Sie sind auf Seite 1von 12

SAUDI COMMITTEE FOR PALESTINIAN RELEIF

UNITED NATIONS DEVELOPMENT PROGRAMME

CONSTRUCTION OF 300 RESIDENTIAL UNITS IN RAFAH

Construction of Infrastructure works

Bill of Quantity

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

Bill No (1) 1. Mobilization & Demobilization


ITEM DESCRIPTION UNIT QTY RATE (US$) in Numbers In Letters Total (US$)

All works according to particular specifications, and supervisor engineer instructions. Preparation works including: 1- Supply Site office, shed, equipments, and furniture for both supervision and contractor. 2- Access road to and through the site. 3- Transportation & Communication.for the supervisor engineers 1/1 4- Cleaning the existing site outside the buildings, the work includes removing all debris around buildings and transmitting to approved dumping site. 5-Determination the Road axis ,coordinates by Total Stationand allignment of the sewage , water and electrical networks. Dismantle and remove all facilities, services, furniture, 1/2 shed and any equipment related to the project supervisor and contractor office.As per the engineer instructon. Total

LS

LS

Contractor Signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

BILL NO. 2 WATER SUPPLY WORKS


ITEM 2 DESCRIPTION UNIT QTY RATE (US$) in Numbers In Letters Total (US$)

Water Supply Works


1- All works must be coordinated with the water department at the Municipality &CMWU. 2- The price includes the cost of excavation to depth indicated in drawings not less than 1m using retaining shuttering, shoring according to instructions of Engineer, bedding of 20 cm clean sand under around and above the pipe with compaction, backfilling of the trench up to design level with sand in layers 25 cm thick for each with compaction 98% MDD and all required tests. 3- The work includes removal of the surplus materials outside the site to places as instructed by the Engineer. 4- The work includes supply and installation of metallic warning tap, and other accessories and thrust blocks according to details. 5- The covers of manholes are made of cast iron with diameter 60 cm engraved by the word " Water " in English and Arabic. the ring is from cast iron square shaped with 70*70 cm dimensions. the concrete which used around the ring is B350 and should have a Basalts layer of 2 cm above the concrete and around the cover rings. according to drawings, specifications and Engineers instruction. 6-Cleaning ,disinfection and testing all the installed pipes according to technical specification, Engineers instructions and coordinating with water department in the municipality & CMWU. 7-All works are performed according to the drawings, specifications and Engineers instruction 8-All Manholes items to be painted with hot bituminous 70/25 paint in addition to primer coat as directed by the supervision Engineers & the manufacture instructions. 9-The price include reinstate repairing any damage resulted from the works, all according to specification & as per engineer instructions 10-The contractor must be submit detailed shop drawings of the coming items for the approval by the Engineer before starting the work. 11-The price includs supply and lay warning tape over the pipeline with text indicating the exiatance of Water Pipeline. 12-All gate valves should be 16 bar working pressure Hakohav, Raphael made or equivalent 13- All ball valves should be 16 bar working pressure Zagiv made or equivalent 14- Air release valves should be 16 bar working pressure A.R.I made or equivalent

2.1 Supply, and install 110mm diameter PVC-U water pipes PN 10 L.M
including excavation, backfilling, elbows, angles, Tees, flanges, end caps, joints and accessories .The pipe should be bedded and covered with at lest 20 cm of clean sand around, at the top and bottom of the pipe . The used sand for backfilling of the trench will be in layers not exceeding 25cm, with compaction not less than 98 % , up to the design leveling of the road all according to the engineer's instruction, drawings and technical specifications

800

2.2 Ditto but 63 mm diameter MDPE (Polyethylene) water pipes .

L.M

3500

Contractor signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

BILL NO. 2 WATER SUPPLY WORKS


ITEM DESCRIPTION UNIT QTY RATE (US$) in Numbers In Letters Total (US$)

2.3 Supply and install 80 cm internal diameter precast circular reinforced concrete water manhole for air release valve, complete with B300 cast in place reinforced concrete base, cast iron cover (25ton Capacity) with frame. The supplied concrete rings should be provided with cast iron steps @ 30cm maximum. The work includes excavation in any type of soil to any depth , backfilling with clean sand and compaction 98% MDD up to the design leveling of the roads. The manhole base should be provided with drainage opening with aggregate bed.
The price shall include Tee 110x110x50mm, ball valve 2" diameter Sagiv or equivalent, air release valve 2" diameter double action ARI or equivalent, Nipples, fittings and all needed tests to finish work according to drawing, specification and engineer's instructions. 2.4 Ditto but Manhole 100 cm diameter for washout valve. The price includes supply and install gate valve 3", flanged dresser 3", Tee 63x63x50mm , Nipples, Jack supports, male connector for firefighting hose, fire fighting hose 2" with length 15 m and all fittings according to drawing, specification and engineer instructions pipe 110 mm (MH1). The price includes Flanges, dressers, socket flange, gate valve 4" diameter, Jack supports, and all fittings according to drawings, specification and engineer's instructions

No.

No.

2.5 Ditto but Manhole 80 cm diameter for Gate Valve 4" on the No.

2.6 Ditto but Manhole 80 cm diameter for Gate Valve 3" on the No.
pipe 63 mm (MH2, MH3). The price includes Flanges, dressers, socket flange, gate valve 3" diameter, Jack supports and all fittings according to drawings, specification and engineer's instructions 2.7 Ditto but Manhole 80 cm diameter for Gate Valve 4" on the pipe 110 mm (MH4,MH5,MH6,MH7)). The price includes Flanges, dressers, socket flange, reducer 4"/3", gate valve 4" diameter, Jack supports, and all fittings according to drawings, specification and engineer's instructions

No.

2.8 Ditto but Manhole 80 cm diameter for the fire hydrant. The No.
price includes Flanges, dressers, socket flange, gate valve 4" diameter, Jack supports,3" & 4" galvanized steel pipes, galv. steel reducer 4"/3"galvanized elbow 3", fire hyrant valve 3" 16 bar and all flanges and fittings. The galv. pipes should be painted and supprted by concrete thrust block ,all works as specification drawings and engineer's instruction.

2.9 Cutting the existing 200mm UPVC pipe and connecting the No.
new UPVC pipe 110mm including T200X200X110mm, Dressers, flanges and all needed fittings and accessories. The work includes excavation and backfilling with clean compacted sand all as specification drawings and engineer's instruction.

2.10 Cutting the existing 160mm UPVC pipe and connecting the No.
new UPVC pipe 110mm including T160X160X110mm, Dressers, flanges and all needed fittings and accessories. The work includes excavation and backfilling with clean compacted sand all as specification drawings and engineer's instruction. 2.11 Excavation , backfilling with clean sand on layers not to exceed 25 cm each , Supply and install house connection 32". The price includes approved Saddle 110/32mm , thrust block ,MDPE pipe 32 mm diameter to be connected to the existing 1" steel pipe and all needed fittings according to drawings, specification and engineer's instructions.

No.

20

2.12 Ditto, but saddle 63/32 mm


Total ($)

No.

80

Contractor signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB2012-099

BILL NO.3 SEWAGE WORKS ITEM 3 DESCRIPTION UNIT QTY RATE (US$) n Number In Letters Total (US$)

Sewage works _The contractor has to submit detailed shop drawings of the coming items for the approval by the Rafah municipality and CMWU before starting the work. _The Contractor has to visit the site for inspection. _The price includes the cost of excavation to depth indicated in drawings and using retaining shuttering, shoring according to the instructions of Engineer, bedding of 15 cm clean sand under ,around and above the pipe with compaction, backfilling of the trench up to design level in layers 25cm thick for each with compaction 98% MDD and all required tests. _The work includes removal of the surplus materials outside the site to places as instructed by the Engineer. _The work includes connection of the manholes to the existing sewage line after cleaning and adjusting the level and orientation of the existing pipes if needed according to engineer instructions. _ The holes of the manholes have to be done using core machine. _ All the manholes have to be coated by one coat primer and external hot bitumen coating 75/25. _ Measurement of pipes and manholes depth is from the invert level of pipes to the design asphalt level. the price include erecteing Flexible Joints for manholes at the main line of sewage _Cleaning and testing all the installed pipes according to technical specification, Engineers instructions and coordinating with water department in the municipality _All tests costs to be included in the unit rate items, without any extra paid money. _The price include reinstate repairing any damage resulted from the work, all according to specification & as per engineer instructions _Covers of manholes are made of cast iron with diameter 60 cm for all manholes sizes 25 ton capacity, and engraved by the word " Sewage " in English and Arabic. the ring is from cast iron square shaped with 70*70 cm dimensions. The concrete used around the ring is B300 for at least 30cm width and depth, Basalt layer of 2 cm thick above the concrete and around the cover to fix the ring should be supplied and installed, all according to drawings, specifications and Engineers instruction. _All the above mentioned instructions considered part of the next items are

Contractor Signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB2012-099

BILL NO.3 SEWAGE WORKS ITEM 3-1 DESCRIPTION UNIT QTY RATE (US$) n Number In Letters Total (US$)

UPVC Pipes:Supply, install and join, UPVC pipes SN8 250 mm outside diameter. for the sewer networks with watertight and flexible joints sealed with approved gasket rubber ring including excavation in any ground for the depth indicated in the drawings, shoring, shuttering, safety measures, testing, sand beds all according to the drawings, specifications and Engineers instruction. 200 mm outside diameter UPVC Pipes

L.M

150

3-2

L.M L.M

120 1200

160 mm outside diameter UPVC Pipes


3-3 3-4

Manholes: Supply, install precast circular reinforced concreteB300 kg/cm2 Sewage manholes 1.25m internal diameter and wall thicness 15 cm with reinforced base, cast iron steps @30cm spacing, cast iron manhole cover,(25 ton capacity), outlet pipes for future connection with end cap where shown or necessary. The price including two external bitumen coating, shuttering, excavation in any ground to the depth indicated in the drawings, shoring, safety measures, formwork, backfilling with sand, removing the surplus soil to the tip ..etc. The price includes also supply and install 10cm plain concrete B200 under the base of the manhole and for benching. The price includes also erecteing Flexible Joint 80-50 cm at connection btween pipe and manhole . All are as per drawings , specifications and the engineer instructions.

No

Ditto but Manholes with internal dia. 1. 0 m wall thicness 14 cm and 25 ton capacity Ditto but Manholes with internal dia. 0.80 m wall 3-6 thicness 12.5 cm and 25 ton capacity Ditto but Manholes with internal dia. 0.60 m wall thicness 7.5 cm and 40 cm opening with 8 ton capacity 3-6 cover
3-5

No No

68 62

No

66

total

Contractor Signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

BILL NO.4 COMMUNICATION WORKS ITEM 4 DESCRIPTION UNIT QTY RATE (US$) n Number In Letters Total (US$)

Communication Works _The contractor has to submit detailed shop drawings of the coming items for the approval by the PalTel Company before starting the work. _The Contractor has to visit the site for inspection. _The price includes the cost of excavation to depth indicated in drawings and using retaining shuttering, shoring according to the instructions of Engineer, bedding of 15 cm clean sand under ,around and above the pipe with compaction, backfilling of the trench up to design level in layers 25cm thick for each with compaction 98% MDD and all required tests. _The work includes removal of the surplus materials outside the site to places as instructed by the Engineer. _The work includes connection of the manholes to the existing PalTel line after cleaning and adjusting the level and orientation of the existing pipes if needed according to engineer instructions. _ The holes of the manholes have to be done using core machine. _ All the manholes have to be coated by one coat primer and external hot bitumen coating 75/25. _ Measurement of pipes and manholes depth is from the invert level of pipes to the design asphalt level. _Cleaning and testing all the installed pipes according to technical specification, Engineers instructions and coordinating with PalTel. _All tests costs to be included in the unit rate items, without any extra paid money. The price includs supply and lay warning tape over the pipe with text indicating the exiatance of PalTel line. _The price includes installation of pulling ropes inside the the PVC pipes _The price includes reinstate repairing any damage resulted from the work, all according to specification & as per engineer instructions _Covers of manholes are made of cast iron with diameter 70 cm for all manholes sizes 25 ton capacity, and engraved by the word " PalTel " in English and Arabic. the ring is from cast iron square shaped with 80*80 cm dimensions. The concrete used around the ring is B350 for at least 30cm width and depth, Basalt layer of 2 cm thick above the concrete and around the cover to fix the ring should be supplied and installed, all according to drawings, specifications and Engineers instruction. _All the above mentioned instructions considered part of the next items are

Contractor signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

BILL NO.4 COMMUNICATION WORKS ITEM 4-1 DESCRIPTION UNIT QTY RATE (US$) n Number In Letters Total (US$)

PVC Pipes:Supply, install and join single line of PVC pipes 4" diameter V1. for the PalTel network with approved gasket rubber ring including excavation in any ground for min. 1.5m depth, shoring, shuttering, safety measures, testing, sand beds all according to the drawings, specifications and Engineers instruction. Ditto but double lines of PVC pipes 4" V2

L.M

800

4-2

L.M L.M L.M

620 150 850

Ditto but trible lines of PVC pipes 4" V3


4-3

Ditto but four lines of PVC pipes 4" V4


4-4

4-5 4-6

Supply, install and join single line of flexible PVC pipes 3" diameter for the PalTel house connection including excavation in any ground for min. 1.5m depth, shoring, shuttering, safety measures, testing, sand beds all according to the drawings, specifications and Engineers instruction.

L.M

1000

Manholes: Supply, install precast circular reinforced concrete B300 kg/cm2 manhole 100cm internal diameter and wall thicness 15 cm with cast iron manhole cover,(25 ton capacity . The price includes two coats of external hot bitumen, shuttering, excavation in any ground to the depth of 1.5-2.0m, shoring, safety measures, formwork, backfilling with sand, removing the surplus soil to approved site ..etc. all as per drawings , specifications and the engineer instructions. Supply and cast in situe reinforced concrete B300 kg/cm2 for the manholes M1 with cast iron manhole cover,(25 ton capacity . The price includes two coats of external hot bitumen, shuttering, excavation in any ground to the internal height of 2.0 m, shoring, safety measures, formwork, backfilling with sand, removing the surplus soil to approved site ..etc. all as per drawings , specifications and the engineer instructions.

No

31

4-7

No

25

total

Contractor signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

Bill No (5) Electricity Works


RATE (US$) ITEM DESCRIPTION UNIT QTY in Numbers In Letters Total (US$)

A-

Steel Poles and Bases: Supply and Install Lattice Steel Pole L.S.P 70/80 12 m long. with Steel Base ,Arms &brackets , B200 Concrete Foundation, Lattice Pole Suspension Side Arm, K7972, 1.5m, 1.st Phase. Auxiliary Steel Arm K160/3. Transformer Isolator Side Arm , K1558 , 3m, Protection Arm, K81. Anti-Climbing Steel Arm K113/8, for (L.S.P). 22 kV Pin & Tension type Insulators, Complete Low Tension Insulator Unit, Wire KHF CU 95 mm2 Stranded (Hard Drawn). Line KHF CU 35 mm2 Stranded (Soft drawn). 22 kV Cable 1*50 mm2 CU, XLPE. With Steel bolts , Nuts , Washers ,Clamps, Earth Rod 15mm Diameter, 1.5 m. Wire PN CU 70 mm2 PVC Yellow/Green and Master lock key.and all needed fittings and accessories to hand over the work in clean tested and good workmanship and operable Condition.

5.1

No.

5.2

Supply and Instal 24 kV, 630A Switchgear, and 16 kA Short Circuit Current Ring Main Unit SF6, 2 incoming switch Disconnectors, one Transformer Protection fuse switch combination (CTC) With 22 kV Porcelain Fuses 63 A. Including cables Trench.and chaqar cover Supply and Install hermetically sealed Type, 1250KVA,22/0.4KV, ,Mineral oil Low losses Transformer With Bushings and Arms for Fixing the Cable, Beside the Transformer with cable ladder. The Works Includes Transformer Concrete base B250 , And all needed Lugs, Clamps ,Wires and Earthling system for transformer and chaqar Plate cover for trenchs. According to Engineer Instructions and Approval of Gedco Supply and Install L.V Distribution Board 2000A with Main CB IZM 2000A (8 Feeder).with Bus Bars 2000A, NZM Circuit Breakers , KWH Meters , Current and Voltage Instruments With CTs , wires , Clamps and all needed Accessorizes Per drawings and Engineer Instructions . Supply and Install Underground 22 kV Cable 1*240 2 mm AL, XLPE.The Works including Excavation 150 cm under ground Cable Trench and Backfilling with Clean sand ,Warning Tape and concrete Slabs (45x45x5)cm entire the length of trench ,6 inch UPVC Pipes With compression lugs, Shrink Insulator for Lugs (Color). PVC& Buckle Clamps with all needed wires and Accessories as per Drawings . Supply and Install LV Panel with main Vertical Disconnect or switch LTL 630/400 Amps and 6 Vertical Disconnector switch LTL 160/100 A including Earthing , civil structure 10 Nos ,4 Inch Pvc sleeves pipes and all needed to fix and connect the Panel as per drawings. Supply and Install LV Panel with main Vertical Disconnect or switch LTL 400//250 Amps With LTL(3X63/40A) With Bus bars including earthing , civil structure with 6mm thick chaqar plate cover with hand held ,10 Nos ,4 Inch sleeves and all needed wires and PVC Terminals connections to fix and connect consumers Cables .with Electricity

No.

5.3

No.

5.4

No.

5.5

L.m.

1200

5.6

No.

5.7

No.

Contractor Signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

Bill No (5) Electricity Works


RATE (US$) ITEM DESCRIPTION UNIT QTY in Numbers In Letters Total (US$)

5.8

Supply and Install LV Panel with main Vertical Disconnect or switch LTL 400//200 Amps with LTL(3x63/40)A With Bus bars including earthing , civil structure with 6mm thick Chaqar plate cover with hand held ,8 No S,4 Inch Sleeves and all needed wires and PVC Terminals connections to fix and connect consumers Cables .with Electricity Supply and Install LV Panel with main Vertical Disconnector switch LTL400//160 Amps with LTL(3x63/40)A and three phases Bus bars including Neutral and Earthling Buses , civil structure with 6mm thick Chaqar plate cover with hand held ,8 No S,4 Inch Sleeves and all needed wires and PVC Terminals connections to fix and connect consumers Cables .with Electricity Supply, Install and connect 0.6/1KV ,L.V Cable 3*240+120 mm 2 CU, XLPE. Supply, install and connect 0.6/1KV,L.V Cable 2 3*150+75 mm CU, XLPE. Supply, Install and connect 0.6/1KV,L.V Cable 2 3*120+60 mm CU, XLPE Supply, Install and connect 0.6/1KV,L.V Cable 3*95+50 2 mm CU, XLPE Supply, Install and connect 0.6/1KV,L.V Cable 3*70+50 2 mm CU, XLPE Supply, Install and connect 0.6/1KV,L.V Cable 3*50+25 2 mm CU, XLPE Supply, Install and connect 0.6/1KV,L.V Cable 3*16+10 2 mm CU, XLPE Supply, Install and connect L.V Cable 4*16 mm 2 Cu., XLPE, including spring pipe 2", Civil works to lay the cables and all needed to connect the dwelling units M.D.Bs with electricity .The work includes Excavation 80cm depth in soil and back filling with clean sand , warning tape and 80cm diameter manholes every 25 meter distance as per drawings and Engineer approval . Supply and Install materials for future installation of Hot galvanized octagonal street light pole 8m long including bolts galvanized steel base and B200 concrete foundations 1*1*1m. Supply and Install 3" spring pipe dumped at 80cm deep as following (pipe then 30cm soft sand then warning tape then 50cm sand).as per drawings. Supply and Install N 8-4" UPVC pipe dumped at 80cm deep as following (pipe then 30cm soft sand then warning tape then 50cm sand) for low voltage Cables crossings at The Roads. Supply and Install N2XY cable 3*35+16mm 2. Supply and Install N2XY cable 5*16mm 2. Supply and Install N2XY cable 5*6mm 2. Supply and Install Cu stranded wire 35mm 2 for Earthing. Excavation under ground high voltage cable trench 150 cm from finishing floor level in different soil levels at road crossing and laying 6 inch pipes covered with 50 cm B200, concrete above the pipes and backfilling with clean sand and compaction for cables trenches. including warning tape and concrete slab 45x45x5 cm entire the length of the trench as Per drawings .

No.

5.9

No.

18

5.10 5.11 5.12 5.13 5.14 5.15 5.16

L.m. L.m. L.m. L.m. L.m. L.m. L.m.

200 350 300 665 450 800 100

5.17

L.m.

6000

5.18

No.

50

5.19

L.m.

3500

5.2 5.21 5.22 5.23 5.24

L.m. L.m. L.m. L.m. L.m.

300 200 200 500 100

5.25

L.m.

200

Contractor Signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

Bill No (5) Electricity Works


RATE (US$) ITEM DESCRIPTION UNIT QTY in Numbers In Letters Total (US$)

5.26

Supply and Construct transformer room buildings with two lighting fixtures (2x36W) ,IP65 With lighting switch and one socket , The work includes Transformer Base foundation , High Voltage switchgear and low voltage main trenches covered with 6 mm galvanized steel chaqar plate entire the trenches . The room shall be provided with painted galvanized steel door and window with louvers, plastered internally and externally, tiled and internally and externally painted . All the work should be according to GEDCO Regulations, drawings, specifications and approval of Engineer .

No.

Total

Contractor Signature

Construction of Infrastructure works PAL10-49740: Construction of 300 Residential Units in Rafah

ITB 2012-099

Summary Bill No Description Mobilization Water Works Sewage Works Communication Works (PalTel) Electricity Works Grand Total (US$) Not including Value Added Tax (VAT) Total in numbers ...................................................................... Total in letters .............................................................................. Name of the contractor ...... Authorized signature ...... Signature and Sealing. Title ... Telephone. Fax . Mobile . Total

Bill No (1) Bill No (2) Bill No (3) Bill No (4) Bill No (5)

Contractor Signature