Beruflich Dokumente
Kultur Dokumente
Contents
1 2 Sector round up and key data IPP News
3
4
5
6 7
All India (in MWs) Deficit % -13.3 ( -11.6) -15.1 (-12.3) -12.8(-11.8) -12.7( -13.6) -12.1(-12) -10.7(-14.6) -8.9(-11.7)
All India (in MUs) Deficit % -11.7 ( -10.9) -14.6 ( -11.2) -11.4(-8.8) -9.4(-8.4) -8.3(-8.9) -7.5(-10.9) -5.9(-9.6) -5.9(-9.4) -6.5(-8.9) -8.2(-10.7) -7.6(-10.7) -7.8(-9.7)
Capacity (mw)
1,32,329 1,71,926 39,597
Oct-10
Nov-10 Dec-10 Jan -11 Feb -11
118533(115432)
114234(109611) 117409(112505) 122470 (112505) 120536 (113505)
-9.4(-12.1)
-8.7(-12.2) -10.5(-12.5) -11.1(-12.5) -10.2(-12.5)
(in MWs)
(2009-10)
(feb 11)
(in MUs)
(feb-11)
Demand met Deficit %
State U.P Chttgh Punj Guj M.P Delhi A.P T.N Katka Mah
Peak Demand 10856 2819 9786 10406 7490 4502 12168 11,125 7942 19388
Peak met 8563 2703 7407 9515 6415 4408 10880 9813 6897 14664
Deficit % -21.1 -4.1 -24.3 -8.6 -14.4 -2.1 -10.6 -11.8 -13.2 -24
Peak Demand
Peak met 8951 2535 4910 9028 8068 3306 11232 10436 7618 15479
Deficit % -18.6 -6.7 -9.2 -6.6 -7.6 -3.3 -0.2 -8.3 -6.4 -20.7
State
11003 2719 5406 9671 8728 3418 11250 11377 8137 19530
A.P
T.N Katka Mah
78996
76293 45550 124936
73765
71568 42041 101512
-6.6
-6.2 -7.7 -18.7
6665
6589 4676
6595
6122 4459
-1.1
-7.1 -4.6
10982
9258
-15.7
Deficit of 10% 15 % :
(mn tns)
% annual dispatch 80
Power
Steel Cement
20 7
5 2
22 6
5 2
(2009)
0 (2010)
Day ahead Price (Rs/ Kwh) Average IEX Prices (Rs/ Kwh) 2.04 2.47 3.34 3.68
Bilateral rates (Wght. Avg ) IEX Traded volumes (mus) 833.5 1121 1205 1163
41
10
46
11
401
415
Financial Closure
NCC - Krishnapatnam project Hopes to achieve financial closure by May for the Rs 7,000-crore, 1,320-MW thermal power project it is setting up in partnership with Gayatri Projects at Krishnapatnam . May dilute stake to a private equity player , to meet the equity requirement for some projects. PFC and REC have agreed in principle to pump in Rs 3,200 crore, which is part of the Rs 5,200crore debt portion For the rest, NCC is negotiating with SBI and ICICI Bank. NCC picked up 55 per cent stake in Nelcast thermal project at Krishnapatnam for Rs 150 crore. The coal linkage for the project has been achieved with Coal India Ltd agreeing to re-allot the coal initially meant for 1320-MW thermal project at Sompeta.
Financial Closure
DB Power - Chhattisgarh DB is developing a 1,200-mw coal-fired mega power plant at an estimated cost of Rs 4600 crore. Debt portion amounts to 3500 crs It is raising 75% of the project cost as debt. The company hopes to sign the credit deal in the next two weeks, with SBI as the sole debt arranger and syndicator DB Power is close to raising Rs 2,625 crore to part-finance its mega power project in Chhattisgarh. The interest rate is likely to be 12 %. The firm is little tying up with eight financial institutions with LIC, Union Bank of India and L&T Infrastructure and Finance among them.
Other News
Ispat Industries may buy stake in JSW Energy's 300 MW Ratnagiri power project Ispat Industries is taking it's first steps towards backward integration to turnaround the company, as announced by JSW Steel at the time of the Ispat's acquisition in December, 2010. Sources said, Ispat is close to buying 26% stake in JSW Energy's 300 MW Ratnagiri power project for a little over Rs 100 crores. This will allow Ispat to use the electricity from the plant for captive consumption to produce steel at it's Khopoli plant. Sources say Ispat Industries may buy a 26% stake in an SPV (special purpose vehicle) which will own 300 MW of JSW Energy , the rest of the 74% will be held by JSW Energy. Ispat's cost of electricity is at Rs 6/unit and will be reduced to Rs 4.5-4.8/unit post synergies
JSW Energy and GVK may submit fresh bids for acquiring two coal assets put on the block by Hancock Coal JSW Energy and GVK Power and Infrastructure will have to submit fresh bids for acquiring two coal assets put on the block by Hancock Coal as the Australian firm now wants joint bids for the assets, sources said. Hancock Coal is selling Kevin's Corner and Alpha Coal, both located in Australia's Queensland province, as it expects good valuation for the assets. Some Chinese and Japanese power generation companies are also among the shortlisted bidders. The two mines have an estimated 7.9 billion tonnes of thermal coal, according to the company's website. Hancock is expected to finalise one buyer by the end of this month. Kevin's Corner and Alpha Coal are located close to the mine that Adani Enterprises acquired last year from Linc Energy. Some sources say that The valuation could go over $4 billion considering the asset size . Lanco Infra concludes buyout of 2 Australian coal firms Lanco Infratech Ltd has completed the buy out of two coal mining companies - Griffin Coal Mining Company Pty Ltd and Carpenter Mine Management Pty Ltd, that entails a total structured investment of A$730 million, including upfront payment of A$480 million. Lanco said that this is a significant part of the company strategy to secure fuel supplies for the company's expansion and new projects. The deal is structured in such a way that there is an upfront payment of about A$ 480 million. This will be followed by a payment of A$100 million after two years and A$ 150 million after four years. These companies have total estimated reserves of about 1.2 billion tonnes. And of this, about 700 million tones (MT) is extractable. At present, these mines produce about 4.5 MT per annum and this would be ramped up to 5.5 MT per annum soon. Initially, these mines would continue to supply coal to current buyers in China and Japan.
Governor's powers: Indiabulls challenges interpretation in HC Indiabulls, which is setting up a 2,640-MW thermal power station in Amravati district of Vidarbha, has challenged the prevalent interpretation of the Governor's powers to ensure equitable development of the state. The company is facing people's agitation against its project, mainly on the ground that the project will usurp water from Upper Wardha dam meant for farmers. A petition has been filed by the Backlog Removal Committee, a citizen's body, challenging the water supply. The committee has cited the Governor's directives to remove Vidarbha's backlog, which also includes irrigation backlog. The company said the Rs. 14,000-crore project would provide 1,200 MW power to the state at Rs. 3.26 per unit and it has already spent Rs. 1,250 crore on it. The government has assured to provide 87.6 million cubic metres of water to the project from the Upper Wardha dam. A Petitioner committee had argued last week that the Governor's directives are of constitutional nature and are, as such, binding on the state government. They said Vidarbha's irrigation backlog is 68.47 per cent and Amravati has a backlog of 70,000 hectares. They claimed that supply of water from the dam will reduce Vidarbha's irrigation by 23,219 hectares. They had also said that Prime Minister Manmohan Singh had announced a package for Vidarbha's crisis-ridden farmers, which included one for irrigation. So, supply of water meant for irrigation was also a violation of the PM's package. The company has now filed a separate petition, challenging the interpretation of the Governor's powers. "The Hon'ble Governor has no power or authority to issue directives in the nature and scope as is being interpreted. The petitioner submits that if at all it is a case that such directions have been issued by the Governor to the State Government and its functionaries, it will be a case where the Governor has been wrongly advised that he has powers to do so. It is submitted that the role of the Governor is only a supervisory role," the petition said.
1320*2
Coal
BGR
Rs 30 Crs
design, engineer, manufacture, supply and commission two Condensate Polishing Units (CPU)
Gujarat SEC
375
Gas
L&T
Rs.1100 / 3crs / MW
The engineering, procurement and construction contract includes design, supply, installation and commissioning of the complete power plant on a turnkey basis
Gujarat contemplating fines for delayed solar projects Gujarat Energy Development Agency said that there may be fines imposed in the projects where there were inordinate delays . Five of six projects that agreed to start operating by 2011 were delayed, including one by New Jersey-based Zeba Solar Inc. Gujarat state has led India's nascent solar industry, awarding licenses for 959 megawatts to developers seeking a foothold in a statesubsidized renewable energy market. The first 48.5 megawatts were required to start operating by Dec. 31 . How Gujarat deals with delayed projects sets a precedent for India's Solar Mission, a nationwide program that calls for 20,000 megawatts of capacity by 2022. Lanco Infratech Ltd, the Hyderabad-based developer that completed its 5-megawatt allotment on Dec. 20, is the only company that met the deadline. Five projects awarded to Azure Power of New Delhi, Zeba Solar, Germany's Dreisatz GmbH and MI MySolar24 Ltd. weren't completed. Azure, which built a 2-megawatt plant in Punjab, said the first phases of two plants were delayed to the end of March by unseasonably heavy rains. The company was supposed to have completed 3.5 megawatts by now, according to the list. The penalties for delays in beginning operations are 10,000 rupees ($222) a day per megawatt for the first 60 days and 15,000 rupees thereafter, according to the state power company
MoEF gives conditional nod to coal mining for Bedabahal project : The environment ministry has asked the power ministry to reduce coal mining area of a block attached to the 4,000 mw ultra mega power project at Bedabahal in Orissa by 10-15 %. Power ministry officials said the move would not affect the power project We have given conditional clearance to the coal block attached to Orissa ultra mega power project. If the power ministry agrees to protect at least 200 of 260 hectares forest land, we can give them forest clearance. Also, mining approval to the block would be granted only if the power ministry is willing to forego two more power projects proposed to be lighted up with mines in the vicinity, environment minister Jairam Ramesh said. The two other projects are proposed to be set up by NTPC and Orissa Power Generation Corporation . Dulanga and Manoharpur coal blocks are allocated these projects. Bedabahal project was allocated three coal blocks in IB valley coalfield in Orissa with a total of 886 million tonnes of reserves in 2006. The environment ministry had denied mining permission to Meenakshi coal block while the other two have been cleared. Power minister Sushilkumar Shinde had said that MoEF at a meeting with PMO had agreed to grant clearance to the Meenakshi block. However, there is no official communication in this regard .
CEA plans to finalize sites for additional UMPPs in Gujarat, Jharkhand by March-April 2011 While sites at Kutch, Junagarh and Dwarka and are being considered for the second UMPP in Gujarat, the second UMPP in Jharkhand is likely to be set up at either Deoghar or Tenughat.
10
PPA
Project VS Lignite Warora KSK Chhattisgarh PPA Long-term PPA: multiple captive industrial consumers; 13.5 MW merchant Long-term PPA: Viraj Profile and other group captive; 135 MW merchant Phase 1 : GIDC: 450 MW; CSEB: 135 (full term); 540 (20 yrs); merchant 675 MW Phase 2 : GUVNL: 1,010 MW, CSEB: 135 ( full-term) +540 (20 yrs); merchant 115 MW
Sai Regency
Sitapuram
Tamil Nadu
Andhra Pradesh
56
43
Gas
Coal
Arasmeta Long-term PPA: Lafarge, short-term PPA: CSEB Sai Regency - Long-term PPA: multiple captive industrial consumers Sitapuram Long-term PPA: Zuari and Sri Vishnu Cements Ltd.
Status
Capacity Location
Fuel
Note : Some of the industrial users could not off take the power and hence KSK is currently selling the operational capacity of Warora to MSEDCL
Total
6475
11
Demand Side methodology: 2009 10 Figures taken as base year Historical sales, unmet sales, T&D loss figures, GDP growth factor used to arrive at demand side projections. Rural electrification has also been considered 75 % weightage has been given to historical based CAGR figures and 25 % has been given to GDP based projections. GDP has been assumed to grow at 8.5 % T&D losses assumed to fall to 20% levels by 2016-17 For peak figures , load factor is taken based on historicals with worsening ratio of 2% Supply Side Methodology: 2009 -10 Taken as the base year ( including any short term purchases ) Capacity coming up and outside the state with PPA already signed have been considered . Case 1 bids for which the bids have been concluded have been considered.
12
For further enquiries on any of the news stories or Statistics please contact the following individuals from the Thermal Energy Business Development Team :
Adarsh Srinivas :
adarsh.srinivas@gmrgroup.in Mobile : +91 96862 00110 Ext : 3005 or
Vidhi Tyagi :
vidhi.tyagi@gmrgroup.in Mobile : +91 97313 01935 Ext : 2976
13