Sie sind auf Seite 1von 12

0.

High
SMALL HEADLINE

Performance
Hospitals
USING CONCRETE FRAMES AND CLADDING
0.2

Good hospital design can provide more efficient facilities and a


better environment for both staff and patients.

Concrete construction presents great opportunities for the project


team to meet the needs of the client by helping to improve the
function, value and whole life performance of the facility.

By checking that the design and construction process gives


timely consideration of the benefits discussed in this publication,
decision makers in the procurement process can ensure that extra
value is added to the building, often at no or little additional cost.

Front cover (left to right)


• The Great Western Hospital, Swindon: in-situ flat slab concrete frame with precast cladding. Photography: Gillian Bond.
• Central Middlesex Hospital ACAD Centre: a concrete framed structure which is exposed in public areas. Photography: Nicholas Kane.
This page
Photo captions to West
• The go here
Middlesex University Hospital: concrete walls clad in timber, render and brick. Design: Nightingale Associates; Photography: Charlotte Wood.
1

BUILDING BETTER HEALTHCARE


Hospitals are facilities that help medical staff in the efficient delivery of
quality healthcare and provide a positive environment for speedy patient
recovery. Good building design can provide more efficient facilities and a
better environment for both staff and patients.
This publication examines the role of concrete construction in the current hospital development programme
to provide additional effective, high quality healthcare to meet the nation’s growing and changing needs. It
aims to inform decision makers in the procurement process about areas where concrete construction can help
improve the function, value and whole life cost of the facility.

A major government initiative is underway to provide 100 new hospital buildings by 2010. To meet this
ambitious target and also ensure best value, the plan is being funded by a mixture of public, private and local
NHS trust capital, with procurement under the Private Public Partnership, often involving ProCure21, PFI
and DBFO. These aim to promote better capital procurement and improve the service to patients through a
partnering programme between the NHS and the private sector. Construction partnerships will often design
the facilities and be financially involved with their operation and maintenance. This will help secure high-
quality designs and earlier access to new facilities, and ensure best value, both from initial and whole life cost
perspectives.

Recent research has confirmed that good design creates the best environment for patients, staff and visitors,
which promotes effective services and speedier recovery, resulting in more efficient use of resources. The design,
construction and operation of new facilities is now formally assessed using a variety of measures – not just
financial – encouraging more considered and holistic design and construction processes and better value solutions.

The new buildings will have to satisfy a range of complex and often conflicting needs, including the flexibility
to accommodate not only changes in demand, healthcare procedures, IT and working methods but also newly
emerging issues such as cross-infection and MRSA, daylighting, natural ventilation and sustainability.

Romford New Hospital: floor plan (level 3) showing the central core servicing the ward towers. Concrete framed ward tower under construction.
2

The benefits of CONCRETE FOR


using concrete: HOSPITAL CONSTRUCTION
Well-designed and effectively managed hospital buildings help support the work of
frontline staff, provide an appropriate environment for patient recovery, and so improve
• Reduces initial and running costs efficiency. The choice and design of a building’s frame and cladding can have a surprisingly
large influence on the performance of the final building. An important example of this is

• Speeds construction the effect on the provision of M&E services, which are generally the most critical item in
cost and construction time, and are a major factor in the costs of running, maintaining and
refurbishing a building over its life.
• Minimises vibration
Although every new facility has specific requirements, a typical list of needs to be
• Accommodates future changes considered might be:
• Value/cost – how well it performs its function in terms of helping staff and patients in
• Facilitates partition wall sealing relation to initial and running costs and residual value
• Speed – how quickly it can be brought into use
• Caters for easy services • Flexibility – how easily it can accommodate or be adapted for changing needs
installation • Sustainability issues – both during construction and in use.

• Enhances sustainability Behind these requirements lie some particularly important considerations, some of which
are specific to healthcare buildings, and include:

• Promotes a good work • Vibration – operating theatres and night wards require the designer to pay special
attention to reducing vibration
environment • Services – often the most expensive and slowest element to construct
• Partition walls – installing and sealing literally miles of these to the frame
• Resists spread of fire and sound • Work environment – proven to affect staff morale and patient recovery

• Improves air quality • Further issues such as sound, fire resistance and air quality.

Today’s concrete frames are ideally suited to support the requirements of modern hospital
buildings; and by playing an important background role in the operation and performance
of the building, concrete frames can help reduce running costs and maintenance.
Exposed concrete walls look good and provide fabric energy
storage (European Institute of Health and Medical Sciences). The following sections consider these issues further and discuss how concrete’s properties
Courtesy of The Concrete Society. can help resolve them.

SPEED AND PROGRAMME


The use of concrete is highly compatible with fast programme construction due to easy
mobilisation at the start and the use of modern methods of construction, including
sophisticated formwork systems, post-tensioning and precast elements. With traditional
methods of construction, concrete frames were erected on a floor-to-floor cycle of
two to three weeks. With modern methods it is common to achieve this in one week.
Concrete frames normally require no disruptive fire protection after erection, and can be
made sufficiently watertight for early installation of M&E services (the longest phase of
construction in hospitals) and other follow-on trades.

The use of concrete flat slab floors provides flush soffits that simplify service provision.
This encourages the swift installation of prefabricated services, where major savings in
cost and time come from factory-tested assemblies and fewer joints on site. Prefabricated
bathroom pods can be installed and set flush by recessing them into the floor slab.
3

VIBRATION CONTROL Vibration control:�����������������������


Vibration control is especially important in areas
����
such as operating theatres, night wards and intensive
care units, and is an important factor in the design ����

����������
and specification of building frames. Concrete can
easily be designed for the most complete control of ����
vibration over whole areas, often without the need for
significantly thicker floor slabs, giving great flexibility ���
for change in use. A recent independent study* into
the vibration performance of different structural �� ��������������
���
����������
forms has provided new insight into the additional
� ������
���
mass and stiffness required to upgrade a basic ‘office‘ �� ��� ��� �
��
� �� ��� ����
structure to meet the higher criteria of hospitals. This ��� ���� ��
��
is summarised in the diagram opposite.

The concrete solutions can meet vibration criteria with Vibration control:����������������������������
only small increases in mass and depth and hence cost,
compared with steel frame solutions. They also help 50%
the D&B team avoid the risks, often associated with
other materials, of having to seek modifications to NHS 40%
% increase

vibration criteria. This is done to avoid the cost penalties


30%
of providing this extra mass and stiffness.
20%

10%

FLEXIBILITY AND 0% ��������������


����������
���

ADAPTABILITY ��
���

��� �
������

��
� �� ���� ����

��� �� ��� ��
Healthcare methods, provision of IT, patient ��

expectations, and standards of environment and


equipment are all changing rapidly; so flexibility of use The above diagram shows the increases in mass and construction depth needed to
upgrade an office frame to hospital vibration criteria for night wards and operating
of new buildings is a major design requirement. For
theatres.
instance, less invasive surgery is likely to continue to
change the required proportions of theatre, recovery
and ward space. The use of concrete construction
automatically ensures many of the qualities that aid PARTITION WALLS
flexibility. Hospitals require literally miles of partition walls and
For services and future stairs or lifts, holes in both their construction is a major factor in cost, time and the
normal and post-tensioned slabs can easily be consequent disruption to other construction procedures.
designed-in and either formed during construction or Sealing walls at the soffits of the floor above is
cut out later as required. For vibration, larger areas can particularly important. The use of flat slabs simplifies
be designed to meet stringent criteria for operating this, reducing partition costs by up to 4% of the frame
theatres at little extra cost, permitting future flexibility. cost before considering additional programme savings.

Early consideration of these benefits during design can


optimise flexibility at little or no extra expense.
Concrete structures reduce vibration cost-effectively. Courtesy of the National Society for Epilepsy.

SOUND
It has been shown that patient comfort is an
important factor in recovery. Concrete’s mass and
damping qualities are easily used to achieve the
required acoustic performance, which provides a
restful and productive environment that is isolated
from the noise and vibrations resulting from normal
hospital routines. In concrete buildings, floor and
ceiling finishes are rarely dictated by acoustic
requirements; these are delivered by the performance
of the concrete slab.

*Hospital floor vibration study. Comparison of possible floor structures


with respect to NHS vibration criteria. Research Report, Arup, 2004.
Available for download from www.concretecentre.com
4

In a building, the SERVICES


The choice of material and design of a building’s frame and cladding can have a

environmental impact
surprisingly influential role on the services, which are generally the most critical element
in construction cost and time.

Concrete flat slabs are ideal for highly serviced areas in hospitals, such as operating

of construction theatres and intensive care units. They allow complete freedom to prefabricate, install
and maintain services without having to thread ducts under or through intrusive down-
stand beams. Openings in the slab for service risers can be simply accommodated during

materials is typically design; they can be formed during casting or cut later to suit. For the longest spans, wide
shallow beam solutions provide large areas uninterrupted by secondary beams and the
freedom to route ducts under the shallow main beams.

one tenth of that For the less heavily serviced areas, designers are now encouraged to use concrete’s
thermal mass properties to reduce air-conditioning. This then reduces capital,
refurbishment and running costs.
caused by operation
SUSTAINABLE CONSTRUCTION
over its life. Concrete has much to offer those who aim for sustainable construction. It has the
potential to reduce both the initial cost and running expenses by:
• Reducing the need for air-conditioning through fabric energy storage, and the use of
daylighting and natural ventilation. Concrete has an excellent track record in passively
cooled buildings.
• Reducing the need for heating through airtight construction.
• Reducing maintenance through providing durable walls, columns and cladding.

Other sustainable aspects of concrete construction include:


• UK manufactured reinforcing steel is made from 100% recycled scrap, unlike structural steel.
• Cement manufacture is increasingly using waste-derived fuels (such as scrap tyres),
thereby saving energy and relieving pressure upon landfill facilities.
• Replacement materials, which would otherwise go to landfill, are being incorporated
into both cement and concrete to reduce their environmental impact.
• Aggregates are often extracted locally, and ready-mixed concrete is typically made
no more than 15 miles from any project. This reduces the environmental impacts
associated with transportation.
Concrete flat slabs are ideal for highly serviced buildings.
• Unlike some materials, impacts arising from reinforced concrete generally occur in the UK,
rather than being ‘hidden’ abroad, and so are recognised and minimised for global benefit.
• The energy and carbon dioxide emissions ‘embodied’ in a concrete frame are slightly
less than those in a steel frame. More importantly, however, the energy used and CO2
emitted during a building’s operation are some 50 times greater than those embodied in
its structural frame. By using the excellent thermal properties of concrete it is possible to
make significant whole life savings in energy, carbon dioxide emissions and operating costs.
• On demolition of a building, concrete and reinforcement can be recycled.
• Concrete buildings are adaptable, durable and have many inherent qualities (sound,
fire and vibration performance), and hence are ‘long life, loose fit’ sustainable buildings.

By the use of thermal modelling, solar shading and passive ventilation techniques
to complement its concrete frame, the designers of Derby PFI hospital are aiming
for an annual energy target of 55 GJ/100 m3 p.a. – making it one of the most
energy-efficient acute hospitals in the UK.

An environmental review of design and construction of the Great Western Hospital


Swindon by environmental award winner, Carillion, achieved a cost saving of £1.8m.
This considered materials used, waste targets and energy in use. The hospital
incorporates a high thermal mass concrete frame and concrete cladding. Excavated
clay material was treated with lime and cement to provide a sub-base for the roads and
car parks, saving the costs of removal from site. The building is designed to consume
30% less energy in use and generate 50% less construction waste than a typical
hospital: it is discussed in detail on page 8.
5

WORK ENVIRONMENT MAINTENANCE AND


The look and feel of a hospital is known to affect REFURBISHMENT
patient and staff well-being and hence healthcare
performance. Uplifting architecture in public areas, Whole life costs can be reduced by the use of concrete
involving the use of exciting structurally efficient which provides long life cladding, durable walls and
exposed soffits, columns and walls can all add to columns with direct finishes, and easily accessed
the character and ambience of a building. This services under flat soffits. Cladding can be designed to
avoids having to develop an artificial architectural last the nominal design life of the building, with only
veneer that adds to first costs, maintenance, and periodic inspection of the external seals.
refurbishment. By using the exposed soffits, suspended ceilings and
air conditioning may be reduced or avoided, lowering
Concrete is inert with no harmful off-gassing, and
maintenance and refurbishment costs.
its structural form is commonly associated with
enhanced natural ventilation and daylighting. It
provides robust surfaces for walls, partitions, columns,
soffits and cladding that are easily sealed for cleaning ANCILLARY BUILDINGS
where required. The use of techniques such as ‘tunnel form’ and
precast wall and floor panels introduces further mass
Aesthetics, ease of cleaning and a healthy atmosphere all
production methods into concrete construction.
lead to enhanced user satisfaction of concrete hospitals.
Both are fast, economic, highly-mechanised and
increasingly popular. For repetitive room layouts, such
as staff residences, they are ideal because of excellent
FIRE sound and fire properties and low maintenance
Concrete is inherently fire resistant, and unlike some durable finishes.
materials normally requires no added fire protection.
This avoids the delays and disruptions of follow-on Concrete is also ideal for car parks due to its
trades caused by site applied protection or repair on robustness and corrosion resistance. It is a popular
site of damaged off-site applied protection. Concrete’s choice with users, with modern design taking
fire protection is provided at no extra cost and does advantage of concrete’s clear span capabilities to
not require the use of intumescent paints. provide easy access/parking, and bright clean soffits
that help security and boost user confidence.
The inherent fire resistance results in concrete often
performing in excess of design requirements for occupant
safety. This over-performance benefits the building
Exploiting the benefits of concrete is simple and
‘owner’ as repairs and the period before re-use following
a fire are minimised. comes at little or no added cost. It just requires
early awareness and consideration of the
potential gains and for decisions to be made at
AIR TIGHTNESS the correct stage in the design process.
With concrete, the flat soffits enable the partitions
between rooms to be sealed easily, helping prevent
airborne cross contamination between compartments.
Large panel external cladding reduces the number of
external joints and so cuts air loss and saves energy.

The light and airy reception at the Great Western Hospital, Swindon. Modern methods of concrete construction
Photography: Gillian Bond. are ideal for staff accommodation.
6

Flat slab concrete DESIGN


Concrete frames are available in a broad range of structural forms to suit all needs and
construction is the can be constructed in precast or in-situ concrete, or a combination of the two, known
as hybrid concrete construction.

preferred framing Currently, flat slab construction, typically on grids of 7.2 to 8.4 m on a 1.2 m module,
is the preferred choice for many hospitals with its speed, vibration performance and
ability to best facilitate the installation of services and partition walls. Increasingly, the

option for many flat slabs are post-tensioned to reduce slab thickness and provide potential for longer
spans of up to 12 m if necessary.

hospitals as it Some alternatives to flat slab construction are shown below.


• Prestressing of concrete beams and floor units provides fast, light and economical
solutions.

provides speed • Ribbed in-situ slabs on wide shallow beams are lighter than flat slabs, but not so
versatile and take longer to construct.
• Hybrid concrete construction combines the best qualities of precast concrete
and flexibility. (accuracy, high quality finishes, off-site manufacture) with those of in-situ
construction (flexibility for late changes, mouldability, robustness, two-way
spanning, local manufacture).

For each hospital the most effective solution can be determined only after considering
all design, construction and use parameters. The benefits of using concrete discussed
in this publication provide a useful guide for designers when comparing construction
types. For the structural engineer, assistance is available from the design tool, Concept
(see back cover).

Design loadings need to be agreed between client, architect and structural engineer
early in the design process. Allowances for larger point loads for ceiling-hung
equipment and heavy-weight blockwork partitions are often required. Vibration criteria
for operating theatres and night wards will often dictate structural design. The client
may choose to have larger areas designed to these tighter criteria to permit future
space planning flexibility.

When considering penetrations through slabs for services, the needs of the services
Concrete options for hospital frames.
engineer must be co-ordinated with those of the structural engineers, who should
incorporate them into their design. Working with the design team, the client will need to
decide how much flexibility it is reasonable to build in. For future flexibility, ‘soft spots’
are generally designed in; polystyrene knock out slots, cast-in lightweight blocks or
cast-in markers are all commonly used. These, together with the design drawings, aid
those making future modifications.

In reinforced concrete, holes near columns can be situated at the faces of the columns,
rather than being restricted to the corners so as not to clash with beams. This avoids
the need to offset pipe work back to column faces or use oversized clad columns to
Solid flat slab (may be post-tensioned)
hide pipe work on column corners.

Off-site manufactured bathroom pods are commonly used. To incorporate these with
the required falls, pods may be set on the slab with a traditional screed used elsewhere.
However, it is common to omit the thick screed and at most have a thin bed levelling
screed. To obtain the falls into the wet area, the slab is locally cast with a recess of
30 to 50 mm into which the pod is placed.

In line with Government policies, various hospital design guides* promote important,
Ribbed slab with integral beams
non-financial aspects to consider. These include:
• Air quality (optimisation of natural ventilation)
• Daylighting (improving natural light penetration and minimising solar gain)
• Integration of passive cooling and sustainable construction into design
• Aesthetics.

*NEAT evaluation toolkit (NHS Estates); Better health buildings (Centre for Healthcare Design); and Design
Hybrid – precast floor units on in-situ beams and columns
evaluation toolkit (Department of Health).
7

PROCUREMENT CLADDING IN
The specialist frame contractors should be involved
early in the procurement process to allow the design
CONCRETE
to reflect the economies of their preferred form of Precast concrete cladding can be designed with a wide
construction, balanced against whole project value. This range of finishes, from brick to reconstructed stone.
will depend on the contractor’s previous experience, the Panels are secure, highly durable, low maintenance and
availability of equipment and the opportunity to tailor long life; especially compared with lightweight metal
design details to the construction method. alternatives. They can have glazing fitted in the factory
and be designed for installation without scaffolding.
For instance, many specialists have their own Recently, some new hospitals have been criticised
prestressing firm (or preferred partner), allowing for problems caused by excessive heat or cold. Using
them to provide fast and cost effective prestressed concrete cladding to control solar gain and thermal
frames. Others may have their own stock of special loss can help avoid this.
formwork, giving them an edge in another form of
concrete construction. Alternatively, precast elements Panels can be large and self-supporting between
that can be swiftly erected may be best. This needs columns if desired, thereby simplifying the frame and
early involvement of the precaster to obtain the best maximising airtightness. Sandwich panels (factory
programme and economies through repetition of insulated between two concrete skins) provide
components and hence mould use. significant extra thermal mass due to their solid inner
wall and have a durable inner face, suitable for direct
Partnering, DBFO and modern methods of decoration.
construction in concrete are highly compatible with
the above approaches as they encourage integration, With most cladding systems, hospitals will have to
rather than the traditional separation, of the design- allow for the major cost of recladding – and loss of
construct process. This minimises construction risk, use of the facilities during this work – within their
with its consequences of higher tender prices, extra design life. However, concrete panels can be designed
programme allowances and potential over-runs. to require only periodic inspection of the external
seals, with any replacement of seals to be carried out
Concrete is regularly used for new construction without scaffolding or closure of the building.
alongside existing working buildings. Construction and
forming methods, and deliveries can be adapted to Precast cladding panels provide opportunities for rapid
suit congested areas, and precast or self-compacting construction, just-in-time delivery and minimal waste,
concrete can be used where construction noise is an with low construction risk. Again, for best economy,
issue. the cladding should be considered early in conjunction
with the specialist supplier. This will ensure best value
by optimising repeat mould use and fixing/interface
details with the frame.

The Great Western Hospital case study on page 8


illustrates the use of concrete cladding.

Cost of precast units drops with repeated use of moulds Concrete sandwich panel being
– Cast in concrete, Architectural Cladding Association, 2003. hoisted into position.

700

500
Index of cost

Labour content & cost

300

100
1 10 20 30
Casts per mould
The effect of repetition on cost of casting precast
concrete structural or cladding units
8

Today most hospitals CASE STUDIES


are built in concrete THE GREAT WESTERN HOSPITAL, SWINDON
The Great Western Hospital is a £100 million, PFI project on the outskirts of Swindon,

because of vibration providing 55,000 m2 of space for the Swindon and Marlborough NHS Trust. The design and
build consortium, which included contractor Carillion, will operate it over the next 27 years,
and put great efforts into choosing the most appropriate components on the basis of user

performance, needs and whole life cost. The six-storey L-shaped building is an environmental flagship
project, featuring an in-situ concrete frame and precast concrete cladding.

simple services Concrete frame - strength and simplicity


An in-situ concrete flat slab frame on a nominal 7.2 by 7.2 m column grid was chosen for speed
and buildability. It also maximised the service zones, provided inherent fire protection and delivered

installation and cost energy savings through the exploitation of the frame’s thermal mass. Finite element design of the
300 mm deep floors provided for large cast-in and drilled service openings without downstand
beams. The frame was constructed ahead of programme in only 38 weeks.

effectiveness for the Designing the interface


Early involvement between engineers TPS Consult, frame contractor Duffy Construction and

required spans. precast cladding contractors Trent Concrete, resulted in an efficient and economical system for
the concrete cladding panels that then became self-supporting between columns. The design
of the cladding and frame accommodated not only operating theatres, ITUs, offices and wards,
but also provided flexibility for future changes in use.

Precast cladding - maximising prefabrication


Factory installed glazing avoided the use of scaffolding. Architect Whicheloe Macfarlane HDR (now part of BDP) chose the 7600 m2 of rich cream-
coloured precast concrete cladding to simulate the local natural stone. Its high quality finish
and careful detailing contributes to the clean and attractive lines of the building.

One of the primary reasons for specifying precast concrete was to avoid external scaffolding,
significantly reducing cost and allowing earlier access for following trades. The factory
pre-glazed 7.2 m panels were each erected in one movement and the large size minimised
the number of just-in-time deliveries, joints and fixings. Cladding was installed ahead of
programme in only 19 weeks.

The resulting early enclosure provided a dry envelope and allowed the follow-on weather-
sensitive trades to start earlier – especially important in hospital construction with complex
M&E services to install. This, together with the freedom provided by a flat soffit, helped speed
installation and minimise M&E costs that amounted to a third of total construction cost.

Sustainability
Carillion intended The Great Western Hospital to be a flagship sustainability project.
Environmental considerations dictated materials used, construction techniques and waste
Cladding on elevation.
handling. At Swindon, the thermal mass of the concrete frame contributes further to
sustainability objectives by maximising its fabric energy storage properties, and the cladding
helps moderate solar gain and heat loss.

Whole life value


Whole life costings and lifetime performance are of critical importance in PFI projects. The
precast cladding not only gave greater certainty in terms of quality, cost and programme time,
but also provided a highly durable, self-finished façade requiring little or no maintenance.
Because of early specialist involvement and value engineering it cost only around 55% of the
cost for basic curtain walling.

Both the frame and cladding at Swindon were erected ahead of programme, and the Great
Western Hospital was delivered on time and on budget in little over three years from start of
construction.
9

COVENTRY AND DERBY PFI HOSPITALS


A large 127,000 m2 six-storey acute hospital forms part theatres, further increasing flexibility. The frame also
of the £334m Coventry New Hospitals PFI contract with supports rooftop plant rooms.
Innisfree. Skanska is constructing the 6000 room building Derby PFI Hospital, another six-storey hospital by the
with 300 mm deep flat slab in-situ concrete floors, same team, will provide 1,159 beds and 128,000 m2
supported on a typical column grid of 7.2 by 7.2 m, of new hospital buildings, including 35 operating
increased to 8.5 m in some areas. The structural form was theatres. Like Coventry, a 300 mm flat slab concrete
chosen for minimum construction depth, with a flat soffit frame was chosen for reasons of ease of partition
to allow uninterrupted services distribution and easy and services installation under a flat soffit, ‘blanket’
fixing and acoustic/smoke sealing at wall partition heads. vibration control to cover wards and theatres, and
Arup’s flexible design allowed for up to two holes service holes for flexibility for clinical re-planning.
in the slab on opposite faces of internal columns The design incorporated 15 m wide blocks surrounding
– either cast-in, or post drilled to allow flexibility for courtyards, producing column grids varying from
future clinical replanning. Floor finishes are applied 6.0 by 6.5 m to 8.5 by 8.5 m. Concrete columns,
to a 6 mm levelling screed on the as-cast concrete precast in steel moulds, increased speed of erection
slab, in which 35 mm deep recesses allow for shower and allowed direct paint finishes, so helping reduce
and bathroom floor finishes to falls. Detailed analysis programme time and risk. Arup’s design supported
confirmed that floors could satisfy HTM vibration ‘roll-out’ reinforcement mats and contractor detailing
criteria without any increase in depth under operating to increase construction efficiency.
The in-situ frame at the Coventry
Hospital.

ROMFORD NEW HOSPITAL


Catalyst Healthcare is constructing this new 800-bed to 3 m in length. The flat slab brought savings of
five-storey hospital under a £200m PFI project for around £800,000 by simplifying the fixing and sealing
Barking, Havering and Redbridge Hospitals NHS Trust. of partition wall heads. All five current UK hospitals by
Four circular ward towers rise three storeys above two Bovis Lend Lease use concrete flat slab frames for
podium floors that contain administration, diagnostic, similar reasons.
and treatment facilities including operating theatres. A
Shearheads (steel cruciforms within the depth of
central service core tower separates staff, patient and
the slab) have been adopted for additional flexibility
visitor flows, and houses staff facilities.
for service penetration at columns – holes can be
The in-situ concrete frame supports 250 to 300 mm constructed on all four axes on internal columns.
thick concrete flat slab floors on a column grid of 8.1 Bathroom pods are recessed into the slab which uses a
to 9.0 m span. Columns are mainly circular with a thin levelling screed.
diameter of 400 mm. The post-tensioned flat slab
The concrete frame facilitates fast construction,
maximises space for services, encouraging their
avoiding delay to services associated with site-applied
prefabrication, and giving greater flexibility for routing
fireproofing and allowing swift partition installation.
and penetration of the slab. It also copes well with the
It also meets vibration criteria without seeking
circular floor plate and irregular cantilever edges of up
dispensations. Post tensioning ducts in place for the
slab at Romford.

JOHN RADCLIFFE HOSPITAL, OXFORD


This hospital is being constructed by Carillion Health depending on the grid layout of each section of hospital
for The Hospital Company under a PFI contract with the and accommodate 4 by 6 m services riser voids. The
Oxford Radcliffe Hospitals NHS Trust. The 45,000 m2 slabs are increased to a thickness of 300 mm for
six-storey frame extends the existing hospital to provide theatre, laboratories and plant areas to cater for heavier
three new sections for the Children’s Hospital, a Head loadings and vibration control.
and Neck Centre, and a theatre block with laboratories. The post-tensioned slab provides knock out points to
Concrete columns, mostly precast, support 250 mm accommodate services for future hospital flexibility. These
thick post-tensioned flat slab concrete floors that will generally provide two holes, situated on opposite or
match existing hospital levels, with stability provided adjacent column faces. All cast-in requirements and post
by the concrete cores. TPS Consult’s flat slab design drilled holes are co-ordinated with the tendon layout
approach maximises services zones and flexibility (which is clearly marked on slab surface and soffit).
within the ceiling voids. Post tensioning was chosen for
Stairs are mostly precast concrete, housed in the cores,
programme speed and cost.
and there is a feature semi-circular in-situ entrance stair.
Square precast columns vary between 500 and 600 mm, Individual large-diameter bored concrete piles up to
with larger circular feature columns up to three storeys 1200 mm across and 35 m long directly support precast
high in the concourse and entrance. The 250 mm thick columns, avoiding the cost and disruption of pile caps.
post-tensioned concrete slabs span from 6.6 to 9.0 m, Flat concrete soffits at the John Radcliffe
Hospital, showing tendon marking.
CI/SfB

UDC
725.5119.057.52:728.5
69.057.52:728.5

FURTHER READING
Ecoconcrete: The contribution of cement and concrete
to a more sustainable built environment.
British Cement Association, 2001, 21 pages.
Ref. 97.381.

Economic concrete frame elements – a handbook for


the rapid sizing of concrete frames.
British Cement Association, 1997, 128 pages.
Ref. 97.358.

Concept – an invaluable design tool for the


conceptual design of reinforced concrete frames in
five minutes.
The Concrete Centre, 2004. Ref. TCC/03/012.

Best practice guidance for hybrid concrete


construction.
The Concrete Centre, 2004, 64 pages. Ref. TCC/03/09.

Concrete and fire – using concrete to achieve safe,


Kings College Hospital: feature staircase in the new Golden Jubilee Wing, an in-situ flat slab concrete
framed building. Design: Nightingale Associates; photography: Charlotte Wood. efficient buildings and structures.
The Concrete Centre, 2004, 13 pages.
Ref. TCC/05/01.

Help and advice on concrete construction for hospitals are Cast in concrete II - a guide to the design of precast
available from buildings@concretecentre.com concrete and reconstructed stone.
or visit www.concretecentre.com Susan Dawson, Architectural Cladding Association,
2003, 96 pages. Ref. BPCF 1.

www.concretecentre.com
The Concrete Centre, Riverside House,
4 Meadows Business Park, Station Approach, Blackwater, Camberley, Surrey GU17 9AB
National Helpline 0700 4 500 500 or 0700 4 CONCRETE

Ref. TCC/03/13
ISBN 1-904818-25-0
First published 2005
© The Concrete Centre 2005

All advice or information from The Concrete Centre is intended for those who will evaluate the significance and
limitations of its contents and take responsibility for its use and application. No liability (including that for negligence)
for any loss resulting from such advice or information is accepted. Readers should note that all Centre publications are
subject
to revision from time to time and should therefore ensure that they are in possession of the latest version.

Das könnte Ihnen auch gefallen