Introduction
One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout the organization. A myriad of details must be considered in planning how to coordinate all these activities, in developing a realistic schedule, and then in monitoring the progress of the project. Fortunately, two closely related operations research techniques, PERT (program evaluation and review technique) and CPM (critical path method), are available to assist the project manager in carrying out these responsibilities.1 The Program (or Project) Evaluation and Review Technique, commonly abbreviated PERT, is a statistical tool, used in project management, that is designed to analyze and represent the tasks involved in completing a given project. PERT is a method to analyze the involved tasks in completing a given project, especially the time needed to complete each task, and to identify the minimum time needed to complete the total project. The concept of network-based cost control offers to project management a basically sound and powerful way of relating expenditures to the work done, a way of reporting what management paid for what it got. Basically, CPM (Critical Path Method) and PERT (Programme Evaluation Review Technique) are project management techniques, which have been created out of the need of Western industrial and military establishments to plan, schedule and control complex projects.2
1 2
Pinkerton, William: Project Managment: Achieving Project Bottom-Line Success, p. 22, 2003. http://www.interventions.org/pertcpm.html
Moder, J. J., Phillips C. R., Davis E. W.: Project management with CPM, PERT and Precedence Diagramming, p.138, 1983. 4 http://www.netmba.com/operations/project/pert/
Optimistic time - generally the shortest time in which the activity can be completed. It is common practice to specify optimistic times to be three standard deviations from the mean so that there is approximately a 1% chance that the activity will be completed within the optimistic time.
Most likely time - the completion time having the highest probability. Note that this time is different from the expected time.
Pessimistic time - the longest time that an activity might require. Three standard deviations from the mean is commonly used for the pessimistic time. PERT assumes a beta probability distribution for the time estimates. For a beta
distribution, the expected time for each activity can be approximated using the following weighted average: Expected time = ( Optimistic + 4 x Most likely + Pessimistic ) / 6 This expected time may be displayed on the network diagram. To calculate the variance for each activity completion time, if three standard deviation times were selected for the optimistic and pessimistic times, then there are six standard deviations between them, so the variance is given by: [ ( Pessimistic - Optimistic ) / 6 ]2
5. Determine the Critical Path The critical path is determined by adding the times for the activities in each sequence and determining the longest path in the project. The critical path determines the total calendar time required for the project. If activities outside the critical path speed up or slow down (within limits), the total project time does not change. The amount of time that a non-critical path activity can be delayed without delaying the project is referred to as slack time. If the critical path is not immediately obvious, it may be helpful to determine the following four quantities for each activity:
ES - Earliest Start time EF - Earliest Finish time LS - Latest Start time LF - Latest Finish time Since the critical path determines the completion date of the project, the project can be
accelerated by adding the resources required to decrease the time for the activities in the critical path. Such a shortening of the project sometimes is referred to as project crashing. 6. Update as Project Progresses Make adjustments in the PERT chart as the project progresses. As the project unfolds, the estimated times can be replaced with actual times. In cases where there are delays, additional resources may be needed to stay on schedule and the PERT chart may be modified to reflect the new situation.
Conclusion
Ever since their inception in the late 1950s, PERT and CPM have been used extensively to assist project managers in planning, scheduling, and controlling their projects. Over time, these two techniques gradually have merged. PERT/CPM generates a great deal of useful scheduling information for the project manager, including the earliest start time, the latest start time, and the slack for each activity. It also identifies the critical path of activities such that any delay along this path will delay project completion. Since the critical path is the longest path through the project network, its length determines the duration of the project, assuming all activities remain on schedule. The concept of network-based cost control offers to project management a basically sound and powerful way of relating expenditures to the work done, a way of reporting what management paid for what it got. Unlike other critical path techniques, however, network cost control cannot be applied easily to only selected projects, or only during certain phases of a project. The design and implementation of such a control system involves modifications in established payroll and cost accounting procedures of the organization.
BIBLIOGRAPHY
William Pinkerton, Project Managment: Achieving Project Bottom-Line Success, p. 22, 2003. Joseph J. Moder, Cecil R. Phillips, Edward W. Davis: Project management with CPM, PERT and Precedence Diagramming, p.138, 1983. internet sources: http://www.interventions.org/pertcpm.html http://www.netmba.com/operations/project/pert