Beruflich Dokumente
Kultur Dokumente
Contents
Executive summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4 Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
The case for asset management. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.2.1 Primary decisions and activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .14 4.2.2 Enabling mechanisms. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .15 4.2.3 Monitoring and review . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .16
7 Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Executive summary
Network Rails commitment to its customers is enshrined in a Promise to deliver the Timetable, so that trains run safely, punctually and reliably now and in increasing numbers in the future. Asset Management supports the delivery of the Promise by planning, delivering and making available an infrastructure that supports the current and future timetable safely, efficiently and sustainably.
We recognise that a significant improvement in our asset management capability is required to live up to this commitment. The purpose of this strategy document is to define the trajectory that will lead us to being demonstrably comparable with best practice in Great Britain by the end of this control period (2014). Over .the .following .five .years .we .are .committed . to .improving .our .asset .management .capabilities . further .so .that .we .provide .the .benchmark .against . which .organisations .worldwide .assess .their .own . asset .management .capabilities . Over .the .past .year .we .have .been .working .with .ORR . and .the .Regulatory .Reporter .for .Asset .Management . (AMCL) .to .develop .an .asset .management . improvement .roadmap . .As .a .result .of .this .work, . we .have .developed .a .good .understanding .of .what . needs .to .be .done .to .achieve .our .objectives .and .have . defined .numerical .maturity .targets .against .which . our .progress .will .be .monitored .
l
Route .based .asset .plans: .Bringing .together . . all .maintenance, .renewal .and .enhancement . activities .at .route .and .sub-route .level, .and . linking .that .work .to .the .route .outputs .that .the . infrastructure .is .required .to .deliver . Asset .information: .Improving .the .quality, . . integration, .accessibility, .and .where .appropriate, . extending .the .scope .of .the .asset .information . needed .to .support .strategic, .planning .and . delivery .processes . . Asset .management .competencies: .Extending .our . . well .established .engineering .competencies .to . provide .individuals .and .teams .with .the .skills .and . aptitudes .necessary .to .meet .the .wider .ranging . demands .of .asset .management .
Were committed to setting the worldwide benchmark for excellence in Asset Management.
The .improvement .roadmap .is .comprehensive, . covering .all .aspects .of .asset .management . . . However, .there .are .a .number .of .areas .which .have . been .prioritised .because .they .are .the .fundamental . building .blocks .of .an .effective .asset .management . regime . .These .include:
l
In .the .first .phase .of .our .Asset .Management . Improvement .Programme .(AMIP), .which .will .focus . on .delivering .the .target .improvements .during .the . current .control .period, .seven .major .workstreams . have .been .launched . .A .strong .governance . framework .has .been .implemented .with .a .board .level . sponsor .and .senior .management .leadership .of .the . individual .workstreams . . Criteria .have .been .developed .that .will .assess .the . outputs .from .the .AMIP . .Completion .of .workstreams . to .the .target .levels .will .demonstrate .an .asset . management .capability .that .is .at .least .on .a .par . with .the .best .asset .intensive .companies .in .the . Great .Britain .and .the .best .railway .infrastructure . companies .in .Europe .
Optimisation .of .asset .interventions: .Improving . . our .analytical .and .decision .making .capabilities .so . that .we .can .demonstrate .that .our .maintenance, . renewals .and .enhancement .activities .will .deliver . the .required .infrastructure .outputs .at .the .lowest . whole-life, .whole-system .cost .
Background
An .efficient .and .sustainable .asset .management . regime .requires .a .well .developed .capability .in .asset . management .(people, .processes, .technology) .which .is . reflected .in .assets .that .are .performing .optimally .for .the . level .of .funding .available . .This .is .illustrated .in .Figure .1 . . An .asset .management .strategy .needs .therefore .to .set . the .direction .in .two .main .areas, .as .follows:
l
particularly .strong .owing .to .the .scale .of .its .investment, . and .the .importance .of .the .railway .infrastructure .to . Great .Britains .transport .system .and .economy .
Firstly, .it .summarises .the .high .level .objectives . and .targets .for .the .infrastructure .for .the . remainder .of .CP4 .(2011 .to .2014) .and .the . baseline .assumpions .for .CP5 .(2014 .to .2019) . Secondly, .it .defines .what .needs .to .be .done .to . improve .Network .Rails .asset .management . capability .in .order .to .deliver .these .requirements . and .to .achieve .a .level .of .asset .management . maturity .that .is .at .least .as .good .as .the .best . comparable .organisations .in .the .UK .
Network .Rail .has .been .active .in .asset .management . for .a .number .of .years . .However, .this .is .the .first .time . that .we .have .formally .defined .our .strategy .for .asset . management .and .put .a .systematic .programme .of . work .in .place .to .support .its .implementation . Developing .a .sustainable .approach .to .asset . management .is .central .to .our .strategy . The .case .for .adopting .a .systematic .approach .to .asset . management .by .asset .intensive .companies .is .strong . . The .case .for .asset .management .in .Network .Rail .is .
Under performing
Promising
1. Background
While .there .is .little .radical .in .this .definition, .it . does .promote .new .ways .of .thinking, .building .on . traditional .good .engineering .practice .but .with .an . additional .emphasis .in .three .main .areas: . 1 . . . It .explicitly .focuses .maintenance, .renewal .and . enhancement .activities .on .delivering .sustainable . outputs .valued .by .customers .and .funders .at .the . lowest .whole-life .cost, .as .opposed .to .prioritising . work .predominantly .according .to .condition; 2 . . . It .provides .an .integrating .mechanism .that . crosses .boundaries . .between .organisational . functions .and .asset .disciplines, .and .between . the .infrastructure .manager .and .contracting . organisations; . 3 . . . It .places .a .greater .weight .on .evidence-based . decision .making, .using .knowledge .of .how .assets . degrade .and .fail .to .optimise .maintenance .and . renewal .interventions . .
The .potential .benefits .from .applying .an .asset . management .approach .are .recognised .by .many . asset .intensive .companies .as .being .numerous .and . significant . .They .include .the .creation .of .a .line .of . sight .between .strategy .and .implementation, .the . capability .to .deliver .the .same .level .of .sustainable . performance .with .reduced .volumes .of .work, .and .the . ability .to .demonstrate .to .external .stakeholders .that . activities .are .being .undertaken .at .the .lowest .whole . life .cost . The .commitment .required .to .achieve .these .benefits . is .also .significant . .The .programme .of .work .to . implement .the .asset .management .improvement . programme .represents .one .of .the .biggest . challenges .that .Network .Rail .has .faced .since .it .took . responsibility .for .the .infrastructure .in .2002 .
Maintaining .safety .at .least .to .current .levels . Delivering .outputs .valued .by .our .customers, .in . a .sustainable .way, .for .the .minimum .whole-life, . whole-system .cost . Optimising .decisions .and .plans .based .on .risk . principles, .robust .information .and .innovative . methodologies . Developing .the .competencies .of .our .asset . management .teams .and .individuals .
The .remainder .of .this .strategy .document .is . structured .as .follows:
l
Section 2 .summarises .how .the .infrastructure . is .currently .performing .against .a .range .of . measures . .It .also .outlines .the .committed .targets . for .the .remainder .of .CP4 .and .the .emerging . assumptions .for .CP5 .and .beyond . Section 3 .provides .an .assessment .of .our .current . asset .management .capability, .based .on .an . external .independent .review, .and .identifies . target .levels .of .capability .to .be .achieved .within . the .next .three .years . .It .also .provides .a .roadmap . which .outlines .the .activities .required .to .achieve . the .target .capability . . Section 4 .introduces .our .Asset .Management . Framework, .which .summarises .the .building . blocks .of .asset .management .in .Network .Rail .and . illustrates .how .they .fit .together . Section 5 .summarises .the .workstreams .that . have .been .designed .to .implement .the .roadmap, . linked .to .the .Asset .Management .Framework . Section 6 .provides .an .outline .programme .for .the . delivery .of .the .workstreams .and .the .governance . process .for .leading .and .monitoring .their . implementation .
1. Background
Inverness
Aberdeen
l l l
30,000km .of .track 40,000 .bridges .and .tunnels 2,500 .stations 8,200 .commercial .properties Largest .private .landowner .in .UK Third .largest .telecoms .network .in .UK Largest .purchaser .of .electricity .in .UK, . lowest .transport .carbon .emissions
SCOTLAND
Fort William
Dundee
l
Stirling
l
Edinburgh Waverley
l l
Ayr
Newcastle Carlisle
Whitby
Scarborough
Barrow-in-Furness
Leeds
LNE
Southport
Wigan North Western Liverpool Lime Street Holyhead Chester Wrexham General
Bolton Manchester Piccadilly Stockport Warrington Bank Quay Buxton She eld
LNW
Crewe
Derby
Grantham
Norwich
Cambridge
ANGLIA
Ipswich Harwich International
Fishguard Harbour
WESTERN
Swansea Swindon Cardi Central Bristol Temple Meads London Paddington London Victoria Ascot Feltham London Euston London Kings Cross Southend Victoria London Bridge Lewisham London Waterloo Rochester Herne Hill Clapham Junction
Ramsgate
Redhill
KENT
Ashford International
Salisbury
WESSEX
Exeter St Davids Bournemouth
Eastleigh
SUSSEX
Ford Brighton Hastings
Plymouth
Penzance
. ASI
100
80
2004/05
2005/06
2006/07
2007/08
2008/09
2. Current performance and future requirements of the infrastructure 2.4 Optimisation criteria
Asset .management .contributes .to .Network .Rails . Timetable .Promise1 .by .planning .and .delivering .a . railway .infrastructure .that .supports .the .current .and . future .timetable . .safely, .efficiently .and .sustainably . As .stated .previously, .the .objective .of .asset . management .is .to .deliver .the .required .route .outputs . at .the .lowest .whole-life .cost . .The .factors .that .are . used .in .determining .the .balance .between .outputs, . costs, .and .risk .include .the .following:
l
The .specification .of .these .requirements .is . complicated .by .uncertainty .around .the .impact .of . constraints .in .the .level .of .available .funding .and, . to .a .lesser .extent .on .the .short .term .forecasts .of . passenger .and .freight .traffic .levels . . . . In .September .2011, .we .will .publish .our .Initial . Industry .Plan .(IIP) .which .will .inform .funders .of .the . range .of .possible .outputs .that .could .be .delivered .in . CP5 .and .the .scale .of .expenditure .required .to .achieve . these .outputs . A .set .of .baseline .assumptions .has .been .compiled .to . inform .how .the .infrastructure .is .required .to .perform . during .CP5 .and .beyond . . 1 . . . The .rail .sector .will .continue .to .grow .in .the .long . term, .to .drive .economic .growth .in .the .face .of . further .population .growth, .increasing .road . congestion .and .carbon .reduction .targets . . 2 . . . The .infrastructure .outputs .at .the .end .of .CP4 . will .be .broadly .maintained .during .CP5, .in .a .way . that .is .sustainable .in .the .long .term . 3 . . . Targeted .improvements .will .be .sought, .for . example .to .close .the .gap .in .variability .between . individual .operators .by .raising .performance . of .worst .performing .services, .and .to .maintain . relative .safety .performance .when .benchmarked . against .European .peers . 4 . . . All .of .this .will .need .to .be .delivered .at .the .same . time .as .further .reducing .the .cost .base .to .the . lowest .level .commensurate .with .sustained .long . term .performance . While .further .clarity .will .be .added .to .the .infrastructure . requirements .for .CP5, .the .asset .management .strategy . is .concerned .with .the .development .of .a .capability .that . provides .flexibility .to .deal .with .a .variety .of .scenarios . and .potential .constraints . .This .is .considered .further .in . the .next .section .
Whole-life .cost .of .maintenance, .renewal .and . enhancement .interventions Safety .risk .to .passengers, .workforce .and .members . of .the .public .caused .by .infrastructure .faults Impact .of .infrastructure .faults .on .train .performance, . measured .principally .by .train .delay .minutes Impact .of .the .infrastructure .on .the .environment . Sustainability .of .the .infrastructure, .measured .by . long .term .condition .trends .and .assessments .of . asset .residual .life Resilience .of .the .infrastructure .to .weather .and . climate .change
l l
As .stated .above, .the .baseline .assumption .is .that . we .will .seek .to .maintain .the .infrastructure .outputs . achieved .at .the .end .of .CP4 .during .CP5 .and .beyond . . Other .scenarios .will .also .be .considered .that .will . change .the .balance .of .outputs .and .costs . .The . optimisation .criteria .will .change .to .reflect .these . scenarios, .although .the .factors .considered .will . remain .the .same . To .ensure .consistency .in .the .application .of .these . criteria .in .asset .policy .development, .for .example . across .asset .disciplines, .we .will .use .Network . Rails .Corporate .Risk .Matrix .as .a .key .reference . for .categorising .safety, .train .performance, . environmental .impact, .etc .
1 . The .Timetable .is .our .PROMISEWhen .we .PROMISE .a .train .can .run, .it .will .runsafely, .punctually .and .reliably . .And .we .PROMISE .that .more .trains .are .able .to .run, .next .year . . 10
11
Figure 4 Results from AMEM assessment for 2009 and target capabilities for 2011-2014
Review & Audit Weather & Climate Change Sustainable Development Risk Assessment & Management Individual Competence & Behaviour Organisational Structure & Culture Contract & Supplier Management Asset Data & Knowledge Asset Information Systems Asset Knowledge Standards
Capex Evaluation
Incident Management
Innocent
Aware
Developing
Competent
Effective
Excellent
12
Enablers:
Asset information Analysis tools Competencies Processes
Ro u t e delivery plans
R a n ou ag te a em sset e nt pla n s
m
k Wor
ex
ec
ut
io
13
Primary .decisions .and .activities: .These .are . the .decisions .and .activities .that .start .with .the . high .level .objectives .for .the .infrastructure .and . end .in .the .delivery .of .work .on .the .ground . .The . framework .facilitates .the .establishment .of .a .line . of .sight .between .them . . . . Enabling .mechanisms: .The .effectiveness .of .the . primary .decisions .and .activities .is .dependent . on .many .support .mechanisms .such .as .asset . information, .analysis .tools, .competencies .and . business .processes . .The .importance .of .these . mechanisms .is .emphasised .by .their .position .at . the .core .of .the .framework . . Reviewing .mechanisms: .Reviewing .mechanisms . provide .the .feedback .loop .between .the . interventions .undertaken .on .the .infrastructure . and .the .asset .condition .and .performance . that .they .give .rise .to . .They .provide .inputs .to . tactical .and .strategic .responses .to .measured . performance .against .targets .and .also .to . the .continuous .improvement .of .the .asset . management .system . . .
Outline .descriptions .are .provided .below .for .each . component .of .the .framework . .In .addition, .a . brief .summary .of .our .current .approach .to .asset . management, .prior .to .the .implementation .of .this . strategy, .is .provided .for .each .component .and .is . linked .to .the .spider .chart .in .Figure 4 .
14
Route asset management plans. The .Route .AMPs . result .from .the .application .of .the .appropriate . asset .policies .to .generate .volumes .of .work .to .be . undertaken .on .a .given .route, .and .they .show .the . cost .of .delivering .these .volumes .and .a .forecast . of .the .outputs .that .the .work .volumes .give .rise . to . .The .plans .provide .a .specification .for .the . delivery .functions . .They .also .provide .assurance . to .external .stakeholders, .such .as .regulators .and . governments, .that .the .costs .are .justified .and .that . the .infrastructure .outputs .will .be .delivered .in .a . sustainable .way . . Route .AMPs .have .recently .been .introduced .in . Network .Rail .and .are .now .firmly .embedded .in .our . business .processes . .However, .the .benefits .have .only . just .started .to .be .realised .and .will .become .much . more .evident .as .the .asset .policies .mature .and .the . decisions .change .the .balance .of .the .work .reflected . in .the .Route .AMPs . Route delivery plans. Translate .the .work .specified .in . the .Route .AMPs .into .a .detailed .plan .for .execution . . The .objectives .of .the .Route .Delivery .Plans .are .to . optimise .the .delivery .of .maintenance, .renewal . and .enhancements, .grouping .work .spatially .and . combining .work .to .be .delivered .at .the .same .time . . They .also .provide .a .detailed .design .for .construction . projects, .confirm .the .availability .and .source .of . funding, .agree .the .delivery .programme .with . customers .and .stakeholders .and .align .the .delivery . programme .with .the .local .track .access .regime .and . the .delivery .capability .of .suppliers . Our .approach .to .the .delivery .planning .work . on .the .infrastructure, .including .contract .and . supply .management, .was .assessed .in .the .AMEM . review .as .being .close .to .best .in .class .and .not .an . immediate .priority .in .this .phase .of .the .improvement . programme . Work execution. The .delivery .of .work .includes . mobilisation .of .the .project .or .maintenance .team, . the .scheduling .of .resources .and .booking .of . possessions . .It .also .includes .the .provision .of .tools, . facilities .and .equipment . .The .hand .back .of .work . following .construction, .testing .and .commissioning . includes .updates .to .asset .registers .and .cost . management .systems .resulting .from .interventions . on .the .infrastructure . . As .with .our .delivery .planning .activities, .we .have . made .good .progress .in .recent .years .in .the .execution . of .work .resulting, .for .example, .from .the .insourcing .of . maintenance .and .the .more .recent .standardisation . of .maintenance .under .the .Phase .2b/c .organisation . . For .this .reason, .further .improvements .were .not . ranked .as .a .priority .in .the .AMCL .roadmap . . .
15
Management Reviews. The .outputs .from .the . audit .regime, .measurements .of .key .performance . indicators .and .other .sources .of .feedback .are . reviewed .regularly .by .management .in .order .to . identify .gaps .in .the .implementation .of .the .asset . management .system, .to .identify .the .root .causes .of . deviations .in .key .performance .indicators .from .target . values, .and .to .confirm .that .the .implementation . of .asset .management .is .driving .sustainable . performance .and .costs . . Corrective actions. A .process .for .managing . corrective .actions .arising .from .management .reviews . and .other .sources .is .required .to .remove .noncompliances, .address .short .term .improvements .in . the .performance .of .the .infrastructure, .and .deliver . longer .term .continuous .improvement .in .the .asset . management .system . Our .overall .approach .to .audit, .KPIs, .management . reviews .and .corrective .actions .has .undergone . significant .improvements .over .the .past .five . years . .Improvements .are .still .being .progressed, . for .example .in .the .refinement .of .the .Asset . Stewardship .Indicator .(ASI) .and .the .introduction . of .the .engineering .verification .programme . .Our . relative .strength .in .this .area, .as .evidenced .by .the . AMEM .review, .means .that .it .is .a .lower .priority .for . further .improvement .than .for .some .of .the .other . components .of .the .asset .management .framework . discussed .above .
16
The .Asset .Management .Strategy .is .as .set .out .in . this .document . .It .adds .detail .to .the .Policy, .focussing . on .how .the .infrastructure .needs .to .perform .to . meet .customer .and .stakeholder .requirements . and .on .what .Network .Rail .needs .to .do .to .build .its . asset .management .capability .in .response .to .these . requirements . . The .first .phase .of .this .workstream .will .be .completed . by .the .issue .of .the .Asset .Management .Policy .and . Strategy . .It .is .intended .that .the .documents .will .be . reviewed .on .a .two .yearly .cycle, .with .the .next .formal . issue .coinciding .with .the .SBP .submission .
Asset .management .policy .and .strategy Asset .policies Route .asset .management .plans Asset .information Asset .management .competencies Asset .management .benchmarking Asset .management .research .and .development
17
Completion .of .the .ten .stage .process .will .result .in . policies .that .are .evidenced .based, .have .optimised . maintenance .renewal .trade-offs, .and .enable . short .and .long .term .forecasts .of .work .volumes, . expenditures .and .outputs .
Our .strategy .for .asset .information .has .both .short . term .and .long .term .components . .The .short .term . component .(Phase .1) .is .focussed .on .ensuring .that . the .asset .information .necessary .to .support .the .IIP . and .SBP .is .fit .for .purpose . .it .does .not .involve .any . significant .system .development . .The .longer .term . component .(Phase .2) .will .build .on .Phase .1, .but .will . also .set .the .strategy .for .the .future .systems .solution . Phase .1 .is .primarily .concerned .with .improving . the .quality .of .information .we .already .hold, .while . ensuring .that .the .appropriate .processes .and . procedures .are .in .place .to .maintain .the .quality . once .it .has .been .improved . .The .requirements .will .be . prioritised, .firstly .on .the .basis .that .it .is .required .to . support .the .modelling .of .policy .options .for .the .IIP . and .secondly .that .it .is .required .to .support .the .more . detailed .planning .for .the .SBP . .The .scope .of .Phase .1 . also .includes .the .requirement .to .have .fit .for .purpose . asset .information .available .at .the .beginning .of .CP5 . Phase .2 .will .be .run .in .parallel .with, .and .will . learn .from, .the .implementation .of .Phase .1 . .A . fundamental .and .comprehensive .review .of .business . processes .and .the .information .required .to .support . these .will .be .undertaken .prior .to .the .consideration . of .the .optimum .system .solution . .Phase .2 .will .also . assess .the .experience .of .other .companies .who . have .successfully .implemented .asset .information . strategies .on .a .similar .scale . .
18
We .will .integrate .the .IAM .competency .approach .with . our .own .well .developed .competency .framework .in . order .to .identify .competence .requirements, .assess . gaps .and .implement .training .and .development . programmes . .We .will .start .with .the .people .and .teams . involved .in .the .preparation .of .the .IIP .and .SBP . .We . will .then .extend .the .framework .to .include .all .of .our . people .involved .in .core .asset .management .activities .
Progress .has .been .less .evident .in .the .ability .of . organisations .gain .a .better .understanding .of .how: . assets .degrade .and .fail .with .age .and .usage; .how .this . degradation .and .failure .impacts .on .service .outputs; . the .optimum .interventions .to .mitigate .or .prevent . failures . .In .short, .Life .Cycle .Costing .(LCC) .models . have .not .kept .pace .with .the .development .of .the . management .systems . The .development .of .our .asset .policies .and .route . asset .management .plans .is .critically .dependent .on . robust .LCC .methods .and .tools . .In .parallel .with .the . commitment .we .have .made .to .improvements .in . support .of .the .IIP .and .SBP, .we .are .also .supporting . more .fundamental .university .based .asset . management .R&D . The .main .vehicle .of .our .AM .R&D .programme .is . the .Chair .in .Asset .Management .at .Nottingham . University .which .we .are .co-sponsoring .with .the .Royal . Academy .of .Engineering . .The .research .programme . is .built .around .getting .a .better .understanding .of . asset .degradation .and .failure .mechanisms .and .the . optimisation .of .interventions . .The .results .from .the . research .will .provide .the .basis .for .the .next .generation . of .our .Life .Cycle .Costing .tools . A .small .team .of .asset .management .researchers . is .currently .being .assembled .at .Nottingham, . which .will .grow .as .the .research .starts .to .deliver . results .and .attracts .funding .from .other .sources . . The .key .output .from .the .Nottingham .research . will .be .a .compendium .of .asset .degradation .and . failure .relationships .and .the .optimum .mitigating . interventions . . We .also .have .strategic .relationships .with .two . other .universities, .Imperial .College .and .Sheffield . University, .who .are .also .undertaking .technically . based .research .that .is .relevant .to .our .asset . management .objectives . . .
Asset .Management .Strategy Optimised .lifecycle .decision .making .(including . analysis .tools) Asset .management .planning Asset .information Asset .management .competencies Key .performance .indicators
l l l l
Comparator .organisations, .who .we .believe .to .be . leaders .in .each .area .have .been .identified .and . contacts .established . .Structured .questionnaires . will .be .developed .to .support .discussions .with .each . organisation . .The .results .from .each .exchange . will .be .documented .and .recommendations .for . improvement .will .be .added .to .the .AMIP .
19
Table 1
Workstream Asset Management Policy and Strategy Asset Policies IIP September 2011 First .issue .of .policy .and . strategy .by .September .2010 . SBP January 2013 CP5 Delivery Plan April 2014
Updates .following .first . Periodic .updates .following . biennial .review .in .September . biennial .reviews . 2012 . Third .issue .of .Asset . Strategies .to .reflect .CP5 . Determination . Route .AMPs .aligned .with . CP5 .Determination . Data .maintenance .and . assurance .processes .fully . implemented .and .working . Asset .Management . competencies .fully . integrated .with .NR . Competency .Framework . Recommendations .from . benchmarking .studies .fully . implemented . NR .has .the .most . comprehensive .repository .of . asset .degradation .
First .issue .of .asset .strategies, . Second .issue .of .asset . volumes, .costs .and .outputs . strategies .to .reflect .HLSO . for .CP5 .in .March .2012 . and .SOFA . Route .AMP .structure . Bottom .up .Route .AMPS . adapted .to .CP5 .asset .policies . form .integral .part .of .SBP . by .March .2011 . submission . Fit .for .purpose .asset . information .by .December . 2010 .to .support .CP5 .Asset . Policies . Competency .requirements . established .and .training . provided .to .key .staff .involved . in .PR13 . First .phase .of .benchmarking . complete .and .documented . by .December .2010 . Programme .of .work . underway .compiling . degradation .mechanisms .for . key .asset .groups . Fit .for .purpose .information . available .to .support .bottom . up .SBP .plans . Competency .profiles . produced .for .all .AM . roles . .Training .courses . implemented . .Competence . records .maintained . Key .lessons .learned .from . benchmarking .implemented . to .support .SBP . First .release .of .compendium . of .degradation .mechanisms .
Route AMPs
Asset Information
managers .from .across .the .business . .An .AMSG . member .is .assigned .to .each .workstream .and .is . accountable .for .its .success . AMSG .meetings .are .held .every .four .weeks . . Additional .progress .meetings .involving .the .client, . sponsor .and .the .programme .director .for .delivery .are . held .frequently .to .provide .more .detailed .guidance . and .review . . The .majority .of .the .workstreams .form .part .of .a . wider .programme .of .work .for .PR13 . .The .governance . arrangements .for .AMIP .are .consistent .with .and . support .the .governance .for .PR13 .
20
Client
Head of Technical Planning
Sponsor
Director SP&C Asset Management
Sponsor Representative
AMSG Leads
Head of Technical Planning Asset Management Policy and Strategy Director SP&C Asset Management Asset Strategies and Volume Forecasts Director SP&C Asset Management Route AMPs Director Asset Information Asset Information Director Infrastructure Maintenance AM Competency Director SP&C Asset Management AM Benchmarking Director SP&C Asset Management AM Research & Developement
achieved . .The .mapping .of .activities .to .measures .is . documented .separately .(Summary .of .milestones . and .outputs .from .Network .Rails .Asset .Management . Improvement .Programme, .Version .1 .0, .January . 2011) . .The .document .identifies .the .key .output .from . each .activity .and .the .timescale .for .its .completion, . aligned .to .the .main .PR13 .milestones . The .AMCL .Roadmap .has .been .constructed .in .such . a .way .that .achievement .of .the .measures .would . result .in .Network .Rail .being .classed .as .excellent . in .Asset .Management . .The .trajectories .towards . excellence .for .each .of .the .priority .components .of . the .AMEM .model .are .shown .in .Table .2 .below, .which . . reproduces, .in .tabular .form, .the .Spider .Chart .shown . in .Figure 4 . .
21
22
7. Conclusions
The .purpose .of .this .asset .management .strategy .has . been .to .specify .the .activities .that, .if .implemented . successfully, .will .provide .Network .Rail .with .a . significantly .improved .asset .management .capability . . Such .an .improvement .will .enable .Network .Rail . to .deliver .the .future .requirements .for .the .railway . infrastructure .at .the .lowest .whole .life .cost . . The .programme .of .work .has .been .phased .to . deliver .key .improvements .that .are .aligned .with .the . periodic .review .process .for .CP5, .most .notably .the . IIP .submission .in .September .2011, .the .SBP .in .the . January .2013 .and .the .start .of .CP5 .in .April .2014 . The .programme .is .aligned .with .the .activities .and . measures .specified .in .the .AMCL .Asset .Management . Improvement .Roadmap . .Completion .of .the . programme .will .deliver .these .activities .to .the . required .standard .and, .in .doing .so, .will .establish .an . asset .management .capability .that .would .be .classed . as .excellent .compared .with .peer .organisations .in .the . utility .and .transport .sectors .
23
101/February 2011