Project: Lake Towers Cluster S Consultant: ARCHGROUP MEP Contractor: Middle East LLC
for
Flushing
and
Chemical
1
Water will be filled in riser and the pumps will be started for flushing. First the dynamic flushing will be done only for the riser and water will be
drained at the lowest point particals etc. till the water gets free from major debris,
Water will be drained totally from riser and fresh water will be filled in the
system for 2nd stage of the flushing. All strainers will be cleaned again and Isolation valves at each floors will be opened except FCUs , FAHUs Isolation valve. Again pump will be started and flushing will be done through riser & floor main header and water will be drained at lowest point till water gets free from small debris & particals. Same procedure will be repeated with all FCUs and AHUs valve opened and water will be continuously drained and water sample will be taken and will be tested at laboratory for the water quality analysis.
Bilt.AC
Partly
fill the system with water then add the chemical B-16 in ratio
sujjested by the chemical suppliers and then fill the system completely with plain water.
3. Post Chemical Flushing Stage Dynamic flushing of the system with plain water for at least 8-10 hrs
through drain points will done until all the chemical residuals are removed from the system and water is cleared.
Chemical Supplier will take two samples at 3 hrs Interval will submit their
report. Water will be drained out from the system.
4. Final Treatment
All strainers will be cleaned , all drain valves will be closed and all system valves will be Installed i.e DPCV valves, Flow meters .
After getting chemical suppliers report the system will be filled again with
fresh water for final treatment.
Initial dosage of the corrosion inhibitor CLT 407 will be added to the fresh
water at the range of minimum 700 ppm nitrite.
Microbioside ML 13G will be added at the range of 100 ppm approximately. Automatic conductivity based dosing system and manual dosing pot will be
connected to the system.