Authors Name:
Harvinder Singh Saund HOD (Design and Development) S.K.G Engineering Company. Ludhiana. Satbir Singh Production Engineer G.S Auto Limited Ludhiana Mohan Lal Bhawra Dy.G.M (Quality Assurance) S.K.G Engineering Company. Ludhiana.
Submitted to: PTUs Gian Jyoti School of TQM & Entrepreneurship, Mohali (Punjab) Date of Submission: 31May 2010 Project Guide: Mr. Naresh Chawla
1
TABLE OF CONTENTS
S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Description Title page Companys Introduction Summary of Project Problem Statement, Project Mission & Project Plan Team member & Project History Project Design and Methodology Flow Diagram Brain Storming Cause and effect diagram Data collection & Analysis and Pareto analysis Remedial Journey Resistance to change Counter Measure Benefits Control for Holding the gains Page No.
1 2 6 7 9 11 12 13 14 15 19 25 26 32 33
JOURNEY SO FAR
1984 Founded by the Sonis and became a supplier to the After Market in the US. 1990 Entered the European After Market Largest supplier to the EU and US markets by volume and value Entered the European OEM market as a Tier II Supplier Commenced sales to OEMS in India as a Tier I supplier
1996 2000
2001 Uniparts India Ltd. was awarded an All India Certificate Of Merit For Outstanding Export Performance. Uniparts India Ltd. received the Highest Exporter Award in the North India Region. 2002 Commenced sales to OEMS in US as a Tier I supplier Validated by OEMs like John Deere, CNH, Kubota, Yanmar.
2003 Uniparts India Ltd. received an All India Award for Highest Exports. 2005 Commenced sales to OEMS in JAPAN as a Tier I supplier Partnered with Olsen Engg. Uniparts India Ltd. received an All India Award for Top Exporter in the North India Region.
2006 Uniparts India Ltd. received an All India Award for Highest Growth in Exports 2007 Partnered with KRAMP BV & entered hydraulic space in Europe Inauguration of US warehouse in Augusta (GA) Acquisition of balance stake Olsen Engg. Tier I supplies from Uniparts Kavee BV to European OEMs Inauguration Uniparts India Vizag Operation UNIPARTS India - VIZAG is a new Greenfield Project. The unit is spread over 30 acres with 18,000 Sq M of manufacturing under roof. The unit is next to one of India's biggest ports and in the same city as one of India's and The Group's biggest steel supplier. 4
2009
SKG Engineering Company Ludhiana is a manufacturing unit of UNIPARTS India Ltd. SKG Engineering Company was established in 1989 primarily to meet growing demand of group units and export market for supply of raw and machined forging, components based on forging and farm hardware products.
PRODUCT RANGE:
Competencies
Forging Fabrications Surface Finish Quality & Testing Machining Heat Treatment Logistics Design & Validation
SUMMARY: This project was initiated in November 2009. The objective was to reduce the Sale loss of Eyebolts On the basis of six month (April 2009-Oct. 2009) data it was found that Excess no. of setting due to complicated process i.e 3 times Forging & Trimming and excess movement of material within the section & Intersection movement results in the delivery failure. It has resulted in Sale loss of 8.51 Lac during this period which is equivalent to loss of12.76 lac/annum against the Budgeted sale 54.58 lac. Target was to improve the delivery compliance from 76% to 95% by 31st May 2009, resulting to minimize the sale loss to 2.73lac/annum. A brain storming session is conducted to find the possible causes for sale loss. In order to find out the vital few causes, Causes & Effect Study conducted & all causes (identified during brain storming) were rated through Nominal Group Technique. After finding out the Vital few Causes, necessary corrective /preventive actions were taken. Simultaneously feedback was also taken during implementation of corrective / preventive actions, which also helps in designing the improvement plan. After implementation of improvement plan data of were collected and again feed back was taken, which shows the improvement. In the last, necessary steps were implemented to hold the achieved gain.
PROBLEM STATEMENT:
Delivery compliance for Eyebolt product group is 76% during April-09 to Nov-09. It has resulted in Sale loss of 8.51 Lac during this period which is equivalent to loss of 12.76 lac /annum against the Budgeted sale 54.58 lac.
Ordered Qty
15412 9470 8528 8858 13058 16543 17537 14661
Dispatched Qty
11758 4188 10354 9471 3458 13494 5805 20306
Pendency
3654 8936 7110 6497 16097 19146 30878 25233
TOTAL
104067
78834
6.09 2.55 2.11 0.86 Apr-09 May-09 Jun-09 0.80 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 3.87 2.35
Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 SALE VALUE (In Lac) 9.25 0.86 2.11 2.55 0.80 3.87 2.35 6.09 MONTH
Current Average SALE :3.48 Lac Target Average SALE :4.55 Lac
MISSION STATEMENT:
To improve the delivery compliance from 76% to 95% by 31st May 2010. It will minimize the sale loss to 2.73 lac/annum
PROJECT PLANNING:
Project Start Date: Project Finish Date: Meeting Frequency: Methodology: Project Undertaken At: Current Status:
15.01.10 15.04.10 Twice in a week (Tuesday & Friday, 5pm-6pm) Juran Quality Improvement SKG Engineering Company, Ldh Completed
TEAM MEMBERS
S.No.
1
NAME
Harvinder Singh Saund Mohan Lal Bhawra Satbir Singh
SID NO.
0707-0044
COMPANY NAME
SKG Engg. Company, Ludhiana SKG Engg. Company, Ludhiana GS Auto, Ludhiana
ROLE Coordinator
2 3
0707-0076 0707-0107
PROJECT HISTORY:
It was noticed that there was excess no of setting & excess movement of material with in the section & Intersection movement leads to delivery failure. It was decided to first analyze the reasons for excess no of setting. This was followed by dissection of the process to various steps of this project in order to follow a well defined & stream lined working during whole journey of the project
PROJECT PLAN:
1. Project Goal
Develop the team of people, to align them with the system & make them understand & operative by creating awareness among themselves. To visualize the effect of the wastages due to Multiple settings, material movement in plant, identify the root cause & eliminate these wastage through improvement activity. To improve the productivity of Forge shop. To improve customer satisfaction level (Internal & External). To update the existing Systematic requirements: Data preparation and analysis & utilization.
2. Success Measures- Improved customer satisfaction:We measured our success by improved customer (Internal) satisfaction. This has measured through customer (Internal) feedback before and after the project.
10
Step 1 Flow Diagram Step 2 Brainstorming Step 3 Cause and Effect Diagram Step 4 Data collection and analysis Step 5 Pareto Analysis Step 6 Implementation of remedies Step 7 Resistance to Change & Countermeasure Step 8 Holding the gains
11
Brainstorming sessions with, production dept. & team members were carried out. The probable causes identified during these sessions are as follows:-
1. Excess lead time. 2. Inadequate environmental condition. 3. Excess movement of material. 4. Excess no. of settings. 5. Communication gap. 6. High Inter Section material movement. 7. No product owner. 8. Frequent change in schedule. 9. Complicated process. 10. Product capacity not updated. 11. Ineffective Supervision. 12. Improper follow up. 13. High inspection time. 14. More setting time. 15. Unskilled operator.
13
Method
Improper Follow up
Higher inspection time No production owner Low utilization of resources. Multiple setting required
Sale Loss
Non availability of raw material Excess Movement of material
High tooling breakdown
Lack of skill
In balanced line
S.NO.
1 2 3 4 5 6 7 8 9 10
Manufacturing Operation
Draw & Cutting Facing & Chamfering Stamping Forging & Trimming (3Times) Drilling & Counter sunking Normalizing Shot Blasting Machining Centre less Grinding Threading
Production / Day
2000 2000 2000 394 750 750 1000 750 800 750
15
16
S.N O. 1 2 3 4 5 6
ROOT CAUSE Communica tion Gap Poor Environmen tal Condition High Inspection Time Excess No. Of Setting Higher Tooling Break Down Excess Movement Of Material
VINOD CHOP RA 4 5 7 8 5 7
M.S NE GI 3 5 6 9 5 7
RAME SH SINGH 4 4 6 9 3 7
MOH AN SING H 4 4 8 9 5 6
VIVE K 4 5 7 9 6 8
KULWIND ER 4 6 8 9 3 7
SUKHD EV 3 6 7 8 5 6
JASBI R SING H 4 6 9 9 6 7
PARVE EN 7 6 9 9 3 4
LAL SING H 6 4 6 9 5 6
TOTA L 43 51 73 88 46 65
17
DATA ANALYSIS
S.NO. REASON OF SALE LOSS
RATING % CONTRIBUTION CUMMULATION
1 2 3 4 5 6
Excess No. Of Setting Higher Inspection Time Excess Movement Of Material Inadequate Environmental Condition High Tooling Break Down Communication Gap
88 73 65 51 46 43
1 0 0 .0 0 9 0 .0 0 8 0 .0 0 7 0 .0 0
P A R E T O C H A R T F O R S A L E L O S S 1 0 0 .0 0
8 8 .2 5
1 0 0 .0 0 9 0 .0 0 8 0 .0 0
Vital Few
6 1 .7 5
7 5 .6 8
7 0 .0 0
% CONTRIBUTION
6 0 .0 0 5 0 .0 0 4 0 .0 0 3 0 .0 0 2 0 .0 0 1 0 .0 0 0 .0 0 2 4 .0 4 2 4 .0 4 1 9 .9 5 1 7 .7 6 4 3 .9 9
Useful Many
6 0 .0 0 5 0 .0 0 4 0 .0 0 3 0 .0 0
1 3 .9 3
1 2 .5 7
1 1 .7 5
2 0 .0 0 1 0 .0 0 0 .0 0
REASO N
18
CUMMULATION
REMEDIAL JOURNEY
Forging of eyebolts includes a series of sequential operations, pre forging and trimming done three time each . The dissection of process helps us to make measurements at intermediate steps in the process to discover at which step the time is taken more.
S.NO.
CAUSE
WHY
Process Limitation ( Forging of Eye bolt completed in 6setting )
COUNTER MEASURE
Technology Up gradation Proper Tooling Design
Inadequate Tooling
Unskilled Die Setter High no. of process ( Forging of Eye bolt completed in 6setting ) 2 Higher Inspection Time More Intersection Movement Result more Stage inspection Process Limitation at Forging 3 Excess Movement Of Material Inadequate Lay-out
Training Mechanism Technology Up gradation Re-Layout in forge shop Technology Up gradation Redesign Layout for Machining cell
19
The Metal Gathering Machines or Resistance Heating and Upsetting Machines are designed for use in drop forging and valve industry. Generally, upsetting can be applied to almost any application calling for the gathering of stock material to enable a component to be provided with the minimum of press works. The perfect "grain-flow" obtained together with extremely short heating times, the upsetting machine is ideal for a variety of jobs and almost in all cases no external or additional heat is required for the subsequent forging operations
WORKING The work piece is firmly gripped in hydraulically operated sliding contact dies. One end of the rod rests on the upset slide operated from a hydraulic cylinder; the top end of the rod, which is to be upset rests against an anvil whose movement is controlled by an adjustable hydraulic flow control valve. The Transformer output is connected between the clamping dies and the anvil. On application of the ram pressure and high amperage current, the length of the work piece between the clamping dies and anvil heats up and gathers. Simultaneously, the rod is slowly pushed through the clamping dies and the anvil is retracted gradually until the required shape of bulb is formed. CONVENTIONAL ROUTE METAL GATHERING ROUTE
Stages of Forging on Conventional Route 1st Pre Forging , 2nd Forging & Final Forging
20
Simultaneous heating and forming in one machine. No longitudinal flash is formed such as is unavoidable in a split-die mechanical up settler. No waste of heating energy or material. Outside of the upset volume can be precisely controlled to allow subsequent, "flash less" forging in closed dies. Always ready for instant use, no warm up period. Energy efficient, about 0.35 - 0.40 kwh / kg. Minimal scaling because of simultaneous heating and gathering. Improved die life in subsequent forging operations. No environmental pollution by emission of heat, fume or exhaust gas. Free upsets can be finish forged without re-heating and so save time and energy. Consistent heating temperature through the use of thyristor control. Optimal grain flow and fault free surface. The unheated bar length remains unchanged.
21
FINANCIAL BACKUP
Metal Gathering in place of Forging to reduce the excess no. of setting. Process Cost Reduction: Eyebolt (that can be produced through Metal Gathering) Average cost of Forging through Conventional Route Average cost of Forging through Metal Gathering Difference in Cost Saving Input Reduction: Eyebolts with body diameter 15mm Eyebolts with body diameter 32mm Average Reduction in Weight Average Raw Material Rate Saving TOTAL SAVING PAY BACK PERIOD Investment on Two Machines Installation Expenses Total Cost Incurred Pay Back Period (In Years) 0.010 Kg 0.063 Kg 0.03645 Kg 38 193283.07 768208.47
727787 25000 752787 Cost of Project / Annual Saving 752787 / 768208.47 = 0.98
Reduction in Lead Time: Based on Cycle time study for 10 different type of eyebolts constituting 95945 nos. No. of Shifts required through Conventional Route: 250Ton Screw Press: 125Ton Screw Press: Total Shifts: No. of Shifts required through Metal Gathering Route: Saving in No. of Shifts: Spare capacity can be utilized for other valuable products 79.56 Shifts 61.98 Shifts 141.54 Shifts 65.45 Shifts 76.09 Shifts
22
Amendment in layout of Forging Shop after addition of Metal Gathering has resulted in reduction in material movement by distance of 39.30 Metre
23
Total path for material movement (As is): Total path for material movement (After implementation): Total Saving in distance covered:
Amendment in layout of Forging Shop & Machining cell has resulted in reduction in material movement by distance of 101.02 Metre
BENEFITS: Reduce the excess movement of material. Reduce WIP. Improved Efficiency. Save Manpower 24
25
TRAINING MECHANISM
Deptt. :- Forging
Sr.No.
Name of Employee
Expected Benefits
Faculty (In House / On the Job Training / Outside Agency) Mohan Singh Sri Krishan
Yog Raj
203
2 3 4 5 6 7 8 9 10 11 12 13 14 15
Suraj Bhan Guru Dev Fagu Manjhi Ram Ratan Kuldeep Singh Dharminder Singh Dinesh Dubay Adit Kumar Vinod Kumar Shankar Dayal Bal Ram Madan Chaudary Vijay Shankar Ram Partap
220 222 213 206 208 204 217 226 207 210 214 218 223 224
Date :- 25.02.10
Issue Date :-
:-
Name
Machine Location :- Forge Shop
Check Points OK / Investigation
Sign
S. No. 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 2.0 2.1 2.2 2.3 3.0 3.1 3.2 Monthly Routine by Maintenance Tighten all nuts & bolts. Check the wheel check nut for Looseness. Check the lead screw for any play. Check for any play between jib and slide. Check the motor IR and load current. Check that foundation nuts are not loose. Check the electrical terminals for any loose connections. Check the condition of starter, coil and o/l relay. Half yearly Routine by Maintenance Repeat all monthly checks. Check the bushes for wear & tear. Check the shaft bearings. Yearly Routine by Maintenance Repeat all Half yearly checks. Check the condition of slides for any play.
Not OK.
S.NO. Ref
Possible Cause
Action
No. 1 2 3 4 5 6 7 8 9 10 11 12
Name of Employee Yog Raj Suraj Bhan Guru Dev Fagu Manjhi Ram Ratan Kuldeep Singh Dharminder Singh Dinesh Dubay Adit Kumar Vinod Kumar Shankar Dayal Bal Ram
T. No. 203 220 222 213 206 208 204 217 226 207 210 214
Remarks
1) Operation at Metal Gathering 2) Integration of Forging & Trimming Operation with Metal Gathering.
TRE N D OF E YE B OLT S AL E 1 0 .0 0 8 .0 0 6 .0 0 4 .0 0 2 .0 0 0 .0 0 9 .2 5 6 .0 9 2 .1 1 0 .8 6 2 .5 5 0 .8 0 3 .8 7 2 .3 5
Ap r Ma -09 y Jun-09 Ju 09 Au l-09 g Se -09 pOc 09 t No -09 v De -09 c Jan-09 Fe -10 b Ma -10 r-1 0
S A L E V A L U E (9In.2L50 c ) 62 . 1 12 .5 50 .8 03 .8 72 . 3 56 .0 9 a .8 MON TH
Month
Ordered Qty
Dispatched Qty
Cumulative Order Qty 15412 24882 33410 42268 55326 71869 89406 104067 115398 126999 141748 155748
Cumulative Dispatched Qty 11758 15946 26300 35771 39229 52723 58528 78834 94334 107927 124844 146500
Pendency
Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 TOTAL
15412 9470 8528 8858 13058 16543 17537 14661 11331 11601 14749 14000 155748
11758 4188 10354 9471 3458 13494 5805 20306 15500 13593 16917 21656 146500
3654 8936 7110 6497 16097 19146 30878 25233 21064 19072 16904 9248
TREND OF EYEBOLT SALE SALE VALUE (IN LACS) 16.00 14.00 12.00 10.00 8.00 6.00 4.00 2.00 0.00
12.37
13.95 10.80
6.09
6.58
Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar09 09 09 09 09 09 09 09 09 10 10 10 Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- Dec- Jan- Feb- Mar09 09 09 09 09 09 09 09 09 10 10 10
SALE VALUE (In Lac) 9.25 0.86 2.11 2.55 0.80 3.87 2.35 6.09 12.37 10.80 6.58 13.95
MONTH
Sale of 71.58 lac during 2009-2010 has been done against the budgeted 54.58 lac
30
9854.3
348491.9
31
TANGIBLE BENIFITS:
Top line is increased by 17 Lac. Sale of 71.58 lac has been done against the budgeted 54.58 lac during 2009-10 Delivery compliance is increased to 94.1% against 76% Reduction in material movement by distance of 101.02 Metre Saving of 76.09 Shifts, Spare capacity can be utilized for other valuable products
INTANGIBLE BENIFITS:
Process Cost Reduction Input Cost Reduction Morale of employee is enhanced Reduced Inventory Quick change over time Learning of Project by Project approach of Improvement
32
OTHER CONTROLS FOR HOLDING THE GAINS:To hold the gains of improvement following has been planned as regular feature in future: Control during operations will be done through use of feedback loop Actual performance Vs. Standard performance and action on the variation observed. Initially analysis will be reviewed in Monthly Operational Review Meeting (ORM) & later on in Management Review Meeting (MRM). Conducting frequent training programs for Workers, Supervisors & Staff Members. Conduct monthly meeting with Production, Quality & Tool Room Monthly trend will be displayed on company display board.
33
The whole project revealed that regular follow-up / interaction / awareness / training programs help in achieving the set target. This whole project was concentrated on increasing the awareness on new technology & material movement activity in workers / supervisors so they start taking it as the opportunity for improvement.
ACKNOWLEDGEMENTS
For the successful completion of the project, we are thankful to,
Our guide, Mr. Naresh Chawla for providing necessary advice & guidelines during the entire journey of the project. Management of SKG Engineering Company for giving us the permission for organizing project, training & awareness programs. Engineering, NPD, Tool Room, Production & Quality staff for the implementation of required changes.
34