Beruflich Dokumente
Kultur Dokumente
ONGC &
Bassein Mumbai
Onshore Operations
A hole is drilled for the production casing and the casing is run in the hole and cemented into place. The production casing string is usually run to the total depth of the well. A cement plug is also left in the production casing.
A down hole packer assembly (a type of seal assembly) is also run on the tubing & installed in the production casing to seal the reservoir from all strings of pipe, except the production tubing.
REMEMBER.. No job is so important & No service is so urgent that we cannot take time to perform our work safely.
Well Abandonment
Production Testing
Hermetical Test
Operation: Types of Test: Hazard : Hydraulic Pressure Test of Production Casing/ Liner to verify the integrity of the well from bottom to head 1)Negative Test 2) Positive Test Casing damage & Hanger Top Leakages may result in channeling behind casing, & may cause uncontrolled flow Blow out/ Fire
The casing head and casing shall be pressure tested separately to the maximum pressure expected in the formations subject to the rating of the casing/ liner assembly. The annular space between two consecutive casings should be connected to a valve. Ensure that It SHALL NOT be plugged. The valves shall be tested to working pressure only and all the lines being subjected to pressure are to be properly secured/anchored. Pressure gauges with suitable cocks should be installed for release of pressure during the test. Every well heads assembly shall be provided with suitable arrangement for recording tubing and annulus pressure. Well Head assembly should be pressure tested to 1-1/2 times the working pressure before installation.
Perforation
Operation: The casing in the well is perforated by firing explosive charges at appropriate horizon by means of a perforation gun or other charges, so that oil under reservoir pressure can flow through the perforations into the well and then to surface
Perforation Methods: 1)Gun Conveyed 2) Through tubing 3) TCP Hazard :If formation fluids entering the well are not kept under control may cause loss of well control. Hazards due to use of explosives and danger of fire. Consequence: Blow out/ Fire/ Surface Explosive damage Safety Measures:
1. Transport,
Explosives should be handled by persons authorized for the purpose. The persons should undergo an instruction programme in handling and use of explosive, before they are so authorized. Explosives should be primed at well site only but not be primed under conditions of lightning and thunder. The explosives should be suitable for the temperature conditions expected at the bottom of the hole. Precaution against sources of stray current be taken.
Perforation contd
Safety Measures:
2. To Prevent Blow-out:
A double ram preventer, should be installed and tested to the expected bottom hole pressures. A master gate valve with tubing head & a short length of tubing should be pre-assembled and kept ready at the site so that it can be used in case of activity in the well is noticed after perforation. While perforation through tubing - a wire line blowout preventer should also be installed so that the well can be closed with the perforation wire line tool in the hole, Before commencement of perforation operations, it should be ensured that :
The well is filled with mud or other suitable fluid to an over balance of the expected bottom hole pressure. In case of through - tubing perforation, a lubricator, duly pressure tested, is installed, with a valve to release pressure before disconnection. The Insulation resistance of the electro-logging cable is not less than one mega ohm. After every check, the cable should be shorted to release residual electric charges. EMERGENCY RESPONSE PROCEDURE is clearly understood by all concerned for
Perforation contd
General Dos & Donts:
Perforation should not be carried out during night hours or under conditions of thunder, lightning, high rains. At the well site, all operations not directly connected with perforation, should be kept suspended till the perforation job is satisfactorily completed. All equipment incl. rig used for perforation should be efficiently earthed and electric bonding should be established between the equipment and well head before connecting explosive charges. Persons not directly connected with perforation job should remain at a safe distance not less than 30mts from the well. An area within 30 mts of the well should be demarcated as danger zone in which no smoking or open fire should be permitted and all electric installations should be de-energised. Effective means of communications between the derrick floor and perforation unit should be provided. Adequate fittings of flow lines and tanks should be provided, to safely collect the well produce, before the production casing is perforated. Adequate number of self contained portable hand lamps of approved type should be kept available for use in emergency.
Well Activation
Operation: After a well is perforated it is to be activated to induce flow of formation fluids into the well by
Displacement with lighter fluid Compressor / Nitrogen application Swabbing Aerisation Acidization
Hazard :
An area within 30 meters of the well should be treated danger zone in which no smoking or open flame should be permitted and all electrical equipments should be de-energised. Diesel engines if in use, should be located outside the danger zone on the upwind side. Adequate fire fighting system shall be made available
Safety Measures:
swabbing should not be attempted in gas wells When swabbing is done through the Christmas tree assembly wire line blow out prevent or and an oil saver should be used at the top to control the flow of fluids. The control wheel should be provided with protective screen for safe operation and clear instructions should be pasted for its correct operation. The valve assembly and flow lines should be checked carefully for any leakage. The swab rod should be run in or pulled out at a steady rate so as to avoid pressure surges. When the swab is being run in or pulled out, all persons should remain at a safe distance from the well head because any interruption may throw slack on the line and cause serious injury to persons. Suitable roller guides should be provided to ensure that the wire rope, coils or uncoils on the winch drum uniformly without any overlap.
Consequence: Blow out Safety Measures: Specific gravity of displacing fluid is to be gradually reduced
Hazard : 1. Swabbing the hole on the way out with the test tool could cause a kick
2. 3.
to occur, which could result in a blowout leading to injuries and deaths. Being exposed to unexpected release of H2S or other gases or liquids. A packer seat failure or fluid loss to an upper formation could cause a kick that might result in a blowout causing injuries and deaths.
Consequence: Blow out / Fire Safety Measures: 1. Keep a method for filling the hole in place at all times. Before any test starts, the rig
management must ensure that the blow-out prevention system includes a kill system that is capable of pumping fluid into the well below the annular preventer and at least on-set of pipe rams. Run a pump-out-sub or down hole circulating device in the test string to enable the system to be reversed.
2.
Well Testing
High pressure/temperature well testing presents an additional failure/safety risk if critical factors are not investigated
Fluids used during testing: Down hole fluid has to be of higher specific gravity with minimum solid settlement in static conditions. Sealing Material: Metal to metal seals are highly desirable in high pressure situations or organic polymer material seals. Mechanical stresses on tubular and packer: Tubings with premium connections and high differential pressure packers have to be considered Perforation: Special high temperature charges are to be used and cement bond quality behind the casing must be ascertained before perforation Surface Testing Equipment: All flow lines, choke manifold and line valves should be rated and tested to the same working pressure as the well head equipment Redundancy in safety system must be ensured Killing Operation: Depending upon the severity of operating conditions, dual production/kill string completion hook up may be required to kill the well safely at the conclusion of testing operations.
Well Abandonment
Open hole abandonment: 1st Isolation plug-50mt open hole 50mt csg. Tag & test plug-pipe wt15000ibs/1000psi 2nd Surface plug-100mt inside csg. 200-300 mts Never place two plug simultaneously-in one go.
Well Abandonment-II
Cased hole abandonment: 1st Isolate producing zone- By cement squeeze./plug Cement plug -150mt Tag & test 2nd Surface plug:100mt-plug top-100-200mt below surface. Never place two plug simultaneously-in one go
and.almost there!
Concern for man and his fate must always form the Chief Interest of all technical endeavours Never forget this in the midst of your diagram, equations and formulas -- Albert Einstein
THANKS