
14.370
0
6.107
120
2.934
13.772
3.364
10.281
0
1.472
1.221
18.551
0
22.828
60.943
3.778
65.961
98.058
25.714
53.925
46.919

1.062,512

2.025.279

DISCONNECTED
INSTALLED
CAPACITY (MW)

NAME OF PLANT
CAM ELEKTRK (AYIROVA)

-12,200

SEKA (DG+F.O.)(zmit/Kseky)

-18,000

BRKO ENERJ(Bor)

-11,520

BERK ENERJ(Kurtky) (Dzeltme)

-8,310

TERMAL SERAMK (St) (Dzeltme)

-0,002

AK EN (DG+N)(Alapl-Zonguldak)

-5,200

ATAER ENER.ELEKT.RET.A..(DG+N)(Ebso)

-0,090

TOPRAK ENERJ(Eskiehir-2)

-9,000

MODERN ENERJ (LLEBURGAZ) (Dzeltme)

-3,880

MURGUL BAKIR (.Kaya)

-0,100

AK-ENERJ (orlu)

-10,400

KAREGE (K.Paa) (Dzeltme)

-0,690

TRK HENKEL Kimya (zole)

-1,590

TOTAL

-80,982

GARAND TOTAL (MW)

981,530

97

ANNEX 3 : POWER PLANTS EXPECTED TO BE IN SERVICE BETWEEN 2009-2016


UNDER CONSTRUCTION AND GRANTED BY LICENCE
(According to January 2009 Progress Report Published by EPDK Scenario 1)

YEAR

NAME OF THE PLANT

FUEL
TYPE

TOTAL
INSTALLED
CAPACITY
(MW)

FIRM
PROJECT
GENERATION GENERATION
(GWh)
(GWh)

2009
EPDK
EPDK
EPDK
EPDK

1,7
67,0
91,9
187,1

8,4
390,2
704,2
1190,3

8,4
390,2
704,2
1190,3

347,7

2293,1

2293,1

2,6
54,9
205,8

19,8
375,5
801,1

19,8
375,5
680,9

263,3

1196,4

1076,2

160,0
115,0
200,0
20,3
562,0

488,0
343,0
473,0
60,0
2225,7

418,0
176,0
337,0
45,0
1046,1

HYDRO TOTAL

1057,3

3589,7

2022,1

YEAR TOTAL

1668,3

7079,2

5391,4

145,6

1159,8

1159,8

145,6

1159,8

1159,8

11,4
173,3

87,5
646,9

87,5
549,9

184,7

734,4

637,4

308,9
57,2
39,5
64,8
1024,7

1187,0
100,0
118,0
200,0
3942,5

837,0
7,0
18,0
146,0
1853,0

HYDRO TOTAL

1495,1

5547,5

2861,0

YEAR TOTAL

1825,4

7441,7

4658,2

GRANTED BY LICENCE
GRANTED BY LICENCE
GRANTED BY LICENCE
GRANTED BY LICENCE

LIGNITE
F. OIL
D. GAZ
IMP.COAL

THERMAL TOTAL
EPDK
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE
GRANTED BY LICENCE

BIOGAS
GEOTH.
WIND

RENEWABLE(WIND+GEOTH.)
DS
DS
DS
DS
EPDK

ALPASLAN-I
AKKPR
OBRUK
MANYAS
GRANTED BY LICENCE

HYDRO
HYDRO
HYDRO
HYDRO
HYDRO

2010
EPDK

GRANTED BY LICENCE

N. GAS

THERMAL TOTAL
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE

WASTE
WIND

RENEWABLE(WIND+GEOTH.)
DS
DS
DS
DS
EPDK

ERMENEK
KILAVUZLU
NE
TOPAM
GRANTED BY LICENCE

HYDRO
HYDRO
HYDRO
HYDRO
HYDRO

98

YEAR

NAME OF THE PLANT

FUEL
TYPE

TOTAL
INSTALLED
CAPACITY
(MW)

FIRM
PROJECT
GENERATION GENERATION
(GWh)
(GWh)

2011
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE

N. GAS
IMP.COAL

805,9
410,3

6241,7
2916,0

6241,7
2916,0

1216,2

9157,7

9157,7

7,8
269,5

60,0
973,1

60,0
827,1

277,3

1033,1

887,1

670,0
1007,5

2118,0
3644,4

1212,0
1712,9

HYDRO TOTAL

1677,5

5762,4

2924,9

YEAR TOTAL

3171,0

15953,2

12969,7

1911,9
1215,8

15348,8
8640,0

15348,8
8640,0

3127,7

23988,8

23988,8

0,0

0,0

0,0

1818,7

5906,8

2776,2

HYDRO TOTAL

1818,7

5906,8

2776,2

YEAR TOTAL

4946,4

29895,6

26765,0

840,0
1213,3

5880,0
8015,7

5606,4
8015,7

2053,3

13895,7

13622,1

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

HYDRO TOTAL

0,0

0,0

0,0

2053,3

13895,7

13622,1

TERMK TOPLAMI
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE

WASTE
WIND

RENEWABLE(WIND+GEOTH.)
DS
EPDK

DERNER
LSANS ALMI PROJELER

HES
HES

2012
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE

LIGNITE
IMP.COAL.

TERMK TOPLAMI

RENEWABLE(WIND+GEOTH.)
EPDK

GRANTED BY LICENCE

HES

2013
EA
EPDK

AMBARLI - B DGK
LSANS ALMI PROJELER

N. GAS
IMP.COAL

THERMAL TOTAL

YEAR TOTAL

99

YEAR

NAME OF THE PLANT

FUEL
TYPE

TOTAL
INSTALLED
CAPACITY
(MW)

FIRM
PROJECT
GENERATION GENERATION
(GWh)
(GWh)

2014
THERMAL TOTAL

0,0

0,0

0,0

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

HYDRO TOTAL

0,0

0,0

0,0

YEAR TOTAL

0,0

0,0

0,0

THERMAL TOTAL

0,0

0,0

0,0

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

HYDRO TOTAL

0,0

0,0

0,0

YEAR TOTAL

0,0

0,0

0,0

THERMAL TOTAL

0,0

0,0

0,0

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

1200,0

3833,0

2459,0

HYDRO TOTAL

1200,0

3833,0

2459,0

YEAR TOTAL

1200,0

3833,0

2459,0

2015

2016

DS

ILISU

HYDRO

Note: DSI projects and Ambarl-B N.G.C.C Power Plant constructed by EA are currently
under construction and remaining projects are granted by licence.

100

ANNEX 3 (Cont.) : POWER PLANTS EXPECTED TO BE IN SERVICE BETWEEN


2009-2016 UNDER CONSTRUCTION AND GRANTED BY LICENCE
(According to January 2009 Progress Report Published by EPDK Scenario 2)

YEAR

NAME OF THE PLANT

FUEL
TYPE

TOTAL
INSTALLED
CAPACITY
(MW)

FIRM
PROJECT
GENERATION GENERATION
(GWh)
(GWh)

2009
EPDK
EPDK
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE
GRANTED BY LICENCE
GRANTED BY LICENCE

LIGNITE
F. OIL
N.GAZ

1,7
67,0
91,9
187,1

8,4
390,2
704,2
1190,3

8,4
390,2
704,2
1190,3

347,7

2293,1

2293,1

2,6
47,4
172,8

19,8
312,5
639,7

19,8
312,5
543,8

222,8

972,0

876,1

160,0
115,0
200,0
20,3
412,5

488,0
343,0
473,0
60,0
1650,0

418,0
176,0
337,0
45,0
775,5

907,8

3014,0

1751,5

1478,3

6279,1

4920,7

78,6

639,8

639,8

78,6

639,8

639,8

11,4
183,8
7,5

87,5
706,3
63,0

87,5
600,3
63,0

202,7

856,8

750,8

308,9
57,2
39,5
64,8
893,3

1187,0
100,0
118,0
200,0
3508,2

837,0
7,0
18,0
146,0
1648,9

HYDRO TOTAL

1363,7

5113,2

2656,9

YEAR TOTAL

1645,0

6609,8

4047,5

IMP.COAL

THERMAL TOTAL
EPDK
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE
GRANTED BY LICENCE

BIOGAS
GEOTH.
WIND

RENEWABLE(WIND+GEOTH.)
DS
DS
DS
DS
EPDK

ALPASLAN-I
AKKPR
OBRUK
MANYAS
LSANS ALMI PROJELER

HYDRO
HYDRO
HYDRO
HYDRO
HYDRO

HYDRO TOTAL
YEAR TOTAL
2010
EPDK

GRANTED BY LICENCE

N. GAS

THERMAL TOTAL
EPDK
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE
GRANTED BY LICENCE

WASTE
WIND
GEOTH.

RENEWABLE(WIND+GEOTH.)
DS
DS
DS
DS
EPDK

ERMENEK
KILAVUZLU
NE
TOPAM
GRANTED BY LICENCE

HYDRO
HYDRO
HYDRO
HYDRO
HYDRO

101

YAKIT
YIL

SANTRAL ADI

TP

SANTRAL
KURULU
GC
(MW)

PROJE

GVENLR

RETM

RETM

(GWh)

(GWh)

2011
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE

N.GAS
IMP.COAL

872,9
410,3

6761,7
2916,0

6761,7
2916,0

1283,2

9677,7

9677,7

7,8
202,0

60,0
720,3

60,0
612,3

209,8

780,3

672,3

670,0
956,2

2118,0
3547,7

1212,0
1667,4

HYDRO TOTAL

1626,2

5665,7

2879,4

YEAR TOTAL

3119,2

16123,7

13229,4

607,9

4320,0

4320,0

607,9

4320,0

4320,0

0,0

0,0

0,0

1594,0

5128,6

2410,4

HYDRO TOTAL

1594,0

5128,6

2410,4

YEAR TOTAL

2201,9

9448,6

6730,4

840,0
1213,3
1025,0

5880,0
8015,7
8400,0

5606,4
8015,7
8400,0

3078,3

22295,7

22022,1

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

HYDRO TOTAL

0,0

0,0

0,0

3078,3

22295,7

22022,1

THERMAL TOTAL
EPDK
EPDK

GRANTED BY LICENCE
GRANTED BY LICENCE

WASTE
WIND

RENEWABLE(WIND+GEOTH.))
DS
EPDK

DERNER
GRANTED BY LICENCE

HYDRO
HYDRO

2012
EPDK

GRANTED BY LICENCE

IMP.COAL

THERMAL TOTAL

RENEWABLE(WIND+GEOTH.)
EPDK

GRANTED BY LICENCE

HYDRO

2013
EA
EPDK
EPDK

AMBARLI - B DGK
GRANTED BY LICENCE
GRANTED BY LICENCE

N.GAS
IMP.COAL
N.GAS

THERMAL TOTAL

YEAR TOTAL

102

YEAR

NAME OF THE PLANT

FUEL
TYPE

TOTAL
INSTALLED
CAPACITY
(MW)

FIRM
PROJECT
GENERATION GENERATION
(GWh)
(GWh)

2014
THERMAL TOTAL

0,0

0,0

0,0

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

HYDRO TOTAL

0,0

0,0

0,0

YEAR TOTAL

0,0

0,0

0,0

THERMAL TOTAL

0,0

0,0

0,0

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

HYDRO TOTAL

0,0

0,0

0,0

YEAR TOTAL

0,0

0,0

0,0

THERMAL TOTAL

0,0

0,0

0,0

RENEWABLE(WIND+GEOTH.)

0,0

0,0

0,0

1200,0

3833,0

2459,0

HYDRO TOTAL

1200,0

3833,0

2459,0

YEAR TOTAL

1200,0

3833,0

2459,0

2015

2016

DS

ILISU

HYDRO

Note: DSI projects and Ambarl-B N.G.C.C Power Plant constructed by EA are currently
under construction and remaining projects are granted by licence.

103

X.

TEA
TETA
EA
ETKB
EGM
EA
KEPEZ
MYTM
TEDA
EPDK
EPK
DS
ADA
DTP
GDP
WASP
MAED
BOT
BOO
TOR

Abbrivations

Turkish Electricity Transmission Company


Turkish Electricity Trading Company
Electricity Generation Company (State owned)
Ministry of Energy and Natural Resources
General Directorate of Energy Affairs
Former Private Company (Transferred to EA)
Former Private Company (Transferred to EA)
National Load Dispatching Center
Turkish Electricity Distribution Company
Energy Market Regulatory Authority
Electricity Market Law N0:4628
State Hydraulic Works
Private Generation Company
State Planning Organization
Gross Domestic Product
Wien Automatic System Planning
(Planning Model to use for Electricity Generation Expansion Planning)
Model for Analysis of Energy Demand
Built-Operate-Transfer
Built-Operate-Own
Transfer of Operational Right

104

Das könnte Ihnen auch gefallen