PROJECT OVERVIEW
Our team is developing the De Anza Technical Writing course on Adobe tools. The
course is divided into four sections, one software program per section. Each team
member is responsible for creating the instructor and student materials for one of the
sections:
Team members will jointly create the introductory and appended materials that are not
part of their particular software section.
The final product of our project will be a binder to be used by the course instructor. The
binder will be broken down by software program and still further by lecture modules
within each program. The modules will include instructor lecture notes, student lecture
worksheets, student exercises and solutions.
Each software program will have a portfolio assignment that requires students utilize
their new skills. For each portfolio assignment, the students will be provided with an
project prompt with several requirements for the assignment.
WORK COMPLETED
The following tasks have been completed by our team.
• Our team met with one of the project owners, Teague S., to review and gain approval
for the materials created so far. He gave the team guidance on course scope, depth of
materials, exercises and portfolio projects.
• We have created the content for all portfolio assignments including requirements for
each assignment.
• Significant portions of lecture notes and exercises have been created, with InDesign
approaching completion, and Photoshop and Illustrator sections well underway.
• Tentative FrameMaker section modules have been outlined and research and writing
are underway.
WORK TO BE COMPLETED
The major tasks our team still needs to complete are listed below.
• Write introductory section, table of contents, syllabus, class schedule, and course
submission document.
• We are having some difficulty sticking to a limited scope for each software section.
• We have abandoned the expectation that the FrameMaker section will be based on
the content in the other FrameMaker class.
• We are feeling the pressure of our looming team deadline of February 25 for all
software section content to be completed.
Our deliverables and milestone dates continue to be the same as we reported in our prior
status report.