Beruflich Dokumente
Kultur Dokumente
Item
Yes
Remarks
Centre line,Dimensions and Levels Checked Form work and staging checked for accuracy, strength & finish Cover, Reinf. Checked / Bar bending Sch. Enclosed Electrical & Miscellaneous work checked Adequacy of materials / equipments for pour checked Supervisory Staff allocation made Temporary lighting and mechanic presence Finishing masons available Soffit (S) and Pour top (T) levels checked Construction Joint Location & Time (if not as per Drawing) Cement consumption No. of cubes and identification mark Test cube results (7 days / 28 days) Concrete condition on form removal
4 5
6 7
8 9
10
11 12 13 14
Max Aggregate Size / Slump : .mm.mm Start time : Concrete Grade / Quantity : M: / M3 Completion time : Checked By GIL Client Signature: