Beruflich Dokumente
Kultur Dokumente
Words to remember
Albert Schweitzer
Example is not the main thing in influencing others, it is the only thing.
Direct Workers
Lean Leadership
Direct Workers
Lean Construction
Cultural Change
Waste
Henry Ford The easiest waste, and the hardest to correct is the waste of time, because wasted time does not litter the floor like wasted material
Why
Seven Wastes
Overproduction Why put in cable tray for something that isnt needed for weeks when others are waiting for it in another work area. This is the worst form of waste and leads to the other six. Waiting Standing around because you need something before you can start/continue working on your task. Conveyance Unnecessary movement of equipment, parts and tools. Processing Performing unnecessary work. Inventory Too much or not enough are both wastes. Motion Unnecessary movement of people Correction Rework for any reason
9
INCREASE RELATEDNESS
10
11
Adapted from:
Learning Loops
Purposes Design Concepts Product Design Fabrication & Logistics
Commissioning
Modifications
Design Criteria
Process Design
Detailed Engineering
Construction
Project Definition
Design
Procure
Construct
Production Control
Work Structuring
Continuous Learning
12
Measurement and Metrics 90% of measuring the value of Lean Construction is in use today.
Earned Quantities/Planned Quantities Recordable/Lost Time Injury Rates Quality metrics (weld reject rates and non-conformances) Rework Etc.
14
System of commitments 6-12 week look-ahead (from material management through the hands at the workface, plus all interfacing disciplines) Work face planning (one crews work for one (or two) week period) Elimination of restraints and going right to work without delay for the entire week
The focus is on ensuring reliable flow of work from one task to the next, minimizing the seven wastes. Accept the fundamental reality of constant change and continuously re-planning throughout a project Improved Safety Performance!
15
16
Acknowledgements: COAA
17
Background Workface Planning (Last Planner)? Engineering Sub-Contractor Experience Project Size Labour Availability Job A (Used) Same Less Job B (Did not use) Same More
More More
Less Less
Planners Contract
12 Reimbursable
1 Lump Sum
18
Background
Workface Planning (Last Planner)? Schedule Predictability Hours Rework Progress Reporting
Job B (Did not use) On time Major Deviations 3X Budget Same Hit and Miss
Productivity Scaffolding
2X greater Same
Baseline Same
19
Results JOB A Productivity increased for all contractors Piping productivity doubled Electrical productivity increased by 50% Scaffolding costs greatly reduced All contractors believed the increased planning resulted in improved productivity All contractors believed the Workface Planning was introduced too late on the project
Job B was converted to a cost reimbursable job and immediately implemented Workface Planning (Last Planner) to recover schedule.
20
Lean Behaviors
(5 fundamental concepts)
Specify Value
Pull
Perfection
Flow
21
Project Delivery
Value Coordination Decision making
22
Acknowledgement - CII
Going Lean The Construction Industry Institute surveyed Lean Construction Practitioners and found that there are five major principles, on which each team must focus:
Customer Focus
Culture/People
Workplace Organisation/Standardisation Waste Elimination
23
LEADERSHIP
24
25
26