MATERIAL REQUIREMENT PLANNING ( MRP ) Material list : Material type FERT HALB HALB ROH ROH ROH ROH Material name acer00f monitorip1 keybordip2 screenrh1 camrh2 keysrh3 speeakersrh4

Sudheer .N

Material Description Acer laptop monitor Key board screens Web cam keys speakers

1. PLANNED INDIPENDENT REQUIREMENTS. Planned independent requirements are prime input of production planning.

TRANSACTION CODE : MD61

Then click enter, Page 1 of 25

Sap pp MRP user manuals


Then create planning table.

Sudheer .N

For each material , enter the daily requirements, say for the next 5 days.

Page 2 of 25

Sap pp MRP user manuals

Sudheer .N

SCHEDULING LINES.

Click save icon .

2. MRP RUN : MRP run or planning is an engine which converts the requirements elements (issues), into planned supply elements (receipts), balance the demand/ supply gaps. Issues & receipts are called MRP elements. Page 3 of 25

Sap pp MRP user manuals

Sudheer .N

T CODE : MD01

Page 4 of 25

Sap pp MRP user manuals

Sudheer .N

The above is the planning of our planning run. It shows the number of materials planned. It also shows the no. of planned orders and purchase requisition generated etc.

Page 5 of 25

Sap pp MRP user manuals


3. SINGLE ITEM, MULTI LEVEL planning :

Sudheer .N

Here individual material is planned individually. Enter material : ACER00F Enter plant : NSUS Processing key : NETCH Create purchase req, : 2 Delivery schedules : 3 Create mrp list : 1 Planning mode : 1 Press tick twice

Page 6 of 25

Sap pp MRP user manuals


4. MRP LIST :

Sudheer .N

This displays the receipt elements against issue elements.

Page 7 of 25

Sap pp MRP user manuals


5. STOCK REQUIREMENT LIST : T CODE : MD04

Sudheer .N

Page 8 of 25

Sap pp MRP user manuals

Sudheer .N

Then click save I con

Page 9 of 25

Sap pp MRP user manuals

Sudheer .N

Page 10 of 25

Sap pp MRP user manuals

Sudheer .N

Press enter

Page 11 of 25

Sap pp MRP user manuals

Sudheer .N

Here, we take the one of the planed order which are generated again the dependent requirements. Say planned order no. 0000038258 by double clicking the lans. You will get this pop-up, click the production order.

Page 12 of 25

Sap pp MRP user manuals

Sudheer .N

Then order release. Click on status line.

Page 13 of 25

Sap pp MRP user manuals

Sudheer .N

Page 14 of 25

Sap pp MRP user manuals

Sudheer .N

You can see that our order now has the released status Click the back ( arrow ) button to go to main header screen

Then click on flog icon The order has been released

Page 15 of 25

Sap pp MRP user manuals

Sudheer .N

Now the most important step, press the save button at the top.

Page 16 of 25

Sap pp MRP user manuals


6. Goods issue : T CODE : MIGO

Sudheer .N

Here one can give goods issue to an order. Enter movement type as 261 Enter the order no : 60003767

Page 17 of 25

Sap pp MRP user manuals

Sudheer .N

Information document 5000000158 posted

7. PRODUCTION ORDER CONFIRMATION : T CODE : CO15

Order number : 60003767 Then click enter Page 18 of 25

Sap pp MRP user manuals

Sudheer .N

By the confirming at the order level, all the operation are confirmed at once.

Press the save button at the top.

Page 19 of 25

Sap pp MRP user manuals

Sudheer .N

8. GOODS RECIPT FOR AN ORDER : T CODE : MIGO

Enter order no. 60003767 Enter movement type : 101

Page 20 of 25

Sap pp MRP user manuals

Sudheer .N

Page 21 of 25

Sap pp MRP user manuals

Sudheer .N

Which says that this goods receipt is being posted in the document no. 701000057

9. CHECK STOCK AVAILABILITY : T CODE : MD04

Page 22 of 25

Sap pp MRP user manuals

Sudheer .N

Press enter

10. STOCK OVERVIEW : T CODE : MMBE

Page 23 of 25

Sap pp MRP user manuals

Sudheer .N

Enter material no : monitorip1 Enter plant : NSUS Press execution button at the top left corner,

Page 24 of 25

Sap pp MRP user manuals

Sudheer .N

RESULT: one MRP cycle is completed

Page 25 of 25