Beruflich Dokumente
Kultur Dokumente
November 2011
GENERATION
Hydel power generation had been given massive impetus during the Xth Plan following the decision of the Govt. to open up the sector for private and public participation. The Energy & Power Department has till date allotted 26 hydroelectric power projects with a total installed capacity of 5303.5 MW to various Independent Power Producers and National Hydroelectric Power Corporation. The details of allotted projects and developers are as listed: Sl. No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Name of Project Installed capacity (MW) 280 330 1200 520 510 500 210 300 99 96 Developer
Teesta Stage-I HEP Teeste Stage-II HEP Teesta Stage-III HEP Teesta Stage-IV HEP Teesta Stage-V HEP Teesta Stage-VI HEP Lachen HEP Panam HEP Lachung HEP Dikchu HEP
Himalayan Green Energy Pvt. Ltd. Him Urja Infra Pvt. Ltd. Teesta Urja Ltd. NHPC Ltd. NHPC Ltd. Lanco Energy Pvt. Ltd. NHPC Himgiri Hydro Energy Pvt. Ltd. Lachung Power Pvt. Ltd. Sneha Kinetic Power Projects Ltd. 1|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26.
Bimkyong HEP Bop HEP Rongnichu HEP Sada-Mangder HEP Chujachen HEP Bhasmey HEP Rangit-II HEP Rangit-III HEP Rangit-IV HEP Jorethang Loop HEP Ting Ting HEP Tashiding HEP Lethang HEP Kalaz Khola-I HEP Kalaz Khola-II HEP Rechu HEP
99 99 96 71 99 51 66 60 120 96 99 97 96 27.5 60 22
Teesta Power Pvt. Ltd. Chungthang Power Pvt. Ltd. Madhya Bharati Power Corp. Gati Infrastructure Ltd. Gati Infrastructure Ltd. Gati Infrastructure Ltd. Sikkim Hydro Ventures Ltd. NHPC Ltd. Jal Power Corporation Ltd. Dans Energy Pvt. Ltd. TT Energy Pvt. Ltd. Shiga Energy Pvt. Ltd. KHC Lethang Hydro Project Pvt. Ltd. Cosmic Infra Power Gen Pvt. Ltd. Pentacle Power Pvt. Ltd. Green Lake Power Development Ltd.
The projects allotted to Independent Power Producers (IPP) are on BOOT (Build Own Operate Transfer) arrangement for a period of 35 years and at the end of the 35th year the projects will be reverted back to the State free of cost in good operating condition by the developers. The projects allotted to NHPC Ltd. are in BOO (Build Own Operate) arrangement and the projects will remain with NHPC Ltd. The projects of installed capacity above 100 MW allotted to IPPs are being developed under Joint Venture with the State Government having 26% equity and in some projects below 100 MW the State Government will be infusing equity upto 11%. There is no equity participation in projects being developed by NHPC Ltd. As per the Memorandum of Understanding/Implementing Agreements signed with the Independent Power Producers, the State of Sikkim will be entitled to 12% free power from 1st to 15th year and 15% from 16th to 35th year from the commercial date of operation of the project. For all projects allotted to Independent Power Producers after 2008, the State will receive free power @ of 13% from 1 st to 15th year and 16% from 16th to 35th year from commercial operation date of the project. This is inclusive of the 1% Local Area Development allocation. The State will also receive Environment Cess @ 1.00 paisa per unit. The State will also earn dividends from the equity infused in the projects being developed in Joint Venture. The free power receivable from NHPC Ltd. is 12% only. Out of the total projects allotted, the following projects are all in advance stage of construction: 1. 2. 3. 4. 5. Teesta Stage-III HEP Teesta Stage-IV HEP Chujachen HEP Rangit-IV HEP Jorethang Loop HEP.
After obtaining all the mandatory and statutory clearances the construction works of the following projects have also started in earnest. 1. Dikchu HEP 2|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
2. 3. 4. 5.
The remaining projects are at various stages of survey, investigation, preparation of Detail Project Reports and obtaining the statutory clearances. These projects are expected to start constructions by 2012 and put into commercial operation within 2017. Projects under SPDC The following projects under SPDC have been commissioned during the XIth Plan period as indicated in the table below. Sl.No. 1 2 3 Name of HEP Manglay HEP (2 MW) Lachung Phase-II (3 MW) Rongli HEP (5 MW) Capacity addition Unit MW MW MW 5 2007-08 2008-09 5 2009-10 2010-11
The total installed hydro power generation capacity in the state at the end of the XIth Plan stands as follows: Power projects under Energy & Power Department Power projects under SPDC Power projects under NHPC TOTAL INSTALLED CAPACITY : : : 35 MW 10 MW 570 MW 615 MW
TRANSMISSION
All round development of the state meant wider demand for electricity across the state. Newer load centres were emerging as a result of developing townships and industrial areas. The existing load centres have also seen a massive increase in demand. It was therefore thrust upon Energy & Power Department to strategise for and envision higher capacity transmission lines of 132 KV voltage level and above which would enable transfer of higher quantum of power with minimal losses. New hydro projects being developed in the state also required setting up of high capacity transmission lines up to 400 KV level for evacuation of power out of the state to consumers in other energy deficit regions of the country as the local demand of about 100 MW is comparatively negligible. The Xth and XIth plan has seen development of 132 KV lines within the state both in the state and also in the central sector. In the state sector, with assistance from DONER, some vital works have been taken up during the XIth Plan. The Rangit-Gyalzing 132 KV S/C transmission line along with associated 66 KV line was completed during the year 2009-10. The 132/66 KV transformation capacity of 20 MVA has been added during the period. This has greatly enhanced the 3|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
transmission capacity and will benefit the south and west districts of the state tremendously. Another 132 KV line from LLHP to Sherathang near Nathula is under construction and upon its completion will play a pivotal role in development of the important border region. The Department has already taken up the work of the 132 KV Double Circuit Transmission Line from Chuzhachen to Rangpo and is on the verge of completion. The work was taken up at a cost of 31 crores . The money was arranged on loan by M/S Gati Infrastructures and the payback will be done from the 2% of the 99 MWs installed capacity, which has been agreed upon as the wheeling charges to be paid by the company to the Energy & Power Department. INTRA STATE TRANSMISSION: The Energy & Power Department has received approval from the Standing Committee on Power System Planning of the Eastern Region for the construction of the following Transmission systems in the State of Sikkim all of which have to be taken up in the XIIth Plan. 132 KV Double Circuit (Moose) Transmission Line from Chuzhachen HEP to Rangpo with LILO at Bhasmay of one circuit. 220 KV pooling Station at Tashiding and construction of 220 KV Twin Moose Transmission System from Tashiding to New Melli Switching Station. Construction of 132 KV Double Circuit (Moose) Transmission system from Mangan 132/400 KV Pooling Station to LLHP with LILO at Dikchu.
The concept note for the 220 KV KV pooling Station at Tashiding and construction of 220 KV Twin Moose Transmission System from Tashiding to New Melli Switching Station amounting to Rs.120 Crores has been placed before the NEC. The Survey works for the (1) 220 KV pooling Station at Tashiding and construction of 220 KV Twin Moose Transmission System from Tashiding to New Melli Switching Station and (2) Construction of 132 KV Double Circuit (Moose) Transmission system from Mangan 132/400 KV Pooling Station to LLHP with LILO at Dikchu are under way and the Detailed Project Reports are being Prepared. These are proposed to be funded either from CS schemes or bank loans and will be taken up in the XIIth Plan too.
4|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
REVENUE REALIZATION AND TARGET FROM SALE OF POWER WITHIN THE STATE Sl.No. 1. 2. 3. 4. 5. Year 2007-08 2008-09 2009-10 2010-11 2011-12(Target) Revenue Realization/Target in Rs.Crore 37.66 40.31 47.39 53.75 66.12
T&D AND AT&C LOSSES IN THE STATE Year 2007-08 2008-09 2009-10 2010-11 2011-12(Anticipated) T & D loss 30.64% 29.52% 29.06% 41.33% 36.60% AT&C loss 46.87% 46.81% 51.35% 50.06% 44.99%
The department has been taking up various sub-transmission works like upgradation, improvement and extension of distribution lines, conversion of overhead lines (both HT & LT) to underground cables in towns and other built-up areas, establishment of new DTs and extension of 66 KV networks. This exercise is targeted at improving the distribution system, decrease T&D losses in the system, enhance operational safety, improve aesthetics (in towns) and ensure adequate capacity to meet increasing demand thus preventing bottlenecks in distribution. Majority of such schemes are being taken up with assistance from NEC and DONER. Metering of consumers has also been accorded top priority. Capacity addition with respect to 66/11 KV sub-stations achieved during the XIth Plan period is as follows:
Sl.No. a 1 2 3 4 5 Name of 66/11 KV sub-station b 2 x 5 MVA at Mangan 2 x 10 MVA at Bulbuley 1 x 5 MVA at Rabongla 1 x 5 MVA at Pelling 2 x 5 MVA at Maltin Capacity addition Unit c MVA MVA MVA MVA MVA 10 20 10 2007-08 d 2008-09 e 10 2009-10 f 2010-11 g 2011-12 h
5|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
FLAGSHIP PROGRAMMES OF GOVT. OF INDIA IN THE POWER SECTOR BEING TAKEN UP DURING THE XITH PLAN
The National Electricity Policy, 2005, aims at achieving the following objectives:
Access to Electricity - Available for all households in next five years Availability of Power - Demand to be fully met by 2012. Energy and peaking shortages to be overcome and adequate spinning reserve to be available. Supply of Reliable and Quality Power of specified standards in an efficient manner and at reasonable rates. Per capita availability of electricity to be increased to over 1000 units by 2012. Minimum lifeline consumption of 1 unit/household/day as a merit good by year 2012. Financial Turnaround and Commercial Viability of Electricity Sector. Protection of consumers interests.
In order to achieve the stated objective of the National Electricity Policy, the Government of India has launched the following flagship programmes in the Power Sector and they are as follows: 1. Re-structured Accelerated Power Development and Reforms Programme(R-APDRP). 2. Rajiv Gandhi Gramin Vidyutikaran Yojana(RGGVY).
2) 3) 4)
6|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
5)
PFC / REC will be the prime lender for funding these schemes. In case of default by the utility the commercial loan of PFC / REC will be recovered first (being the primary Lender) before that of any other lender for funding such schemes.
Conversion of GoI Loan to Grant: 1) The entire amount of GoI loan (100%) for part A of the project shall be converted into grant after establishment of the required Base-Line data system within a stipulated time frame and duly verified by TPIEA. Up to 50% (90% for special category States) loan for Part-B projects shall be converted into grant in five equal tranches on achieving 15% AT&C loss in the project area duly verified by TPIEA on a sustainable basis for a period of five years. If the utility fails to achieve or sustain the 15% AT&C loss target in a particular year, that years tranche of conversion of loan to grant will be reduced in proportion to the shortfall in achieving 15% AT&C loss target from the starting AT&C loss figure.
2)
3)
objectives. Once this scheme is successfully implemented in Gangtok and Upper Tadong, the same can be replicated in other parts of the state. Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY)
Electrification of left out villages is being taken up by the government under the Rajiv Gandhi Grameen Vidyutikaran Yojana(RGGVY) at a total cost of Rs.148.91 crore. Basic facts about this programme.
Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) was launched in April-05 by merging all ongoing schemes.
7|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
Under the programme 90% grant is provided by Govt. of India and 10% as loan by REC to the State Governments. REC is the nodal agency for the programme. The RGGVY aims at:
Electrifying all villages and habitations as per new definition Providing access to electricity to all rural households Providing electricity Connection to Below Poverty Line (BPL) families free of charge Present status of work progress:
Coverage Sl.No. 1 1 2 1 2 Name of project/District 2 10th Plan Projects North West 11th Plan Projects South East 9 0 3062 4672 9 0 3062 3031 UEVs (nos.) 3 8 8 BPL H/Hs 4 747 2977 Actual Achievement so far UEVs (nos.) 5 8 8 BPL H/Hs 6 747 2977
As per milestones established earlier, this scheme was supposed to be completed by 31st March 2011. However, owing to site conditions, this date has been extended to 30-06-2011. Franchisee deployment that has been mandated by the Govt. of India upon completion of the scheme is being processed for govt. approval. GIS mapping containing spatial data of the entire spatial electrical network of EHV/HV/LT right up to village/taluka level as per the census data of villages and geo-referencing is being done too.
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
Progress achieved during the XIth Plan in terms of relevant Physical Indicators is as follows:
Sl.No. a b c d e f g h i j k l m n o
Indicators No. of Employees No. of Consumers No. of Employees per 1000 Consumers. Input Energy Billed Energy
Billing Efficiency f = e / d * 100
2007-08 3666 77700 47.18 375.22 260.25 69% 49.16 37.66 77% 199.37 31% 47% 40.7 102.5 100
2008-09 3688 78354 47.07 393.48 277.31 70% 53.41 40.31 75% 209.29 30% 47% 45.7 122.5 100
2009-10 3750 81996 45.73 512.12 363.30 71% 69.10 47.39 69% 249.16 29% 51% 45.7 132.5 120
2010-11 3657 82921 44.10 575.50 337.62 59% 63.14 53.75 85% 287.41 41% 50% 50.7 142.5 120
MU MU (%) (Rs., Crs) (Rs., Crs) (%) MU (%) (%) MW MVA MVA
9|Page
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
Harnessing hydro-power potential has been identified as a priority sector for the state during the XIIth Plan with other thrust areas being Capacity Building, Tourism and Agriculture. The vision of Energy & Power Department for the XIIth Plan (2012-17) aims to complement the collective effort and contribute towards achievement of these goals. The XIIth Plan will be a continuation of the process started in the previous plan periods all of which have been geared to achieve the objectives elucidated above.
GENERATION
Generation has been accorded top priority sector by the Government and features prominently in Vision of the Government of Sikkim for the XIIth Plan. In keeping with the aims and objectives of the government, the XIIth Plan will see a continuation of process set in motion during the Xth and XIth Plan. Apart from the projects allotted to private developers, the Government of Sikkim also envisages to speedily develop the mini and small hydro potential of the state through Sikkim Power Development Corporation Limited (SPDCL). To infuse professionalism, efficiency and to ramp up capital, the Government has restructured SPDCL by bringing in a strategic Joint Venture Partner M/s Athena Power Ltd. holding 49% equity participation. To ensure corporate efficiency and effectiveness, the management of SPDCL has been entrusted to M/s Athena Power Ltd. The speedy development of mini and small hydropower HEP will meet the daily growing power demands of the State apart from trading of the surplus power which will generate additional revenue for the State. SET BACKS AND CHALLANGES IN THE GENERATIONS SECTOR There have been some setbacks and challenges to the stated goal of the government to have in place an installed capacity of 5000 MW and annual revenue generation of Rs.1,500.00 crore by 10 | P a g e
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
the end of the year 2015. These have come about as a result of environmental clearance issues and also due to local sentiments which have been unfavourable towards some of the planned power projects. These issues were unforeseen and have been unexpected. The expected installed capacity by the end of year 2015 has been accordingly revised to 2792 MW in keeping with the ground realities. This figure will be hold true till the end of XIIth Plan. Revenue earnings from sale of power has now been estimated to be 454.26 crore by the end of XIIth Plan. Year-wise revenue projection till the end of XIIth Plan has been work out which may be seen in the table below:
REVENUE STATEMENT FOR THE FINANCIAL YEAR APRIL 2011 TO MARCH 2012 AND REVENUE FORECAST FOR THE XIITH PLAN PERIOD SL.NO. PERIOD REVENUE EARNINGS THROUGH POWER TRADING FROM ISGS SHARE AND 12% FREE POWER FROM TEESTA V AND RANGIT HEP IN RUPEES A 2,04,58,60,111.20 1,19,84,40,000.00 1,07,85,96,000.00 1,01,86,74,000.00 89,88,30,000.00 83,89,08,000.00 REVENUE EARNINGS FROM INTERNAL REVENUE COLLECTION OF THE POWER CONSUMED WITHIN THE STATE IN RUPEES REVENUE EARNINGS THROUGH POWER TRADING FROM THE SALE OF 50% OF THE FREE POWER FROM IPPS IN RUPEES B C 80,00,00,000.00 NIL 90,00,00,000.00 PAYMENTS TOWARDS PURCHASE OF POWER OF THE ISGS SHARE AND TRANSMISSION CHARGES I N RUPEES D 2,21,71,87,017.00 TOTAL REVENUE EARNINGS IN RUPEES
1 2 3 4 5 6
April 2011 to March 2012 April 2012 to March 2013 April 2013 to March 2014 April 2014 to March 2015 April 2015 to March 2016 April 2016 to March 2017
6,24,65,307.00 2,30,63,29,212.00
1,00,00,00,000.00 1,10,63,50,537.00 2,48,56,91,905.00 1,10,00,00,000.00 3,18,78,23,040.00 2,60,78,05,440.00 1,20,00,00,000.00 4,19,22,57,600.00 2,71,07,72,912.00 1,30,00,00,000.00 5,13,61,63,200.00 2,73,23,76,368.00
The Revenue Receipt for the FY April 2012 to March 2013 is expected to fall negative Rs.14.54 crore since there will be only a marginal addition of 11.7 MW. The Revenue Receipts are expected to increase substantially from the FY April 2013 to March 2014 to Rs. 69.92 crore and reach Rs. 454.26 crore in the FY April 2016 to March 2017. The expenditure towards transmission and allied charges will increase to above Rs. 46 crore by the year 2016. The total addition in Generation till 2016-17 will be 2792 MW (Revised projection).
RENOVATION, MODERNIZATION AND AUGMENTATION OF EXISTING POWER HOUSES The existing power houses under the department are in urgent need of repair and renovation. This has resulted in poor generation from the plants and almost of these power houses are now practically non-functional post the 18th September 2011 earthquake as most of the projects have suffered damages. It may be appreciated that setting up a new power project is an expensive proposition and demands considerable investment in terms of capital and time. It therefore makes sound economic 11 | P a g e
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
sense to revive the existing power houses and where feasible, augment the existing installed capacity. These can be achieved at a comparatively minimal cost. A preliminary study has been done by the department in this regards and it is expected that a sum of Rs. 150.00 crore will be required for the purpose. A list of existing power houses under the department may be seen below.
SL.NO. NAME OF PROJECT INSTALLED CAPACITY UNIT PRESENT GENERATION NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL NIL REMARKS
NORTH SIKKIM MEYONGCHUHEP 4 RABOMCHU HEP 3 LACHUNG STAGE-II HEP 0.2 EAST SIKKIM 1 LOWER LAGYAP HYDEL PROJECT 12 2 UPPER ROGNICHU HYDEL 8 PROJECT 3 JALI POWER HOUSE 2 4 ROGNICHU STAGE-II HEP 2 WEST SIKKIM 1 RIMBI-I 0.6 2 RIMBI-II 1 3 KALEZ 2 SOUTH SIKKIM 1 ROTHAK 0.2 TOTAL INSTALLED CAPACITY 35 ESTIMATED COST FOR RENOVATION, 150 CRORE AUGMENTATION AND MODERNISATION WORK 1 2 3
MW MW MW MW MW MW MW KW MW MW MW MW
damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake damaged due to earthquake
TRANSMISSION
PLANNING FOR THE INTRA STATE TRANSMISSION SYSTEM AND STATE LOAD DESPATCH CENTRE: INTRA STATE TRANSMISSION : The State of Sikkim will be seeing a total generation of 5000 MW coming online in the next five years. Although the majority of this generation will be evacuated by the CTU, i.e. PGCIL, it is extremely important that the State build and strengthen its own Intra State Transmission System for the evacuation of a substantial portion of this generation. This will be a crucial area of Revenue generation for the State of Sikkim since the transmission charges are not dependent on the actual generation and are based on the installed capacity. Other charges like short term and medium term open access charges will further add to the revenue collections of the State. The department plans to prioritize this during the XIIth Plan period. STATE LOAD DESPATCH CENTRE: Establishment of SLDC by all the States is mandated by the Indian Electricity Act 2003. Accordingly, SLDC in Sikkim was established in the year 2008. It is the apex body to ensure 12 | P a g e
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
integrated operation of Power System in the State of Sikkim. It monitors integrated grid operation for quality, security and reliability of Power supply in the State of Sikkim in coordination with Eastern regional Load Dispatch Centre. It exercises supervision and control over the intra-state transmission system & keeps accounts of the quality of electricity transmitted through the state grid. It is responsible for carrying out real time operations of grid control and dispatch of electricity within the State of Sikkim through secure and economic operation of the state grid in accordance with the grid standards and grid code. Further, it is responsible for optimum scheduling and dispatch of electricity within the State of Sikkim. All IPPS evacuating power through the Intra State Transmission System will have their power scheduled by the SLDC and SLDC shall keep accounts of the quantity of the power transmitted. In order to establish a reliable communication network, the Department proposes to establish an optical fibre network through our Transmission network on OPGW wires. The State Load Despatch Centre may levy and collect such fee and charges from the generating companies and licensees engaged in intra-State transmission of electricity as may be specified by the State Commission as per the Indian Electricity Act 2003 and as such the establishment will be self sustainable and provide a means of further revenue generation for the state. The Optical fibre network will provide an additional means of revenue generation for the State by leasing out the spare fibres to the telecom companies.
Power
Development
and
Reforms
As introduced in the XIth Plan review, R-APDRP scheme, PART-A for which has already been initiated in two towns classified as Gangtok and Upper Tadong, will be the agent of change along with various other programmes of the government. It is principally through this scheme that different objectives of the department like reduction of AT&C loss to 15%, improving operational efficiency and service delivery through use of newer technologies, energy audit, etc. is expected to be achieved. The XIIth Plan will see implementation and completion of R-APDRP work in Gangtok and Upper Tadong at the end of which it is endeavoured to reduce the AT&C loss within the project area to 15% and below. The R-APDRP under the present policy of Govt. of India, is approved only for those townships having population of more than 5000 (for special category states). The department through the State Govt. has requested the Central Govt. to relax this condition for a hilly state like 13 | P a g e
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
Sikkim so that many other towns in the State can be covered under this scheme. This is under active consideration and it is expected that this condition will be relaxed so that the department can take up this work in all major towns of the State. This is expected to drastically reduce the AT&C losses of the state and along with other programmes, the AT&C losses of the state of Sikkim will be curtailed to sub 15% level from the present figure of 50.06% (2010-11 level).
14 | P a g e
Approach Paper for 12th Five Year Plan - Energy & Power Department, Govt. of Sikkim.
November 2011
Summary of outlay proposed under State Plan for XIIth Plan(2012-17) for Energy & Power Department
SL.NO. I 1 2 3 4 5 6 A II 1 2 3 4 5 B C
PARTICULAR CONTINUING SCHEMES OF XITH PLAN Miscellaneous Distribution Scheme Tribal Sub-Plan Scheduled Caste Component Plan APDRP Land compensation against ongoing schemes Counter-funding for Central Schemes Sub-Total-I NEW SCHEMES FOR XIITH PLAN Schemes sanctioned during Sikkim Brahaman of Hon'ble Chief Minsiter Revonation, modernization and augmentation of existing power houses Counter-funding for schemes proposed to be posed to DONER and NEC Miscellaneous Distribution Scheme(MDS) TSP/SCSP Sub-Total-II DIRECTION AND ADMINISTRATION FOR XIITH PLAN
AMOUNT (in Rs.Lakh) 1,250.00 460.00 15.00 2,365.00 259.27 5,894.34 10,243.61 23,100.00 15,000.00 4,003.33 5,250.00 19,200.00 66,553.33 23,117.00
99,913.94
THE END
15 | P a g e