CONCRETE POUR CARD / CHECK LIST Ref: Project name : Location: SI.

No 1 2 Date: Date of checking: Ref drawing No: No

Item

Yes

Remarks

Centre line,Dimensions and Levels Checked Form work and staging checked for accuracy, strength & finish Cover, Reinf. Checked / Bar bending Sch. Enclosed Electrical & Miscellaneous work checked Adequacy of materials / equipments for pour checked Supervisory Staff allocation made Temporary lighting and mechanic presence Finishing masons available Soffit (S) and Pour top (T) levels checked Construction Joint Location & Time (if not as per Drawing) Cement consumption No. of cubes and identification mark Test cube results (7 days / 28 days) Concrete condition on form removal

4 5

6 7

8 9

10

11 12 13 14

Max Aggregate Size / Slump : .mm.mm Start time : Concrete Grade / Quantity : M: / M3 Completion time : Checked By GIL Client Signature: