Beruflich Dokumente
Kultur Dokumente
Agenda
Definitionofestimating Whatisestimatinginconstruction? Costvariableinconstruction Typesofestimates Conceptualestimate Detailedestimate AvoidingErrorsinEstimates
ESTIMATINGCONSTRUCTIONCOSTS
Thekeytoagoodjobandsuccessfulcostcontrol isthedevelopmentofagoodestimateasthe basisforbidsubmittal. Estimatingistheprocessoflookingintothe futureandtryingtopredictprojectcostsand resourcerequirements. Tominimizeerrors,aconsistentprocedureorset ofstepsforpreparinganestimateisneededto minimizeerrorsandachievereliableresults.
TYPESOFESTIMATES
TYPESOFESTIMATES
Type Conceptual When? Priortothecommencementof design How? Arepresentativeunitismultiplied byapriceperunittoobtainagross estimate( 10%accuracy)ofthe facilitycost. Bythearchitector architect/engineertoreflect expectedcostsbasedonmore definitivedata. Totaljobcostminusmarkup Shouldachieveapproximately 3%accuracy. Onthebasisofthebidding documents, Includeamarkupforprofit.
Preliminary
40%completionofthetotal design
Engineer
Detaildesignisaccomplished
Bid
Biddingphase
Example 1: A 5M GPD desalinization plant was constructed in 1995 at a cost of 20M. What would be the cost of 15M GPD in 2005, if the cost capacity factor is 0.37,andDesalinizationIndexDI2005=107,andDI1995=99. CostCapacityformulaisoftheform:
x 0.37
Q 15 C2 = C1 2 = 20 = 20 30.37 = 30 M Q 5 1 C2(now)=30*107/99=32.4M
Example 2: You are required to submit an estimate for 6m high, 3000 m2 warehouse construction. You looked up your cost file and found that you had built an 8mhigh,2500m2 for2.5M,7yearsagowhenthecostindexwas120.Ifthe costindexisnow165,whatisyourcostestimatepercubicmeter? Cost/m3(7)=2,500,000/(8*2,500)=125 Cost/m3(Now)=125*165/120=171.88 Estimate=171.88*6*3000=3,093,840
DETAILEDESTIMATEDEVELOPING STEPS
1.Breaktheprojectintocostcenters. 2.Estimatethequantitiesrequiredforcostcentersthat representphysicalenditems(e.g.,cubicyardsofearth, linealfeetofpipe,etc.).Forphysicalsystemsthis procedureiscommonlycalledquantitytakeoff.Forthose costcentersthatrelatetononphysicalitems,determine anappropriateparameterforcostcalculation(e.g.,the levelofbuilder'sriskinsurancerequiredbythecontract ortheamountsoftherequiredbonds).
ESTIMATEDEVELOPINGSTEPS(Contd)
3. Priceoutthequantitiesdeterminedinstep2usinghistorical data,vendorquotations,suppliercatalogs,andotherpricing information.Pricedevelopmentforphysicalworkitemsmay requireananalysisoftheproductionratestobeachieved basedonresourceanalysis.Ifthisanalysisisused,the estimatormust: a. Assumeworkteamcompositiontoincludenumberof workers(skilledandunskilled)andequipmentrequired. b. Onthebasisofteamcomposition,estimateanhourly productionratebasedonthetechnologybeingused. c. Makeanestimateoftheefficiencytobeachievedonthis job,consideringsiteconditionsandotherfactors. d. Calculatetheeffectiveunitprice. 4. Calculatethetotalpriceforeachcostcenter.
TypicalEstimate SummarySheet
QUANTITYTAKEOFF (SURVEYING)
Thedevelopmentofthequantitiesofworktobeplacedin appropriateunits(e.g.,squarefeet,cubicyards,etc.). Theproceduresemployedbytheestimatortocalculatethese quantitiesshouldincorporatestepstominimizeerrors. Fiveofthemostcommonerrorsexperiencedduringquantity takeoffare:
1. Arithmetic:Errorsinaddition,subtraction,andmultiplication 2. Transposition:Mistakesincopyingortransferringfigures,dimensions, orquantities 3. Errorsofomission:Overlookingitemscalledfororrequiredto accomplishthework 4. Poorreference:Scalingdrawingsratherthanusingthedimensions indicated 5. Unrealisticwasteorlossfactor.
WorkBreakdownStructureWBS
Foundation
Excavation
Concrete
Steel
ProjectControl
13
Workpackages
Aworkpackage isawelldefinedscopeofwork thatusuallyterminatesinadeliverableproduct. Eachpackagemayvaryinsizebutmustbea measurableandcontrollableunitofworktobe perform. Italsomustbeidentifiableinanumerical accountingsysteminordertopermitcaptureof bothbudgetedandactualperformance information. Aworkpackageisacostcenter.
1. GENERAL REQUIREMENTS 2. SITE CONSTRUCTION 3. CONCRETE 4. MASONRY 5. METALS 6. WOOD AND PLASTICS 7. THERMAL AND MOISTURE PROTECTION 8. DOORS AND WINDOWS 9. FINISHES 10. SPECIALTIES 11. EQUIPMENT 12. FURNISHINGS 13. SPECIAL CONSTRUCTION 14. CONVEYING SYSTEMS 15. MECHANICAL 16. ELECTRICAL
CE321 ConstructionManagement
Division3 Concrete
1. Concrete:
Plain Concrete Reinforced Concrete: Substructure Reinforced Concrete: Superstructure
2. Formwork
Foundations Columns Beams Slabs
3. Reinforcing Steel
CE321 ConstructionManagement
PlainConcrete
Concrete is classified by type, strength, and location Concrete volume is measured from detailed drawings in cubic meters, rounded to the nearest 0.5 meter Concrete Mat Foundation (Spread, Continuous, Raft) Pedestal Grade Beams Shear Walls Use 5-10% waste factor
CE321 ConstructionManagement
Slab on grade Columns Beams Slabs Retaining Structures Stairs & Landings
FoundationDetails
CE321 ConstructionManagement
ASTMStandardReinforcingBars
Soft Metric Size
10 13 16 19 22 25 29 32 36 43 57
Nom Diam mm
9.5 12.7 15.9 19.1 22.2 25.4 28.7 32.3 35.8 43.0 57.3
Area mm2
71 129 199 284 387 510 645 819 1006 1452 2581
CE321 ConstructionManagement
Bar Size 6 8 10 12 14 16 20 25 28 32 40 50
(kg/m) 0.222 0.395 0.617 0.888 1.21 1.58 2.47 3.85 4.83 6.31 9.86 15.4
Area (mm) 28.3 50.3 78.5 113 154 201 314 491 616 804 1257 1963
CE321 ConstructionManagement
SmallWallConstruction
UnitPrice
Iftheworkisfairlystandard,thecostcanbecalculated bysimplytakingdollarperunitcostfromcompany recordsandapplyingthiscostwithaqualitative correctionfactortothequantityofworktobe performed.
Unitpricingvaluesareavailableinmanystandard estimatingreferences:
R.S.MeansCompany,buildingConstructionCostData F.R.Walker'sTheBuildingEstimator'sReferenceBook TheRichardsonGeneralConstructionEstimating Standards
LineItemCostDevelopment UsingR.S.Means
Figure13.1(p.206)
Costsbasedonarepresentativeunit.
(FromBuildingConstructionCostData.CopyrightReed ConstructionData,KingstonMA7815857880allrights reserved.)
AvoidingErrorsinEstimates
Theaccuracyofanestimateisameasureof howaccurateorcorrectthenumbersinthe estimateare Thecompletenessofanestimateisameasure ofwhetherthebidhasalltheitemsneeded fortheprojectwithoutduplicatingitems
AvoidingErrorsinEstimates
ListCostCodes SpendMoreTimeonLargeCosts PrepareDetailedEstimates MarkItemsCountedDuringtheQuantity Takeoff
AvoidingErrorsinEstimates
DoubleCheckAllTakeoffs IncludeUnitsinCalculations AutomatewithSpreadsheets UseWellTestedandCheckedFormulas DoubleCheckAllCalculations
AvoidingErrorsinEstimates
PerformCalculationsinTwoWays DropthePennies HaveSomeoneReviewtheEstimate ReviewEachCostCodeasaPercentageofthe TotalCosts
AvoidingErrorsinEstimates
CheckUnitCostsforEachCostCode CompareCoststoanotherProject AllowPlentyofTime
Questions