Sie sind auf Seite 1von 24

Contents

1 Precautions ..............................................................................................................................................2
2 Tools for Installation .............................................................................................................................3
3 Outline and Structure.............................................................................................................................4
4 Installing the Lifting eyes.....................................................................................................................5
5 Adjust the Position of the MDF (optional)........................................................................................6
6 Installing the Cabinet on a Concrete Pedestal (reshell)..................................................................7
6.1 Plan Space for the cabinet..............................................................................................................................................7
6.2 Constructing the concrete pedestal................................................................................................................................8
6.3 Installing the Cabinet Base Frame.................................................................................................................................9
6.4 Installing the Passive Cabinet......................................................................................................................................10
6.5 Fixing the CCC rack(optional).....................................................................................................................................11
6.6 Installing the Active Cabinet.......................................................................................................................................12
6.7 Installing the Waterproof Module................................................................................................................................13

7 Routing Cables .....................................................................................................................................14


7.1 Connecting AC Power Cables and Ground Cable.......................................................................................................14
7.2 Connecting Subscriber Cables.....................................................................................................................................15
7.3 Connecting Optical Cable and Optical Fibers..............................................................................................................16

8 Installing the accessories of the Passive Cabinet...........................................................................17


8.1 Installing the Maintenance Socket...............................................................................................................................17
8.2 Installing the Maintenance Illuminator........................................................................................................................18
8.3 Installing the Door Status Sensor.................................................................................................................................19

9 Installing Batteries................................................................................................................................20
10 Checking the Cabinet Installation ..................................................................................................21
11 Powering On the Device....................................................................................................................22
12 Sealing the Cabinet.............................................................................................................................23
13 MDF Label............................................................................................................................................24

Precautions

NOTE

This document aims to provide simple and distinctive guidelines for hardware installation.
This document does not describe operations for the pre-delivery installation of the internal cables and so on. Instead, this document
describers only the operations for on-site installation.

Electrostatic Discharge
Before touching the device, or holding the boards and IC chips, wear the ESD gloves or the ESD wrist strap to prevent the
electrostatic discharge of the human body from damaging the sensitive components. Ensure that the other end of the ESD
wrist strap is well grounded.

Bundling cables
The distance between cable ties or fiber binding straps inside the cabinet should be within 250 mm. (For subscriber
cablethe distance is 200 mm. )

Affixing labels / tags


l

After routing the cable, affix the label or fasten the tag to the cable, and 20 mm away from the connector.

After the label for the signal cable is affixed to the signal cable, the rectangular text area of the label should face
rightwards or downwards.

After the identification plate for the power cable is affixed to the power cable, the text area of the plate should face
rightwards or downwards. Ensure that the side affixed with the label faces outwards.

Using the desiccant


After removing the packing case of the cabinet on the site, take out the desiccant packages from the corresponding paper
bag (Note: Do not tear the own packages of the desiccant). Then, put the desiccant packages at proper places of the cabinet.
After powering on the cabinet, the desiccant packages must be removed and disposed of as an industrial waste.

Copyright Huawei Technologies Co., Ltd. 2011. All rights reserved.

Tools for Installation

Before you begin, get the following tools ready.

Tape measure

Philips screwdriver

Flathead screwdriver

Adjustable wrench

Socket wrench

Percussion drill

Claw hammer

Diagonal pliers

Hydraulic crimper

Cable cutter

Network cable crimping pliers

Wire stripper

ESD wrist strap

Wire cutter

Multimeter

Rubber hammer

Outline and Structure

Installing the Lifting eyes

Adjust the Position of the MDF (optional)

Installing the Cabinet on a Concrete Pedestal (reshell)

6.1 Plan Space for the cabinet

Installing the Cabinet on a Concrete Pedestal (reshell)

6.2 Constructing the concrete pedestal

Installing the Cabinet on a Concrete Pedestal (reshell)

6.3 Installing the Cabinet Base Frame

Installing the Cabinet on a Concrete Pedestal (reshell)

6.4 Installing the Passive Cabinet

10

Installing the Cabinet on a Concrete Pedestal (reshell)

6.5 Fixing the CCC rack(optional)

11

Installing the Cabinet on a Concrete Pedestal (reshell)

6.6 Installing the Active Cabinet

12

Installing the Cabinet on a Concrete Pedestal (reshell)

6.7 Installing the Waterproof Module

13

Routing Cables

7.1 Connecting AC Power Cables and Ground Cable

14

Routing Cables

7.2 Connecting Subscriber Cables

15

Routing Cables

7.3 Connecting Optical Cable and Optical Fibers

16

Installing the accessories of the Passive Cabinet

8.1 Installing the Maintenance Socket

17

Installing the accessories of the Passive Cabinet

8.2 Installing the Maintenance Illuminator

18

Installing the accessories of the Passive Cabinet

8.3 Installing the Door Status Sensor

19

Installing Batteries

20

Checking the Cabinet Installation

No.

Requirement

Method

The cabinet components are installed correctly. The cabinet door shall have no distortion.
The boards can be plugged and unplugged without difficulty. Installation of self-made
components shall comply with the requirements.

Observe and try out

The cabinet is installed correctly without flake-off or damage.

Observe

The cabinet is installed reliably, satisfying the quakeproof requirements in the project
file.

Observe

The cabinet installation site complies with the project file.

Observe the
installation site

All cable apertures are sealed well, including apertures for power cables, ground cable,
optical cable, and external subscriber cables.

Observe

The external positive lead and positive lead of battery are correctly and reliably
connected to the power system.

Test with a
multimeter

The protective covers on the battery terminals are intact.

Observe

None of the cables has damage, fracture, or joint on the cable.

Observe

The power cable and ground cable adopt a whole segment of copper core. The cable has
no joint in the middle or scratch on the skin.

Observe

10

The cross sectional area of the power cable and that of the ground cable comply with the
project file, satisfying the power distribution requirements of the cabinet.

Observe

11

Optical fiber headers and board optical ports to be used are protected with protective
caps. If necessary, clean them in compliance with Huawei regulations.

Observe

12

Cables outside the cabinet are buried underground if possible. If they are routed through
the cabling rack, the lightning proof measures shall be adopted.

Observe

21

Powering On the Device

22

Sealing the Cabinet

23

MDF Label